|
|
Line 18: |
Line 18: |
|
| |
|
| =Text= | | =Text= |
| {{#Wiki_filter:December 9, 2015 | | {{#Wiki_filter:December 9, 2015 Mr. Ralph Butler, Executive Director University of Missouri-Columbia Research Reactor Center 1513 Research Park Drive Columbia, MO 65211 |
| | |
| Mr. Ralph Butler, Executive Director | |
| | |
| University of Missouri-Columbia | |
| | |
| Research Reactor Center 1513 Research Park Drive Columbia, MO 65211 | |
|
| |
|
| ==SUBJECT:== | | ==SUBJECT:== |
| UNIVERSITY OF MISSOURI AT COLUMBIA - REVIEW OF THE EMERGENCY PLAN IN SUPPORT OF THE LICENSE RENEWAL (TAC NO. ME1580) | | UNIVERSITY OF MISSOURI AT COLUMBIA - REVIEW OF THE EMERGENCY PLAN IN SUPPORT OF THE LICENSE RENEWAL (TAC NO. ME1580) |
|
| |
|
| ==Dear Mr. Butler:== | | ==Dear Mr. Butler:== |
|
| |
|
| As part of your application for renewal of Facility Operating License No. R-103, dated August 31, 2006 (a redacted version of the application is available on the U.S. Nuclear Regulatory Commission (NRC's) public web site at www.nrc.gov under Agencywide Documents Access and Management System (ADAMS) Accession Nos.: ML062540114 - cover letter; ML092110573 - Safety Analysis Report (SAR), Chapters 1-9; ML092110597 - SAR, Chapters 10-18), as supplemented, for the University of Missouri at Columbia Research Reactor (MURR), the NRC staff performed a review of the MURR Emergency Plan Revision 17, dated | | As part of your application for renewal of Facility Operating License No. R-103, dated August 31, 2006 (a redacted version of the application is available on the U.S. Nuclear Regulatory Commission (NRCs) public web site at www.nrc.gov under Agencywide Documents Access and Management System (ADAMS) Accession Nos.: ML062540114 - cover letter; ML092110573 - Safety Analysis Report (SAR), Chapters 1-9; ML092110597 - SAR, Chapters 10-18), as supplemented, for the University of Missouri at Columbia Research Reactor (MURR), the NRC staff performed a review of the MURR Emergency Plan Revision 17, dated October 17, 2014. |
| | |
| October 17, 2014. | |
| We have completed our review of the MURR Emergency Plan, Revision 17, and concluded that it remains compliant with the regulations and guidance below: | | We have completed our review of the MURR Emergency Plan, Revision 17, and concluded that it remains compliant with the regulations and guidance below: |
| * Title 10 of the Code of Federal Regulations, Part 50, Section 50.34, paragraph 50.34(b)(6)(v) | | * Title 10 of the Code of Federal Regulations, Part 50, Section 50.34, paragraph 50.34(b)(6)(v) |
| * Regulatory Guide 2.6, Revision 1, "Emergency Planning for Research and Test Reactors," issued March 1983 (ADAMS Accession No. ML003740234) | | * Regulatory Guide 2.6, Revision 1, Emergency Planning for Research and Test Reactors, issued March 1983 (ADAMS Accession No. ML003740234) |
| * American National Standards Institute/American Nuclear Society-15.16-2015, "Emergency Planning for Research Reactors" | | * American National Standards Institute/American Nuclear Society-15.16-2015, Emergency Planning for Research Reactors |
| * NUREG-0849, "Standard Review Plan for the Review and Evaluation of Emergency Plans for Research and Test Reactors," issued October 1983 (ADAMS Accession No. | | * NUREG-0849, Standard Review Plan for the Review and Evaluation of Emergency Plans for Research and Test Reactors, issued October 1983 (ADAMS Accession No. |
| ML062190191) | | ML062190191) |
