MONTHYEARML0702903282006-11-30030 November 2006 Tornado/Helb Mitigation Strategies and Regulatory Commitments Project stage: Request ML0705300702007-02-21021 February 2007 Emcb Review of the High Energy Line Break Mitigation Strategies for the Oconee Units as Proposed by Duke in a Letter Dated November 30, 2006 Project stage: Approval ML0706702062007-03-0505 March 2007 Handouts Provided at Beginning of 3/05/07 Oconee Meeting Project stage: Request ML0706702032007-03-0505 March 2007 Handouts Provided at Isnd of 03/05/2007 Oconee Meeting Project stage: Request ML0708205222007-03-20020 March 2007 Revised Handout from 03/20/2007 Meeting Project stage: Request ML0707501262007-03-28028 March 2007 Summary of Meeting Between the NRC and Duke Regarding Oconee High-Energy Line Break and Tornado Mitigation Strategies Project stage: Meeting ML0708701502007-04-0303 April 2007 Summary of Meeting with Duke Power Company LLC Regarding Oconee High-Energy Line Break Mitigation Strategy Project stage: Meeting ML0711403642007-05-15015 May 2007 Tornado and High-Energy Line Break (HELB) Mitigation Strategies Project stage: Other ML0721304832007-08-0202 August 2007 Notice of Meeting with Duke Power Company Llc., to Discuss Status of Oconee Tornado and High-Energy Line Break Efforts (TAC Nos. MD3721 Through MD3726) Project stage: Meeting ML0723901192007-09-0505 September 2007 Summary of Meeting with Duke Power Company LLC to Discuss the Status of the Oconee Tornado and High-Energy Line Break Efforts (TAC Nos. MD3721 Through MD3726) Project stage: Meeting ML0730602422007-11-0707 November 2007 Notice of Meeting with Duke Power Company LLC, to Discuss High-Energy Line Break Mitigating Strategy. Project stage: Meeting ML0734100632007-12-0606 December 2007 Handouts from 12/06/07 Oconee Meeting Project stage: Request ML0735202512008-01-0707 January 2008 Summary of Meeting with Duke Power Company to to Discuss Status of Tornado and High-energy Line Break (HELB) Efforts for Oconee, Units 1, 2, and 3 Project stage: Meeting 2007-03-28
[Table View] |
|
---|
Category:Memoranda
MONTHYEARML24122C6932024-05-0101 May 2024 Referral of Petition to Intervene and Request for Hearing Re Subsequent License Renewal Application from Duke Energy Carolinas, LLC for Oconee Units 1, 2 & 3 ML24124A0342024-05-0101 May 2024 Summary of Public Meeting Concerning Annual Assessment of Catawba Nuclear Station Units 1 and 2, McGuire Nuclear Station Units 1 and 2, Oconee Nuclear Station Units 1, 2, and 3, Brunswick Steam Electric Plant Units 1 and 2, Shearon Harris ML24071A1692024-03-15015 March 2024 February 2024 Subsequent License Renewal Public Draft Environmental Impact Statement Meetings-Memo ML24047A2092024-02-22022 February 2024 Calendar Year 2023 Baseline Inspection Completion ML23118A2852023-05-0202 May 2023 Public Meeting Summary - 2022 Annual Assessment Meeting Regarding Catawba Nuclear Station, McGuire Nuclear and Oconee Nuclear Station ML22299A0482023-01-11011 January 2023 Final Environmental Assessment and Finding of No Significant Impact for the Duke Energy’S Updated Decommissioning Funding Plans Submitted in Accordance with 10 CFR 72.30(C) for Oconee Nuclear Station Independent Spent Fuel Storage Installat ML22349A1482022-12-19019 December 2022 Transmittal Letter for Oconee SE for SLRA Review ML22193A2542022-08-0505 August 2022 SLRA - Audit Report ML22111A3142022-05-0202 May 2022 Limited Aging Management Audit Plan Regarding the