{{#Wiki_filter:OFFICIAL USE ONLY - PROPRIETARY INFORMATION January 15, 2019 Mr. Gary Peters, Director Licensing and Regulatory Affairs Framatome Inc.
3315 Old Forest Road Lynchburg, VA 24501
 
==SUBJECT:==
REGULATORY AUDIT PLAN FOR JANUARY 30-31, 2019, AUDIT FOR FRAMATOME INC. TOPICAL REPORT BAW-10227, REVISION 1, SUPPLEMENT 1P, EVALUATION OF ADVANCED CLADDING AND STRUCTURAL MATERIAL (M5) IN PWR REACTOR FUEL (CAC MF9716/EPID L-2017-TOP-0031)
 
==Dear Mr. Peters:==
 
By letter dated May 4, 2017, Framatome Inc. (Framatome, formerly AREVA Inc.) submitted Topical Report (TR) BAW-10227, Revision 1, Supplement 1P, Evaluation of Advanced Cladding and Structural Material (M5) in PWR [Pressurized Water Reactor] Reactor Fuel (Agencywide Documents Access and Management System (ADAMS) Accession No. ML17130A708). The purpose of the TR is to re-establish the iron impurity concentration limit without a need to change any application methods or licensee Technical Specifications methodology references based on its evaluation.
The NRC staff determined that a regulatory audit is needed to allow the NRC staff to increase their level of knowledge and understanding of the topic and associated methodologies. The NRC staff will perform a regulatory audit at Framatomes facility in Lynchburg, Virginia on January 30-31, 2019. Enclosed for your information is a copy of the plan the NRC staff will follow on the audit.
NOTICE: Enclosure transmitted herewith contains proprietary information. When separated from Enclosure, this transmittal document is decontrolled.
OFFICIAL USE ONLY - PROPRIETARY INFORMATION
 
OFFICIAL USE ONLY - PROPRIETARY INFORMATION G. Peters                                  Please contact Jonathan Rowley at 301-415-4053 or via e-mail at Jonathan.Rowley@nrc.gov with any questions you may have regarding this letter.
Sincerely,
                                                  /RA/
Dennis C. Morey, Chief Licensing Processes Branch Division of Licensing Projects Office of Nuclear Reactor Regulation Docket: 99902041 Project: 0728
 
==Enclosures:==
: 1. Audit Plan (Proprietary)
: 2. Audit Plan (Non-Proprietary)
OFFICIAL USE ONLY - PROPRIETARY INFORMATION
 
Package- ML18355A977, Letter- ML18355A980, Plan- ML18355A898 (Prop), Plan - ML19003A359 (Non-Prop)            *concurred via e-mail NRR-106 OFFICE    NRR/DLP/PLPB/PM      NRR/DLP/PLPB/LA*    NRR/DSS/SNPB/BC  NRR/DLP/PLPB/BC NAME      JRowley              DHarrison          RLukes            DMorey DATE      01/7/19              01/3/19            01/10/19          01/15/19}}

Latest revision as of 08:44, 20 October 2019

Regulatory Audit Plan for January 30-31, 2019, Audit for Framatome Inc. Topical Report BAW-10227, Revision 1, Supplement 1P,Evaluation of Advanced Cladding and Structural Material (M5) in PWR Reactor Fuel
ML18355A980
Person / Time
Site: 99902041
Issue date: 01/15/2019
From: Dennis Morey
NRC/NRR/DLP/PLPB
To: Peters G
Framatome
Rowley J, NRC/NRR/DLP/PLPB, 415-4053
Shared Package
ML18355A977 List:
References
CAC MF9716, EPID L-2017-TOP-0031 BAW-10227, Rev. 1
Download: ML18355A980 (2)


Text

OFFICIAL USE ONLY - PROPRIETARY INFORMATION January 15, 2019 Mr. Gary Peters, Director Licensing and Regulatory Affairs Framatome Inc.

3315 Old Forest Road Lynchburg, VA 24501

SUBJECT:

REGULATORY AUDIT PLAN FOR JANUARY 30-31, 2019, AUDIT FOR FRAMATOME INC. TOPICAL REPORT BAW-10227, REVISION 1, SUPPLEMENT 1P, EVALUATION OF ADVANCED CLADDING AND STRUCTURAL MATERIAL (M5) IN PWR REACTOR FUEL (CAC MF9716/EPID L-2017-TOP-0031)

Dear Mr. Peters:

By letter dated May 4, 2017, Framatome Inc. (Framatome, formerly AREVA Inc.) submitted Topical Report (TR) BAW-10227, Revision 1, Supplement 1P, Evaluation of Advanced Cladding and Structural Material (M5) in PWR [Pressurized Water Reactor] Reactor Fuel (Agencywide Documents Access and Management System (ADAMS) Accession No. ML17130A708). The purpose of the TR is to re-establish the iron impurity concentration limit without a need to change any application methods or licensee Technical Specifications methodology references based on its evaluation.

The NRC staff determined that a regulatory audit is needed to allow the NRC staff to increase their level of knowledge and understanding of the topic and associated methodologies. The NRC staff will perform a regulatory audit at Framatomes facility in Lynchburg, Virginia on January 30-31, 2019. Enclosed for your information is a copy of the plan the NRC staff will follow on the audit.

NOTICE: Enclosure transmitted herewith contains proprietary information. When separated from Enclosure, this transmittal document is decontrolled.

OFFICIAL USE ONLY - PROPRIETARY INFORMATION

OFFICIAL USE ONLY - PROPRIETARY INFORMATION G. Peters Please contact Jonathan Rowley at 301-415-4053 or via e-mail at Jonathan.Rowley@nrc.gov with any questions you may have regarding this letter.

Sincerely,

/RA/

Dennis C. Morey, Chief Licensing Processes Branch Division of Licensing Projects Office of Nuclear Reactor Regulation Docket: 99902041 Project: 0728

Enclosures:

1. Audit Plan (Proprietary)
2. Audit Plan (Non-Proprietary)

OFFICIAL USE ONLY - PROPRIETARY INFORMATION

Package- ML18355A977, Letter- ML18355A980, Plan- ML18355A898 (Prop), Plan - ML19003A359 (Non-Prop) *concurred via e-mail NRR-106 OFFICE NRR/DLP/PLPB/PM NRR/DLP/PLPB/LA* NRR/DSS/SNPB/BC NRR/DLP/PLPB/BC NAME JRowley DHarrison RLukes DMorey DATE 01/7/19 01/3/19 01/10/19 01/15/19