| * NRC Information Notice 97-34, "Deficiencies in Licensee Submittals Regarding Terminology for Radiological Emergency Action Levels in Accordance with the New Part 20," dated June 12, 1997 | | * NRC Information Notice 97-34, Deficiencies in Licensee Submittals Regarding Terminology for Radiological Emergency Action Levels in Accordance with the New Part 20, dated June 12, 1997 |
| * NRC Information Notice 92-79, "Nonpower Reactor Emergency Response," dated December 1, 1992 | | * NRC Information Notice 92-79, Nonpower Reactor Emergency Response, dated December 1, 1992 |
| | |
| We request that you continue to implement your approved Emergency Plan. If you have any questions regarding this review, please contact me at (301) 415-0893 or via electronic mail at Geoffrey.Wertz@nrc.gov. Sincerely, /Alexander Adams for RA/
| |
| Geoffrey A. Wertz, Project Manager Research and Test Reactors Licensing Branch
| |
| | |
| Division of Policy and Rulemaking Office of Nuclear Reactor Regulation Docket No. 50-186
| |
| | |
| cc: See next page
| |
| | |
| ML15331A049 *concurrence via email NRR-088
| |
| | |
| University of Missouri-Columbia Docket No. 50-186
| |
| | |
| cc: Les Foyto, Associate Director Reactor and Facilities Operations University of Missouri - Columbia
| |
| | |
| Research Reactor Center 1513 Research Park Drive Columbia, MO 65211
| |
| | |
| Homeland Security Coordinator
| |
| | |
| Missouri Office of Homeland Security P.O. Box 749 Jefferson City, MO 65102
| |
| | |
| Planner, Dept of Health and Senior Services Section for Environmental Public Health P.O. Box 570 Jefferson City, MO 65102-0570
| |
| | |
| Deputy Director for Policy Department of Natural Resources 1101 Riverside Drive Fourth Floor East Jefferson City, MO 65101
| |
|
| |
|
| A-95 Coordinator Division of Planning Office of Administration P.O. Box 809, State Capitol Building Jefferson City, MO 65101 | | R. Butler We request that you continue to implement your approved Emergency Plan. If you have any questions regarding this review, please contact me at (301) 415-0893 or via electronic mail at Geoffrey.Wertz@nrc.gov. |
| | Sincerely, |
| | /Alexander Adams for RA/ |
| | Geoffrey A. Wertz, Project Manager Research and Test Reactors Licensing Branch Division of Policy and Rulemaking Office of Nuclear Reactor Regulation Docket No. 50-186 cc: See next page |
|
| |
|
| Test, Research, and Training
| | ML15331A049 *concurrence via email NRR-088 OFFICE DPR/PRLB/PM* DPR/PRLB/LA* DPR/PRLB/BC DPR/PRLB/PM NAME GWertz NParker AAdams (AAdams for GWertz) |
| | DATE 11/30/2015 11/30/2015 12/08/2015 12/09/2015 |
|
| |
|
| Reactor Newsletter University of Florida 202 Nuclear Sciences Center Gainesville, FL 32611}} | | University of Missouri-Columbia Docket No. 50-186 cc: |
| | Les Foyto, Associate Director Reactor and Facilities Operations University of Missouri - Columbia Research Reactor Center 1513 Research Park Drive Columbia, MO 65211 Homeland Security Coordinator Missouri Office of Homeland Security P.O. Box 749 Jefferson City, MO 65102 Planner, Dept of Health and Senior Services Section for Environmental Public Health P.O. Box 570 Jefferson City, MO 65102-0570 Deputy Director for Policy Department of Natural Resources 1101 Riverside Drive Fourth Floor East Jefferson City, MO 65101 A-95 Coordinator Division of Planning Office of Administration P.O. Box 809, State Capitol Building Jefferson City, MO 65101 Test, Research, and Training Reactor Newsletter University of Florida 202 Nuclear Sciences Center Gainesville, FL 32611}} |
Letter Sequence Approval |
---|
|
Initiation
- Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request
- Acceptance...