Subsequent License Renewal Application Review ML22084A6142022-04-0404 April 2022 SLRA - Summary of March 16, 2022 (Closed Public Meeting) ML22024A1392022-03-11011 March 2022 SLRA - Request for Withholding Information ML21347A0102021-12-20020 December 2021 Proposed Alternative to Implement ASME Code Case OMN-26 ML21279A1542021-11-0808 November 2021 August 25, 2021, Oconee Nuclear Station, Units 1, 2, and 3 Subsequent License Renewal Application Public Environmental Scoping Meeting Summary Memo ML21064A3502021-07-26026 July 2021 OEDO-21-00048 - Oconee Nuclear Station, Units 1, 2, and 3 - Response Memorandum ML21195A2692021-07-14014 July 2021 Meeting Summary: Pre-Submittal Meeting for the Oconee Subsequent License Renewal Application (EPID Number: L-2020-RNW-0028) (Docket Numbers: 50 269, 50-270, and 50-287) - Memo ML21055A8672021-04-22022 April 2021 Memo to File: Final Ea/Fonsi of Independent Spent Fuel Storage Facilities Decommissioning Funding Plans Related to Oconee ML21099A0932021-04-0909 April 2021 Public Meeting Summary - 2020 Annual Assessment Meeting Regarding Catawba, McGuire, and Oconee Nuclear Stations ML20357B1332020-12-30030 December 2020 Transmittal Memo - Delivery of Partial Deliverable Associated with the Trace Code Maintenance, Plant Model Maintenance, and Plant Model Development to Support Licensing Actions and Emergent Technical Issues User Need ML20141L4172020-05-20020 May 2020 EOC Public Meeting Summary ML20036E3902020-02-11011 February 2020 Regulatory Audit in Support of Review of License Amendment Request to Revise the Licensing Basis for High Energy Line Breaks Outside of the Containment Building ML19102A3352019-04-12012 April 2019 Public Meeting Summary - Oconee Nuclear Station Docket Nos. 50-269, 50-270, and 50-287 ML19037A0052019-02-0808 February 2019 Regulatory Audit in Support of Review of License Amendment Request No. 2018-02 ML18226A2152019-01-22022 January 2019 Response to Task Interface Agreement 2014-04, Adequacy of the Oconee Nuclear Station Design and Licensing Bases for Degraded Voltage Protection (TAC Nos. MF4622, MF4623, and MF4624; EPID L-2014-LRA-0003) ML18082A0582018-03-23023 March 2018 Summary of Meeting with Oconee Nuclear Station to Discuss Annual Assessment of Oconee for the Period of January 01, 2017 - December 31, 2017 ML18032A4612018-03-0505 March 2018 Regulatory Audit in Support of Review of License Amendment Request No. 2017-03 ML18004A0122018-01-0404 January 2018 Regulatory Audit in Support of Review of Proposed Alternative (CAC Nos. MF7365, MF7366 and MF7367; EPID No. L-2016-LLR-001) ML17264A0312017-09-29029 September 2017 Draft Response to Task Interface Agreement 2014-05 to Licensee Oconee Design Analysis for Single Failure/Integration of Class 1E Direct Current Control Cabling in Raceways with High Energy Power Cabling ML17202U7312017-07-25025 July 2017 Regulatory Audit in Support of License Amendment Request No. 2015-03 ML17103A0292017-04-13013 April 2017 Summary of Meeting to Provide Opportunities to Discuss Annual Assessment of Oconee Nuclear Station Units 1, 2 and 3 ML16088A2042016-03-28028 March 2016 Memo T Bowers from s Ruffin, Technical Assistance Requests - Review 2015 Tri-Annual Decommissioning Funding Plans for Multiple Independent Spent Fuel Storage Installations W/ Encl 2 (Template) ML16088A2052016-03-28028 March 2016 Enclosure 1 - (72.30 DFP Reviews to Be Completed 2015) - Memo T Bowers from s Ruffin, Technial Assistance