:on 950718,CR Emergency Air Conditioning Sys Failed to Meet GDC 19 Criteria.Performed Calculactions to Identify Alternative Operating Mode for Eacs to Ensure That Requirements of GDC 19 Satisfied| ML18101A890 |
| Person / Time |
|---|
| Site: |
Salem  |
|---|
| Issue date: |
08/11/1995 |
|---|
| From: |
Zarechnak A Public Service Enterprise Group |
|---|
| To: |
|
|---|
| Shared Package |
|---|
| ML18101A889 |
List: |
|---|
| References |
|---|
| LER-95-017, LER-95-17, NUDOCS 9508170070 |
| Download: ML18101A890 (4) |
|
Similar Documents at Salem |
|---|
|
text
NRC FORM 366 (4-95)
I LE(4)
U.S. N AR REGULATORY COMMISSION LICENSEE EVENT REPORT (LER)
(See reverse for required number of digits/characters for each block)
OVED BY OMB NO. 3150-0104 EXPIRES 04/30/98 ESTIMATED BURDEN PER RESPONSE TO COMPLY WITH THIS MANDATORY INFORMATION COLLECTION REQUEST: 50.0 HRS.
REPORTED LESSONS LEARNED ARE INCORPORATED INTO THE LICENSING PROCESS AND FED BACK TO INDUSTRY.
FORWARD COMMENTS REGARDING BURDEN ESTIMATE TO THE INFORMATION AND RECORDS MANAGEMENT BRANCH (T-6 F33), U.S. NUCLEAR REGULATORY COMMISSION, WASHINGTON, DC 20555-0001, AND TO THE PAPERWORK REDUCTION PROJECT 05000-272
)
1OF4 FAILURE OF CONTROL ROOM EMERGENCY AIR CONDITIONING SYSTEM TO MEET GDC 19 CRITERIA A. Zarechnak 609 - 339 - 1755 11----+-----+------+-----+-----fll-----+----+----+------+------ll As a result of reviews being performed as part of corrective actions in LER-95-006 and other ongoing efforts, it was determined on July 18, 1995 that the GDC 19 requirements for control room habitability would have exceeded the 30 rem thyroid dose limit b¥ about 5 rem for a LOCA event at Salem.
This was reported on that date in accordance with 10 CFR 50.72.
The UFSAR uses an assumed value of 100 cfm for air in-leakage to the control room for calculating the dose.
The value used is considered to be much less than the current expected in-leakage.
Use of the realistic air in-leakage number results in an increased thyroid dose which exceeds the GDC 19 criteria when combined with ingress and egress dose.
Current Emergency Air Conditioning System configuration following a LOCA according to UFSAR section 9.4 is a 10 hour1.157407e-4 days <br />0.00278 hours <br />1.653439e-5 weeks <br />3.805e-6 months <br /> recirculation/one hour pressurization cycle.
To meet GDC 19 criteria the Emergency Air Conditioning System needs to be placed and maintained in the pressurization mode within three hours of a LOCA event.
This is a change to the design basis and will be reflected in emergency procedures prior to restart of the unit.
The UFSAR will also be revised.
This issue is reportable under 10 CFR 50.73(a) was outside the design basis of the plant.
9508170070 950811 PDR ADDCK 05000272 NRC FORM 366 (4-95)
S PDR (2) (ii) as a condition that (4-95)
U.S. NUCLEAR REGULATORY COMMISSION LICENSEE EVENT REPORT (LER)
TEXT CONTINUATION FACILITY NAME (1)
DOCKET LER NUMBER (6)
SALEM GENERATING STATION, UNIT 1 05000-272 YEAR I <>C:.NUUMBE~AL I ra::=u'I 95 017 00 TEA l (If more space 1s required, use aaa1uona1 copies or NHi., Form.:sooA) (17 I.
PLANT AND SYSTEM IDENTIFICATION
Westinghouse -
Pressurized Water Reactor PAGE (3) 02 01-04 Energy Industry Identification System (EIIS) codes and component function identifier codes appear in the text as [xx/xx].
II. IDENTIFICATION OF OCCURRENCE The Salem Generating Station UFSAR describes the Control Room dose consequences following a loss-of-coolant accident in Chapter 15.4.1.4.
This describes the design of the Control Room Emergency Air Conditioning System (EACS)
[VI/-] being in a recirculation mode for 10 hours1.157407e-4 days <br />0.00278 hours <br />1.653439e-5 weeks <br />3.805e-6 months <br /> followed by a one hour pressurization mode, and then returning to the recirculation mode.for another 10 hours1.157407e-4 days <br />0.00278 hours <br />1.653439e-5 weeks <br />3.805e-6 months <br />.
The stated doses in the UFSAR are well below the limits specified in Footnote 2 of 10 CFR 100.
However, calculations to support response to one of the corrective actions in LER 95-006 indicate the current configuration of the Control Room envelope exceeds the UFSAR stated doses and further exceeds the 10 CFR 50 Appendix A, GDC 19 criteria for Control Room Habitability in modes 1, 2,and 3.
Doses are within acceptable values for the current configuration during modes 4 and 5.
III. CONDITIONS PRIOR TO OCCURRENCE Unit 1:
Unit 2:
Mode 5, Reactor Power 0 %,
Mode 5, Reactor Power 0 %
IV.
