Category:Letter
MONTHYEARIR 05000369/20230042024-01-31031 January 2024 Integrated Inspection Report 05000369/2023004 and 05000370/2023004 ML24019A1392024-01-25025 January 2024 TSTF 505 and 50.69 Audit Summary ML24019A2002024-01-24024 January 2024 Notification of Inspection and Request for Information for NRC Problem Identification and Resolution Inspection IR 05000369/20234022023-12-14014 December 2023 Material Control and Accounting Program Inspection Report 05000369/2023402 and 05000370/2023402 ML23317A2272023-11-17017 November 2023 William B. McGuire Nuclear Station, Units 1 and 2 - Transmittal of Dam Inspection Report - Non-Proprietary ML23317A3462023-11-14014 November 2023 Duke Fleet - Correction Letter to License Amendment Nos. 312 & 340 Issuance of Amendments Regarding the Adoption of Technical Specifications Task Force Traveler TSTF-554, Revision 1 IR 05000369/20230032023-10-24024 October 2023 Integrated Inspection Report 05000369/2023003 and 05000370/2023003; and Inspection Report 07200038/2023001 IR 05000369/20240102023-10-13013 October 2023 Notification of McGuire Nuclear Station Comprehensive Engineering Team Inspection U.S. Nuclear Regulatory Commission Inspection Report 05000369, 370/2024010 IR 05000369/20230102023-10-13013 October 2023 Age Related Degradation Inspection Report 05000369/2023010 and 05000370/2023010 ML23256A0882023-09-25025 September 2023 Issuance of Alternative to Steam Generator Welds IR 05000369/20233012023-09-20020 September 2023 William B. McGuire Nuclear Station - NRC Examination Report 05000369/2023301 and 05000370/2023301 ML23230A0652023-08-31031 August 2023 William B. McGuire Nuclear Station, Units 1 and 2 - Relief Request Use of Later Edition of ASME Code ML23195A0782023-08-29029 August 2023 Issuance of Amendments Regarding the Adoption of Technical Specifications Task Force Traveler TSTF-554, Revision 1 IR 05000369/20230052023-08-25025 August 2023 Updated Inspection Plan for McGuire Nuclear Station Units 1 and 2 (Report 05000369/2023005 and 05000370/2023005) IR 05000369/20230022023-07-28028 July 2023 Integrated Inspection Report 05000369/2023002 and 05000370/2023002 IR 05000369/20234202023-07-24024 July 2023 Security Baseline Inspection Report 050003692023420 and 050003702023420 ML23206A0092023-07-24024 July 2023 William B. McGuire Nuclear Station Operator Licensing Written Examination Approval 05000369/2023301 and 05000370/2023301 ML23207A0762023-07-14014 July 2023 EN 56557 - Update to Part 21 Report Re Potential Defect with Trane External Auto/Stop Emergency Stop Relay Card Pn: XI2650728-06 ML23159A2712023-06-20020 June 2023 William B. McGuire Nuclear Station, Unit 1 - Relief Request Impractical Reactor System Welds ML23237A2672023-06-13013 June 2023 June 13, 2002 - Meeting Announcement - McGuire and Catawba Nuclear Stations 50-369, 50-370 and 50-413, 50-414 ML23159A0052023-06-0505 June 2023 56557-EN 56557 - Paragon - Redlined ML23115A2122023-05-0101 May 2023 Review of the Spring 2022 Steam Generator Tube Inspection Report ML23118A0762023-05-0101 May 2023 Approval for Use of Specific Provision of a Later Edition of the American Society of Mechanical Engineers Boiler and Pressure Vessel Code, Section XI IR 05000369/20230012023-05-0101 May 2023 Integrated Inspection Report 05000369/2023001 and 05000370/2023001 ML23094A1832023-04-18018 April 2023 Audit Plan TSTF-505, Rev. 2, RITSTF Initiative 4B & 10 CFR 50.69, Risk-Informed Categorization & Treatment of Structures, Systems & Components for Nuclear Power Reactors (EPIDs L-2023-LLA-0021 & L-2023-LLA-0022) ML22332A4932023-03-10010 March 2023 William States Lee III 1 and 2 - Issuance of Amendments Regarding the Relocation of the Emergency Operations Facility IR 05000369/20220062023-03-0101 March 2023 Annual Assessment Letter for McGuire Nuclear Station Units 1 