{{#Wiki_filter:Public Service Electric and Gas Company P.O. Box 236 Hancocks Bridge, New Jersey 08038-0236 Nuclear Business Unit August 11, 1995 U. S. Nuclear Regulatory Commission Document Control Desk Washington, DC 20555 Attn: Document Control Desk SALEM GENERATING STATION LICENSE NO. DPR-70 DOCKET NO. 50-272 UNIT NO. 1 LICENSEE EVENT REPORT NO. 95-017-00 This Licensee Event Report entitled "Failure of Control Room Emergency Air Conditioning System to meet GDC 19 criteria is being submitted pursuant to the requirements of the Code of Federal Regulations 10CFR50.73{a)
{{#Wiki_filter:Public Service Electric and Gas Company P.O. Box 236 Hancocks Bridge, New Jersey 08038-0236 Nuclear Business Unit August 11, 1995 U. S. Nuclear Regulatory Commission Document Control Desk Washington,             DC 20555 Attn:                       Document Control Desk SALEM GENERATING STATION LICENSE NO.                 DPR-70 DOCKET NO.                 50-272 UNIT NO.                   1 LICENSEE EVENT REPORT NO. 95-017-00 This Licensee Event Report entitled "Failure of Control Room Emergency Air Conditioning System to meet GDC 19 criteria is being submitted pursuant to the requirements of the Code of Federal Regulations 10CFR50.73{a) (2) {ii). Attachment A contains those commitments which are currently outstanding related to this issue.
(2) {ii). Attachment A contains those commitments which are currently outstanding related to this issue. Attachment A SORC Mtg. 95-088 DVH Sincerely, General Manager Salem Operations c Distribution LER File The }Xl\YcT is in your t "./' .'" ,/1 .. *. i._ i .... 9508170064 950811 PDR ADOCK 05000272 S PDR Attachment A PSE&G Commitments for LER 272/95-017 The following item represents PSE&G commitments made to the Nuclear Regulatory Commission related to LER 272/95-017-00.
Sincerely,
The commitment is as follows: One Time Actions 1. Emergency procedures and the UFSAR will be revised to implement the pressurization operating mode as the design basis for the Emergency Air Conditioning System (EACS). The revised mode of operation for the EACS will be implemented prior to the.restart of the Salem units.}}
                                                              ~~~p._
General Manager Salem Operations Attachment A SORC Mtg. 95-088 DVH c                           Distribution LER File t "./' .'"
                                        ~..
                                            .-~ -~
i._ i ....
                                                        ,/1.*.
The }Xl\YcT is in your hand~.              9508170064 950811 PDR ADOCK 05000272 S                         PDR
 
Attachment A PSE&G Commitments for LER 272/95-017 The following item represents PSE&G commitments made to the Nuclear Regulatory Commission related to LER 272/95-017-00. The commitment is as follows:
One Time Actions
: 1. Emergency procedures and the UFSAR will be revised to implement the pressurization operating mode as the design basis for the Emergency Air Conditioning System (EACS). The revised mode of operation for the EACS will be implemented prior to the.restart of the Salem units.}}

Latest revision as of 10:10, 21 October 2019

Forwards LER 95-017 Re Failure of CR Emergency Air Conditioning Sys to Meet GDC 19 Criteria
ML18101A887
Person / Time
Site: Salem PSEG icon.png
Issue date: 08/11/1995
From: Warren C
Public Service Enterprise Group
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
Shared Package
ML18101A889 List:
References
NUDOCS 9508170064
Download: ML18101A887 (2)


Text

Public Service Electric and Gas Company P.O. Box 236 Hancocks Bridge, New Jersey 08038-0236 Nuclear Business Unit August 11, 1995 U. S. Nuclear Regulatory Commission Document Control Desk Washington, DC 20555 Attn: Document Control Desk SALEM GENERATING STATION LICENSE NO. DPR-70 DOCKET NO. 50-272 UNIT NO. 1 LICENSEE EVENT REPORT NO. 95-017-00 This Licensee Event Report entitled "Failure of Control Room Emergency Air Conditioning System to meet GDC 19 criteria is being submitted pursuant to the requirements of the Code of Federal Regulations 10CFR50.73{a) (2) {ii). Attachment A contains those commitments which are currently outstanding related to this issue.

Sincerely,

~~~p._

General Manager Salem Operations Attachment A SORC Mtg.95-088 DVH c Distribution LER File t "./' .'"

~..

.-~ -~

i._ i ....

,/1.*.

The }Xl\YcT is in your hand~. 9508170064 950811 PDR ADOCK 05000272 S PDR

Attachment A PSE&G Commitments for LER 272/95-017 The following item represents PSE&G commitments made to the Nuclear Regulatory Commission related to LER 272/95-017-00. The commitment is as follows:

One Time Actions

1. Emergency procedures and the UFSAR will be revised to implement the pressurization operating mode as the design basis for the Emergency Air Conditioning System (EACS). The revised mode of operation for the EACS will be implemented prior to the.restart of the Salem units.