|
MONTHYEARML0917402832009-07-10010 July 2009 University of Missouri at Columbia - Request for Additional Information License Renewal Project stage: RAI ML13079A2162013-02-28028 February 2013 Letter from Kelly Mescher the Court in Sherman V. the Curators of the University of Missouri Project stage: Other ML13079A2152013-03-0505 March 2013 Statement of Intent Project stage: Other ML13079A2172013-03-12012 March 2013 Letter from Ralph A. Butler Enclosed with University of Missouri-Columbia Research Reactor'S Responses to the U.S. Nuclear Regulatory Commission'S (NRC) Request for Additional Information, Dated February 11, 2013, Regarding Our Renewal Requ Project stage: Request ML13079A2142013-03-12012 March 2013 Written Communication as Specified by 10 CFR 50.4(b)(1) Regarding the Response to the University of Missouri at Columbia - Request for Additional Information Updated Financial Information for License Renewal (TAC No. ME1580), Dated 02/11/20 Project stage: Request ML13079A2182013-03-12012 March 2013 University of Missouri System 2012 Financial Report Project stage: Other ML14324A7072014-12-0303 December 2014 Request for Additional Information Regarding the MURR License Renewal Review (Updated Info 11/19/2014) Project stage: RAI ML15034A4732015-01-28028 January 2015 University of Missouri-Columbia Research Reactor Response to NRC Request for Additional Information Re License Renewal Application Project stage: Response to RAI ML15034A4742015-01-28028 January 2015 Written Communication as Specified by 10 CFR 50.4(b)(1) Regarding the Response to the University of Missouri at Columbia - Request for Additional Information Regarding the Renewal of Facility Operating License No. R-103 for the University o Project stage: Request ML15049A0392015-02-12012 February 2015 University of Missouri-Columbia - Response to Request for Additional Information Regarding the Renewal of Facility Operating License No. R- 103 Dated December.3, 2014 Project stage: Response to RAI ML15051A0042015-02-20020 February 2015 University of Missouri at Columbia, Request for Withholding Information from Public Disclosure Project stage: Withholding Request Acceptance ML15098A6482015-04-17017 April 2015 University of Missouri at Columbia - Request for Additional Information Regarding the Renewal of Facility Operating License No. R-103 for the University of Missouri at Columbia Research Reactor Project stage: RAI ML15154B8122015-07-21021 July 2015 University of Missouri at Columbia Acknowledgement of the Imposition of an Administrative Limit for the Quantity of Iodine Processed in the Iodine Processing Laboratory Hot Cells for Facility Operating License No. R 103 Project stage: Other ML15224B3092015-09-14014 September 2015 University of Missouri at Columbia - Request for Additional Information Regarding, Physical Security Plan Review for Renewal of Facility Operating License No. R-103 for the University of Missouri at Columbia Research Reactor Project stage: RAI ML15260A4392015-09-15015 September 2015 University of Missouri-Columbia - Request for a Copy of the Emergency Plan in Support of the Renewal of Amended Facility License No. R-103 Project stage: Request ML15275A3142015-10-0101 October 2015 University of Missouri, Columbia - Responses to NRC Request for Additional Information, Dated April 17, 2015, Regarding Renewal Request for Amended Facility Operating License Project stage: Response to RAI ML15350A0882015-10-0606 October 2015 State of Missouri, Federal Assistance Clearinghouse Letter NRC Request for Additional Info Regarding the Physical Security Plan Review for Renewal of Facility Operating License No.R-103 for the Univ. of Missouri at Columbia Research Reactor Project stage: Request ML15280A3142015-10-28028 October 2015 University of Missouri at Columbia Research Reactor Request for Additional Information Regarding the Proposed Technical Specifications for the Murr License Renewal Review Project stage: RAI ML15344A0232015-12-0202 December 2015 University of Missouri(Um) at Columbia - Response to Request for Additional