DESCRIPTION OF OCCURRENCE Unit Load 0 MWe Unit Load 0 MWe LER 95-006-00 reported a condition where the Unit 1 and 2 Control Room EACS would not have automatically actuated into the emergency recirculation mode in response to a high radiation signal.
One of the corrective actions in LER 95-006-00 stated "Before restart of either Salem Unit from the current self-imposed shutdown of both units~ the current design basis of the Control Room EACS and supporting radiation monitoring equipment will be appropriately documented.
Appropriate design changes will be implemented,* as necessary."
As part of the LER review and other ongoing efforts, the design bases of the Control Area Air Conditioning System (CAACS)/Emergency Air Conditioning System (EACS) were examined.
This review recognized the need to assess the ca~ability of the system operating in the Inside Air (recirculation) and Mixed Air (pressurization) modes.
Assessment results using current information and industry accepted practice indicate that doses exceed GDC 19 criteria of Appendix A to 10 CFR 50 for LOCA conditions.
The UFSAR uses an assumed value for air in-leakage to the control room for calculating dose.
The value used is considered to be much less than the current expected in-leakage.
Use of realistic air in-leakage values results in an increased thyroid dose which exceeds the GDC 19 criteria when comb.ined with ingress and egress dose. {4-95)
LICENSEE EVENT REPORT (LER)
TEXT CONTINUATION FACILITY NAME (1)
DOCKET SALEM GENERATING STATION, UNIT 1 05000-272 TEXT (I more space is reqwred, use a ditiona copies of NRC Form 366 ) (17)
V.
APPARENT CAUSE OF OCCURRENCE U.S. NUCLEAR REGULATORY COMMISSION The need to reconstitute the design basis for the emergency air conditioning S¥stem was recognized ~n 1988 during the development of the Configuration Baseline Document. for the EACS.
Specifically, the control room dose calculations available were poorly documented and the control room air in-leakage basis was not sup~orted by specific calculations.
An engineering effort was initiated to reconstitute this information that resulted in the development of several proposed design basis calculations.
These calculations all showed that the design of the EACS satisfied the requirements of GDC 19.
However, none of the calculations were final accepted as design basis, primarily due to the limited technical basis for the control room air in-leakage.
Therefore the issue remained unresolved.
The most coinrnon presently accepted industry practice for calculating control room air in-leakage is the Standard Review Plan guidelines.
The control room air in-leakage was calculated in 1994 using this approach which increased the air in-leaKage to about 800 cfm during recirculation and about 450 cfm during pressurization compared to the original 100 cfm value assumed in the UFSAR.
However the effect on increased dose from the higher air in-leakage was not determined.
As a result of the LER 95-006 corrective action review and other ongoing efforts, the effects of the increased air in-leakage on the control room dose were calculated in mid July, 1995.
The increase in air in-leakage, used with the conservative methodology developed by Murphy and Campe (industry accepted practice) resulted in the calculated thyroid dose exceeding the requirements of GDC 19 by about 5 rem.
The extended period of time required to reconstitute the missing elements of the EACS design basis and recognize the link to possible effects on GDC 19 criteria is attributable to hllinan error by assigning a low priorit¥ to resolving this issue.
The lack of a questioning attitude concerning the potential significance that the increased air in-leakage had on the control room dose also contributed to the period required to resolve this problem.
VI.
PRIOR SIMILAR OCCURRENCE LER 91-038 This LER identified.a Control Room habitability concern from a postulated ammonium hydroxide releas.e.
In th_is instance there was a design change whereby the contents of a storage tank were changed to ammonium hydroxide.
Appropriate controls and evaluations were ~erformed to address this concern.
The methodology used in these evaluations does not use air in-leakage and therefore is not affected by the problem noted in this LER. {4-95)
LICENSEE EVENT REPORT (LER)
TEXT CONTINUATION FACILITY NAME (1)
DOCKET SALEM GENERATING STATION, UNIT 1 05000-272 more space ts required, use additional copies of NRG Form 366 (17)
VII. SAFETY SIGNIFICANCE
.S. NUCLEAR REGULATORY COMMISSION Evaluation of the safety significance of this event has shown that the existing emergency air conditioning system configuration complied with the requirements of GDC 19 for all habitability concerns except thyroid dose.
In addition doses are within acceptable values for the current configuration during modes 4 and 5.
The control room thyroid dosage complies with the GDC 19 limits for the system operation and air in-leakage documented as the UFSAR licensing basis. When the estimates for the air in-leakage developed using the Standard Review Plan guidelines are combined with the original design basis for LOCA, the calculated thyroid dose exceeds the GDC 19 criteria by about 5 rem.
The design basis source term values are considered to be conservatively high.
Based on the source term definition accepted for the Advanced Light Water Reactor design, the NRC and the industry are evaluating the use of more realistic source term methodology for operating plants.
Use of realistic source term predictions and the current calculated air in-leakage indicate the GDC 19 criteria would not likely have been exceeded if an event had occurred.
VIII.CORRECTIVE ACTIONS Calculations were performed to identify an alternative operating mode for the EACS to ensure that the requirements of GDC 19 were satisfied.
Using the air in-leakage value for the control room area calculated in accordance with the Standard Review Plan methodology and a standard, conservative model of the dose impact of in-leakage, it was determined that the reguirements of GDC 19 are satisfied as long as the pressurization mode of EACS operation is implemented within three (3) hours of the LOCA event.