and 2 (NRC Inspection Report 05000369/2022006 and 05000370 2022006) IR 05000369/20220042023-01-30030 January 2023 Mcguire Nuclear Station - Integrated Inspection Report 05000369/2022004 and 05000370/2022004 IR 05000369/20224202023-01-11011 January 2023 Security Baseline Inspection Report 05000369/2022420 and 05000370/2022420 ML22356A0512022-12-14014 December 2022 Curtiss-Wright Nuclear Division, Letter Regarding Potential Efect in a Configuration of the 11/2 Inch Quick Disconnect Connector Cable Assemblies Supplied to Duke Energy (See Attached Spreadsheet) for a Total of 460 of Connectors Only Suppl ML22347A1512022-12-13013 December 2022 William B. Mcguire Nuclear Station Notification of Licensed Operator Initial Examination 05000369/2023301 and 05000370/2023301 ML22340A6662022-12-0808 December 2022 Summary of November 30, 2022, Public Meeting with Duke Energy Carolinas, LLC for McGuire Nuclear Station, Units 1 & 2 Proposed LAR to Adopt TSTF-505, Rev. 2 and 10 CFR 50.69 Risk-Informed Categorization and Treatment of Structures, Systems ML22290A1012022-11-29029 November 2022 Issuance of Amendment Nos. 326 and 305, Regarding Changes to Technical Specification 3.4.3, Reactor Coolant System Pressure Temperature Limits ML22096A0032022-11-18018 November 2022 McGuire Nuclear Station and Shearon Harris Nuclear Power Plant Authorization of RA-19-0352 Regarding Use of Alternative for RPV Head Closure Stud Examinations ML22256A2532022-11-14014 November 2022 Issuance of Amendments Regarding the Adoption of Technical Specifications Task Force Traveler TSTF-541, Rev. 2 IR 05000369/20220032022-10-27027 October 2022 Integrated Inspection Report 05000369/2022003 and 05000370/2022003 IR 05000369/20220112022-09-29029 September 2022 Biennial Problem Identification and Resolution Inspection Report 05000369/2022011 and 05000370/2022011 ML22266A0782022-09-26026 September 2022 William B. Mcguire Nuclear Station, Unit 2 Pressurizer Power Operated Relief Valve Relief Request ML22258A0302022-09-15015 September 2022 Evacuation Time Estimate Reports ML22242A0022022-09-12012 September 2022 Issuance of Amendments to Adopt TSTF 569, Revision 2, Revise Response Time Testing Definition IR 07200038/20220012022-09-12012 September 2022 Operation of an Independent Spent Fuel Storage Installation Report 07200038/2022001 ML22230B6132022-09-0101 September 2022 Review of the Draft Environmental Assessment and Finding of No Significant Impact for Brunswick Steam Electric Plant and McGuire Nuclear Station Independent Spent Fuel Storage Installations Decommissioning Funding Plans IR 05000369/20220052022-08-29029 August 2022 Updated Inspection Plan for McGuire Nuclear Station Units 1 and 2 NRC Inspection Report 05000369/2022005 and 05000370/2022005 IR 05000369/20220022022-07-26026 July 2022 Integrated Inspection Report 05000369/2022002 and 05000370/2022002 ML22215A2502022-07-25025 July 2022 EN 55960 - Update - Curtiss Wright ML22164A0362022-07-19019 July 2022 Mcguire Nuclear Station, Units 1 and 2; Issuance of Amendments to Revise the Conditional Exemption of the End-Of-Cycle Moderator Temperature Coefficient Measurement Methodology (EPID L-2021-LLA-0198) Public ML22175A0162022-06-24024 June 2022 Notification of Inspection and Request for Information for NRC Problem Identification and Resolution Inspection ML22046A0222022-06-14014 June 2022 Issuance of Amendments to Adopt TSTF-439, Eliminate Second Completion Times Limiting Time from Discovery of Failure to Meet an LCO ML22111A3112022-05-16016 May 2022 Letter Issuing Exemption to McGuire IR 05000369/20224012022-05-12012 May 2022 Cyber Security Inspection Report 05000369/2022401 and 05000370/2022401 2024-01-31
[Table view] |
Text
REGIS T. REPKO Duke Vice President tin VEnergyv McGuire Nuclear Station Duke Energy MG01 VP / 12700 Hagers Ferry Rd.