Information Regarding Physical Security Plan Review for Renewal of Facility Operating License No. R-103 for the Um at Columbia Research Reactor Project stage: Response to RAI ML15331A0492015-12-0909 December 2015 University of Missouri at Columbia Review of the Emergency Plan in Support of the License Renewal Project stage: Approval ML15337A1752015-12-17017 December 2015 University of Missouri at Columbia Clarifications Needed to NRC Staff Request for Additional Information Regarding the Renewal of Facility Operating License No. R-103 for the University of Missouri at Columbia Research Reactor Project stage: RAI ML16028A2552016-02-0808 February 2016 University of Missouri at Columbia; Request for Additional Information Updated Financial Information for Renewal of Facility Operating License No. R-103 for the University of Missouri at Columbia Research Reactor (Tac No. Me1580) Project stage: RAI ML16103A5302016-04-0808 April 2016 Univ. of Missouri, Columbia - Transmittal of Responses to NRC Request for Additional Information Dated February 8, 2016 Regarding Renewal Request for Amendment Project stage: Response to RAI ML16110A1642016-04-15015 April 2016 University of Missouri - Columbia Research Reactor, Response to Request for Additional Information on License Renewal Amendment Request Project stage: Response to RAI ML16155A1322016-05-31031 May 2016 University of Missouri-Columbia Research Reactor'S Responses to the NRC Request for Additional Information, Dated October 28, 2015, Regarding Our Renewal Request for Amended Facility Operating License No. R-103 Project stage: Request ML16209A2362016-07-25025 July 2016 University of Missouri, Response to Request for Additional Information Regarding the Proposed Technical Specifications for the License Renewal Project stage: Response to RAI ML16215A4152016-08-0202 August 2016 MURR Hazards Summary Report - Addendums 1-5 Redacted, in Support of an Application for a Research Reactor Project stage: Request ML16216A1222016-08-24024 August 2016 University of Missouri at Columbia - Request for Additional Information Financial Information for Renewal of Facility Operating License No. R-103 for the University of Missouri at Columbia Research Reactor Project stage: RAI ML16239A4252016-09-0707 September 2016 University of Missouri at Columbia - Request for Additional Information Regarding the Proposed Technical Specifications for the Renewal of Facility Operating License No. R-103 for the University of Missouri at Columbia Research Reactor Project stage: RAI ML16313A5172016-11-0707 November 2016 University If Missouri, Response to NRC Request for RAI, Dated September 7, 2016 Regarding License Renewal Amendment Project stage: Request ML16321A4552016-11-15015 November 2016 Written Communication as Specified by 10 CPR 73.4 Regarding Changes to the University of Missouri-Columbia Research Reactor Physical Security Plan That Was Previously Submitted in Response to University of Missouri at Columbia - Request for Project stage: Request ML16321A4852016-11-15015 November 2016 University of Missouri-Columbia Research Reactor - Response to Request for Additional Information Regarding License Renewal Request Project stage: Response to RAI ML15289A0142016-11-18018 November 2016 FRN: General Notice: Environmental Assessment and Finding of No Significant Impact RE: Renewal of Facility Operating License No. R-103, University of Missouri at Columbia Project stage: Request ML15289A0122016-11-18018 November 2016 University of Missouri at Columbia - Environmental Assessment and Finding of No Significant Impact Regarding Renewal of Facility Operating License No. R-103 for the University of Missouri at Columbia Research Reactor Project stage: Other ML16350A4242016-12-14014 December 2016 Written Communication as Specified by 10 CFR 50.4(b)(1) Regarding Responses to the University of Missouri at Columbia - Request for Additional Information Regarding the Proposed Technical Specifications for the Renewal of Facility Operating Project stage: Request ML16124A8872017-01-0404 January 2017 the University of Missouri Columbia Safety Evaluation Report for the Renewal of the Facility Operating License for the Nuclear Research Reactor Project stage: Approval 2015-07-21