Continued operation of the EACS in the pressurization mode for the duration of the accident condition is also required.
Based on this evaluation, emergency procedures and the UFSAR will be revised to implement the pressurized operating mode as the design basis for the system.
The revised mode of operation for the EACS will be implemented prior to the restart of the Salem units.
An improved corrective action process for emergent issues has also been established for Salem Nuclear Generating Station.
This process, Corrective Action Program, Nuclear Administrative Procedure NC.NA-AP. ZZ-0006 (Q) Rev 9, includes a more rigorous initial operability assessment of each potential problem.
The Corrective Action Program requires a review by the Senior Nuclear Shift Supervisor for operability and reportability determinations whereas the previous engineering process did not require this review.
Existing plant issues are being re-evaluated for operability and safety significance by both the Engineering Review of Issues for Restart and the System Readiness Review Team.
This effort will ensure that the priority assigned to all existing issues reflects the significance of the issue. The existing issues will be resolved based on the priority assigned as a result of these two screenings.
These continuing efforts will ensure that any other significant issues receive appropriate attention for resolution.
|
|---|
|
|
| | | Reporting criterion |
|---|
| 05000311/LER-1995-001, :on 950212,manually Initiated Esfa to Effect MSIS in Order to Increase RCS T-avg Above 541 Degrees F. Caused by Less than Conservative Decision Making.Temporary Hold Placed on Startup Activities |
- on 950212,manually Initiated Esfa to Effect MSIS in Order to Increase RCS T-avg Above 541 Degrees F. Caused by Less than Conservative Decision Making.Temporary Hold Placed on Startup Activities
| 10 CFR 50.73(a)(2)(v), Loss of Safety Function 10 CFR 50.73(a)(2)(vii), Common Cause Inoperability 10 CFR 50.73(a)(2)(iv), System Actuation 10 CFR 50.73(a)(2)(i) 10 CFR 50.72(b)(3)(ii), Degraded or Unanalyzed Condition 10 CFR 50.73(a)(2)(viii)(A) 10 CFR 50.73(a)(2)(viii)(B) | | 05000272/LER-1995-001-01, :on 950201,both Ssps Trains Declared Inoperable After Discovery That AC Power Distribution within Ssps Susceptible to Common Mode Failure.Caused by Aged Components.New Power Supplies Installed |
- on 950201,both Ssps Trains Declared Inoperable After Discovery That AC Power Distribution within Ssps Susceptible to Common Mode Failure.Caused by Aged Components.New Power Supplies Installed
| 10 CFR 50.73(a)(2)(v), Loss of Safety Function 10 CFR 50.73(a)(2)(vii), Common Cause Inoperability 10 CFR 50.73(a)(2)(iv), System Actuation 10 CFR 50.73(a)(2)(i) 10 CFR 50.73(a)(2)(iii) 10 CFR 50.72(b)(3)(ii), Degraded or Unanalyzed Condition 10 CFR 50.73(a)(2)(viii)(A) | | 05000272/LER-1995-002-01, :on 950224,required TS 1 H Timeframe Not Met Re Closing Associated Block Valve.Caused by Personnel Error. Positive Discipline Has Been Taken |
- on 950224,required TS 1 H Timeframe Not Met Re Closing Associated Block Valve.Caused by Personnel Error. Positive Discipline Has Been Taken
| 10 CFR 50.73(a)(2)(vii), Common Cause Inoperability 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications 10 CFR 50.73(a)(2)(x) 10 CFR 50.73(a)(2)(iii) 10 CFR 50.72(b)(3)(ii), Degraded or Unanalyzed Condition 10 CFR 50.73(a)(2) | | 05000272/LER-1995-003-01, :on 950228,four Planned TS 3.0.3 Entries Occurred During Maintenance Analog Rod Position Indication Drift.Drift Caused by Mfg,Design,Const/Installation.Internal Adjustments to Rods Made |
- on 950228,four Planned TS 3.0.3 Entries Occurred During Maintenance Analog Rod Position Indication Drift.Drift Caused by Mfg,Design,Const/Installation.Internal Adjustments to Rods Made
| 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications 10 CFR 50.73(a)(2)(i) 10 CFR 50.73(a)(2)(x) 10 CFR 50.73(a)(2)(iii) 10 CFR 50.72(b)(3)(ii), Degraded or Unanalyzed Condition 10 CFR 50.73(a)(2)(viii)(A) 10 CFR 50.73(a)(2)(viii)(B) | | 05000311/LER-1995-003-02, :on 950311,three Planned TS 3.0.3 Entries Occurred During Maint to Correct Analog RPI Drift Affecting Rod 2SB4.Caused by Design Mfg Const/Installation.Ts 3.0.3 Was Exited |
