{{#Wiki_filter:Calvert Cliffs Nuclear Power Plant 1650 Calvert Cliffs Parkway Lusby, Maryland 20657 CENG a joint venture of 0Constellation eD wEnergy- O CALVERT CLIFFS NUCLEAR POWER PLANT February 22, 2012 U. S. Nuclear Regulatory Commission Washington, DC 20555 ATTENTION:
{{#Wiki_filter:Calvert Cliffs Nuclear Power Plant                               1650 Calvert Cliffs Parkway Lusby, Maryland 20657 CENG a joint venture of 0Constellation           eD wEnergy-                   O CALVERT CLIFFS NUCLEAR POWER PLANT February 22, 2012 U. S. Nuclear Regulatory Commission Washington, DC 20555 ATTENTION:                 Document Control Desk


==SUBJECT:==
==SUBJECT:==
Document Control Desk Calvert Cliffs Nuclear Power Plant Unit Nos. 1 & 2; Docket Nos. 50-317 & 50-318 Independent Spent Fuel Storage Installation; Docket No. 72-8 Report of Changes, Tests, and Experiments  
Calvert Cliffs Nuclear Power Plant Unit Nos. 1 & 2; Docket Nos. 50-317 & 50-318 Independent Spent Fuel Storage Installation; Docket No. 72-8 Report of Changes, Tests, and Experiments - 10 CFR 50.59 and 10 CFR 72.48 In accordance with 10 CFR 50.59(d)(2) and 10 CFR 72.48(d)(2), a report of changes, tests and experiments is provided as Attachment (1). This attachment contains brief descriptions of changes, tests, and experiments approved under the provisions of 10 CFR 50.59 between January 1, 2011 and December 31, 2011. There were no approved changes, tests, and experiments under 10 CFR 72.48 for the January 1, 2011 to December 31, 2011 timeframe.
-10 CFR 50.59 and 10 CFR 72.48 In accordance with 10 CFR 50.59(d)(2) and 10 CFR 72.48(d)(2), a report of changes, tests and experiments is provided as Attachment (1). This attachment contains brief descriptions of changes, tests, and experiments approved under the provisions of 10 CFR 50.59 between January 1, 2011 and December 31, 2011. There were no approved changes, tests, and experiments under 10 CFR 72.48 for the January 1, 2011 to December 31, 2011 timeframe.
Should you have questions regarding this matter, please contact Mr. Douglas E. Lauver at (410) 495-5219.
Should you have questions regarding this matter, please contact Mr. Douglas E. Lauver at (410) 495-5219.Manager -Engineering Services JJS/PSF/bjd
Manager - Engineering Services JJS/PSF/bjd


==Attachment:==
==Attachment:==
(1)    Calvert Cliffs Nuclear Power Plant Report of Changes, Tests, and Experiments
[10 CFR 50.59(d)(2) and 10 CFR 72.48(d)(2)]
cc:      D. V. Pickett, NRC                                S. Gray, DNR W. M. Dean, NRC                                    C. Haney, NMSS Resident Inspector, NRC EJ/ISP)c


(1) Calvert Cliffs Nuclear Power Plant Report of Changes, Tests, and Experiments
ATTACHMENT (1)
CALVERT CLIFFS NUCLEAR POWER PLANT REPORT OF CHANGES, TESTS, AND EXPERIMENTS
[10 CFR 50.59(d)(2) and 10 CFR 72.48(d)(2)]
[10 CFR 50.59(d)(2) and 10 CFR 72.48(d)(2)]
cc: D. V. Pickett, NRC W. M. Dean, NRC Resident Inspector, NRC S. Gray, DNR C. Haney, NMSS EJ/ISP)c ATTACHMENT (1)CALVERT CLIFFS NUCLEAR POWER PLANT REPORT OF CHANGES, TESTS, AND EXPERIMENTS
Calvert Cliffs Nuclear Power Plant, LLC February 22, 2012
[10 CFR 50.59(d)(2) and 10 CFR 72.48(d)(2)]
 
