| | number = ML15034A106 | | | number = ML15034A106 |
| | issue date = 02/03/2015 | | | issue date = 02/03/2015 |
| | title = Pilgrim Nuclear Power Station, Supplemental Information Needed for Acceptance of Requested Licensing Action Regarding the Safety Limit Minimum Critical Power Ratio License Amendment Request (TAC No. MF5431) | | | title = Supplemental Information Needed for Acceptance of Requested Licensing Action Regarding the Safety Limit Minimum Critical Power Ratio License Amendment Request |
| | author name = Morgan N S | | | author name = Morgan N |
| | author affiliation = NRC/NRR/DORL/LPLI-1 | | | author affiliation = NRC/NRR/DORL/LPLI-1 |
| | addressee name = Dent J A | | | addressee name = Dent J |
| | addressee affiliation = Entergy Nuclear Operations, Inc | | | addressee affiliation = Entergy Nuclear Operations, Inc |
| | docket = 05000293 | | | docket = 05000293 |
| | license number = DPR-035 | | | license number = DPR-035 |
| | contact person = Morgan N S | | | contact person = Morgan N |
| | case reference number = TAC MF5431 | | | case reference number = TAC MF5431 |
| | document type = Letter | | | document type = Letter |
| | page count = 3 | | | page count = 3 |
| | project = TAC:MF5431 | | | project = TAC:MF5431 |
| | stage = Supplement | | | stage = Acceptance Review |
| }} | | }} |
|
| |
|
| =Text= | | =Text= |
| {{#Wiki_filter:UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 Mr. John A. Dent, Jr. Site Vice President Entergy Nuclear Operations, Inc. Pilgrim Nuclear Power Station 600 Rocky Hill Road Plymouth, MA 02360 February 3, 2015 | | {{#Wiki_filter:UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 February 3, 2015 Mr. John A. Dent, Jr. |
| | Site Vice President Entergy Nuclear Operations, Inc. |
| | Pilgrim Nuclear Power Station 600 Rocky Hill Road Plymouth, MA 02360 |
|
| |
|
| ==SUBJECT:== | | ==SUBJECT:== |
| PILGRIM NUCLEAR POWER STATION-SUPPLEMENTAL INFORMATION NEEDED FOR ACCEPTANCE OF REQUESTED LICENSING ACTION REGARDING THE SAFETY LIMIT MINIMUM CRITICAL POWER RATIO LICENSE AMENDMENT REQUEST (TAC NO. MF5431) | | PILGRIM NUCLEAR POWER STATION- SUPPLEMENTAL INFORMATION NEEDED FOR ACCEPTANCE OF REQUESTED LICENSING ACTION REGARDING THE SAFETY LIMIT MINIMUM CRITICAL POWER RATIO LICENSE AMENDMENT REQUEST (TAC NO. MF5431) |
|
| |
|
| ==Dear Mr. Dent:== | | ==Dear Mr. Dent:== |
| By letter dated December 10, 2014 (Agencywide Documents Access and Management System Accession No. ML 14349A495), Entergy Nuclear Operations, Inc., the licensee, submitted a license amendment request (LAR) for Pilgrim Nuclear Power Station. The LAR would change the Safety Limit Minimum Critical Power Ratio from <:: 1. 08 to <:: 1.10 for two recirculation loop operation and from <:: 1.11 to <:: 1.12 for single loop operation. The purpose of this letter is to provide the results of the U.S. Nuclear Regulatory Commission (NRC) staff's acceptance review of this LAR. The acceptance review was performed to determine if there is sufficient technical information in scope and depth to allow the NRC staff to complete its detailed technical review. The acceptance review is also intended to identify whether the application has any readily apparent information insufficiencies in its characterization of the regulatory requirements or the licensing basis of the plant. Consistent with Title 10 of the Code of Federal Regulations (1 0 CFR) Section 50.90, an amendment to the license (including the technical specifications) must fully describe the changes requested, and following as far as applicable, the form prescribed for original applications. Section 50.34 of 10 CFR addresses the content of technical information required. This section stipulates that the submittal address the design and operating characteristics, unusual or novel design features, and principal safety considerations. In order to accept the LAR for review, the NRC staff requests that the licensee provide its regulatory criteria used to determine that the LAR is acceptable. This will support an independent assessment by the NR staff regarding appropriate regulatory requirements and the protection of public health and safety and the environment. If the licensee's response to the NRC staff's request is not received by February 15, 2015, the application will not be accepted for review pursuant to 10 CFR 2.101 and the NRC will cease its review activities associated with the application. If the application is subsequently accepted for review, you will be advised of any further information needed to support the NRC staff's detailed technical review by separate correspondence.