- on 950311,three Planned TS 3.0.3 Entries Occurred During Maint to Correct Analog RPI Drift Affecting Rod 2SB4.Caused by Design Mfg Const/Installation.Ts 3.0.3 Was Exited
| 10 CFR 50.72(b)(3)(ii), Degraded or Unanalyzed Condition | | 05000311/LER-1995-003-03, :on 890309,failed to Perform Type C Local Leak Rate Testing Following Piping Mod to 21 Containment Spray Piping Sys Due to Not Identifying Need to Perform Required Testing.Enhanced Business Procedures |
- on 890309,failed to Perform Type C Local Leak Rate Testing Following Piping Mod to 21 Containment Spray Piping Sys Due to Not Identifying Need to Perform Required Testing.Enhanced Business Procedures
| 10 CFR 50.73(a)(2)(v), Loss of Safety Function 10 CFR 50.73(a)(2)(vii), Common Cause Inoperability 10 CFR 50.73(a)(2)(iv), System Actuation 10 CFR 50.73(a)(2)(x) 10 CFR 50.73(a)(2)(iii) 10 CFR 50.73(a)(2)(viii)(A) | | 05000272/LER-1995-004-01, :on 790515,used Ten Containment Air Temp Points to Determine Primary Containment Average Air Temp.Caused by Mgt/Qa Defeciency.Implemented Procedure Revs to Satisfy TS SR |
- on 790515,used Ten Containment Air Temp Points to Determine Primary Containment Average Air Temp.Caused by Mgt/Qa Defeciency.Implemented Procedure Revs to Satisfy TS SR
| 10 CFR 50.73(a)(2)(v), Loss of Safety Function 10 CFR 50.73(a)(2)(vii), Common Cause Inoperability 10 CFR 50.73(a)(2)(iv), System Actuation 10 CFR 50.73(a)(2)(i) 10 CFR 50.73(a)(2) 10 CFR 50.73(a)(2)(viii)(A) | | 05000311/LER-1995-004-02, :on 950607,ESFA RT Occurred During Unit 2 Controlled Shutdown Per TS 3.0.3.Caused by RHR Sys Inoperability.Replaced All SBF-1 Failed Protection Relays on 500 Kv Breakers |
- on 950607,ESFA RT Occurred During Unit 2 Controlled Shutdown Per TS 3.0.3.Caused by RHR Sys Inoperability.Replaced All SBF-1 Failed Protection Relays on 500 Kv Breakers
| 10 CFR 50.73(a)(2)(vii), Common Cause Inoperability 10 CFR 50.73(a)(2)(x) 10 CFR 50.73(a)(2)(iii) 10 CFR 50.72(b)(3)(ii), Degraded or Unanalyzed Condition 10 CFR 50.73(a)(2)(viii)(A) 10 CFR 50.73(a)(2)(viii)(B) | | 05000311/LER-1995-004, :on 950607,EFS Actuation Occurred During Unit 2 Controlled Shutdown Per TS 3.0.3.Caused by Inadequate Mgt Oversight of Operability Determination Process.Trained All Licensed Operators |
- on 950607,EFS Actuation Occurred During Unit 2 Controlled Shutdown Per TS 3.0.3.Caused by Inadequate Mgt Oversight of Operability Determination Process.Trained All Licensed Operators
| 10 CFR 50.73(a)(2)(vii), Common Cause Inoperability 10 CFR 50.72(b)(3)(ii), Degraded or Unanalyzed Condition | | 05000311/LER-1995-005-02, :on 950705,failure to Analyze Second Sample W/ Radiation Monitor Inoperable Occurred.Caused by Personnel Error.Second Sample Analyzed & Determined to Be in Agreement W/First Sample |
- on 950705,failure to Analyze Second Sample W/ Radiation Monitor Inoperable Occurred.Caused by Personnel Error.Second Sample Analyzed & Determined to Be in Agreement W/First Sample
| 10 CFR 50.73(a)(2)(viii)(B) | | 05000272/LER-1995-005-01, :on 900508,seven Occurrences Noted That Revealed Lift Settings of Pressurizer Code Safety Valves on Both Units Out of Required Tolerance.Util Supplemented Rept W/Results of Vendor Conducted Root Cause |
- on 900508,seven Occurrences Noted That Revealed Lift Settings of Pressurizer Code Safety Valves on Both Units Out of Required Tolerance.Util Supplemented Rept W/Results of Vendor Conducted Root Cause
| 10 CFR 50.73(a)(2)(v), Loss of Safety Function 10 CFR 50.73(a)(2)(vii), Common Cause Inoperability 10 CFR 50.72(b)(3)(ii), Degraded or Unanalyzed Condition 10 CFR 50.73(a)(2) 10 CFR 50.73(a)(2)(viii)(B) | | 05000311/LER-1995-005, Forwards LER 95-005-00 Re Failure to Analyze Second Sample W/Radiation Monitor Inoperable | Forwards LER 95-005-00 Re Failure to Analyze Second Sample W/Radiation Monitor Inoperable | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | | 05000272/LER-1995-005, :on 950508,eight Occurrences Revealed Lift Settings of Pressurizer Code Safety Valves on Both Units Out of Required Tolerance.Caused by Testing Intrument Error. Counseled Personnel Involved |
- on 950508,eight Occurrences Revealed Lift Settings of Pressurizer Code Safety Valves on Both Units Out of Required Tolerance.Caused by Testing Intrument Error. Counseled Personnel Involved
