MONTHYEARULNRC-05295, Response Update to Generic Letter 2004-02: Potential Impact of Debris Blockage on Emergency Recirculation During Design Basis Accidents at Pressurized-Water Reactors2006-05-30030 May 2006 Response Update to Generic Letter 2004-02: Potential Impact of Debris Blockage on Emergency Recirculation During Design Basis Accidents at Pressurized-Water Reactors Project stage: Request ULNRC-05293, Revision to Technical Specification 3.5.2, ECCS - Operating, and 3.6.7, Recirculation Fluid Ph Control System.2006-05-30030 May 2006 Revision to Technical Specification 3.5.2, ECCS - Operating, and 3.6.7, Recirculation Fluid Ph Control System. Project stage: Request ULNRC-05347, Response to Request for Additional Information Revision to Technical Specification 3.5.2, ECCS - Operating.2006-11-22022 November 2006 Response to Request for Additional Information Revision to Technical Specification 3.5.2, ECCS - Operating. Project stage: Response to RAI ULNRC-05351, Response to Request for Additional Information Regarding 10 CFR 50.55a Request ISI-33 (Request for Relief from ASME Section XI Inservice Inspection Qualification Requirements)2006-12-12012 December 2006 Response to Request for Additional Information Regarding 10 CFR 50.55a Request ISI-33 (Request for Relief from ASME Section XI Inservice Inspection Qualification Requirements) Project stage: Response to RAI ULNRC-05353, Clarifying Information Regarding Application for License Amendment to Revise Technical Specification 3.6.7, Recirculation Fluid Ph Control System.2006-12-19019 December 2006 Clarifying Information Regarding Application for License Amendment to Revise Technical Specification 3.6.7, Recirculation Fluid Ph Control System. Project stage: Request ML0705206142007-02-21021 February 2007 Tech Spec Pages for Amendment 180 Regarding Replacing Containment Sump Trash Racks and Screens with Strainers and Relocate the Containment Ph Control System from Current Location Project stage: Acceptance Review ML0634200472007-02-21021 February 2007 License Amendment 180 Regarding Replacing Containment Sump Trash Racks and Screens with Strainers and Relocate the Containment Ph Control System from Current Location Project stage: Approval ML0705803332007-03-15015 March 2007 Authorization of Relief Request No. ISI-33 for Second 10-Year and Third 10-Year ISI Interval Project stage: Other ML0708710142007-03-29029 March 2007 Correction to Authorization of Relief Request No. ISI-33 for the Second and Third 10-Year Inservice Inspection Intervals Project stage: Other ML0710103542007-04-18018 April 2007 Correction to Amendment No. 180 Replacing Containment Sump Trash Racks and Screens with Strainers and Relocate Containment Ph Control System from Current Location Project stage: Other 2006-05-30
[Table View] |
|
---|
Category:Letter
MONTHYEARULNRC-06853, Submittal of 2023 Fitness for Duty Performance Data Per Per 10 CFR 26.7172024-01-29029 January 2024 Submittal of 2023 Fitness for Duty Performance Data Per Per 10 CFR 26.717 IR 05000483/20230042024-01-19019 January 2024 Integrated Inspection Report 05000483/2023004 ML24008A0552024-01-19019 January 2024 Acceptance of Requested Licensing Action - Proposed Alternative to the Requirements of the ASME Code (EPID L-2023-LLR- 0061) ML23353A1712024-01-18018 January 2024 Issuance of Amendment No. 237 to Clarify Support System Requirements for the Residual Heat Removal System and Control Room Air Conditioning System Under Technical Specifications 3.4.8, 3.7.11, and 3.9.6 ML23317A0012024-01-12012 January 2024 Audit Summary Regarding LAR to Clarify Support System Requirements for the Residual Heat Removal and Control Room Air Conditioning System Under Technical Specifications 3.4.8, 3.7.11, and 3.9.6 ML23347A1212024-01-11011 January 2024 Issuance of Amendment No. 236 to Adopt TSTF-501, Revision 1, Relocate Stored Fuel Oil and Lube Volume Values to Licensee Control EPID