{{#Wiki_filter:QF-1030-11 Rev. 2 (FP-T-SAT-30)
{{#Wiki_filter:QF-1030-11 Rev. 2 (FP-T-SAT-30)
Retention: Life of policy + 10yrs. Disposition: Reviewer and Approver Retain in:  Training Program File M/jlg Page 1 of 9 JOB PERFORMANCE MEASURE (JPM)
JOB PERFORMANCE MEASURE (JPM)
SITE: MONTICELLO NUCLEAR GENERATING PLANT JPM TITLE:
SITE:                     MONTICELLO NUCLEAR GENERATING PLANT JPM TITLE:                 Bulk D/W Temperature Manual Calculation JPM NUMBER:               JPM-001                                     REV.         1 RELATED PRA               None INFORMATION:
Bulk D/W Temperature Manual Calculation JPM NUMBER:
TASK NUMBER(S) /           CR304.103 TASK TITLE(S):             Perform Actions Associated with Primary Containment Control K/A NUMBERS:           2.1.25                                   Rating: SRO/RO:       3.1/2.8 APPLICABLE METHOD OF TESTING:
JPM-001 REV. 1   RELATED PRA  
Discussion:               Simulate/walkthrough:               Perform:   X EVALUATION LOCATION:             In-Plant:                           Control Room:
 
Simulator:                 X       Other:
INFORMATION:
Lab:
None  TASK NUMBER(S) /  
Time for Completion:           15     Minutes                   Time Critical:       No Alternate Path / Faulted:       No TASK APPLICABILITY:             SRO:             SRO/RO:         X     SRO/RO/NLO:
 
TASK TITLE(S):
CR304.103 Perform Actions Associated with Primary Containment Control K/A NUMBERS:
2.1.25 Rating: SRO/RO:
3.1/2.8 APPLICABLE METHOD OF TESTING:
Discussion:   Simulate/walkthrough:   Perform: X EVALUATION LOCATION:
In-Plant:   Control Room:
Simulator: X Other:
Lab:       Time for Completion: 15 Minutes Time Critical: No     Alternate Path / Faulted: No TASK APPLICABILITY:
SRO: SRO/RO:X SRO/RO/NLO:
Additional signatures may be added as needed.
Additional signatures may be added as needed.
Developed by:
Developed by:                               J. Ruth Instructor                                 Date Validated by:
J. Ruth   Instructor Date   Validated by:
Validation Instructor                           Date (See JPM Validation Checklist, Attachment 1)
 
Approved by:
Validation Instructor (See JPM Validation Checklist, Attachment 1)
Training Supervisor                             Date Retention: Life of policy + 10yrs.                                           Disposition: Reviewer and Approver Retain in: Training Program File M/jlg Page 1 of 9
Date    Approved by:
 
Training Supervisor Date QF-1030-11  Rev. 2  (FP-T-SAT-30)
JPM-001, Bulk D/W Temperature Manual Calculation Rev. 1 M/jlg Page 2 of 9 JPM Number:
JPM-001  JPM Title:
Bulk D/W Temperature Manual Calculation  Examinee:  Evaluator: Job Title:  Date: Start Time  Finish Time PERFORMANCE RESULTS:
SAT: UNSAT:   
 
COMMENTS/FEEDBACK: (Comments shall be made for any steps graded unsatisfactory).  
 
EVALUATOR'S SIGNATURE:  
 
NOTE: Only this page needs to be retained in examinee's record if completed satisfactorily. If unsatisfactory performance is demonstrated, the entire JPM should be retained.
QF-1030-11  Rev. 2  (FP-T-SAT-30)
JPM-001, Bulk D/W Temperature Manual Calculation Rev. 1 M/jlg Page 3 of 9 JPM BRIEFING/TURNOVER (See MTCP-03.32, Figure 6.2)
I will explain the initial conditions, which step(s) to simulate or discuss, and provide initiating cues. When you


complete the task successfully, the objective for this job performance measure will be satisfied.  
QF-1030-11 Rev. 2 (FP-T-SAT-30)
JPM-001, Bulk D/W Temperature Manual Calculation Rev. 1 JPM Number: JPM-001 JPM Title: Bulk D/W Temperature Manual Calculation Examinee:                                            Evaluator:
Job Title:                                                Date:
Start Time                                          Finish Time PERFORMANCE RESULTS:                            SAT:                    UNSAT:
COMMENTS/FEEDBACK: (Comments shall be made for any steps graded unsatisfactory).
EVALUATORS SIGNATURE:
NOTE: Only this page needs to be retained in examinees record if completed satisfactorily. If unsatisfactory performance is demonstrated, the entire JPM should be retained.
M/jlg Page 2 of 9


QF-1030-11 Rev. 2 (FP-T-SAT-30)
JPM-001, Bulk D/W Temperature Manual Calculation Rev. 1 JPM BRIEFING/TURNOVER (See MTCP-03.32, Figure 6.2)
I will explain the initial conditions, which step(s) to simulate or discuss, and provide initiating cues. When you complete the task successfully, the objective for this job performance measure will be satisfied.
DURING THE JPM, ENSURE PROPER SAFETY PRECAUTIONS, FME, AND/OR RADIOLOGICAL CONCERNS AS APPLICABLE ARE FOLLOWED.
DURING THE JPM, ENSURE PROPER SAFETY PRECAUTIONS, FME, AND/OR RADIOLOGICAL CONCERNS AS APPLICABLE ARE FOLLOWED.
INITIAL CONDITIONS: A LOCA is in progress EOP-1200 has been entered SPDS is OOS You are an extra licensed operator in the control room INITIATING CUES (IF APPLICABLE):   The CRS directs you to manually calculate and report bulk average Drywell temperature. INFORM EVALUATOR WHEN YOU HAVE COMPLETED THE TASK.  
INITIAL CONDITIONS:
 
* A LOCA is in progress
QF-1030-11  Rev. 2  (FP-T-SAT-30)
* EOP-1200 has been entered
JPM-001, Bulk D/W Temperature Manual Calculation Rev. 1 M/jlg Page 4 of 9 JPM PERFORMANCE INFORMATION
* SPDS is OOS
* You are an extra licensed operator in the control room INITIATING CUES (IF APPLICABLE):
* The CRS directs you to manually calculate and report bulk average Drywell temperature.
* INFORM EVALUATOR WHEN YOU HAVE COMPLETED THE TASK.
M/jlg Page 3 of 9


Required Materials:
QF-1030-11 Rev. 2 (FP-T-SAT-30)
Simulator General  
JPM-001, Bulk D/W Temperature Manual Calculation Rev. 1 JPM PERFORMANCE INFORMATION Required Materials:       Simulator General  


==References:==
==References:==
Operator Aid for Bulk Drywell Temperature Manual Calculation Task Standards:            Determine Bulk Drywell Temperature via manual calculation Start Time:
NOTE: When providing Evaluator Cues to the examinee, care must be exercised to avoid prompting the examinee. Typically cues are only provided when the examinees actions warrant receiving the information (i.e. the examinee looks or asks for the indication).
NOTE: Critical steps are marked with a Y below the performance step number. Failure to meet the standard for any critical step SHALL result in failure of this JPM.
Performance Step: 1            Locates Operator Aid for Bulk Drywell Temperature Manual Calculation Critical: N Standard:                      Locates Operator Aid Evaluator Cue:                  None Performance:                  SATISFACTORY              UNSATISFACTORY Comments:
Performance Step: 2            From TR23-115 determines Drywell temperature from the following points:
Critical: Y
* East 932 Point 22
* South 951 Point 23
* West 970 Point 21
* North 994 Point 24 Standard:                      Determines the following temperatures:
* East 932 Point 22 = 259.2°F
* South 951 Point 23 = 267.2°F
* West 970 Point 21 = 259.8°F
* North 994 Point 24 = 275.5°F Evaluator Cue:                  After operator identifies the trend recorder and applicable points, provide the sheet with a printout of the above points and their readings.
Performance:                  SATISFACTORY              UNSATISFACTORY Comments:
M/jlg Page 4 of 9


Operator Aid for Bulk Drywell Temperature Manual Calculation Task Standards:
QF-1030-11 Rev. 2 (FP-T-SAT-30)
Determine Bulk Drywell Temperature via manual calculation Start Time:
JPM-001, Bulk D/W Temperature Manual Calculation Rev. 1 Performance Step: 3        Apply Weight Factor to the temperatures from previous step to determine Weight Critical: Y               Temperatures.
NOTE:  When providing "Evaluator Cues" to the examinee, care must be exercised to avoid prompting the examinee. Typically cues are only provided when the examinee's actions warrant receiving the information (i.e. the examinee looks or asks for the indication).
* East 932 Point 22 X .400
NOTE: Critical steps are marked with a "Y" below the performance step number. Failure to meet the standard for any critical step SHALL result in failure of this JPM.
* South 951 Point 23 X .423
Performance Step:  1 Critical:  N Locates Operator Aid for Bulk Drywell Temperature Manual Calculation Standard:
* West 970 Point 21 X .093
Locates Operator Aid Evaluator Cue:
* North 994 Point 24 X .084 Standard:                 Apply Weight Factor to the temperatures as follows:
None  Performance: SATISFACTORY  UNSATISFACTORY Comments:
* East 932 Point 22 X .400 = (259.2 x .4 = 103.68)
Performance Step: 2 Critical: Y From TR23-115 determines Drywell temperature from the following points:  East 932' Point 22 South 951' Point 23 West 970' Point 21 North 994' Point 24 Standard:
* South 951 Point 23 X .423 = (267.2 x .423 = 113.03)
Determines the following temperatures: East 932' Point 22 = 259.2 South 951' Point 23 = 267.2 West 970' Point 21 = 259.8 North 994' Point 24 = 275.5 Evaluator Cue:
* West 970 Point 21 X .093 = (259.8 x .093 = 24.16)
After operator identifies the trend recorder and applicable points, provide the sheet with a printout of the above points and their readings.
* North 994 Point 24 X .084 = (275.5 x .084 = 23.14)
Performance: SATISFACTORY   UNSATISFACTORY Comments:  
Evaluator Cue:            None Performance:              SATISFACTORY          UNSATISFACTORY Comments:
Performance Step: 4        Add Weight Temperatures to determine Bulk Average Drywell Temperature Total.
Critical: Y Standard:                  Adds Weight Temperatures to obtain a calculated temperature of 264.01°F + or
                          - 2°F Evaluator Cue:            None Performance:              SATISFACTORY          UNSATISFACTORY Comments:
Performance Step: 5        Reports bulk average Drywell temperature calculated above to CRS.
Critical: N Standard:                  Reports bulk average Drywell temperature calculated above to CRS.
Evaluator Cue:            Acknowledge report.
Performance:               SATISFACTORY         UNSATISFACTORY Comments:
M/jlg Page 5 of 9


QF-1030-11 Rev. 2 (FP-T-SAT-30)
QF-1030-11 Rev. 2 (FP-T-SAT-30)
JPM-001, Bulk D/W Temperature Manual Calculation Rev. 1 M/jlg Page 5 of 9 Performance Step: 3 Critical: Y Apply Weight Factor to the temperatures from previous step to determine Weight Temperatures. East 932' Point 22 X .400  South 951' Point 23 X .423  West 970' Point 21 X .093  North 994' Point 24 X .084 Standard:
JPM-001, Bulk D/W Temperature Manual Calculation Rev. 1 Performance Step: 6        INFORM EVALUATOR THAT THE TASK HAS BEEN COMPLETED.
Apply Weight Factor to the temperatures as follows:  East 932' Point 22 X .400 = (259.2 x .4 = 103.68)  South 951' Point 23 X .423 = (267.2 x .423 = 113.03)  West 970' Point 21 X .093 = (259.8 x .093 = 24.16)  North 994' Point 24 X .084 = (275.5 x .084 = 23.14)
Critical: N Standard:                   Operator informs evaluator that the task is completed.
Evaluator Cue:
Evaluator Cue:             When informed of calculated average drywell bulk temperature, acknowledge the report and state that the JPM is complete.
None  Performance: SATISFACTORY   UNSATISFACTORY Comments:
Performance:               SATISFACTORY           UNSATISFACTORY Comments:
Performance Step: 4 Critical:  Y Add Weight Temperatures to determine Bulk Average Drywell Temperature Total.
Terminating Cues:     When informed of calculated average drywell bulk temperature, acknowledge the report and state that the JPM is complete.
Standard:
Stop Time:
Adds Weight Temperatures to obtain a calculated temperature of  264.01 F + or - 2 F    Evaluator Cue:
M/jlg Page 6 of 9
None  Performance: SATISFACTORY  UNSATISFACTORY Comments:
Performance Step:  5 Critical:  N Reports bulk average Drywell temperature calculated above to CRS.


Standard:
QF-1030-11 Rev. 2 (FP-T-SAT-30)
Reports bulk average Drywell temperature calculated above to CRS.
TURNOVER SHEET INITIAL CONDITIONS:
Evaluator Cue:
* A LOCA is in progress
Acknowledge report.
* EOP-1200 has been entered
Performance: SATISFACTORY  UNSATISFACTORY Comments:
* SPDS is OOS
* You are an extra licensed operator in the control room INITIATING CUES (IF APPLICABLE):
* The CRS directs manually calculate and report bulk average Drywell temperature.
* INFORM EVALUATOR WHEN YOU HAVE COMPLETED THE TASK.
M/jlg Page 7 of 9


QF-1030-11 Rev. 2 (FP-T-SAT-30)
QF-1030-11 Rev. 2 (FP-T-SAT-30)
JPM-001, Bulk D/W Temperature Manual Calculation Rev. 1 M/jlg Page 6 of 9 Performance Step:  6 Critical: N INFORM EVALUATOR THAT THE TASK HAS BEEN COMPLETED.
JPM-001, Bulk D/W Temperature Manual Calculation Rev. 1 SIMULATOR SET UP:
Standard:
Operator informs evaluator that the task is completed.
Evaluator Cue:
When informed of calculated average drywell bulk temperature, acknowledge the report and state that the JPM is complete.
Performance: SATISFACTORY  UNSATISFACTORY Comments: 
 
Terminating Cues:
 
When informed of calculated average drywell bulk temperature, acknowledge the report and state that the JPM is complete.
Stop Time: 
 
QF-1030-11  Rev. 2  (FP-T-SAT-30)
M/jlg Page 7 of 9 TURNOVER SHEET INITIAL CONDITIONS:  A LOCA is in progress  EOP-1200 has been entered  SPDS is OOS  You are an extra licensed operator in the control room INITIATING CUES (IF APPLICABLE):  The CRS directs manually calculate and r eport bulk average Drywell temperature. INFORM EVALUATOR WHEN YOU HAVE COMPLETED THE TASK.
 
QF-1030-11  Rev. 2  (FP-T-SAT-30)
JPM-001, Bulk D/W Temperature Manual Calculation Rev. 1 M/jlg Page 8 of 9 SIMULATOR SET UP:
INITIAL CONDITIONS:
INITIAL CONDITIONS:
Any simulator condition is acceptable as the only requirement for the simulator is access to the calculation instructions on the trend recorder.
Any simulator condition is acceptable as the only requirement for the simulator is access to the calculation instructions on the trend recorder.
SET UP INSTRUCTIONS: None
SET UP INSTRUCTIONS:
* None M/jlg Page 8 of 9


QF-1030-11 Rev. 2 (FP-T-SAT-30)
QF-1030-11 Rev. 2 (FP-T-SAT-30)
JPM-001, Bulk D/W Temperature Manual Calculation Rev. 1 M/jlg Page 9 of 9 ATTACHMENT 1 JOB PERFORMANCE MEASURE VALIDATION CHECKLIST ALL STEPS IN THIS CHECKLIST ARE TO BE PERFORMED UPON INITIAL VALIDATION AND PRIOR TO USE.
JPM-001, Bulk D/W Temperature Manual Calculation Rev. 1 ATTACHMENT 1 JOB PERFORMANCE MEASURE VALIDATION CHECKLIST ALL STEPS IN THIS CHECKLIST ARE TO BE PERFORMED UPON INITIAL VALIDATION AND PRIOR TO USE.
REVIEW STATEMENTS YES NO N/A 1. Are all items on the signature page filled in correctly?
REVIEW STATEMENTS                                                           YES       NO       N/A
: 1. Are all items on the signature page filled in correctly?
: 2. Has the JPM been reviewed and validated by SMEs?
: 2. Has the JPM been reviewed and validated by SMEs?
: 3. Can the required conditions for the JPM be appropriately established in the simulator if required?
: 3. Can the required conditions for the JPM be appropriately established in the simulator if required?
: 4. Does the performance steps accurately reflect trainee's actions in accordance with plant procedures?
: 4. Does the performance steps accurately reflect trainees actions in accordance with plant procedures?
: 5. Is the standard for each performance item specific as to what controls, indications and ranges are required to evaluate if the  
: 5. Is the standard for each performance item specific as to what controls, indications and ranges are required to evaluate if the trainee properly performed the step?
 
trainee properly performed the step?
: 6. Has the completion time been established based on validation data or incumbent experience?
: 6. Has the completion time been established based on validation data or incumbent experience?
: 7. If the task is time critical, is the time critical portion based upon actual task performance requirements?
: 7. If the task is time critical, is the time critical portion based upon actual task performance requirements?
Line 136: Line 134:
Sequence / Time Critical) appropriately?
Sequence / Time Critical) appropriately?
: 11. Have all special tools and equipment needed to perform the task been identified and made available to the trainee?
: 11. Have all special tools and equipment needed to perform the task been identified and made available to the trainee?
: 12. Are all references identified, current, accurate, and available to the trainee?   13. Have all required cues (as anticipated) been identified for the evaluator to assist task completion?
: 12. Are all references identified, current, accurate, and available to the trainee?
All questions/statements must be answered "YES" or the JPM is not valid for use. If all questions/statements  
: 13. Have all required cues (as anticipated) been identified for the evaluator to assist task completion?
 
All questions/statements must be answered YES or the JPM is not valid for use. If all questions/statements are answered YES then the JPM is considered valid and can be performed as written. The individual(s) performing the validation shall sign and date this form.
are answered "YES" then the JPM is considered valid and can be performed as written. The individual(s)  
__________________________                  __________________________
Validation Personnel /Date                  Validation Personnel/Date
__________________________                  __________________________
Validation Personnel /Date                  Validation Personnel/Date
__________________________                  __________________________
Validation Personnel /Date                  Validation Personnel/Date
__________________________                  __________________________
Validation Personnel /Date                  Validation Personnel/Date Historical Record: (Optional)
M/jlg Page 9 of 9


performing the validation shall sign and date this form.
QF-1030-11 Rev. 2 (FP-T-SAT-30)
__________________________        __________________________
JOB PERFORMANCE MEASURE (JPM)
 
SITE:                     MONTICELLO NUCLEAR GENERATING PLANT JPM TITLE:                 CONTROL ROOM SHIFT TURNOVER CHECKLIST JPM NUMBER:               JPM-3139-001                               REV.         0 RELATED PRA               None INFORMATION:
Validation Personnel /Date                  Validation Personnel/Date
TASK NUMBER(S) /           CR298.103 TASK TITLE(S):             Perform the Control Room Shift Turnover Checklist K/A NUMBERS:           2.1.3                                     Rating: SRO/RO:       3.4 /3.0 APPLICABLE METHOD OF TESTING:
__________________________        __________________________
Discussion:               Simulate/walkthrough:               Perform:   x EVALUATION LOCATION:             In-Plant:                           Control Room:
 
Simulator:                 x       Other:
Validation Personnel /Date                  Validation Personnel/Date
Lab:
__________________________        __________________________
Time for Completion:           20     Minutes                   Time Critical:       No Alternate Path / Faulted:       Yes TASK APPLICABILITY:             SRO:             SRO/RO:         X     SRO/RO/NLO:
 
Validation Personnel /Date                  Validation Personnel/Date
__________________________        __________________________
 
Validation Personnel /Date                  Validation Personnel/Date Historical Record:  (Optional)
 
QF-1030-11 Rev. 2 (FP-T-SAT-30)
Retention: Life of policy + 10yrs. Disposition: Reviewer and Approver Retain in:  Training Program File M/jlg Page 1 of 13 JOB PERFORMANCE MEASURE (JPM)
SITE: MONTICELLO NUCLEAR GENERATING PLANT JPM TITLE:
CONTROL ROOM SHIFT TURNOVER CHECKLIST JPM NUMBER:
JPM-3139-001 REV. 0   RELATED PRA  
 
INFORMATION:
None  TASK NUMBER(S) /  
 
TASK TITLE(S):
CR298.103 Perform the Control Room Shift Turnover Checklist K/A NUMBERS:
 
====2.1.3 Rating====
SRO/RO:
3.4 /3.0 APPLICABLE METHOD OF TESTING:
Discussion:   Simulate/walkthrough:   Perform: x EVALUATION LOCATION:
In-Plant:   Control Room:
Simulator: x Other:
Lab:       Time for Completion: 20 Minutes Time Critical: No     Alternate Path / Faulted: Yes TASK APPLICABILITY:
SRO: SRO/RO:X SRO/RO/NLO:
Additional signatures may be added as needed.
Additional signatures may be added as needed.
Developed by:
Developed by:                               J Ruth Instructor                                 Date Validated by:
J Ruth   Instructor Date   Validated by:
Validation Instructor                            Date (See JPM Validation Checklist, Attachment 1)
Approved by:
Training Supervisor                              Date Retention: Life of policy + 10yrs.                                            Disposition: Reviewer and Approver Retain in: Training Program File M/jlg Page 1 of 13


Validation Instructor (See JPM Validation Checklist, Attachment 1)
QF-1030-11 Rev. 2 (FP-T-SAT-30)
Date    Approved by:
JPM-3139-001 (CONTROL ROOM SHIFT TURNOVER CHECKLIST) Rev.0 JPM Number: JPM-3139-001 JPM Title: Control Room Shift Turnover Checklist Examinee:                                             Evaluator:
 
Job Title:                                               Date:
Training Supervisor Date QF-1030-11 Rev. 2 (FP-T-SAT-30)
Start Time                                         Finish Time PERFORMANCE RESULTS:                           SAT:                   UNSAT:
JPM-3139-001 (CONTROL ROOM SHIFT T URNOVER CHECKLIST) Rev.0 M/jlg Page 2 of 13 JPM Number:
COMMENTS/FEEDBACK: (Comments shall be made for any steps graded unsatisfactory).
JPM-3139-001 JPM Title: Control Room Shift Turnover Checklist Examinee: Evaluator: Job Title: Date: Start Time Finish Time PERFORMANCE RESULTS:
EVALUATORS SIGNATURE:
SAT: UNSAT:  
NOTE: Only this page needs to be retained in examinees record if completed satisfactorily. If unsatisfactory performance is demonstrated, the entire JPM should be retained.
 
M/jlg Page 2 of 13
COMMENTS/FEEDBACK: (Comments shall be made for any steps graded unsatisfactory).  
 
EVALUATOR'S SIGNATURE:  
 
NOTE: Only this page needs to be retained in examinee's record if completed satisfactorily. If unsatisfactory performance is demonstrated, the entire JPM should be retained.
QF-1030-11  Rev. 2  (FP-T-SAT-30)
JPM-3139-001 (CONTROL ROOM SHIFT T URNOVER CHECKLIST) Rev.0 M/jlg Page 3 of 13 JPM BRIEFING/TURNOVER (See MTCP-03.32, Figure 6.2)
I will explain the initial conditions, which step(s) to simulate or discuss, and provide initiating cues. When you
 
complete the task successfully, the objective for this job performance measure will be satisfied.


QF-1030-11 Rev. 2 (FP-T-SAT-30)
JPM-3139-001 (CONTROL ROOM SHIFT TURNOVER CHECKLIST) Rev.0 JPM BRIEFING/TURNOVER (See MTCP-03.32, Figure 6.2)
I will explain the initial conditions, which step(s) to simulate or discuss, and provide initiating cues. When you complete the task successfully, the objective for this job performance measure will be satisfied.
DURING THE JPM, ENSURE PROPER SAFETY PRECAUTIONS, FME, AND/OR RADIOLOGICAL CONCERNS AS APPLICABLE ARE FOLLOWED.
DURING THE JPM, ENSURE PROPER SAFETY PRECAUTIONS, FME, AND/OR RADIOLOGICAL CONCERNS AS APPLICABLE ARE FOLLOWED.
INITIAL CONDITIONS: The reactor is operating at power You are the LPEO on the 19-07 shift The Shift Manager is "Smith" INITIATING CUES (IF APPLICABLE):   Perform the front page of 3139, Control Room Shift Turnover Checklist  
INITIAL CONDITIONS:
* The reactor is operating at power
* You are the LPEO on the 19-07 shift
* The Shift Manager is Smith INITIATING CUES (IF APPLICABLE):
* Perform the front page of 3139, Control Room Shift Turnover Checklist M/jlg Page 3 of 13


QF-1030-11 Rev. 2 (FP-T-SAT-30)
QF-1030-11 Rev. 2 (FP-T-SAT-30)
JPM-3139-001 (CONTROL ROOM SHIFT T URNOVER CHECKLIST) Rev.0 M/jlg Page 4 of 13 JPM PERFORMANCE INFORMATION  
JPM-3139-001 (CONTROL ROOM SHIFT TURNOVER CHECKLIST) Rev.0 JPM PERFORMANCE INFORMATION Required Materials:       Checklist 3139 General  
 
Required Materials:
Checklist 3139 General  


==References:==
==References:==
OWI-02.01, Operations Shift Turnover Task Standards:            Complete front page of Control Room Shift Turnover Checklist Start Time:
NOTE: When providing Evaluator Cues to the examinee, care must be exercised to avoid prompting the examinee. Typically cues are only provided when the examinees actions warrant receiving the information (i.e. the examinee looks or asks for the indication).
NOTE: Critical steps are marked with a Y below the performance step number. Failure to meet the standard for any critical step shall result in failure of this JPM.
Performance Step: 1            Complete the shift complement section of the checklist.
Critical: N Standard:                      Fills in Shift Manager, Date, Shift.
Evaluator Cue:                  None Performance:                  SATISFACTORY            UNSATISFACTORY Comments:
Performance Step: 2            Record Mode Switch position Critical: N Standard:                      Checks Run box Evaluator Cue:                  None Performance:                  SATISFACTORY            UNSATISFACTORY Comments:
M/jlg Page 4 of 13


OWI-02.01, Operations Shift Turnover Task Standards:
QF-1030-11 Rev. 2 (FP-T-SAT-30)
Complete front page of Control Room Shift Turnover Checklist Start Time:
JPM-3139-001 (CONTROL ROOM SHIFT TURNOVER CHECKLIST) Rev.0 Performance Step: 3       Record Core thermal Power Critical: N Standard:                 Records 1765 - 1775 MWT Evaluator Cue:             None Performance:               SATISFACTORY         UNSATISFACTORY Comments:
NOTE:  When providing "Evaluator Cues" to the examinee, care must be exercised to avoid prompting the examinee. Typically cues are only provided when the examinee's actions warrant receiving the information (i.e. the examinee looks or asks for the indication).
Performance Step: 4       Record Core Flow Critical: N Standard:                 Records 51 x 106 Lb/Hr +/- 0.5 Evaluator Cue:             None Performance:               SATISFACTORY         UNSATISFACTORY Comments:
NOTE: Critical steps are marked with a "Y" below the performance step number. Failure to meet the standard for any critical step shall result in failure of this JPM.
Performance Step: 5       Record Core/Rx dP Critical: N Standard:                 Records 14.2 / 22 Psid +/- 0.5 Evaluator Cue:             None Performance:               SATISFACTORY         UNSATISFACTORY Comments:
Performance Step:  1 Critical:  N Complete the shift complement section of the checklist.
Performance Step: 6       Record Rx Pressure Critical: N Standard:                 Records 1000 Psig +/- 5 Evaluator Cue:             None Performance:               SATISFACTORY         UNSATISFACTORY Comments:
Standard:
M/jlg Page 5 of 13
Fills in Shift Manager, Date, Shift.
Evaluator Cue:
None  Performance: SATISFACTORY UNSATISFACTORY Comments:
Performance Step:  2 Critical:  N Record Mode Switch position Standard: Checks Run box Evaluator Cue:
None  Performance: SATISFACTORY UNSATISFACTORY Comments:
 
QF-1030-11 Rev. 2 (FP-T-SAT-30)
JPM-3139-001 (CONTROL ROOM SHIFT T URNOVER CHECKLIST) Rev.0 M/jlg Page 5 of 13 Performance Step: 3 Critical:  N Record Core thermal Power Standard:
Records 1765 - 1775 MWT Evaluator Cue:
None   Performance: SATISFACTORY UNSATISFACTORY Comments:
Performance Step: 4 Critical: N Record Core Flow Standard:
Records 51 x 10 6 Lb/Hr 0.5   Evaluator Cue:
None   Performance: SATISFACTORY UNSATISFACTORY Comments:
Performance Step: 5 Critical:  N Record Core/Rx dP Standard:
Records 14.2 / 22 Psid 0.5   Evaluator Cue:
None   Performance: SATISFACTORY UNSATISFACTORY Comments:
Performance Step: 6 Critical:  N Record Rx Pressure Standard:
Records 1000 Psig  5    Evaluator Cue:
None  Performance: SATISFACTORY UNSATISFACTORY Comments:
 
QF-1030-11  Rev. 2  (FP-T-SAT-30)
JPM-3139-001 (CONTROL ROOM SHIFT T URNOVER CHECKLIST) Rev.0 M/jlg Page 6 of 13 Performance Step:  7 Critical: N Record Rx Level Standard:
Records 35 inches  1  Evaluator Cue:
None  Performance: SATISFACTORY UNSATISFACTORY Comments:
Performance Step:  8 Critical:  N Record Torus Level Standard:
Records 0 inches
  .5  Evaluator Cue:
None  Performance: SATISFACTORY UNSATISFACTORY Comments:
Performance Step:  9 Critical:  N Record RCP dP Standard:
Records 117 / 116 psid  2  Evaluator Cue:
None  Performance: SATISFACTORY UNSATISFACTORY Comments:
Performance Step:  10 Critical:  N Record Steam Flow Standard:
Records 7.25 x 10 6 Lb/Hr  .25  Evaluator Cue:
None  Performance: SATISFACTORY UNSATISFACTORY Comments:
 
QF-1030-11  Rev. 2  (FP-T-SAT-30)
JPM-3139-001 (CONTROL ROOM SHIFT T URNOVER CHECKLIST) Rev.0 M/jlg Page 7 of 13 Performance Step:  11 Critical:  N Record FW Flow Standard:
Records 7.25 x 10 6 Lb/Hr  .25  Evaluator Cue:
None  Performance: SATISFACTORY UNSATISFACTORY Comments:
Performance Step:  12 Critical:  N Records status of Nuclear Instruments Standard:
Records APRMs 2 and 5 bypassed with none above normal Evaluator Cue:
None  Performance: SATISFACTORY UNSATISFACTORY Comments:
Performance Step:  13 Critical:  N Records status of Rad Monitors Standard:
Records none are bypassed and none above normal Evaluator Cue:
None  Performance: SATISFACTORY UNSATISFACTORY Comments:
Performance Step:  14 Critical:  N Record Rx Level Mode / Controllers Standard:
Records 3 element, MSTR-AUTO, and Lo Flow Reg Va is in MAN.
Evaluator Cue:
None   Performance: SATISFACTORY UNSATISFACTORY Comments:  
 
QF-1030-11  Rev. 2  (FP-T-SAT-30)
JPM-3139-001 (CONTROL ROOM SHIFT T URNOVER CHECKLIST) Rev.0 M/jlg Page 8 of 13 Performance Step:  15 Critical:  N Record RFP Level Trip Standard:
Records position of RFP Level Trip in NORMAL Evaluator Cue:
None  Performance: SATISFACTORY UNSATISFACTORY Comments:
Performance Step:  16 Critical:  N Record Press Contr Standard:
Records MPR # 910  5 and EPR# 903  1  Evaluator Cue:
None  Performance: SATISFACTORY UNSATISFACTORY Comments:
Performance Step:  17 Critical:  N Record Switch position and Alarms for 11 & 12 D Gen Standard:
Records AUTO for switch positions and None for alarms Evaluator Cue:
None  Performance: SATISFACTORY UNSATISFACTORY Comments:
Performance Step:  18 Critical:  N Record ADS "A", "C", "D" switch positions and alarms Standard:
Records ADS switch positions in AUTO and None for alarms Evaluator Cue:
None  Performance: SATISFACTORY UNSATISFACTORY Comments:
 