| 10 CFR 50.73(a)(2) | | 05000311/LER-1995-006, Revises Corrective Action Due Date in LER 95-006-00 to Correspond W/Due Dates in Restart Action Plan,Consisting of 960501 for Reviews & 960630 for Applicable Procedure Revs | Revises Corrective Action Due Date in LER 95-006-00 to Correspond W/Due Dates in Restart Action Plan,Consisting of 960501 for Reviews & 960630 for Applicable Procedure Revs | | | 05000272/LER-1995-006-01, :on 950404,TS 3.0.3 for Both Units Was Entered Due to Inability of CR Emergency Air Conditioning Sys to Automatically Actuate.Operability Determination Has Been Completed |
- on 950404,TS 3.0.3 for Both Units Was Entered Due to Inability of CR Emergency Air Conditioning Sys to Automatically Actuate.Operability Determination Has Been Completed
| 10 CFR 50.73(a)(2)(vii), Common Cause Inoperability 10 CFR 50.73(a)(2)(i) 10 CFR 50.73(a)(2)(x) 10 CFR 50.73(a)(2)(iii) 10 CFR 50.72(b)(3)(ii), Degraded or Unanalyzed Condition 10 CFR 50.73(a)(2) 10 CFR 50.73(a)(2)(viii)(A) 10 CFR 50.73(a)(2)(viii)(B) | | 05000311/LER-1995-006-02, :on 950822,surveillance Was Missed & Charcoal Absorber Testing Exceeded TS SR Time Limit.Caused by Informal Process to Monitor Charcoal Absorber Run Time Hs Being Used.Assigned Responsibility to Operations Dept |
- on 950822,surveillance Was Missed & Charcoal Absorber Testing Exceeded TS SR Time Limit.Caused by Informal Process to Monitor Charcoal Absorber Run Time Hs Being Used.Assigned Responsibility to Operations Dept
| 10 CFR 50.73(a)(2)(v), Loss of Safety Function 10 CFR 50.73(a)(2)(viii) 10 CFR 50.73(a)(2) | | 05000311/LER-1995-007-02, :on 900503,diesel Surveillance Required by TS Was Missed.Revised Process for Modifying EDG Surveillance Frequency |
- on 900503,diesel Surveillance Required by TS Was Missed.Revised Process for Modifying EDG Surveillance Frequency
| 10 CFR 50.73(a)(2)(i) 10 CFR 50.73(a)(2) | | 05000272/LER-1995-007, :on 950505,EDGs 1A,1B & 1C Simultaneously Paralleled to Electrical Grid,Resulting in Potential for Common Mode Failure of All Three Edgs.Caused by Mgt/Qa Deficiency.Procedures Revised |
- on 950505,EDGs 1A,1B & 1C Simultaneously Paralleled to Electrical Grid,Resulting in Potential for Common Mode Failure of All Three Edgs.Caused by Mgt/Qa Deficiency.Procedures Revised
| 10 CFR 50.73(a)(2)(ii)(B), Unanalyzed Condition 10 CFR 50.73(a)(2)(v), Loss of Safety Function 10 CFR 50.73(a)(2)(vii), Common Cause Inoperability 10 CFR 50.73(a)(2)(iv), System Actuation 10 CFR 50.72(b)(3)(ii), Degraded or Unanalyzed Condition 10 CFR 50.73(a)(2) 10 CFR 50.73(a)(2)(viii)(B) | | 05000311/LER-1995-008-02, :on 951215,Tech Spec 4.9.9 Missed Isolation Testing Discovered.Caused by Lack of Adequate Controls to Ensure All Testing Requirements Addressed.Procedure S2.IC-FT.RM--0088(Q) Revised |
- on 951215,Tech Spec 4.9.9 Missed Isolation Testing Discovered.Caused by Lack of Adequate Controls to Ensure All Testing Requirements Addressed.Procedure S2.IC-FT.RM--0088(Q) Revised
| | | 05000272/LER-1995-008-01, :on 950517,controlled Shutdown Completed Due to Inoperability of Switchgear & Penetration Area Ventilation Sys (Spavs).Three Spavs Supply Fans Will Be Inspected & Fan Motors Replaced |
- on 950517,controlled Shutdown Completed Due to Inoperability of Switchgear & Penetration Area Ventilation Sys (Spavs).Three Spavs Supply Fans Will Be Inspected & Fan Motors Replaced
| 10 CFR 50.73(a)(2)(v), Loss of Safety Function 10 CFR 50.73(a)(2)(vii), Common Cause Inoperability 10 CFR 50.73(a)(2)(i) 10 CFR 50.73(a)(2)(x) 10 CFR 50.73(a)(2)(iii) 10 CFR 50.73(a)(2)(i)(A), Completion of TS Shutdown 10 CFR 50.72(b)(3)(ii), Degraded or Unanalyzed Condition 10 CFR 50.73(a)(2)(viii)(B) | | 05000272/LER-1995-009, :on 950601,valid Test of 1B EDG & Subsequent Inoperability of 1B & 1C EDGs Identified.Caused by Inadequate Vibration Tolerant Design of Original Equipment. Cracked Nipple Replace to Restore EDG 1B Availability |
- on 950601,valid Test of 1B EDG & Subsequent Inoperability of 1B & 1C EDGs Identified.Caused by Inadequate Vibration Tolerant Design of Original Equipment. Cracked Nipple Replace to Restore EDG 1B Availability
| 10 CFR 50.73(a)(2)(v), Loss of Safety Function 10 CFR 50.73(a)(2)(i) 10 CFR 50.73(a)(2)(x) 10 CFR 50.73(a)(2)(iii) | | 05000272/LER-1995-010-01, :on 950615,RHR Pumps for long-term Flow Requirements for Both Units Declared Inoperable Due to RHR Flow Instrument Uncertainties.Evaluated EOPs |
