| | title = Duke Energy McGuire Nuclear Station Answer to March 12, 2012 Commission Order Modifying License with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) | | | title = Duke Energy McGuire Nuclear Station Answer to March 12, 2012 Commission Order Modifying License with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) |
| | author name = Repko R T | | | author name = Repko R |
| | author affiliation = Duke Energy Carolinas, LLC | | | author affiliation = Duke Energy Carolinas, LLC |
| | addressee name = | | | addressee name = |
Revision as of 00:08, 29 June 2019
|
---|
Category:Letter
MONTHYEARIR 05000369/20240032024-11-0404 November 2024 Integrated Inspection Report 05000369/2024003 and 05000370/2024003 ML24303A4212024-10-30030 October 2024 Mcguire Nuclear Station, Units 1 & 2, Notification of an NRC Fire Protection Team Inspection FPTI NRC 05000369/2025010, 05000370/2025010 and Request for Information RFI IR 05000369/20244022024-10-0808 October 2024 Security Baseline Inspection Report 05000369/2024402 05000370/2024402 IR 05000369/20240052024-08-26026 August 2024 Updated Inspection Plan for McGuire Nuclear Station, Units 1 and 2, (Report 05000369-2024005 and 05000370-2024005) IR 05000369/20244042024-08-0101 August 2024 Cover Letter Security Baseline Inspection Report 05000369/2024404 and 05000370/2024404 IR 05000369/20253012024-07-29029 July 2024 Notification of Licensed Operator Initial Examination 05000369/2025301 and 05000370/2025301 IR 05000369/20244032024-07-25025 July 2024 – Cyber Security Inspection Report 05000369/2024403 and 05000370/2024403 Rev IR 05000369/20240022024-07-24024 July 2024 Integrated Inspection Report 05000369/2024002 and 05000370/2024002 ML24183A0972024-07-12012 July 2024 ISFSI; Catawba 1, 2 & ISFSI; McGuire 1, 2 & ISFSI; Oconee 1, 2, 3 & ISFSI; Shearon Harris 1; H. B. Robinson 2 & ISFSI; and Radioactive Package Shipping Under 10 CFR 71 (71-266 & 71-345) – Review of QA Program Changes EPID L-2024-LLQ-0002 IR 05000369/20244012024-07-0303 July 2024 – Security Baseline Inspection Report 05000369/2024401 and 05000370/2024401 ML24176A2802024-06-26026 June 2024 Notification of Target Set Inspection and Request for Information (NRC Inspection Report 05000369-2024404 and 05000370-2024404) IR 05000369/20240112024-06-0404 June 2024 Biennial Problem Identification and Resolution Inspection Report 05000369/2024011 and 05000370/2024011 ML24149A1772024-05-28028 May 2024 NRC Response to Duke Energy 2025 FOF Schedule Change Request (Catawba and McGuire) IR 05000369/20240012024-05-0808 May 2024 Integrated Inspection Report 05000369-2024001 and 05000370-2024001 and 07200038-2024001 ML24110A0382024-04-30030 April 2024 – Correction to Issuance of Amendment Nos. 330 and 309, Regarding Implementation of Technical Specifications Task Force (TSTF) Traveler TSTF 505, Revision 2, Provide Risk-Informed Extended Completion Times - Ritstf ML24100A8742024-04-10010 April 2024 Information Request for the Cybersecurity Baseline Inspection, Notification to Perform Inspection 05000369/2024403; and 05000370/2024403 ML24052A3062024-04-0808 April 2024 Issuance of Amendment Nos. 331 & 310, Regarding Adoption of Title 10 of Code of Federal Regulations Section 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Plants ML24031A5402024-03-26026 March 2024 Issuance of Amendment Nos. 330 and 309 Regarding Implementation of TSTF 505,Rev. 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4B ML24085A2402024-03-21021 March 2024 Requalification Program Inspection - McGuire Nuclear Station IR 05000369/20230062024-02-28028 February 2024 Annual Assessment Letter for McGuire Nuclear Station, Units 1 and 2 - NRC Inspection Report 05000369/2023006 and 05000370/2023006 ML24024A2182024-02-0505 February 2024 Exemption from Select Requirements of 10 CFR Part 73 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting) IR 05000369/20230042024-01-31031 January 2024 Integrated Inspection Report 05000369/2023004 and 05000370/2023004 ML24019A1392024-01-25025 January 2024 TSTF 505 and 50.69 Audit Summary ML24019A2002024-01-24024 January 2024 Notification of Inspection and Request for Information for NRC