QF-1030-11  Rev. 2  (FP-T-SAT-30)
JPM-3139-001 (CONTROL ROOM SHIFT T URNOVER CHECKLIST) Rev.0 M/jlg Page 9 of 13 Performance Step:  19 Critical:  N Record SRV Low-Low Set  C-03 "E", "G", "H" switch positions and alarms Standard:
Records Low-Low Set switch positions in AUTO and None for alarms Evaluator Cue:
None  Performance: SATISFACTORY UNSATISFACTORY Comments:
Performance Step:  20 Critical:  N Record DIV II Low-Low Set Logic switch position and alarms Standard:
Records switch in Auto and None for alarms Evaluator Cue:
None  Performance: SATISFACTORY UNSATISFACTORY Comments:
Performance Step:  21 Critical:  Y Record "A" RHR switch position, alarms, and valve line-up Standard:
Records switch position in Auto, None for alarms, and notes MO-2002 (RHR DIV 1 HX BYPASS) valve is in the CLOSED position. Reports to CRS and takes keylock
 
switch to OPEN when directed by CRS.
Evaluator Cue: Acknowledge report of MO-2002 (RHR DIV 1 HX BYPASS) valve is in the CLOSED position. Directs valve be opened.
Performance: SATISFACTORY UNSATISFACTORY Comments:
Performance Step:  22 Critical:  N Record "A" RHRSW switch position, alarms, and valve line-up Standard:
Records switch position in Auto, None for alarms, and valve line-up sat Evaluator Cue:
None  Performance: SATISFACTORY UNSATISFACTORY Comments:
 
QF-1030-11  Rev. 2  (FP-T-SAT-30)
JPM-3139-001 (CONTROL ROOM SHIFT T URNOVER CHECKLIST) Rev.0 M/jlg Page 10 of 13 Performance Step:  23 Critical:  N Record "A" Core Spray switch position, alarms, and valve line-up Standard:
Records switch position in Auto, None for alarms, and valve line-up sat Evaluator Cue:
None  Performance: SATISFACTORY UNSATISFACTORY Comments:
Performance Step:  24 Critical:  Y Record HPCI switch position, alarms, and valve line-up. Notes and reports to the CRS that the HPCI Flow Controller is in MANUAL control.
Standard:
Recognizes that the HPCI Flow Controller is in MANUAL control and reports to the CRS the discrepancy. Selects AUTO control when directed.
Evaluator Cue:
Acknowledge the report and direct that the HPCI Flow Controller be placed in AUTO. Performance: SATISFACTORY UNSATISFACTORY Comments:
 
Terminating Cues:


When the HPCI check has been completed, state that the JPM is completed Stop Time:
QF-1030-11 Rev. 2 (FP-T-SAT-30)
Critical Time
JPM-3139-001 (CONTROL ROOM SHIFT TURNOVER CHECKLIST) Rev.0 Performance Step: 7        Record Rx Level Critical: N Standard:                  Records 35 inches +/- 1 Evaluator Cue:            None Performance:              SATISFACTORY          UNSATISFACTORY Comments:
___N/A____
Performance Step: 8        Record Torus Level Critical: N Standard:                  Records 0 inches +/- .5 Evaluator Cue:            None Performance:              SATISFACTORY          UNSATISFACTORY Comments:
QF-1030-11 Rev. 2 (FP-T-SAT-30)
Performance Step: 9        Record RCP dP Critical: N Standard:                  Records 117 / 116 psid +/- 2 Evaluator Cue:            None Performance:              SATISFACTORY          UNSATISFACTORY Comments:
M/jlg Page 11 of 13 TURNOVER SHEET INITIAL CONDITIONS:  The reactor is operating at power  You are the LPEO on the 19-07 shift  The Shift Manager is "Smith" INITIATING CUES (IF APPLICABLE):  Perform the front page of 3139, Control Room Shift Turnover Checklist
Performance Step: 10      Record Steam Flow Critical: N Standard:                  Records 7.25 x 106 Lb/Hr +/- .25 Evaluator Cue:            None Performance:              SATISFACTORY          UNSATISFACTORY Comments:
M/jlg Page 6 of 13


QF-1030-11 Rev. 2 (FP-T-SAT-30)
QF-1030-11 Rev. 2 (FP-T-SAT-30)
JPM-3139-001 (CONTROL ROOM SHIFT T URNOVER CHECKLIST) Rev.0 M/jlg Page 12 of 13 SIMULATOR SET UP:
JPM-3139-001 (CONTROL ROOM SHIFT TURNOVER CHECKLIST) Rev.0 Performance Step: 11      Record FW Flow Critical: N Standard:                  Records 7.25 x 106 Lb/Hr +/- .25 Evaluator Cue:            None Performance:              SATISFACTORY          UNSATISFACTORY Comments:
IC-15 or other 100% power IC. Place the HPCI flow controller in Manual  Place the key lock switch for MO-2002 (RHR DIV 1 HX BYPASS) in the CLOSED position.  
Performance Step: 12       Records status of Nuclear Instruments Critical: N Standard:                  Records APRMs 2 and 5 bypassed with none above normal Evaluator Cue:            None Performance:              SATISFACTORY          UNSATISFACTORY Comments:
Performance Step: 13       Records status of Rad Monitors Critical: N Standard:                  Records none are bypassed and none above normal Evaluator Cue:            None Performance:              SATISFACTORY          UNSATISFACTORY Comments:
Performance Step: 14      Record Rx Level Mode / Controllers Critical: N Standard:                  Records 3 element, MSTR-AUTO, and Lo Flow Reg Va is in MAN.
Evaluator Cue:            None Performance:              SATISFACTORY          UNSATISFACTORY Comments:
M/jlg Page 7 of 13


SIMULATOR - MALFUNCTIONS:  
QF-1030-11 Rev. 2 (FP-T-SAT-30)
JPM-3139-001 (CONTROL ROOM SHIFT TURNOVER CHECKLIST) Rev.0 Performance Step: 15      Record RFP Level Trip Critical: N Standard:                  Records position of RFP Level Trip in NORMAL Evaluator Cue:            None Performance:              SATISFACTORY          UNSATISFACTORY Comments:
Performance Step: 16      Record Press Contr Critical: N Standard:                  Records MPR # 910 +/- 5 and EPR# 903 +/- 1 Evaluator Cue:            None Performance:              SATISFACTORY          UNSATISFACTORY Comments:
Performance Step: 17      Record Switch position and Alarms for 11 & 12 D Gen Critical: N Standard:                  Records AUTO for switch positions and None for alarms Evaluator Cue:            None Performance:              SATISFACTORY          UNSATISFACTORY Comments:
Performance Step: 18      Record ADS A, C, D switch positions and alarms Critical: N Standard:                  Records ADS switch positions in AUTO and None for alarms Evaluator Cue:            None Performance:              SATISFACTORY          UNSATISFACTORY Comments:
M/jlg Page 8 of 13


MALF ID MALFUNCTION TITLE DELAY RAMP EVENT VALUE FINAL. 1.       2.      
QF-1030-11 Rev. 2 (FP-T-SAT-30)
JPM-3139-001 (CONTROL ROOM SHIFT TURNOVER CHECKLIST) Rev.0 Performance Step: 19      Record SRV Low-Low Set C-03 E, G, H switch positions and alarms Critical: N Standard:                  Records Low-Low Set switch positions in AUTO and None for alarms Evaluator Cue:            None Performance:              SATISFACTORY          UNSATISFACTORY Comments:
Performance Step: 20      Record DIV II Low-Low Set Logic switch position and alarms Critical: N Standard:                  Records switch in Auto and None for alarms Evaluator Cue:            None Performance:              SATISFACTORY          UNSATISFACTORY Comments:
Performance Step: 21      Record A RHR switch position, alarms, and valve line-up Critical: Y Standard:                  Records switch position in Auto, None for alarms, and notes MO-2002 (RHR DIV 1 HX BYPASS) valve is in the CLOSED position. Reports to CRS and takes keylock switch to OPEN when directed by CRS.
Evaluator Cue:            Acknowledge report of MO-2002 (RHR DIV 1 HX BYPASS) valve is in the CLOSED position. Directs valve be opened.
Performance:              SATISFACTORY          UNSATISFACTORY Comments:
Performance Step: 22      Record A RHRSW switch position, alarms, and valve line-up Critical: N Standard:                  Records switch position in Auto, None for alarms, and valve line-up sat Evaluator Cue:            None Performance:              SATISFACTORY          UNSATISFACTORY Comments:
M/jlg Page 9 of 13


SIMULATOR - OVERRIDES:  
QF-1030-11 Rev. 2 (FP-T-SAT-30)
JPM-3139-001 (CONTROL ROOM SHIFT TURNOVER CHECKLIST) Rev.0 Performance Step: 23      Record A Core Spray switch position, alarms, and valve line-up Critical: N Standard:                  Records switch position in Auto, None for alarms, and valve line-up sat Evaluator Cue:            None Performance:              SATISFACTORY          UNSATISFACTORY Comments:
Performance Step: 24      Record HPCI switch position, alarms, and valve line-up. Notes and reports to the Critical: Y                CRS that the HPCI Flow Controller is in MANUAL control.
Standard:                  Recognizes that the HPCI Flow Controller is in MANUAL control and reports to the CRS the discrepancy. Selects AUTO control when directed.
Evaluator Cue:            Acknowledge the report and direct that the HPCI Flow Controller be placed in AUTO.
Performance:              SATISFACTORY          UNSATISFACTORY Comments:
Terminating Cues:      When the HPCI check has been completed, state that the JPM is completed Stop Time:
Critical Time ___N/A____
M/jlg Page 10 of 13


OVERRIDE ID.
QF-1030-11 Rev. 2 (FP-T-SAT-30)
OVERRIDE DESCRIPTION DELAY RAMP EVENT VALUE FINAL 1.        2.       
TURNOVER SHEET INITIAL CONDITIONS:
* The reactor is operating at power
* You are the LPEO on the 19-07 shift
* The Shift Manager is Smith INITIATING CUES (IF APPLICABLE):
* Perform the front page of 3139, Control Room Shift Turnover Checklist M/jlg Page 11 of 13


SIMULATOR - REMOTE FUNCTIONS:  
QF-1030-11 Rev. 2 (FP-T-SAT-30)
JPM-3139-001 (CONTROL ROOM SHIFT TURNOVER CHECKLIST) Rev.0 SIMULATOR SET UP:
* IC-15 or other 100% power IC.
* Place the HPCI flow controller in Manual
* Place the key lock switch for MO-2002 (RHR DIV 1 HX BYPASS) in the CLOSED position.
SIMULATOR - MALFUNCTIONS:
MALF ID    MALFUNCTION TITLE                DELAY    RAMP      EVENT  VALUE    FINAL.
1.
2.
SIMULATOR - OVERRIDES:
OVERRIDE ID.                OVERRIDE        DELAY    RAMP      EVENT  VALUE    FINAL DESCRIPTION 1.
2.
SIMULATOR - REMOTE FUNCTIONS:
REMOTE        REMOTE FUNCTION TITLE          DELAY    RAMP      EVENT  VALUE      FINAL FUNC. No.
1.
2.
M/jlg Page 12 of 13


REMOTE FUNC. No.
QF-1030-11 Rev. 2 (FP-T-SAT-30)
REMOTE FUNCTION TITLE DELAY RAMP EVENT VALUE FINAL 1.        2.
JPM-3139-001 (CONTROL ROOM SHIFT TURNOVER CHECKLIST) Rev.0 ATTACHMENT 1 JOB PERFORMANCE MEASURE VALIDATION CHECKLIST ALL STEPS IN THIS CHECKLIST ARE TO BE PERFORMED UPON INITIAL VALIDATION AND PRIOR TO USE.
QF-1030-11 Rev. 2 (FP-T-SAT-30)
REVIEW STATEMENTS                                                           YES       NO       N/A
JPM-3139-001 (CONTROL ROOM SHIFT T URNOVER CHECKLIST) Rev.0 M/jlg Page 13 of 13 ATTACHMENT 1 JOB PERFORMANCE MEASURE VALIDATION CHECKLIST ALL STEPS IN THIS CHECKLIST ARE TO BE PERFORMED UPON INITIAL VALIDATION AND PRIOR TO USE.
: 1. Are all items on the signature page filled in correctly?
REVIEW STATEMENTS YES NO N/A 1. Are all items on the signature page filled in correctly?
: 2. Has the JPM been reviewed and validated by SMEs?
: 2. Has the JPM been reviewed and validated by SMEs?
: 3. Can the required conditions for the JPM be appropriately established in the simulator if required?
: 3. Can the required conditions for the JPM be appropriately established in the simulator if required?
: 4. Does the performance steps accurately reflect trainee's actions in accordance with plant procedures?
: 4. Does the performance steps accurately reflect trainees actions in accordance with plant procedures?
: 5. Is the standard for each performance item specific as to what controls, indications and ranges are required to evaluate if the  
: 5. Is the standard for each performance item specific as to what controls, indications and ranges are required to evaluate if the trainee properly performed the step?
 
trainee properly performed the step?
: 6. Has the completion time been established based on validation data or incumbent experience?
: 6. Has the completion time been established based on validation data or incumbent experience?
: 7. If the task is time critical, is the time critical portion based upon actual task performance requirements?
: 7. If the task is time critical, is the time critical portion based upon actual task performance requirements?
Line 347: Line 281:
Sequence / Time Critical) appropriately?
Sequence / Time Critical) appropriately?
: 11. Have all special tools and equipment needed to perform the task been identified and made available to the trainee?
: 11. Have all special tools and equipment needed to perform the task been identified and made available to the trainee?
: 12. Are all references identified, current, accurate, and available to the trainee?   13. Have all required cues (as anticipated) been identified for the evaluator to assist task completion?
: 12. Are all references identified, current, accurate, and available to the trainee?
All questions/statements must be answered "YES" or the JPM is not valid for use. If all questions/statements  
: 13. Have all required cues (as anticipated) been identified for the evaluator to assist task completion?
 
All questions/statements must be answered YES or the JPM is not valid for use. If all questions/statements are answered YES then the JPM is considered valid and can be performed as written. The individual(s) performing the validation SHALL sign and date this form.
are answered "YES" then the JPM is considered valid and can be performed as written. The individual(s) performing the validation SHALL sign and date this form.
__________________________                   __________________________
__________________________         __________________________
Validation Personnel /Date                  Validation Personnel/Date
Validation Personnel /Date                 Validation Personnel/Date
__________________________                  __________________________
__________________________         __________________________  
Validation Personnel /Date                  Validation Personnel/Date
__________________________                  __________________________
Validation Personnel /Date                   Validation Personnel/Date
__________________________                   __________________________
Validation Personnel /Date                  Validation Personnel/Date Historical Record: (Optional)
M/jlg Page 13 of 13


Validation Personnel /Date                  Validation Personnel/Date
QF-1030-11 Rev. 2 (FP-T-SAT-30)
__________________________        __________________________
JOB PERFORMANCE MEASURE (JPM)
 
SITE:                     MONTICELLO NUCLEAR GENERATING PLANT JPM TITLE:                 DETERMINE SHIFT STAFFING JPM NUMBER:               JPM OWI-01.06-003                           REV.       0 RELATED PRA               None INFORMATION:
Validation Personnel /Date                  Validation Personnel/Date
TASK NUMBER(S) /           SS299.289 TASK TITLE(S):             Implement the Operations Group Organization and Responsibilities Assignments K/A NUMBERS:           2.1.4                                     Rating: SRO/RO:       3.4 / 2.3 APPLICABLE METHOD OF TESTING:
__________________________        __________________________
Discussion:               Simulate/walkthrough:             Perform:   x EVALUATION LOCATION:             In-Plant:                         Control Room:
 
Simulator:                         Other:                   x Lab:
Validation Personnel /Date                  Validation Personnel/Date Historical Record:  (Optional)
Time for Completion:           15     Minutes                 Time Critical:       No Alternate Path / Faulted:       No TASK APPLICABILITY:             SRO:       X       SRO/RO:               SRO/RO/NLO:
 
QF-1030-11 Rev. 2 (FP-T-SAT-30)
Retention: Life of policy + 10yrs. Disposition: Reviewer and Approver Retain in:  Training Program File M/jlg Page 1 of 9 JOB PERFORMANCE MEASURE (JPM)
SITE: MONTICELLO NUCLEAR GENERATING PLANT JPM TITLE:
DETERMINE SHIFT STAFFING JPM NUMBER:
JPM OWI-01.06-003 REV. 0   RELATED PRA  
 
INFORMATION:
None  TASK NUMBER(S) /  
 
TASK TITLE(S):
SS299.289 Implement the Operations Group Organization and Responsibilities  
 
Assignments K/A NUMBERS:
 
====2.1.4 Rating====
SRO/RO:
3.4 / 2.3 APPLICABLE METHOD OF TESTING:
Discussion:   Simulate/walkthrough:   Perform: x EVALUATION LOCATION:
In-Plant:   Control Room:
Simulator:   Other: x Lab:       Time for Completion: 15 Minutes Time Critical: No     Alternate Path / Faulted: No TASK APPLICABILITY:
SRO: X SRO/RO: SRO/RO/NLO:
Additional signatures may be added as needed.
Additional signatures may be added as needed.
Developed by:
Developed by:                               J Ruth Instructor                               Date Validated by:
J Ruth   Instructor Date   Validated by:
Validation Instructor                          Date (See JPM Validation Checklist, Attachment 1)
Approved by:
Training Supervisor                            Date Retention: Life of policy + 10yrs.                                          Disposition: Reviewer and Approver Retain in: Training Program File M/jlg Page 1 of 9


Validation Instructor (See JPM Validation Checklist, Attachment 1)
QF-1030-11 Rev. 2 (FP-T-SAT-30)
Date    Approved by:
JPM-OWI-01.06-003 (DETERMINE SHIFT STAFFING) Rev. 0 JPM Number: JPM-OWI-01.06-003 JPM Title: Determine Shift Staffing Examinee:                                             Evaluator:
 
Job Title:                                               Date:
Training Supervisor Date QF-1030-11 Rev. 2 (FP-T-SAT-30)
Start Time                                         Finish Time PERFORMANCE RESULTS:                           SAT:                   UNSAT:
JPM-OWI-01.06-003 (DETERMINE SHIFT STAFFING) Rev. 0 M/jlg Page 2 of 9 JPM Number: JPM-OWI-01.06-003 JPM Title: Determine Shift Staffing Examinee: Evaluator: Job Title: Date: Start Time Finish Time PERFORMANCE RESULTS:
COMMENTS/FEEDBACK: (Comments shall be made for any steps graded unsatisfactory).
SAT: UNSAT:  
EVALUATORS SIGNATURE:
 
NOTE: Only this page needs to be retained in examinees record if completed satisfactorily. If unsatisfactory performance is demonstrated, the entire JPM should be retained.
COMMENTS/FEEDBACK: (Comments shall be made for any steps graded unsatisfactory).  
M/jlg Page 2 of 9
 
EVALUATOR'S SIGNATURE:  
 
NOTE: Only this page needs to be retained in examinee's record if completed satisfactorily. If unsatisfactory performance is demonstrated, the entire JPM should be retained.
QF-1030-11  Rev. 2  (FP-T-SAT-30)
JPM-OWI-01.06-003 (DETERMINE SHIFT STAFFING) Rev. 0 M/jlg Page 3 of 9 JPM BRIEFING/TURNOVER (See MTCP-03.32, Figure 6.2)
I will explain the initial conditions, which step(s) to simulate or discuss, and provide initiating cues. When you
 
complete the task successfully, the objective for this job performance measure will be satisfied.


QF-1030-11 Rev. 2 (FP-T-SAT-30)
JPM-OWI-01.06-003 (DETERMINE SHIFT STAFFING) Rev. 0 JPM BRIEFING/TURNOVER (See MTCP-03.32, Figure 6.2)
I will explain the initial conditions, which step(s) to simulate or discuss, and provide initiating cues. When you complete the task successfully, the objective for this job performance measure will be satisfied.
DURING THE JPM, ENSURE PROPER SAFETY PRECAUTIONS, FME, AND/OR RADIOLOGICAL CONCERNS AS APPLICABLE ARE FOLLOWED.
DURING THE JPM, ENSURE PROPER SAFETY PRECAUTIONS, FME, AND/OR RADIOLOGICAL CONCERNS AS APPLICABLE ARE FOLLOWED.
INITIAL CONDITIONS: You are a fully qualified CRS at the beginning of a shift change The reactor is operating in MODE 1 Shift 4 is the duty shift Noland is filling the vacant NPE&RO position The Shift Chemist (Beaker) and Shift Rad. Prot. Specialist ( Marx) are available and are fire brigade qualified All operations personnel are respirator qualified unless noted otherwise INITIATING CUES (IF APPLICABLE):   Determine if the staffing requirements are met for the following On-shift collateral duties by filling out the provided roster with the appropriate names: Fire Brigade Toxic Gas S/D Outside the Control Room   Provide MNGP Operations Department Organization/Qualification chart Provide Respirator qualification memo from RP/Chem Provide blank roster form  
INITIAL CONDITIONS:
* You are a fully qualified CRS at the beginning of a shift change
* The reactor is operating in MODE 1
* Shift 4 is the duty shift
* Noland is filling the vacant NPE&RO position
* The Shift Chemist (Beaker) and Shift Rad. Prot. Specialist ( Marx) are available and are fire brigade qualified
* All operations personnel are respirator qualified unless noted otherwise INITIATING CUES (IF APPLICABLE):
* Determine if the staffing requirements are met for the following On-shift collateral duties by filling out the provided roster with the appropriate names:
Fire Brigade Toxic Gas S/D Outside the Control Room
* Provide MNGP Operations Department Organization/Qualification chart
* Provide Respirator qualification memo from RP/Chem
* Provide blank roster form M/jlg Page 3 of 9


QF-1030-11 Rev. 2 (FP-T-SAT-30)
QF-1030-11 Rev. 2 (FP-T-SAT-30)
JPM-OWI-01.06-003 (DETERMINE SHIFT STAFFING) Rev. 0 M/jlg Page 4 of 9 JPM PERFORMANCE INFORMATION  
JPM-OWI-01.06-003 (DETERMINE SHIFT STAFFING) Rev. 0 JPM PERFORMANCE INFORMATION Required Materials:       MTF-7600-002, Monticello Fire Brigade Training Summary, Monticello Nuclear Generating Plant Operations Department Organization/Qualification General  
 
Required Materials:
MTF-7600-002, Monticello Fire Brigade Training Summary, Monticello Nuclear Generating Plant Operations Department Organization/Qualification General  


==References:==
==References:==
OWI-01.06 Rev. 28 Task Standards:            Determine Staffing Requirements Start Time:
NOTE: When providing Evaluator Cues to the examinee, care must be exercised to avoid prompting the examinee. Typically cues are only provided when the examinees actions warrant receiving the information (i.e. the examinee looks or asks for the indication).
NOTE: Critical steps are marked with a Y below the performance step number. Failure to meet the standard for any critical step shall result in failure of this JPM.
Performance Step: 1            Refers to OWI-01.06, DUTY OPERATIONS PERSONNEL REQUIREMENTS AND Critical: N                    RESPONSIBILITIES Standard:                      Refers to OWI for guidance Evaluator Cue:                  None Performance:                  SATISFACTORY              UNSATISFACTORY Comments:
Performance Step: 2            On-shift collateral duties require the following staffing:
Critical: Y                          1. Fire Brigade:
Five duty crew members normally filled by the following individuals: BOP, two NAPEOs, Shift Chemist, Shift Rad Prot Spec. These individuals are required to be respirator qualified.
Standard:                      Assigned White, Thompson, Williams, Shift Chemist and Shift Rad Prot Spec to Fire Brigade.
Evaluator Cue:                  If asked, inform the candidate that all non-operations required individuals are available and respirator qualified.
Performance:                  SATISFACTORY              UNSATISFACTORY Comments:
M/jlg Page 4 of 9


OWI-01.06 Rev. 28 Task Standards:
QF-1030-11 Rev. 2 (FP-T-SAT-30)
Determine Staffing Requirements Start Time:
JPM-OWI-01.06-003 (DETERMINE SHIFT STAFFING) Rev. 0 Performance Step: 3        On-shift collateral duties require the following staffing:
NOTE:  When providing "Evaluator Cues" to the examinee, care must be exercised to avoid prompting the examinee. Typically cues are only provided when the examinee's actions warrant receiving the information (i.e. the examinee looks or asks for the indication).
Critical: Y                    2. Toxic Gas Event:
NOTE: Critical steps are marked with a "Y" below the performance step number. Failure to meet the standard for any critical step shall result in failure of this JPM.
Technical specifications requires two active SROs and two active ROs while in Startup or Run mode. The Shift Mgr, Control Room Supv, and two of the three Control Room Operators satisfy this requirement. These individuals are required by A.4 (HAZARDOUS MATERIALS PROCEDURES) to be respirator qualified.
Performance Step:  1 Critical:  N Refers to OWI-01.06, DUTY OPERATIONS PERSONNEL REQUIREMENTS AND RESPONSIBILITIES Standard:
Standard:                 Determines that any 2 of the 3 ROs will satisfy the requirement.
Refers to OWI for guidance Evaluator Cue:
Determines that this requirement cannot be satisfied due to Smith not being respirator qualified.
None  Performance: SATISFACTORY UNSATISFACTORY Comments:
Evaluator Cue:             Acknowledges report Performance:               SATISFACTORY             UNSATISFACTORY Comments:
Performance Step: 2 Critical:  Y On-shift collateral duties require the following staffing: 1. Fire Brigade:
Performance Step: 4        On-shift collateral duties require the following staffing:
Five duty crew members normally filled by the following individuals: BOP, two
Critical: Y                    3. S/D Outside the Control Room:
Three duty crew members are required to effectively implement C.4-C (SHUTDOWN OUTSIDE CONTROL ROOM). Normally four individuals are available to implement this procedure. These individuals cannot simultaneously have fire Brigade duties. (Fire in the Control room or Cable spreading Room requires both Fire Brigade and C.4-C implementation). The Shift Mgr, NLPE&RO, NPE&RO, and NAPEO normally satisfies this requirement. There are no respirator qualifications associated with this requirement.
Standard:                  Determines this requirement can be met by assigning any combination of Smith, Jones, Nolan, or Black.
Evaluator Cue:            None Performance:              SATISFACTORY            UNSATISFACTORY Comments:
M/jlg Page 5 of 9


NAPEOs, Shift Chemist, Shift Rad Prot Spec. These individuals are required to be
QF-1030-11 Rev. 2 (FP-T-SAT-30)
 
JPM-OWI-01.06-003 (DETERMINE SHIFT STAFFING) Rev. 0 Performance Step: 5        INFORM EVALUATOR THAT THE TASK HAS BEEN COMPLETED.
respirator qualified.
Critical: N Standard:                 Operator informs evaluator that the task is completed.
 
Evaluator Cue:             When the operator informs evaluator that the task is completed state that the JPM is complete.
Standard:
Performance:               SATISFACTORY           UNSATISFACTORY Comments:
Assigned White,  Thompson, Williams, Shift Chemist and Shift Rad Prot Spec to Fire Brigade.
Terminating Cues:     When the operator informs evaluator that the task is completed state that the JPM is complete.
Evaluator Cue:
Stop Time:
If asked, inform the candidate that all non-operations required individuals are available and respirator qualified.
Critical Time ___N/A____
Performance: SATISFACTORY UNSATISFACTORY Comments:
M/jlg Page 6 of 9
 
QF-1030-11 Rev. 2 (FP-T-SAT-30)
JPM-OWI-01.06-003 (DETERMINE SHIFT STAFFING) Rev. 0 M/jlg Page 5 of 9 Performance Step: 3 Critical: Y On-shift collateral duties require the following staffing: 2. Toxic Gas Event:
Technical specifications requires two active SROs and two active ROs while in
 
Startup or Run mode. The Shift Mgr, Control Room Supv, and two of the three
 
Control Room Operators satisfy this requirement. These individuals are required
 
by A.4 (HAZARDOUS MATERIALS PROCEDURES) to be respirator qualified.
Standard:
Determines that any 2 of the 3 ROs will satisfy the requirement.
Determines that this requirement cannot be satisfied due to Smith not being
 
respirator qualified.
Evaluator Cue:
Acknowledges report Performance: SATISFACTORY UNSATISFACTORY Comments:
Performance Step: 4 Critical:  Y On-shift collateral duties require the following staffing: 3. S/D Outside the Control Room:
Three duty crew members are required to effectively implement C.4-C (SHUTDOWN OUTSIDE CONTROL ROOM). Normally four individuals are
 
available to implement this procedure. These individuals cannot simultaneously
 
have fire Brigade duties.  (Fire in the Control room or Cable spreading Room
 
requires both Fire Brigade and C.4-C implementation). The Shift Mgr, NLPE&RO, NPE&RO, and NAPEO normally satisfies this requirement. There are no respirator


qualifications associated with this requirement.
QF-1030-11 Rev. 2 (FP-T-SAT-30)
Standard:
TURNOVER SHEET INITIAL CONDITIONS:
Determines this requirement can be met by assigning any combination of Smith, Jones, Nolan, or Black.
* You are a fully qualified CRS at the beginning of a shift change
Evaluator Cue:
* The reactor is operating in MODE 1
None  Performance: SATISFACTORY UNSATISFACTORY Comments:  
* Shift 4 is the duty shift
* Noland is filling the vacant NPE&RO position
* The Shift Chemist (Beaker) and Shift Rad. Prot. Specialist ( Marx) are available and are fire brigade qualified
* All operations personnel are respirator qualified unless noted otherwise INITIATING CUES (IF APPLICABLE):
* Determine if the staffing requirements are met for the following On-shift collateral duties by filling out the provided roster with the appropriate names:
Fire Brigade Toxic Gas S/D Outside the Control Room
* Provide MNGP Operations Department Organization/Qualification chart
* Provide Respirator qualification memo from RP/Chem
* Provide blank roster form M/jlg Page 7 of 9


QF-1030-11 Rev. 2 (FP-T-SAT-30)
QF-1030-11 Rev. 2 (FP-T-SAT-30)
JPM-OWI-01.06-003 (DETERMINE SHIFT STAFFING) Rev. 0 M/jlg Page 6 of 9 Performance Step: 5 CriticalN INFORM EVALUATOR THAT THE TASK HAS BEEN COMPLETED.
JPM-OWI-01.06-003 (DETERMINE SHIFT STAFFING) Rev. 0 SIMULATOR SET UP:
Standard:
Admin JPM; no simulator setup required.
Operator informs evaluator that the task is completed.
SIMULATOR - MALFUNCTIONS:
Evaluator Cue:
MALF ID    MALFUNCTION TITLE              DELAY    RAMP    EVENT    VALUE FINAL.
When the operator informs evaluator that the task is completed state that the JPM is complete.
1.
Performance: SATISFACTORY UNSATISFACTORY Comments:
2.
Terminating Cues:
SIMULATOR - OVERRIDES:
OVERRIDE ID.              OVERRIDE      DELAY  RAMP  EVENT    VALUE  FINAL DESCRIPTION 1.
2.
SIMULATOR - REMOTE FUNCTIONS:
REMOTE        REMOTE FUNCTION TITLE      DELAY    RAMP  EVENT    VALUE  FINAL FUNC. No.
1.
2.
M/jlg Page 8 of 9


When the operator informs evaluator that the task is completed state that the JPM is complete. Stop Time:
QF-1030-11 Rev. 2 (FP-T-SAT-30)
Critical Time
JPM-OWI-01.06-003 (DETERMINE SHIFT STAFFING) Rev. 0 ATTACHMENT 1 JOB PERFORMANCE MEASURE VALIDATION CHECKLIST ALL STEPS IN THIS CHECKLIST ARE TO BE PERFORMED UPON INITIAL VALIDATION AND PRIOR TO USE.
___N/A____
REVIEW STATEMENTS                                                           YES       NO       N/A
QF-1030-11 Rev. 2 (FP-T-SAT-30)
: 1. Are all items on the signature page filled in correctly?
M/jlg Page 7 of 9 TURNOVER SHEET INITIAL CONDITIONS:  You are a fully qualified CRS at the beginning of a shift change  The reactor is operating in MODE 1  Shift 4 is the duty shift  Noland is filling the vacant NPE&RO position  The Shift Chemist (Beaker) and Shift Rad. Prot. Specialist ( Marx) are available and are fire brigade qualified  All operations personnel are respirator qualified unless noted otherwise INITIATING CUES (IF APPLICABLE):  Determine if the staffing requirements are met for the following On-shift collateral duties by filling out the provided roster  with the appropriate names:  Fire Brigade  Toxic Gas  S/D Outside the Control Room  Provide MNGP Operations Department Organization/Qualification chart  Provide Respirator qualification memo from RP/Chem  Provide blank roster form
 
QF-1030-11  Rev. 2  (FP-T-SAT-30)
JPM-OWI-01.06-003 (DETERMINE SHIFT STAFFING) Rev. 0 M/jlg Page 8 of 9 SIMULATOR SET UP:
Admin JPM; no simulator setup required.
 
SIMULATOR - MALFUNCTIONS:
 
MALF ID MALFUNCTION TITLE DELAY RAMP EVENT VALUE FINAL. 1.        2.       
 
SIMULATOR - OVERRIDES:
 
OVERRIDE ID.
OVERRIDE DESCRIPTION DELAY RAMP EVENT VALUE FINAL 1.        2.       
 