Requests - Review 2015 Tri-Annual Decommissioning Funding Plans for Multiple Independent Spent Fuel Storage Installations ML16061A5652016-03-0909 March 2016 Request for Additional Information for Relief Request 14-ON-001, Letdown Cooler Nozzle Welds ML16056A5832016-02-26026 February 2016 and 3, Draft Request for Additional Information License Amendment Request to Adopt Emergency Action Level Scheme Based on NEI 99-01 Rev.6 ML16021A3452016-01-29029 January 2016 Draft Request for Additional Information License Amendment to Add High Flux Trip for 3 Reactor Coolant Pump Operation ML15364A3802016-01-0808 January 2016 Draft Request for Additional Information Relief Request ON-GRR-01 ML15363A2962015-12-29029 December 2015 Special Inspection Charter to Evaluate the Power Cable Failures/Degradations on the Oconee Units 1 and 3 Startup Transformers ML15345A3982015-12-15015 December 2015 Draft Request for Additional Information License Amendment Request to Adopt Emergency Action Level Scheme Based on NEI 99-01 Rev. 6 ML15265A1272015-09-17017 September 2015 Memoranda to C. Bladey Notice of Availability of Exemption for Duke Energy Carolinas, LLC, Oconee Nuclear Station Independent Spent Fuel Storage Installation ML15231A1922015-08-19019 August 2015 NRC June 9 2009 Memo Revision ML15233A4952015-08-14014 August 2015 Memo to C Bladey, Notice of Environmental Assessment and Finding of No Significant Impact - Duke Ene4rgy Carolinas LLC, Oconee Nuclear Station ISFSI - Admin EA Memo ML15181A4332015-07-0707 July 2015 Closure of Licensee Responses to External Flooding Letters ML15099A5612015-05-11011 May 2015 Safety Evaluation for Duke Submittal on Electronic Records (Nirma) ML15089A1642015-04-27027 April 2015 Summary of February 25, 2015, Partially Closed Meeting with Industry Stakeholders Regarding the Babcock and Wilcox Loss of Coolant Accident Evaluation Model Analysis ML15113A6262015-04-23023 April 2015 April 14, 2015 Summary of Public Meeting on Oconee Nuclear Station, Units 1, 2 and 3 to Discuss the Annual Assessment ML14356A0052014-12-31031 December 2014 Summary of December 3, 2014, Category 1 Public Meeting with Duke Energy Carolinas, LLC to Discuss NTTF Recommendation 2.1, Flooding Response for Oconee Nuclear Station, Units 1, 2, and 3 ML14311A8622014-11-0707 November 2014 Request for Technical Assistance Regarding the Adequacy of the Oconee Station Design and Licensing Bases for the Degraded Voltage Relay Protection Design (TIA 2014-04) (Final) ML14147A3652014-05-27027 May 2014 Annual Assessment Public Meeting Summary Memo ML14055A4742014-02-0404 February 2014 Draft Memorandum from G. Cunningham, NRR to E. Leeds, NRR on Oconee Flood Protection and the Jocassee Dam Hazard Basis for Continued Operation ML14058A0162014-02-0404 February 2014 Draft Memo from M. Cunningham, NRR Et Al to E. Leeds, NRR on Oconee Flood Protection and the Jocassee Dam Hazard Basis for NRC Allowing Continued Operation ML14058A0172014-02-0404 February 2014 Draft Memo from M. Cunningham, NRR Et Al to E. Leeds, NRR on Oconee Flood Protection and the Jocassee Dam Hazard Basis for NRC Allowing Continued Operation 2024-05-01
[Table view] |
Text
March 28, 2007LICENSEE:DUKE POWER COMPANY LLC (DUKE)FACILITY:OCONEE NUCLEAR STATION, UNITS 1, 2, AND 3 (OCONEE)
SUBJECT:
SUMMARY
OF MARCH 5, 2007, MEETING TO DISCUSS THE NOVEMBER 30, 2006, LETTER REGARDING OCONEE HIGH-ENERGY LINE BREAK (HELB) AND TORNADO MITIGATION STRATEGIES (TAC NOS.
