MONTHYEARML20071C8992020-03-24024 March 2020 Closeout of Bulletin 2012-01, Design Vulnerability in Electric Power System Project stage: Other ML20365A0702020-12-30030 December 2020 Schedule Change to Open Phase Condition Detection Implementation Project stage: Request ML21049A3072021-03-0505 March 2021 Status of Closeout of Bulletin 2012-01, Design Vulnerability in Electric Power System Project stage: Other ML21165A3442021-06-29029 June 2021 Closeout of Bulletin 2012-01, Design Vulnerability in Electric Power System Project stage: Other ML21201A1052021-07-27027 July 2021 Closeout of Bulletin 2012-01, Design Vulnerability in Electric Power System Project stage: Other ML21242A3302021-09-14014 September 2021 Closeout of Bulletin 2012-01, Design Vulnerability in Electric Power System Project stage: Other ML21253A1132021-09-20020 September 2021 Closeout of Bulletin 2012-01, Design Vulnerability in Electric Power System Project stage: Other ML21272A1832021-10-19019 October 2021 Closeout of Bulletin 2012-01, Design Vulnerability in Electric Power System Project stage: Other ML21279A1672021-10-22022 October 2021 Closeout of Bulletin 2012-01, Design Vulnerability in Electric Power System Project stage: Other ML21293A0262021-10-27027 October 2021 Closeout of Bulletin 2012 01, Design Vulnerability in Electric Power System Project stage: Other ML21295A4122021-11-15015 November 2021 Closeout of Bulletin 2012-01, Design Vulnerability in Electric Power System Project stage: Other ML21323A0742021-11-22022 November 2021 Closeout of Bulletin 2012-01, Design Vulnerability in Electric Power System Project stage: Other ML22040A1582022-02-10010 February 2022 Closeout of Bulletin 2012 01, Design Vulnerability in Electric Power System Project stage: Other ML22108A2862022-04-29029 April 2022 Closeout of Bulletin 2012 01, Design Vulnerability in Electric Power System Project stage: Other ML22145A0202022-05-26026 May 2022 Closeout of Bulletin 2012-01, Design Vulnerability in Electric Power System Project stage: Other ML22186A1502022-07-0808 July 2022 Closeout of Bulletin 2012-01, Design Vulnerability in Electric Power System Project stage: Other ML22189A1772022-07-13013 July 2022 Closeout of Bulletin 2012 01, Design Vulnerability in Electric Power System Project stage: Other ML22187A2772022-07-19019 July 2022 Closeout of Bulletin 2012-01, Design Vulnerability in Electric Power System Project stage: Other ML22188A0892022-07-21021 July 2022 Closeout of Bulletin 2012 01, Design Vulnerability in Electric Power System Project stage: Other ML23025A3532023-01-26026 January 2023 Closeout of Bulletin 2012 01, Design Vulnerability in Electric Power System Project stage: Other 2021-07-27
[Table View] |
|
---|
Category:Letter
MONTHYEARIR 05000483/20240032024-10-23023 October 2024 Integrated Inspection Report 05000483/2024003 IR 05000483/20240132024-10-21021 October 2024 Design Basis Assurance Inspection (Programs) Inspection Report 05000483/2024013 IR 05000483/20244012024-10-0909 October 2024 Material Control and Accounting Program Inspection Report 05000483/2024401 Public ULNRC-06901, Concurrent Inoperability of Control Room Air Conditioning System Train and Opposite Train Emergency Diesel Generator Results in Condition Prohibited by Technical Specifications Limiting (Letter)2024-10-0101 October 2024 Concurrent Inoperability of Control Room Air Conditioning System Train and Opposite Train Emergency Diesel Generator Results in Condition Prohibited by Technical Specifications Limiting (Letter) ML24247A3042024-09-11011 September 2024 Regulatory Audit Questions for License Renewal Commitments 34 and 35 (EPID L-2024-LRO-0009) - Non-Proprietary IR 05000483/20244032024-08-28028 August 2024 Security Baseline Inspection 05000483-2024-403 IR 05000483/20240052024-08-14014 August 2024 Updated Inspection Plan for