| The U.S. Nuclear Regulatory Commission has approved the enclosed temporary exemption from specific requirements of Title 10 of the Code of Federal Regulations (10 CFR) Part 73, Appendix B, Section VI, Nuclear Power Reactor Training and Qualification Plan for Personnel Performing Security Program Duties, for the Beaver Valley Power Station, Unit Nos. 1 and 2. | | The U.S. Nuclear Regulatory Commission has approved the enclosed temporary exemption from specific requirements of Title 10 of the Code of Federal Regulations (10 CFR) Part 73, Appendix B, Section VI, Nuclear Power Reactor Training and Qualification Plan for Personnel Performing Security Program Duties, for the Beaver Valley Power Station, Unit Nos. 1 and 2. |
| This action is in response to your application dated April 23, 2020 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML20114E136), as supplemented by letter dated May 6, 2020 (ADAMS Accession No. ML20128J218), that requested a temporary exemption from the periodic requalification requirements for security personnel in paragraphs B.5.(a), C.3.(l)(1), D.1.(b)(3), D.2.(a), E.1.(c), E.1.(f), and F.5.(a) of 10 CFR 73, Appendix B, Section VI. | | This action is in response to your application dated April 23, 2020 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML20114E136), as supplemented by {{letter dated|date=May 6, 2020|text=letter dated May 6, 2020}} (ADAMS Accession No. ML20128J218), that requested a temporary exemption from the periodic requalification requirements for security personnel in paragraphs B.5.(a), C.3.(l)(1), D.1.(b)(3), D.2.(a), E.1.(c), E.1.(f), and F.5.(a) of 10 CFR 73, Appendix B, Section VI. |
| A copy of the exemption is enclosed. This exemption expires 90 days after the end of the Coronavirus Disease 2019 (COVID-19) public health emergency, or December 31, 2020, whichever occurs first. The exemption will be forwarded to the Office of the Federal Register for publication. | | A copy of the exemption is enclosed. This exemption expires 90 days after the end of the Coronavirus Disease 2019 (COVID-19) public health emergency, or December 31, 2020, whichever occurs first. The exemption will be forwarded to the Office of the Federal Register for publication. |
|
| |
|
Latest revision as of 22:27, 22 September 2022
Letter Sequence Other |
---|
EPID:L-2020-LLE-0033, Request for Approval of Decommissioning Quality Assurance Program, Revision 0 for the Davis-Besse Nuclear Power Station (Approved, Closed) |
|
MONTHYEARL-19-038, Request for Approval of Decommissioning Quality Assurance Program, Revision 0 for the Davis-Besse Nuclear Power Station2019-04-30030 April 2019 Request for Approval of Decommissioning Quality Assurance Program, Revision 0 for the Davis-Besse Nuclear Power Station Project stage: Request L-19-185, Withdrawal of Certification of Permanent Cessation of Power Operations for Davis-Besse Nuclear Station. Unit No. 1. and Perry Nuclear Power Plant, Unit No. 12019-07-26026 July 2019 Withdrawal of Certification of Permanent Cessation of Power Operations for Davis-Besse Nuclear Station. Unit No. 1. and Perry Nuclear Power Plant, Unit No. 1 Project stage: Request L-19-219, Supplement to Application for Order Consenting to Transfer of Licenses and Conforming License Amendments2019-09-25025 September 2019 Supplement to Application for Order Consenting to Transfer of Licenses and Conforming License Amendments Project stage: Supplement L-19-243, Supplement to Application for Order Consenting to Transfer of Licenses and Conforming License Amendments (EPID-L-2019-LLM-0000)2019-10-17017 October 2019 Supplement to Application for Order Consenting to Transfer of Licenses and Conforming License Amendments (EPID-L-2019-LLM-0000) Project stage: Supplement ML20114E1572020-04-23023 April 2020 Commission Memorandum and Order (CLI-20-05) Project stage: Request ML20119B0862020-05-19019 May 2020 