IR 05000483/2018011
| ML18289A652 | |
| Person / Time | |
|---|---|
| Site: | Callaway |
| Issue date: | 10/16/2018 |
| From: | Greg Werner NRC/RGN-IV/DRS/EB-2 |
| To: | Diya F Ameren Missouri |
| Werner G | |
| References | |
| IR 2018011 | |
| Download: ML18289A652 (13) | |
Text
October 16, 2018
SUBJECT:
CALLAWAY PLANT, UNIT 1 - NRC INSPECTION OF TEMPORARY INSTRUCTION 2515/194, INSPECTION REPORT 05000483/2018011
Dear Mr. Diya:
On September 13, 2018, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at your Callaway Plant. On September 18, 2018, the inspector discussed the results of this inspection with Mr. Roger Wink, Regulatory Affairs Manager, and other members of your staff. The results of this inspection are documented in the enclosed report.
The NRC inspector did not identify any findings or violations of more than minor significance.
This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with 10 CFR 2.390, Public Inspections, Exemptions, Requests for Withholding.
Sincerely,
/RA Gregory Pick Acting for/
Gregory E. Werner, Chief Engineering Branch 2 Division of Reactor Safety
Docket Nos. 50-483 License Nos. NPF-30
Enclosure:
Inspection Report 05000483/2018011 w/ Attachment: TI 2515/194 Inspection Documentation Request
Enclosure
U.S. NUCLEAR REGULATORY COMMISSION
Inspection Report
Docket Number(s):
05000483
License Number(s):
Report Number(s):
Enterprise Identifier: I-2018-011-0050
Licensee:
Union Electric Company
Facility:
Callaway Plant
Location:
Steedman, Missouri
Inspection Dates:
September 10, 2018, to September 13, 2018
Inspectors:
B. Correll, Reactor Inspector
Approved By:
Gregory E. Werner, Chief
Engineering Branch 2
Division of Reactor Safety
SUMMARY
The U.S. Nuclear Regulatory Commission (NRC) continued monitoring licensees performance by conducting Temporary Instruction 2515/194, Inspection of the Licensees Implementation of Industry Initiative Associated with the Open Phase Condition Design Vulnerabilities in Electric Power Systems (NRC Bulletin 2012-01), at Callaway Plant, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the Nuclear Regulatory Commission program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.
List of Findings and Violations
No findings were identified.
Additional Tracking Items
None.
INSPECTION SCOPE
This inspection was conducted using Temporary Instruction 2515/194 (ADAMS Accession No. ML17137A416), dated October 31, 2017. The inspectors reviewed the licensees implementation of Nuclear Energy Institute voluntary industry initiative in compliance with Commission guidance. The inspector discussed the licensees open phase condition system design and ongoing implementation plans with plant staff. The inspector reviewed licensee and vendor documentation, and performed system walk downs to verify that the installed equipment was supported by the design documentation. The inspector verified that the licensee had completed the installation and testing of equipment (with the exception of the tripping functions),installed and tested alarming circuits both local and in the control room, and analyzed potential impacts associated with the design implementation on the current licensing basis.
OTHER ACTIVITIES
- TEMPORARY INSTRUCTIONS, INFREQUENT AND ABNORMAL
Temporary Instruction 2515/194 - Inspection of the Licensees Implementation of Industry Initiative Associated With the Open Phase Condition Design Vulnerabilities in Electric Power Systems (NRC BULLETIN 2012-01)
The objective of Temporary Instruction 2515/194 is to verify that licensees have appropriately implemented the Nuclear Energy Institute voluntary industry initiative (ADAMS Accession No. ML15075A454), dated March 16, 2015, including updating their licensing basis to reflect the need to protect against open phase conditions.
Temporary Instruction 2515/194-03.01 - Voluntary Industry Initiative (Part 1)
Callaway Plant selected a hybrid design using safety-related negative sequence relays and the open phase detection system designed and manufactured by Power System Sentinel Technologies, LLC. At the end of this inspection the system was still in the monitoring mode of operation to facilitate continued data gathering of grid perturbations for evaluation of alarm and trip setpoints. The open phase condition equipment was installed on the safety-related 4160 Vac buses (NB01 and NB02), and the Power System Sentinel Technologies, LLC equipment installed on Safeguards Transformer A (XMDV24). The licensee is scheduled to transition the negative sequence relays to full implementation (tripping functions enabled) by December 31, 2018. The licensee was preparing associated documentation for this transition, however they were not available for review at the time of inspection.