SIMULATOR - REMOTE FUNCTIONS:
 
REMOTE FUNC. No.
REMOTE FUNCTION TITLE DELAY RAMP EVENT VALUE FINAL 1.        2.       
 
QF-1030-11  Rev. 2  (FP-T-SAT-30)
JPM-OWI-01.06-003 (DETERMINE SHIFT STAFFING) Rev. 0 M/jlg Page 9 of 9 ATTACHMENT 1 JOB PERFORMANCE MEASURE VALIDATION CHECKLIST ALL STEPS IN THIS CHECKLIST ARE TO BE PERFORMED UPON INITIAL VALIDATION AND PRIOR TO USE.
REVIEW STATEMENTS YES NO N/A 1. Are all items on the signature page filled in correctly?
: 2. Has the JPM been reviewed and validated by SMEs?
: 2. Has the JPM been reviewed and validated by SMEs?
: 3. Can the required conditions for the JPM be appropriately established in the simulator if required?
: 3. Can the required conditions for the JPM be appropriately established in the simulator if required?
: 4. Does the performance steps accurately reflect trainee's actions in accordance with plant procedures?
: 4. Does the performance steps accurately reflect trainees actions in accordance with plant procedures?
: 5. Is the standard for each performance item specific as to what controls, indications and ranges are required to evaluate if the  
: 5. Is the standard for each performance item specific as to what controls, indications and ranges are required to evaluate if the trainee properly performed the step?
 
trainee properly performed the step?
: 6. Has the completion time been established based on validation data or incumbent experience?
: 6. Has the completion time been established based on validation data or incumbent experience?
: 7. If the task is time critical, is the time critical portion based upon actual task performance requirements?
: 7. If the task is time critical, is the time critical portion based upon actual task performance requirements?
Line 517: Line 418:
Sequence / Time Critical) appropriately?
Sequence / Time Critical) appropriately?
: 11. Have all special tools and equipment needed to perform the task been identified and made available to the trainee?
: 11. Have all special tools and equipment needed to perform the task been identified and made available to the trainee?
: 12. Are all references identified, current, accurate, and available to the trainee?   13. Have all required cues (as anticipated) been identified for the evaluator to assist task completion?
: 12. Are all references identified, current, accurate, and available to the trainee?
All questions/statements must be answered "YES" or the JPM is not valid for use. If all questions/statements  
: 13. Have all required cues (as anticipated) been identified for the evaluator to assist task completion?
 
All questions/statements must be answered YES or the JPM is not valid for use. If all questions/statements are answered YES then the JPM is considered valid and can be performed as written. The individual(s) performing the validation SHALL sign and date this form.
are answered "YES" then the JPM is considered valid and can be performed as written. The individual(s) performing the validation SHALL sign and date this form.
__________________________                   __________________________
__________________________         __________________________
Validation Personnel /Date                   Validation Personnel/Date
Validation Personnel /Date                 Validation Personnel/Date
__________________________                   __________________________
__________________________         __________________________  
Validation Personnel /Date                   Validation Personnel/Date
 
__________________________                   __________________________
Validation Personnel /Date                 Validation Personnel/Date
Validation Personnel /Date                   Validation Personnel/Date
__________________________         __________________________  
__________________________                   __________________________
 
Validation Personnel /Date                   Validation Personnel/Date Historical Record: (Optional)
Validation Personnel /Date                 Validation Personnel/Date
M/jlg Page 9 of 9
__________________________         __________________________  
 
Validation Personnel /Date                 Validation Personnel/Date Historical Record: (Optional)  


QF-1030-11 Rev. 2 (FP-T-SAT-30)
QF-1030-11 Rev. 2 (FP-T-SAT-30)
Retention: Life of policy + 10yrs. Disposition: Reviewer and Approver Retain in:  Training Program File M/jlg Page 1 of 14 JOB PERFORMANCE MEASURE (JPM)
JOB PERFORMANCE MEASURE (JPM)
SITE: MONTICELLO NUCLEAR GENERATING PLANT JPM TITLE:
SITE:                     MONTICELLO NUCLEAR GENERATING PLANT JPM TITLE:                 DAILY JET PUMP OPERABILITY CHECK TEST 0133 JPM NUMBER:               JPM-0133-001                               REV.         0 RELATED PRA               None INFORMATION:
DAILY JET PUMP OPERABILITY CHECK TEST 0133 JPM NUMBER:
TASK NUMBER(S) /           CR299.349 TASK TITLE(S):             Perform Operations Daily Log - Parts A, B, D, E, G, H, & J K/A NUMBERS:           2.2.12                                   Rating: SRO/RO:       3.4/3.0 APPLICABLE METHOD OF TESTING:
JPM-0133-001 REV. 0   RELATED PRA  
Discussion:               Simulate/walkthrough:               Perform:   X EVALUATION LOCATION:             In-Plant:                           Control Room:
 
Simulator:                 X       Other:
INFORMATION:
Lab:
None  TASK NUMBER(S) /  
Time for Completion:           25     Minutes                   Time Critical:       No Alternate Path / Faulted:       No TASK APPLICABILITY:             SRO:             SRO/RO:         X     SRO/RO/NLO:
 
TASK TITLE(S):
CR299.349 Perform Operations Daily Log - Parts A, B, D, E, G, H, & J K/A NUMBERS:
2.2.12 Rating: SRO/RO:
3.4/3.0 APPLICABLE METHOD OF TESTING:
Discussion:   Simulate/walkthrough:   Perform: X EVALUATION LOCATION:
In-Plant:   Control Room:
Simulator: X Other:
Lab:       Time for Completion: 25 Minutes Time Critical: No     Alternate Path / Faulted: No TASK APPLICABILITY:
SRO: SRO/RO:X SRO/RO/NLO:
Additional signatures may be added as needed.
Additional signatures may be added as needed.
Developed by:
Developed by:                               J Ruth Instructor                                 Date Validated by:
J Ruth   Instructor Date   Validated by:
Validation Instructor                            Date (See JPM Validation Checklist, Attachment 1)
Approved by:
Training Supervisor                              Date Retention: Life of policy + 10yrs.                                            Disposition: Reviewer and Approver Retain in: Training Program File M/jlg Page 1 of 14


Validation Instructor (See JPM Validation Checklist, Attachment 1)
QF-1030-11 Rev. 2 (FP-T-SAT-30)
Date    Approved by:
JPM-0133-001 (DAILY JET PUMP OPERABILITY CHECK TEST 0133) Rev.0 JPM Number: JPM-0133-001 JPM Title: Daily Jet Pump Operability Check Test 0133 Examinee:                                             Evaluator:
 
Job Title:                                               Date:
Training Supervisor Date QF-1030-11 Rev. 2 (FP-T-SAT-30)
Start Time                                         Finish Time PERFORMANCE RESULTS:                           SAT:                   UNSAT:
JPM-0133-001 (DAILY JET PUMP OPERABILITY CHECK TEST 0133) Rev.0 M/jlg Page 2 of 14 JPM Number:
COMMENTS/FEEDBACK: (Comments shall be made for any steps graded unsatisfactory).
JPM-0133-001 JPM Title:
EVALUATORS SIGNATURE:
Daily Jet Pump Operability Check Test 0133 Examinee: Evaluator: Job Title: Date: Start Time Finish Time PERFORMANCE RESULTS:
NOTE: Only this page needs to be retained in examinees record if completed satisfactorily. If unsatisfactory performance is demonstrated, the entire JPM should be retained.
SAT: UNSAT:  
M/jlg Page 2 of 14
 
COMMENTS/FEEDBACK: (Comments shall be made for any steps graded unsatisfactory).  
 
EVALUATOR'S SIGNATURE:  
 
NOTE: Only this page needs to be retained in examinee's record if completed satisfactorily. If unsatisfactory performance is demonstrated, the entire JPM should be retained.
QF-1030-11  Rev. 2  (FP-T-SAT-30)
JPM-0133-001 (DAILY JET PUMP OPERABILITY CHECK TEST 0133) Rev.0 M/jlg Page 3 of 14 JPM BRIEFING/TURNOVER (See MTCP-03.32, Figure 6.2)
I will explain the initial conditions, which step(s) to simulate or discuss, and provide initiating cues. When you
 
complete the task successfully, the objective for this job performance measure will be satisfied.


QF-1030-11 Rev. 2 (FP-T-SAT-30)
JPM-0133-001 (DAILY JET PUMP OPERABILITY CHECK TEST 0133) Rev.0 JPM BRIEFING/TURNOVER (See MTCP-03.32, Figure 6.2)
I will explain the initial conditions, which step(s) to simulate or discuss, and provide initiating cues. When you complete the task successfully, the objective for this job performance measure will be satisfied.
DURING THE JPM, ENSURE PROPER SAFETY PRECAUTIONS, FME, AND/OR RADIOLOGICAL CONCERNS AS APPLICABLE ARE FOLLOWED.
DURING THE JPM, ENSURE PROPER SAFETY PRECAUTIONS, FME, AND/OR RADIOLOGICAL CONCERNS AS APPLICABLE ARE FOLLOWED.
INITIAL CONDITIONS: The reactor is operating at power You are the BOP operator INITIATING CUES (IF APPLICABLE):   The CRS directs you to perform Test 0133, Daily Jet Pu mp Operability Check per Operations Daily Log - Part B
INITIAL CONDITIONS:
 
* The reactor is operating at power
QF-1030-11  Rev. 2  (FP-T-SAT-30)
* You are the BOP operator INITIATING CUES (IF APPLICABLE):
JPM-0133-001 (DAILY JET PUMP OPERABILITY CHECK TEST 0133) Rev.0 M/jlg Page 4 of 14 JPM PERFORMANCE INFORMATION
* The CRS directs you to perform Test 0133, Daily Jet Pump Operability Check per Operations Daily Log - Part B
M/jlg Page 3 of 14


Required Materials:
QF-1030-11 Rev. 2 (FP-T-SAT-30)
Individual Jet Pump dP readings, B.01.04-06 Figures 15, 16 & 17.
JPM-0133-001 (DAILY JET PUMP OPERABILITY CHECK TEST 0133) Rev.0 JPM PERFORMANCE INFORMATION Required Materials:       Individual Jet Pump dP readings, B.01.04-06 Figures 15, 16 & 17.
General  
General  


==References:==
==References:==
Simulator IC at 100% power. (IC-15)
Simulator IC at 100% power. (IC-15)
Task Standards:
Task Standards:           Complete Test 0133 (Expected readings are provided in red.)
Complete Test 0133 (Expected readings are provided in red.) Start Time:
Start Time:
NOTE: When providing "Evaluator Cues" to the examinee, care must be exercised to avoid prompting the examinee. Typically cues are only provided when the examinee's actions warrant receiving the information (i.e. the examinee looks or asks for the indication).
NOTE: When providing Evaluator Cues to the examinee, care must be exercised to avoid prompting the examinee. Typically cues are only provided when the examinees actions warrant receiving the information (i.e. the examinee looks or asks for the indication).
NOTE: Critical steps are marked with a "Y" below the performance step number. Failure to meet the standard for any critical step shall result in failure of this JPM.
NOTE: Critical steps are marked with a Y below the performance step number. Failure to meet the standard for any critical step shall result in failure of this JPM.
Performance Step: 1 Critical:  Y NOTE: STEP 3.b. and 3.c. not required to be performed until [[estimated NRC review hours::4 hours]] after associated recirculation loop is in operation and until [[estimated NRC review hours::24 hours]] after THERMAL POWER >25% RTP.
Performance Step: 1           NOTE: STEP 3.b. and 3.c. not required to be performed until [[estimated NRC review hours::4 hours]] after Critical: Y                    associated recirculation loop is in operation and until [[estimated NRC review hours::24 hours]] after THERMAL POWER >25% RTP.
IF the Reactor is in MODE 1 or 2, AND recirculation loop(s) is in operation, THEN obtain and record the values for the operating loop(s) described in the matrices below and perform the following:  
IF the Reactor is in MODE 1 or 2, AND recirculation loop(s) is in operation, THEN obtain and record the values for the operating loop(s) described in the matrices below and perform the following:
 
Variable   Panel                 Item Description             Value     Unit CRT     RPV501, Core Thermal Power %             99.5 -     %
Variable Panel Item Description Value Unit CRT RPV501, Core Thermal Power %
100 A         C-04     SI-2-184-16A, Recirc Pump 11 %Speed       85-87       %
99.5 - 100 % A C-04 SI-2-184-16A, Recirc Pump 11 %Speed 85-87 % B C-04 SI-2-184-16B, Recirc Pump 12 %Speed 85-87 % C C-04 FI-2-159A, Recirc Loop 11 Flow 26.5-27.5 x 10 3 gpm D C-04 FI-2-159B, Recirc Loop 12 Flow 26.5-27.5 x 10 3 gpm    Standard:
B         C-04     SI-2-184-16B, Recirc Pump 12 %Speed       85-87       %
Obtains and records the above data.
C         C-04     FI-2-159A, Recirc Loop 11 Flow             26.5-     gpm 27.5 x 103 D         C-04     FI-2-159B, Recirc Loop 12 Flow             26.5-     gpm 27.5 x 103 Standard:                       Obtains and records the above data.
Evaluator Cue:
Evaluator Cue:                 None Performance:                   SATISFACTORY           UNSATISFACTORY Comments:
None   Performance: SATISFACTORY UNSATISFACTORY Comments:  
M/jlg Page 4 of 14
 
QF-1030-11  Rev. 2  (FP-T-SAT-30)
JPM-0133-001 (DAILY JET PUMP OPERABILITY CHECK TEST 0133) Rev.0 M/jlg Page 5 of 14 Performance Step:  2 Critical:  Y On Figure 17, Recirculation Pump Flow vs Speed, of Ops Man B.01.04-06 (REACTOR RECIRCULATION SYSTEM - FIGURES) plot points for values of


variables A vs C and variables B vs D. 1) Does point A vs C fall in ACCEPTABLE RANGE?  
QF-1030-11 Rev. 2 (FP-T-SAT-30)
JPM-0133-001 (DAILY JET PUMP OPERABILITY CHECK TEST 0133) Rev.0 Performance Step: 2        On Figure 17, Recirculation Pump Flow vs Speed, of Ops Man B.01.04-06 Critical: Y                (REACTOR RECIRCULATION SYSTEM - FIGURES) plot points for values of variables A vs C and variables B vs D.
: 1) Does point A vs C fall in ACCEPTABLE RANGE?
Yes        No
: 2) Does point B vs D fall in ACCEPTABLE RANGE?
Yes          No Standard:                  Plots points and determines values are in the acceptable range.
Evaluator Cue:            None Performance:              SATISFACTORY          UNSATISFACTORY Comments:
Performance Step: 3 Critical: Y Variable    Panel                Item Description            Value    Unit E        C-04    FI-2-3-92B, Jet Pump Loop A Flow    25-26 x 106 lb/hr F        C-04    FI-2-3-92A, Jet Pump Loop B Flow    25-26 x 106 lb/hr G        calc    (E ÷ L) X 100, % Loop A Flow          86.8-90.3    %
H        calc    (F ÷ L) X 100, % Loop B Flow          86.8-90.3    %
J        calc    (G ÷ A) % Loop Flow / % Pump        0.99 - 1.06 ratio Speed K        calc    (H ÷ B) % Loop Flow / % Pump        0.99 - 1.06 ratio Speed L=Constant            Half of rated Core Flow              28.8 x 106  lb/hr M        calc    (E÷(L x 2)) x 100%, % Core Flow      43.4-45.2    %
N        calc    (F÷(L x 2)) x 100%, % Core Flow      43.4-45.2    %
Standard:                  Obtains and records the above data.
Evaluator Cue:            None Performance:              SATISFACTORY          UNSATISFACTORY Comments:
M/jlg Page 5 of 14


Yes        No  2) Does point B vs D fall in ACCEPTABLE RANGE?
QF-1030-11 Rev. 2 (FP-T-SAT-30)
 
JPM-0133-001 (DAILY JET PUMP OPERABILITY CHECK TEST 0133) Rev.0 Performance Step: 4       IF THERMAL POWER IS >25% RTP, Critical: Y                THEN on Figure 15, Loop A: Jet Pump Loop Flow/Pump Speed, of Ops Man B.01.04-06 plot points for values of variables J vs A.
Yes        No    Standard:
Plots points and determines values are in the acceptable range.
Evaluator Cue:
None  Performance: SATISFACTORY UNSATISFACTORY Comments:
Performance Step:  3 Critical:  Y Variable Panel Item Description Value Unit E C-04 FI-2-3-92B, Jet Pump Loop A Flow 25-26 x 10 6 lb/hr F C-04 FI-2-3-92A, Jet Pump Loop B Flow 25-26 x 10 6 lb/hr G calc (E ÷ L) X 100, % Loop A Flow 86.8-90.3
% H calc (F ÷ L) X 100, % Loop B Flow 86.8-90.3
% J calc (G ÷ A) % Loop Flow / % Pump Speed 0.99 - 1.06 ratio K calc (H ÷ B) % Loop Flow / % Pump Speed 0.99 - 1.06 ratio L=Constant Half of rated Core Flow 28.8  x 10 6 lb/hr M calc (E÷(L x 2)) x 100%, % Core Flow 43.4-45.2
% N calc (F÷(L x 2)) x 100%, % Core Flow 43.4-45.2 %    Standard:
Obtains and records the above data.
Evaluator Cue:
None  Performance: SATISFACTORY UNSATISFACTORY Comments:
 
QF-1030-11 Rev. 2 (FP-T-SAT-30)
JPM-0133-001 (DAILY JET PUMP OPERABILITY CHECK TEST 0133) Rev.0 M/jlg Page 6 of 14 Performance Step: 4 Critical:  Y IF THERMAL POWER IS >25% RTP, THEN on Figure 15, Loop A: Jet Pump Loop Flow/Pump Speed, of Ops Man B.01.04-06 plot points for values of variables J vs A.
: 1) Does point J vs A fall in ACCEPTABLE RANGE?
: 1) Does point J vs A fall in ACCEPTABLE RANGE?
Yes No N/A   Standard:
Yes           No       N/A Standard:                 Plots points and determines values are in the acceptable range.
Plots points and determines values are in the acceptable range.
Evaluator Cue:             None Performance:               SATISFACTORY           UNSATISFACTORY Comments:
Evaluator Cue:
Performance Step: 5       IF THERMAL POWER IS >25% RTP, Critical: Y                THEN on Figure 16, Loop B: Jet Pump Loop Flow/Pump Speed, of Ops Man B.01.04-06 plot points for values of variables K vs B.
None   Performance: SATISFACTORY UNSATISFACTORY Comments:
Performance Step: 5 Critical:  Y IF THERMAL POWER IS >25% RTP, THEN on Figure 16, Loop B: Jet Pump Loop Flow/Pump Speed, of Ops Man B.01.04-06 plot points for values of variables K vs B.
: 1) Does point K vs B fall in ACCEPTABLE RANGE?
: 1) Does point K vs B fall in ACCEPTABLE RANGE?
Yes No N/A   Standard:
Yes       No       N/A Standard:                 Plots points and determines values are in the acceptable range.
Plots points and determines values are in the acceptable range.
Evaluator Cue:             None Performance:               SATISFACTORY           UNSATISFACTORY Comments:
Evaluator Cue:
Performance Step: 6       IF any question in STEPs 3.a. through 3.c. is checked No, Critical: N                THEN notify Control Room Supervisor, AND perform procedure 0442 (SPECIAL JET PUMP OPERABILITY TEST).
None   Performance: SATISFACTORY UNSATISFACTORY Comments:
Standard:                  Determines no step is No.
Performance Step: 6 Critical:  N IF any question in STEPs 3.a. through 3.c. is checked "No", THEN notify Control Room Supervisor, AND perform procedure 0442 (SPECIAL JET PUMP OPERABILITY TEST).  
Evaluator Cue:            None Performance:              SATISFACTORY            UNSATISFACTORY Comments:
M/jlg Page 6 of 14


Standard:
QF-1030-11 Rev. 2 (FP-T-SAT-30)
Determines no step is "No".
JPM-0133-001 (DAILY JET PUMP OPERABILITY CHECK TEST 0133) Rev.0 Performance Step: 7        IF in MODE 1 or 2, Critical: Y                AND both recirculation loops are in operation, THEN :
Evaluator Cue:
: 1) Calculate percent of total rated core flow (M + N) 86.8-90.4%
None   Performance: SATISFACTORY UNSATISFACTORY Comments:  
Standard:                  Calculates percent of total rated core flow.
Evaluator Cue:            None Performance:              SATISFACTORY            UNSATISFACTORY Comments:
Performance Step: 8        IF in MODE 1 or 2, Critical: Y                AND both recirculation loops are in operation, THEN :
: 2) Calculate absolute value (M - N), Jet Pump Flow Mismatch _0-1.8__%
Standard:                  Calculates absolute value.
Evaluator Cue:            None Performance:              SATISFACTORY            UNSATISFACTORY Comments:
Performance Step: 9        IF in MODE 1 or 2, Critical: N                AND both recirculation loops are in operation, THEN :
: 3) IF percent of total rated core flow from STEP 3.e.1) is <70%,
THEN is the Jet Pump Flow Mismatch from STEP 3.e.2) 10%?
Yes          No          N/A Standard:                  Determines this step is N/A.
Evaluator Cue:             None Performance:               SATISFACTORY           UNSATISFACTORY Comments:
M/jlg Page 7 of 14


QF-1030-11 Rev. 2 (FP-T-SAT-30)
QF-1030-11 Rev. 2 (FP-T-SAT-30)
JPM-0133-001 (DAILY JET PUMP OPERABILITY CHECK TEST 0133) Rev.0 M/jlg Page 7 of 14 Performance Step: 7 Critical:  Y IF in MODE 1 or 2, AND both recirculation loops are in operation, THEN :  1) Calculate percent of total rated core flow (M + N) 86.8-90.4%    Standard:
JPM-0133-001 (DAILY JET PUMP OPERABILITY CHECK TEST 0133) Rev.0 Performance Step: 10      IF in MODE 1 or 2, Critical: Y               AND both recirculation loops are in operation, THEN :
Calculates percent of total rated core flow.
: 4) IF percent of total rated core flow from STEP 3.e.1) is 70%,
Evaluator Cue:
THEN is the Jet Pump Flow Mismatch from STEP 3.e.2) 5%?
None  Performance: SATISFACTORY UNSATISFACTORY Comments:
Yes         No         N/A Standard:                 Determines Jet Pump Flow Mismatch is 5%.
Performance Step:  8 Critical: Y IF in MODE 1 or 2, AND both recirculation loops are in operation, THEN : 2) Calculate absolute value (M - N), Jet Pump Flow Mismatch _
Evaluator Cue:             None Performance:               SATISFACTORY           UNSATISFACTORY Comments:
0-1.8__%    Standard:
Performance Step: 11       IF any question in STEP 3.e. is checked No, Critical: N                THEN notify Control Room Supervisor, AND evaluate Tech Spec 3.4.1 and enter appropriate Condition.
Calculates absolute value.
Standard:                 Determines no step is No.
Evaluator Cue:
Evaluator Cue:             None Performance:               SATISFACTORY           UNSATISFACTORY Comments:
None  Performance: SATISFACTORY UNSATISFACTORY Comments:
Performance Step: 12       IF the Reactor is in MODE 1, Critical: Y                AND there is recirculation flow, THEN perform the following:
Performance Step:  9 Critical:  N IF in MODE 1 or 2, AND both recirculation loops are in operation, THEN :  3) IF percent of total rated core flow from STEP 3.e.1) is <70%, THEN is the Jet Pump Flow Mismatch from STEP 3.e.2)  10%?  Yes  No  N/A    Standard:
: a. From FPR-2-3-95 (C-04), Core dP Red Pen, record dP: (14-14.5)
Determines this step is N/A.
: b. Record the square root of Core dP (from a. above): (3.7-3.81)
Evaluator Cue:
: c. From CRT mimic obtain and record Core Flow: (50.5-51.5 X 106)
None  Performance: SATISFACTORY UNSATISFACTORY Comments:
: d. Calculate and record 100 x (c. &#xf7; 57.6 x106 lb/hr): (87.5-89.5)
 
QF-1030-11  Rev. 2  (FP-T-SAT-30)
JPM-0133-001 (DAILY JET PUMP OPERABILITY CHECK TEST 0133) Rev.0 M/jlg Page 8 of 14 Performance Step:  10 Critical:  Y IF in MODE 1 or 2, AND both recirculation loops are in operation, THEN :  4) IF percent of total rated core flow from STEP 3.e.1) is  70%, THEN is the Jet Pump Flow Mismatch from STEP 3.e.2) 5%?   Yes No N/A   Standard:
Determines Jet Pump Flow Mismatch is 5%. Evaluator Cue:
None   Performance: SATISFACTORY UNSATISFACTORY Comments:
Performance Step: 11 Critical:  N IF any question in STEP 3.e. is checked "No", THEN notify Control Room Supervisor, AND evaluate Tech Spec 3.4.1 and enter appropriate Condition.
Standard:
Determines no step is "No".
Evaluator Cue:
None   Performance: SATISFACTORY UNSATISFACTORY Comments:
Performance Step: 12 Critical:  Y IF the Reactor is in MODE 1, AND there is recirculation flow, THEN perform the following: a. From FPR-2-3-95 (C-04), Core dP Red Pen, record dP:
(14-14.5) b. Record the square root of Core dP (from a. above):
(3.7-3.81)
: c. From CRT mimic obtain and record Core Flow: (50.5-51.5 X 10
: 6) d. Calculate and record 100 x (c. &#xf7; 57.6 x10 6 lb/hr):
(87.5-89.5)
: e. On Figure 20 Core Plate dP vs Core Flow, of Ops Man B.01.04-06 plot point for value of b. vs d. above.
: e. On Figure 20 Core Plate dP vs Core Flow, of Ops Man B.01.04-06 plot point for value of b. vs d. above.
Standard:
Standard:                 Obtains and records the above data.
Obtains and records the above data.
Evaluator Cue:             None Performance:               SATISFACTORY           UNSATISFACTORY Comments:
Evaluator Cue:
M/jlg Page 8 of 14
None   Performance: SATISFACTORY UNSATISFACTORY Comments:  


QF-1030-11 Rev. 2 (FP-T-SAT-30)
QF-1030-11 Rev. 2 (FP-T-SAT-30)
JPM-0133-001 (DAILY JET PUMP OPERABILITY CHECK TEST 0133) Rev.0 M/jlg Page 9 of 14 Performance Step: 13 Critical:  Y On figure 20 Core Plate dP vs. Core Flow, of Ops Man B.01.04-06 plot point for value b. vs. d. above.
JPM-0133-001 (DAILY JET PUMP OPERABILITY CHECK TEST 0133) Rev.0 Performance Step: 13       On figure 20 Core Plate dP vs. Core Flow, of Ops Man B.01.04-06 plot point for Critical: Y                value b. vs. d. above.
: 1) Does point for b. vs. d fall in ACCEPTABLE RANGE?
: 1) Does point for b. vs. d fall in ACCEPTABLE RANGE?
Yes          No
Yes          No
: 2) IF No, THEN notify Shift Supervision to determine actions and notifications.
: 2) IF No, THEN notify Shift Supervision to determine actions and notifications.
Standard:
Standard:                 Plots points and determines values are in the acceptable range.
Plots points and determines values are in the acceptable range.
Evaluator Cue:             None Performance:               SATISFACTORY           UNSATISFACTORY Comments:
Evaluator Cue:
Performance Step: 14       IF the Reactor is in MODE 1, Critical: N                AND THERMAL POWER >25% RTP with a recirculation loop in operation, THEN from FR-7288, JET PUMP FLOW RECORDER (Panel C-38), record individual Jet Pump and loop average dPs in the matrix below and perform the following:
None   Performance: SATISFACTORY UNSATISFACTORY Comments:
Loop A                                  Loop B Jet        Raw      DP/Loop            Jet        Raw      DP/Loop Pump          dP          Avg            Pump          dP        Avg 11          8.8          1                1        8.8          1 12          8.8          1                2        8.6        0.93 13          8.7        0.96              3        8.7        0.96 14          8.8          1                4        8.9        1.03 15          8.6        0.93              5        8.7        0.96 16          8.9        1.03              6        8.8          1 17          8.8          1                7        8.7        0.96 18          8.7        0.96              8        8.6        0.93 19          8.8          1                9        8.7        0.96 20          8.6        0.93              10        8.7        0.96 Loop          8.8                        Loop        8.8 Avg dP                                    Avg dP Standard:                  Records data provided.
Performance Step: 14 Critical:  N IF the Reactor is in MODE 1, AND THERMAL POWER >25% RTP with a recirculation loop in operation, THEN from FR-7288, JET PUMP FLOW RECORDER (Panel C-38), record individual Jet Pump and loop average dPs in the matrix below and perform the  
Evaluator Cue:            Iindividual Jet Pump Raw dP data has been provided.
Performance:              SATISFACTORY            UNSATISFACTORY Comments:
M/jlg Page 9 of 14


following:
QF-1030-11 Rev. 2 (FP-T-SAT-30)
 
JPM-0133-001 (DAILY JET PUMP OPERABILITY CHECK TEST 0133) Rev.0 Performance Step: 15       For each loop divide each individual Jet Pump raw dP by its Loop Average dP and Critical: N                record in matrix.
Loop A  Loop B Jet Pump Raw dP DP/Loop Avg  Jet Pump Raw dP DP/Loop Avg 11 8.8 1  1 8.8 1 12 8.8 1  2 8.6 0.93 13 8.7 0.96  3 8.7 0.96 14 8.8 1  4 8.9 1.03 15 8.6 0.93  5 8.7 0.96 16 8.9 1.03  6 8.8 1 17 8.8 1  7 8.7 0.96 18 8.7 0.96  8 8.6 0.93 19 8.8 1  9 8.7 0.96 20 8.6 0.93  10 8.7 0.96 Loop Avg dP 8.8  Loop Avg dP 8.8    Standard:
Standard:                 Divides and records in matrix.
Records data provided.
Evaluator Cue:             None Performance:               SATISFACTORY           UNSATISFACTORY Comments:
Evaluator Cue:
Performance Step: 16       IF the Reactor is in MODE 1, Critical: Y                AND Recirc Pump speed (SI-2-184-16A&B on C04) >50%,
Iindividual Jet Pump Raw dP data has been provided.
THEN perform the following:
Performance: SATISFACTORY UNSATISFACTORY Comments:
: a. Record 2-184-23A (C04), A Pump Volts, indication: (3050-3150Volts)
 
: b. Record 2-184-23B (C04), B Pump Volts, indication: (3100-3200 Volts)
QF-1030-11 Rev. 2 (FP-T-SAT-30)
: c. Record SI-2-184-16A, Recirc Pump 11 %Speed, indication: (85-87)
JPM-0133-001 (DAILY JET PUMP OPERABILITY CHECK TEST 0133) Rev.0 M/jlg Page 10 of 14 Performance Step: 15 Critical:  N For each loop divide each individual Jet Pump raw dP by its Loop Average dP and record in matrix.
: d. Record SI-2-184-16B, Recirc Pump 12 %Speed, indication: (85-87)
Standard:
: e. Record result of a. &#xf7; c.: (35.0-37.1) Volts/% Speed for 11(35.5 - 40.5)
Divides and records in matrix.
: f. Record result of b. &#xf7; d.: (35.6-37.7) Volts/% Speed for 12 (35.5 - 40.5)
Evaluator Cue:
Standard:                 Obtains and records above parameters.
None   Performance: SATISFACTORY UNSATISFACTORY Comments:
Evaluator Cue:             None Performance:               SATISFACTORY           UNSATISFACTORY Comments:
Performance Step: 16 Critical:  Y IF the Reactor is in MODE 1, AND Recirc Pump speed (SI-2-184-16A&B on C04) >50%, THEN perform the following: a. Record 2-184-23A (C04), A Pump Volts, indication:
Performance Step: 17       IF either acceptance criteria is not met, Critical: N*              THEN on Panel C-21from TR-2-184-26, RECIRC MG SET WINDING TEMP, and TR-2-2-31, RECIRC PUMP AND MTR TEMP, verify MG set generator and Recirc pump motor winding temperatures are normal and not unexpectedly trending up, AND notify Shift Supervision to determine actions and notifications.
(3050-3150Volts)
Standard:                 Determines acceptance criteria is met. *(This step is critical if step 16e above is calculated to not meet acceptance criteria).
: b. Record 2-184-23B (C04), B Pump Volts, indication:
Evaluator Cue:             None Performance:               SATISFACTORY           UNSATISFACTORY Comments:
(3100-3200 Volts)
M/jlg Page 10 of 14
: c. Record SI-2-184-16A, Recirc Pump 11 %Speed, indication:
(85-87) d. Record SI-2-184-16B, Recirc Pump 12 %Speed, indication:
(85-87) e. Record result of a. &#xf7; c.:
(35.0-37.1)
Volts/% Speed for 11(35.5 - 40.5) f. Record result of b. &#xf7; d.:
(35.6-37.7)
Volts/% Speed for 12 (35.5 - 40.5)
Standard:
Obtains and records above parameters.
Evaluator Cue:
None   Performance: SATISFACTORY UNSATISFACTORY Comments:  
 
Performance Step: 17 Critical:  N*
IF either acceptance criteria is not met, THEN on Panel C-21from TR-2-184-26, RECIRC MG SET WINDING TEMP, and TR-2-2-31, RECIRC PUMP AND MTR TEMP, verify MG set generator and Recirc  
 
pump motor winding temperatures are normal and not unexpectedly trending up, AND notify Shift Supervision to determine actions and notifications.
Standard:
Determines acceptance criteria is met. *(This step is critical if step 16e above is calculated to not meet acceptance criteria).
Evaluator Cue:
None   Performance: SATISFACTORY UNSATISFACTORY Comments:  
 
QF-1030-11  Rev. 2  (FP-T-SAT-30)
JPM-0133-001 (DAILY JET PUMP OPERABILITY CHECK TEST 0133) Rev.0 M/jlg Page 11 of 14 Performance Step:  18 Critical:  N INFORM EVALUATOR THAT THE TASK HAS BEEN COMPLETED.
Standard:
Operator informs evaluator that the task is completed.
Evaluator Cue:
Acknowledge report of task completion.
Performance: SATISFACTORY UNSATISFACTORY Comments:
Terminating Cues:
 
AFTER TASK COMPLETION REPORT IS MADE, STATE THAT THE JPM IS COMPLETE.