[Table View] |
|
---|
Category:Letter
MONTHYEAR05000186/LER-2024-003, University of Missouri Research Reactor, Specification Deviation from Technical Specification 3.2.g.212024-10-25025 October 2024 University of Missouri Research Reactor, Specification Deviation from Technical Specification 3.2.g.21 ML24281A1322024-10-0404 October 2024 University of Missouri - Notification of NIST Award 60NANB23D160 NEPA Catex ML24270A0992024-10-0101 October 2024 Examination Confirmation Letter No. 50-186/Ol-25-01, University of Missouri - Columbia ML24142A1432024-08-27027 August 2024 Examination Result Letter No. 50-186/OL-24-02, University of Missouri - Columbia ML24142A1422024-08-27027 August 2024 Examination Report Letter No. 50-186/OL-24-02, University of Missouri - Columbia ML24184A1132024-07-0202 July 2024 Written Communication as Required by University of Missouri Research Reactor Technical Specification 6.6.c(3) Regarding a Deviation from Technical Specification 3.10.d IR 05000186/20242012024-05-29029 May 2024 The Curators of the University of Missouri - U.S. Nuclear Regulatory Commission Safety Inspection Report No. 05000186/2024201 05000186/LER-2024-001, Written Communication as Required by by LER 2024-001-00 for University of Missouri Research Reactor Technical Specification 6.6.c(3) Re Deviation from Technical Specification 3.1 0.d2024-05-23023 May 2024 Written Communication as Required by by LER 2024-001-00 for University of Missouri Research Reactor Technical Specification 6.6.c(3) Re Deviation from Technical Specification 3.1 0.d ML24081A1332024-04-0202 April 2024 University of Missouri-Columbia (MURR) – Change of Facility Project Manager ML24044A1162024-03-0101 March 2024 Examination Confirmation Letter No. 50-186/OL-24-02, University of Missouri-Columbia ML24064A1922024-03-0101 March 2024 Federal Funding for the Conversion of the University of Missouri-Columbia Research Reactor from Highly-Enriched Uranium Fuel to Low-Enriched Uranium Fuel ML24059A4412024-02-28028 February 2024 Univ. of Missouri - Columbia - Submittal of Annual Operating Report Technical Specification 6.6.e IR 05000186/20232022023-12-12012 December 2023 The Curators of the University of Missouri - U.S. Nuclear Regulatory Commission Safety Inspection Report No. 05000186/2023202 ML23198A0222023-08-29029 August 2023 Examination Report Letter No. 50-186/OL-23-02, University of Missouri - Columbia ML23198A0232023-08-29029 August 2023 Examination Result Letter No. 50-186/OL-23-02, University of Missouri-Columbia ML23221A1172023-08-0303 August 2023 Written Communication as Specified by 10 CFR 50.4(b)(4) Regarding the Submittal of the Physical Security Plan for the University of Missouri Research Reactor as a Part of the Process to Renew Amended Facility Operating License R-103 ML23213A0592023-08-0101 August 2023 Written Communication as Specified by University of Missouri Research Reactor Technical Specification 6.6.2(d) Regarding a Permanent Change in the Facility Organization Involving the Executive Director ML23186A2132023-07-31031 July 2023 Examination Confirmation Letter No. 50-186/OL-23-03, University of Missouri - Columbia IR 05000186/20232012023-07-31031 July 2023 The Curators of the University of Missouri – U.S. Nuclear Regulatory Commission Safety Inspection Report No. 05000186/2023201 05000186/LER-2023-003, University of Missouri - Columbia Research Reactor, Written Communication as Required Technical Specification 6.6.c(3) Regarding a Deviation from Technical Specification 3.2.b2023-06-0606 June 2023 University of Missouri - Columbia Research Reactor, Written Communication as Required Technical Specification 6.6.c(3) Regarding a Deviation from Technical Specification 3.2.b ML23124A0422023-05-0808 May 2023 Examination Confirmation Letter 50-186/OL-23-02, University of Missouri - Columbia ML23103A0742023-04-10010 April 2023 University of