INSPECTION RESULTS
- OBSERVATIONS/ASSESSMENT
Based on discussions with the licensee staff, review of available design, testing, grid data trending results documentation, and walk downs of installed equipment, the inspector had reasonable assurance the licensee appropriately implemented the voluntary industry initiative.
The inspector determined that:
Detection, Alarms, and General Criteria TI 2515/194-03.01 - Voluntary Industry Initiative (Part 1)
- (1) Open phase conditions will be detected and alarmed in the control room for each unit on the common annunciator panel.
- (2) Detection circuits will be sensitive enough to identify an open phase condition for all credited loading conditions.
- (3) No Class-1E circuits were being replaced with non-Class 1E circuits in the design.
Protective Actions Criteria TI 2515/194-03.01 - Voluntary Industry Initiative (Part 1)
- (1) One transformer was susceptible to an open phase condition and the licensee was implementing design changes to mitigate the effects.
- (2) With an open phase condition present and no accident condition signal, the open phase design would not adversely affect the function of important-to-safety systems, structures, or components. The licensees open phase condition design solution added two safety-related negative sequence relays on the safety-related 4160 Vac buses, and a Power System Sentinel Technologies system on the Safeguards B transformer for alarm only. This addition added a new tripping condition (open phase) to safety-related bus incoming supply breakers. The credited plant response was unaffected and would be the same regardless of the conditions that generated the isolation of the transformer.
No findings were identified.
The inspector identified the following exceptions to the Temporary Instruction criteria resulting from the incomplete design modifications:
Detection, Alarms and General Criteria Exceptions TI 2515/194-03.01 - Voluntary Industry Initiative (Part 1)
- (1) The licensees design was operating in the monitoring mode with established setpoints enabled to gather data to ensure the open phase condition design and protective schemes would minimize misoperation, or spurious actions in the range of voltage unbalance normally expected in the transmission system. Because actual demonstration of this criterion requires the system to be in operation with final trip setpoints established, the inspector was not able to fully verify this criterion. After discussions with licensee staff, design document and test results reviews, the inspector had reasonable assurance that the actuation circuit design would not result in lower overall plant reliability. The inspector did not identify any issues of concern.
- (2) The Final Safety Analysis Report (FSAR) had not been updated to include information related to open phase conditions at the conclusion of the onsite inspection. The licensee provided the inspector with proposed changes to the licensing basis that discussed the system requirements related to the effects of, and protection for, any open phase condition design vulnerability. The licensee continued to modify and update the proposed changes during the onsite portion of the inspection. The inspector verified the proposed change process is being tracked under License Document Change Notice, LDCN 17-0012 for the completion of the FSAR updates.
The inspector did not identify any issues of concern.
Protective Actions Criteria Exceptions TI 2515/194-03.01 - Voluntary Industry Initiative (Part 1)
- (1) The licensees open phase condition design solution uses safety-related negative sequence relays on the 4160 Vac safety buses in a 2-out-of-2 coincidence logic for protection. A voltage unbalance of sufficient magnitude will actuate both negative sequence relays. The relays are designed to trip open the normal and alternate supply breakers to the associated safety bus, causing a loss of voltage to the bus.
The existing undervoltage relays will operate as designed to initiate starting of the emergency diesel generator to restore power to the bus.
The tripping function of the incoming breakers remained disabled during the onsite portion of the inspection and was not able to be demonstrated to perform the designed function. This action was being tracked in the modification package MP 15-0008.
Through review of design documents and discussions with licensee staff, the inspector had reasonable assurance that with an open phase condition present and with and without an accident condition signal, the open phase design would isolate the affected bus and cause an automatic restoration of power from the emergency diesel generators. Due to the configuration of Callaway Plants electrical distribution system, a loss of phase on one transformer would only affect one train of equipment, and loads required to mitigate postulated accidents would be available on the non-affected train, ensuring that safety functions are preserved as required by the current licensing bases. The inspector did not identify any issues of significance.
- (2) At the time of this inspection, the licensee had not finalized documentation for periodic tests, calibrations, setpoint verifications, or inspection procedures associated with the Power System Sentinel Technologies, LLC at the time of this inspection. This action was being tracked in the modification package MP 15-0008. The inspector held discussions with licensee staff and identified that plans were in place to establish contracts with the vendor to provide maintenance and support activities for the Power System Sentinel Technologies, LLC equipment.
The licensee established maintenance activities for the safety-related portion of the open phase condition design, and the inspector verified the activities were appropriate.
Existing plant equipment will continue to be maintained according to the licensees current preventative maintenance program. The inspector did not identify any issues of concern.
EXIT MEETINGS AND DEBRIEFS
On September 18, 2018, the inspector conducted a telephonic exit to present the Temporary Instruction 2515/194 inspection results to Mr. R. Wink, Regulatory Affairs Manager, and other members of the licensee staff. The inspector verified no proprietary information was retained.