Callaway Plant (Report 05000483/2024005) IR 05000483/20253012024-08-0505 August 2024 Notification of NRC Initial Operator Licensing Examination 05000483/2025301 ML24212A2822024-08-0202 August 2024 Regulatory Audit Summary Concerning Review of Request No. C3R-01 for Proposed Alternative to ASME Code, Section XI Requirements for Containment Building Inspections IR 05000483/20240022024-07-18018 July 2024 And Independent Spent Fuel Storage Installation Integrated Inspection Report 05000483/2024002 and 07201045/2024001 ML24185A1032024-07-16016 July 2024 2024 Biennial Problem Identification and Resolution Inspection Report ULNRC-06892, Independent Spent Fuel Storage Installation Registration of Dry Spent Fuel Storage Canister HGMPC00062024-06-26026 June 2024 Independent Spent Fuel Storage Installation Registration of Dry Spent Fuel Storage Canister HGMPC0006 ULNRC-06891, Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Storage Canister HGMPC00052024-06-26026 June 2024 Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Storage Canister HGMPC0005 ULNRC-06884, Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Storage Canister HGMPC00022024-06-12012 June 2024 Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Storage Canister HGMPC0002 ULNRC-06886, Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Storage Canister HGMPC00042024-06-12012 June 2024 Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Storage Canister HGMPC0004 ULNRC-06885, Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Storage Canister HGMPC00032024-06-12012 June 2024 Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Storage Canister HGMPC0003 ML24144A0492024-06-11011 June 2024 Requests for Relief from ASME OM Code Pump and Valve Testing Requirements for Fifth 120-Month Inservice Testing Interval ML24158A5222024-06-0606 June 2024 Application to Revise Technical Specifications to Adopt Tstf-569, Rev. 2, Revise Response Time Testing Definition (LDCN 24-0008) ML24178A1132024-06-0606 June 2024 Ameren Missouris Intent to Adopt Revision 1 to Amendment 0 of Certificate of Compliance No. 1040 as Applicable to the ISFSI at the Callaway Plant Site ML24143A1632024-05-23023 May 2024 Independent Spent Fuel Storage Installation Registration of Dry Spent Storage Canister HGMPC0001 ULNRC-06882, Independent Spent Fuel Storage Installation Registration of Dry Spent Fuel Storage Canister HGMPC00122024-05-16016 May 2024 Independent Spent Fuel Storage Installation Registration of Dry Spent Fuel Storage Canister HGMPC0012 ML24137A2342024-05-16016 May 2024 Independent Spent Fuel Storage Installation - Registration of Dry Spent Fuel Storage Canister HGMPC0011 ML24122A1502024-05-0707 May 2024 Audit Plan to Support Review of Steam Generator License Renewal Response to Commitment Nos 34 and 35 ULNRC-06877, Final Safety Analysis Report Revision OL-27 and Technical Specification Bases Revision 252024-05-0606 May 2024 Final Safety Analysis Report Revision OL-27 and Technical Specification Bases Revision 25 IR 05000483/20244022024-05-0606 May 2024 Security Baseline Inspection Report 05000483/2024402 (Full Report) IR 05000483/20240112024-05-0101 May 2024 NRC Post-Approval Site Inspection for License Renewal (Phase 2) Report 05000483/2024011 ULNRC-06856, CFR 50.59 and 10 CFR 72.48 Summary Report2024-05-0101 May 2024 CFR 50.59 and 10 CFR 72.48 Summary Report ULNRC-06869, Submittal of Callaway, Unit 1, 2023 Annual Radiological Environmental Operating Report2024-04-30030 April 2024 Submittal of Callaway, Unit 1, 2023 Annual Radiological Environmental Operating Report ML24122A1132024-04-30030 April 2024 Submittal of Callaway, Unit 1, 2023 Annual Radioactive Effluent Release Report ULNRC-06876, Registration of Dry Spent Fuel Storage Canister HGMPC00102024-04-25025 April 2024 Registration of Dry Spent Fuel Storage Canister