QF-1030-11 Rev. 2 (FP-T-SAT-30)
JPM-0133-001 (DAILY JET PUMP OPERABILITY CHECK TEST 0133) Rev.0 Performance Step: 18      INFORM EVALUATOR THAT THE TASK HAS BEEN COMPLETED.
Critical: N Standard:                  Operator informs evaluator that the task is completed.
Evaluator Cue:            Acknowledge report of task completion.
Performance:              SATISFACTORY          UNSATISFACTORY Comments:
Terminating Cues:      AFTER TASK COMPLETION REPORT IS MADE, STATE THAT THE JPM IS COMPLETE.
Stop Time:
Stop Time:
Critical Time
Critical Time ___N/A____
___N/A____
M/jlg Page 11 of 14
QF-1030-11  Rev. 2  (FP-T-SAT-30)
JPM-0133-001 (DAILY JET PUMP OPERABILITY CHECK TEST 0133) Rev.0 M/jlg Page 12 of 14 TURNOVER SHEET INITIAL CONDITIONS:  The reactor is operating at power  You are the BOP operator INITIATING CUES (IF APPLICABLE):  The CRS directs you to perform Test 0133, Daily Jet Pu mp Operability Check per Operations Daily Log - Part B
QF-1030-11 Rev. 2  (FP-T-SAT-30)
M/jlg Page 13 of 14 SIMULATOR SET UP:
IC-15 or other 100% power IC.
 
SIMULATOR - MALFUNCTIONS:
 
MALF ID MALFUNCTION TITLE DELAY RAMP EVENT VALUE FINAL. 1.        2.       
 
SIMULATOR - OVERRIDES:
 
OVERRIDE ID.
OVERRIDE DESCRIPTION DELAY RAMP EVENT VALUE FINAL 1.        2.       


SIMULATOR - REMOTE FUNCTIONS:  
QF-1030-11 Rev. 2 (FP-T-SAT-30)
JPM-0133-001 (DAILY JET PUMP OPERABILITY CHECK TEST 0133) Rev.0 TURNOVER SHEET INITIAL CONDITIONS:
* The reactor is operating at power
* You are the BOP operator INITIATING CUES (IF APPLICABLE):
* The CRS directs you to perform Test 0133, Daily Jet Pump Operability Check per Operations Daily Log - Part B
M/jlg Page 12 of 14


REMOTE FUNC. No.
QF-1030-11 Rev. 2 (FP-T-SAT-30)
REMOTE FUNCTION TITLE DELAY RAMP EVENT VALUE FINAL 1.       2.      
SIMULATOR SET UP:
* IC-15 or other 100% power IC.
SIMULATOR - MALFUNCTIONS:
MALF ID    MALFUNCTION TITLE            DELAY    RAMP    EVENT  VALUE  FINAL.
1.
2.
SIMULATOR - OVERRIDES:
OVERRIDE ID.              OVERRIDE      DELAY  RAMP  EVENT  VALUE  FINAL DESCRIPTION 1.
2.
SIMULATOR - REMOTE FUNCTIONS:
REMOTE        REMOTE FUNCTION TITLE     DELAY   RAMP   EVENT VALUE   FINAL FUNC. No.
1.
2.
M/jlg Page 13 of 14


QF-1030-11 Rev. 2 (FP-T-SAT-30)
QF-1030-11 Rev. 2 (FP-T-SAT-30)
JPM-0133-001 (DAILY JET PUMP OPERABILITY CHECK TEST 0133) Rev.0 M/jlg Page 14 of 14 ATTACHMENT 1 JOB PERFORMANCE MEASURE VALIDATION CHECKLIST ALL STEPS IN THIS CHECKLIST ARE TO BE PERFORMED UPON INITIAL VALIDATION AND PRIOR TO USE.
JPM-0133-001 (DAILY JET PUMP OPERABILITY CHECK TEST 0133) Rev.0 ATTACHMENT 1 JOB PERFORMANCE MEASURE VALIDATION CHECKLIST ALL STEPS IN THIS CHECKLIST ARE TO BE PERFORMED UPON INITIAL VALIDATION AND PRIOR TO USE.
REVIEW STATEMENTS YES NO N/A 1. Are all items on the signature page filled in correctly?
REVIEW STATEMENTS                                                           YES       NO       N/A
: 1. Are all items on the signature page filled in correctly?
: 2. Has the JPM been reviewed and validated by SMEs?
: 2. Has the JPM been reviewed and validated by SMEs?
: 3. Can the required conditions for the JPM be appropriately established in the simulator if required?
: 3. Can the required conditions for the JPM be appropriately established in the simulator if required?
: 4. Does the performance steps accurately reflect trainee's actions in accordance with plant procedures?
: 4. Does the performance steps accurately reflect trainees actions in accordance with plant procedures?
: 5. Is the standard for each performance item specific as to what controls, indications and ranges are required to evaluate if the  
: 5. Is the standard for each performance item specific as to what controls, indications and ranges are required to evaluate if the trainee properly performed the step?
 
trainee properly performed the step?
: 6. Has the completion time been established based on validation data or incumbent experience?
: 6. Has the completion time been established based on validation data or incumbent experience?
: 7. If the task is time critical, is the time critical portion based upon actual task performance requirements?
: 7. If the task is time critical, is the time critical portion based upon actual task performance requirements?
Line 776: Line 627:
Sequence / Time Critical) appropriately?
Sequence / Time Critical) appropriately?
: 11. Have all special tools and equipment needed to perform the task been identified and made available to the trainee?
: 11. Have all special tools and equipment needed to perform the task been identified and made available to the trainee?
: 12. Are all references identified, current, accurate, and available to the trainee?   13. Have all required cues (as anticipated) been identified for the evaluator to assist task completion?
: 12. Are all references identified, current, accurate, and available to the trainee?
All questions/statements must be answered "YES" or the JPM is not valid for use. If all questions/statements  
: 13. Have all required cues (as anticipated) been identified for the evaluator to assist task completion?
 
All questions/statements must be answered YES or the JPM is not valid for use. If all questions/statements are answered YES then the JPM is considered valid and can be performed as written. The individual(s) performing the validation SHALL sign and date this form.
are answered "YES" then the JPM is considered valid and can be performed as written. The individual(s) performing the validation SHALL sign and date this form.
__________________________                   __________________________
__________________________         __________________________
Validation Personnel /Date                   Validation Personnel/Date
Validation Personnel /Date                 Validation Personnel/Date
__________________________                   __________________________
__________________________         __________________________  
Validation Personnel /Date                   Validation Personnel/Date
 
__________________________                   __________________________
Validation Personnel /Date                 Validation Personnel/Date
Validation Personnel /Date                   Validation Personnel/Date
__________________________         __________________________  
__________________________                   __________________________
 
Validation Personnel /Date                   Validation Personnel/Date Historical Record: (Optional)
Validation Personnel /Date                 Validation Personnel/Date
M/jlg Page 14 of 14
__________________________         __________________________  
 
Validation Personnel /Date                 Validation Personnel/Date Historical Record: (Optional)  
 
QF-1030-11  Rev. 2  (FP-T-SAT-30)
Retention: Life of policy + 10yrs. Disposition: Reviewer and Approver Retain in:  Training Program File M/jlg Page 1 of 10 JOB PERFORMANCE MEASURE (JPM)
SITE: MONTICELLO NUCLEAR GENERATING PLANT JPM TITLE:
DAILY JET PUMP OPERABILITY CHECK TEST 0133 JPM NUMBER:
JPM-0133-002 REV. 0  RELATED PRA
 
INFORMATION:
None  TASK NUMBER(S) /


TASK TITLE(S):
QF-1030-11 Rev. 2 (FP-T-SAT-30)
CR299.349 Perform Operations Daily Log - Parts A, B, D, E, G, H, & J K/A NUMBERS:
JOB PERFORMANCE MEASURE (JPM)
2.1.12 Rating: SRO/RO:
SITE:                      MONTICELLO NUCLEAR GENERATING PLANT JPM TITLE:                DAILY JET PUMP OPERABILITY CHECK TEST 0133 JPM NUMBER:                JPM-0133-002                                REV.        0 RELATED PRA                None INFORMATION:
3.4/3.0 APPLICABLE METHOD OF TESTING:
TASK NUMBER(S) /          CR299.349 TASK TITLE(S):            Perform Operations Daily Log - Parts A, B, D, E, G, H, & J K/A NUMBERS:           2.1.12                                   Rating: SRO/RO:       3.4/3.0 APPLICABLE METHOD OF TESTING:
Discussion:   Simulate/walkthrough:   Perform: X EVALUATION LOCATION:
Discussion:               Simulate/walkthrough:             Perform:   X EVALUATION LOCATION:             In-Plant:                         Control Room:
In-Plant:   Control Room:
Simulator:                 X       Other:
Simulator: X Other:
Lab:
Lab:       Time for Completion: 25 Minutes Time Critical: No     Alternate Path / Faulted: Yes TASK APPLICABILITY:
Time for Completion:           25     Minutes                 Time Critical:       No Alternate Path / Faulted:       Yes TASK APPLICABILITY:             SRO:       X       SRO/RO:               SRO/RO/NLO:
SRO: X SRO/RO: SRO/RO/NLO:
Additional signatures may be added as needed.
Additional signatures may be added as needed.
Developed by:
Developed by:                               J Ruth Instructor                               Date Validated by:
J Ruth   Instructor Date   Validated by:
Validation Instructor                          Date (See JPM Validation Checklist, Attachment 1)
Approved by:
Training Supervisor                            Date Retention: Life of policy + 10yrs.                                          Disposition: Reviewer and Approver Retain in: Training Program File M/jlg Page 1 of 10


Validation Instructor (See JPM Validation Checklist, Attachment 1)
QF-1030-11 Rev. 2 (FP-T-SAT-30)
Date    Approved by:
JPM-0133-002 (DAILY JET PUMP OPERABILITY CHECK TEST 0133) Rev.0 JPM Number: JPM-0133-002 JPM Title: Daily Jet Pump Operability Check Test 0133 Examinee:                                             Evaluator:
 
Job Title:                                               Date:
Training Supervisor Date QF-1030-11 Rev. 2 (FP-T-SAT-30)
Start Time                                         Finish Time PERFORMANCE RESULTS:                           SAT:                   UNSAT:
JPM-0133-002 (DAILY JET PUMP OPERABILITY CHECK TEST 0133) Rev.0 M/jlg Page 2 of 10 JPM Number:
COMMENTS/FEEDBACK: (Comments shall be made for any steps graded unsatisfactory).
JPM-0133-002 JPM Title:
EVALUATORS SIGNATURE:
Daily Jet Pump Operability Check Test 0133 Examinee: Evaluator: Job Title: Date: Start Time Finish Time PERFORMANCE RESULTS:
NOTE: Only this page needs to be retained in examinees record if completed satisfactorily. If unsatisfactory performance is demonstrated, the entire JPM should be retained.
SAT: UNSAT:  
M/jlg Page 2 of 10
 
COMMENTS/FEEDBACK: (Comments shall be made for any steps graded unsatisfactory).  
 
EVALUATOR'S SIGNATURE:  
 
NOTE: Only this page needs to be retained in examinee's record if completed satisfactorily. If unsatisfactory performance is demonstrated, the entire JPM should be retained.
QF-1030-11  Rev. 2  (FP-T-SAT-30)
JPM-0133-002 (DAILY JET PUMP OPERABILITY CHECK TEST 0133) Rev.0 M/jlg Page 3 of 10 JPM BRIEFING/TURNOVER (See MTCP-03.32, Figure 6.2)
I will explain the initial conditions, which step(s) to simulate or discuss, and provide initiating cues. When you
 
complete the task successfully, the objective for this job performance measure will be satisfied.


QF-1030-11 Rev. 2 (FP-T-SAT-30)
JPM-0133-002 (DAILY JET PUMP OPERABILITY CHECK TEST 0133) Rev.0 JPM BRIEFING/TURNOVER (See MTCP-03.32, Figure 6.2)
I will explain the initial conditions, which step(s) to simulate or discuss, and provide initiating cues. When you complete the task successfully, the objective for this job performance measure will be satisfied.
DURING THE JPM, ENSURE PROPER SAFETY PRECAUTIONS, FME, AND/OR RADIOLOGICAL CONCERNS AS APPLICABLE ARE FOLLOWED.
DURING THE JPM, ENSURE PROPER SAFETY PRECAUTIONS, FME, AND/OR RADIOLOGICAL CONCERNS AS APPLICABLE ARE FOLLOWED.
INITIAL CONDITIONS: The reactor is operating at power Test 0133, Daily Jet Pump Operability Check per Operations Daily Log - Part B has been completed by the RO You are the CRS INITIATING CUES (IF APPLICABLE):   Review for satisfactoy completion of the provided Test 0133, Daily Jet Pump Operability Check per Operations Daily Log - Part B  
INITIAL CONDITIONS:
* The reactor is operating at power
* Test 0133, Daily Jet Pump Operability Check per Operations Daily Log - Part B has been completed by the RO
* You are the CRS INITIATING CUES (IF APPLICABLE):
* Review for satisfactoy completion of the provided Test 0133, Daily Jet Pump Operability Check per Operations Daily Log - Part B M/jlg Page 3 of 10


QF-1030-11 Rev. 2 (FP-T-SAT-30)
QF-1030-11 Rev. 2 (FP-T-SAT-30)
JPM-0133-002 (DAILY JET PUMP OPERABILITY CHECK TEST 0133) Rev.0 M/jlg Page 4 of 10 JPM PERFORMANCE INFORMATION  
JPM-0133-002 (DAILY JET PUMP OPERABILITY CHECK TEST 0133) Rev.0 JPM PERFORMANCE INFORMATION Required Materials:       Marked up copy of completed test, B.01.04-06 Figures 15, 16 & 17.
 
Required Materials:
Marked up copy of completed test, B.01.04-06 Figures 15, 16 & 17.
General  
General  


==References:==
==References:==
Simulator IC at 100% power.
Simulator IC at 100% power.
Task Standards:
Task Standards:           Perform a supervisory review of the daily Jet Pump Operability Test.
Perform a supervisory review of the daily Jet Pump Operability Test. Start Time:
Start Time:
NOTE: When providing "Evaluator Cues" to the examinee, care must be exercised to avoid prompting the examinee. Typically cues are only provided when the examinee's actions warrant receiving the information (i.e. the examinee looks or asks for the indication).
NOTE: When providing Evaluator Cues to the examinee, care must be exercised to avoid prompting the examinee. Typically cues are only provided when the examinees actions warrant receiving the information (i.e. the examinee looks or asks for the indication).
NOTE: Critical steps are marked with a "Y" below the performance step number. Failure to meet the standard for any critical step shall result in failure of this JPM.
NOTE: Critical steps are marked with a Y below the performance step number. Failure to meet the standard for any critical step shall result in failure of this JPM.
Performance Step: 1 Critical:  N NOTE: STEP 3.b. and 3.c. not required to be performed until [[estimated NRC review hours::4 hours]] after associated recirculation loop is in operation and until [[estimated NRC review hours::24 hours]] after THERMAL POWER >25% RTP.
Performance Step: 1           NOTE: STEP 3.b. and 3.c. not required to be performed until [[estimated NRC review hours::4 hours]] after Critical: N                    associated recirculation loop is in operation and until [[estimated NRC review hours::24 hours]] after THERMAL POWER >25% RTP.
IF the Reactor is in MODE 1 or 2, AND recirculation loop(s) is in operation, THEN obtain and record the values for the operating loop(s) described in the matrices below and perform the following:  
IF the Reactor is in MODE 1 or 2, AND recirculation loop(s) is in operation, THEN obtain and record the values for the operating loop(s) described in the matrices below and perform the following:
Variable    Panel                  Item Description            Value      Unit CRT      RPV501, Core Thermal Power %              99.9      %
A        C-04    SI-2-184-16A, Recirc Pump 11 %Speed        94        %
B        C-04    SI-2-184-16B, Recirc Pump 11 %Speed        96        %
C        C-04    FI-2-159A, Recirc Loop 11 Flow          25 x 103    gpm D        C-04    FI-2-159B, Recirc Loop 12 Flow          27 x 103    gpm Standard:                      Reviews the above data.
Evaluator Cue:                  None Performance:                  SATISFACTORY            UNSATISFACTORY Comments:
M/jlg Page 4 of 10


Variable Panel Item Description Value Unit  CRT RPV501, Core Thermal Power % 99.9 % A C-04 SI-2-184-16A, Recirc Pump 11 %Speed 94 % B C-04 SI-2-184-16B, Recirc Pump 11 %Speed 96 % C C-04 FI-2-159A, Recirc Loop 11 Flow 25 x 10 3 gpm D C-04 FI-2-159B, Recirc Loop 12 Flow 27 x 10 3 gpm    Standard:
QF-1030-11 Rev. 2 (FP-T-SAT-30)
Reviews the above data.
JPM-0133-002 (DAILY JET PUMP OPERABILITY CHECK TEST 0133) Rev.0 Performance Step: 2        On Figure 17, Recirculation Pump Flow vs Speed, of Ops Man B.01.04-06 Critical: Y                (REACTOR RECIRCULATION SYSTEM - FIGURES) plot points for values of variables A vs C and variables B vs D.
Evaluator Cue:
: 1) Does point A vs C fall in ACCEPTABLE RANGE?
None   Performance: SATISFACTORY UNSATISFACTORY Comments:  
Yes        No
: 2) Does point B vs D fall in ACCEPTABLE RANGE?
Yes          No Standard:                  Reviews points and determines 1) is NOT in the acceptable range and 2) is in the acceptable range.
Evaluator Cue:            None Performance:              SATISFACTORY          UNSATISFACTORY Comments:
Performance Step: 3 Critical: N                  Variable    Panel                Item Description          Value        Unit E        C-04     FI-2-3-92B, Jet Pump Loop A Flow   24.9 x 106    lb/hr F        C-04     FI-2-3-92A, Jet Pump Loop B Flow    26.1 x 106    lb/hr G        calc    (E &#xf7; L) X 100, % Loop A Flow          86.5          %
H        calc    (F &#xf7; L) X 100, % Loop B Flow          90.6          %
J        calc    (G &#xf7; A) X 100, % Loop Flow / %        0.92        ratio Pump Speed K        calc    (H &#xf7; B) X 100, % Loop Flow / %        0.94        ratio Pump Speed L=Constant            Half of rated Core Flow            28.8 x 106    lb/hr M        calc    (E&#xf7;(L x 2)) x 100%, % Core Flow        43.2          %
N        calc    (F&#xf7;(L x 2)) x 100%, % Core Flow        45.3         %
Standard:                 Reviews the above data.
Evaluator Cue:             None Performance:               SATISFACTORY           UNSATISFACTORY Comments:
M/jlg Page 5 of 10


QF-1030-11 Rev. 2 (FP-T-SAT-30)
QF-1030-11 Rev. 2 (FP-T-SAT-30)
JPM-0133-002 (DAILY JET PUMP OPERABILITY CHECK TEST 0133) Rev.0 M/jlg Page 5 of 10 Performance Step: 2 Critical:  Y On Figure 17, Recirculation Pump Flow vs Speed, of Ops Man B.01.04-06 (REACTOR RECIRCULATION SYSTEM - FIGURES) plot points for values of
JPM-0133-002 (DAILY JET PUMP OPERABILITY CHECK TEST 0133) Rev.0 Performance Step: 4       IF THERMAL POWER IS >25% RTP, Critical: Y                THEN on Figure 15, Loop A: Jet Pump Loop Flow/Pump Speed, of Ops Man B.01.04-06 plot points for values of variables J vs A.
 
variables A vs C and variables B vs D. 1) Does point A vs C fall in ACCEPTABLE RANGE?
 
Yes       No  2) Does point B vs D fall in ACCEPTABLE RANGE?
 
Yes        No    Standard:
Reviews points and determines 1) is NOT in the acceptable range and 2) is in the acceptable range.
Evaluator Cue:
None  Performance: SATISFACTORY UNSATISFACTORY Comments:
Performance Step:  3 Critical:  N Variable Panel Item Description Value Unit E C-04 FI-2-3-92B, Jet Pump Loop A Flow 24.9 x 10 6 lb/hr F C-04 FI-2-3-92A, Jet Pump Loop B Flow  26.1 x 10 6 lb/hr G calc (E &#xf7; L) X 100, % Loop A Flow 86.5 % H calc (F &#xf7; L) X 100, % Loop B Flow 90.6 % J calc (G &#xf7; A) X 100, % Loop Flow / %
Pump Speed 0.92 ratio K calc (H &#xf7; B) X 100, % Loop Flow / %
Pump Speed 0.94 ratio L=Constant Half of rated Core Flow 28.8  x 10 6 lb/hr M calc (E&#xf7;(L x 2)) x 100%, % Core Flow 43.2 % N calc (F&#xf7;(L x 2)) x 100%, % Core Flow 45.3 %
Standard:
Reviews the above data.
Evaluator Cue:
None  Performance: SATISFACTORY UNSATISFACTORY Comments:
 
QF-1030-11  Rev. 2  (FP-T-SAT-30)
JPM-0133-002 (DAILY JET PUMP OPERABILITY CHECK TEST 0133) Rev.0 M/jlg Page 6 of 10 Performance Step:  4 Critical:  Y IF THERMAL POWER IS >25% RTP, THEN on Figure 15, Loop A: Jet Pump Loop Flow/Pump Speed, of Ops Man B.01.04-06 plot points for values of variables J vs A.
: 1) Does point J vs A fall in ACCEPTABLE RANGE?
: 1) Does point J vs A fall in ACCEPTABLE RANGE?
Yes No N/A   Standard:
Yes           No         N/A Standard:                 Review points and determines values are NOT in the acceptable range.
Review points and determines values are NOT in the acceptable range.
Evaluator Cue:             If informed, acknowledge that point does not fall within the acceptable range.
Evaluator Cue:
Performance:               SATISFACTORY           UNSATISFACTORY Comments:
If informed, acknowledge that point does not fall within the acceptable range.
Performance Step: 5       IF THERMAL POWER IS >25% RTP, Critical: Y                THEN on Figure 16, Loop B: Jet Pump Loop Flow/Pump Speed, of Ops Man B.01.04-06 plot points for values of variables K vs B.
Performance: SATISFACTORY UNSATISFACTORY Comments:
Performance Step: 5 Critical:  Y IF THERMAL POWER IS >25% RTP, THEN on Figure 16, Loop B: Jet Pump Loop Flow/Pump Speed, of Ops Man B.01.04-06 plot points for values of variables K vs B.
: 1) Does point K vs B fall in ACCEPTABLE RANGE?
: 1) Does point K vs B fall in ACCEPTABLE RANGE?
Yes No N/A   Standard:
Yes         No           N/A Standard:                 Reviews points and determines values are NOT in the acceptable range.
Reviews points and determines values are NOT in the acceptable range.
Evaluator Cue:             If informed, acknowledge that point does not fall within the acceptable range.
Evaluator Cue:
Performance:               SATISFACTORY           UNSATISFACTORY Comments:
If informed, acknowledge that point does not fall within the acceptable range.
Performance Step: 6       IF any question in STEPs 3.a. through 3.c. is checked No, Critical: Y                THEN notify Control Room Supervisor, AND perform procedure 0442 (SPECIAL JET PUMP OPERABILITY TEST).
Performance: SATISFACTORY UNSATISFACTORY Comments:
Standard:                 When informed, acknowledge that performance of procedure 0442 is required and state that the JPM is complete.
Performance Step: 6 Critical:  Y IF any question in STEPs 3.a. through 3.c. is checked "No", THEN notify Control Room Supervisor, AND perform procedure 0442 (SPECIAL JET PUMP OPERABILITY TEST).  
Evaluator Cue:             None Performance:               SATISFACTORY           UNSATISFACTORY Comments:
 
M/jlg Page 6 of 10
Standard:
When informed, acknowledge that performance of procedure 0442 is required and state that the JPM is complete.
Evaluator Cue:
None   Performance: SATISFACTORY UNSATISFACTORY Comments:  
 
QF-1030-11  Rev. 2  (FP-T-SAT-30)
JPM-0133-002 (DAILY JET PUMP OPERABILITY CHECK TEST 0133) Rev.0 M/jlg Page 7 of 10  


Terminating Cues:  
QF-1030-11 Rev. 2 (FP-T-SAT-30)
 
JPM-0133-002 (DAILY JET PUMP OPERABILITY CHECK TEST 0133) Rev.0 Terminating Cues:     EVALUATOR INFORMS OPERATOR THAT THE JPM IS COMPLETE.
EVALUATOR INFORMS OPERATOR THAT THE JPM IS COMPLETE.
Stop Time:
Stop Time:
Critical Time
Critical Time ___N/A____
___N/A____
M/jlg Page 7 of 10
QF-1030-11  Rev. 2  (FP-T-SAT-30)
JPM-0133-002 (DAILY JET PUMP OPERABILITY CHECK TEST 0133) Rev.0 M/jlg Page 8 of 10 TURNOVER SHEET INITIAL CONDITIONS:  The reactor is operating at power  Test 0133, Daily Jet Pump Operability Check per Operations Daily Log - Part B has been completed by the RO  You are the CRS INITIATING CUES (IF APPLICABLE):  Review for satisfactoy completion of the provided Test 0133, Daily Jet Pump Operability Check per Operations Daily Log - Part B


QF-1030-11 Rev. 2 (FP-T-SAT-30)
QF-1030-11 Rev. 2 (FP-T-SAT-30)
M/jlg Page 9 of 10 SIMULATOR SET UP:
JPM-0133-002 (DAILY JET PUMP OPERABILITY CHECK TEST 0133) Rev.0 TURNOVER SHEET INITIAL CONDITIONS:
Admin JPM - no simulator setup is required.
* The reactor is operating at power
* Test 0133, Daily Jet Pump Operability Check per Operations Daily Log - Part B has been completed by the RO
* You are the CRS INITIATING CUES (IF APPLICABLE):
* Review for satisfactoy completion of the provided Test 0133, Daily Jet Pump Operability Check per Operations Daily Log - Part B M/jlg Page 8 of 10


SIMULATOR - MALFUNCTIONS:  
QF-1030-11 Rev. 2 (FP-T-SAT-30)
SIMULATOR SET UP:
* Admin JPM - no simulator setup is required.
SIMULATOR - MALFUNCTIONS:
MALF ID    MALFUNCTION TITLE                DELAY    RAMP    EVENT  VALUE  FINAL.
1.
2.
SIMULATOR - OVERRIDES:
OVERRIDE ID.            OVERRIDE          DELAY  RAMP  EVENT  VALUE  FINAL DESCRIPTION 1.
2.
SIMULATOR - REMOTE FUNCTIONS:
REMOTE        REMOTE FUNCTION TITLE          DELAY    RAMP  EVENT  VALUE  FINAL FUNC. No.
1.
2.
M/jlg Page 9 of 10


MALF ID MALFUNCTION TITLE DELAY RAMP EVENT VALUE FINAL. 1.        2.       
QF-1030-11 Rev. 2 (FP-T-SAT-30)
 
JPM-0133-001 (DAILY JET PUMP OPERABILITY CHECK TEST 0133) Rev.0 ATTACHMENT 1 JOB PERFORMANCE MEASURE VALIDATION CHECKLIST ALL STEPS IN THIS CHECKLIST ARE TO BE PERFORMED UPON INITIAL VALIDATION AND PRIOR TO USE.
SIMULATOR - OVERRIDES:
REVIEW STATEMENTS                                                           YES       NO       N/A
 
: 1. Are all items on the signature page filled in correctly?
OVERRIDE ID.
OVERRIDE DESCRIPTION DELAY RAMP EVENT VALUE FINAL 1.        2.       
 
SIMULATOR - REMOTE FUNCTIONS:
 
REMOTE FUNC. No.
REMOTE FUNCTION TITLE DELAY RAMP EVENT VALUE FINAL 1.        2.       
 
QF-1030-11 Rev. 2 (FP-T-SAT-30)
JPM-0133-001 (DAILY JET PUMP OPERABILITY CHECK TEST 0133) Rev.0 M/jlg Page 10 of 10 ATTACHMENT 1 JOB PERFORMANCE MEASURE VALIDATION CHECKLIST ALL STEPS IN THIS CHECKLIST ARE TO BE PERFORMED UPON INITIAL VALIDATION AND PRIOR TO USE.
REVIEW STATEMENTS YES NO N/A 1. Are all items on the signature page filled in correctly?
: 2. Has the JPM been reviewed and validated by SMEs?
: 2. Has the JPM been reviewed and validated by SMEs?
: 3. Can the required conditions for the JPM be appropriately established in the simulator if required?
: 3. Can the required conditions for the JPM be appropriately established in the simulator if required?
: 4. Does the performance steps accurately reflect trainee's actions in accordance with plant procedures?
: 4. Does the performance steps accurately reflect trainees actions in accordance with plant procedures?
: 5. Is the standard for each performance item specific as to what controls, indications and ranges are required to evaluate if the  
: 5. Is the standard for each performance item specific as to what controls, indications and ranges are required to evaluate if the trainee properly performed the step?
 
trainee properly performed the step?
: 6. Has the completion time been established based on validation data or incumbent experience?
: 6. Has the completion time been established based on validation data or incumbent experience?
: 7. If the task is time critical, is the time critical portion based upon actual task performance requirements?
: 7. If the task is time critical, is the time critical portion based upon actual task performance requirements?
Line 946: Line 767:
Sequence / Time Critical) appropriately?
Sequence / Time Critical) appropriately?
: 11. Have all special tools and equipment needed to perform the task been identified and made available to the trainee?
: 11. Have all special tools and equipment needed to perform the task been identified and made available to the trainee?
: 12. Are all references identified, current, accurate, and available to the trainee?   13. Have all required cues (as anticipated) been identified for the evaluator to assist task completion?
: 12. Are all references identified, current, accurate, and available to the trainee?
All questions/statements must be answered "YES" or the JPM is not valid for use. If all questions/statements  
: 13. Have all required cues (as anticipated) been identified for the evaluator to assist task completion?
 