Calvert Cliffs Nuclear Power Plant, LLC February 22, 2012 ATTACHMENT (1)CALVERT CLIFFS NUCLEAR POWER PLANT REPORT OF CHANGES, TESTS, AND EXPERIMENTS
ATTACHMENT (1)
CALVERT CLIFFS NUCLEAR POWER PLANT REPORT OF CHANGES, TESTS, AND EXPERIMENTS
[10 CFR 50.59(d)(2) and 10 CFR 72.48(d)(2)]
[10 CFR 50.59(d)(2) and 10 CFR 72.48(d)(2)]
Document Id Doc Type Rev Status Revision Date Issued SE00508 50.59 60 0000 3/7/11 Subject Evaluate One Keyway (1/8" x 1/8" x 5/8") from the flange machine being dropped into the Reactor Coolant System.Summary The proposed activity 'accepts as is' an identified loose part in the reactor vessel or reactor coolant system. The loose part is a small stainless steel key (1/8" x 1/8" x 5/8"). The debris is assumed to remain within the reactor vessel or more likely migrate to a number of potential locations including:
Document Id                 Doc Type                         Rev Status                         Revision                         Date Issued SE00508                     50.59                           60                                 0000                             3/7/11 Subject       Evaluate One Keyway (1/8" x 1/8" x 5/8") from the flange machine being dropped into the Reactor Coolant System.
steam generator inlet (hot leg) bowl or be captured within a steam generator u-tube, or the shutdown cooling suction nozzle on 22 hot leg, the pressurizer surge line on the 21 hot leg, or if the loose part is small enough it could travel through a steam generator U-tube and exit out into a cold leg and either into the reactor vessel bottom or interfacing Reactor Coolant System systems. This evaluation considered the likelihood and consequences of loose part intrusion into any one of these locations and concluded that there are no credible failure mechanisms that exceed the design basis described for accidents and malfunctions in the Updated Final Safety Analysis Report.1}}
Summary       The proposed activity 'accepts as is' an identified loose part in the reactor vessel or reactor coolant system. The loose part is a small stainless steel key (1/8" x 1/8" x 5/8"). The debris is assumed to remain within the reactor vessel or more likely migrate to a number of potential locations including: steam generator inlet (hot leg) bowl or be captured within a steam generator u-tube, or the shutdown cooling suction nozzle on 22 hot leg, the pressurizer surge line on the 21 hot leg, or if the loose part is small enough it could travel through a steam generator U-tube and exit out into a cold leg and either into the reactor vessel bottom or interfacing Reactor Coolant System systems. This evaluation considered the likelihood and consequences of loose part intrusion into any one of these locations and concluded that there are no credible failure mechanisms that exceed the design basis described for accidents and malfunctions in the Updated Final Safety Analysis Report.
1}}

Latest revision as of 07:49, 12 November 2019

Independent Spent Fuel Storage Installation, Report of Changes, Tests, and Experiments - 10 CFR 50.59 and 10 CFR 72.48
ML12055A048
Person / Time
Site: Calvert Cliffs  Constellation icon.png
Issue date: 02/22/2012
From: John Stanley
Calvert Cliffs, Constellation Energy Group, EDF Development
To:
Document Control Desk, Office of Nuclear Material Safety and Safeguards, Office of Nuclear Reactor Regulation
References
Download: ML12055A048 (3)


Text

Calvert Cliffs Nuclear Power Plant 1650 Calvert Cliffs Parkway Lusby, Maryland 20657 CENG a joint venture of 0Constellation eD wEnergy- O CALVERT CLIFFS NUCLEAR POWER PLANT February 22, 2012 U. S. Nuclear Regulatory Commission Washington, DC 20555 ATTENTION: Document Control Desk

SUBJECT:

Calvert Cliffs Nuclear Power Plant Unit Nos. 1 & 2; Docket Nos. 50-317 & 50-318 Independent Spent Fuel Storage Installation; Docket No. 72-8 Report of Changes, Tests, and Experiments - 10 CFR 50.59 and 10 CFR 72.48 In accordance with 10 CFR 50.59(d)(2) and 10 CFR 72.48(d)(2), a report of changes, tests and experiments is provided as Attachment (1). This attachment contains brief descriptions of changes, tests, and experiments approved under the provisions of 10 CFR 50.59 between January 1, 2011 and December 31, 2011. There were no approved changes, tests, and experiments under 10 CFR 72.48 for the January 1, 2011 to December 31, 2011 timeframe.

Should you have questions regarding this matter, please contact Mr. Douglas E. Lauver at (410) 495-5219.

Manager - Engineering Services JJS/PSF/bjd

Attachment:

(1) Calvert Cliffs Nuclear Power Plant Report of Changes, Tests, and Experiments

[10 CFR 50.59(d)(2) and 10 CFR 72.48(d)(2)]

cc: D. V. Pickett, NRC S. Gray, DNR W. M. Dean, NRC C. Haney, NMSS Resident Inspector, NRC EJ/ISP)c

ATTACHMENT (1)

CALVERT CLIFFS NUCLEAR POWER PLANT REPORT OF CHANGES, TESTS, AND EXPERIMENTS

[10 CFR 50.59(d)(2) and 10 CFR 72.48(d)(2)]

Calvert Cliffs Nuclear Power Plant, LLC February 22, 2012

ATTACHMENT (1)

CALVERT CLIFFS NUCLEAR POWER PLANT REPORT OF CHANGES, TESTS, AND EXPERIMENTS

[10 CFR 50.59(d)(2) and 10 CFR 72.48(d)(2)]

Document Id Doc Type Rev Status Revision Date Issued SE00508 50.59 60 0000 3/7/11 Subject Evaluate One Keyway (1/8" x 1/8" x 5/8") from the flange machine being dropped into the Reactor Coolant System.

Summary The proposed activity 'accepts as is' an identified loose part in the reactor vessel or reactor coolant system. The loose part is a small stainless steel key (1/8" x 1/8" x 5/8"). The debris is assumed to remain within the reactor vessel or more likely migrate to a number of potential locations including: steam generator inlet (hot leg) bowl or be captured within a steam generator u-tube, or the shutdown cooling suction nozzle on 22 hot leg, the pressurizer surge line on the 21 hot leg, or if the loose part is small enough it could travel through a steam generator U-tube and exit out into a cold leg and either into the reactor vessel bottom or interfacing Reactor Coolant System systems. This evaluation considered the likelihood and consequences of loose part intrusion into any one of these locations and concluded that there are no credible failure mechanisms that exceed the design basis described for accidents and malfunctions in the Updated Final Safety Analysis Report.