HGMPC0010 ML24108A1082024-04-17017 April 2024 Independent Spent Fuel Storage Installation Registration of Dry Spent Fuel Storage Canister HGMPC0009 ULNRC-06871, Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Storage Canister HGMPC00072024-04-17017 April 2024 Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Storage Canister HGMPC0007 ULNRC-06872, Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Storage Canister HGMPC00082024-04-17017 April 2024 Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Storage Canister HGMPC0008 ULNRC-06866, Submittal of Cycle 26 Commitment Change Summary Report2024-04-17017 April 2024 Submittal of Cycle 26 Commitment Change Summary Report IR 05000483/20240012024-04-16016 April 2024 Integrated Inspection Report 05000483/2024001 IR 05000483/20244042024-04-0909 April 2024 Cyber Security Inspection Report 05000483/2024404 ML24088A3212024-04-0101 April 2024 Notification of Commercial Grade Dedication Inspection (05000483/2024013) and Request for Information ML24086A5132024-03-26026 March 2024 CFR 50.46 Annual Report Regarding ECCS Evaluation Model Revisions ULNRC-06863, Submittal of Annual Exposure Report for 20232024-03-20020 March 2024 Submittal of Annual Exposure Report for 2023 ML24079A1622024-03-19019 March 2024 Re Nuclear Property Insurance Reporting ML24066A1932024-03-0707 March 2024 2024 Callaway Plant Notification of Biennial Problem Identification and Resolution Inspection and Request for Information ULNRC-06852, Owners Activity Reports (OAR-1 Forms) for Cycle/Refuel 262024-03-0505 March 2024 Owners Activity Reports (OAR-1 Forms) for Cycle/Refuel 26 IR 05000483/20230062024-02-28028 February 2024 Annual Assessment Letter for Callaway Plant Report 05000483/2023006 ML24052A3662024-02-26026 February 2024 Regulatory Audit Plan in Support of Proposed Alternative to ASME Code, Section XI Requirements for Containment Building Inspections ULNRC-06858, Completion of License Renewal Activities Prior to Entering the Period of Extended Operation2024-02-21021 February 2024 Completion of License Renewal Activities Prior to Entering the Period of Extended Operation ML24036A1712024-02-20020 February 2024 Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0079 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) ULNRC-06853, Submittal of 2023 Fitness for Duty Performance Data Per Per 10 CFR 26.7172024-01-29029 January 2024 Submittal of 2023 Fitness for Duty Performance Data Per Per 10 CFR 26.717 ML24008A0552024-01-19019 January 2024 Acceptance of Requested Licensing Action - Proposed Alternative to the Requirements of the ASME Code (EPID L-2023-LLR- 0061) IR 05000483/20230042024-01-19019 January 2024 – Integrated Inspection Report 05000483/2023004 ML23353A1712024-01-18018 January 2024 Issuance of Amendment No. 237 to Clarify Support System Requirements for the Residual Heat Removal System and Control Room Air Conditioning System Under Technical Specifications 3.4.8, 3.7.11, and 3.9.6 2024-09-11
[Table view] |
Text
July 27, 2021 Mr. Fadi Diya Senior Vice President and Chief Nuclear Officer Ameren Missouri Callaway Energy Center 8315 County Road 459 Steedman, MO 65077
SUBJECT:
CALLAWAY PLANT, UNIT 1 - CLOSEOUT OF BULLETIN 2012-01, DESIGN VULNERABILITY IN ELECTRIC POWER SYSTEM (EPID L-2017-CRS-0063)
Dear Mr. Diya,
The purpose of this letter is to inform you that the U.S. Nuclear Regulatory Commission (NRC) staff has verified that Union Electric Company, dba Ameren Missouri (the licensee) has provided the necessary information requested in Bulletin (BL) 2012-01, Design Vulnerability in Electric Power System, dated July 27, 2012 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML12074A115), for Callaway Plant, Unit No. 1 (Callaway).
The NRC staff has completed its review of this information and has closed out BL 2012-01 for Callaway.