DOCUMENTS REVIEWED
Inspection Procedure TI 2515/194
Condition Reports
201707350
201707586
201802205
201802672
Drawings
Number
Title
Revision
8618-X-94076
Metering and Relaying 345-13.8KV Safeguard
Transformers POSN-V22 and V24
8618-X-94091
345-13.8KV SFGD XFMR-B AC Portion
8618-X-94726
Annunciator -1 Sheet -2 Drop -51 Thru 96, 98, & 100 18
8618-X-94760
Alarms and Metering to Plant Unit-1 ANN., BOP
Computer and Site Related Panel
8618-X-95741
345-13.8KV SFGD XFMR-B DC Portion
E-21001
Main Single Line Diagram
E-21023
Relay Setting Tabulations and Coordination Curves
System NB
E-21NB01
Lower Medium Voltage System Class 1E 4.16KV
Single Line Meter and Relay Diagram
E-21NB02
Lower Medium Voltage System Class 1E 4.16KV
Single Line Meter and Relay Diagram
E-23NB01
Lower Medium Voltage System Class 1E 4.16KV
Three Line Meter and Relay Diagram
E-23NB03
Lower Medium Voltage System Class 1E 4.16KV
Three Line Meter and Relay Diagram
E-23NB04
Lower Medium Voltage System Class 1E 4.16KV
Three Line Meter and Relay Diagram
E-23NB06
Lower Medium Voltage System Class 1E 4.16KV
Three Line Meter and Relay Diagram
E-23NB12
Class 1E Bus NB01 Feeder Brkr 152NB0112
E-23NB13
Class 1E Bus NB01 Feeder Brkr 152NB0109
E-23NB14
Class 1E Bus NB02 Feeder Brkr 152NB0209
E-23NB15
Class 1E Bus NB02 Feeder Brkr 152NB0212
Engineering Studies
Number
Title
Revision
MP 15-0008
Engineering Disposition - Modification Open Phase
Condition Protection
007
NB-05
System NB Protective Relay Setpoints
004, Addendum
ZZ-561
Open Phase Fault Study for the Callaway Energy
Center
000
Miscellaneous
Documents
Number
Title
Revision
or Date
DCN: IEGR-DD-1672
Open Phase Protection (OPP) System Non-Class 1E
OPP Protection Settings, Ameren-Callaway SFGD-B
0.0.1
DCN: ITST-TP-1704
Open Phase Protection (OPP) System Site
Acceptance Test (SAT) Plan Single Channel Analog
System for the Callaway Nuclear Plant
0.0.2
Evaluation of Inclusion of Open Phase Condition
Equipment Requirements in the Technical
Specifications
October 8, 2015
LOCT/NLOCT
T61.0810 8/T61.0740
Cycle 18-1
Large Transformers
January 25,
2018
Modification
Number
Title
Revision
MP 15-0008
Open Phase Condition Protection
000
Procedures
Number
Title
Revision
MPE-ZZ-QY055
Inspection, Test and Calibration of Protective
Negative Sequence Overvoltage Relays, ABB
Type 60Q
000
MPE-ZZ-QY109
Operational Test Sequence of 4.16KV Bus NB01
Main Air Circuit Breaker 152NB0109
011
MPE-ZZ-QY112
Operational Test Sequence of 4.16KV Bus NB01
Main Air Circuit Breaker 152NB0112
011
MPE-ZZ-QY126
Operational Test Sequence of 4.16KV Bus NB02
Main Air Circuit Breaker 152NB0209
013
MPE-ZZ-QY129
Operational Test Sequence of 4.16KV Bus NB02
Main Air Circuit Breaker 152NB0212
011
Procedures
Number
Title
Revision
OTA-RK-00016,
Addendum 21B
NB02 Bus Undervoltage
000
OTA-RK-00016,
Addendum 21D
NB02 Undervoltage Relay 1/4
001
OTA-RK-00016,
Addendum 22E
NB02 Bus Degraded Voltage or Phase Imbalance
003
OTA-ZZ-00SA1,
Addendum 77
Safeguards Transformer B Open Phase Trouble
2
OTO-NB-00002
Loss of Power to NB02
031
Vendor Document
Number
Title
Revision
IB 7.4.1.7-3
ABB Phase Unbalance Relay
Issue C
TI 2515/194 Inspection Documentation Request
Please provide the following documentation (Items 1 - 8) to the lead inspector prior to the onsite
inspection date, preferably no later than August 27, 2018. Whenever practical, please provide
copies electronically (IMS/CERTREC is preferred). Please provide an index of the requested
documents which includes a brief description of the document and the numerical heading
associated with the request (i.e., where it can be found in the list of documents requested).