Letter with Exemption Request from Certain Requirements of 10 CFR Part 73, Appendix B, General Criteria for Security Personnel (EPID L-2020-LLE-0033 (COVID-19)) Project stage: Other ML20119B0832020-05-19019 May 2020 Exemption from Certain Requirements of 10 CFR Part 73, Appendix B, General Criteria for Security Personnel (EPID L-2020-LLE-0033 (COVID-19)) Project stage: Approval ML20119B0842020-05-19019 May 2020 FRN - Beaver Valley Power Station, Units 1 and 2 - Request for Exemption from Certain Requirements of 10 CFR Part 73, Appendix B, General Criteria for Security Personnel (EPID L-2020-LLE-0033 (COVID-19)) Project stage: Approval 2019-07-26
[Table View] |
|
---|
Category:Exemption from NRC Requirements
MONTHYEARML24134A1522024-09-17017 September 2024 Exemption from the Requirements of 10 CFR 50.71(e)(4) Final Safety Analysis Report Update Schedule (EPID L-2024-LLE-0005) - Letter ML24134A1532024-09-17017 September 2024 Exemption from the Requirements of 10 CFR 50.71(e)(4) Final Safety Analysis Report Update Schedule (EPID L-2024-LLE-0005) - Exemption ML24102A2572024-04-25025 April 2024 Federal Register Notice - Issuance of Multiple Exemptions Regarding 10 CFR Part 73 - March 2024 ML24044A0662024-03-0404 March 2024 Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0083 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting L-23-264, Request for Exemption from 10 CFR 50.71(e)(4) Final Safety Analysis Report Update Schedule2024-02-23023 February 2024 Request for Exemption from 10 CFR 50.71(e)(4) Final Safety Analysis Report Update Schedule L-23-198, Independent Spent Fuel Storage Installation - Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation2023-12-0707 December 2023 Independent Spent Fuel Storage Installation - Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation ML20335A0902020-12-21021 December 2020 Federal Register Notice - November 2020 COVID-19 Exemptions ML20326A0002020-11-23023 November 2020 Exemption from Select Requirements of 10 CFR Part 26 (EPID L-2020-LLE-0211 (COVID-19)) ML20288A6402020-11-0606 November 2020 Temporary Exemption from Biennial Emergency Preparedness Exercise Frequency Requirements of 10 CFR Part 50, Appendix E, Section IV L-20-279, Request for a One-Time Exemption from 10 CFR 73, Appendix B, Section VI, Subsection C.3.(1)(1) Regarding Annual Force-on-Force (FOF) Exercises, Due to Covid 19 Pandemic2020-10-28028 October 2020 Request for a One-Time Exemption from 10 CFR 73, Appendix B, Section VI, Subsection C.3.(1)(1) Regarding Annual Force-on-Force (FOF) Exercises, Due to Covid 19 Pandemic ML20283A7722020-10-0909 October 2020 Submittal of Pennsylvania Letter Requesting Exemption from Biennial Exercise Requirements for Pennsylvania Nuclear Power Plants in Calendar Year 2020 ML20275A2032020-09-30030 September 2020 Acceptance of Requested Licensing Action, One-Time Acceptance for Review: Beaver Valley of Exemption from 10 CFR 50, Appendix E, Biennial Emergency Preparedness Exercise Requirements Due to COVID-19 Pandemic ML20119B0862020-05-19019 May 2020 Letter with Exemption Request from Certain Requirements of 10 CFR Part 73, Appendix B, General Criteria for Security Personnel (EPID L-2020-LLE-0033 (COVID-19)) ML20119B0832020-05-19019 May 2020 Exemption from Certain Requirements of 10 CFR Part 73, Appendix B, General Criteria for Security Personnel (EPID L-2020-LLE-0033 (COVID-19)) ML20119B0842020-05-19019 May 2020 FRN - Beaver Valley Power Station, Units 1 and 2 - Request for Exemption from Certain Requirements of 10 CFR Part 73, Appendix B, General Criteria for Security Personnel (EPID L-2020-LLE-0033 (COVID-19)) ML20119A5242020-05-0707 May 2020 FRN: Notice of Issuance of Multiple Exemptions Regarding 10 CFR Part 26 (COVID-19) ML20109A0002020-04-20020 April 2020 Exemption from Select Requirements of 10 CFR Part 26 (EPID L-2020-LLE-0025)(COVID-19)) L-20-140, Work Hour Rule