The NRC issued BL 2012-01 to all holders of operating licenses and combined licenses for nuclear power reactors, except those who have permanently ceased operation and have certified that fuel has been removed from the reactor vessel. The Bulletin requested information about each facilitys electric power system designs that would allow the NRC staff to verify the systems capability to address open phase conditions. Specifically, the NRC requested licensees to provide the following information:
A description of how the protection scheme for engineered safety features buses (Class 1E for current operating plants or non-Class 1E for passive plants) is designed to detect and automatically respond to a single-phase open circuit condition or high impedance ground fault condition on offsite power circuits or another power source; and A description of the operating configuration of engineered safety features buses (Class 1E for current operating plants or non-Class 1E for passive plants) at power (i.e.,
normal operating condition).
By letter dated October 24, 2012 (ADAMS Accession No. ML12298A514), the licensee provided its response to BL 2012-01 for Callaway. By letter dated January 30, 2014 (ADAMS Accession No. ML14030A423), the license provided supplemental information for this facility in response to an NRC staff request for additional information issued on December 20, 2013 (ADAMS Accession No. ML13351A314).
By letters dated October 9, 2013, and March 16, 2015 (ADAMS Accession Nos. ML13333A147 and ML15075A454, respectively), the Nuclear Energy Institute (NEI) submitted a voluntary
F. Diya industry initiative to address open phase conditions at nuclear power plants. The NEI letter dated March 16, 2015, stated, in part: The initiative is a formal commitment by the companies that operate nuclear power plants to follow a specific policy or plan of action. The initiative calls for a proactive plan and schedule for addressing the potential design vulnerabilities to the open phase condition.
To evaluate the adequacy of the open phase isolation systems designs, the NRC staff inspected four nuclear power plants with four distinct open phase isolation system designs using the NRCs Temporary Instruction (TI) 2515/194, Inspection of the Licensees Implementation of Industry Initiative Associated with the Open Phase Condition Design Vulnerabilities in Electric Power Systems (NRC Bulletin 2012-01), dated October 31, 2017 (ADAMS Accession No. ML17137A416). A summary of the NRC staffs preliminary observations and issues needing additional clarity were discussed with industry representatives in two public meetings conducted on September 19, 2018, and October 17, 2018. The meeting summaries can be found in ADAMS under Accession Nos. ML18268A342 and ML18309A226, respectively.
In September 2018, the NRC staff performed an inspection using TI 2515/194 at Callaway to verify the licensees implementation of Revision 1 of the voluntary industry initiative at this facility. To address the open phase condition design vulnerability issue at Callaway, the licensee implemented open phase isolation system plant modifications, which provide detection, alarm, and automatic protective features. The NRC inspection report, as identified below, documents the results of this TI 2515/194 inspection. No findings or violations of more than minor significance were identified. The licensee completed the implementation of its open phase isolation system in April 2020.
NRC Inspection Report 05000483/2018011, Callaway Plant, Unit 1 - NRC Inspection of Temporary Instruction 2515/194, Inspection Report 05000483/2018011, dated October 16, 2018 (ADAMS Accession No. ML18289A652).
The NRC staff reviewed the information submitted by the licensee and the results of the TI 2515/194 inspection for Callaway. Based on this review, the NRC staff concludes that the licensee provided the necessary information requested in BL 2012-01. Therefore, the NRC staff has closed BL 2012-01 for Callaway.
If you have any questions, please contact me at 301-415-8371 or by e-mail to Mahesh.Chawla@nrc.gov.
Sincerely,
/RA/
Mahesh L. Chawla, Project Manager Plant Licensing Branch IV Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-483 cc: Listserv
ML21201A105 *by email OFFICE NRR/DORL/LPL4/PM NRR/DORL/LPL4/LA NRR/DEX/EEEB/BC (A)
NAME MChawla PBlechman SRay DATE 07/23/2021 07/20/2021 07/19/2021 OFFICE NRR/DRO/IOEB/BC NRR/DORL/LPL4/BC NRR/DORL/LPL4/PM NAME LRegner JDixon-Herrity MChawla DATE 07/26/2021 07/27/2021 07/27/2021