Problem Identification and Resolution Inspection IR 05000369/20234022023-12-14014 December 2023 – Material Control and Accounting Program Inspection Report 05000369/2023402 and 05000370/2023402 05000369/LER-1923-001, Automatic Actuation of the 1A Motor Driven Auxiliary Feedwater Pump Due to Human Error2023-12-13013 December 2023 Automatic Actuation of the 1A Motor Driven Auxiliary Feedwater Pump Due to Human Error ML23317A2272023-11-17017 November 2023 William B. McGuire Nuclear Station, Units 1 and 2 - Transmittal of Dam Inspection Report - Non-Proprietary ML23317A3462023-11-14014 November 2023 Duke Fleet - Correction Letter to License Amendment Nos. 312 & 340 Issuance of Amendments Regarding the Adoption of Technical Specifications Task Force Traveler TSTF-554, Revision 1 IR 05000369/20230032023-10-24024 October 2023 Integrated Inspection Report 05000369/2023003 and 05000370/2023003; and Inspection Report 07200038/2023001 IR 05000369/20230102023-10-13013 October 2023 Age Related Degradation Inspection Report 05000369/2023010 and 05000370/2023010 IR 05000369/20240102023-10-13013 October 2023 Notification of McGuire Nuclear Station Comprehensive Engineering Team Inspection – U.S. Nuclear Regulatory Commission Inspection Report 05000369, 370/2024010 ML23256A0882023-09-25025 September 2023 Issuance of Alternative to Steam Generator Welds IR 05000369/20233012023-09-20020 September 2023 William B. McGuire Nuclear Station - NRC Examination Report 05000369/2023301 and 05000370/2023301 ML23230A0652023-08-31031 August 2023 William B. McGuire Nuclear Station, Units 1 and 2 - Relief Request Use of Later Edition of ASME Code ML23195A0782023-08-29029 August 2023 Issuance of Amendments Regarding the Adoption of Technical Specifications Task Force Traveler TSTF-554, Revision 1 IR 05000369/20230052023-08-25025 August 2023 Updated Inspection Plan for McGuire Nuclear Station Units 1 and 2 (Report 05000369/2023005 and 05000370/2023005) IR 05000369/20230022023-07-28028 July 2023 Integrated Inspection Report 05000369/2023002 and 05000370/2023002 IR 05000369/20234202023-07-24024 July 2023 Security Baseline Inspection Report 050003692023420 and 050003702023420 ML23206A0092023-07-24024 July 2023 William B. McGuire Nuclear Station Operator Licensing Written Examination Approval 05000369/2023301 and 05000370/2023301 ML23207A0762023-07-14014 July 2023 EN 56557 - Update to Part 21 Report Re Potential Defect with Trane External Auto/Stop Emergency Stop Relay Card Pn: XI2650728-06 ML23159A2712023-06-20020 June 2023 William B. McGuire Nuclear Station, Unit 1 - Relief Request Impractical Reactor System Welds ML23237A2672023-06-13013 June 2023 June 13, 2002 - Meeting Announcement - McGuire and Catawba Nuclear Stations 50-369, 50-370 and 50-413, 50-414 ML23159A0052023-06-0505 June 2023 56557-EN 56557 - Paragon - Redlined ML23115A2122023-05-0101 May 2023 Review of the Spring 2022 Steam Generator Tube Inspection Report ML23118A0762023-05-0101 May 2023 Approval for Use of Specific Provision of a Later Edition of the American Society of Mechanical Engineers Boiler and Pressure Vessel Code, Section XI IR 05000369/20230012023-05-0101 May 2023 Integrated Inspection Report 05000369/2023001 and 05000370/2023001 ML23094A1832023-04-18018 April 2023 Audit Plan TSTF-505, Rev. 2, RITSTF Initiative 4B & 10 CFR 50.69, Risk-Informed Categorization & Treatment of Structures, Systems & Components for Nuclear Power Reactors (EPIDs L-2023-LLA-0021 & L-2023-LLA-0022) ML22332A4932023-03-10010 March 2023 William States Lee III 1 and 2 - Issuance of Amendments Regarding the Relocation of the Emergency Operations Facility IR 05000369/20220062023-03-0101 March 2023 Annual Assessment Letter for McGuire Nuclear Station Units 1 and 2 (NRC Inspection Report 05000369/2022006 and 05000370 2022006) IR 05000369/20220042023-01-30030 January 2023 Mcguire Nuclear Station - Integrated Inspection Report 05000369/2022004 and 05000370/2022004 2024-08-26
[Table view] |
Text
REGIS T. REPKO Duke Vice President tin VEnergyv McGuire Nuclear Station Duke Energy MG01 VP / 12700 Hagers Ferry Rd.Huntersville, NC 28078 980-875-4111 980-875-4809 fax regis. repko@duke-energy.
