MONTHYEARML24032A1112024-02-0101 February 2024 Owner'S Activity Report for North Anna, Unit 2, Refueling Outage N2R29 - First Period of the Fifth ISI Interval ML24032A4662024-01-16016 January 2024 Response to Comments on Draft Vpdes Permit No. VA0052451 ML24017A0802024-01-11011 January 2024 Notification of Licensed Operator Initial Examination 05000338/2024301 and 05000339/2024301 ML24003A8372024-01-0909 January 2024 Letter to Elizabeth Toombs, Thpo, Cherokee Nation, Notice of Availability of the Draft Site-Specific EIS for North Anna Power Station, Units 1 and 2, Subsequent License Renewal ML24003A8412024-01-0909 January 2024 Notice of Availability of the Draft Site-Specific Environmental Impact Statement for the North Anna Power Station, Units 1 and 2, Subsequent License Renewal ML24003A8502024-01-0909 January 2024 Letter to Wenonah Haire, Thpo, Catawba Indian Nation, Notice of Availability of the Draft Site-Specific EIS for North Anna Power Station, Units 1 and 2, Subsequent License Renewal ML23332A7272024-01-0909 January 2024 Notice of Availability of the Draft Site-Specific Environmental Impact Statement for the North Anna Power Station, Units 1 and 2, Subsequent License Renewal ML24003A8382024-01-0909 January 2024 Letter to G. Anne Richardson, Chief, Rappahannock Tribe, Inc., Notice of Availability of Draft Site-Specific Environmental Impact Statement for North Anna Power Station Units 1 and 2, Subsequent License Renewal ML24003A8482024-01-0909 January 2024 Notice of Availability of the Draft Site-Specific Environmental Impact Statement for the North Anna Power Station, Units 1 and 2, Subsequent License Renewal ML24003A8392024-01-0909 January 2024 Letter to Gerald Stewart, Chief, Chickahominy Indian Tribe, Eastern Division Re Re Notice of Availability of the Draft Site-Specific Environmental Impact Statement for North Anna Power Station Subsequent License Renewal ML24003A8472024-01-0909 January 2024 Letter to Tom Jonathan, Chief, Tuscarora Nation, Notice of Availability of the Draft Site-Specific EIS for North Anna Power Station, Units 1 and 2, Subsequent License Renewal ML24003A8492024-01-0909 January 2024 Letter to W. Frank Adams, Chief, Upper Mattaponi Tribe Re Re Notice of Availability of the Draft Site-Specific Environmental Impact Statement for North Anna Power Station Subsequent License Renewal ML24003A8462024-01-0909 January 2024 Notice of Availability of the Draft Site-Specific Environmental Impact Statement for the North Anna Power Station, Units 1 and 2, Subsequent License Renewal ML24003A8352024-01-0909 January 2024 Letter to Acee Watt, Thpo, United Keetoowah Band of Cherokee Indians in Oklahoma Re Notice of Availability of the Draft Site-Specific Environmental Impact Statement for North Anna Power Station Subsequent License Renewal ML24003A8422024-01-0909 January 2024 Letter to Paul Barton, Thpo, Eastern Shawnee Tribe of Oklahoma, Notice of Availability of Draft Site-Specific Environmental Impact Statement for North Anna Power Station Units 1 and 2, Subsequent License Renewal ML24003A8432024-01-0909 January 2024 Letter to Robert Gray, Chief, Pamunkey Indian Tribe, Notice of Availability of the Draft Site-Specific EIS for North Anna Power Station, Units 1 and 2, Subsequent License Renewal ML24003A8362024-01-0909 January 2024 Notice of Availability of the Draft Site-Specific Environmental Impact Statement for the North Anna Power Station, Units 1 and 2, Subsequent License Renewal ML24003A8442024-01-0909 January 2024 Letter to Russell Townsend, Thpo, Eastern Band of Cherokee Indians ML24003A8402024-01-0909 January 2024 Letter to Katelyn Lucas, Thpo, Delaware Nation, Oklahoma, Notice of Availability of Draft Site-Specific Environmental Impact Statement for North Anna Power Station Units 1 and 2, Subsequent License Renewal ML24003A8452024-01-0909 January 2024 Letter to Stephen Adkins, Chief, Chickahominy Indian Tribe, Notice of Availability of Draft Site-Specific