| |
| J. Dent The NRC staff requests that the licensee supplement the application to address the information requested by February 15, 2015, in accordance with the Office of Nuclear Reactor Regulation Office Instruction LIC-109, "Acceptance Review Procedures." However, since the licensee requested approval of the LAR by April 1, 2015, it is highly recommended that the licensee provide the requested supplemental information earlier to expedite the NRC staff's review. The information requested and associated time frame in this letter was discussed with Murray Williams of your staff on February 2, 2015. If you have any questions, please contact me at (301) 415-1016. Docket No. 50-293 cc: Distribution via Listserv Nadiyah S. Morgan, Project Manager Plant Licensing Branch 1-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation
| |
|
| |
|
| ML 15034A106 *via email OFFICE NRR/DORL/LPLI-1/PM NRR/DORL/LPLI-1/LA NRR/DSS/SRXB/BC NRR/DORL/LPLI-1/BC NAME NMorgan KGoldstein CJackson BBeasley DATE 2/03/2015 02/03/2015 1/30/2015* 2/03/2015}}
| | By letter dated December 10, 2014 (Agencywide Documents Access and Management System Accession No. ML14349A495), Entergy Nuclear Operations, Inc., the licensee, submitted a license amendment request (LAR) for Pilgrim Nuclear Power Station. The LAR would change the Safety Limit Minimum Critical Power Ratio from <:: 1. 08 to <:: 1.10 for two recirculation loop operation and from <:: 1.11 to <:: 1.12 for single loop operation. The purpose of this letter is to provide the results of the U.S. Nuclear Regulatory Commission (NRC) staff's acceptance review of this LAR. The acceptance review was performed to determine if there is sufficient technical information in scope and depth to allow the NRC staff to complete its detailed technical review. |
| | The acceptance review is also intended to identify whether the application has any readily apparent information insufficiencies in its characterization of the regulatory requirements or the licensing basis of the plant. |
| | Consistent with Title 10 of the Code of Federal Regulations (1 0 CFR) Section 50.90, an amendment to the license (including the technical specifications) must fully describe the changes requested, and following as far as applicable, the form prescribed for original applications. Section 50.34 of 10 CFR addresses the content of technical information required. |
| | This section stipulates that the submittal address the design and operating characteristics, unusual or novel design features, and principal safety considerations. |
| | In order to accept the LAR for review, the NRC staff requests that the licensee provide its regulatory criteria used to determine that the LAR is acceptable. This will support an independent assessment by the NR staff regarding appropriate regulatory requirements and the protection of public health and safety and the environment. If the licensee's response to the NRC staff's request is not received by February 15, 2015, the application will not be accepted for review pursuant to 10 CFR 2.101 and the NRC will cease its review activities associated with the application. If the application is subsequently accepted for review, you will be advised of any further information needed to support the NRC staff's detailed technical review by separate correspondence. |
| | |
| | J. Dent The NRC staff requests that the licensee supplement the application to address the information requested by February 15, 2015, in accordance with the Office of Nuclear Reactor Regulation Office Instruction LIC-109, "Acceptance Review Procedures." However, since the licensee requested approval of the LAR by April 1, 2015, it is highly recommended that the licensee provide the requested supplemental information earlier to expedite the NRC staff's review. |