Brian Correll, Lead Inspector
RIV/DRS/EB2
1600 E. Lamar Blvd.
Arlington, TX 76011
817-200-1565
brian.correll@nrc.gov
1. Copies of any calculations, analyses, and/or test reports performed to support the
implementation of your open phase condition (OPC) solution. If, in your implementation,
OPCs are not detected and alarmed in the control room please include documentation that:
a. Demonstrates the OPC will not prevent functioning of important-to-safety SSCs; AND
b. Detection of an OPC will occur within a short period of time (e.g., 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />).
2. Copies of any modification packages, including 10 CFR 50.59 evaluations if performed,
used for or planned for the implementation of your OPC solution.
3. Copies of periodic maintenance, surveillance, setpoint calibration, and/or test procedures
implemented or planned, for your OPC solution.
4. Copies of your licensing basis changes to Updated Final Safety Analysis Report (UFSAR)
and/or Technical Specifications (TS), as applicable, which discuss the design features and
analyses related to the effects of, and protection for, any open phase condition design
vulnerability. If these documents have not been updated, provide documentation of your
plans to do so.
5. Copies of any procurement specifications and acceptance testing documents related to the
installation of your OPC solution.
6. Copies of any site training the team will need to accomplish to gain access to areas with, or
planned, major electrical equipment used in your OPC solution (i.e. switchyard).
7. Provide documentation showing that with an OPC occurrence and no accident condition
signal present, either:
a. An OPC does not adversely affect the function of important-to-safety SSCs, OR
b. TS LCOs are maintained or the TS actions are met without entry into TS LCO 3.0.3
AND
i.
Important-to-safety equipment is not damaged by the OPC, AND
ii.
Shutdown safety is not compromised
8. With OPC occurrence and an accident condition signal present:
a. Provide documentation showing that automatic detection and actuation will transfer
loads required to mitigate postulated accidents to an alternate source and ensure
that safety functions are preserved, as required by the current licensing bases, OR
b. Provide documentation showing that all design basis accident acceptance criteria are
met with the OPC, given other plant design features. Accident assumptions must
include licensing provisions associated with single failures. Typically, licensing bases
will not permit consideration of the OPC as the single failure since this failure is a
non-safety system.
Please provide the following documentation to the team when they arrive onsite. Whenever
practical, please provide copies electronically, except for drawings. Drawings should be
provided as paper copies of sufficient size (ANSI C or D) such that all details are legible.
9. A brief presentation describing your electric power system design and typical electrical
transmission and distribution system alignments; OPC design schemes installed to detect,
alarm and actuate; bus transfer schemes; and maintenance and surveillance requirements.
This presentation should be a general overview of your system. Please schedule the
overview shortly after the entrance meeting.
10. Plant layout and equipment drawings for areas that identify: (a) the physical plant locations
of major electrical equipment used in your open phase condition solution; (b) the locations of
detection and indication equipment used in the open phase condition sensing circuits.
11. If OPC actuation circuits are required, provide documentation that demonstrates continued
coordination with the other protective devices in both the offsite electrical system (within
Callaway Plant area of responsibility) and the onsite electrical systems.
2. Access to locations in which open phase condition equipment is installed or planned (i.e.
switchyard, etc.)
Copies of documentation or testing that demonstrates your OPC solution minimizes spurious
actuation or misoperation in the range of voltage imbalance normally expected in the
transmission system that could cause undesired separation from an operable off-site power
source.
This document does not contain new or amended information collection requirements
subject to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing
information collection requirements were approved by the Office of Management and
Budget, Control Number 31500011. The NRC may not conduct or sponsor, and a person
is not required to respond to, a request for information or an information collection
requirement unless the requesting document displays a currently valid Office of
Management and Budget control number.
This document will be made available for public inspection and copying at
http://www.nrc.gov/reading-rm/adams.html and at the NRC Public document Room in
accordance with 10 CFR 2.390, Public Inspections, Exemptions, Requests for
Withholding.
SUNSI Review: ADAMS: Non-Publicly Available Non-Sensitive Keyword: NRC-002
By: BKC Yes No Publicly Available Sensitive
OFFICE
RI: EB2
C:EB2
C:PBB
C:EB2
NAME
BCorrell
GWerner
NTaylor
GWerner
SIGNATURE
/RA/
/RA/
/RA/
/RA/GAP for
DATE
09/21/2018
10/10/2018
10/13/2018
10/16/2018