ML13073A092: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
 
(Created page by program invented by StriderTol)
 
(2 intermediate revisions by the same user not shown)
Line 2: Line 2:
| number = ML13073A092
| number = ML13073A092
| issue date = 03/14/2013
| issue date = 03/14/2013
| title = Davis-Besse Nuclear Power Station, Unit No. 1 - Acceptance of Requested Licensing Action Proposed Alternative Regarding Post-Repair Pressure Testing Requirements (TAC No. MF0537)
| title = Acceptance of Requested Licensing Action Proposed Alternative Regarding Post-Repair Pressure Testing Requirements
| author name = Mahoney M
| author name = Mahoney M
| author affiliation = NRC/NRR/DORL/LPLIII-2
| author affiliation = NRC/NRR/DORL/LPLIII-2
Line 18: Line 18:


=Text=
=Text=
{{#Wiki_filter:UNITED NUCLEAR REGULATORY WASHINGTON, D.C. 20555-0001 March 14, 2013 Mr. Ray Ueb Site Vice President FirstEnergy Nuclear Operating Company Davis-Besse Nuclear Power Station Mail Stop A-DB-30BO 5501 North State Route 2 Oak Harbor, OH 43449-9760 DAVIS-BESSE NUCLEAR POWER STATION, UNIT NO.1 -ACCEPTANCE OF REQUESTED LICENSING ACTION RE: PROPOSED ALTERNATIVE REGARDING POST-REPAIR PRESSURE TESTING REQUIREMENTS (TAC NO. MF0537)  
{{#Wiki_filter:UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 March 14, 2013 Mr. Ray Ueb Site Vice President FirstEnergy Nuclear Operating Company Davis-Besse Nuclear Power Station Mail Stop A-DB-30BO 5501 North State Route 2 Oak Harbor, OH 43449-9760 SUB,JECT:        DAVIS-BESSE NUCLEAR POWER STATION, UNIT NO.1 - ACCEPTANCE OF REQUESTED LICENSING ACTION RE: PROPOSED ALTERNATIVE REGARDING POST-REPAIR PRESSURE TESTING REQUIREMENTS (TAC NO. MF0537)


==Dear Mr. Leib:==
==Dear Mr. Leib:==
By letter to the U.S. Nuclear Regulatory Commission (NRC) dated January 1B, 2013 (Agency Document and Management System (ADAMS) Accession No. ML 1301 BA349), FirstEnergy Nuclear Operating Company (FENOC), submitted an exemption request for the Davis-Besse Nuclear Power Station, Unit No.1 (DBNPS). By letter dated February 2B, 2013 (Agency Document and Management System Accession No. ML 1305BA253), the NRC sent a letter to FENOC requesting supplemental information to make an acceptance review determination.
By letter dated March B, 2013 (ADAMS Accession No. ML 13070A226), FENOC submitted supplemental information which replaces the January 1B, 2013, submittal in its entirety.
The March B, 2013, letter contained a proposed alternative which would allow the use of an alternate method of containment testing following activities associated with steam generator replacement The purpose of this letter is to provide the results of the NRC staff's acceptance review of this relief request. The acceptance review was performed to determine if there is sufficient technical information in scope and depth to allow the NRC staff to complete its detailed technical review. The acceptance review is also intended to identify whether the application has any readily apparent information insufficiencies in its characterization of the regulatory requirements or the licensing basis of the plant. Pursuant to Title 10 of the Code of Federai Regulations, Section 50.55a(a)(3)(i), the applicant shall demonstrate that the proposed alternatives would provide an acceptable level of quality and safety. The NRC staff has reviewed your application and concluded that it does provide technical information in sufficient detail to enable the NRC staff to complete its detailed technical review and make an independent assessment regarding the acceptability of the proposed amendment in terms of regulatory requirements and the protection of public health and safety and the environment.
Given the lesser scope and depth of the acceptance review as compared to the R Leib -detailed technical review, there may be instances in which issues that impact the NRC staffs ability to complete the detailed technical review are identified despite completion of an adequate acceptance review. You will be advised of any further information needed to support the NRC staff's detailed technical review by separate correspondence.
If you have any questions, please contact the DBNPS Project Manager, Michael Mahoney, at (301)-415-3867.
/ Michael Mahoney, P Manager Plant Licensing Br ch 111-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-346