- on 950615,RHR Pumps for long-term Flow Requirements for Both Units Declared Inoperable Due to RHR Flow Instrument Uncertainties.Evaluated EOPs
| 10 CFR 50.73(a)(2)(v)(A), Loss of Safety Function - Shutdown the Reactor 10 CFR 50.73(a)(2)(v), Loss of Safety Function 10 CFR 50.73(a)(2)(vii), Common Cause Inoperability 10 CFR 50.73(a)(2)(i) 10 CFR 50.73(a)(2)(x) 10 CFR 50.72(b)(3)(ii), Degraded or Unanalyzed Condition 10 CFR 50.73(a)(2) 10 CFR 50.73(a)(2)(viii)(A) 10 CFR 50.73(a)(2)(viii)(B) | | 05000272/LER-1995-010, :on 950615,both Units RHR Pumps Inoperable for long-term Flow Requirements Due to RHR Flow Instrument Uncertainties.Further Evaluated New EOP Setpoint for RHR Pump Operation |
- on 950615,both Units RHR Pumps Inoperable for long-term Flow Requirements Due to RHR Flow Instrument Uncertainties.Further Evaluated New EOP Setpoint for RHR Pump Operation
| 10 CFR 50.73(a)(2)(v), Loss of Safety Function | | 05000272/LER-1995-011, :on 880222,inconsistency Between WCAP-11634 Analysis Used for Postulated Steam Line Breaks Outside Containment & Updated FSAR Was Discovered Due to Inadequate Design Review |
- on 880222,inconsistency Between WCAP-11634 Analysis Used for Postulated Steam Line Breaks Outside Containment & Updated FSAR Was Discovered Due to Inadequate Design Review
| 10 CFR 50.73(a)(2)(vii), Common Cause Inoperability 10 CFR 50.73(a)(2)(iv), System Actuation 10 CFR 50.73(a)(2)(i) 10 CFR 50.73(a)(2)(x) 10 CFR 50.73(a)(2)(iii) 10 CFR 50.72(b)(3)(ii), Degraded or Unanalyzed Condition 10 CFR 50.73(a)(2)(viii)(A) | | 05000272/LER-1995-012, :on 761211,adequacy of Turbine Driven Auxiliary FW Pump Encls Occurred.Caused by Inadequate Verification of Assumptions in Calculations Performed to Evaluate Previously Identified.Calculation Assumptions Reviewed |
- on 761211,adequacy of Turbine Driven Auxiliary FW Pump Encls Occurred.Caused by Inadequate Verification of Assumptions in Calculations Performed to Evaluate Previously Identified.Calculation Assumptions Reviewed
| | | 05000272/LER-1995-012-01, :During Nov 1995,TDAFWP Encl Not Matching as- Built Conditions of 761211.Caused by Inadequate Verification of as-build Design Deficiency Calculations.Helb Calculations Reviewed |
- During Nov 1995,TDAFWP Encl Not Matching as- Built Conditions of 761211.Caused by Inadequate Verification of as-build Design Deficiency Calculations.Helb Calculations Reviewed
| 10 CFR 50.73(a)(1), Submit an LER 10 CFR 50.73(a)(2)(v), Loss of Safety Function 10 CFR 50.73(a)(2)(x) 10 CFR 50.72(b)(3)(ii), Degraded or Unanalyzed Condition | | 05000272/LER-1995-013-01, :on 950703,surveillance Testing of Seismic Monitoring Instrumentation Was Performed Approx Six & One Half Hr Late Due to Personnel Error.Provides Appropriate Levels of Discipline to Personnel Involved |
- on 950703,surveillance Testing of Seismic Monitoring Instrumentation Was Performed Approx Six & One Half Hr Late Due to Personnel Error.Provides Appropriate Levels of Discipline to Personnel Involved
| 10 CFR 50.73(a)(2)(v), Loss of Safety Function 10 CFR 50.73(a)(2)(vii), Common Cause Inoperability 10 CFR 50.73(a)(2)(iv), System Actuation 10 CFR 50.73(a)(2)(i) 10 CFR 50.73(a)(2)(x) 10 CFR 50.73(a)(2)(iii) 10 CFR 50.72(b)(3)(ii), Degraded or Unanalyzed Condition | | 05000272/LER-1995-014-01, :on 951211,SI Throttle Valve Was Inoperable. Caused by Inadequate Deficiency.Installed Orifice in Cold Leg Branch Lines Prior to Startup |
- on 951211,SI Throttle Valve Was Inoperable. Caused by Inadequate Deficiency.Installed Orifice in Cold Leg Branch Lines Prior to Startup
| 10 CFR 50.72(b)(3)(ii), Degraded or Unanalyzed Condition | | 05000272/LER-1995-015-01, :on 950711,failed to Complete Documentation of EDG TS Surveillance.Caused by Lack of Procedural Clarity Re Method of Timing EDG Start & Standby Performance.Developed Special Surveillance Testing Procedures |
- on 950711,failed to Complete Documentation of EDG TS Surveillance.Caused by Lack of Procedural Clarity Re Method of Timing EDG Start & Standby Performance.Developed Special Surveillance Testing Procedures
| | | 05000272/LER-1995-016-01, :on 950720,difference Between Containment Design Parameters & Accident Analysis Was Discovered.Caused by Inadequate 10CFR50.59 SEs for Changes in Containment Temp Profiles.Changed UFSAR & TS |