Exemption Request Due to Pandemic (L-20-140)2020-04-18018 April 2020 Work Hour Rule Exemption Request Due to Pandemic (L-20-140) ML20109A0102020-04-18018 April 2020 Verbal Part 26 Exemption - Delivered 4/18/20 at 7:00 P.M ML19126A1952019-06-0505 June 2019 Transmittal Letter: Beaver Valley Power Station, Unit 2 - Exemption from the Regulations in 10 CFR Part 50, Appendix H ML19067A0212019-06-0404 June 2019 FENOC Fleet - Exemption from the Requirements of 10 CFR 73.55(p)(1)(i) and (II) Related to the Suspension of Security Measures in an Emergency or During Severe Weather ML17313A5542018-03-0101 March 2018 FRN Exemption from the Requirements of 10 CFR 50.46 and Appendix K to 10 CFR Part 50 to Allow the Use of Optimized Zirlo Clad Fuel Rods (CAC Nos. MF9582 and MF9583; EPID L-2017-LLE-0011) ML17313A5502018-03-0101 March 2018 Exemption from the Requirements of 10 CFR 50.46 and Appendix K to 10 CFR Part 50 to Allow the Use of Optimized Zirlo Fuel Rod Cladding (CAC Nos. MF9582 and MF9583; EPID L-2017-LLE-0011) ML1002300042010-03-0101 March 2010 Part 73 Exemption Request ML0205001382002-02-19019 February 2002 Exemption from the Requirements of 10 CFR 50.60(a) and Appendix G 2024-09-17
[Table view] Category:Letter
MONTHYEARIR 05000334/20240112024-10-17017 October 2024 License Renewal Phase IV Inspection Report 05000334/2024011 L-24-015, Twenty-Ninth Refueling Outage Inservice Inspection Summary Report2024-09-17017 September 2024 Twenty-Ninth Refueling Outage Inservice Inspection Summary Report ML24134A1522024-09-17017 September 2024 Exemption from the Requirements of 10 CFR 50.71(e)(4) Final Safety Analysis Report Update Schedule (EPID L-2024-LLE-0005) - Letter L-24-038, License Amendment Request to Remove the Expired One-Time Action for Valve Leak Repair in Technical Specification (TS) 3.5.2 and to Correct Core Operating Limits Rep Ort (COLR) References2024-09-17017 September 2024 License Amendment Request to Remove the Expired One-Time Action for Valve Leak Repair in Technical Specification (TS) 3.5.2 and to Correct Core Operating Limits Rep Ort (COLR) References ML24260A1912024-09-16016 September 2024 Operator Licensing Examination Approval IR 05000334/20240052024-08-29029 August 2024 Updated Inspection Plan for Beaver Valley Power Station, Units 1 and 2 (Reports 05000334/2024005 and 05000412/2024005) L-24-188, Submittal of Quality Assurance Program Manual, Revision 302024-08-27027 August 2024 Submittal of Quality Assurance Program Manual, Revision 30 IR 05000334/20244022024-08-22022 August 2024 Security Baseline Inspection Report 05000334/2024402 and 05000412/2024402 (Cover Letter Only) L-24-199, Discharge Monitoring Report (NPDES) Permit No. PA00256152024-08-22022 August 2024 Discharge Monitoring Report (NPDES) Permit No. PA0025615 IR 05000334/20240102024-08-20020 August 2024 Comprehensive Engineering Team Inspection - Inspection Report 05000334/2024010 and 05000412/2024010 L-24-186, Response to RAI for Exemption Request from 10 CFR 50.71(e)(4) Final Safety Analysis Update Schedule2024-08-15015 August 2024 Response to RAI for Exemption Request from 10 CFR 50.71(e)(4) Final Safety Analysis Update Schedule IR 05000334/20240022024-08-0505 August 2024 Integrated Inspection Report 05000334/2024002 and 05000412/2024002 ML24208A0462024-07-26026 July 2024 NRC Office of Investigations Case No. 1-2023-005 L-24-182, Discharge Monitoring Report (NPDES) Permit No. PA00256152024-07-23023 July 2024 Discharge Monitoring Report (NPDES) Permit No. PA0025615 L-24-161, Discharge Monitoring Report (NPDES) Permit No. PA00256152024-07-19019 July 2024 Discharge Monitoring Report (NPDES) Permit No. PA0025615 L-24-158, Reactor Trip Due to Bypass Feedwater Regulating Valve Failure to Control2024-07-17017 July 2024 Reactor Trip Due to Bypass Feedwater Regulating Valve Failure to Control L-24-014, Annual 10 CFR 50.46 Report of Changes to or Errors in Emergency