Missouri, Columbia Research Reactor, Shipment of Radioactive Material Shipment Identifier MURR 23-01 Highway Route Controlled Quantity ML23024A2772023-04-0707 April 2023 Cover Letter for the Security Inspection Report for the University of Missouri (Public) - October 2022 ML23087A1132023-03-29029 March 2023 Examination Report No. 50-186/OL-23-01, University of Missouri-Columbia ML23089A3162023-03-29029 March 2023 Letter Notifying Univ. of Missouri That Us Dept. of Energy Funding Will Not Be Available in Fiscal Year 2023 to Complete the Conversion of MURR to LEU Fuel ML23087A1142023-03-29029 March 2023 Examination Results Letter No. 50-186/OL-23-01, University of Missouri - Columbia ML23055B1372023-02-24024 February 2023 Submittal of Annual Operating Report for the University of Missouri-Columbia Research Reactor as Required by MURR Technical Specification 6.6.e IR 05000186/20222022023-02-23023 February 2023 The Curators of the University of Missouri - U.S. Nuclear Regulatory Commission Routine Inspection Report No. 05000186/2022202 - Cover Letter and Enclosure ML23031A0132023-02-14014 February 2023 Examination Confirmation Letter No. 50-186/OL-23-01, University of Missouri-Columbia ML23017A2072023-01-13013 January 2023 Written Communication as Required by University of Missouri Research Reactor Technical Specification 6.6.c(3) Regarding a Deviation from Technical Specification 6.1.f ML22349A0422022-12-0808 December 2022 Written Communication as Specified in 10 CFR 50.54(b)(5) Regarding Changes to the University of Missouri-Columbia Research Reactor Facility Emergency Plan Without Prior Commission Approval Pursuant to 10 CFR 50.54(q)(3) ML22314A2102022-11-0909 November 2022 Written Communication as Required by Technical Specification 6.6.d(2), Other Reports, Regarding a Change in University of Missouri-Columbia Research Reactor Organization Involving the Reactor Facility Director ML22304A0042022-10-27027 October 2022 University of Missouri - Columbia, Shipment of Radioactive Material, Highway Route Controlled Quantity ML22291A0322022-10-14014 October 2022 University of Missouri Written Communication as Required by 10 CFR 73, Appendix G Regarding a Deviation from the MURR Physical Security Plan ML22290A0042022-10-12012 October 2022 University of Missouri-Columbia Research Reactor, Reportable Event Report Pursuant to 20.2201(a)(ii) Regarding Loss of Licensed Material During Shipment IR 05000186/20222012022-06-14014 June 2022 The Curators of the University of Missouri - U.S. NRC Routine Inspection Report No. 05000186/2022201 ML22158A0792022-06-0606 June 2022 Submittal of Revised Annual Operating Report for the University of Missouri-Columbia Research Reactor as Required by MURR Technical Specification 6.6.e ML22097A0592022-04-0707 April 2022 Approval for Spent Nuclear Fuel Highway Route Application - NRC Route No. 182D - Docket Number 050-0186 ML22088A0782022-03-25025 March 2022 Univ. of Missouri, Federal Funding for the Conversion of the Columbia Research Reactor from Highly-Enriched Uranium Fuel to Low-Enriched Uranium Fuel IR 05000186/20212032022-03-0202 March 2022 The Curators of the University of Missouri U.S. Nuclear Regulatory Commission Routine Inspection Report No. 05000186/2021203 ML22056A5162022-02-25025 February 2022 Submittal of Annual Operating Report for the University of Missouri-Columbia Research Reactor as Required by MURR Technical Specification 6.6.e ML22038A6012022-02-0808 February 2022 Acceptance for Spent Nuclear Fuel Highway Route Application NRC No. 182D-Docket No. 050-0186 ML22013B1412022-01-21021 January 2022 Examination Confirmation Letter No. 50-186-OL-22-02, University of Missouri-Columbia 05000186/LER-2021-004, University of Missouri Research Reactor, Deviation from Technical Specification 3.2.g.102021-11-23023 November 2021 University of Missouri Research Reactor, Deviation from Technical Specification 3.2.g.10 ML21327A3042021-11-23023 November 2021 Written Communication as Required by University of Missouri Research Reactor Technical Specification 6.6.c(3) Regarding