- on 950720,difference Between Containment Design Parameters & Accident Analysis Was Discovered.Caused by Inadequate 10CFR50.59 SEs for Changes in Containment Temp Profiles.Changed UFSAR & TS
| 10 CFR 50.73(a)(2)(x) 10 CFR 50.73(a)(2)(iii) | | 05000272/LER-1995-016, Informs That Revised Date for Submission of Suppl to LER 95-016 Will Be 960329 | Informs That Revised Date for Submission of Suppl to LER 95-016 Will Be 960329 | | | 05000272/LER-1995-017, :on 950718,CR Emergency Air Conditioning Sys Failed to Meet GDC 19 Criteria.Performed Calculactions to Identify Alternative Operating Mode for Eacs to Ensure That Requirements of GDC 19 Satisfied |
- on 950718,CR Emergency Air Conditioning Sys Failed to Meet GDC 19 Criteria.Performed Calculactions to Identify Alternative Operating Mode for Eacs to Ensure That Requirements of GDC 19 Satisfied
| | | 05000272/LER-1995-018, :on 950720,improper Range Gauges Used for Ist. Caused by Inadequate IST Program & Lack of IST Program Maint & Implementation Processes & Associated Controls.Issued Stop Work Order by QA 950731 |
- on 950720,improper Range Gauges Used for Ist. Caused by Inadequate IST Program & Lack of IST Program Maint & Implementation Processes & Associated Controls.Issued Stop Work Order by QA 950731
| 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications 10 CFR 50.73(a)(2)(i) 10 CFR 50.73(a)(2)(x) | | 05000272/LER-1995-019, :on 950726,operability Functional Test Was Not Performed Prior to Mode Entry.Caused by Lack of Managerial Oversight & Organizational Breakdowns.Entered Tracking as for 1VC1 & 1VC2 for Mode 6 |
- on 950726,operability Functional Test Was Not Performed Prior to Mode Entry.Caused by Lack of Managerial Oversight & Organizational Breakdowns.Entered Tracking as for 1VC1 & 1VC2 for Mode 6
| 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications 10 CFR 50.73(a)(2)(x) | | 05000272/LER-1995-020, Forwards LER 95-020-00 Re Inoperable Volt Motor Control Ctrs Due to Failed Bus Bar Bolting.Attachment a Contains Commitments Currently Outstanding Related to Issue | Forwards LER 95-020-00 Re Inoperable Volt Motor Control Ctrs Due to Failed Bus Bar Bolting.Attachment a Contains Commitments Currently Outstanding Related to Issue | 10 CFR 50.73(a)(2)(ii)(B), Unanalyzed Condition | | 05000272/LER-1995-020-01, :on 950914,vital 230 Volt MCCs Declared Inoperable Due to Failed Bus Bar Bolting.Caused by Stress Corrosion Cracking.Design Change Package DCP-1ER-0098 Implemented to Replace Bus Bolts W/Carbon Steel Bolts |
- on 950914,vital 230 Volt MCCs Declared Inoperable Due to Failed Bus Bar Bolting.Caused by Stress Corrosion Cracking.Design Change Package DCP-1ER-0098 Implemented to Replace Bus Bolts W/Carbon Steel Bolts
| | | 05000272/LER-1995-021-01, :on 930403,both Reactor Vessel Level Indication Sys Trains Inoperable Due to Inadvertent CO2 Actuation Due to Water Intrusion.Completed RVLIS & Cabinet Sealing Repaired |
- on 930403,both Reactor Vessel Level Indication Sys Trains Inoperable Due to Inadvertent CO2 Actuation Due to Water Intrusion.Completed RVLIS & Cabinet Sealing Repaired
| 10 CFR 50.73(a)(2)(vii), Common Cause Inoperability | | 05000272/LER-1995-022, :on 950916,ABV Sys Exceeded Allowable Bypass Leakage Due to Tear in Expansion Joint Fabric.Caused by Equipment Failure.Expansion Joint Fabric Replaced |
- on 950916,ABV Sys Exceeded Allowable Bypass Leakage Due to Tear in Expansion Joint Fabric.Caused by Equipment Failure.Expansion Joint Fabric Replaced
| 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | | 05000272/LER-1995-023-01, Forwards Supplemental LER 95-023-01 Re Failure to Plug SG Tubes Due to Missed Eddy Current Indications.Suppl Being Submitted to Discuss Cause & Safety Significance of Event | Forwards Supplemental LER 95-023-01 Re Failure to Plug SG Tubes Due to Missed Eddy Current Indications.Suppl Being Submitted to Discuss Cause & Safety Significance of Event | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | | 05000272/LER-1995-023, :on 940106,failed to Plug SG Tubes.Caused by Lack of Contractor Oversight in Area of Eddy Current Testing.Analyst Guidelines Specific to Salem,Units 1 & 2 & Performance Demonstration Program Were Developed |