==Enclosure:==
By letter to the U.S. Nuclear Regulatory Commission (NRC) dated January 1B, 2013 (Agency Document and Management System (ADAMS) Accession No. ML1301 BA349) , FirstEnergy Nuclear Operating Company (FENOC), submitted an exemption request for the Davis-Besse Nuclear Power Station, Unit No.1 (DBNPS). By letter dated February 2B, 2013 (Agency Document and Management System Accession No. ML 1305BA253), the NRC sent a letter to FENOC requesting supplemental information to make an acceptance review determination.
By letter dated March B, 2013 (ADAMS Accession No. ML13070A226), FENOC submitted supplemental information which replaces the January 1B, 2013, submittal in its entirety. The March B, 2013, letter contained a proposed alternative which would allow the use of an alternate method of containment testing following activities associated with steam generator replacement The purpose of this letter is to provide the results of the NRC staff's acceptance review of this relief request.
The acceptance review was performed to determine if there is sufficient technical information in scope and depth to allow the NRC staff to complete its detailed technical review. The acceptance review is also intended to identify whether the application has any readily apparent information insufficiencies in its characterization of the regulatory requirements or the licensing basis of the plant.
Pursuant to Title 10 of the Code of Federai Regulations, Section 50.55a(a)(3)(i), the applicant shall demonstrate that the proposed alternatives would provide an acceptable level of quality and safety.
The NRC staff has reviewed your application and concluded that it does provide technical information in sufficient detail to enable the NRC staff to complete its detailed technical review and make an independent assessment regarding the acceptability of the proposed amendment in terms of regulatory requirements and the protection of public health and safety and the environment. Given the lesser scope and depth of the acceptance review as compared to the


As stated cc w/encl: Distribution via Listserv R Leib -2 environment.
R Leib                                         - 2 detailed technical review, there may be instances in which issues that impact the NRC staffs ability to complete the detailed technical review are identified despite completion of an adequate acceptance review. You will be advised of any further information needed to support the NRC staff's detailed technical review by separate correspondence.
Given the lesser scope and depth of the acceptance review as compared to the detailed technical review, there may be instances in which issues that impact the NRC staff's ability to complete the detailed technical review are identified despite completion of an adequate acceptance review. You will be advised of any further information needed to support the NRC staff's detailed technical review by separate correspondence.
If you have any questions, please contact the DBNPS Project Manager, Michael Mahoney, at (301)-415-3867.                                                                           /
If you have any questions, please contact the DBNPS Project Manager, Michael Mahoney, at (301 )-415-3867.
Michael Mahoney, P ~ect Manager Plant Licensing Br ch 111-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-346
Docket No. 50-346  


==Enclosure:==
==Enclosure:==


As stated cc w/encl: Distribution via Listserv DISTRIBUTION:
As stated cc w/encl: Distribution via Listserv
PUBLIC Branch Reading File RidsAcrsAcnw_MailCTR Resource RidsNrrDorl Resource RidsNrrDorlLpl3-2 Resource GThomas, NRR/EMCB ADAMS Accession No.: ML 13073A092 Sincerely, 1 RA 1 Michael Mahoney, Project Manager Plant Licensing Branch 111-2 Division of Operating Reactor licensing Office of Nuclear Reactor Regulation RidsRgn3MailCenter Resource RidsOgcRp Resource RidsNrrPMMMahoney Resource RidsNrrLASRohrer Resource RidsNrrEmcb Resource DORLlLPL3-2/PM DORLlLPL3-2/LA  
 
