|
|
Line 44: |
Line 44: |
| It is currently expected that the evaluation of this defect will be completed by July 22, 2016. If you have any questions pertaining to this information, please contact Timothy Franchuk, Director of Quality Assurance, at 513-201-2176. | | It is currently expected that the evaluation of this defect will be completed by July 22, 2016. If you have any questions pertaining to this information, please contact Timothy Franchuk, Director of Quality Assurance, at 513-201-2176. |
| Sincerely. | | Sincerely. |
| Timothy Franchuk Director, Quality Assurance Nuclear Division Curtiss-Wright cc: Regional Administrator, USNRC, Region II CURTISS-DOCUMENT CONTRACT WRIGHT N/A TRANSMITTAL Nuclear Division QTNP3548 P.O. NUMBER 4600 East Tech Drive, Cincinnati, OH 45245 N/A T: 513.528.7900 IF: 513.528.4537 TO: NRC'S DOCUMENT CONTROL DESK ACTION I LEGEND I STATUS U.S. REGULATORY COMMISSION WASHINGTON, DC 20555-0001 | | Timothy Franchuk Director, Quality Assurance Nuclear Division Curtiss-Wright cc: Regional Administrator, USNRC, Region II CURTISS-DOCUMENT CONTRACT WRIGHT N/A TRANSMITTAL Nuclear Division QTNP3548 P.O. NUMBER 4600 East Tech Drive, Cincinnati, OH 45245 N/A T: 513.528.7900 IF: 513.528.4537 TO: NRC'S DOCUMENT CONTROL DESK ACTION I LEGEND I STATUS U.S. REGULATORY COMMISSION WASHINGTON, DC 20555-0001 |
| : 1. For Approval A. Approved-Released for 2. Final Documents for Construction ATTN: HOO HOC Record B. Approved as noted-(301) 816-5151 3. For Information Only Resubmit-Construction | | : 1. For Approval A. Approved-Released for 2. Final Documents for Construction ATTN: HOO HOC Record B. Approved as noted-(301) 816-5151 3. For Information Only Resubmit-Construction |
| : 4. For Preliminary Use may proceed 5. For Your Use C. Not approved-Resubmit PROJECT: 6. Revised as Requested D. L NO. NO. 0 DRAWINGS E DOCUMENT/ | | : 4. For Preliminary Use may proceed 5. For Your Use C. Not approved-Resubmit PROJECT: 6. Revised as Requested D. L NO. NO. 0 DRAWINGS E DOCUMENT/ |
| REV. OF OF 0 SPECIFICATION 0 PROCEDURE G DRAWING NUMBER PRINTS/ SEPIAS D OTHER E COPIES N D N/A N/A 1 INTERIM 10 CFR PART 21 REPORT REGARDING 2 DISPOSITION OF A NONCONFORMANCE ON STRUTHERS-DUNN RELAY PART NUMBER B255XCXPFHSC125V FOR PSEG NUCLEAR LLC PLEASE EMAIL MARGIE HOVER CONFIRMATION PLEASE ACKNOWLEDGE RECEIPT BELOW AND REMARKS RETURN A SIGNED COPY OF RECEIPT mhover@curtisswright.com. | | REV. OF OF 0 SPECIFICATION 0 PROCEDURE G DRAWING NUMBER PRINTS/ SEPIAS D OTHER E COPIES N D N/A N/A 1 INTERIM 10 CFR PART 21 REPORT REGARDING 2 DISPOSITION OF A NONCONFORMANCE ON STRUTHERS-DUNN RELAY PART NUMBER B255XCXPFHSC125V FOR PSEG NUCLEAR LLC PLEASE EMAIL MARGIE HOVER CONFIRMATION PLEASE ACKNOWLEDGE RECEIPT BELOW AND REMARKS RETURN A SIGNED COPY OF RECEIPT mhover@curtisswright.com. |
| THANK YOU. RECEIVED BY DATED BY 911argie Jfover DATE: 6/8/2016 DOCUMENT CONTROL In order to avoid delays in the project PAGE: 1 of 1 these documents must be returned by: 020-07-91, REV.5}} | | THANK YOU. RECEIVED BY DATED BY 911argie Jfover DATE: 6/8/2016 DOCUMENT CONTROL In order to avoid delays in the project PAGE: 1 of 1 these documents must be returned by: 020-07-91, REV.5}} |
Revision as of 04:12, 27 April 2019
|
---|
Category:Deficiency Report (per 10CFR50.55e and Part 21)