- on 940106,failed to Plug SG Tubes.Caused by Lack of Contractor Oversight in Area of Eddy Current Testing.Analyst Guidelines Specific to Salem,Units 1 & 2 & Performance Demonstration Program Were Developed
| 10 CFR 50.73(a)(2)(v), Loss of Safety Function 10 CFR 50.73(a)(2)(iv), System Actuation 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications 10 CFR 50.73(a)(2)(x) 10 CFR 50.73(a)(2)(iii) 10 CFR 50.73(a)(2)(viii) | | 05000272/LER-1995-024, :on 950911,determined Fuel Handling Bldg Low Differential Pressure Surveillance Testing Did Not Ensure Compliance W/Ts Requirements.Caused by Inadequate Design Basis Info.Fuel Handling Bldg Changed |
- on 950911,determined Fuel Handling Bldg Low Differential Pressure Surveillance Testing Did Not Ensure Compliance W/Ts Requirements.Caused by Inadequate Design Basis Info.Fuel Handling Bldg Changed
| 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | | 05000272/LER-1995-025, :on 951012,identified Plant Procedures Did Not Contain Specific Instructions to Limit Sys Flow for Pump Accident Alignments.Caused by Limited Appreciation of Significance of Operating.Baseline Document Revised |
- on 951012,identified Plant Procedures Did Not Contain Specific Instructions to Limit Sys Flow for Pump Accident Alignments.Caused by Limited Appreciation of Significance of Operating.Baseline Document Revised
| | | 05000272/LER-1995-026, :on 951023,MSSV Failed Lift Set Test.Cause Under Investigation.Appropriate Enhancements Will Be Made to Safety Valve Program Based on Results of Root Cause Determination |
- on 951023,MSSV Failed Lift Set Test.Cause Under Investigation.Appropriate Enhancements Will Be Made to Safety Valve Program Based on Results of Root Cause Determination
| 10 CFR 50.73(a)(2)(x) 10 CFR 50.73(a)(2)(1) | | 05000272/LER-1995-026-01, :on 951023,main Steam Safety Valves Failed Lift Set Test.Caused by Use of Furmanite Trevitest Equipment That Had Inaccuracies.Rebuilt MSSV That Failed Lift Setpoint Test or Exceeded Allowable Seat Leakage Limits |
- on 951023,main Steam Safety Valves Failed Lift Set Test.Caused by Use of Furmanite Trevitest Equipment That Had Inaccuracies.Rebuilt MSSV That Failed Lift Setpoint Test or Exceeded Allowable Seat Leakage Limits
| 10 CFR 50.73(a)(2)(iii) 10 CFR 50.73(a)(2) | | 05000272/LER-1995-027-01, :on 761211,doses During LOCA Exceeded Plant Licensing Basis Due to Inaccurate Assumptions in Dose Calculations.Revised Procedures in August 1994.W/forwarding Ltr |
- on 761211,doses During LOCA Exceeded Plant Licensing Basis Due to Inaccurate Assumptions in Dose Calculations.Revised Procedures in August 1994.W/forwarding Ltr
| 10 CFR 50.73(a)(2)(vii), Common Cause Inoperability 10 CFR 50.73(a)(2)(iii) | | 05000272/LER-1995-028-01, :on 950920,effective Leakage Monitoring Program Did Not Meet TS 6.8.4a Requirements Due to Mgt/Qa Deficiency.Consolidated Program Under Single Organization to Assure Plant Design Basis Satisfied |
- on 950920,effective Leakage Monitoring Program Did Not Meet TS 6.8.4a Requirements Due to Mgt/Qa Deficiency.Consolidated Program Under Single Organization to Assure Plant Design Basis Satisfied
| 10 CFR 50.73(a)(2)(v), Loss of Safety Function 10 CFR 50.73(a)(2)(vii), Common Cause Inoperability 10 CFR 50.73(a)(2)(iv), System Actuation 10 CFR 50.73(a)(2)(i) 10 CFR 50.73(a)(2)(x) 10 CFR 50.73(a)(2)(iii) 10 CFR 50.73(a)(2)(viii) | | 05000272/LER-1995-029, :on 951219,all 4 Kv Vital Busses Declared Inoperable.Caused by Inadequate Initial Design of GE Type SBM Switches by Mfg.Replaced All Suspect Switches in 4 Kv Switchgear |
- on 951219,all 4 Kv Vital Busses Declared Inoperable.Caused by Inadequate Initial Design of GE Type SBM Switches by Mfg.Replaced All Suspect Switches in 4 Kv Switchgear
| 10 CFR 50.73(a)(2)(v), Loss of Safety Function 10 CFR 50.73(a)(2)(iv), System Actuation | | 05000272/LER-1995-029-01, :on 951219,4 Kv Vital Buses Declared Inoperable.Caused by Inadequate Initial Design of GE Type SBM Switches by Mfg.All Suspect Switches in 4 Kv Switchgear, Vital & Group Busses Replaced |
- on 951219,4 Kv Vital Buses Declared Inoperable.Caused by Inadequate Initial Design of GE Type SBM Switches by Mfg.All Suspect Switches in 4 Kv Switchgear, Vital & Group Busses Replaced
| 10 CFR 50.73(a)(2)(v), Loss of Safety Function 10 CFR 50.73(a)(2)(vii), Common Cause Inoperability |
|