| | The information requested and associated time frame in this letter was discussed with Murray Williams of your staff on February 2, 2015. |
| | If you have any questions, please contact me at (301) 415-1016. |
| | Nadiyah S. Morgan, Project Manager Plant Licensing Branch 1-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-293 cc: Distribution via Listserv |
| | |
| | ML15034A106 *via email OFFICE NRR/DORL/LPLI-1/PM NRR/DORL/LPLI-1/LA NRR/DSS/SRXB/BC NRR/DORL/LPLI-1/BC NAME NMorgan KGoldstein CJackson BBeasley DATE 2/03/2015 02/03/2015 1/30/2015* 2/03/2015}} |
Letter Sequence Acceptance Review |
---|
|
|
MONTHYEARML14349A4952014-12-10010 December 2014 Proposed Change to Technical Specifications Concerning the Safety Limit Minimum Critical Power Ratio Project stage: Request ML15034A1062015-02-0303 February 2015 Supplemental Information Needed for Acceptance of Requested Licensing Action Regarding the Safety Limit Minimum Critical Power Ratio License Amendment Request Project stage: Acceptance Review ML15050A2452015-02-13013 February 2015 Response to Request for Supplemental Information Needed for Acceptance of Requested Licensing Action Regarding the Safety Limit Minimum Critical Power Ratio License Amendment Request Project stage: Supplement ML15051A2832015-02-19019 February 2015 NRR E-mail Capture - Pilgrim - Acceptance Review Safety Limit Minimum Critical Power Ratio (MF5431) Project stage: Acceptance Review ML15051A0322015-02-25025 February 2015 Request for Additional Information Regarding the Safety Limit Minimum Critical Power Ratio License Amendment Request Project stage: RAI ML15051A0232015-02-25025 February 2015 Request for Withholding Information from Public Disclosure (Tac No. MF5431) Project stage: Withholding Request Acceptance ML15051A0272015-03-0606 March 2015 Federal Register Notice - License Amendment Application; Opportunity to Comment, Request a Hearing, and Petition for Leave to Intervene; Order for Entergy Nuclear Operations, Inc. Pilgrim Nuclear Power Station Project stage: Other ML15051A0242015-03-0606 March 2015 Individual Notice of Consideration of Issuance of Amendment to Facility Operating License, Proposed No Significant Hazards Consideration Determination & Opportunity for a Hearing & Order Imposing Procedures for Document Access (MF5431) Project stage: Other NRC-2015-0053, Federal Register Notice - License Amendment Application; Opportunity to Comment, Request a Hearing, and Petition for Leave to Intervene; Order for Entergy Nuclear Operations, Inc. Pilgrim Nuclear Power Station2015-03-0606 March 2015 Federal Register Notice - License Amendment Application; Opportunity to Comment, Request a Hearing, and Petition for Leave to Intervene; Order for Entergy Nuclear Operations, Inc. Pilgrim Nuclear Power Station Project stage: Other ML15075A0332015-03-11011 March 2015 Response to NRC Request for Additional Information Regarding the Safety Limit Minimum Critical Power Ratio License Amendment Request Project stage: Response to RAI ML15037A5232015-03-27027 March 2015 Request for Withholding Information from Public Disclosure Project stage: Withholding Request Acceptance ML15114A0212015-05-0606 May 2015 Issuance of Amendment Regarding the Minimum Critical Power Ratio License Amendment Request Project stage: Approval 2015-02-03
[Table View] |
|
---|
Category:Letter