MD3721, MD3722, MD3723, MD3724, MD3725, AND MD3726)On March 5, 2007, the U.S. Nuclear Regulatory Commission (NRC) met with Duke (thelicensee) to discuss the licensee's letter dated November 30, 2006, (available in the Agencywide Documents Access and Management System under accession number ML070290328) regarding the Oconee HELB/tornado mitigation strategies and NRC concerns that resulted from NRC review of this letter (ML07050530070). At the beginning of the meeting, the licensee provided a handout (ML070670206) that included a list of the NRC concerns. This list was modified to reflect comments and agreements made during the meeting, and the modified list was made available at the end of the meeting (ML070670203). Enclosed is a list of the attendees.During the meeting, the NRC staff and the licensee agreed that most of the items were eitherresolved with no further information needed or that additional information would be provided in the future license amendment requests. The following two issues remained unresolved:
(1) Volumetric inspections of non-seismic piping instead of evaluating the effects of pipe ruptures in the turbine and auxiliary buildings, and (2) Justification of 100-percent humidity, non-condensing environment in the penetration rooms as a result of a pipe break. The licensee and the NRC staff agreed to have a meeting in the near future to discuss these two unresolved
issues./RA/Leonard N. Olshan, Project ManagerPlant Licensing Branch II-1 Division of Operating Reactor Licensing Office of Nuclear Reactor RegulationDocket Nos. 50-269, 50-270, and 50-287
Enclosure:
List of Attendees
cc w/encl: See next page March 28, 2007LICENSEE:DUKE POWER COMPANY LLC (DUKE)
FACILITY:OCONEE NUCLEAR STATION, UNITS 1, 2, AND 3 (OCONEE)
SUBJECT:
SUMMARY
OF MARCH 5, 2007, MEETING TO DISCUSS THE NOVEMBER 30, 2006, LETTER REGARDING OCONEE HIGH-ENERGY LINE BREAK (HELB) AND TORNADO MITIGATION STRATEGIES (TAC NOS.
MD3721, MD3722, MD3723, MD3724, MD3725, AND MD3726)On March 5, 2007, the U.S. Nuclear Regulatory Commission (NRC) met with Duke (thelicensee) to discuss the licensee's letter dated November 30, 2006, (available in the Agencywide Documents Access and Management System under accession number ML070290328) regarding the Oconee HELB/tornado mitigation strategies and NRC concerns that resulted from NRC review of this letter (ML07050530070). At the beginning of the meeting, the licensee provided a handout (ML070670206) that included a list of the NRC concerns. This list was modified to reflect comments and agreements made during the meeting, and the modified list was made available at the end of the meeting (ML070670203). Enclosed is a list of the attendees.During the meeting, the NRC staff and the licensee agreed that most of the items were eitherresolved with no further information needed or that additional information would be provided in the future license amendment requests. The following two issues remained unresolved:
(1) Volumetric inspections of non-seismic piping instead of evaluating the effects of pipe ruptures in the turbine and auxiliary buildings, and (2) Justification of 100-percent humidity, non-condensing environment in the penetration rooms as a result of a pipe break. The licensee and the NRC staff agreed to have a meeting in the near future to discuss these two unresolved