! DORLlLPL3-2/BC DORLlLPL3-2/PM MMahoney SRohrer JBowen . MMahoney 03/13/2013 03/14/2013 03/14 12013 031 14/2013 OFFICIAL RECORD}}
ML13073A092 DORLlLPL3-2/PM       DORLlLPL3-2/LA       ! DORLlLPL3-2/BC     DORLlLPL3-2/PM MMahoney             SRohrer               JBowen           . MMahoney 03/13/2013           03/14/2013             03/14 12013         031 14/2013}}

Latest revision as of 21:47, 4 November 2019

Acceptance of Requested Licensing Action Proposed Alternative Regarding Post-Repair Pressure Testing Requirements
ML13073A092
Person / Time
Site: Davis Besse Cleveland Electric icon.png
Issue date: 03/14/2013
From: Michael Mahoney
Plant Licensing Branch III
To: Lieb R
FirstEnergy Nuclear Operating Co
Mahoney M NRR/DORL/LPL3-2 301-415-3867
References
TAC MF0537
Download: ML13073A092 (3)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 March 14, 2013 Mr. Ray Ueb Site Vice President FirstEnergy Nuclear Operating Company Davis-Besse Nuclear Power Station Mail Stop A-DB-30BO 5501 North State Route 2 Oak Harbor, OH 43449-9760 SUB,JECT: DAVIS-BESSE NUCLEAR POWER STATION, UNIT NO.1 - ACCEPTANCE OF REQUESTED LICENSING ACTION RE: PROPOSED ALTERNATIVE REGARDING POST-REPAIR PRESSURE TESTING REQUIREMENTS (TAC NO. MF0537)

Dear Mr. Leib:

By letter to the U.S. Nuclear Regulatory Commission (NRC) dated January 1B, 2013 (Agency Document and Management System (ADAMS) Accession No. ML1301 BA349) , FirstEnergy Nuclear Operating Company (FENOC), submitted an exemption request for the Davis-Besse Nuclear Power Station, Unit No.1 (DBNPS). By letter dated February 2B, 2013 (Agency Document and Management System Accession No. ML 1305BA253), the NRC sent a letter to FENOC requesting supplemental information to make an acceptance review determination.

By letter dated March B, 2013 (ADAMS Accession No. ML13070A226), FENOC submitted supplemental information which replaces the January 1B, 2013, submittal in its entirety. The March B, 2013, letter contained a proposed alternative which would allow the use of an alternate method of containment testing following activities associated with steam generator replacement The purpose of this letter is to provide the results of the NRC staff's acceptance review of this relief request.

The acceptance review was performed to determine if there is sufficient technical information in scope and depth to allow the NRC staff to complete its detailed technical review. The acceptance review is also intended to identify whether the application has any readily apparent information insufficiencies in its characterization of the regulatory requirements or the licensing basis of the plant.

Pursuant to Title 10 of the Code of Federai Regulations, Section 50.55a(a)(3)(i), the applicant shall demonstrate that the proposed alternatives would provide an acceptable level of quality and safety.

The NRC staff has reviewed your application and concluded that it does provide technical information in sufficient detail to enable the NRC staff to complete its detailed technical review and make an independent assessment regarding the acceptability of the proposed amendment in terms of regulatory requirements and the protection of public health and safety and the environment. Given the lesser scope and depth of the acceptance review as compared to the

R Leib - 2 detailed technical review, there may be instances in which issues that impact the NRC staffs ability to complete the detailed technical review are identified despite completion of an adequate acceptance review. You will be advised of any further information needed to support the NRC staff's detailed technical review by separate correspondence.

If you have any questions, please contact the DBNPS Project Manager, Michael Mahoney, at (301)-415-3867. /

Michael Mahoney, P ~ect Manager Plant Licensing Br ch 111-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-346

Enclosure:

As stated cc w/encl: Distribution via Listserv

ML13073A092 DORLlLPL3-2/PM DORLlLPL3-2/LA  ! DORLlLPL3-2/BC DORLlLPL3-2/PM MMahoney SRohrer JBowen . MMahoney 03/13/2013 03/14/2013 03/14 12013 031 14/2013