L-2023-LLA-0046) ML24011A1492024-01-11011 January 2024 Notification of Post-Approval Site Inspection for License Renewal and Request for Information (05000483/2024011) ULNRC-06847, Supplement to Relief Request from Requirements of ASME BPV Code, Section XI, Subsection Iwl Regarding Examination and Testing of the Unbonded Post-Tensioning System (Relief Request C3R-01)2023-12-21021 December 2023 Supplement to Relief Request from Requirements of ASME BPV Code, Section XI, Subsection Iwl Regarding Examination and Testing of the Unbonded Post-Tensioning System (Relief Request C3R-01) ULNRC-06849, License Renewal Resolution for Commitments 34 and 35 Perform Evaluation of Crack Initiation and Propagation in Steam Generator Divider Plate and Tube-To-Tubesheet Welds2023-12-20020 December 2023 License Renewal Resolution for Commitments 34 and 35 Perform Evaluation of Crack Initiation and Propagation in Steam Generator Divider Plate and Tube-To-Tubesheet Welds ML23346A0392023-12-14014 December 2023 Supplemental Information Needed for Acceptance of Requested Licensing Action Request for Relief from Requirements of ASME Code, Section Xl, Examination and Testing Unbonded Post-Tensioning System ULNRC-06844, Request for Exemption from Specific Requirements in 2023 Security Rule, Enhanced Weapons, Firearms Background Checks, and Security Event Notification2023-12-0707 December 2023 Request for Exemption from Specific Requirements in 2023 Security Rule, Enhanced Weapons, Firearms Background Checks, and Security Event Notification 05000483/LER-2023-001, Submittal of LER 2023-001-00 for Callaway, Unit 1, Inoperable Instrument Tunnel Sump Level Indication Resulted in Condition Prohibited by Technical Specifications2023-11-29029 November 2023 Submittal of LER 2023-001-00 for Callaway, Unit 1, Inoperable Instrument Tunnel Sump Level Indication Resulted in Condition Prohibited by Technical Specifications ULNRC-06827, Supplement to License Amendment Request Regarding Support System Requirements for Residual Heat Removal and Control Room Air Conditioning Systems Under Technical Specifications 3.4.8, 3.7.11, and 3.9.6 (LDCN 22-0029)2023-11-20020 November 2023 Supplement to License Amendment Request Regarding Support System Requirements for Residual Heat Removal and Control Room Air Conditioning Systems Under Technical Specifications 3.4.8, 3.7.11, and 3.9.6 (LDCN 22-0029) IR 05000483/20230102023-11-15015 November 2023 NRC License Renewal Phase 1 Inspection Report 05000483 2023010 IR 05000483/20233012023-11-0909 November 2023 NRC Examination Report 05000483-2023301 ML23311A2082023-11-0909 November 2023 Reassignment of U.S. Nuclear Regulatory Commission Branch Chief in the Division of Operating Reactor Licensing for Plant Licensing Branch IV ML23297A2502023-11-0606 November 2023 Individual Notice of Consideration of Issuance of Amendment to Renewed Facility Operating License, Proposed No Significant Hazards Consideration Determination and Opportunity for a Hearing (EPID L-2022-LLA-0176) - Letter IR 05000483/20240122023-10-24024 October 2023 Information Request for the Cybersecurity Baseline Inspection, Notification to Perform Inspection (05000483/2024012) ML23293A2652023-10-24024 October 2023 3rd Quarter 2023 Integrated Inspection Report ML23240A3692023-10-0505 October 2023 Issuance of Amendment No. 235 to Revise Technical Specifications to Use of Framatome Gaia Fuel (EPID L-2022-LLA-0150) (Non-Proprietary) ML23234A1522023-10-0505 October 2023 Exemption from the Requirements of 10 CFR Part 50, Section 50.46, and Appendix K Regarding Use of M5 Cladding Material (EPID L-2022-LLE-0030) (Letter) ML23305A0942023-10-0202 October 2023 10-CW-2023-09 Post-Exam Submittal ML23270B9662023-09-27027 September 2023 10 CFR 50.55a(z)(I) Request for Relief from ASME OM Code Pump and Valve Testing Requirements for Fifth 120-Month Inservice Testing Interval ML23228A0252023-09-25025 September 2023 Issuance of Amendment No. 