MONTHYEARML20071C8992020-03-24024 March 2020 Closeout of Bulletin 2012-01, Design Vulnerability in Electric Power System Project stage: Other ML20365A0702020-12-30030 December 2020 Schedule Change to Open Phase Condition Detection Implementation Project stage: Request ML21049A3072021-03-0505 March 2021 Status of Closeout of Bulletin 2012-01, Design Vulnerability in Electric Power System Project stage: Other ML21165A3442021-06-29029 June 2021 Closeout of Bulletin 2012-01, Design Vulnerability in Electric Power System Project stage: Other ML21201A1052021-07-27027 July 2021 Closeout of Bulletin 2012-01, Design Vulnerability in Electric Power System Project stage: Other ML21242A3302021-09-14014 September 2021 Closeout of Bulletin 2012-01, Design Vulnerability in Electric Power System Project stage: Other ML21253A1132021-09-20020 September 2021 Closeout of Bulletin 2012-01, Design Vulnerability in Electric Power System Project stage: Other ML21272A1832021-10-19019 October 2021 Closeout of Bulletin 2012-01, Design Vulnerability in Electric Power System Project stage: Other ML21279A1672021-10-22022 October 2021 Closeout of Bulletin 2012-01, Design Vulnerability in Electric Power System Project stage: Other ML21293A0262021-10-27027 October 2021 Closeout of Bulletin 2012 01, Design Vulnerability in Electric Power System Project stage: Other ML21295A4122021-11-15015 November 2021 Closeout of Bulletin 2012-01, Design Vulnerability in Electric Power System Project stage: Other ML21323A0742021-11-22022 November 2021 Closeout of Bulletin 2012-01, Design Vulnerability in Electric Power System Project stage: Other ML22040A1582022-02-10010 February 2022 Closeout of Bulletin 2012 01, Design Vulnerability in Electric Power System Project stage: Other ML22108A2862022-04-29029 April 2022 Closeout of Bulletin 2012 01, Design Vulnerability in Electric Power System Project stage: Other ML22145A0202022-05-26026 May 2022 Closeout of Bulletin 2012-01, Design Vulnerability in Electric Power System Project stage: Other ML22186A1502022-07-0808 July 2022 Closeout of Bulletin 2012-01, Design Vulnerability in Electric Power System Project stage: Other ML22189A1772022-07-13013 July 2022 Closeout of Bulletin 2012 01, Design Vulnerability in Electric Power System Project stage: Other ML22187A2772022-07-19019 July 2022 Closeout of Bulletin 2012-01, Design Vulnerability in Electric Power System Project stage: Other ML22188A0892022-07-21021 July 2022 Closeout of Bulletin 2012 01, Design Vulnerability in Electric Power System Project stage: Other ML23025A3532023-01-26026 January 2023 Closeout of Bulletin 2012 01, Design Vulnerability in Electric Power System Project stage: Other 2021-07-27
[Table View] |
|
---|
Category:Letter
MONTHYEARML23334A2012024-01-0303 January 2024 Issuance of Amendment No. 274 Revision to Technical Specifications to Adopt TSTF-551, Revision 3, Revise Secondary Containment Surveillance Requirements ML23311A1122023-11-0909 November 2023 Project Manager Assignment ML23311A2082023-11-0909 November 2023 Reassignment of U.S. Nuclear Regulatory Commission Branch Chief in the Division of Operating Reactor Licensing for Plant Licensing Branch IV IR 05000298/20230032023-11-0202 November 2023 Integrated Inspection Report 05000298/2023003 IR 05000298/20234012023-11-0101 November 2023 Cyber Security Report 05000298/2023401 Public ML23264A8052023-10-11011 October 2023 Issuance of Amendment No. 273 Revision to Technical Specifications to Adopt TSTF-580, Revision 1, Provide Exception from Entering Mode 4 with No Operable RHR Shutdown Cooling ML23233A1882023-09-0505 September 2023 Regulatory Audit Plan in Support of Relief Request RC3-02 Regarding Drywell Head Bolting IR 05000298/20243012023-09-0101 September 2023 Notification of NRC Initial Operator Licensing Examination 05000298/2024301 IR 