Environmental Impact Statement for North Anna Power Station Units 1 and 2, Subsequent License Renewal ML23332A1852024-01-0404 January 2024 Notice of Availability of the Draft Site-Specific Environmental Impact Statement for the North Anna Power Station, Units 1 and 2, Subsequent License Renewal ML23332A0872024-01-0404 January 2024 Notice of Availability of the Draft Site-Specific Environmental Impact Statement for the North Anna Power Station, Units 1 and 2, Subsequent License Renewal ML23360A6352024-01-0404 January 2024 Letter to Dominion Availability for North Anna Units 1 and 2 Draft Site Specific Environmental Impact Statement ML23332A1472023-12-21021 December 2023 Issuance of Environmental Scoping Summary Report Associated with the Staff'S Review of the North Anna Power Station, Units 1 and 2, Subsequent License Renewal Application ML23283A3052023-12-20020 December 2023 Review of Appendix F to DOM-NAF2, Qualification of the Framatome ORFEO-GAIA and ORFEO-NMGRID CHF Correlations in the Dominion Energy VIPRE-D Computer Code (EPID L-2022-LLT-0003) (Nonproprietary) ML23346A0972023-12-11011 December 2023 License Amendment Request to Revise the Emergency Plan Relocation of the Technical Support Center - Response to NRC Request for Additional Information ML23346A1022023-12-11011 December 2023 2024 North Anna Power Station Brq Inspection Notification Letter ML24012A0942023-12-0707 December 2023 GL Report from Dominion Virginia Power Regarding Transfer of Devices ML24012A0892023-12-0707 December 2023 GL Registration from Dominion Virginia Power ML23334A2432023-11-30030 November 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation ML23362A0602023-11-29029 November 2023 ISFSI, Submittal of Cask Registration for Spent Fuel Storage IR 05000339/20234022023-11-27027 November 2023 Security Baseline Inspection Report 05000338 and 05000339/2023402 IR 05000338/20230032023-11-13013 November 2023 Integrated Inspection Report 05000338/2023003 and 05000339/2023003 ML23311A2042023-10-0909 October 2023 Annual Submittal of Technical Specification Bases Changes Pursuant to Technical Specification 5.5.13.d IR 05000338/20234032023-10-0505 October 2023 Reissue - North Anna Power Station - Cyber Security Inspection Report 05000338/2023403 and 05000339/2023403 (Cover Letter) ML23279A0612023-10-0505 October 2023 Paragon Energy Solutions LLC, Part 21 Final Report Re Potential Defect with Eaton Jd and Hjd Series Molded Case Circuit Breakers (Mccbs) ML23230A0502023-10-0202 October 2023 5 of the Quality Assurance Topical Report - Review of Program Changes ML23275A0992023-09-28028 September 2023 Subsequent License Renewal Application Third 10 CFR 54.21(b) Annual Amendment IR 05000338/20230112023-09-26026 September 2023 Quadrennial Focused Engineering Inspection Commercial Grade Dedication Report 05000338/2023011 and 05000339/2023011 ML23242A3482023-09-11011 September 2023 Cyber Security Inspection Report 05000338/2023403 and 05000339/2023403 - Cover ML23254A0242023-09-0606 September 2023 Paragon Energy Solutions LLC, Potential Defect with Eaton Jd and Hjd Series Molded Case Circuit Breakers (Mccbs) ML23249A2592023-09-0606 September 2023 Core Operating Limits Report Cycle 30, Pattern Ukr, Revision 0 ML23214A2022023-09-0505 September 2023 Staff Assessment of Updated Seismic Hazards Following the NRC Process for the Ongoing Assessment of Natural Hazards Information 2024-02-01
[Table view] Category:License-Operator Examination Report