Core Cooling Svstem Evaluation Models2024-07-16016 July 2024 Annual 10 CFR 50.46 Report of Changes to or Errors in Emergency Core Cooling Svstem Evaluation Models ML24193A2912024-07-16016 July 2024 Revision to Reactor Vessel Surveillance Capsule Withdrawal Schedule IR 05000334/20245012024-07-0808 July 2024 Emergency Preparedness Biennial Exercise Inspection Report 05000334/2024501 and 05000412/2024501 L-24-157, Unanalyzed Containment Bypass Condition Due to Degraded River Water Piping2024-07-0202 July 2024 Unanalyzed Containment Bypass Condition Due to Degraded River Water Piping L-24-164, BV-2, Post Accident Monitor Report2024-06-27027 June 2024 BV-2, Post Accident Monitor Report IR 05000334/20244012024-06-26026 June 2024 Material Control and Accounting Program Inspection Report 05000334/2024401 and 05000412/2024401 (Cover Letter Only) L-24-094, Reactor Vessel Surveillance Capsule Withdrawal Schedule2024-06-24024 June 2024 Reactor Vessel Surveillance Capsule Withdrawal Schedule L-24-152, Response to NRC Regulatory Issue Summary 2024-01 Preparation and Scheduling of Operator Licensing Examinations2024-06-17017 June 2024 Response to NRC Regulatory Issue Summary 2024-01 Preparation and Scheduling of Operator Licensing Examinations L-24-114, Automatic Reactor Trip Due to Low Reactor Coolant Flow Caused by Transformer Overexcitation Protection Relay Actuation2024-06-11011 June 2024 Automatic Reactor Trip Due to Low Reactor Coolant Flow Caused by Transformer Overexcitation Protection Relay Actuation L-24-115, Offsite AC Power Source Inoperable Due to Breaker Failure Resulting in Condition Prohibited by Technical Specification2024-06-0606 June 2024 Offsite AC Power Source Inoperable Due to Breaker Failure Resulting in Condition Prohibited by Technical Specification ML24135A2282024-05-29029 May 2024 Review of the Spring 2023 Outage Generic Letter 95-05 Voltage-Based Alternate Repair Criteria and Steam Generator F Star Reports ML24135A1702024-05-29029 May 2024 – Steam Generator Tube Inspection - Review of the Spring 2023 Tube Inspection Reports L-24-121, Discharge Monitoring Report (NPDES) Permit No. PA00256152024-05-23023 May 2024 Discharge Monitoring Report (NPDES) Permit No. PA0025615 L-24-021, Cycle 30 Core Operating Limits Report2024-05-23023 May 2024 Cycle 30 Core Operating Limits Report ML24141A1052024-05-20020 May 2024 Senior Reactor and Reactor Operator Initial License Examinations L-24-107, CFR 50.55a Request 1-TYP-5-RRP-l, for Alternative Method of Nondestructive Examination for River Water Outlet Piping Weld Repair2024-05-13013 May 2024 CFR 50.55a Request 1-TYP-5-RRP-l, for Alternative Method of Nondestructive Examination for River Water Outlet Piping Weld Repair IR 05000334/20240012024-05-0808 May 2024 Integrated Inspection Report 05000334/2024001 and 05000412/2024001 L-23-269, Application to Revise Technical Specifications to Adopt TSTF-569, Revision of Response Time Testing Definitions2024-05-0707 May 2024 Application to Revise Technical Specifications to Adopt TSTF-569, Revision of Response Time Testing Definitions L-24-054, Submittal of 2023 Annual Radioactive Effluent Release Report 2023 Annual Radiological Environmental Operating Report and 2023 Annual Environmental Operating Report (Non-Radiological)2024-04-29029 April 2024 Submittal of 2023 Annual Radioactive Effluent Release Report 2023 Annual Radiological Environmental Operating Report and 2023 Annual Environmental Operating Report (Non-Radiological) L-24-089, Emergency Preparedness Plan2024-04-23023 April 2024 Emergency Preparedness Plan L-24-088, Discharge Monitoring Report (NPDES) Permit No. PA0025615 for March 20242024-04-22022 April 2024 Discharge Monitoring Report (NPDES) Permit No. PA0025615 for March 2024 ML24101A2752024-04-10010 April 2024 Response to Request for Additional Information Regarding Spring 2023 180-Day Steam Generator Tube Inspection Report