05000298/20230052023-08-21021 August 2023 Updated Inspection Plan for Cooper Nuclear Station (Report 05000298/2023005)- Mid Cycle Letter IR 05000298/20230022023-08-0808 August 2023 Integrated Inspection Report 05000298/2023002 IR 05000298/20234022023-08-0303 August 2023 NRC Security Inspection Report 05000298/2023402 ML23214A2742023-08-0303 August 2023 Nuclear Station - Notification of Inspection (NRC Inspection Report 05000298/2023004) and Request for Information IR 05000298/20234202023-08-0101 August 2023 Security Baseline Inspection Report 05000298/2023420 ML23173A0862023-06-26026 June 2023 Information Request for the Cybersecurity Baseline Inspection, Notification to Perform Inspection 05000298/2023401 IR 05000298/20230102023-05-17017 May 2023 Biennial Problem Identification and Resolution Inspection Report 05000298/2023010 IR 05000298/20234032023-05-0404 May 2023 Security Baseline Inspection Report 05000298/2023403 ML23129A2822023-04-20020 April 2023 Submittal of Revision 31 to Updated Safety Analysis Report ML23102A0282023-04-19019 April 2023 U.S. Nuclear Regulatory Commission Presentation at the May 8, 2023, Brownville Village Meeting IR 05000298/20230012023-04-17017 April 2023 Integrated Inspection Report 05000298/2023001 ML23060A1582023-03-0808 March 2023 Design Basis Assurance Inspection (Programs) Inspection Report 05000298/2023001 IR 05000298/20220062023-03-0101 March 2023 Annual Assessment Letter for Cooper Nuclear Station Report 05000298/2022006 ML23041A1622023-02-10010 February 2023 Licensed Operator Positive Fitness-for-Duty Test Request for Additional Information IR 05000298/20220042023-01-30030 January 2023 Integrated Inspection Report 05000298/2022004 IR 05000298/20220112022-12-23023 December 2022 License Renewal Phase 4 Inspection Report 05000298/2022011 ML22286A2072022-11-30030 November 2022 Issuance of Amendment No. 272 Revision to Technical Specifications to Adopt TSTF-554, Revision 1, Revise Reactor Coolant Leakage Requirements IR 05000298/20220032022-10-27027 October 2022 Integrated Inspection Report 05000298/2022003 ML22304A0052022-10-26026 October 2022 Surveillance Capsule Location (Re-insertion Into the Reactor Vessel) IR 05000298/20223022022-10-20020 October 2022 NRC Initial Operator Licensing Examination Approval 05000298/2022302 ML22276A1562022-10-0505 October 2022 Notification of Commercial Grade Dedication Inspection 05000298/2023011 and Request for Information IR 05000298/20224022022-09-29029 September 2022 NRC Security Inspection Report 05000298/2022402 (Full Report) IR 05000298/20220052022-08-18018 August 2022 Updated Inspection Plan for Cooper Nuclear Station (Report 05000298 2022005) IR 05000298/20223012022-08-10010 August 2022 NRC Examination Report 05000298/2022301 IR 05000298/20220022022-07-28028 July 2022 Integrated Inspection Report 05000298/2022002 ML22200A2772022-07-21021 July 2022 Correction to Proposed Inservice Testing Alternative RS-01, Revision of Error in Safety Evaluation ML22152A1232022-07-18018 July 2022 Issuance of Amendment No. 271 Request for Exception from Certain Primary Containment Leak Rate Testing Requirements IR 05000298/20224012022-06-29029 June 2022 Security Baseline Inspection Report 05000298/2022401 IR 05000298/20224032022-06-28028 June 2022 Security Baseline Inspection Report 05000298/2022403 IR 05000298/20220102022-06-16016 June 2022 Triennial Fire Protection Inspection Report 05000298/2022010 ML22140A1612022-06-0808 June 2022 Proposed Inservice Inspection Alternative RR5-01 Revision 1 ML22147A1122022-06-0101 June 2022 NRC Initial Operator Licensing Examination Approval 05000298/2022301 ML22111A1382022-05-13013 May 2022 Proposed Inservice Testing Alternative RS-01, Revision 0 IR 05000298/20220012022-04-28028 April 2022 Integrated Inspection Report 05000298/2022001 IR 05000298/20224042022-04-13013 April 