MONTHYEARML22234A0282022-08-19019 August 2022 NA-2022-6 Examination Report and Cover Letter IR 05000338/20203012020-09-16016 September 2020 NRC Operator License Examination Report 05000338/2020301, 05000339/2020301 IR 05000338/20123022013-01-15015 January 2013 Er 05000338-12-302, 05000339-12-302; 12/18-19/2012; North Anna Power Station; Operator License Examinations IR 05000338/20123012012-10-17017 October 2012 Er 05000338-12-301, 05000339-12-301; 09/10-14/2012 and 09/19/2012; North Anna Power Station; Operator License Examinations IR 05000338/20103012010-08-0404 August 2010 Er 05000338-10-301, 05000339-10-301, on 06/07-23/2010 and 06/16/2010, North Anna Power Station, Operator License Examinations ML0821800072008-08-0505 August 2008 Er 05000338-08-301, 05000339-08-301, on 06/02-20/2008 and 06/24/2008; North Anna Power Station; Licensed Operator Examinations ML0818405022008-07-0202 July 2008 Retake Exam 05000338-06-302 Draft Job Performance Measures (Part 2 of 2) ML0635203872006-12-18018 December 2006 Initial Retake Examination Report - 05000338-06302 and 0500339-06302 IR 05000338/20063012006-08-0202 August 2006 Er 05000338-06-301, 05000339-06-301; 5/22-26/2006, 6/5-9/2006, 6/14/2006; North Anna Power Station; Licensed Operator Examinations ML0220703442002-07-25025 July 2002 Examination Reports 050-338/2002-301 & 50-339/2002-301on June 10-4, 24-25 & June 6, 2002. Eleven of Thirteen Applicants Passed Both Written & Operating Examinations. One RO & One SRO Failed Written Examination ML0220000992002-07-10010 July 2002 Stations, Units 1 & 2 -- Requested Information on Proposed Site-Specific Operator Licensing Examination Schedules & Estimated Number of Applicants, Regulatory Issue Summary 2002-09 ML0037616232000-10-19019 October 2000 Sept/2000 Exam 50-338/2000-301 North Anna Exam Report - Reactor & Senior Reactor Operator Initial Examinations 2022-08-19
[Table view] |
Text
October 17, 2012
SUBJECT:
NORTH ANNA POWER STATION - NRC OPERATOR LICENSE EXAMINATION REPORT 05000338/2012301, 05000339/2012301
Dear Mr. Heacock:
During the period of September 10-14, 2012, the Nuclear Regulatory Commission (NRC)
administered operating tests to employees of your company who had applied for licenses to operate the North Anna Power Station. At the conclusion of the tests, the examiners discussed preliminary findings related to the operating tests with those members of your staff identified in the enclosed report. The written examination was administered by your staff on September 19, 2012.
Six Reactor Operator (RO) and two Senior Reactor Operator (SRO) applicants passed both the operating test and written examination. One SRO applicant passed the written examination, but did not pass the operating test. There were no post-examination comments. A Simulator Fidelity Report is included in this report as Enclosure 2.
The initial examination submittal was within the range of acceptability expected for a proposed examination. All examination changes agreed upon between the NRC and your staff were made according to NUREG-1021, Operator Licensing Examination Standards for Power Reactors, Revision 9, Supplement 1.
In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its enclosures will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of the NRC's document system (ADAMS). ADAMS is accessible from the NRC Website at http://www.nrc.gov/reading-rm.adams.html (the Public Electronic Reading Room). If you have any questions concerning this letter, please contact me at (404) 997-4550.
Sincerely,
/RA/
Malcolm T. Widmann, Chief Operations Branch 1 Division of Reactor Safety
Docket Nos: 50-338, 50-339
License Nos: NPF-4, NPF-7
Enclosures:
1. Report Details
2. Simulator Fidelity Report
REGION II==
Docket No.: 50-338, 50-339
License No.: NPF-4, NPF-7 Report No.: 05000338/2012301, 05000339/2012301
Licensee: Virginia Electric and Power Company
Facility: North Anna Power Station, Units 1 & 2 Location: 1022 Haley Drive Mineral, VA 23117 Dates: Operating Test - September 10-14, 2012 Written Examination - September 19, 2012
Examiners: M. Bates, Chief Examiner, Senior Operations Engineer T. Kolb, Senior Reactor Systems Engineer J. A. Toth, Operations Engineer
Approved by: Malcolm T. Widmann, Chief Operations Branch 1 Division of Reactor Safety Enclosure 1 SUMMARY OF FINDINGS ER 05000338/2012301, 05000339/2012301; 09/10-14/2012 and 09/19/2012; North Anna Power Station; Operator License Examinations.