MONTHYEARL-24-002, Late LLRW Shipment Investigation Report Pursuant to 10 CFR 20, Appendix G2024-02-0202 February 2024 Late LLRW Shipment Investigation Report Pursuant to 10 CFR 20, Appendix G ML23342A1182024-01-0909 January 2024 Independent Spent Fuel Storage Installation Security Inspection Plan L-23-019, Proof of Financial Protection 10 CFR 140.152023-12-18018 December 2023 Proof of Financial Protection 10 CFR 140.15 ML23334A1822023-11-30030 November 2023 Biennial Report for the Defueled Safety Analysis Report Update, Technical Specification Bases Changes, 10 CFR 50.59 Evaluation Summary, and Regulatory Commitment Change Summary November 2021 Through October 2023 L-23-012, Master Decommissioning Trust Agreement Changes for Indian Point Nuclear Generating Units 1, 2 and 3, Pilgrim Nuclear Power Station, Palisades Nuclear Plant and the Non-Qualified Trust for Big Rock Point2023-11-13013 November 2023 Master Decommissioning Trust Agreement Changes for Indian Point Nuclear Generating Units 1, 2 and 3, Pilgrim Nuclear Power Station, Palisades Nuclear Plant and the Non-Qualified Trust for Big Rock Point ML23306A0992023-11-0202 November 2023 and Indian Point Energy Center, Notification of Changes in Schedule in Accordance with 10 CFR 50.82(a)(7) L-23-011, 10 CFR 72.48 Biennial Change Summary Report2023-10-27027 October 2023 10 CFR 72.48 Biennial Change Summary Report IR 05000293/20234012023-08-31031 August 2023 NRC Inspection Report No. 05000293/2023401 & 2023001 (Cover Letter Only) IR 05000293/20230022023-08-0404 August 2023 NRC Inspection Report No. 05000293/2023002 L-23-008, Correction to Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations Holtec Decommissioning International, LLC (HDI)2023-05-23023 May 2023 Correction to Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations Holtec Decommissioning International, LLC (HDI) ML23136A7792023-05-15015 May 2023 Annual Radiological Environmental Operating Report, January 1 Through December 31, 2022 ML23135A2152023-05-15015 May 2023 Annual Radioactive Effluent Release Report, January 1 Through December 31, 2022 L-23-004, HDI Annual Occupational Radiation Exposure Data Reports - 20222023-04-24024 April 2023 HDI Annual Occupational Radiation Exposure Data Reports - 2022 L-23-003, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations2023-03-31031 March 2023 Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations ML23088A0382023-03-29029 March 2023 Stations 1, 2, & 3, Palisades Nuclear Plant, and Big Rock Point - Nuclear Onsite Property Damage Insurance ML23069A2782023-03-13013 March 2023 Request for Scoping Comments Concerning the Environmental Review of Monticello Nuclear Generating Plant, Unit 1 Subsequent License Renewal Application ML22361A1022023-02-24024 February 2023 Reactor Decommissioning Branch Project Management Changes for Some Decommissioning Facilities and Establishment of Backup Project Manager for All Decommissioning Facilities IR 05000293/20220042023-02-15015 February 2023 NRC Inspection Report No. 05000293/2022004 ML22356A0712023-01-31031 January 2023 Issuance of Exemption for Pilgrim Nuclear Power Station ISFSI Regarding Annual Radioactive Effluent Release Report - Cover Letter ML22347A2782022-12-21021 December 2022 Independent Spent Fuel Storage Installation Security Inspection Plan Dated December 21, 2022 L-22-042, Oyster, Pilgrim, Indian Point, Palisades and Big Rock Point - Proof of Financial Protection 10 CFR 140.152022-12-14014 December 2022 Oyster, Pilgrim, Indian Point, Palisades and Big Rock Point - Proof of Financial Protection 10 CFR 140.15 L-22-041, Supplemental Information to Enhance Exemption Request Detail for Pilgrim ISFSI Annual Radioactive Effluent Release Report Due Date Extension2022-12-0909 December 2022 Supplemental Information to Enhance Exemption Request Detail for Pilgrim ISFSI Annual Radioactive Effluent Release Report Due Date Extension IR 05000293/20220032022-11-18018 November 2022 NRC Inspection Report No. 05000293/2022003 L-22-036, Decommissioning Trust Fund Agreement2022-11-0808 November 2022 Decommissioning Trust Fund Agreement ML22276A1762022-10-24024 October 2022 Decommissioning International Proposed Revisions to the