2022 Material Control and Accounting Program Inspection Report 05000298/2022404 - (Public) ML22084A6032022-04-0404 April 2022 Notification of NRC Evaluations of Changes, Tests and Experiments Inspection 05000298/2022002 and Request for Information ML22090A2892022-04-0101 April 2022 John Larson'S Invitation to Participate in the 8th Nuclear Regulatory Commission'S Workshop on Vendor Oversight ML22045A0012022-03-31031 March 2022 Proposed Inservice Inspection Alternative RI5- 02 Revision 3 IR 05000298/20210062022-03-0202 March 2022 Annual Assessment Letter for Cooper Nuclear Station (Report 05000298/2021006) IR 05000298/20210042022-01-24024 January 2022 Integrated Inspection Report 05000298/2021004 ML21350A0582021-12-21021 December 2021 Withdrawal of an Amendment Request ML21340A2362021-12-20020 December 2021 Issuance of Amendment No. 270 Adoption of Technical Specifications Task Force Traveler TSTF-582, Revision 0, RPV WIC Enhancements 2024-01-03
[Table view] |
Text
November 22, 2021 Mr. John Dent, Jr.
Vice President and Chief Nuclear Officer Nebraska Public Power District 72676 648A Avenue P.O. Box 98 Brownville, NE 68321
SUBJECT:
COOPER NUCLEAR STATION - CLOSEOUT OF BULLETIN 2012-01, DESIGN VULNERABILITY IN ELECTRIC POWER SYSTEM (EPID L-2017-CRS-0063)
Dear Mr. Dent:
The purpose of this letter is to inform you that the U.S. Nuclear Regulatory Commission (NRC) staff has verified that Nebraska Public Power District (the licensee) has provided the necessary information requested in NRCs Bulletin (BL) 2012-01, Design Vulnerability in Electric Power System, dated July 27, 2012 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML12074A115), for Cooper Nuclear Station (Cooper). The NRC staff has completed its review of this information and has closed out BL 2012-01 for Cooper.
The NRC issued BL 2012-01 on July 27, 2012, to all holders of operating licenses and combined licenses for nuclear power reactors, except those who have permanently ceased operation and have certified that fuel has been removed from the reactor vessel. The Bulletin requested information about each facilitys electric power system designs that would allow the NRC staff to verify the systems capability to address open phase conditions. Specifically, the NRC requested licensees to provide the following information:
A description of how the protection scheme for engineered safety features buses (Class 1E for current operating plants or non-Class 1E for passive plants) is designed to detect and automatically respond to a single-phase open circuit condition or high impedance ground fault condition on offsite power circuits or another power source; and A description of the operating configuration of engineered safety features buses (Class 1E for current operating plants or non-Class 1E for passive plants) at power (i.e., normal operating condition).
By letter dated October 24, 2012 (ADAMS Accession No. ML12306A090), the licensee provided its response to BL 2012-01 for Cooper. By letter dated February 3, 2014 (ADAMS Accession No. ML14038A120), the licensee provided supplemental information for this facility in response to an NRC staff request for additional information issued on December 20, 2013 (ADAMS Accession No. ML13351A314).
By letters dated October 9, 2013, and March 16, 2015 (ADAMS Accession Nos. ML13333A147 and ML15075A454, respectively), the Nuclear Energy Institute (NEI) submitted a voluntary
J. Dent, Jr. industry initiative to address open phase conditions at nuclear power plants. The NEI letter dated March 16, 2015, stated, in part: The initiative is a formal commitment by the companies that operate nuclear power plants to follow a specific policy or plan of action. The initiative calls for a proactive plan and schedule for addressing potential design vulnerabilities to the open phase condition.