All questions/statements must be answered YES or the JPM is not valid for use. If all questions/statements are answered YES then the JPM is considered valid and can be performed as written. The individual(s) performing the validation SHALL sign and date this form.
are answered "YES" then the JPM is considered valid and can be performed as written. The individual(s) performing the validation SHALL sign and date this form.
__________________________                   __________________________
__________________________         __________________________
Validation Personnel /Date                   Validation Personnel/Date
Validation Personnel /Date                 Validation Personnel/Date
__________________________                   __________________________
__________________________         __________________________  
Validation Personnel /Date                   Validation Personnel/Date
 
__________________________                   __________________________
Validation Personnel /Date                 Validation Personnel/Date
Validation Personnel /Date                   Validation Personnel/Date
__________________________         __________________________  
__________________________                   __________________________
 
Validation Personnel /Date                   Validation Personnel/Date Historical Record: (Optional)
Validation Personnel /Date                 Validation Personnel/Date
M/jlg Page 10 of 10
__________________________         __________________________  
 
Validation Personnel /Date                 Validation Personnel/Date Historical Record: (Optional)
 
QF-1030-11  Rev. 2  (FP-T-SAT-30)
M/jlg Page 1 of 10 JOB PERFORMANCE MEASURE (JPM)
SITE: MONTICELLO NUCLEAR GENERATING PLANT JPM TITLE:
LOCKED HIGH RADIATION AREA ENTRY JPM NUMBER:
JPM-4 AWI-08.04.06-002 REV. 0  RELATED PRA
 
INFORMATION:
None  TASK NUMBER(S) /
 
TASK TITLE(S):
CR999.299 ADMINISTRATIVE PROCEDURES K/A NUMBERS:  2.3.10   Rating: SRO/RO:
3.3/2.9  APPLICABLE METHOD OF TESTING:
Discussion:    Simulate/walkthrough: X  Perform:
EVALUATION LOCATION:
In-Plant:  Control Room:
Simulator:  Other: X Lab:      Time for Completion:  15 Minutes Time Critical:  NO      Alternate Path / Faulted: NO TASK APPLICABILITY:
SRO:  SRO/RO: SRO/RO/NLO: X Additional signatures may be added as needed.
Developed by:
J. Ruth  Instructor Date    Validated by:
 
Validation Instructor (See JPM Validation Checklist, Attachment 1)
Date    Approved by:
 
Training Supervisor Date QF-1030-11  Rev. 2  (FP-T-SAT-30)
JPM-4 AWI-08.04.06-002 (LOCKED HIGH RADIATION AREA ENTRY) Rev. 0 M/jlg Page 2 of 10 JPM Number:
JPM-4 AWI-08.04.06-002 JPM Title: LOCKED HIGH RADIATION AREA ENTRY  Examinee:  Evaluator: Job Title:  Date: Start Time  Finish Time PERFORMANCE RESULTS:
SAT: UNSAT:   
 
COMMENTS/FEEDBACK: (Comments shall be made for any steps graded unsatisfactory).


EVALUATOR'S SIGNATURE:  
QF-1030-11 Rev. 2 (FP-T-SAT-30)
JOB PERFORMANCE MEASURE (JPM)
SITE:                      MONTICELLO NUCLEAR GENERATING PLANT JPM TITLE:                LOCKED HIGH RADIATION AREA ENTRY JPM NUMBER:                JPM-4 AWI-08.04.06-002                      REV.        0 RELATED PRA                None INFORMATION:
TASK NUMBER(S) /          CR999.299 TASK TITLE(S):            ADMINISTRATIVE PROCEDURES K/A NUMBERS:            2.3.10                                    Rating: SRO/RO:      3.3/2.9 APPLICABLE METHOD OF TESTING:
Discussion:                Simulate/walkthrough:      X      Perform:
EVALUATION LOCATION:              In-Plant:                          Control Room:
Simulator:                        Other:                  X Lab:
Time for Completion:          15    Minutes                  Time Critical:      NO Alternate Path / Faulted:      NO TASK APPLICABILITY:              SRO:              SRO/RO:                SRO/RO/NLO:          X Additional signatures may be added as needed.
Developed by:                              J. Ruth Instructor                                Date Validated by:
Validation Instructor                          Date (See JPM Validation Checklist, Attachment 1)
Approved by:
Training Supervisor                            Date M/jlg Page 1 of 10


NOTE:  Only this page needs to be retained in examinee's record if completed satisfactorily. If unsatisfactory performance is demonstrated, the entire JPM should be retained.
QF-1030-11 Rev. 2 (FP-T-SAT-30)
QF-1030-11 Rev. 2 (FP-T-SAT-30)
JPM-4 AWI-08.04.06-002 (LOCKED HIGH RADIATION AREA ENTRY) Rev. 0 JPM Number: JPM-4 AWI-08.04.06-002 JPM Title: LOCKED HIGH RADIATION AREA ENTRY Examinee:                                            Evaluator:
JPM-4 AWI-08.04.06-002 (LOCKED HIGH RADIATION AREA ENTRY) Rev. 0 M/jlg Page 3 of 10 JPM BRIEFING/TURNOVER (See MTCP-03.32, Figure 6.2)
Job Title:                                                Date:
 
Start Time                                          Finish Time PERFORMANCE RESULTS:                            SAT:                    UNSAT:
I will explain the initial conditions, which step(s) to simulate or discuss, and provide initiating cues. When you
COMMENTS/FEEDBACK: (Comments shall be made for any steps graded unsatisfactory).
 
EVALUATORS SIGNATURE:
complete the task successfully, the objective for this job performance measure will be satisfied.  
NOTE: Only this page needs to be retained in examinees record if completed satisfactorily. If unsatisfactory performance is demonstrated, the entire JPM should be retained.
M/jlg Page 2 of 10


QF-1030-11 Rev. 2 (FP-T-SAT-30)
JPM-4 AWI-08.04.06-002 (LOCKED HIGH RADIATION AREA ENTRY) Rev. 0 JPM BRIEFING/TURNOVER (See MTCP-03.32, Figure 6.2)
I will explain the initial conditions, which step(s) to simulate or discuss, and provide initiating cues. When you complete the task successfully, the objective for this job performance measure will be satisfied.
DURING THE JPM, ENSURE PROPER SAFETY PRECAUTIONS, FME, AND/OR RADIOLOGICAL CONCERNS AS APPLICABLE ARE FOLLOWED.
DURING THE JPM, ENSURE PROPER SAFETY PRECAUTIONS, FME, AND/OR RADIOLOGICAL CONCERNS AS APPLICABLE ARE FOLLOWED.
INITIAL CONDITIONS:
INITIAL CONDITIONS:
The task conditions are as follows: The plant is at 100% power. The RWCU pump room must be entered and MO-2398 must be inspected for potential valve stem leakage. You are an extra operator on shift Provide Survey Map Provide RWP  
The task conditions are as follows:
* The plant is at 100% power.
* The RWCU pump room must be entered and MO-2398 must be inspected for potential valve stem leakage.
* You are an extra operator on shift
* Provide Survey Map
* Provide RWP INITIATING CUES (IF APPLICABLE):
The CRS directs you to perform the specific instructions per 4 AWI-08.04.06, section 4.4.2, for a non routine entry into the posted locked high radiation area for the inspection.
M/jlg Page 3 of 10


INITIATING CUES (IF APPLICABLE):
QF-1030-11 Rev. 2 (FP-T-SAT-30)
The CRS directs you to perform the specific instructions per 4 AWI-08.04.06, section 4.4.2, for a non routine entry into the posted locked high radiation area for the inspection.
JPM-4 AWI-08.04.06-002 (LOCKED HIGH RADIATION AREA ENTRY) Rev. 0 JPM PERFORMANCE INFORMATION Required Materials:       SURVEY MAP AND RWP FOR HI RADIATION AREA TO BE ENTERED General  
 
QF-1030-11 Rev. 2 (FP-T-SAT-30)
JPM-4 AWI-08.04.06-002 (LOCKED HIGH RADIATION AREA ENTRY) Rev. 0 M/jlg Page 4 of 10 JPM PERFORMANCE INFORMATION  
 
Required Materials:
SURVEY MAP AND RWP FOR HI RADIATION AREA TO BE ENTERED General  


==References:==
==References:==
4 AWI-08.04.06, AREA CONTROL Task Standards:            VERIFY INDIVIDUAL EXPOSURE LIMITS ALLOW ENTRY INTO LOCKED HIGH RADITION AREA Start Time:
NOTE: When providing Evaluator Cues to the examinee, care must be exercised to avoid prompting the examinee. Typically cues are only provided when the examinees actions warrant receiving the information (i.e. the examinee looks or asks for the indication).
NOTE: Critical steps are marked with a Y below the performance step number. Failure to meet the standard for any critical step shall result in failure of this JPM.
Performance Step: 1            Provided a copy of 4 AWI-08.04.06 (AREA CONTROL) reviews procedure and Critical: N                    locates Section 4.4.2 specific instructions for high, locked high, and very high radiation areas.
Standard:                      Locates appropriate section of procedure.
Evaluator Cue:                  Provide copy of procedure 4 AWI-08.04.06 (AREA CONTROL)
Performance:                    SATISFACTORY          UNSATISFACTORY Comments:
M/jlg Page 4 of 10


4 AWI-08.04.06, AREA CONTROL Task Standards:
QF-1030-11 Rev. 2 (FP-T-SAT-30)
VERIFY INDIVIDUAL EXPOSURE LIMITS ALLOW ENTRY INTO LOCKED HIGH RADITION AREA Start Time:
JPM-4 AWI-08.04.06-002 (LOCKED HIGH RADIATION AREA ENTRY) Rev. 0 Performance Step: 2        Specific instructions for high, locked high, and very high radiation areas.
NOTE: When providing "Evaluator Cues" to the examinee, care must be exercised to avoid prompting the examinee. Typically cues are only provided when the examinee's actions warrant receiving the information (i.e. the examinee looks or asks for the indication).
Critical: N Y                    A. Obtain any required special approvals as follows:
NOTE: Critical steps are marked with a "Y" below the performance step number. Failure to meet the standard for any critical step shall result in failure of this JPM.
: 1. Locked High Radiation Area:
Performance Step: 1 Critical: N Provided a copy of 4 AWI-08.04.06 (AREA CONTROL) reviews procedure and locates Section 4.4.2 specific instructions for high, locked high, and very high
[ NOTE: Post-Exam                            Non-routine entries your supervisor (if on site), the Shift review determined that                      Managers, or the Rad Prot Coords approval prior to the entry.
this step was a Critical                    Supervisors may approve their own entries.
Step ]
: 2. Very High Radiation Area You SHALL obtain written approval from the plant manager, which is based on a sound operational or safety reason.
Standard:                   Determines step is applicable.
Evaluator Cue:              If asked, state that the entry has been approved.
Performance:                SATISFACTORY            UNSATISFACTORY Comments:
Performance Step: 3        Obtain a high radiation area pre-entry briefing from the Radiation Protection staff.
Critical: N Y              This briefing and all high radiation area requirements of the RWP are required if any part of the body breaks the plane of the boundary, even if permission to reach
[ NOTE: Post-Exam          over was granted.
review determined that this step was a Critical Step ]
Standard:                  Determines that a radiological briefing must be performed.
Evaluator Cue:              State that the radiological briefing has been performed.
Performance:                SATISFACTORY            UNSATISFACTORY Comments:
M/jlg Page 5 of 10


radiation areas.
QF-1030-11 Rev. 2 (FP-T-SAT-30)
Standard:
JPM-4 AWI-08.04.06-002 (LOCKED HIGH RADIATION AREA ENTRY) Rev. 0 Performance Step: 4        Prepare to perform your individual exposure control duties as follows:
Locates appropriate section of procedure.
Critical: Y                      1. You SHALL determine the expected area does rates for all regions of the area you will be entering by reviewing area surveys.
Evaluator Cue:
Reviews areas surveys provided and determines the dose rate for the inspection is 1200 Mrem/hr at the valve and 180 Mrem/hr in the general vicinity of the valve.
Provide copy of procedure 4 AWI-08.04.06 (AREA CONTROL)
Standard:                  Determines dose rates will be 1200 Mrem/hr at the valve and 180 Mrem/hr in the general vicinity of the valve.
Performance: SATISFACTORY UNSATISFACTORY Comments:
Evaluator Cue:              None Performance:                SATISFACTORY            UNSATISFACTORY Comments:
Performance Step: 5        Prepare to perform your individual exposure control duties as follows:
Critical: Y                      2. Determine the expected duration of the entry and the expected dose needed to make the entry.
Operator determines expected dose using determined dose rate and given duration of entry.
Standard:                  Determines expected dose to be 138 Mrem.
Evaluator Cue:              State the expected duration of the entry is 6 minutes at the valve and an additional 6 minutes in the general vicinity of the valve.
Performance:                SATISFACTORY            UNSATISFACTORY Comments:
Performance Step: 6        Prepare to perform your individual exposure control duties as follows:
Critical: Y                      3. Determine the allowable entry dose, either from the electronic dosimeter log-in process, from the local point, or from your dosimeter.
Standard:                  Operator determines the dose alarm and dose rate alarm setpoints are too low for the performance of this task.
Evaluator Cue:              If reported, acknowledge the report.
Performance:               SATISFACTORY             UNSATISFACTORY Comments:
M/jlg Page 6 of 10


QF-1030-11 Rev. 2 (FP-T-SAT-30)
QF-1030-11 Rev. 2 (FP-T-SAT-30)
JPM-4 AWI-08.04.06-002 (LOCKED HIGH RADIATION AREA ENTRY) Rev. 0 M/jlg Page 5 of 10 Performance Step: 2 Critical: N Y
JPM-4 AWI-08.04.06-002 (LOCKED HIGH RADIATION AREA ENTRY) Rev. 0 Performance Step: 7        Prepare to perform your individual exposure control duties as follows:
[ NOTE: Post-Exam review determined that this step was a Critical
Critical: Y                     4. IF the allowable entry dose is less than the expected entry dose, THEN you SHALL report to the Rad Prot Coord for resolution.
 
Standard:                   Operator determines the allowable entry dose is less than the expected entry dose and reports to the Rad Prot Coord.
Step ] Specific instructions for high, locked high, and very high radiation areas.
Evaluator Cue:             Acknowledge report as the Rad Prot Coord.
A. Obtain any required special approvals as follows: 1. Locked High Radiation Area:
Performance:               SATISFACTORY           UNSATISFACTORY Comments:
Non-routine entries your supervisor (if on site), the Shift
Terminating Cues:     WHEN REPORT IS MADE, STATE THAT THE JPM IS COMPLETE.
 
Manager's, or the Rad Prot Coord's approval prior to the entry. 
 
Supervisors may approve their own entries. 2. Very High Radiation Area You SHALL obtain written approval from the plant manager, which is based on a sound operational or safety reason.
Standard:
Determines step is applicable.
Evaluator Cue:
If asked, state that the entry has been approved.
Performance: SATISFACTORY UNSATISFACTORY Comments:
Performance Step: 3 Critical: N Y
[ NOTE: Post-Exam review determined that this step was a Critical
 
Step ] Obtain  a high radiation area pre-entry briefing from the Radiation Protection staff.
This briefing and all high radiation area requirements of the RWP are required if
 
any part of the body breaks the plane of the boundary, even if permission to reach
 
over was granted.
Standard:
Determines that a radiological briefing must be performed.
Evaluator Cue:
State that the radiological briefing has been performed.
Performance: SATISFACTORY UNSATISFACTORY Comments:
 
QF-1030-11  Rev. 2  (FP-T-SAT-30)
JPM-4 AWI-08.04.06-002 (LOCKED HIGH RADIATION AREA ENTRY) Rev. 0 M/jlg Page 6 of 10 Performance Step: 4 Critical: Y Prepare to perform your individual exposure control duties as follows: 1. You SHALL determine the expected area does rates for all regions of the area you will be entering by reviewing area surveys.
 
Reviews areas surveys provided and determines the dose rate for the inspection is
 
1200 Mrem/hr at the valve and 180 Mrem/hr in the general vicinity of the valve.
Standard:
Determines dose rates will be 1200 Mrem/hr at the valve and 180 Mrem/hr in the general vicinity of the valve.
Evaluator Cue:
None  Performance: SATISFACTORY UNSATISFACTORY Comments:
Performance Step: 5 Critical: Y Prepare to perform your individual exposure control duties as follows: 2. Determine the expected duration of the entry and the expected dose needed to make the entry.
 
Operator determines expected dose using determined dose rate and given
 
duration of entry.
Standard:
Determines expected dose to be 138 Mrem.
Evaluator Cue:
State the expected duration of the entry is 6 minutes at the valve and an additional 6 minutes in the general vicinity of the valve.
Performance: SATISFACTORY UNSATISFACTORY Comments:
Performance Step: 6 Critical: Y Prepare to perform your individual exposure control duties as follows: 3. Determine the allowable entry dose, either from the electronic dosimeter log-in process, from the local point, or from your dosimeter.
 
Standard:
Operator determines the dose alarm and dose rate alarm setpoints are too low for the performance of this task.
Evaluator Cue:
If reported, acknowledge the report.
Performance: SATISFACTORY UNSATISFACTORY Comments:
 
QF-1030-11  Rev. 2  (FP-T-SAT-30)
JPM-4 AWI-08.04.06-002 (LOCKED HIGH RADIATION AREA ENTRY) Rev. 0 M/jlg Page 7 of 10 Performance Step: 7 Critical: Y Prepare to perform your individual exposure control duties as follows: 4. IF the allowable entry dose is less than the expected entry dose, THEN you SHALL report to the Rad Prot Coord for resolution.
Standard:
Operator determines the allowable entry dose is less than the expected entry dose and reports to the Rad Prot Coord.
Evaluator Cue:
Acknowledge report as the Rad Prot Coord.
Performance: SATISFACTORY UNSATISFACTORY Comments:  
 
Terminating Cues:  
 
WHEN REPORT IS MADE, STATE THAT THE JPM IS COMPLETE.
Stop Time:
Stop Time:
Critical Time
Critical Time ___N/A____
___N/A____
M/jlg Page 7 of 10
QF-1030-11  Rev. 2  (FP-T-SAT-30)
M/jlg Page 8 of 10 TURNOVER SHEET INITIAL CONDITIONS:
The task conditions are as follows:  The plant is at 100% power. The RWCU pump room must be entered and MO-2398 must be inspected for potential valve stem leakage. You are an extra operator on shift  Provide Survey Map  Provide RWP
 
INITIATING CUES (IF APPLICABLE):
The CRS directs you to perform the specific instructions per 4 AWI-08.04.06, section 4.4.2, for a non routine entry into the posted locked high radiation area for the inspection.
 
QF-1030-11  Rev. 2  (FP-T-SAT-30)
JPM-4 AWI-08.04.06-002 (LOCKED HIGH RADIATION AREA ENTRY) Rev. 0 M/jlg Page 9 of 10 SIMULATOR SET UP:
Admin JPM; no simulator setup required.
 
SIMULATOR - MALFUNCTIONS:
 
MALF ID MALFUNCTION TITLE DELAY RAMP EVENT VALUE FINAL. 1.        2.       
 
SIMULATOR - OVERRIDES:
 
OVERRIDE ID.
OVERRIDE DESCRIPTION DELAY RAMP EVENT VALUE FINAL 1.        2.       


SIMULATOR - REMOTE FUNCTIONS:  
QF-1030-11 Rev. 2 (FP-T-SAT-30)
TURNOVER SHEET INITIAL CONDITIONS:
The task conditions are as follows:
* The plant is at 100% power.
* The RWCU pump room must be entered and MO-2398 must be inspected for potential valve stem leakage.
* You are an extra operator on shift
* Provide Survey Map
* Provide RWP INITIATING CUES (IF APPLICABLE):
The CRS directs you to perform the specific instructions per 4 AWI-08.04.06, section 4.4.2, for a non routine entry into the posted locked high radiation area for the inspection.
M/jlg Page 8 of 10


REMOTE FUNC. No.
QF-1030-11 Rev. 2 (FP-T-SAT-30)
REMOTE FUNCTION TITLE DELAY RAMP EVENT VALUE FINAL 1.       2.      
JPM-4 AWI-08.04.06-002 (LOCKED HIGH RADIATION AREA ENTRY) Rev. 0 SIMULATOR SET UP:
Admin JPM; no simulator setup required.
SIMULATOR - MALFUNCTIONS:
MALF ID    MALFUNCTION TITLE              DELAY    RAMP    EVENT  VALUE  FINAL.
1.
2.
SIMULATOR - OVERRIDES:
OVERRIDE ID.              OVERRIDE      DELAY  RAMP  EVENT  VALUE  FINAL DESCRIPTION 1.
2.
SIMULATOR - REMOTE FUNCTIONS:
REMOTE        REMOTE FUNCTION TITLE       DELAY   RAMP   EVENT VALUE   FINAL FUNC. No.
1.
2.
M/jlg Page 9 of 10


QF-1030-11 Rev. 2 (FP-T-SAT-30)
QF-1030-11 Rev. 2 (FP-T-SAT-30)
JPM-4 AWI-08.04.06-002 (LOCKED HIGH RADIATION AREA ENTRY) Rev. 0 M/jlg Page 10 of 10 ATTACHMENT 1 JOB PERFORMANCE MEASURE VALIDATION CHECKLIST ALL STEPS IN THIS CHECKLIST ARE TO BE PERFORMED UPON INITIAL VALIDATION AND PRIOR TO USE.
JPM-4 AWI-08.04.06-002 (LOCKED HIGH RADIATION AREA ENTRY) Rev. 0 ATTACHMENT 1 JOB PERFORMANCE MEASURE VALIDATION CHECKLIST ALL STEPS IN THIS CHECKLIST ARE TO BE PERFORMED UPON INITIAL VALIDATION AND PRIOR TO USE.
REVIEW STATEMENTS YES NO N/A 1. Are all items on the signature page filled in correctly?
REVIEW STATEMENTS                                                           YES       NO       N/A
: 1. Are all items on the signature page filled in correctly?
: 2. Has the JPM been reviewed and validated by SMEs?
: 2. Has the JPM been reviewed and validated by SMEs?
: 3. Can the required conditions for the JPM be appropriately established in the simulator if required?
: 3. Can the required conditions for the JPM be appropriately established in the simulator if required?
: 4. Does the performance steps accurately reflect trainee's actions in accordance with plant procedures?
: 4. Does the performance steps accurately reflect trainees actions in accordance with plant procedures?
: 5. Is the standard for each performance item specific as to what controls, indications and ranges are required to evaluate if the  
: 5. Is the standard for each performance item specific as to what controls, indications and ranges are required to evaluate if the trainee properly performed the step?
 
trainee properly performed the step?
: 6. Has the completion time been established based on validation data or incumbent experience?
: 6. Has the completion time been established based on validation data or incumbent experience?
: 7. If the task is time critical, is the time critical portion based upon actual task performance requirements?
: 7. If the task is time critical, is the time critical portion based upon actual task performance requirements?
Line 1,144: Line 921:
Sequence / Time Critical) appropriately?
Sequence / Time Critical) appropriately?
: 11. Have all special tools and equipment needed to perform the task been identified and made available to the trainee?
: 11. Have all special tools and equipment needed to perform the task been identified and made available to the trainee?
: 12. Are all references identified, current, accurate, and available to the trainee?   13. Have all required cues (as anticipated) been identified for the evaluator to assist task completion?
: 12. Are all references identified, current, accurate, and available to the trainee?
All questions/statements must be answered "YES" or the JPM is not valid for use. If all questions/statements  
: 13. Have all required cues (as anticipated) been identified for the evaluator to assist task completion?
All questions/statements must be answered YES or the JPM is not valid for use. If all questions/statements are answered YES then the JPM is considered valid and can be performed as written. The individual(s) performing the validation shall sign and date this form.
__________________________                  __________________________
Validation Personnel /Date                  Validation Personnel/Date
__________________________                  __________________________
Validation Personnel /Date                  Validation Personnel/Date
__________________________                  __________________________
Validation Personnel /Date                  Validation Personnel/Date
__________________________                  __________________________
Validation Personnel /Date                  Validation Personnel/Date Historical Record: (Optional)
M/jlg Page 10 of 10


are answered "YES" then the JPM is considered valid and can be performed as written. The individual(s)
QF-1030-11 Rev. 2 (FP-T-SAT-30)
 
JOB PERFORMANCE MEASURE (JPM)
performing the validation shall sign and date this form.
SITE:                     MONTICELLO NUCLEAR GENERATING PLANT JPM TITLE:                 OFF-SITE PROTECTIVE ACTION RECOMMENDATIONS JPM NUMBER:               JPM-A.2-204-004                             REV.       2 RELATED PRA               None INFORMATION:
__________________________        __________________________
TASK NUMBER(S) /           SS304.121 TASK TITLE(S):             Formulate off-site protective action recommendations for the general public during the early phase of an emergency.
 
K/A NUMBERS:           Generic 2.4.44                             Rating: SRO/RO:       4.0/2.1 APPLICABLE METHOD OF TESTING:
Validation Personnel /Date                  Validation Personnel/Date
Discussion:               Simulate/walkthrough:               Perform:     X EVALUATION LOCATION:             In-Plant:                           Control Room:
__________________________        __________________________
Simulator:                 X       Other:
 
Lab:
Validation Personnel /Date                  Validation Personnel/Date
Time for Completion:           15     Minutes                 Time Critical:     YES Alternate Path / Faulted:       NO TASK APPLICABILITY:             SRO:       X       SRO/RO:               SRO/RO/NLO:
__________________________        __________________________
 
Validation Personnel /Date                  Validation Personnel/Date
__________________________        __________________________
 
Validation Personnel /Date                  Validation Personnel/Date Historical Record:  (Optional)
 
QF-1030-11 Rev. 2 (FP-T-SAT-30)
Retention: Life of policy + 10yrs. Disposition: Reviewer and Approver Retain in:  Training Program File M/jlg Page 1 of 9 JOB PERFORMANCE MEASURE (JPM)
SITE: MONTICELLO NUCLEAR GENERATING PLANT JPM TITLE:
OFF-SITE PROTECTIVE ACTION RECOMMENDATIONS JPM NUMBER:
JPM-A.2-204-004 REV. 2   RELATED PRA  
 
INFORMATION:
None  TASK NUMBER(S) /
TASK TITLE(S):
SS304.121 Formulate off-site protective action recommendations for the general public during  
 
the early phase of an emergency.
K/A NUMBERS: Generic 2.4.44 Rating: SRO/RO:
4.0/2.1 APPLICABLE METHOD OF TESTING:
Discussion:   Simulate/walkthrough:   Perform: X EVALUATION LOCATION:
In-Plant:   Control Room:
Simulator: X Other:
Lab:       Time for Completion: 15 Minutes Time Critical: YES     Alternate Path / Faulted: NO TASK APPLICABILITY:
SRO: X SRO/RO: SRO/RO/NLO:
Additional signatures may be added as needed.
Additional signatures may be added as needed.
Developed by:
Developed by:
Instructor                                Date Validated by:
Validation Instructor                            Date (See JPM Validation Checklist, Attachment 1)
Approved by:
Training Supervisor                              Date Retention: Life of policy + 10yrs.                                            Disposition: Reviewer and Approver Retain in: Training Program File M/jlg Page 1 of 9


Instructor Date    Validated by:
QF-1030-11 Rev. 2 (FP-T-SAT-30)
 
JPM Number: JPM-A.2-204-004 JPM Title: Off-Site Protective Action Recommendations Examinee:                                             Evaluator:
Validation Instructor (See JPM Validation Checklist, Attachment 1)
Job Title:                                               Date:
Date    Approved by:
Start Time                                         Finish Time PERFORMANCE RESULTS:                           SAT:                   UNSAT:
 
COMMENTS/FEEDBACK: (Comments SHALL be made for any steps graded unsatisfactory).
Training Supervisor Date QF-1030-11 Rev. 2 (FP-T-SAT-30)
EVALUATORS SIGNATURE:
M/jlg Page 2 of 9 JPM Number:
NOTE: Only this page needs to be retained in examinees record if completed satisfactorily. If unsatisfactory performance is demonstrated, the entire JPM should be retained.
JPM-A.2-204-004 JPM Title:
M/jlg Page 2 of 9
Off-Site Protective Action Recommendations Examinee: Evaluator: Job Title: Date: Start Time Finish Time PERFORMANCE RESULTS:
SAT: UNSAT:  
 
COMMENTS/FEEDBACK: (Comments SHALL be made for any steps graded unsatisfactory).  
 
EVALUATOR'S SIGNATURE:  
 
NOTE: Only this page needs to be retained in examinee's record if completed satisfactorily. If unsatisfactory performance is demonstrated, the entire JPM should be retained.
QF-1030-11  Rev. 2  (FP-T-SAT-30)
M/jlg Page 3 of 9 JPM BRIEFING/TURNOVER (See MTCP-03.32, Figure 6.2)
 
I will explain the initial conditions, which step(s) to simulate or discuss, and provide initiating cues. When you
 
complete the task successfully, the objective for this job performance measure will be satisfied.


QF-1030-11 Rev. 2 (FP-T-SAT-30)
JPM BRIEFING/TURNOVER (See MTCP-03.32, Figure 6.2)
I will explain the initial conditions, which step(s) to simulate or discuss, and provide initiating cues. When you complete the task successfully, the objective for this job performance measure will be satisfied.
DURING THE JPM, ENSURE PROPER SAFETY PRECAUTIONS, FME, AND/OR RADIOLOGICAL CONCERNS AS APPLICABLE ARE FOLLOWED.
DURING THE JPM, ENSURE PROPER SAFETY PRECAUTIONS, FME, AND/OR RADIOLOGICAL CONCERNS AS APPLICABLE ARE FOLLOWED.
INITIAL CONDITIONS: THIS IS A DRILL.
INITIAL CONDITIONS:
The plant is shutdown in an Emergency Condition. An escalation to a General Emergency has just been declared (EAL RG1.1, Stack Effluent Monitor "A" exceeds 2.1E+8 curies/second). Current Met Data is: Wind direction (from): 0 degrees Wind speed: 13 mph Temperature: 85&deg;F Precipitation: none Ch. 11 - Diff. Temp: -0.79 Dose assessment is not currently available  
* THIS IS A DRILL.
 