Huntersville, NC 28078 980-875-4111 980-875-4809 fax regis.repko@duke-energy.corn March 28, 2012 U.S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555-0001
Subject:
Duke Energy Carolinas, LLC (Duke Energy)
McGuire Nuclear Station, Units 1 and 2 Docket Nos. 50-369 and 50-370 Duke Energy McGuire Nuclear Station Answer to March 12, 2012 Commission Order Modifying License with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051)
On March 12, 2012, the Nuclear Regulatory Commission ("NRC" or "Commission") issued an immediately effective order in the captioned matter entitled Order Modifying License with Regard to Reliable Spent Fuel Pool Instrumentation (Effective Immediately) ("Order") to, inter alia, Duke Energy. The Orders state that, as a result of the NRC's evaluation of the lessons learned from the accident at Fukushima Dai-ichi in March 2011, the NRC had decided to direct nuclear power plant licensees and construction permit holders to take certain actions.
Specifically, the NRC is requiring additional defense-in-depth measures to address uncertainties associated with protection from beyond-design-basis events. With respect to this Order, licensees are specifically directed to provide a reliable means of remotely monitoring "wide-range spent fuel pool levels" to support effective prioritization of event mitigation and recovery actions in the event of a beyond-design-basis external event. Specific requirements are outlined in Attachment 2 to the Order.
The Order requires submission of an overall integrated plan, including a description of how compliance with the requirements described in Attachment 2 will be achieved, to the NRC for review by February 28, 2013. In addition, the Order requires submission of an initial status report 60 days following issuance of the final interim staff guidance, and at six month intervals following submittal of an overall integrated plan. The Order states that the NRC intends to issue the interim staff guidance containing specific details on implementation of the requirements of this order in August 2012. Finally, the order requires full implementation of its requirements no later than two refueling cycles after submittal of the overall integrated plan, or December 31, 2016, whichever comes first.
Pursuant to 10 C.F.R. § 2.202 and the terms specified in the Order, Duke Energy hereby submits its answer to the Order. Duke Energy consents to the Order and does not request a hearing. Based on information currently available, Duke Energy has not identified any circumstances of the type described in Sections IV.B.1 and IV.B.2 of the Order requiring relief at this time. In addition, Duke Energy has not identified any impediments to compliance with the Order within two refueling cycles after submittal of the integrated plan, or December 31, 2016, www. duke -energy~com
U. S. Nuclear Regulatory Commission March 28, 2012 Page 2 whichever is earlier. Duke Energy will provide further responses as required by Section IV.C, in accordance with the specified deadlines. However, given the uncertainties associated with the ultimate scope of required work caused by the unavailability of implementing guidance until August 2012, and the impact on the ability of Duke Energy to comply with the specific compliance deadline dates based on the probable availability of that guidance, Duke Energy's future responses may include requests for schedule relief as warranted by subsequent NRC requirements or implementing guidance or the results of engineering analyses not yet performed. Any such request would be submitted in accordance with the relaxation provision in Section IV of the Order.
Please direct any questions you may have in this matter to M. K. Leisure at (980) 875-5171.
Very truly yours, Regis T. Repko
U. S. Nuclear Regulatory Commission March 28, 2012 Page 3 cc:
V. M. McCree Administrator, Region II U.S. Nuclear Regulatory Commission Marquis One Tower 245 Peachtree Center Ave., NE, Suite 1200 Atlanta, GA 30303-1257 E.J. Leeds Director, Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission One White Flint North, Mail Stop 13-H16M 11555 Rockville Pike Rockville, MD 20852-2738 J. Zeiler NRC Senior Resident Inspector McGuire Nuclear Station J. H. Thompson, Project Manager U.S. Nuclear Regulatory Commission 11555 Rockville Pike Mail Stop 0-8 G9A Rockville, MD 20852-2738
U. S. Nuclear Regulatory Commission March 28, 2012 Page 4 Regis Repko affirms that he is the person who subscribed his name to the foregoing statement, and that all the matters and facts set forth herein are true and correct to the best of his knowledge.
Regis Repko, Site Vice President, McGuire Nuclear Station Subscribed and sworn to me:
Date ZZ .,W1-Z.,
(r{i¶JC' A /ý Notary Public U
My commission expires: L2U/) ý / /Z'Oýý