234 to Revise Technical Specification 5.5.16, Containment Leakage Rate Testing Program, for Permanent Extension of Type a and Type C Leak Rate Test Frequencies ML23261C3852023-09-25025 September 2023 Safety Evaluation for Operating Quality Assurance Manual Revision 36A ML23166B0882023-09-20020 September 2023 Issuance of Amendment No. 233 for Adoption of Alternative Source Term and Revision of Technical Specifications ML23206A1992023-09-15015 September 2023 Regulatory Audit Summary Regarding License Amendment and Regulatory Exemptions Request for Fuel Transition to Framatome Gaia Fuel (Epids L-2022-LLA-0150 and L-2022-LLE-0030) IR 05000483/20234012023-09-13013 September 2023 NRC Security Baseline Inspection Report 05000483/2023401 ML23240A7572023-08-31031 August 2023 NRC Initial Operator Licensing Examination Approval 05000483/2023301 IR 05000483/20230052023-08-23023 August 2023 Updated Inspection Plan for Callaway Nuclear Power Plant, Unit 1 (Report 05000483/2023005) - Mid Cycle Letter 2023 ULNRC-06824, Response to Request for Additional Information Regarding Operating Quality Assurance Manual (Oqam) Revision 36A2023-08-17017 August 2023 Response to Request for Additional Information Regarding Operating Quality Assurance Manual (Oqam) Revision 36A ML23219A1392023-08-15015 August 2023 Request for Withholding Information from Public Disclosure ULNRC-06830, Transmittal of Updated Technical Specification Markup and Clean Pages for License Amendment Request to Revise Technical Specification 5.5.16, Containment Leakage Rate Testing Program, for Permanent Extension of Type a and Type C Leak2023-08-15015 August 2023 Transmittal of Updated Technical Specification Markup and Clean Pages for License Amendment Request to Revise Technical Specification 5.5.16, Containment Leakage Rate Testing Program, for Permanent Extension of Type a and Type C Leak ML23215A1972023-08-0303 August 2023 Supplement to License Amendment and Exemption Request Regarding Use of Framatome Gaia Fuel (LDCN 22-0002) ULNRC-06223, Minor Correction to License Amendment Request to Revise Technical Specification 5.5.16, Containment Leakage Rate Testing Program, for Permanent Extension of Type a and Type C Leak Rate Test Frequencies (LDCN 2020-0004)2023-07-25025 July 2023 Minor Correction to License Amendment Request to Revise Technical Specification 5.5.16, Containment Leakage Rate Testing Program, for Permanent Extension of Type a and Type C Leak Rate Test Frequencies (LDCN 2020-0004) ULNRC-06799, Submittal of Licensee Event Report 2022-003-01, Class 1E Electrical Air Conditioning System Thermal Expansion Valve Failure Resulted in Condition Prohibited by Technical Specifications2023-07-13013 July 2023 Submittal of Licensee Event Report 2022-003-01, Class 1E Electrical Air Conditioning System Thermal Expansion Valve Failure Resulted in Condition Prohibited by Technical Specifications IR 05000483/20230022023-07-10010 July 2023 Integrated Inspection Report 05000483/2023002 ML23174A1272023-06-23023 June 2023 Cw FFD Document Request List 2023 ML23171A9942023-06-22022 June 2023 Acceptance of Request for Approval of Operating Quality Assurance Manual Revision 36a ULNRC-06821, Post-Audit Follow-Up Information in Support of Callaway'S License Amendment Request and Proposed Exemption to Allow Use of Framatome Gaia Fuel (LDCN 22-0002) (EPID L-2022-LLA-0150 and EPID L-2022-LLE-00301)2023-06-21021 June 2023 Post-Audit Follow-Up Information in Support of Callaway'S License Amendment Request and Proposed Exemption to Allow Use of Framatome Gaia Fuel (LDCN 22-0002) (EPID L-2022-LLA-0150 and EPID L-2022-LLE-00301) IR 05000483/20230112023-06-15015 June 2023 Comprehensive Engineering Team Inspection (CETI) Inspection Report 05000483/2023011 ULNRC-06822, Additional Information Regarding Request for NRC Approval of Operating Quality Assurance Manual (Oqam) Revision 36a2023-06-14014 June 2023 Additional Information Regarding