* The plant is shutdown in an Emergency Condition. An escalation to a General Emergency has just been declared (EAL RG1.1, Stack Effluent Monitor A exceeds 2.1E+8 curies/second).
INITIATING CUES (IF APPLICABLE):   THIS IS A DRILL.
* Current Met Data is:
Initiate and complete Form 5790-102-02 (MONTICE LLO EMERGENCY NOTIFICATION REPORT FORM) and provide to Shift Manager/Emergency Director when complete. This is a time critical JPM THIS IS A DRILL.
Wind direction (from): 0 degrees Wind speed: 13 mph Temperature: 85&deg;F Precipitation: none Ch. 11 - Diff. Temp: -0.79 Dose assessment is not currently available INITIATING CUES (IF APPLICABLE):
 
* THIS IS A DRILL.
* Initiate and complete Form 5790-102-02 (MONTICELLO EMERGENCY NOTIFICATION REPORT FORM) and provide to Shift Manager/Emergency Director when complete.
* This is a time critical JPM
* THIS IS A DRILL.
INSTRUCTOR NOTE: This JPM is time critical. Start time is when the initiating cue is acknowledged by the examinee. Stop time is when the examinee returns the JPM paper work to you or verbally states the task is complete.
INSTRUCTOR NOTE: This JPM is time critical. Start time is when the initiating cue is acknowledged by the examinee. Stop time is when the examinee returns the JPM paper work to you or verbally states the task is complete.
M/jlg Page 3 of 9


QF-1030-11 Rev. 2 (FP-T-SAT-30)
QF-1030-11 Rev. 2 (FP-T-SAT-30)
M/jlg Page 4 of 9 JPM PERFORMANCE INFORMATION Required Materials:
JPM PERFORMANCE INFORMATION Required Materials:       None General  
None General  


==References:==
==References:==
 
Simulator Task Standards:           Formulate off-site protective action recommendations for the general public during the early phase of an emergency.
Simulator Task Standards:
Start Time:
Formulate off-site protective action recommendations for the general public during the early phase of an emergency. Start Time:
NOTE: When providing Evaluator Cues to the examinee, care must be exercised to avoid prompting the examinee. Typically cues are only provided when the examinees actions warrant receiving the information (i.e. the examinee looks or asks for the indication).
NOTE: When providing "Evaluator Cues" to the examinee, care must be exercised to avoid prompting the examinee. Typically cues are only provided when the examinee's actions warrant receiving the information (i.e. the examinee looks or asks for the indication).
NOTE: Critical steps are marked with a Y below the performance step number. Failure to meet the standard for any critical step shall result in failure of this JPM.
NOTE: Critical steps are marked with a "Y" below the performance step number. Failure to meet the standard for any critical step shall result in failure of this JPM.
Performance Step: 1             Locate General Emergency form packet. (May also reference procedure A.2-204 Critical: N                    OFF-SITE PROTECTION ACTON RECOMMENDATIONS)
Performance Step: 1 Critical:  N Locate General Emergency form packet. (May also reference procedure A.2-204 OFF-SITE PROTECTION ACTON RECOMMENDATIONS)
Standard:                       Locates General Emergency packet.
Standard:
Evaluator Cue:                 When examinee locates General Emergency packet, hand them a copy of the material from the packet.
Locates General Emergency packet.
Evaluator Cue:
When examinee locates General Emergenc y packet, hand them a copy of the material from the packet.
NOTE: The items covered by JPM steps 2 and 3 may be done in any order as long as the standard for each step is met.
NOTE: The items covered by JPM steps 2 and 3 may be done in any order as long as the standard for each step is met.
Performance: SATISFACTORY UNSATISFACTORY Comments:  
Performance:                   SATISFACTORY           UNSATISFACTORY Comments:
 
M/jlg Page 4 of 9
QF-1030-11  Rev. 2  (FP-T-SAT-30)
M/jlg Page 5 of 9 Performance Step:  2 Critical:  Y 6.1.1 Initiate Form 5790-102-02 (MONTICELLO EMERGENCY NOTIFICATION REPORT FORM) A. Complete the Protective Action Recommendations section recommending sheltering or an evacuation of a 2 mile radius and 5
 
miles downwind and advise the remainder of the plume EPZ to go
 
indoors to monitor EAS broadcasts.  (See Figure 7.3.A for assistance.) B. Determine which geopolitical subareas are affected by referring to the Sector-Subarea Conversion Table on Form 5790-102-02 Standard:
Complete Section 10 of Form 5790-102-02. The grading standard is as follows:  Item B is circled. The blank in front of  "Sectors out to 2 miles" contains the word "ALL"  The blank in front of "Sectors out to 5 miles" contains "H,J,K"  Only the following subareas are circled: 2, 5W and 5S.
Evaluator Cue:
None  NOTE: See attached form with data filled in.
Performance: SATISFACTORY UNSATISFACTORY Comments:
 
QF-1030-11  Rev. 2  (FP-T-SAT-30)
M/jlg Page 6 of 9 Performance Step:  3 Critical:  Y Initiate Form 5790-102-02 C. Ensure completion of the remaining sections of Form 5790-102-02 and submit the completed form to the ED for approval.
Standard:
The grading standard is as follows:  Section 1: item B should be circled (not critical). Section 2: item B should be circled. Section 4: item D should be circled. Section 5: item A circled (not critical) and date and time filled in and EAL RG1.1. Section 6: item B should be circled. Section 7: item B should be circled (not critical). Section 8: Wind direction is 0 degrees and affected downwind sectors H, J and K should be circled. Section 9: Wind speed of 13 mph and stability class E circled (stability class not critical). Section 11: Examinee should indicate that they would use the label from the General emergency packet here (specifically the label for RG1.1) or they
 
may write the IC description for RG1 in the space provided.
Evaluator Cue:
None  NOTE:  See attached form with data filled in.
Performance: SATISFACTORY UNSATISFACTORY Comments:
Performance Step:  4 Critical: N INFORM EVALUATOR THAT THE TASK HAS BEEN COMPLETED.
Standard:
Operator informs evaluator that the task is completed.
Evaluator Cue:
None  Performance: SATISFACTORY UNSATISFACTORY Comments: 


Terminating Cues:  
QF-1030-11 Rev. 2 (FP-T-SAT-30)
Performance Step: 2        6.1.1    Initiate Form 5790-102-02 (MONTICELLO EMERGENCY NOTIFICATION Critical: Y                      REPORT FORM)
A. Complete the Protective Action Recommendations section recommending sheltering or an evacuation of a 2 mile radius and 5 miles downwind and advise the remainder of the plume EPZ to go indoors to monitor EAS broadcasts. (See Figure 7.3.A for assistance.)
B. Determine which geopolitical subareas are affected by referring to the Sector-Subarea Conversion Table on Form 5790-102-02 Standard:                  Complete Section 10 of Form 5790-102-02. The grading standard is as follows:
* Item B is circled.
* The blank in front of Sectors out to 2 miles contains the word ALL
* The blank in front of Sectors out to 5 miles contains H,J,K
* Only the following subareas are circled: 2, 5W and 5S.
Evaluator Cue:            None NOTE: See attached form with data filled in.
Performance:              SATISFACTORY            UNSATISFACTORY Comments:
M/jlg Page 5 of 9


When told the actions are complete, acknowledge, and state the JPM is complete.
QF-1030-11 Rev. 2 (FP-T-SAT-30)
Performance Step: 3        Initiate Form 5790-102-02 Critical: Y                  C. Ensure completion of the remaining sections of Form 5790-102-02 and submit the completed form to the ED for approval.
Standard:                  The grading standard is as follows:
* Section 1: item B should be circled (not critical).
* Section 2: item B should be circled.
* Section 4: item D should be circled.
* Section 5: item A circled (not critical) and date and time filled in and EAL RG1.1.
* Section 6: item B should be circled.
* Section 7: item B should be circled (not critical).
* Section 8: Wind direction is 0 degrees and affected downwind sectors H, J and K should be circled.
* Section 9: Wind speed of 13 mph and stability class E circled (stability class not critical).
* Section 11: Examinee should indicate that they would use the label from the General emergency packet here (specifically the label for RG1.1) or they may write the IC description for RG1 in the space provided.
Evaluator Cue:            None NOTE: See attached form with data filled in.
Performance:              SATISFACTORY            UNSATISFACTORY Comments:
Performance Step: 4        INFORM EVALUATOR THAT THE TASK HAS BEEN COMPLETED.
Critical: N Standard:                  Operator informs evaluator that the task is completed.
Evaluator Cue:            None Performance:              SATISFACTORY            UNSATISFACTORY Comments:
Terminating Cues:      When told the actions are complete, acknowledge, and state the JPM is complete.
Stop Time:
Stop Time:
Critical Time
Critical Time ___   ____
___
M/jlg Page 6 of 9
____
QF-1030-11  Rev. 2  (FP-T-SAT-30)
M/jlg Page 7 of 9 TURNOVER SHEET INITIAL CONDITIONS:  THIS IS A DRILL.
The plant is shutdown in an Emergency Condition. An escalation to a General Emergency has just been declared (EAL RG1.1, Stack Effluent Monitor "A" exceeds 2.1E+8  curies/second). Current Met Data is:  Wind direction (from):  0 degrees  Wind speed:  13 mph  Temperature:  85&deg;F  Precipitation:  none  Ch. 11 - Diff. Temp:  -0.79  Dose assessment is not currently available
 
INITIATING CUES (IF APPLICABLE):  THIS IS A DRILL.
Initiate and complete Form 5790-102-02 (MONTICE LLO EMERGENCY NOTIFICATION REPORT FORM) and provide to Shift Manager/Emergency Director when complete. This is a time critical JPM  THIS IS A DRILL.
 
QF-1030-11  Rev. 2  (FP-T-SAT-30)
JPM-A.2-204-004 (OFF-SITE PROTECTIVE ACTION RECOMMENDATIONS) Rev. 2 M/jlg Page 8 of 9 SIMULATOR SET UP:
Admin JPM; no simulator setup required.


SIMULATOR - MALFUNCTIONS:  
QF-1030-11 Rev. 2 (FP-T-SAT-30)
TURNOVER SHEET INITIAL CONDITIONS:
* THIS IS A DRILL.
* The plant is shutdown in an Emergency Condition. An escalation to a General Emergency has just been declared (EAL RG1.1, Stack Effluent Monitor A exceeds 2.1E+8 curies/second).
* Current Met Data is:
Wind direction (from): 0 degrees Wind speed: 13 mph Temperature: 85&deg;F Precipitation: none Ch. 11 - Diff. Temp: -0.79 Dose assessment is not currently available INITIATING CUES (IF APPLICABLE):
* THIS IS A DRILL.
* Initiate and complete Form 5790-102-02 (MONTICELLO EMERGENCY NOTIFICATION REPORT FORM) and provide to Shift Manager/Emergency Director when complete.
* This is a time critical JPM
* THIS IS A DRILL.
M/jlg Page 7 of 9


MALF ID MALFUNCTION TITLE DELAY RAMP EVENT VALUE FINAL. 1.        2.      
QF-1030-11 Rev. 2 (FP-T-SAT-30)
JPM-A.2-204-004 (OFF-SITE PROTECTIVE ACTION RECOMMENDATIONS) Rev. 2 SIMULATOR SET UP:
Admin JPM; no simulator setup required.
SIMULATOR - MALFUNCTIONS:
MALF ID   MALFUNCTION TITLE             DELAY   RAMP   EVENT VALUE FINAL.
1.
2.
SIMULATOR - OVERRIDES:
OVERRIDE ID.              OVERRIDE      DELAY  RAMP  EVENT  VALUE  FINAL DESCRIPTION 1.
2.
SIMULATOR - REMOTE FUNCTIONS:
REMOTE       REMOTE FUNCTION TITLE      DELAY    RAMP  EVENT  VALUE  FINAL FUNC. No.
1.
2.
M/jlg Page 8 of 9


SIMULATOR - OVERRIDES:
QF-1030-11 Rev. 2 (FP-T-SAT-30)
 
JPM-A.2-204-004 (OFF-SITE PROTECTIVE ACTION RECOMMENDATIONS) Rev. 2 ATTACHMENT 1 JOB PERFORMANCE MEASURE VALIDATION CHECKLIST ALL STEPS IN THIS CHECKLIST ARE TO BE PERFORMED UPON INITIAL VALIDATION AND PRIOR TO USE.
OVERRIDE ID.
REVIEW STATEMENTS                                                           YES       NO       N/A
OVERRIDE DESCRIPTION DELAY RAMP EVENT VALUE FINAL 1.        2.       
: 1. Are all items on the signature page filled in correctly?
 
SIMULATOR - REMOTE FUNCTIONS:
 
REMOTE FUNC. No.
REMOTE FUNCTION TITLE DELAY RAMP EVENT VALUE FINAL 1.        2.       
 
QF-1030-11 Rev. 2 (FP-T-SAT-30)
JPM-A.2-204-004 (OFF-SITE PROTECTIVE ACTION RECOMMENDATIONS) Rev. 2 M/jlg Page 9 of 9 ATTACHMENT 1 JOB PERFORMANCE MEASURE VALIDATION CHECKLIST ALL STEPS IN THIS CHECKLIST ARE TO BE PERFORMED UPON INITIAL VALIDATION AND PRIOR TO USE.
REVIEW STATEMENTS YES NO N/A 1. Are all items on the signature page filled in correctly?
: 2. Has the JPM been reviewed and validated by SMEs?
: 2. Has the JPM been reviewed and validated by SMEs?
: 3. Can the required conditions for the JPM be appropriately established in the simulator if required?
: 3. Can the required conditions for the JPM be appropriately established in the simulator if required?
: 4. Does the performance steps accurately reflect trainee's actions in accordance with plant procedures?
: 4. Does the performance steps accurately reflect trainees actions in accordance with plant procedures?
: 5. Is the standard for each performance item specific as to what controls, indications and ranges are required to evaluate if the  
: 5. Is the standard for each performance item specific as to what controls, indications and ranges are required to evaluate if the trainee properly performed the step?
 
trainee properly performed the step?
: 6. Has the completion time been established based on validation data or incumbent experience?
: 6. Has the completion time been established based on validation data or incumbent experience?
: 7. If the task is time critical, is the time critical portion based upon actual task performance requirements?
: 7. If the task is time critical, is the time critical portion based upon actual task performance requirements?
Line 1,309: Line 1,067:
Sequence / Time Critical) appropriately?
Sequence / Time Critical) appropriately?
: 11. Have all special tools and equipment needed to perform the task been identified and made available to the trainee?
: 11. Have all special tools and equipment needed to perform the task been identified and made available to the trainee?
: 12. Are all references identified, current, accurate, and available to the trainee?   13. Have all required cues (as anticipated) been identified for the evaluator to assist task completion?
: 12. Are all references identified, current, accurate, and available to the trainee?
All questions/statements must be answered "YES" or the JPM is not valid for use. If all questions/statements  
: 13. Have all required cues (as anticipated) been identified for the evaluator to assist task completion?
 
All questions/statements must be answered YES or the JPM is not valid for use. If all questions/statements are answered YES then the JPM is considered valid and can be performed as written. The individual(s) performing the validation shall sign and date this form.
are answered "YES" then the JPM is considered valid and can be performed as written. The individual(s)  
Validation Personnel /Date                   Validation Personnel/Date
 
__________________________                   __________________________
performing the validation shall sign and date this form.
Validation Personnel /Date                   Validation Personnel/Date
Validation Personnel /Date                 Validation Personnel/Date
__________________________                   __________________________
__________________________         __________________________  
Validation Personnel /Date                   Validation Personnel/Date
 
__________________________                   __________________________
Validation Personnel /Date                 Validation Personnel/Date
Validation Personnel /Date                   Validation Personnel/Date Historical Record: (Optional)
__________________________         __________________________  
M/jlg Page 9 of 9}}
 
Validation Personnel /Date                 Validation Personnel/Date
__________________________         __________________________  
 
Validation Personnel /Date                 Validation Personnel/Date Historical Record: (Optional)}}

Revision as of 08:18, 23 November 2019

Final As-Administered Administrative Jpms for the Monticello Initial Examination - February 2007
ML071070542
Person / Time
Site: Monticello Xcel Energy icon.png
Issue date: 04/17/2007
From: Valos N
NRC/RGN-III/DRS/OLB
To:
References
50-263/07-301, JPM-001, Rev 1
Download: ML071070542 (125)


Text

QF-1030-11 Rev. 2 (FP-T-SAT-30)

JOB PERFORMANCE MEASURE (JPM)

SITE: MONTICELLO NUCLEAR GENERATING PLANT JPM TITLE: Bulk D/W Temperature Manual Calculation JPM NUMBER: JPM-001 REV. 1 RELATED PRA None INFORMATION:

TASK NUMBER(S) / CR304.103 TASK TITLE(S): Perform Actions Associated with Primary Containment Control K/A NUMBERS: 2.1.25 Rating: SRO/RO: 3.1/2.8 APPLICABLE METHOD OF TESTING:

Discussion: Simulate/walkthrough: Perform: X EVALUATION LOCATION: In-Plant: Control Room:

Simulator: X Other:

Lab:

Time for Completion: 15 Minutes Time Critical: No Alternate Path / Faulted: No TASK APPLICABILITY: SRO: SRO/RO: X SRO/RO/NLO:

Additional signatures may be added as needed.

Developed by: J. Ruth Instructor Date Validated by:

Validation Instructor Date (See JPM Validation Checklist, Attachment 1)

Approved by:

Training Supervisor Date Retention: Life of policy + 10yrs. Disposition: Reviewer and Approver Retain in: Training Program File M/jlg Page 1 of 9

QF-1030-11 Rev. 2 (FP-T-SAT-30)

JPM-001, Bulk D/W Temperature Manual Calculation Rev. 1 JPM Number: JPM-001 JPM Title: Bulk D/W Temperature Manual Calculation Examinee: Evaluator:

Job Title: Date:

Start Time Finish Time PERFORMANCE RESULTS: SAT: UNSAT:

COMMENTS/FEEDBACK: (Comments shall be made for any steps graded unsatisfactory).

EVALUATORS SIGNATURE:

NOTE: Only this page needs to be retained in examinees record if completed satisfactorily. If unsatisfactory performance is demonstrated, the entire JPM should be retained.

M/jlg Page 2 of 9

QF-1030-11 Rev. 2 (FP-T-SAT-30)

JPM-001, Bulk D/W Temperature Manual Calculation Rev. 1 JPM BRIEFING/TURNOVER (See MTCP-03.32, Figure 6.2)

I will explain the initial conditions, which step(s) to simulate or discuss, and provide initiating cues. When you complete the task successfully, the objective for this job performance measure will be satisfied.

DURING THE JPM, ENSURE PROPER SAFETY PRECAUTIONS, FME, AND/OR RADIOLOGICAL CONCERNS AS APPLICABLE ARE FOLLOWED.

INITIAL CONDITIONS:

  • A LOCA is in progress
  • You are an extra licensed operator in the control room INITIATING CUES (IF APPLICABLE):
  • The CRS directs you to manually calculate and report bulk average Drywell temperature.
  • INFORM EVALUATOR WHEN YOU HAVE COMPLETED THE TASK.

M/jlg Page 3 of 9

QF-1030-11 Rev. 2 (FP-T-SAT-30)

JPM-001, Bulk D/W Temperature Manual Calculation Rev. 1 JPM PERFORMANCE INFORMATION Required Materials: Simulator General

References:

Operator Aid for Bulk Drywell Temperature Manual Calculation Task Standards: Determine Bulk Drywell Temperature via manual calculation Start Time:

NOTE: When providing Evaluator Cues to the examinee, care must be exercised to avoid prompting the examinee. Typically cues are only provided when the examinees actions warrant receiving the information (i.e. the examinee looks or asks for the indication).

NOTE: Critical steps are marked with a Y below the performance step number. Failure to meet the standard for any critical step SHALL result in failure of this JPM.

Performance Step: 1 Locates Operator Aid for Bulk Drywell Temperature Manual Calculation Critical: N Standard: Locates Operator Aid Evaluator Cue: None Performance: SATISFACTORY UNSATISFACTORY Comments:

Performance Step: 2 From TR23-115 determines Drywell temperature from the following points:

Critical: Y

  • East 932 Point 22
  • South 951 Point 23
  • West 970 Point 21
  • North 994 Point 24 Standard: Determines the following temperatures:
  • East 932 Point 22 = 259.2°F
  • South 951 Point 23 = 267.2°F
  • West 970 Point 21 = 259.8°F
  • North 994 Point 24 = 275.5°F Evaluator Cue: After operator identifies the trend recorder and applicable points, provide the sheet with a printout of the above points and their readings.

Performance: SATISFACTORY UNSATISFACTORY Comments:

M/jlg Page 4 of 9

QF-1030-11 Rev. 2 (FP-T-SAT-30)

JPM-001, Bulk D/W Temperature Manual Calculation Rev. 1 Performance Step: 3 Apply Weight Factor to the temperatures from previous step to determine Weight Critical: Y Temperatures.

  • East 932 Point 22 X .400
  • South 951 Point 23 X .423
  • West 970 Point 21 X .093
  • North 994 Point 24 X .084 Standard: Apply Weight Factor to the temperatures as follows:
  • East 932 Point 22 X .400 = (259.2 x .4 = 103.68)
  • South 951 Point 23 X .423 = (267.2 x .423 = 113.03)
  • West 970 Point 21 X .093 = (259.8 x .093 = 24.16)
  • North 994 Point 24 X .084 = (275.5 x .084 = 23.14)

Evaluator Cue: None Performance: SATISFACTORY UNSATISFACTORY Comments:

Performance Step: 4 Add Weight Temperatures to determine Bulk Average Drywell Temperature Total.

Critical: Y Standard: Adds Weight Temperatures to obtain a calculated temperature of 264.01°F + or

- 2°F Evaluator Cue: None Performance: SATISFACTORY UNSATISFACTORY Comments:

Performance Step: 5 Reports bulk average Drywell temperature calculated above to CRS.

Critical: N Standard: Reports bulk average Drywell temperature calculated above to CRS.

Evaluator Cue: Acknowledge report.

Performance: SATISFACTORY UNSATISFACTORY Comments:

M/jlg Page 5 of 9

QF-1030-11 Rev. 2 (FP-T-SAT-30)

JPM-001, Bulk D/W Temperature Manual Calculation Rev. 1 Performance Step: 6 INFORM EVALUATOR THAT THE TASK HAS BEEN COMPLETED.

Critical: N Standard: Operator informs evaluator that the task is completed.

Evaluator Cue: When informed of calculated average drywell bulk temperature, acknowledge the report and state that the JPM is complete.

Performance: SATISFACTORY UNSATISFACTORY Comments:

Terminating Cues: When informed of calculated average drywell bulk temperature, acknowledge the report and state that the JPM is complete.

Stop Time:

M/jlg Page 6 of 9

QF-1030-11 Rev. 2 (FP-T-SAT-30)

TURNOVER SHEET INITIAL CONDITIONS:

  • A LOCA is in progress
  • You are an extra licensed operator in the control room INITIATING CUES (IF APPLICABLE):
  • The CRS directs manually calculate and report bulk average Drywell temperature.
  • INFORM EVALUATOR WHEN YOU HAVE COMPLETED THE TASK.

M/jlg Page 7 of 9

QF-1030-11 Rev. 2 (FP-T-SAT-30)

JPM-001, Bulk D/W Temperature Manual Calculation Rev. 1 SIMULATOR SET UP:

INITIAL CONDITIONS:

Any simulator condition is acceptable as the only requirement for the simulator is access to the calculation instructions on the trend recorder.

SET UP INSTRUCTIONS:

  • None M/jlg Page 8 of 9

QF-1030-11 Rev. 2 (FP-T-SAT-30)

JPM-001, Bulk D/W Temperature Manual Calculation Rev. 1 ATTACHMENT 1 JOB PERFORMANCE MEASURE VALIDATION CHECKLIST ALL STEPS IN THIS CHECKLIST ARE TO BE PERFORMED UPON INITIAL VALIDATION AND PRIOR TO USE.

REVIEW STATEMENTS YES NO N/A

1. Are all items on the signature page filled in correctly?
2. Has the JPM been reviewed and validated by SMEs?
3. Can the required conditions for the JPM be appropriately established in the simulator if required?
4. Does the performance steps accurately reflect trainees actions in accordance with plant procedures?
5. Is the standard for each performance item specific as to what controls, indications and ranges are required to evaluate if the trainee properly performed the step?
6. Has the completion time been established based on validation data or incumbent experience?
7. If the task is time critical, is the time critical portion based upon actual task performance requirements?
8. Is the Licensee level appropriate for the task being evaluated if required?
9. Is the K/A appropriate to the task and to the licensee level if required?
10. Have the performance steps been identified and typed (Critical /

Sequence / Time Critical) appropriately?

11. Have all special tools and equipment needed to perform the task been identified and made available to the trainee?
12. Are all references identified, current, accurate, and available to the trainee?
13. Have all required cues (as anticipated) been identified for the evaluator to assist task completion?

All questions/statements must be answered YES or the JPM is not valid for use. If all questions/statements are answered YES then the JPM is considered valid and can be performed as written. The individual(s) performing the validation shall sign and date this form.

__________________________ __________________________

Validation Personnel /Date Validation Personnel/Date

__________________________ __________________________

Validation Personnel /Date Validation Personnel/Date

__________________________ __________________________

Validation Personnel /Date Validation Personnel/Date

__________________________ __________________________

Validation Personnel /Date Validation Personnel/Date Historical Record: (Optional)

M/jlg Page 9 of 9

QF-1030-11 Rev. 2 (FP-T-SAT-30)

JOB PERFORMANCE MEASURE (JPM)

SITE: MONTICELLO NUCLEAR GENERATING PLANT JPM TITLE: CONTROL ROOM SHIFT TURNOVER CHECKLIST JPM NUMBER: JPM-3139-001 REV. 0 RELATED PRA None INFORMATION:

TASK NUMBER(S) / CR298.103 TASK TITLE(S): Perform the Control Room Shift Turnover Checklist K/A NUMBERS: 2.1.3 Rating: SRO/RO: 3.4 /3.0 APPLICABLE METHOD OF TESTING:

Discussion: Simulate/walkthrough: Perform: x EVALUATION LOCATION: In-Plant: Control Room:

Simulator: x Other:

Lab:

Time for Completion: 20 Minutes Time Critical: No Alternate Path / Faulted: Yes TASK APPLICABILITY: SRO: SRO/RO: X SRO/RO/NLO:

Additional signatures may be added as needed.

Developed by: J Ruth Instructor Date Validated by:

Validation Instructor Date (See JPM Validation Checklist, Attachment 1)

Approved by:

Training Supervisor Date Retention: Life of policy + 10yrs. Disposition: Reviewer and Approver Retain in: Training Program File M/jlg Page 1 of 13

QF-1030-11 Rev. 2 (FP-T-SAT-30)

JPM-3139-001 (CONTROL ROOM SHIFT TURNOVER CHECKLIST) Rev.0 JPM Number: JPM-3139-001 JPM Title: Control Room Shift Turnover Checklist Examinee: Evaluator:

Job Title: Date:

Start Time Finish Time PERFORMANCE RESULTS: SAT: UNSAT:

COMMENTS/FEEDBACK: (Comments shall be made for any steps graded unsatisfactory).

EVALUATORS SIGNATURE:

NOTE: Only this page needs to be retained in examinees record if completed satisfactorily. If unsatisfactory performance is demonstrated, the entire JPM should be retained.

M/jlg Page 2 of 13

QF-1030-11 Rev. 2 (FP-T-SAT-30)

JPM-3139-001 (CONTROL ROOM SHIFT TURNOVER CHECKLIST) Rev.0 JPM BRIEFING/TURNOVER (See MTCP-03.32, Figure 6.2)

I will explain the initial conditions, which step(s) to simulate or discuss, and provide initiating cues. When you complete the task successfully, the objective for this job performance measure will be satisfied.

DURING THE JPM, ENSURE PROPER SAFETY PRECAUTIONS, FME, AND/OR RADIOLOGICAL CONCERNS AS APPLICABLE ARE FOLLOWED.

INITIAL CONDITIONS:

  • The reactor is operating at power
  • You are the LPEO on the 19-07 shift
  • The Shift Manager is Smith INITIATING CUES (IF APPLICABLE):
  • Perform the front page of 3139, Control Room Shift Turnover Checklist M/jlg Page 3 of 13

QF-1030-11 Rev. 2 (FP-T-SAT-30)

JPM-3139-001 (CONTROL ROOM SHIFT TURNOVER CHECKLIST) Rev.0 JPM PERFORMANCE INFORMATION Required Materials: Checklist 3139 General

References:

OWI-02.01, Operations Shift Turnover Task Standards: Complete front page of Control Room Shift Turnover Checklist Start Time:

NOTE: When providing Evaluator Cues to the examinee, care must be exercised to avoid prompting the examinee. Typically cues are only provided when the examinees actions warrant receiving the information (i.e. the examinee looks or asks for the indication).

NOTE: Critical steps are marked with a Y below the performance step number. Failure to meet the standard for any critical step shall result in failure of this JPM.

Performance Step: 1 Complete the shift complement section of the checklist.

Critical: N Standard: Fills in Shift Manager, Date, Shift.

Evaluator Cue: None Performance: SATISFACTORY UNSATISFACTORY Comments:

Performance Step: 2 Record Mode Switch position Critical: N Standard: Checks Run box Evaluator Cue: None Performance: SATISFACTORY UNSATISFACTORY Comments:

M/jlg Page 4 of 13

QF-1030-11 Rev. 2 (FP-T-SAT-30)

JPM-3139-001 (CONTROL ROOM SHIFT TURNOVER CHECKLIST) Rev.0 Performance Step: 3 Record Core thermal Power Critical: N Standard: Records 1765 - 1775 MWT Evaluator Cue: None Performance: SATISFACTORY UNSATISFACTORY Comments:

Performance Step: 4 Record Core Flow Critical: N Standard: Records 51 x 106 Lb/Hr +/- 0.5 Evaluator Cue: None Performance: SATISFACTORY UNSATISFACTORY Comments:

Performance Step: 5 Record Core/Rx dP Critical: N Standard: Records 14.2 / 22 Psid +/- 0.5 Evaluator Cue: None Performance: SATISFACTORY UNSATISFACTORY Comments:

Performance Step: 6 Record Rx Pressure Critical: N Standard: Records 1000 Psig +/- 5 Evaluator Cue: None Performance: SATISFACTORY UNSATISFACTORY Comments:

M/jlg Page 5 of 13

QF-1030-11 Rev. 2 (FP-T-SAT-30)

JPM-3139-001 (CONTROL ROOM SHIFT TURNOVER CHECKLIST) Rev.0 Performance Step: 7 Record Rx Level Critical: N Standard: Records 35 inches +/- 1 Evaluator Cue: None Performance: SATISFACTORY UNSATISFACTORY Comments:

Performance Step: 8 Record Torus Level Critical: N Standard: Records 0 inches +/- .5 Evaluator Cue: None Performance: SATISFACTORY UNSATISFACTORY Comments:

Performance Step: 9 Record RCP dP Critical: N Standard: Records 117 / 116 psid +/- 2 Evaluator Cue: None Performance: SATISFACTORY UNSATISFACTORY Comments:

Performance Step: 10 Record Steam Flow Critical: N Standard: Records 7.25 x 106 Lb/Hr +/- .25 Evaluator Cue: None Performance: SATISFACTORY UNSATISFACTORY Comments:

M/jlg Page 6 of 13

QF-1030-11 Rev. 2 (FP-T-SAT-30)

JPM-3139-001 (CONTROL ROOM SHIFT TURNOVER CHECKLIST) Rev.0 Performance Step: 11 Record FW Flow Critical: N Standard: Records 7.25 x 106 Lb/Hr +/- .25 Evaluator Cue: None Performance: SATISFACTORY UNSATISFACTORY Comments:

Performance Step: 12 Records status of Nuclear Instruments Critical: N Standard: Records APRMs 2 and 5 bypassed with none above normal Evaluator Cue: None Performance: SATISFACTORY UNSATISFACTORY Comments:

Performance Step: 13 Records status of Rad Monitors Critical: N Standard: Records none are bypassed and none above normal Evaluator Cue: None Performance: SATISFACTORY UNSATISFACTORY Comments:

Performance Step: 14 Record Rx Level Mode / Controllers Critical: N Standard: Records 3 element, MSTR-AUTO, and Lo Flow Reg Va is in MAN.

Evaluator Cue: None Performance: SATISFACTORY UNSATISFACTORY Comments:

M/jlg Page 7 of 13

QF-1030-11 Rev. 2 (FP-T-SAT-30)

JPM-3139-001 (CONTROL ROOM SHIFT TURNOVER CHECKLIST) Rev.0 Performance Step: 15 Record RFP Level Trip Critical: N Standard: Records position of RFP Level Trip in NORMAL Evaluator Cue: None Performance: SATISFACTORY UNSATISFACTORY Comments:

Performance Step: 16 Record Press Contr Critical: N Standard: Records MPR # 910 +/- 5 and EPR# 903 +/- 1 Evaluator Cue: None Performance: SATISFACTORY UNSATISFACTORY Comments:

Performance Step: 17 Record Switch position and Alarms for 11 & 12 D Gen Critical: N Standard: Records AUTO for switch positions and None for alarms Evaluator Cue: None Performance: SATISFACTORY UNSATISFACTORY Comments:

Performance Step: 18 Record ADS A, C, D switch positions and alarms Critical: N Standard: Records ADS switch positions in AUTO and None for alarms Evaluator Cue: None Performance: SATISFACTORY UNSATISFACTORY Comments:

M/jlg Page 8 of 13

QF-1030-11 Rev. 2 (FP-T-SAT-30)

JPM-3139-001 (CONTROL ROOM SHIFT TURNOVER CHECKLIST) Rev.0 Performance Step: 19 Record SRV Low-Low Set C-03 E, G, H switch positions and alarms Critical: N Standard: Records Low-Low Set switch positions in AUTO and None for alarms Evaluator Cue: None Performance: SATISFACTORY UNSATISFACTORY Comments:

Performance Step: 20 Record DIV II Low-Low Set Logic switch position and alarms Critical: N Standard: Records switch in Auto and None for alarms Evaluator Cue: None Performance: SATISFACTORY UNSATISFACTORY Comments:

Performance Step: 21 Record A RHR switch position, alarms, and valve line-up Critical: Y Standard: Records switch position in Auto, None for alarms, and notes MO-2002 (RHR DIV 1 HX BYPASS) valve is in the CLOSED position. Reports to CRS and takes keylock switch to OPEN when directed by CRS.

Evaluator Cue: Acknowledge report of MO-2002 (RHR DIV 1 HX BYPASS) valve is in the CLOSED position. Directs valve be opened.

Performance: SATISFACTORY UNSATISFACTORY Comments:

Performance Step: 22 Record A RHRSW switch position, alarms, and valve line-up Critical: N Standard: Records switch position in Auto, None for alarms, and valve line-up sat Evaluator Cue: None Performance: SATISFACTORY UNSATISFACTORY Comments:

M/jlg Page 9 of 13

QF-1030-11 Rev. 2 (FP-T-SAT-30)

JPM-3139-001 (CONTROL ROOM SHIFT TURNOVER CHECKLIST) Rev.0 Performance Step: 23 Record A Core Spray switch position, alarms, and valve line-up Critical: N Standard: Records switch position in Auto, None for alarms, and valve line-up sat Evaluator Cue: None Performance: SATISFACTORY UNSATISFACTORY Comments:

Performance Step: 24 Record HPCI switch position, alarms, and valve line-up. Notes and reports to the Critical: Y CRS that the HPCI Flow Controller is in MANUAL control.

Standard: Recognizes that the HPCI Flow Controller is in MANUAL control and reports to the CRS the discrepancy. Selects AUTO control when directed.

Evaluator Cue: Acknowledge the report and direct that the HPCI Flow Controller be placed in AUTO.

Performance: SATISFACTORY UNSATISFACTORY Comments:

Terminating Cues: When the HPCI check has been completed, state that the JPM is completed Stop Time:

Critical Time ___N/A____

M/jlg Page 10 of 13

QF-1030-11 Rev. 2 (FP-T-SAT-30)

TURNOVER SHEET INITIAL CONDITIONS:

  • The reactor is operating at power
  • You are the LPEO on the 19-07 shift
  • The Shift Manager is Smith INITIATING CUES (IF APPLICABLE):
  • Perform the front page of 3139, Control Room Shift Turnover Checklist M/jlg Page 11 of 13

QF-1030-11 Rev. 2 (FP-T-SAT-30)

JPM-3139-001 (CONTROL ROOM SHIFT TURNOVER CHECKLIST) Rev.0 SIMULATOR SET UP:

  • IC-15 or other 100% power IC.
  • Place the HPCI flow controller in Manual
  • Place the key lock switch for MO-2002 (RHR DIV 1 HX BYPASS) in the CLOSED position.