corn March 28, 2012 U.S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555-0001
Subject:
Duke Energy Carolinas, LLC (Duke Energy)McGuire Nuclear Station, Units 1 and 2 Docket Nos. 50-369 and 50-370 Duke Energy McGuire Nuclear Station Answer to March 12, 2012 Commission Order Modifying License with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051)
On March 12, 2012, the Nuclear Regulatory Commission
("NRC" or "Commission")
issued an immediately effective order in the captioned matter entitled Order Modifying License with Regard to Reliable Spent Fuel Pool Instrumentation (Effective Immediately)
("Order")
to, inter alia, Duke Energy. The Orders state that, as a result of the NRC's evaluation of the lessons learned from the accident at Fukushima Dai-ichi in March 2011, the NRC had decided to direct nuclear power plant licensees and construction permit holders to take certain actions.Specifically, the NRC is requiring additional defense-in-depth measures to address uncertainties associated with protection from beyond-design-basis events. With respect to this Order, licensees are specifically directed to provide a reliable means of remotely monitoring "wide-range spent fuel pool levels" to support effective prioritization of event mitigation and recovery actions in the event of a beyond-design-basis external event. Specific requirements are outlined in Attachment 2 to the Order.The Order requires submission of an overall integrated plan, including a description of how compliance with the requirements described in Attachment 2 will be achieved, to the NRC for review by February 28, 2013. In addition, the Order requires submission of an initial status report 60 days following issuance of the final interim staff guidance, and at six month intervals following submittal of an overall integrated plan. The Order states that the NRC intends to issue the interim staff guidance containing specific details on implementation of the requirements of this order in August 2012. Finally, the order requires full implementation of its requirements no later than two refueling cycles after submittal of the overall integrated plan, or December 31, 2016, whichever comes first.Pursuant to 10 C.F.R. § 2.202 and the terms specified in the Order, Duke Energy hereby submits its answer to the Order. Duke Energy consents to the Order and does not request a hearing. Based on information currently available, Duke Energy has not identified any circumstances of the type described in Sections IV.B.1 and IV.B.2 of the Order requiring relief at this time. In addition, Duke Energy has not identified any impediments to compliance with the Order within two refueling cycles after submittal of the integrated plan, or December 31, 2016, www. duke -energy~com U. S. Nuclear Regulatory Commission March 28, 2012 Page 2 whichever is earlier. Duke Energy will provide further responses as required by Section IV.C, in accordance with the specified deadlines.
However, given the uncertainties associated with the ultimate scope of required work caused by the unavailability of implementing guidance until August 2012, and the impact on the ability of Duke Energy to comply with the specific compliance deadline dates based on the probable availability of that guidance, Duke Energy's future responses may include requests for schedule relief as warranted by subsequent NRC requirements or implementing guidance or the results of engineering analyses not yet performed.
Any such request would be submitted in accordance with the relaxation provision in Section IV of the Order.Please direct any questions you may have in this matter to M. K. Leisure at (980) 875-5171.Very truly yours, Regis T. Repko U. S. Nuclear Regulatory Commission March 28, 2012 Page 3 cc: V. M. McCree Administrator, Region II U.S. Nuclear Regulatory Commission Marquis One Tower 245 Peachtree Center Ave., NE, Suite 1200 Atlanta, GA 30303-1257 E.J. Leeds Director, Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission One White Flint North, Mail Stop 13-H16M 11555 Rockville Pike Rockville, MD 20852-2738 J. Zeiler NRC Senior Resident Inspector McGuire Nuclear Station J. H. Thompson, Project Manager U.S. Nuclear Regulatory Commission 11555 Rockville Pike Mail Stop 0-8 G9A Rockville, MD 20852-2738 U. S. Nuclear Regulatory Commission March 28, 2012 Page 4 Regis Repko affirms that he is the person who subscribed his name to the foregoing statement, and that all the matters and facts set forth herein are true and correct to the best of his knowledge.
Regis Repko, Site Vice President, McGuire Nuclear Station Subscribed and sworn to me: Date ZZ -Z.,., W1 (r{i¶J C'A /ýNotary Public U My commission expires: L2U/) ý //Z'Oýý