Request for NRC Approval of Operating Quality Assurance Manual (Oqam) Revision 36a ML23158A1462023-06-13013 June 2023 Notification of Post-Approval Site Inspection for License Renewal and Request for Information Inspection (05000483/2023010) ULNRC-06815, Request for NRC Approval of Operating Quality Assurance Manual, Revision 36a2023-06-0505 June 2023 Request for NRC Approval of Operating Quality Assurance Manual, Revision 36a ULNRC-06818, Response to Request for Additional Information Regarding License Amendment Request to Revise Technical Specification 5.5.16, Containment Leakage Rate Testing Program, for Permanent Extension of Type a and Type C Leak Rate .2023-06-0505 June 2023 Response to Request for Additional Information Regarding License Amendment Request to Revise Technical Specification 5.5.16, Containment Leakage Rate Testing Program, for Permanent Extension of Type a and Type C Leak Rate . ML23093A0952023-05-10010 May 2023 Issuance of Amendment No. 232 Regarding Technical Specification Changes for Spent Fuel Storage ULNRC-06816, Withdrawal of Previously Submitted Enclosures Regarding License Amendment Request for Adoption of Alternative Source Term and Revision of Technical Specifications (LDCN 21-0015)2023-05-0909 May 2023 Withdrawal of Previously Submitted Enclosures Regarding License Amendment Request for Adoption of Alternative Source Term and Revision of Technical Specifications (LDCN 21-0015) ML23129A7942023-05-0909 May 2023 Post-Audit Supplement to License Amendment Request and Exemption to Allow Use of Framatome Gaia Fuel (LDCN 22-0002) (Iepid L-2022-LLA-0150 and EPID L-2022-LLE-0030) ML23122A3172023-05-0808 May 2023 Review of the Spring 2022 Steam Generator Tube Inservice Inspections ML23118A3492023-05-0808 May 2023 Request for Withholding Information from Public Disclosure 2024-01-29
[Table view] |
Text
April 18, 2007Mr. Charles D. NaslundSenior Vice President and Chief Nuclear Officer Union Electric Company Post Office Box 620 Fulton, MO 65251
SUBJECT:
CALLAWAY PLANT, UNIT 1 - CORRECTION TO AMENDMENT NO. 180 RE: REPLACING CONTAINMENT SUMP TRASH RACKS AND SCREENS WITH STRAINERS AND RELOCATE CONTAINMENT PH CONTROL SYSTEM FROM CURRENT LOCATION (TAC NO. MD2363)
Dear Mr. Naslund:
In our letter to you dated February 21, 2007, the Nuclear Regulatory Commission (NRC) issuedAmendment No. 180 to Facility Operating License No. NPF-30 for the Callaway Plant, Unit 1.
The amendment consisted of changes to the Technical Specifications, in response to yourapplication dated May 30, 2006 (ULNRC-05293), as supplemented by letters dated November 22 and December 19, 2006 (ULNRC-05347 and ULNRC-05353, respectively).Inadvertently, in the amendment, the NRC staff also issued an out-of-date Page 5 of thelicense. Enclosed is a corrected Page 5 of the license with the correct reference to the revised Callaway Physical Security Plan, Training and Qualification Plan, and Safeguards Contingency Plan that implemented NRC Order EA-06-037, which was issued on February 13, 2007.Please replace Page 5 of the license with the enclosed page. We apologize for any problemscaused by this mistake.Sincerely,/RA/Jack Donohew, Senior Project ManagerPlant Licensing Branch IV Division of Operating Reactor Licensing Office of Nuclear Reactor RegulationDocket No. 50-483
Enclosure:
Revised Page 5 of the license cc w/encl: See next page April 18, 2007Mr. Charles D. Naslund Senior Vice President and Chief Nuclear Officer Union Electric Company Post Office Box 620 Fulton, MO 65251
SUBJECT:
CALLAWAY PLANT, UNIT 1 - CORRECTION TO AMENDMENT NO. 180 RE: REPLACING CONTAINMENT SUMP TRASH RACKS AND SCREENS WITH STRAINERS AND RELOCATE CONTAINMENT PH CONTROL SYSTEM FROM CURRENT LOCATION (TAC NO. MD2033)
Dear Mr. Naslund:
In our letter to you dated February 21, 2007, the Nuclear Regulatory Commission (NRC) issuedAmendment No. 180 to Facility Operating License No. NPF-30 for the Callaway Plant, Unit 1.