SIMULATOR - MALFUNCTIONS:

MALF ID MALFUNCTION TITLE DELAY RAMP EVENT VALUE FINAL.

1.

2.

SIMULATOR - OVERRIDES:

OVERRIDE ID. OVERRIDE DELAY RAMP EVENT VALUE FINAL DESCRIPTION 1.

2.

SIMULATOR - REMOTE FUNCTIONS:

REMOTE REMOTE FUNCTION TITLE DELAY RAMP EVENT VALUE FINAL FUNC. No.

1.

2.

M/jlg Page 12 of 13

QF-1030-11 Rev. 2 (FP-T-SAT-30)

JPM-3139-001 (CONTROL ROOM SHIFT TURNOVER CHECKLIST) Rev.0 ATTACHMENT 1 JOB PERFORMANCE MEASURE VALIDATION CHECKLIST ALL STEPS IN THIS CHECKLIST ARE TO BE PERFORMED UPON INITIAL VALIDATION AND PRIOR TO USE.

REVIEW STATEMENTS YES NO N/A

1. Are all items on the signature page filled in correctly?
2. Has the JPM been reviewed and validated by SMEs?
3. Can the required conditions for the JPM be appropriately established in the simulator if required?
4. Does the performance steps accurately reflect trainees actions in accordance with plant procedures?
5. Is the standard for each performance item specific as to what controls, indications and ranges are required to evaluate if the trainee properly performed the step?
6. Has the completion time been established based on validation data or incumbent experience?
7. If the task is time critical, is the time critical portion based upon actual task performance requirements?
8. Is the Licensee level appropriate for the task being evaluated if required?
9. Is the K/A appropriate to the task and to the licensee level if required?
10. Have the performance steps been identified and typed (Critical /

Sequence / Time Critical) appropriately?

11. Have all special tools and equipment needed to perform the task been identified and made available to the trainee?
12. Are all references identified, current, accurate, and available to the trainee?
13. Have all required cues (as anticipated) been identified for the evaluator to assist task completion?

All questions/statements must be answered YES or the JPM is not valid for use. If all questions/statements are answered YES then the JPM is considered valid and can be performed as written. The individual(s) performing the validation SHALL sign and date this form.

__________________________ __________________________

Validation Personnel /Date Validation Personnel/Date

__________________________ __________________________

Validation Personnel /Date Validation Personnel/Date

__________________________ __________________________

Validation Personnel /Date Validation Personnel/Date

__________________________ __________________________

Validation Personnel /Date Validation Personnel/Date Historical Record: (Optional)

M/jlg Page 13 of 13

QF-1030-11 Rev. 2 (FP-T-SAT-30)

JOB PERFORMANCE MEASURE (JPM)

SITE: MONTICELLO NUCLEAR GENERATING PLANT JPM TITLE: DETERMINE SHIFT STAFFING JPM NUMBER: JPM OWI-01.06-003 REV. 0 RELATED PRA None INFORMATION:

TASK NUMBER(S) / SS299.289 TASK TITLE(S): Implement the Operations Group Organization and Responsibilities Assignments K/A NUMBERS: 2.1.4 Rating: SRO/RO: 3.4 / 2.3 APPLICABLE METHOD OF TESTING:

Discussion: Simulate/walkthrough: Perform: x EVALUATION LOCATION: In-Plant: Control Room:

Simulator: Other: x Lab:

Time for Completion: 15 Minutes Time Critical: No Alternate Path / Faulted: No TASK APPLICABILITY: SRO: X SRO/RO: SRO/RO/NLO:

Additional signatures may be added as needed.

Developed by: J Ruth Instructor Date Validated by:

Validation Instructor Date (See JPM Validation Checklist, Attachment 1)

Approved by:

Training Supervisor Date Retention: Life of policy + 10yrs. Disposition: Reviewer and Approver Retain in: Training Program File M/jlg Page 1 of 9

QF-1030-11 Rev. 2 (FP-T-SAT-30)

JPM-OWI-01.06-003 (DETERMINE SHIFT STAFFING) Rev. 0 JPM Number: JPM-OWI-01.06-003 JPM Title: Determine Shift Staffing Examinee: Evaluator:

Job Title: Date:

Start Time Finish Time PERFORMANCE RESULTS: SAT: UNSAT:

COMMENTS/FEEDBACK: (Comments shall be made for any steps graded unsatisfactory).

EVALUATORS SIGNATURE:

NOTE: Only this page needs to be retained in examinees record if completed satisfactorily. If unsatisfactory performance is demonstrated, the entire JPM should be retained.

M/jlg Page 2 of 9

QF-1030-11 Rev. 2 (FP-T-SAT-30)

JPM-OWI-01.06-003 (DETERMINE SHIFT STAFFING) Rev. 0 JPM BRIEFING/TURNOVER (See MTCP-03.32, Figure 6.2)

I will explain the initial conditions, which step(s) to simulate or discuss, and provide initiating cues. When you complete the task successfully, the objective for this job performance measure will be satisfied.

DURING THE JPM, ENSURE PROPER SAFETY PRECAUTIONS, FME, AND/OR RADIOLOGICAL CONCERNS AS APPLICABLE ARE FOLLOWED.

INITIAL CONDITIONS:

  • You are a fully qualified CRS at the beginning of a shift change
  • The reactor is operating in MODE 1
  • Shift 4 is the duty shift
  • Noland is filling the vacant NPE&RO position
  • The Shift Chemist (Beaker) and Shift Rad. Prot. Specialist ( Marx) are available and are fire brigade qualified
  • All operations personnel are respirator qualified unless noted otherwise INITIATING CUES (IF APPLICABLE):
  • Determine if the staffing requirements are met for the following On-shift collateral duties by filling out the provided roster with the appropriate names:

Fire Brigade Toxic Gas S/D Outside the Control Room

  • Provide MNGP Operations Department Organization/Qualification chart
  • Provide Respirator qualification memo from RP/Chem
  • Provide blank roster form M/jlg Page 3 of 9

QF-1030-11 Rev. 2 (FP-T-SAT-30)

JPM-OWI-01.06-003 (DETERMINE SHIFT STAFFING) Rev. 0 JPM PERFORMANCE INFORMATION Required Materials: MTF-7600-002, Monticello Fire Brigade Training Summary, Monticello Nuclear Generating Plant Operations Department Organization/Qualification General

References:

OWI-01.06 Rev. 28 Task Standards: Determine Staffing Requirements Start Time:

NOTE: When providing Evaluator Cues to the examinee, care must be exercised to avoid prompting the examinee. Typically cues are only provided when the examinees actions warrant receiving the information (i.e. the examinee looks or asks for the indication).

NOTE: Critical steps are marked with a Y below the performance step number. Failure to meet the standard for any critical step shall result in failure of this JPM.

Performance Step: 1 Refers to OWI-01.06, DUTY OPERATIONS PERSONNEL REQUIREMENTS AND Critical: N RESPONSIBILITIES Standard: Refers to OWI for guidance Evaluator Cue: None Performance: SATISFACTORY UNSATISFACTORY Comments:

Performance Step: 2 On-shift collateral duties require the following staffing:

Critical: Y 1. Fire Brigade:

Five duty crew members normally filled by the following individuals: BOP, two NAPEOs, Shift Chemist, Shift Rad Prot Spec. These individuals are required to be respirator qualified.

Standard: Assigned White, Thompson, Williams, Shift Chemist and Shift Rad Prot Spec to Fire Brigade.

Evaluator Cue: If asked, inform the candidate that all non-operations required individuals are available and respirator qualified.

Performance: SATISFACTORY UNSATISFACTORY Comments:

M/jlg Page 4 of 9

QF-1030-11 Rev. 2 (FP-T-SAT-30)

JPM-OWI-01.06-003 (DETERMINE SHIFT STAFFING) Rev. 0 Performance Step: 3 On-shift collateral duties require the following staffing:

Critical: Y 2. Toxic Gas Event:

Technical specifications requires two active SROs and two active ROs while in Startup or Run mode. The Shift Mgr, Control Room Supv, and two of the three Control Room Operators satisfy this requirement. These individuals are required by A.4 (HAZARDOUS MATERIALS PROCEDURES) to be respirator qualified.

Standard: Determines that any 2 of the 3 ROs will satisfy the requirement.

Determines that this requirement cannot be satisfied due to Smith not being respirator qualified.

Evaluator Cue: Acknowledges report Performance: SATISFACTORY UNSATISFACTORY Comments:

Performance Step: 4 On-shift collateral duties require the following staffing:

Critical: Y 3. S/D Outside the Control Room:

Three duty crew members are required to effectively implement C.4-C (SHUTDOWN OUTSIDE CONTROL ROOM). Normally four individuals are available to implement this procedure. These individuals cannot simultaneously have fire Brigade duties. (Fire in the Control room or Cable spreading Room requires both Fire Brigade and C.4-C implementation). The Shift Mgr, NLPE&RO, NPE&RO, and NAPEO normally satisfies this requirement. There are no respirator qualifications associated with this requirement.

Standard: Determines this requirement can be met by assigning any combination of Smith, Jones, Nolan, or Black.

Evaluator Cue: None Performance: SATISFACTORY UNSATISFACTORY Comments:

M/jlg Page 5 of 9

QF-1030-11 Rev. 2 (FP-T-SAT-30)

JPM-OWI-01.06-003 (DETERMINE SHIFT STAFFING) Rev. 0 Performance Step: 5 INFORM EVALUATOR THAT THE TASK HAS BEEN COMPLETED.

Critical: N Standard: Operator informs evaluator that the task is completed.

Evaluator Cue: When the operator informs evaluator that the task is completed state that the JPM is complete.

Performance: SATISFACTORY UNSATISFACTORY Comments:

Terminating Cues: When the operator informs evaluator that the task is completed state that the JPM is complete.

Stop Time:

Critical Time ___N/A____

M/jlg Page 6 of 9

QF-1030-11 Rev. 2 (FP-T-SAT-30)

TURNOVER SHEET INITIAL CONDITIONS:

  • You are a fully qualified CRS at the beginning of a shift change
  • The reactor is operating in MODE 1
  • Shift 4 is the duty shift
  • Noland is filling the vacant NPE&RO position
  • The Shift Chemist (Beaker) and Shift Rad. Prot. Specialist ( Marx) are available and are fire brigade qualified
  • All operations personnel are respirator qualified unless noted otherwise INITIATING CUES (IF APPLICABLE):
  • Determine if the staffing requirements are met for the following On-shift collateral duties by filling out the provided roster with the appropriate names:

Fire Brigade Toxic Gas S/D Outside the Control Room

  • Provide MNGP Operations Department Organization/Qualification chart
  • Provide Respirator qualification memo from RP/Chem
  • Provide blank roster form M/jlg Page 7 of 9

QF-1030-11 Rev. 2 (FP-T-SAT-30)

JPM-OWI-01.06-003 (DETERMINE SHIFT STAFFING) Rev. 0 SIMULATOR SET UP:

Admin JPM; no simulator setup required.

SIMULATOR - MALFUNCTIONS:

MALF ID MALFUNCTION TITLE DELAY RAMP EVENT VALUE FINAL.

1.

2.

SIMULATOR - OVERRIDES:

OVERRIDE ID. OVERRIDE DELAY RAMP EVENT VALUE FINAL DESCRIPTION 1.

2.

SIMULATOR - REMOTE FUNCTIONS:

REMOTE REMOTE FUNCTION TITLE DELAY RAMP EVENT VALUE FINAL FUNC. No.

1.

2.

M/jlg Page 8 of 9

QF-1030-11 Rev. 2 (FP-T-SAT-30)

JPM-OWI-01.06-003 (DETERMINE SHIFT STAFFING) Rev. 0 ATTACHMENT 1 JOB PERFORMANCE MEASURE VALIDATION CHECKLIST ALL STEPS IN THIS CHECKLIST ARE TO BE PERFORMED UPON INITIAL VALIDATION AND PRIOR TO USE.

REVIEW STATEMENTS YES NO N/A

1. Are all items on the signature page filled in correctly?
2. Has the JPM been reviewed and validated by SMEs?
3. Can the required conditions for the JPM be appropriately established in the simulator if required?
4. Does the performance steps accurately reflect trainees actions in accordance with plant procedures?
5. Is the standard for each performance item specific as to what controls, indications and ranges are required to evaluate if the trainee properly performed the step?
6. Has the completion time been established based on validation data or incumbent experience?
7. If the task is time critical, is the time critical portion based upon actual task performance requirements?
8. Is the Licensee level appropriate for the task being evaluated if required?
9. Is the K/A appropriate to the task and to the licensee level if required?
10. Have the performance steps been identified and typed (Critical /

Sequence / Time Critical) appropriately?

11. Have all special tools and equipment needed to perform the task been identified and made available to the trainee?
12. Are all references identified, current, accurate, and available to the trainee?
13. Have all required cues (as anticipated) been identified for the evaluator to assist task completion?

All questions/statements must be answered YES or the JPM is not valid for use. If all questions/statements are answered YES then the JPM is considered valid and can be performed as written. The individual(s) performing the validation SHALL sign and date this form.

__________________________ __________________________

Validation Personnel /Date Validation Personnel/Date

__________________________ __________________________

Validation Personnel /Date Validation Personnel/Date

__________________________ __________________________

Validation Personnel /Date Validation Personnel/Date

__________________________ __________________________

Validation Personnel /Date Validation Personnel/Date Historical Record: (Optional)

M/jlg Page 9 of 9

QF-1030-11 Rev. 2 (FP-T-SAT-30)

JOB PERFORMANCE MEASURE (JPM)

SITE: MONTICELLO NUCLEAR GENERATING PLANT JPM TITLE: DAILY JET PUMP OPERABILITY CHECK TEST 0133 JPM NUMBER: JPM-0133-001 REV. 0 RELATED PRA None INFORMATION:

TASK NUMBER(S) / CR299.349 TASK TITLE(S): Perform Operations Daily Log - Parts A, B, D, E, G, H, & J K/A NUMBERS: 2.2.12 Rating: SRO/RO: 3.4/3.0 APPLICABLE METHOD OF TESTING:

Discussion: Simulate/walkthrough: Perform: X EVALUATION LOCATION: In-Plant: Control Room:

Simulator: X Other:

Lab:

Time for Completion: 25 Minutes Time Critical: No Alternate Path / Faulted: No TASK APPLICABILITY: SRO: SRO/RO: X SRO/RO/NLO:

Additional signatures may be added as needed.

Developed by: J Ruth Instructor Date Validated by:

Validation Instructor Date (See JPM Validation Checklist, Attachment 1)

Approved by:

Training Supervisor Date Retention: Life of policy + 10yrs. Disposition: Reviewer and Approver Retain in: Training Program File M/jlg Page 1 of 14

QF-1030-11 Rev. 2 (FP-T-SAT-30)

JPM-0133-001 (DAILY JET PUMP OPERABILITY CHECK TEST 0133) Rev.0 JPM Number: JPM-0133-001 JPM Title: Daily Jet Pump Operability Check Test 0133 Examinee: Evaluator:

Job Title: Date:

Start Time Finish Time PERFORMANCE RESULTS: SAT: UNSAT:

COMMENTS/FEEDBACK: (Comments shall be made for any steps graded unsatisfactory).

EVALUATORS SIGNATURE:

NOTE: Only this page needs to be retained in examinees record if completed satisfactorily. If unsatisfactory performance is demonstrated, the entire JPM should be retained.

M/jlg Page 2 of 14

QF-1030-11 Rev. 2 (FP-T-SAT-30)

JPM-0133-001 (DAILY JET PUMP OPERABILITY CHECK TEST 0133) Rev.0 JPM BRIEFING/TURNOVER (See MTCP-03.32, Figure 6.2)

I will explain the initial conditions, which step(s) to simulate or discuss, and provide initiating cues. When you complete the task successfully, the objective for this job performance measure will be satisfied.

DURING THE JPM, ENSURE PROPER SAFETY PRECAUTIONS, FME, AND/OR RADIOLOGICAL CONCERNS AS APPLICABLE ARE FOLLOWED.

INITIAL CONDITIONS:

  • The reactor is operating at power
  • You are the BOP operator INITIATING CUES (IF APPLICABLE):
  • The CRS directs you to perform Test 0133, Daily Jet Pump Operability Check per Operations Daily Log - Part B

M/jlg Page 3 of 14

QF-1030-11 Rev. 2 (FP-T-SAT-30)

JPM-0133-001 (DAILY JET PUMP OPERABILITY CHECK TEST 0133) Rev.0 JPM PERFORMANCE INFORMATION Required Materials: Individual Jet Pump dP readings, B.01.04-06 Figures 15, 16 & 17.

General

References:

Simulator IC at 100% power. (IC-15)

Task Standards: Complete Test 0133 (Expected readings are provided in red.)

Start Time:

NOTE: When providing Evaluator Cues to the examinee, care must be exercised to avoid prompting the examinee. Typically cues are only provided when the examinees actions warrant receiving the information (i.e. the examinee looks or asks for the indication).

NOTE: Critical steps are marked with a Y below the performance step number. Failure to meet the standard for any critical step shall result in failure of this JPM.

Performance Step: 1 NOTE: STEP 3.b. and 3.c. not required to be performed until 4 hours0.167 days <br />0.0238 weeks <br />0.00548 months <br /> after Critical: Y associated recirculation loop is in operation and until 24 hours1 days <br />0.143 weeks <br />0.0329 months <br /> after THERMAL POWER >25% RTP.

IF the Reactor is in MODE 1 or 2, AND recirculation loop(s) is in operation, THEN obtain and record the values for the operating loop(s) described in the matrices below and perform the following:

Variable Panel Item Description Value Unit CRT RPV501, Core Thermal Power % 99.5 -  %

100 A C-04 SI-2-184-16A, Recirc Pump 11 %Speed 85-87  %

B C-04 SI-2-184-16B, Recirc Pump 12 %Speed 85-87  %

C C-04 FI-2-159A, Recirc Loop 11 Flow 26.5- gpm 27.5 x 103 D C-04 FI-2-159B, Recirc Loop 12 Flow 26.5- gpm 27.5 x 103 Standard: Obtains and records the above data.

Evaluator Cue: None Performance: SATISFACTORY UNSATISFACTORY Comments:

M/jlg Page 4 of 14

QF-1030-11 Rev. 2 (FP-T-SAT-30)

JPM-0133-001 (DAILY JET PUMP OPERABILITY CHECK TEST 0133) Rev.0 Performance Step: 2 On Figure 17, Recirculation Pump Flow vs Speed, of Ops Man B.01.04-06 Critical: Y (REACTOR RECIRCULATION SYSTEM - FIGURES) plot points for values of variables A vs C and variables B vs D.

1) Does point A vs C fall in ACCEPTABLE RANGE?

Yes No

2) Does point B vs D fall in ACCEPTABLE RANGE?

Yes No Standard: Plots points and determines values are in the acceptable range.

Evaluator Cue: None Performance: SATISFACTORY UNSATISFACTORY Comments:

Performance Step: 3 Critical: Y Variable Panel Item Description Value Unit E C-04 FI-2-3-92B, Jet Pump Loop A Flow 25-26 x 106 lb/hr F C-04 FI-2-3-92A, Jet Pump Loop B Flow 25-26 x 106 lb/hr G calc (E ÷ L) X 100, % Loop A Flow 86.8-90.3  %

H calc (F ÷ L) X 100, % Loop B Flow 86.8-90.3  %

J calc (G ÷ A) % Loop Flow / % Pump 0.99 - 1.06 ratio Speed K calc (H ÷ B) % Loop Flow / % Pump 0.99 - 1.06 ratio Speed L=Constant Half of rated Core Flow 28.8 x 106 lb/hr M calc (E÷(L x 2)) x 100%, % Core Flow 43.4-45.2  %

N calc (F÷(L x 2)) x 100%, % Core Flow 43.4-45.2  %

Standard: Obtains and records the above data.

Evaluator Cue: None Performance: SATISFACTORY UNSATISFACTORY Comments:

M/jlg Page 5 of 14

QF-1030-11 Rev. 2 (FP-T-SAT-30)

JPM-0133-001 (DAILY JET PUMP OPERABILITY CHECK TEST 0133) Rev.0 Performance Step: 4 IF THERMAL POWER IS >25% RTP, Critical: Y THEN on Figure 15, Loop A: Jet Pump Loop Flow/Pump Speed, of Ops Man B.01.04-06 plot points for values of variables J vs A.

1) Does point J vs A fall in ACCEPTABLE RANGE?

Yes No N/A Standard: Plots points and determines values are in the acceptable range.

Evaluator Cue: None Performance: SATISFACTORY UNSATISFACTORY Comments:

Performance Step: 5 IF THERMAL POWER IS >25% RTP, Critical: Y THEN on Figure 16, Loop B: Jet Pump Loop Flow/Pump Speed, of Ops Man B.01.04-06 plot points for values of variables K vs B.

1) Does point K vs B fall in ACCEPTABLE RANGE?

Yes No N/A Standard: Plots points and determines values are in the acceptable range.

Evaluator Cue: None Performance: SATISFACTORY UNSATISFACTORY Comments:

Performance Step: 6 IF any question in STEPs 3.a. through 3.c. is checked No, Critical: N THEN notify Control Room Supervisor, AND perform procedure 0442 (SPECIAL JET PUMP OPERABILITY TEST).

Standard: Determines no step is No.

Evaluator Cue: None Performance: SATISFACTORY UNSATISFACTORY Comments:

M/jlg Page 6 of 14

QF-1030-11 Rev. 2 (FP-T-SAT-30)

JPM-0133-001 (DAILY JET PUMP OPERABILITY CHECK TEST 0133) Rev.0 Performance Step: 7 IF in MODE 1 or 2, Critical: Y AND both recirculation loops are in operation, THEN :

1) Calculate percent of total rated core flow (M + N) 86.8-90.4%

Standard: Calculates percent of total rated core flow.

Evaluator Cue: None Performance: SATISFACTORY UNSATISFACTORY Comments:

Performance Step: 8 IF in MODE 1 or 2, Critical: Y AND both recirculation loops are in operation, THEN :

2) Calculate absolute value (M - N), Jet Pump Flow Mismatch _0-1.8__%

Standard: Calculates absolute value.

Evaluator Cue: None Performance: SATISFACTORY UNSATISFACTORY Comments:

Performance Step: 9 IF in MODE 1 or 2, Critical: N AND both recirculation loops are in operation, THEN :

3) IF percent of total rated core flow from STEP 3.e.1) is <70%,

THEN is the Jet Pump Flow Mismatch from STEP 3.e.2) 10%?

Yes No N/A Standard: Determines this step is N/A.

Evaluator Cue: None Performance: SATISFACTORY UNSATISFACTORY Comments:

M/jlg Page 7 of 14

QF-1030-11 Rev. 2 (FP-T-SAT-30)

JPM-0133-001 (DAILY JET PUMP OPERABILITY CHECK TEST 0133) Rev.0 Performance Step: 10 IF in MODE 1 or 2, Critical: Y AND both recirculation loops are in operation, THEN :

4) IF percent of total rated core flow from STEP 3.e.1) is 70%,

THEN is the Jet Pump Flow Mismatch from STEP 3.e.2) 5%?

Yes No N/A Standard: Determines Jet Pump Flow Mismatch is 5%.

Evaluator Cue: None Performance: SATISFACTORY UNSATISFACTORY Comments:

Performance Step: 11 IF any question in STEP 3.e. is checked No, Critical: N THEN notify Control Room Supervisor, AND evaluate Tech Spec 3.4.1 and enter appropriate Condition.

Standard: Determines no step is No.

Evaluator Cue: None Performance: SATISFACTORY UNSATISFACTORY Comments:

Performance Step: 12 IF the Reactor is in MODE 1, Critical: Y AND there is recirculation flow, THEN perform the following:

a. From FPR-2-3-95 (C-04), Core dP Red Pen, record dP: (14-14.5)
b. Record the square root of Core dP (from a. above): (3.7-3.81)
c. From CRT mimic obtain and record Core Flow: (50.5-51.5 X 106)
d. Calculate and record 100 x (c. ÷ 57.6 x106 lb/hr): (87.5-89.5)
e. On Figure 20 Core Plate dP vs Core Flow, of Ops Man B.01.04-06 plot point for value of b. vs d. above.

Standard: Obtains and records the above data.

Evaluator Cue: None Performance: SATISFACTORY UNSATISFACTORY Comments:

M/jlg Page 8 of 14

QF-1030-11 Rev. 2 (FP-T-SAT-30)

JPM-0133-001 (DAILY JET PUMP OPERABILITY CHECK TEST 0133) Rev.0 Performance Step: 13 On figure 20 Core Plate dP vs. Core Flow, of Ops Man B.01.04-06 plot point for Critical: Y value b. vs. d. above.

1) Does point for b. vs. d fall in ACCEPTABLE RANGE?

Yes No

2) IF No, THEN notify Shift Supervision to determine actions and notifications.

Standard: Plots points and determines values are in the acceptable range.

Evaluator Cue: None Performance: SATISFACTORY UNSATISFACTORY Comments:

Performance Step: 14 IF the Reactor is in MODE 1, Critical: N AND THERMAL POWER >25% RTP with a recirculation loop in operation, THEN from FR-7288, JET PUMP FLOW RECORDER (Panel C-38), record individual Jet Pump and loop average dPs in the matrix below and perform the following:

Loop A Loop B Jet Raw DP/Loop Jet Raw DP/Loop Pump dP Avg Pump dP Avg 11 8.8 1 1 8.8 1 12 8.8 1 2 8.6 0.93 13 8.7 0.96 3 8.7 0.96 14 8.8 1 4 8.9 1.03 15 8.6 0.93 5 8.7 0.96 16 8.9 1.03 6 8.8 1 17 8.8 1 7 8.7 0.96 18 8.7 0.96 8 8.6 0.93 19 8.8 1 9 8.7 0.96 20 8.6 0.93 10 8.7 0.96 Loop 8.8 Loop 8.8 Avg dP Avg dP Standard: Records data provided.

Evaluator Cue: Iindividual Jet Pump Raw dP data has been provided.

Performance: SATISFACTORY UNSATISFACTORY Comments:

M/jlg Page 9 of 14

QF-1030-11 Rev. 2 (FP-T-SAT-30)

JPM-0133-001 (DAILY JET PUMP OPERABILITY CHECK TEST 0133) Rev.0 Performance Step: 15 For each loop divide each individual Jet Pump raw dP by its Loop Average dP and Critical: N record in matrix.

Standard: Divides and records in matrix.

Evaluator Cue: None Performance: SATISFACTORY UNSATISFACTORY Comments:

Performance Step: 16 IF the Reactor is in MODE 1, Critical: Y AND Recirc Pump speed (SI-2-184-16A&B on C04) >50%,

THEN perform the following:

a. Record 2-184-23A (C04), A Pump Volts, indication: (3050-3150Volts)
b. Record 2-184-23B (C04), B Pump Volts, indication: (3100-3200 Volts)
c. Record SI-2-184-16A, Recirc Pump 11 %Speed, indication: (85-87)
d. Record SI-2-184-16B, Recirc Pump 12 %Speed, indication: (85-87)
e. Record result of a. ÷ c.: (35.0-37.1) Volts/% Speed for 11(35.5 - 40.5)
f. Record result of b. ÷ d.: (35.6-37.7) Volts/% Speed for 12 (35.5 - 40.5)

Standard: Obtains and records above parameters.

Evaluator Cue: None Performance: SATISFACTORY UNSATISFACTORY Comments:

Performance Step: 17 IF either acceptance criteria is not met, Critical: N* THEN on Panel C-21from TR-2-184-26, RECIRC MG SET WINDING TEMP, and TR-2-2-31, RECIRC PUMP AND MTR TEMP, verify MG set generator and Recirc pump motor winding temperatures are normal and not unexpectedly trending up, AND notify Shift Supervision to determine actions and notifications.

Standard: Determines acceptance criteria is met. *(This step is critical if step 16e above is calculated to not meet acceptance criteria).

Evaluator Cue: None Performance: SATISFACTORY UNSATISFACTORY Comments:

M/jlg Page 10 of 14

QF-1030-11 Rev. 2 (FP-T-SAT-30)

JPM-0133-001 (DAILY JET PUMP OPERABILITY CHECK TEST 0133) Rev.0 Performance Step: 18 INFORM EVALUATOR THAT THE TASK HAS BEEN COMPLETED.

Critical: N Standard: Operator informs evaluator that the task is completed.

Evaluator Cue: Acknowledge report of task completion.

Performance: SATISFACTORY UNSATISFACTORY Comments:

Terminating Cues: AFTER TASK COMPLETION REPORT IS MADE, STATE THAT THE JPM IS COMPLETE.

Stop Time:

Critical Time ___N/A____

M/jlg Page 11 of 14

QF-1030-11 Rev. 2 (FP-T-SAT-30)

JPM-0133-001 (DAILY JET PUMP OPERABILITY CHECK TEST 0133) Rev.0 TURNOVER SHEET INITIAL CONDITIONS:

  • The reactor is operating at power
  • You are the BOP operator INITIATING CUES (IF APPLICABLE):
  • The CRS directs you to perform Test 0133, Daily Jet Pump Operability Check per Operations Daily Log - Part B

M/jlg Page 12 of 14

QF-1030-11 Rev. 2 (FP-T-SAT-30)

SIMULATOR SET UP:

  • IC-15 or other 100% power IC.

SIMULATOR - MALFUNCTIONS:

MALF ID MALFUNCTION TITLE DELAY RAMP EVENT VALUE FINAL.

1.

2.

SIMULATOR - OVERRIDES:

OVERRIDE ID. OVERRIDE DELAY RAMP EVENT VALUE FINAL DESCRIPTION 1.

2.

SIMULATOR - REMOTE FUNCTIONS:

REMOTE REMOTE FUNCTION TITLE DELAY RAMP EVENT VALUE FINAL FUNC. No.

1.

2.

M/jlg Page 13 of 14

QF-1030-11 Rev. 2 (FP-T-SAT-30)

JPM-0133-001 (DAILY JET PUMP OPERABILITY CHECK TEST 0133) Rev.0 ATTACHMENT 1 JOB PERFORMANCE MEASURE VALIDATION CHECKLIST ALL STEPS IN THIS CHECKLIST ARE TO BE PERFORMED UPON INITIAL VALIDATION AND PRIOR TO USE.

REVIEW STATEMENTS YES NO N/A

1. Are all items on the signature page filled in correctly?
2. Has the JPM been reviewed and validated by SMEs?
3. Can the required conditions for the JPM be appropriately established in the simulator if required?
4. Does the performance steps accurately reflect trainees actions in accordance with plant procedures?
5. Is the standard for each performance item specific as to what controls, indications and ranges are required to evaluate if the trainee properly performed the step?
6. Has the completion time been established based on validation data or incumbent experience?
7. If the task is time critical, is the time critical portion based upon actual task performance requirements?
8. Is the Licensee level appropriate for the task being evaluated if required?
9. Is the K/A appropriate to the task and to the licensee level if required?
10. Have the performance steps been identified and typed (Critical /

Sequence / Time Critical) appropriately?

11. Have all special tools and equipment needed to perform the task been identified and made available to the trainee?
12. Are all references identified, current, accurate, and available to the trainee?
13. Have all required cues (as anticipated) been identified for the evaluator to assist task completion?

All questions/statements must be answered YES or the JPM is not valid for use. If all questions/statements are answered YES then the JPM is considered valid and can be performed as written. The individual(s) performing the validation SHALL sign and date this form.

__________________________ __________________________

Validation Personnel /Date Validation Personnel/Date

__________________________ __________________________

Validation Personnel /Date Validation Personnel/Date

__________________________ __________________________

Validation Personnel /Date Validation Personnel/Date

__________________________ __________________________

Validation Personnel /Date Validation Personnel/Date Historical Record: (Optional)

M/jlg Page 14 of 14

QF-1030-11 Rev. 2 (FP-T-SAT-30)

JOB PERFORMANCE MEASURE (JPM)

SITE: MONTICELLO NUCLEAR GENERATING PLANT JPM TITLE: DAILY JET PUMP OPERABILITY CHECK TEST 0133 JPM NUMBER: JPM-0133-002 REV. 0 RELATED PRA None INFORMATION:

TASK NUMBER(S) / CR299.349 TASK TITLE(S): Perform Operations Daily Log - Parts A, B, D, E, G, H, & J K/A NUMBERS: 2.1.12 Rating: SRO/RO: 3.4/3.0 APPLICABLE METHOD OF TESTING:

Discussion: Simulate/walkthrough: Perform: X EVALUATION LOCATION: In-Plant: Control Room:

Simulator: X Other:

Lab:

Time for Completion: 25 Minutes Time Critical: No Alternate Path / Faulted: Yes TASK APPLICABILITY: SRO: X SRO/RO: SRO/RO/NLO:

Additional signatures may be added as needed.