MONTHYEARML22307A0602022-11-0303 November 2022 EN 56200 - Fairbanks Morse Re Basic Component Which Fails to Comply or Contains a Defect ML20042E2522020-01-31031 January 2020 EN 54485 Target Rock Redacted Update to Part 21 Report on Defect of Modification of Valve Component and Main Disc Lift Misadjustment ML20029D1612020-01-21021 January 2020 10 CFR Part 21 Report, Notification of a Defect Modification of a Valve Component and Main Disc Lift Misadjustment ML17081A4532017-03-20020 March 2017 Part 21 - Plastic Jar Dedication Sampling ML17039A5692017-02-0303 February 2017 Final Part 21 Report on Defect, Potential for Test Induced Damage 0867F Series Main Steam Safety Relief Valves ML17026A4142017-01-20020 January 2017 C&D Technologies, Inc. - Part 21 - Plastic Jar Dedication Sampling ML16278A4712016-09-22022 September 2016 Notification of 10 CFR Part 21 Condition, Masterpact Breaker Fail to Close ML16281A2702016-09-22022 September 2016 Part 21 - Initial Notification of Masterpact Breaker Fail to Close ML16209A0482016-07-13013 July 2016 Part 21 - Initial Notification of Masterpact Breaker Fail to Close ML16196A0652016-07-0909 July 2016 Part 21 Report - Nonconformance on Struthers-Dunn Relay for Psge Nuclear LLC ML16162A6792016-06-0808 June 2016 Part 21 Report - Nonconformance on Struthers-Dunn Relay for PSEG Nuclear LLC ML16139A8312016-05-13013 May 2016 Part 21 Notification - Potential Defect Applicable to Hytork XL1126 Pneumatic Actuators ML16139A8322016-05-13013 May 2016 Part 21 - Initial Notification of Masterpact Breaker Fail to Close ML16139A8332016-05-13013 May 2016 Part 21 - Initial Notification of Masterpact Breaker Fail to Close ML16126A1112016-04-29029 April 2016 National Technical Systems (Nts) Request for Extension, for Potential Part 21 on Safety Clip, Siemens Part Number 401-158 ML16098A4452016-03-22022 March 2016 Part 21 Notification - Sense and Transfer Module Resistive Short ML16112A2102016-03-14014 March 2016 National Technical Systems - Potential Part 21 on Siemens 401-158 Safety Clip, Per Wolf Creek, Salem, and Arkansas Nuclear One ML15187A1722015-06-30030 June 2015 Interim Part 21 Report - Potential Test Induced Defect in 0867F Main Steam Safety Relief Valves ML15146A0222015-05-0707 May 2015 Qualtech Np - Potential 1O CFR Part 21 Notification on Struthers Dunn Relays ML15134A0182015-05-0707 May 2015 Part 21 Report Regarding Struthers Dunn Relays with Contact Resistance Greater than One Ohm ML15134A0172015-05-0101 May 2015 Part 21 Report Regarding Potential Test Induced Defect in a 0867F Main Steam Safety Relief Valves ML15103A2442015-04-0606 April 2015 Part 21 Report - Deviation of Hk Circuit Breaker Close Latch Spring ML15089A4352015-03-27027 March 2015 Part-21 Notification - Sense and Transfer Module Resistive Short ML15077A4222015-03-17017 March 2015 Curtiss Wright Flow Control Co., Interim Part 21 Report - Potential Test Induced Defect in a 0867F Main Steam Safety Relief Valves ML15049A4582015-02-0606 February 2015 Thermo Gamma-Metrics, LLC - Part 21 Report Regarding Shutdown Margin Monitor Environmental Qualification Noncompliance ML15022A6502015-01-20020 January 2015 Letter from Steven R. Eisenberg USNRC 10CFR Part 21 Notification ML14274A0522014-09-22022 September 2014 Final Report 10CFR Part 21 Evaluation Regarding Misaligned Separators in LCR-25 Standby Batteries, Revision 1 - Original Letter Did Not Include the List of Affected Utilities ML14210A0102014-07-23023 July 2014 Part 21 - Unseating of Valve Spring on Scram Solenoid Pilot Valve ML14204A7082014-07-23023 July 2014 Enclosure 2, Description of Closure Evaluation, Non-Proprietary Information - Class I (Public) ML14204A7072014-07-23023 July 2014 Completed Evaluation of Part 21 Potentially Reportable Condition Notification: Unseating of Valve Spring on SSPV ML14197A2812014-07-15015 July 2014 Part 21 Report - Potential Failure of Reactor Coolant Pump Turning Vane Bolts ML14197A2742014-07-14014 July 2014 Notification of the Potential Existence of Defects Pursuant to 10CFR Part 21 ML14169A0302014-06-15015 June 2014 Update to Interim Report - 10CFR 21 Evaluation Regarding Potential Deficiencies in Seismic Qualifications for PV-62 ML14113A3702014-04-18018 April 2014 Part 21 - Thomas and Betts Printed Circuit Boards ML14113A3982014-04-17017 April 2014 Part 21 - Bearing Defect