Quality Assurance Program Approval Forms for Radioactive Material Packages ML22266A1922022-09-23023 September 2022 and Pilgrim Nuclear Power Station - Request to Withdraw Prior Submissions from NRC Consideration ML22272A0352022-09-22022 September 2022 S. Lynch-Benttinen Letter Regarding U.S. Citizen Intent to Sue U.S. Fish and Wildlife and NOAA Fisheries Representing the Endangered Species (Na Right Whale) Which Will Be Adversely Affected by Holtec International Potential Actions ML22269A4202022-09-22022 September 2022 Citizen Lawsuit ML22241A1122022-08-29029 August 2022 Request for Exemption from 10 CFR 72.212(a)(2), (b)(2), (b)(3), (b)(4), (B)(5)(i), (b)(11), and 72.214 for Pilgrim ISFSI Annual Radioactive Effluent Release Report IR 05000293/20220022022-08-12012 August 2022 NRC Inspection Report No. 05000293/2022002 ML22215A1772022-08-0303 August 2022 Decommissioning International (HDI) Proposed Revisions to the Quality Assurance Program Approval Forms for Radioactive Material Packages ML22206A1512022-08-0101 August 2022 NRC Office of Investigations Case Nos. 1-2022-002 & 1-2022-006 ML22221A2592022-08-0101 August 2022 LTR-22-0217-1-NMSS - Town of Duxbury Letter Opposing the Irradiated Water Release from Pilgrim (Docket No. 05000293) ML22193A1662022-07-28028 July 2022 LTR-22-0154-1 - Heather Govern, VP, Clean Air and Water Program, Et Al., Letter Regarding Radioactive Wastewater Disposal from the Pilgrim Nuclear Power Station (Docket No. 05000293) ML22175A1732022-07-28028 July 2022 LTR-22-0153-1 - Response Letter to D. Turco, Cape Downwinders, from A. Roberts, NRC, Regarding Holtec-Pilgrim Plans to Dump One Million Gallons of Radioactive Waste Into Cape Cod Bay ML22154A4882022-06-0101 June 2022 Letter from Conservation Law Foundation Regarding Irradiated Water Release from Pilgrim ML22154A1622022-05-26026 May 2022 Letter and Email from Save Our Bay/Diane Turco Regarding Irradiated Water Release from Pilgrim ML22136A2602022-05-16016 May 2022 Submittal of Annual Radiological Environmental Operating Report for January 1 Through December 31, 2021 ML22136A2572022-05-16016 May 2022 Submittal of Annual Radioactive Effluent Release Report for January 1 Through December 31, 2021 ML22102A0932022-05-12012 May 2022 LTR-22-0067 Response to Matthew P. Levesque, President, Barnstable Town Council Regarding Irradiated Water Release from Pilgrim IR 05000293/20220012022-05-11011 May 2022 NRC Inspection Report No. 05000293/2022001 ML22104A0542022-04-30030 April 2022 LTR-22-0093 Response to Sheila Lynch-Benttinen, Regarding Irradiated Water Release from Pilgrim L-22-026, Occupational Radiation Exposure Data Report - 20212022-04-29029 April 2022 Occupational Radiation Exposure Data Report - 2021 ML22152A2592022-04-25025 April 2022 Zaccagnini Letter Dated 04/25/22 ML22152A2642022-04-19019 April 2022 Flynn Letter Dated 04/19/22 ML22091A1062022-04-0101 April 2022 Nuclear Onsite Property Damage Insurance (10 CFR 50.54(w)(3)) L-22-022, and Indian Point Nuclear Generating Stations 1, 2, & 3 - Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations - Holtec.2022-03-25025 March 2022 and Indian Point Nuclear Generating Stations 1, 2, & 3 - Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations - Holtec. ML22130A6762022-03-14014 March 2022 Decola Ltr Dtd 03/14/22 Re Potential Discharge of Radioactive Water from Pilgrim Nuclear Power Station ML22041B0762022-03-0707 March 2022 03-07-22 - Letter to the Honorable William R. Keating, Responds to Letter Regarding Proposed Release of Irradiated Water at Pilgrim Nuclear Power Station Into Cape Cod Bay ML22054A2962022-02-23023 February 2022 Annual ISFSI Radioactive Effluent Release Report for 2021 2024-02-02
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 February 3, 2015 Mr. John A. Dent, Jr.