The amendment consisted of changes to the Technical Specifications, in response to yourapplication dated May 30, 2006 (ULNRC-05293), as supplemented by letters dated November 22 and December 19, 2006 (ULNRC-05347 and ULNRC-05353, respectively).Inadvertently, in the amendment, the NRC staff also issued an out-of-date Page 5 of thelicense. Enclosed is a corrected Page 5 of the license with the correct reference to the revised Callaway Physical Security Plan, Training and Qualification Plan, and Safeguards Contingency Plan that implemented NRC Order EA-06-037, which was issued on February 13, 2007.Please replace Page 5 of the license with the enclosed page. We apologize for any problemscaused by this mistake.Sincerely,/RA/Jack Donohew, Senior Project ManagerPlant Licensing Branch IV Division of Operating Reactor Licensing Office of Nuclear Reactor RegulationDocket No. 50-483DISTRIBUTION
- PUBLICLPLIV Reading
Enclosure:
Revised Page 5 of the licenseRidsNrrDorlDprGHill (2)RidsNrrDorlcc w/encl: See next pageRidsNrrDorlLpl4RidsNrrPMJDonohew RidsNrrLALFeizollahi RidsOgcRp RidsAcrsAcnwMailCenter RidsRegion4MailCenterACCESSION NO.: ML071010354OFFICENRR/LPL4/PMNRR/LPL4/LANRR/LPL4/BCNAMEJDonohewLFeizollahiTHiltz DATE04/17/074/18/074/18/07OFFICIAL RECORD COPY (11)Steam Generator Tube Rupture (Section 15.4.4, SSER #3)Deleted per Amendment No. 169.(12)Low Temperature Overpressure Protection (Section 15, SSER #3)Deleted per Amendment No. 169.(13)LOCA Reanalysis (Section 15, SSER #3)Deleted per Amendment No. 169.(14)Generic Letter 83-28Deleted per Amendment No. 169.(15)Additional ConditionsThe Additional Conditions contained in Appendix C, as revised throughAmendment No. 180, are hereby incorporated into this license. UE shall loperate the facility in accordance with the Additional Conditions.D.An Exemption from certain requirements of Appendix J to 10 CFR Part 50, aredescribed in the October 9, 1984 staff letter. This exemption is authorized by law and will not endanger life or property or the common defense and security and are otherwise in the public interest. Therefore, this exemption is hereby granted pursuant to 10 CFR 50.12. With the granting of this exemption the facility will operate, to the extent authorized herein, in conformity with the application, as amended, the provisions of the Act, and the rules and regulations of the Commission.E.UE shall fully implement and maintain in effect all provisions of theCommission-approved physical security, training and qualification, and safeguards contingency plans including amendments made pursuant to provisions of the Miscellaneous Amendments and Search Requirements revisions to 10 CFR 73.55 (51 FR 27817 and 27822) and to the authority of 10 CFR 50.90 and 10 CFR 50.54(p). The combined set of plans, which contain Safeguards Information protected under 10 CFR 73.21, are entitled: "Callaway Security Plan, Training and Qualification Plan, and Safeguards Contingency Plan, Revision 0" submitted by letter dated October 20, 2004, as supplemented by the letter May 11, 2006.F.Deleted per Amendment No. 169.Amendment 180 June 2006Callaway Plant, Unit 1 cc:Professional Nuclear Consulting, Inc.
19041 Raines Drive Derwood, MD 20855John O'Neill, Esq.Pillsbury Winthrop Shaw Pittman LLP 2300 N. Street, N.W.
Washington, D.C. 20037Mr. Keith A. Mills, Supervising EngineerRegional Regulatory Affairs/Safety Analysis AmerenUE P.O. Box 620 Fulton, MO 65251U.S. Nuclear Regulatory CommissionResident Inspector Office
8201 NRC Road Steedman, MO 65077-1302Mr. Les H. KanuckelManager, Quality Assurance AmerenUE P.O. Box 620 Fulton, MO 65251Missouri Public Service CommissionGovernor Office Building 200 Madison Street Jefferson City, MO 65102-0360Regional Administrator, Region IVU.S. Nuclear Regulatory Commission 611 Ryan Plaza Drive, Suite 400 Arlington, TX 76011-4005Mr. H. Floyd GilzowDeputy Director for Policy Missouri Department of Natural Resources P.O. Box 176 Jefferson City, MO 65102-0176Mr. Rick A. MuenchPresident and Chief Executive Officer Wolf Creek Nuclear Operating Corporation P.O. Box 411 Burlington, KA 66839Mr. Dan I. Bolef, PresidentKay Drey, Representative Board of Directors Coalition for the Environment 6267 Delmar Boulevard University City, MO 63130Mr. Lee Fritz, Presiding CommissionerCallaway County Court House 10 East Fifth Street Fulton, MO 65151Mr. David E. Shafer Superintendent, Licensing Regulatory Affairs AmerenUE P.O. Box 66149, MC 470 St. Louis, MO 63166-6149Manager, Regulatory AffairsAmerenUE P.O. Box 620 Fulton, MO 65251Mr. Keith G. Henke, PlannerDivision of Community and Public Health Office of Emergency Coordination 930 Wildwood P.O. Box 570 Jefferson City, MO 65102Certrec Corporation4200 South Hulen, Suite 630 Fort Worth, TX 76109Director, Missouri State Emergency Management Agency P.O. Box 116 Jefferson City, MO 65102-0116