L-24-082, Withdrawal of Exemption Request2024-04-0303 April 2024 Withdrawal of Exemption Request L-24-013, Annual Notification of Property Insurance Coverage2024-03-26026 March 2024 Annual Notification of Property Insurance Coverage L-24-064, Submittal of Discharge Monitoring Report (NPDES) Permit No. PA00256152024-03-13013 March 2024 Submittal of Discharge Monitoring Report (NPDES) Permit No. PA0025615 ML24044A0662024-03-0404 March 2024 Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0083 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting ML24057A0752024-03-0101 March 2024 the Associated Independent Spent Fuel Storage Installations IR 05000334/20230062024-02-28028 February 2024 Annual Assessment Letter for Beaver Valley Power Station, Units 1 and 2 (Reports 05000334/2023006 and 05000412/2023006) CP-202300502, Notice of Planned Closing of Transaction and Provision of Documents to Satisfy Order Conditions2024-02-23023 February 2024 Notice of Planned Closing of Transaction and Provision of Documents to Satisfy Order Conditions L-23-264, Request for Exemption from 10 CFR 50.71(e)(4) Final Safety Analysis Report Update Schedule2024-02-23023 February 2024 Request for Exemption from 10 CFR 50.71(e)(4) Final Safety Analysis Report Update Schedule L-24-050, Retrospective Premium Guarantee2024-02-22022 February 2024 Retrospective Premium Guarantee IR 05000334/20230042024-02-12012 February 2024 Integrated Inspection Report 05000334/2023004 and 05000412/2023004 ML24025A0922024-01-25025 January 2024 Requalification Program Inspection L-23-267, Submittal of Discharge Monitoring Report (Npdes), Permit No. PA00256152023-12-18018 December 2023 Submittal of Discharge Monitoring Report (Npdes), Permit No. PA0025615 2024-09-17
[Table view] |
Text
May 19, 2020 Mr. Rod Penfield Site Vice President Energy Harbor Nuclear Corp.
Beaver Valley Power Station Mail Stop A-BV-SEB1 P.O. Box 4, Route 168 Shippingport, PA 15077
SUBJECT:
BEAVER VALLEY POWER STATION, UNIT NOS. 1 AND 2 - REQUEST FOR TEMPORARY EXEMPTION FROM CERTAIN REQUIREMENTS OF 10 CFR PART 73, APPENDIX B, GENERAL CRITERIA FOR SECURITY PERSONNEL (EPID L-2020-LLE-0033)
Dear Mr. Penfield:
The U.S. Nuclear Regulatory Commission has approved the enclosed temporary exemption from specific requirements of Title 10 of the Code of Federal Regulations (10 CFR) Part 73, Appendix B,Section VI, Nuclear Power Reactor Training and Qualification Plan for Personnel Performing Security Program Duties, for the Beaver Valley Power Station, Unit Nos. 1 and 2.
This action is in response to your application dated April 23, 2020 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML20114E136), as supplemented by letter dated May 6, 2020 (ADAMS Accession No. ML20128J218), that requested a temporary exemption from the periodic requalification requirements for security personnel in paragraphs B.5.(a), C.3.(l)(1), D.1.(b)(3), D.2.(a), E.1.(c), E.1.(f), and F.5.(a) of 10 CFR 73, Appendix B, Section VI.
A copy of the exemption is enclosed. This exemption expires 90 days after the end of the Coronavirus Disease 2019 (COVID-19) public health emergency, or December 31, 2020, whichever occurs first. The exemption will be forwarded to the Office of the Federal Register for publication.
R. Penfield If you have any questions, please contact me at 301-415-2328 or by e-mail to Jennifer.Tobin@nrc.gov.
Sincerely,
/RA/
Jennifer C. Tobin, Project Manager Plant Licensing Branch I Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-334 and 50-412
Enclosure:
Exemption cc: Listserv
ENCLOSURE EXEMPTION
Package: ML20119B081 Letter: ML20119B086; Exemption: ML20119B083; FRN: ML20119B084 OFFICE NRR/DORL/LPL1/PM NRR/DORL/LPL1/LA NSIR/DPC/RSB/BC NAME JTobin LRonewicz ABowers DATE 05/11/2020 05/11/2020 05/12/2020 OFFICE OGC - NLO w/edits NRR/DORL/LPL1/BC NRR/DORL/D NAME MWoods JDanna CErlanger DATE 05/15/2020 05/19/2020 05/19/2020