Site Vice President Entergy Nuclear Operations, Inc.
Pilgrim Nuclear Power Station 600 Rocky Hill Road Plymouth, MA 02360
SUBJECT:
PILGRIM NUCLEAR POWER STATION- SUPPLEMENTAL INFORMATION NEEDED FOR ACCEPTANCE OF REQUESTED LICENSING ACTION REGARDING THE SAFETY LIMIT MINIMUM CRITICAL POWER RATIO LICENSE AMENDMENT REQUEST (TAC NO. MF5431)
Dear Mr. Dent:
By letter dated December 10, 2014 (Agencywide Documents Access and Management System Accession No. ML14349A495), Entergy Nuclear Operations, Inc., the licensee, submitted a license amendment request (LAR) for Pilgrim Nuclear Power Station. The LAR would change the Safety Limit Minimum Critical Power Ratio from <:: 1. 08 to <:: 1.10 for two recirculation loop operation and from <:: 1.11 to <:: 1.12 for single loop operation. The purpose of this letter is to provide the results of the U.S. Nuclear Regulatory Commission (NRC) staff's acceptance review of this LAR. The acceptance review was performed to determine if there is sufficient technical information in scope and depth to allow the NRC staff to complete its detailed technical review.
The acceptance review is also intended to identify whether the application has any readily apparent information insufficiencies in its characterization of the regulatory requirements or the licensing basis of the plant.
Consistent with Title 10 of the Code of Federal Regulations (1 0 CFR) Section 50.90, an amendment to the license (including the technical specifications) must fully describe the changes requested, and following as far as applicable, the form prescribed for original applications. Section 50.34 of 10 CFR addresses the content of technical information required.
This section stipulates that the submittal address the design and operating characteristics, unusual or novel design features, and principal safety considerations.
In order to accept the LAR for review, the NRC staff requests that the licensee provide its regulatory criteria used to determine that the LAR is acceptable. This will support an independent assessment by the NR staff regarding appropriate regulatory requirements and the protection of public health and safety and the environment. If the licensee's response to the NRC staff's request is not received by February 15, 2015, the application will not be accepted for review pursuant to 10 CFR 2.101 and the NRC will cease its review activities associated with the application. If the application is subsequently accepted for review, you will be advised of any further information needed to support the NRC staff's detailed technical review by separate correspondence.
J. Dent The NRC staff requests that the licensee supplement the application to address the information requested by February 15, 2015, in accordance with the Office of Nuclear Reactor Regulation Office Instruction LIC-109, "Acceptance Review Procedures." However, since the licensee requested approval of the LAR by April 1, 2015, it is highly recommended that the licensee provide the requested supplemental information earlier to expedite the NRC staff's review.
The information requested and associated time frame in this letter was discussed with Murray Williams of your staff on February 2, 2015.
If you have any questions, please contact me at (301) 415-1016.
Nadiyah S. Morgan, Project Manager Plant Licensing Branch 1-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-293 cc: Distribution via Listserv
ML15034A106 *via email OFFICE NRR/DORL/LPLI-1/PM NRR/DORL/LPLI-1/LA NRR/DSS/SRXB/BC NRR/DORL/LPLI-1/BC NAME NMorgan KGoldstein CJackson BBeasley DATE 2/03/2015 02/03/2015 1/30/2015* 2/03/2015