Developed by: J Ruth Instructor Date Validated by:

Validation Instructor Date (See JPM Validation Checklist, Attachment 1)

Approved by:

Training Supervisor Date Retention: Life of policy + 10yrs. Disposition: Reviewer and Approver Retain in: Training Program File M/jlg Page 1 of 10

QF-1030-11 Rev. 2 (FP-T-SAT-30)

JPM-0133-002 (DAILY JET PUMP OPERABILITY CHECK TEST 0133) Rev.0 JPM Number: JPM-0133-002 JPM Title: Daily Jet Pump Operability Check Test 0133 Examinee: Evaluator:

Job Title: Date:

Start Time Finish Time PERFORMANCE RESULTS: SAT: UNSAT:

COMMENTS/FEEDBACK: (Comments shall be made for any steps graded unsatisfactory).

EVALUATORS SIGNATURE:

NOTE: Only this page needs to be retained in examinees record if completed satisfactorily. If unsatisfactory performance is demonstrated, the entire JPM should be retained.

M/jlg Page 2 of 10

QF-1030-11 Rev. 2 (FP-T-SAT-30)

JPM-0133-002 (DAILY JET PUMP OPERABILITY CHECK TEST 0133) Rev.0 JPM BRIEFING/TURNOVER (See MTCP-03.32, Figure 6.2)

I will explain the initial conditions, which step(s) to simulate or discuss, and provide initiating cues. When you complete the task successfully, the objective for this job performance measure will be satisfied.

DURING THE JPM, ENSURE PROPER SAFETY PRECAUTIONS, FME, AND/OR RADIOLOGICAL CONCERNS AS APPLICABLE ARE FOLLOWED.

INITIAL CONDITIONS:

  • The reactor is operating at power
  • Test 0133, Daily Jet Pump Operability Check per Operations Daily Log - Part B has been completed by the RO
  • You are the CRS INITIATING CUES (IF APPLICABLE):
  • Review for satisfactoy completion of the provided Test 0133, Daily Jet Pump Operability Check per Operations Daily Log - Part B M/jlg Page 3 of 10

QF-1030-11 Rev. 2 (FP-T-SAT-30)

JPM-0133-002 (DAILY JET PUMP OPERABILITY CHECK TEST 0133) Rev.0 JPM PERFORMANCE INFORMATION Required Materials: Marked up copy of completed test, B.01.04-06 Figures 15, 16 & 17.

General

References:

Simulator IC at 100% power.

Task Standards: Perform a supervisory review of the daily Jet Pump Operability Test.

Start Time:

NOTE: When providing Evaluator Cues to the examinee, care must be exercised to avoid prompting the examinee. Typically cues are only provided when the examinees actions warrant receiving the information (i.e. the examinee looks or asks for the indication).

NOTE: Critical steps are marked with a Y below the performance step number. Failure to meet the standard for any critical step shall result in failure of this JPM.

Performance Step: 1 NOTE: STEP 3.b. and 3.c. not required to be performed until 4 hours0.167 days <br />0.0238 weeks <br />0.00548 months <br /> after Critical: N associated recirculation loop is in operation and until 24 hours1 days <br />0.143 weeks <br />0.0329 months <br /> after THERMAL POWER >25% RTP.

IF the Reactor is in MODE 1 or 2, AND recirculation loop(s) is in operation, THEN obtain and record the values for the operating loop(s) described in the matrices below and perform the following:

Variable Panel Item Description Value Unit CRT RPV501, Core Thermal Power % 99.9  %

A C-04 SI-2-184-16A, Recirc Pump 11 %Speed 94  %

B C-04 SI-2-184-16B, Recirc Pump 11 %Speed 96  %

C C-04 FI-2-159A, Recirc Loop 11 Flow 25 x 103 gpm D C-04 FI-2-159B, Recirc Loop 12 Flow 27 x 103 gpm Standard: Reviews the above data.

Evaluator Cue: None Performance: SATISFACTORY UNSATISFACTORY Comments:

M/jlg Page 4 of 10

QF-1030-11 Rev. 2 (FP-T-SAT-30)

JPM-0133-002 (DAILY JET PUMP OPERABILITY CHECK TEST 0133) Rev.0 Performance Step: 2 On Figure 17, Recirculation Pump Flow vs Speed, of Ops Man B.01.04-06 Critical: Y (REACTOR RECIRCULATION SYSTEM - FIGURES) plot points for values of variables A vs C and variables B vs D.

1) Does point A vs C fall in ACCEPTABLE RANGE?

Yes No

2) Does point B vs D fall in ACCEPTABLE RANGE?

Yes No Standard: Reviews points and determines 1) is NOT in the acceptable range and 2) is in the acceptable range.

Evaluator Cue: None Performance: SATISFACTORY UNSATISFACTORY Comments:

Performance Step: 3 Critical: N Variable Panel Item Description Value Unit E C-04 FI-2-3-92B, Jet Pump Loop A Flow 24.9 x 106 lb/hr F C-04 FI-2-3-92A, Jet Pump Loop B Flow 26.1 x 106 lb/hr G calc (E ÷ L) X 100, % Loop A Flow 86.5  %

H calc (F ÷ L) X 100, % Loop B Flow 90.6  %

J calc (G ÷ A) X 100, % Loop Flow / % 0.92 ratio Pump Speed K calc (H ÷ B) X 100, % Loop Flow / % 0.94 ratio Pump Speed L=Constant Half of rated Core Flow 28.8 x 106 lb/hr M calc (E÷(L x 2)) x 100%, % Core Flow 43.2  %

N calc (F÷(L x 2)) x 100%, % Core Flow 45.3  %

Standard: Reviews the above data.

Evaluator Cue: None Performance: SATISFACTORY UNSATISFACTORY Comments:

M/jlg Page 5 of 10

QF-1030-11 Rev. 2 (FP-T-SAT-30)

JPM-0133-002 (DAILY JET PUMP OPERABILITY CHECK TEST 0133) Rev.0 Performance Step: 4 IF THERMAL POWER IS >25% RTP, Critical: Y THEN on Figure 15, Loop A: Jet Pump Loop Flow/Pump Speed, of Ops Man B.01.04-06 plot points for values of variables J vs A.

1) Does point J vs A fall in ACCEPTABLE RANGE?

Yes No N/A Standard: Review points and determines values are NOT in the acceptable range.

Evaluator Cue: If informed, acknowledge that point does not fall within the acceptable range.

Performance: SATISFACTORY UNSATISFACTORY Comments:

Performance Step: 5 IF THERMAL POWER IS >25% RTP, Critical: Y THEN on Figure 16, Loop B: Jet Pump Loop Flow/Pump Speed, of Ops Man B.01.04-06 plot points for values of variables K vs B.

1) Does point K vs B fall in ACCEPTABLE RANGE?

Yes No N/A Standard: Reviews points and determines values are NOT in the acceptable range.

Evaluator Cue: If informed, acknowledge that point does not fall within the acceptable range.

Performance: SATISFACTORY UNSATISFACTORY Comments:

Performance Step: 6 IF any question in STEPs 3.a. through 3.c. is checked No, Critical: Y THEN notify Control Room Supervisor, AND perform procedure 0442 (SPECIAL JET PUMP OPERABILITY TEST).

Standard: When informed, acknowledge that performance of procedure 0442 is required and state that the JPM is complete.

Evaluator Cue: None Performance: SATISFACTORY UNSATISFACTORY Comments:

M/jlg Page 6 of 10

QF-1030-11 Rev. 2 (FP-T-SAT-30)

JPM-0133-002 (DAILY JET PUMP OPERABILITY CHECK TEST 0133) Rev.0 Terminating Cues: EVALUATOR INFORMS OPERATOR THAT THE JPM IS COMPLETE.

Stop Time:

Critical Time ___N/A____

M/jlg Page 7 of 10

QF-1030-11 Rev. 2 (FP-T-SAT-30)

JPM-0133-002 (DAILY JET PUMP OPERABILITY CHECK TEST 0133) Rev.0 TURNOVER SHEET INITIAL CONDITIONS:

  • The reactor is operating at power
  • Test 0133, Daily Jet Pump Operability Check per Operations Daily Log - Part B has been completed by the RO
  • You are the CRS INITIATING CUES (IF APPLICABLE):
  • Review for satisfactoy completion of the provided Test 0133, Daily Jet Pump Operability Check per Operations Daily Log - Part B M/jlg Page 8 of 10

QF-1030-11 Rev. 2 (FP-T-SAT-30)

SIMULATOR SET UP:

  • Admin JPM - no simulator setup is required.

SIMULATOR - MALFUNCTIONS:

MALF ID MALFUNCTION TITLE DELAY RAMP EVENT VALUE FINAL.

1.

2.

SIMULATOR - OVERRIDES:

OVERRIDE ID. OVERRIDE DELAY RAMP EVENT VALUE FINAL DESCRIPTION 1.

2.

SIMULATOR - REMOTE FUNCTIONS:

REMOTE REMOTE FUNCTION TITLE DELAY RAMP EVENT VALUE FINAL FUNC. No.

1.

2.

M/jlg Page 9 of 10

QF-1030-11 Rev. 2 (FP-T-SAT-30)

JPM-0133-001 (DAILY JET PUMP OPERABILITY CHECK TEST 0133) Rev.0 ATTACHMENT 1 JOB PERFORMANCE MEASURE VALIDATION CHECKLIST ALL STEPS IN THIS CHECKLIST ARE TO BE PERFORMED UPON INITIAL VALIDATION AND PRIOR TO USE.

REVIEW STATEMENTS YES NO N/A

1. Are all items on the signature page filled in correctly?
2. Has the JPM been reviewed and validated by SMEs?
3. Can the required conditions for the JPM be appropriately established in the simulator if required?
4. Does the performance steps accurately reflect trainees actions in accordance with plant procedures?
5. Is the standard for each performance item specific as to what controls, indications and ranges are required to evaluate if the trainee properly performed the step?
6. Has the completion time been established based on validation data or incumbent experience?
7. If the task is time critical, is the time critical portion based upon actual task performance requirements?
8. Is the Licensee level appropriate for the task being evaluated if required?
9. Is the K/A appropriate to the task and to the licensee level if required?
10. Have the performance steps been identified and typed (Critical /

Sequence / Time Critical) appropriately?

11. Have all special tools and equipment needed to perform the task been identified and made available to the trainee?
12. Are all references identified, current, accurate, and available to the trainee?
13. Have all required cues (as anticipated) been identified for the evaluator to assist task completion?

All questions/statements must be answered YES or the JPM is not valid for use. If all questions/statements are answered YES then the JPM is considered valid and can be performed as written. The individual(s) performing the validation SHALL sign and date this form.

__________________________ __________________________

Validation Personnel /Date Validation Personnel/Date

__________________________ __________________________

Validation Personnel /Date Validation Personnel/Date

__________________________ __________________________

Validation Personnel /Date Validation Personnel/Date

__________________________ __________________________

Validation Personnel /Date Validation Personnel/Date Historical Record: (Optional)

M/jlg Page 10 of 10

QF-1030-11 Rev. 2 (FP-T-SAT-30)

JOB PERFORMANCE MEASURE (JPM)

SITE: MONTICELLO NUCLEAR GENERATING PLANT JPM TITLE: LOCKED HIGH RADIATION AREA ENTRY JPM NUMBER: JPM-4 AWI-08.04.06-002 REV. 0 RELATED PRA None INFORMATION:

TASK NUMBER(S) / CR999.299 TASK TITLE(S): ADMINISTRATIVE PROCEDURES K/A NUMBERS: 2.3.10 Rating: SRO/RO: 3.3/2.9 APPLICABLE METHOD OF TESTING:

Discussion: Simulate/walkthrough: X Perform:

EVALUATION LOCATION: In-Plant: Control Room:

Simulator: Other: X Lab:

Time for Completion: 15 Minutes Time Critical: NO Alternate Path / Faulted: NO TASK APPLICABILITY: SRO: SRO/RO: SRO/RO/NLO: X Additional signatures may be added as needed.

Developed by: J. Ruth Instructor Date Validated by:

Validation Instructor Date (See JPM Validation Checklist, Attachment 1)

Approved by:

Training Supervisor Date M/jlg Page 1 of 10

QF-1030-11 Rev. 2 (FP-T-SAT-30)

JPM-4 AWI-08.04.06-002 (LOCKED HIGH RADIATION AREA ENTRY) Rev. 0 JPM Number: JPM-4 AWI-08.04.06-002 JPM Title: LOCKED HIGH RADIATION AREA ENTRY Examinee: Evaluator:

Job Title: Date:

Start Time Finish Time PERFORMANCE RESULTS: SAT: UNSAT:

COMMENTS/FEEDBACK: (Comments shall be made for any steps graded unsatisfactory).

EVALUATORS SIGNATURE:

NOTE: Only this page needs to be retained in examinees record if completed satisfactorily. If unsatisfactory performance is demonstrated, the entire JPM should be retained.

M/jlg Page 2 of 10

QF-1030-11 Rev. 2 (FP-T-SAT-30)

JPM-4 AWI-08.04.06-002 (LOCKED HIGH RADIATION AREA ENTRY) Rev. 0 JPM BRIEFING/TURNOVER (See MTCP-03.32, Figure 6.2)

I will explain the initial conditions, which step(s) to simulate or discuss, and provide initiating cues. When you complete the task successfully, the objective for this job performance measure will be satisfied.

DURING THE JPM, ENSURE PROPER SAFETY PRECAUTIONS, FME, AND/OR RADIOLOGICAL CONCERNS AS APPLICABLE ARE FOLLOWED.

INITIAL CONDITIONS:

The task conditions are as follows:

  • The plant is at 100% power.
  • The RWCU pump room must be entered and MO-2398 must be inspected for potential valve stem leakage.
  • You are an extra operator on shift
  • Provide Survey Map
  • Provide RWP INITIATING CUES (IF APPLICABLE):

The CRS directs you to perform the specific instructions per 4 AWI-08.04.06, section 4.4.2, for a non routine entry into the posted locked high radiation area for the inspection.

M/jlg Page 3 of 10

QF-1030-11 Rev. 2 (FP-T-SAT-30)

JPM-4 AWI-08.04.06-002 (LOCKED HIGH RADIATION AREA ENTRY) Rev. 0 JPM PERFORMANCE INFORMATION Required Materials: SURVEY MAP AND RWP FOR HI RADIATION AREA TO BE ENTERED General

References:

4 AWI-08.04.06, AREA CONTROL Task Standards: VERIFY INDIVIDUAL EXPOSURE LIMITS ALLOW ENTRY INTO LOCKED HIGH RADITION AREA Start Time:

NOTE: When providing Evaluator Cues to the examinee, care must be exercised to avoid prompting the examinee. Typically cues are only provided when the examinees actions warrant receiving the information (i.e. the examinee looks or asks for the indication).

NOTE: Critical steps are marked with a Y below the performance step number. Failure to meet the standard for any critical step shall result in failure of this JPM.

Performance Step: 1 Provided a copy of 4 AWI-08.04.06 (AREA CONTROL) reviews procedure and Critical: N locates Section 4.4.2 specific instructions for high, locked high, and very high radiation areas.

Standard: Locates appropriate section of procedure.

Evaluator Cue: Provide copy of procedure 4 AWI-08.04.06 (AREA CONTROL)

Performance: SATISFACTORY UNSATISFACTORY Comments:

M/jlg Page 4 of 10

QF-1030-11 Rev. 2 (FP-T-SAT-30)

JPM-4 AWI-08.04.06-002 (LOCKED HIGH RADIATION AREA ENTRY) Rev. 0 Performance Step: 2 Specific instructions for high, locked high, and very high radiation areas.

Critical: N Y A. Obtain any required special approvals as follows:

1. Locked High Radiation Area:

[ NOTE: Post-Exam Non-routine entries your supervisor (if on site), the Shift review determined that Managers, or the Rad Prot Coords approval prior to the entry.

this step was a Critical Supervisors may approve their own entries.

Step ]

2. Very High Radiation Area You SHALL obtain written approval from the plant manager, which is based on a sound operational or safety reason.

Standard: Determines step is applicable.

Evaluator Cue: If asked, state that the entry has been approved.

Performance: SATISFACTORY UNSATISFACTORY Comments:

Performance Step: 3 Obtain a high radiation area pre-entry briefing from the Radiation Protection staff.

Critical: N Y This briefing and all high radiation area requirements of the RWP are required if any part of the body breaks the plane of the boundary, even if permission to reach

[ NOTE: Post-Exam over was granted.

review determined that this step was a Critical Step ]

Standard: Determines that a radiological briefing must be performed.

Evaluator Cue: State that the radiological briefing has been performed.

Performance: SATISFACTORY UNSATISFACTORY Comments:

M/jlg Page 5 of 10

QF-1030-11 Rev. 2 (FP-T-SAT-30)

JPM-4 AWI-08.04.06-002 (LOCKED HIGH RADIATION AREA ENTRY) Rev. 0 Performance Step: 4 Prepare to perform your individual exposure control duties as follows:

Critical: Y 1. You SHALL determine the expected area does rates for all regions of the area you will be entering by reviewing area surveys.

Reviews areas surveys provided and determines the dose rate for the inspection is 1200 Mrem/hr at the valve and 180 Mrem/hr in the general vicinity of the valve.

Standard: Determines dose rates will be 1200 Mrem/hr at the valve and 180 Mrem/hr in the general vicinity of the valve.

Evaluator Cue: None Performance: SATISFACTORY UNSATISFACTORY Comments:

Performance Step: 5 Prepare to perform your individual exposure control duties as follows:

Critical: Y 2. Determine the expected duration of the entry and the expected dose needed to make the entry.

Operator determines expected dose using determined dose rate and given duration of entry.

Standard: Determines expected dose to be 138 Mrem.

Evaluator Cue: State the expected duration of the entry is 6 minutes at the valve and an additional 6 minutes in the general vicinity of the valve.

Performance: SATISFACTORY UNSATISFACTORY Comments:

Performance Step: 6 Prepare to perform your individual exposure control duties as follows:

Critical: Y 3. Determine the allowable entry dose, either from the electronic dosimeter log-in process, from the local point, or from your dosimeter.

Standard: Operator determines the dose alarm and dose rate alarm setpoints are too low for the performance of this task.

Evaluator Cue: If reported, acknowledge the report.

Performance: SATISFACTORY UNSATISFACTORY Comments:

M/jlg Page 6 of 10

QF-1030-11 Rev. 2 (FP-T-SAT-30)

JPM-4 AWI-08.04.06-002 (LOCKED HIGH RADIATION AREA ENTRY) Rev. 0 Performance Step: 7 Prepare to perform your individual exposure control duties as follows:

Critical: Y 4. IF the allowable entry dose is less than the expected entry dose, THEN you SHALL report to the Rad Prot Coord for resolution.

Standard: Operator determines the allowable entry dose is less than the expected entry dose and reports to the Rad Prot Coord.

Evaluator Cue: Acknowledge report as the Rad Prot Coord.

Performance: SATISFACTORY UNSATISFACTORY Comments:

Terminating Cues: WHEN REPORT IS MADE, STATE THAT THE JPM IS COMPLETE.

Stop Time:

Critical Time ___N/A____

M/jlg Page 7 of 10

QF-1030-11 Rev. 2 (FP-T-SAT-30)

TURNOVER SHEET INITIAL CONDITIONS:

The task conditions are as follows:

  • The plant is at 100% power.
  • The RWCU pump room must be entered and MO-2398 must be inspected for potential valve stem leakage.
  • You are an extra operator on shift
  • Provide Survey Map
  • Provide RWP INITIATING CUES (IF APPLICABLE):

The CRS directs you to perform the specific instructions per 4 AWI-08.04.06, section 4.4.2, for a non routine entry into the posted locked high radiation area for the inspection.

M/jlg Page 8 of 10

QF-1030-11 Rev. 2 (FP-T-SAT-30)

JPM-4 AWI-08.04.06-002 (LOCKED HIGH RADIATION AREA ENTRY) Rev. 0 SIMULATOR SET UP:

Admin JPM; no simulator setup required.

SIMULATOR - MALFUNCTIONS:

MALF ID MALFUNCTION TITLE DELAY RAMP EVENT VALUE FINAL.

1.

2.

SIMULATOR - OVERRIDES:

OVERRIDE ID. OVERRIDE DELAY RAMP EVENT VALUE FINAL DESCRIPTION 1.

2.

SIMULATOR - REMOTE FUNCTIONS:

REMOTE REMOTE FUNCTION TITLE DELAY RAMP EVENT VALUE FINAL FUNC. No.

1.

2.

M/jlg Page 9 of 10

QF-1030-11 Rev. 2 (FP-T-SAT-30)

JPM-4 AWI-08.04.06-002 (LOCKED HIGH RADIATION AREA ENTRY) Rev. 0 ATTACHMENT 1 JOB PERFORMANCE MEASURE VALIDATION CHECKLIST ALL STEPS IN THIS CHECKLIST ARE TO BE PERFORMED UPON INITIAL VALIDATION AND PRIOR TO USE.

REVIEW STATEMENTS YES NO N/A

1. Are all items on the signature page filled in correctly?
2. Has the JPM been reviewed and validated by SMEs?
3. Can the required conditions for the JPM be appropriately established in the simulator if required?
4. Does the performance steps accurately reflect trainees actions in accordance with plant procedures?
5. Is the standard for each performance item specific as to what controls, indications and ranges are required to evaluate if the trainee properly performed the step?
6. Has the completion time been established based on validation data or incumbent experience?
7. If the task is time critical, is the time critical portion based upon actual task performance requirements?
8. Is the Licensee level appropriate for the task being evaluated if required?
9. Is the K/A appropriate to the task and to the licensee level if required?
10. Have the performance steps been identified and typed (Critical /

Sequence / Time Critical) appropriately?

11. Have all special tools and equipment needed to perform the task been identified and made available to the trainee?
12. Are all references identified, current, accurate, and available to the trainee?
13. Have all required cues (as anticipated) been identified for the evaluator to assist task completion?

All questions/statements must be answered YES or the JPM is not valid for use. If all questions/statements are answered YES then the JPM is considered valid and can be performed as written. The individual(s) performing the validation shall sign and date this form.

__________________________ __________________________

Validation Personnel /Date Validation Personnel/Date

__________________________ __________________________

Validation Personnel /Date Validation Personnel/Date

__________________________ __________________________

Validation Personnel /Date Validation Personnel/Date

__________________________ __________________________

Validation Personnel /Date Validation Personnel/Date Historical Record: (Optional)

M/jlg Page 10 of 10

QF-1030-11 Rev. 2 (FP-T-SAT-30)

JOB PERFORMANCE MEASURE (JPM)

SITE: MONTICELLO NUCLEAR GENERATING PLANT JPM TITLE: OFF-SITE PROTECTIVE ACTION RECOMMENDATIONS JPM NUMBER: JPM-A.2-204-004 REV. 2 RELATED PRA None INFORMATION:

TASK NUMBER(S) / SS304.121 TASK TITLE(S): Formulate off-site protective action recommendations for the general public during the early phase of an emergency.

K/A NUMBERS: Generic 2.4.44 Rating: SRO/RO: 4.0/2.1 APPLICABLE METHOD OF TESTING:

Discussion: Simulate/walkthrough: Perform: X EVALUATION LOCATION: In-Plant: Control Room:

Simulator: X Other:

Lab:

Time for Completion: 15 Minutes Time Critical: YES Alternate Path / Faulted: NO TASK APPLICABILITY: SRO: X SRO/RO: SRO/RO/NLO:

Additional signatures may be added as needed.

Developed by:

Instructor Date Validated by:

Validation Instructor Date (See JPM Validation Checklist, Attachment 1)

Approved by:

Training Supervisor Date Retention: Life of policy + 10yrs. Disposition: Reviewer and Approver Retain in: Training Program File M/jlg Page 1 of 9

QF-1030-11 Rev. 2 (FP-T-SAT-30)

JPM Number: JPM-A.2-204-004 JPM Title: Off-Site Protective Action Recommendations Examinee: Evaluator:

Job Title: Date:

Start Time Finish Time PERFORMANCE RESULTS: SAT: UNSAT:

COMMENTS/FEEDBACK: (Comments SHALL be made for any steps graded unsatisfactory).

EVALUATORS SIGNATURE:

NOTE: Only this page needs to be retained in examinees record if completed satisfactorily. If unsatisfactory performance is demonstrated, the entire JPM should be retained.

M/jlg Page 2 of 9

QF-1030-11 Rev. 2 (FP-T-SAT-30)

JPM BRIEFING/TURNOVER (See MTCP-03.32, Figure 6.2)

I will explain the initial conditions, which step(s) to simulate or discuss, and provide initiating cues. When you complete the task successfully, the objective for this job performance measure will be satisfied.

DURING THE JPM, ENSURE PROPER SAFETY PRECAUTIONS, FME, AND/OR RADIOLOGICAL CONCERNS AS APPLICABLE ARE FOLLOWED.

INITIAL CONDITIONS:

  • THIS IS A DRILL.
  • The plant is shutdown in an Emergency Condition. An escalation to a General Emergency has just been declared (EAL RG1.1, Stack Effluent Monitor A exceeds 2.1E+8 curies/second).
  • Current Met Data is:

Wind direction (from): 0 degrees Wind speed: 13 mph Temperature: 85°F Precipitation: none Ch. 11 - Diff. Temp: -0.79 Dose assessment is not currently available INITIATING CUES (IF APPLICABLE):

  • THIS IS A DRILL.
  • Initiate and complete Form 5790-102-02 (MONTICELLO EMERGENCY NOTIFICATION REPORT FORM) and provide to Shift Manager/Emergency Director when complete.
  • This is a time critical JPM
  • THIS IS A DRILL.

INSTRUCTOR NOTE: This JPM is time critical. Start time is when the initiating cue is acknowledged by the examinee. Stop time is when the examinee returns the JPM paper work to you or verbally states the task is complete.

M/jlg Page 3 of 9

QF-1030-11 Rev. 2 (FP-T-SAT-30)

JPM PERFORMANCE INFORMATION Required Materials: None General

References:

Simulator Task Standards: Formulate off-site protective action recommendations for the general public during the early phase of an emergency.

Start Time:

NOTE: When providing Evaluator Cues to the examinee, care must be exercised to avoid prompting the examinee. Typically cues are only provided when the examinees actions warrant receiving the information (i.e. the examinee looks or asks for the indication).

NOTE: Critical steps are marked with a Y below the performance step number. Failure to meet the standard for any critical step shall result in failure of this JPM.

Performance Step: 1 Locate General Emergency form packet. (May also reference procedure A.2-204 Critical: N OFF-SITE PROTECTION ACTON RECOMMENDATIONS)

Standard: Locates General Emergency packet.

Evaluator Cue: When examinee locates General Emergency packet, hand them a copy of the material from the packet.

NOTE: The items covered by JPM steps 2 and 3 may be done in any order as long as the standard for each step is met.

Performance: SATISFACTORY UNSATISFACTORY Comments:

M/jlg Page 4 of 9

QF-1030-11 Rev. 2 (FP-T-SAT-30)

Performance Step: 2 6.1.1 Initiate Form 5790-102-02 (MONTICELLO EMERGENCY NOTIFICATION Critical: Y REPORT FORM)

A. Complete the Protective Action Recommendations section recommending sheltering or an evacuation of a 2 mile radius and 5 miles downwind and advise the remainder of the plume EPZ to go indoors to monitor EAS broadcasts. (See Figure 7.3.A for assistance.)

B. Determine which geopolitical subareas are affected by referring to the Sector-Subarea Conversion Table on Form 5790-102-02 Standard: Complete Section 10 of Form 5790-102-02. The grading standard is as follows:

  • Item B is circled.
  • The blank in front of Sectors out to 2 miles contains the word ALL
  • The blank in front of Sectors out to 5 miles contains H,J,K
  • Only the following subareas are circled: 2, 5W and 5S.

Evaluator Cue: None NOTE: See attached form with data filled in.

Performance: SATISFACTORY UNSATISFACTORY Comments:

M/jlg Page 5 of 9

QF-1030-11 Rev. 2 (FP-T-SAT-30)

Performance Step: 3 Initiate Form 5790-102-02 Critical: Y C. Ensure completion of the remaining sections of Form 5790-102-02 and submit the completed form to the ED for approval.

Standard: The grading standard is as follows:

  • Section 1: item B should be circled (not critical).
  • Section 2: item B should be circled.
  • Section 4: item D should be circled.
  • Section 5: item A circled (not critical) and date and time filled in and EAL RG1.1.
  • Section 6: item B should be circled.
  • Section 7: item B should be circled (not critical).
  • Section 8: Wind direction is 0 degrees and affected downwind sectors H, J and K should be circled.
  • Section 9: Wind speed of 13 mph and stability class E circled (stability class not critical).
  • Section 11: Examinee should indicate that they would use the label from the General emergency packet here (specifically the label for RG1.1) or they may write the IC description for RG1 in the space provided.

Evaluator Cue: None NOTE: See attached form with data filled in.

Performance: SATISFACTORY UNSATISFACTORY Comments:

Performance Step: 4 INFORM EVALUATOR THAT THE TASK HAS BEEN COMPLETED.

Critical: N Standard: Operator informs evaluator that the task is completed.

Evaluator Cue: None Performance: SATISFACTORY UNSATISFACTORY Comments:

Terminating Cues: When told the actions are complete, acknowledge, and state the JPM is complete.

Stop Time:

Critical Time ___ ____

M/jlg Page 6 of 9

QF-1030-11 Rev. 2 (FP-T-SAT-30)

TURNOVER SHEET INITIAL CONDITIONS:

  • THIS IS A DRILL.
  • The plant is shutdown in an Emergency Condition. An escalation to a General Emergency has just been declared (EAL RG1.1, Stack Effluent Monitor A exceeds 2.1E+8 curies/second).
  • Current Met Data is:

Wind direction (from): 0 degrees Wind speed: 13 mph Temperature: 85°F Precipitation: none Ch. 11 - Diff. Temp: -0.79 Dose assessment is not currently available INITIATING CUES (IF APPLICABLE):

  • THIS IS A DRILL.
  • Initiate and complete Form 5790-102-02 (MONTICELLO EMERGENCY NOTIFICATION REPORT FORM) and provide to Shift Manager/Emergency Director when complete.
  • This is a time critical JPM
  • THIS IS A DRILL.

M/jlg Page 7 of 9

QF-1030-11 Rev. 2 (FP-T-SAT-30)

JPM-A.2-204-004 (OFF-SITE PROTECTIVE ACTION RECOMMENDATIONS) Rev. 2 SIMULATOR SET UP:

Admin JPM; no simulator setup required.

SIMULATOR - MALFUNCTIONS:

MALF ID MALFUNCTION TITLE DELAY RAMP EVENT VALUE FINAL.

1.

2.

SIMULATOR - OVERRIDES:

OVERRIDE ID. OVERRIDE DELAY RAMP EVENT VALUE FINAL DESCRIPTION 1.

2.

SIMULATOR - REMOTE FUNCTIONS:

REMOTE REMOTE FUNCTION TITLE DELAY RAMP EVENT VALUE FINAL FUNC. No.

1.

2.

M/jlg Page 8 of 9

QF-1030-11 Rev. 2 (FP-T-SAT-30)

JPM-A.2-204-004 (OFF-SITE PROTECTIVE ACTION RECOMMENDATIONS) Rev. 2 ATTACHMENT 1 JOB PERFORMANCE MEASURE VALIDATION CHECKLIST ALL STEPS IN THIS CHECKLIST ARE TO BE PERFORMED UPON INITIAL VALIDATION AND PRIOR TO USE.

REVIEW STATEMENTS YES NO N/A

1. Are all items on the signature page filled in correctly?
2. Has the JPM been reviewed and validated by SMEs?
3. Can the required conditions for the JPM be appropriately established in the simulator if required?
4. Does the performance steps accurately reflect trainees actions in accordance with plant procedures?
5. Is the standard for each performance item specific as to what controls, indications and ranges are required to evaluate if the trainee properly performed the step?
6. Has the completion time been established based on validation data or incumbent experience?
7. If the task is time critical, is the time critical portion based upon actual task performance requirements?
8. Is the Licensee level appropriate for the task being evaluated if required?
9. Is the K/A appropriate to the task and to the licensee level if required?
10. Have the performance steps been identified and typed (Critical /

Sequence / Time Critical) appropriately?

11. Have all special tools and equipment needed to perform the task been identified and made available to the trainee?
12. Are all references identified, current, accurate, and available to the trainee?
13. Have all required cues (as anticipated) been identified for the evaluator to assist task completion?

All questions/statements must be answered YES or the JPM is not valid for use. If all questions/statements are answered YES then the JPM is considered valid and can be performed as written. The individual(s) performing the validation shall sign and date this form.

Validation Personnel /Date Validation Personnel/Date

__________________________ __________________________

Validation Personnel /Date Validation Personnel/Date

__________________________ __________________________

Validation Personnel /Date Validation Personnel/Date

__________________________ __________________________

Validation Personnel /Date Validation Personnel/Date Historical Record: (Optional)

M/jlg Page 9 of 9