a Deviation from Technical Specification 3.2.f.6 ML21298A1972021-10-25025 October 2021 University of Missouri-Columbia Research Reactor - Written Communication as Required by University of Missouri Research Reactor Technical Specification 6.6.c(3) Regarding a Deviation from Technical Specification 3.2.g.6 ML21253A2482021-09-23023 September 2021 Examination Confirmation Letter No. 50-186/OL-22-01, University of Missouri Columbia ML21221A3252021-08-0909 August 2021 University of Missouri-Columbia Research Reactor, Written Communication as Required by Technical Specification 6.6.c(3) Regarding a Deviation from Technical Specifications 3.2.a ML21217A2982021-08-0505 August 2021 University of Missouri-Columbia Research Reactor - Reportable Event Report Pursuant to 20.2203(a)(2)(iv) ML21215A4982021-07-0707 July 2021 Univ of Missouri, Submittal of Revised Road Transportation Security Plan for the Shipment of Irradiated Reactor Fuel 2024-08-27
[Table view] |
Text
December 9, 2015 Mr. Ralph Butler, Executive Director University of Missouri-Columbia Research Reactor Center 1513 Research Park Drive Columbia, MO 65211
SUBJECT:
UNIVERSITY OF MISSOURI AT COLUMBIA - REVIEW OF THE EMERGENCY PLAN IN SUPPORT OF THE LICENSE RENEWAL (TAC NO. ME1580)
Dear Mr. Butler:
As part of your application for renewal of Facility Operating License No. R-103, dated August 31, 2006 (a redacted version of the application is available on the U.S. Nuclear Regulatory Commission (NRCs) public web site at www.nrc.gov under Agencywide Documents Access and Management System (ADAMS) Accession Nos.: ML062540114 - cover letter; ML092110573 - Safety Analysis Report (SAR), Chapters 1-9; ML092110597 - SAR, Chapters 10-18), as supplemented, for the University of Missouri at Columbia Research Reactor (MURR), the NRC staff performed a review of the MURR Emergency Plan Revision 17, dated October 17, 2014.
We have completed our review of the MURR Emergency Plan, Revision 17, and concluded that it remains compliant with the regulations and guidance below:
- Title 10 of the Code of Federal Regulations, Part 50, Section 50.34, paragraph 50.34(b)(6)(v)
- American National Standards Institute/American Nuclear Society-15.16-2015, Emergency Planning for Research Reactors
- NUREG-0849, Standard Review Plan for the Review and Evaluation of Emergency Plans for Research and Test Reactors, issued October 1983 (ADAMS Accession No.
ML062190191)
- NRC Information Notice 97-34, Deficiencies in Licensee Submittals Regarding Terminology for Radiological Emergency Action Levels in Accordance with the New Part 20, dated June 12, 1997
R. Butler We request that you continue to implement your approved Emergency Plan. If you have any questions regarding this review, please contact me at (301) 415-0893 or via electronic mail at Geoffrey.Wertz@nrc.gov.
Sincerely,
/Alexander Adams for RA/
Geoffrey A. Wertz, Project Manager Research and Test Reactors Licensing Branch Division of Policy and Rulemaking Office of Nuclear Reactor Regulation Docket No. 50-186 cc: See next page
ML15331A049 *concurrence via email NRR-088 OFFICE DPR/PRLB/PM* DPR/PRLB/LA* DPR/PRLB/BC DPR/PRLB/PM NAME GWertz NParker AAdams (AAdams for GWertz)
DATE 11/30/2015 11/30/2015 12/08/2015 12/09/2015
University of Missouri-Columbia Docket No. 50-186 cc:
Les Foyto, Associate Director Reactor and Facilities Operations University of Missouri - Columbia Research Reactor Center 1513 Research Park Drive Columbia, MO 65211 Homeland Security Coordinator Missouri Office of Homeland Security P.O. Box 749 Jefferson City, MO 65102 Planner, Dept of Health and Senior Services Section for Environmental Public Health P.O. Box 570 Jefferson City, MO 65102-0570 Deputy Director for Policy Department of Natural Resources 1101 Riverside Drive Fourth Floor East Jefferson City, MO 65101 A-95 Coordinator Division of Planning Office of Administration P.O. Box 809, State Capitol Building Jefferson City, MO 65101 Test, Research, and Training Reactor Newsletter University of Florida 202 Nuclear Sciences Center Gainesville, FL 32611