issues./RA/Leonard N. Olshan, Project ManagerPlant Licensing Branch II-1 Division of Operating Reactor Licensing Office of Nuclear Reactor RegulationDocket Nos. 50-269, 50-270, and 50-287
Enclosure:
List of Attendees cc w/encl: See next pageDistribution
- PublicRidsOgcRpJ. Segala, NRC LPL2-1 R/FT. Liu, NRRJ. Wermiel, NRC RidsNrrDorlLpl2-1 (EMarinos)J. Tatum, NRCS. Campbell, NRC RidsNrrPMLOlshan (hard copy)K. Manoly, NRCY. Chung, NRC RidsNrrLAMO'Brien (hard copy)J. Fair, NRCJ. Moorman, NRC RidsAcrsAcnwMailCenterK. O'Brien, NRCR. Carroll, NRC W. Rogers, NRCS. Campbell, EDO Rgn II RidsRgn2MailCenter (MErnstes)Accession Number: ML070750126OFFICENRR/LPL2-1/PMNRR/LPL2-1/LANRR/LPL2-1/BCNAMELOlshan:ncMO'BrienEMarinosDATE 3/22/07 3/22/07 3/28/07 OFFICIAL RECORD COPY EnclosureMEETING ATTENDEESFROM MARCH 5, 2007, MEETING WITH DUKE POWER COMPANY LLCTO DISCUSS THE NOVEMBER 30, 2006, LETTER REGARDING OCONEE HIGH-ENERGYLINE BREAK AND TORNADO MITIGATION STRATEGIES NRC DUKEJ. TatumJ. SumpterE. MarinosL. Kanipe K. ManolyJ. Robertson J. FairG. McAninch K. O'BrienT. Brown L. OlshanA. Park J. SegalaL. Nicholson J. WermielR. Freudenberger S. Campbell Y. Chung J. Moorman (by phone)
R. Carroll (by phone)
W. Rogers (by phone)
Oconee Nuclear Station, Units 1, 2, and 3 cc:
Mr. Bruce H. HamiltonVice President, Oconee Site Duke Power Company LLC 7800 Rochester Highway Seneca, SC 29672Ms. Lisa F. VaughnAssociate General Counsel and Managing Attorney Duke Energy Carolinas, LLC 526 South Church Street - EC07H Charlotte, North Carolina 28202Manager, LISNUS Corporation 2650 McCormick Dr., 3rd Floor Clearwater, FL 34619-1035Senior Resident InspectorU.S. Nuclear Regulatory Commission 7812B Rochester Highway Seneca, SC 29672Mr. Henry Porter, DirectorDivision of Radioactive Waste Management Bureau of Land and Waste Management Dept. of Health and Env. Control 2600 Bull St.
Columbia, SC 29201-1708Mr. Michael A. SchoppmanFramatome ANP 1911 North Ft. Myer Dr.
Suite 705 Rosslyn, VA 22209Mr. B. G. DavenportRegulatory Compliance Manager Oconee Nuclear Site Duke Energy Corporation ON03RC 7800 Rochester Highway Seneca, SC 29672Mr. Leonard G. GreenAssistant Attorney General NC Department of Justice P.O. Box 629 Raleigh, NC 27602Mr. R. L. Gill, Jr.Manager - Nuclear Regulatory Issues and Industry Affairs Duke Power Company LLC 526 S. Church St.
Mail Stop EC05P Charlotte, NC 28202Division of Radiation ProtectionNC Dept of Environment, Health, & Natural
Resources 3825 Barrett Dr.
Raleigh, NC 27609-7721Mr. Peter R. Harden, IVVP-Customer Relations and Sales Westinghouse Electric Company 6000 Fairview Road 12th Floor Charlotte, NC 28210Mr. Henry BarronGroup Vice President, Nuclear Generation and Chief Nuclear Officer P.O. Box 1006-EC07H Charlotte, NC 28201-1006Mr. Charles BrinkmanDirector, Washington Operations Westinghouse Electric Company 12300 Twinbrook Parkway, Suite 330 Rockville, MD 20852Ms. Kathryn B. NolanSenior Counsel Duke Energy Carolinas, LLC 526 South Church Street - EC07H Charlotte, NC 28202