ML14303A5262014-03-28028 March 2014 Interim Part 21 Report - Misaligned Separators in LCR-25 Standby Batteries ML14085A0132014-03-19019 March 2014 Part 21 Report Re Defects & Non-Compliance of Thomas and Betts Printed Circuit Boards in Which the Power Supplies Incorrect Strap Installed on the Trasformers of Cyberex P/N ML14079A3532014-03-17017 March 2014 Notification of Part 21 Re Bearing Defect ML13165A3422013-06-12012 June 2013 60-Day Interim Report Involving an Evaluation of a Design Change to Magne-Blast Circuit Breakers ML13042A0962013-02-0808 February 2013 Completed Evaluation of Part 21 Potentially Reportable Condition Notification: Error in Main Steam Line High Flow Calculational Methodology ML13044A0752013-02-0808 February 2013 Part 21 - Completed Evaluation for Potential Error in Main Steam Line High Flow Calculational Methodology ML12352A1232012-12-13013 December 2012 60-Day Interim Report Involving an Evaluation of a Design Change to Magne-Blast Circuit Breakers ML12348A1362012-12-13013 December 2012 Part 21 60-Day Interim Report Notification: Adequacy of Design Change in Am Magne-Blast Circuit Breakers ML12347A3082012-12-12012 December 2012 Part 21 60-Day Interim Report Notification: Error in Main Steam Line High Flow Calculational Methodology ML12363A0472012-12-10010 December 2012 Part 21 Report Re Failure to Comply with Certain PSEG Specifications as Required by PSEG Purchase Order ML12318A0412012-11-0808 November 2012 Part 21 Report - Commercial Grade Dedication Not Properly Applied to Butterfly Valves ML12319A0122012-09-27027 September 2012 Error in Main Steam Line High Flow Calculational Methodology ML12177A0562012-06-21021 June 2012 Part 21 - Reliability Degradation of Resistors in Trip Units and Readout Assemblies ML12163A1302012-06-0606 June 2012 Part 21 Report - Failure of CRD Collet Retainer Tube/Outer Tube Weld ML12158A4472012-06-0606 June 2012 Part 21 60-Day Interim Report Notification - Closufailure of CRD Collet Retainer Tube/Outer Tube Weld 2022-11-03
[Table view] |
Text
0610812016 U.S. Nuclear Regulatory Commission Operations Center Event Report Pagel Part 21 (PAR) Event# 51988 Rep Org: CURTISS WRIGHT Notification Date I Time: 06/08/2016 09:27 (EDT) Supplier:
STRUTHERS-DUNN Event Date I Time: 06/08/2016 (EDT) Last Modification:
06/08/2016 Region: 3 Docket#: City: CINCINNATI Agreement State: Yes County: License#:
State: OH NRC Notified by: TIMOTHY FRANCHUK Notifications:
BILLY DICKSON R3DO HQ Ops Officer: JEFF HERRERA FRANKARNER R1DO Emergency Class: NON EMERGENCY ANTHONY MASTERS R2DO 10 CFR Section: JOHN KRAMER R4DO 21.21(a)(2)
INTERIM EVAL OF DEVIATION PART 21/50.55 REACTORS EMAIL PART-21 REPORT-NONCONFORMANCE ON STRUTHERS-DUNN RELAY FOR PSEG NUCLEAR LLC "This letter serves as an interim report in accordance with 10 CFR 21.21 pertaining to a potential deviation associated with Struthers-Dunn relays P/N B255XCXPFHSC125V supplied to PSEG Nuclear LLC. Based upon information obtained from PSEG, a defect may exist with the reset coil of the Struthers-Dunn relay listed above. Preliminary observations indicate the reset coil had shorted (opened) during operation, and that no other components of the relay are believed to be associated with this failure. PSEG is aware of Curtiss-Wright's investigation into this failure. "Evaluation of reportability in accordance with 10 CFR Part 21 is not able to be completed within the 60-day evaluation period due to the need for additional time to collect and evaluate the necessary information.
It is currently expected that the evaluation of this defect will be completed by July 22, 2016." ' POC: Timothy Franchuk Director, Quality Assurance 4600 East Tech Drive Cincinnati, Ohio 45245 (513) 528-7900 The licensee indicated that the current list of affected plants are being evaluated.