To evaluate the adequacy of the open phase isolation systems designs, the NRC staff issued Temporary Instruction (TI) 2515/194, Inspection of the Licensees Implementation of Industry Initiative Associated with the Open Phase Condition Design Vulnerabilities in Electric Power Systems (NRC Bulletin 2012-01), dated October 31, 2017 (ADAMS Accession No. ML17137A416), which provided temporary inspection instructions for the purpose of verifying that licensees appropriately implemented the NEI voluntary industry initiative dated March 16, 2015. The NRC staff piloted the use of TI 2515/194 by inspecting four nuclear power plants with four distinct open phase isolation system designs. A summary of the NRC staffs preliminary observations and issues needing additional clarity were discussed with industry representatives in two public meetings conducted on September 19, 2018, and October 17, 2018. The meeting summaries can be found in ADAMS under Package Accession Nos. ML18268A342 and ML18309A226, respectively.
In an e-mail dated June 6, 2019 (ADAMS Accession No. ML19163A176), NEI submitted Revision 3 of the voluntary industry initiative to include an option for plants to perform a risk evaluation under certain boundary conditions to support manual response to an open phase condition. NEI also submitted NEI 19-02, Guidance for Assessing Open Phase Condition Implementation Using Risk Insights on June 20, 2019 (ADAMS Accession No. ML19172A086).
On August 18, 2020, the NRC staff issued Revision 2 of TI 2515/194 (ADAMS Accession No. ML20230A328), which provided temporary inspection instructions for the purpose of verifying that licensees appropriately implemented Revision 3 of the NEI voluntary industry initiative. The revision accounted for changes reflected in Revision 3 of the NEI voluntary initiative.
In November 2019, the NRC staff performed inspections at Cooper using TI 2515/194 dated October 31, 2017. In September 2021, the NRC staff performed inspections at Cooper using TI 2515/194 Revision 2. These inspections at Cooper were performed to verify the licensees implementation of the voluntary industry initiative at this facility. To address the open phase condition design vulnerability issue at this facility, the licensee implemented open phase isolation system plant modifications, which provide detection and alarm in the control room, and necessary plant procedures that allow operators to diagnose and take manual action to mitigate an open phase condition. The NRC inspection reports listed below document the results of the TI 2515/194 inspections.
Cooper Nuclear Station - Temporary Instruction 2515/194 (Inspection Report 05000298/2019013, dated December 18, 2019 (ADAMS Accession No. ML19352E279)
Cooper Nuclear Station - Temporary Instruction 2515/194 Report 05000298/2021011, dated October 19, 2021 (ADAMS Accession No. ML21288A138)
The NRC staff reviewed the information submitted by the licensee and the results of the TI 2515/194 inspections for Cooper. No findings or exceptions were identified. Based on this review, the NRC staff concludes that the licensee provided the necessary information requested
J. Dent, Jr. in BL 2012-01 and has completed the implementation of its open phase isolation system.
Therefore, the NRC staff closes BL 2012-01 for Cooper.
If you have any questions, please contact me at 301-415-4037 or via e-mail at Thomas.Wengert@nrc.gov.
Sincerely,
/RA/
Thomas Wengert, Senior Project Manager Plant Licensing Branch IV Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-298 cc: Listserv
ML21323A074 OFFICE NRR/DORL/LPL4/PM NRR/DORL/LPL4/LA NRR/DEX/EEEB/BC NRR/DRO/IOEB/BC NAME TWengert PBlechman WMorton LRegner DATE 11/22/2021 11/19/2021 11/15/2021 11/22/2021 OFFICE NRR/DRA/APOB/BC NRR/DORL/LPL4/BC NRR/DORL/LPL4/PM NAME AZoulis JDixon-Herrity TWengert DATE 11/22/2021 11/22/2021 11/22/2021