Nuclear Regulatory Commission (NRC) examiners conducted an initial examination in accordance with the guidelines in Revision 9, Supplement 1, of NUREG-1021, "Operator Licensing Examination Standards for Power Reactors." This examination implemented the operator licensing requirements identified in 10 CFR §55.41, §55.43, and §55.45, as applicable.
Members of the North Anna Power Station staff developed both the operating tests and the
written examination.
The NRC administered the operating tests during the period of September 10-14, 2012. Members of the North Anna Power Station training staff administered the written examination on September 19, 2012. Six Reactor Operator (RO) and two Senior Reactor Operator (SRO) applicants passed both the operating test and written examination. One SRO applicant passed the written examination, but did not pass the operating test. Eight applicants were issued licenses commensurate with the level of examination administered.
There were no post-examination comments.
No findings were identified.
Enclosure 1 REPORT DETAILS 4. OTHER ACTIVITIES 4OA5 Operator Licensing Examinations
a. Inspection Scope Members of the North Anna Power Station staff developed both the operating tests and the written examination. All examination material was developed in accordance with the guidelines contained in Revision 9, Supplement 1, of NUREG-1021, "Operator Licensing Examination Standards for Power Reactors." The NRC examination team reviewed the proposed examination. Examination changes agreed upon between the NRC and the licensee were made per NUREG-1021 and incorporated into the final version of the examination materials.
The NRC reviewed the licensee's examination security measures while preparing and administering the examinations in order to ensure compliance with 10 CFR §55.49,
"Integrity of examinations and tests."
The NRC examiners evaluated six Reactor Operator (RO) and three Senior Reactor Operator (SRO) applicants using the guidelines contained in NUREG-1021. The examiners administered the operating tests during the period September 10-14, 2012.
Members of the North Anna Power Station training staff administered the written examination on September 19, 2012. Evaluations of applicants and reviews of associated documentation were performed to determine if the applicants, who applied for licenses to operate the North Anna Power Station, met the requirements specified in 10 CFR Part 55, "Operators' Licenses."
b. Findings No findings were identified. The NRC determined, using NUREG-1021, that the licensee's initial examination submittal was within the range of acceptability expected for a proposed examination.
Six Reactor Operator (RO) and two Senior Reactor Operator (SRO) applicants passed both the operating test and written examination. One SRO applicant passed the written examination, but did not pass the operating test. Six RO and two SRO applicants were issued licenses commensurate with the level of examination administered.
Copies of all individual examination reports were sent to the facility Training Manager for evaluation of weaknesses and determination of appropriate remedial training.
The licensee did not submit any post-examination comments. A copy of the final written examination (RO and SRO) and answer keys may be accessed in the ADAMS system (ADAMS Accession Number(s) ML12283A404 and ML12283A406) not earlier than
October 8, 2014.
4 Enclosure 1 4OA6 Meetings, Including Exit Exit Meeting Summary On September 14, 2012 the NRC examination team discussed generic issues associated with the operating test with Mr. Michael D. Crist, Plant Manager, and members of the North Anna Power Station staff. The examiners asked the licensee if
any of the examination material was proprietary. No proprietary information was identified.
ATTACHMENT: SUPLEMENTAL INFORMATION Attachment KEY POINTS OF CONTACT Licensee Personnel M. Crist, Plant Manager
R. Wesley, Training Manager
S. Hughes, Operations Manager
M. Schry, Supervisor Shift Operations S. Allen, Training Instructor J. Scott, Supervisor, Operator Training D. Tiblis, Training Instructor NRC Personnel R. Clagg, Resident Inspector Enclosure 2 SIMULATOR FIDELITY REPORT Facility Licensee: North Anna Power Station
Facility Docket No.: 05000338 and 05000339
Operating Test Administered: September 10 to 14, 2012.
This form is to be used only to report observations. These observations do not constitute audit or inspection findings, and without further verification and review in accordance with Inspection Procedure 71111.11, are not indicative of noncompliance with 10 CFR 55.46. No licensee action is required in response to these observations.
No simulator fidelity or configuration issues were identified.