Letter Sequence Draft Approval |
|---|
|
|
MONTHYEARML18355A9802019-01-15015 January 2019 Regulatory Audit Plan for January 30-31, 2019, Audit for Framatome Inc. Topical Report BAW-10227, Revision 1, Supplement 1P,Evaluation of Advanced Cladding and Structural Material (M5) in PWR Reactor Fuel Project stage: Other ML18355A9772019-01-15015 January 2019 Audit Plan for January 30-31, 2019, Audit Supporting Review of Framatome Inc. Topical Report BAW-10227, Revision 1, Supplement 1P, Evaluation of Advanced Cladding and Structural Material (M5) in PWR Reactor Fuel Project stage: Request ML19043A8682019-04-0808 April 2019 Audit Report for the January 30 - 31, 2019, Audit in Support of the Review of Topical Report BAW-10227P, Revision 1, Supplement 1P, Evaluation of Advanced Cladding and Structural Material (M5) in Pressurized Water Reactor Reactor Fuel Project stage: Approval ML19043A8422019-04-0808 April 2019 Audit Report for the January 30 - 31, 2019, Audit in Support of the Review of Topical Report BAW-10227P, Revision 1, Supplement 1P, Evaluation of Advanced Cladding and Structural Material (M5) in Pressurized Water Reactor Reactor Fuel (Non- Project stage: Approval ML19043A8312019-04-0808 April 2019 Audit Report for the January 30 - 31, 2019, Audit in Support of the Review of Topical Report BAW-10227P, Revision 1, Supplement 1P, Evaluation of Advanced Cladding and Structural Material (M5) in PWR Reactor Fuel Project stage: Request ML19141A3682019-06-0303 June 2019 Resolution of Framatome Comments on Draft Safety Evaluation for Topical Report BAW-10227,Revision 1, Supplement 1P, Evaluation of Advanced Cladding and Structural Material (M5) in PWR Reactor Fuel Project stage: Draft Approval ML19141A1912019-06-0303 June 2019 Transmittal of Final Safety Evaluation for Framatome Inc. Topical Report BAW-10227, Revision 1, Supplement 1P, Evaluation of Advanced Cladding and Structural Material (M5) in PWR Reactor Fuel Project stage: Approval ML19141A1862019-06-0303 June 2019 Final Safety Evaluation for Framatome Inc., Topical Report BAW-10227, Revision 1, Supplement 1P, Evaluation of Advanced Cladding and Structural Material (M5) in PWR Reactor Fuel Project stage: Approval ML19232A0832019-09-0505 September 2019 Verification Letter of the Approval Version of Framatome Inc. Topical Report Baw 10227, Revision 1, Supplement 1P-A, Revision 0 Evaluation of Advanced Cladding and Structural Material (M5) in PWR Reactor Fuel (CAC MF9716/EPID L-2017-TOP-003 Project stage: Other ML19232A0242019-09-0606 September 2019 Request for Withholding Information from Public Disclosure in August 6, 2019, Publication of BAW-10227, Revision 1, Supplement 1P-A, Revision 0, Evaluation of Advanced Cladding and Structural Material (M5) in PWR Reactor Fuel Project stage: Withholding Request Acceptance 2019-06-03
[Table View] |
Text
RESOLUTION OF COMMENTS BY THE OFFICE OF NUCLEAR REACTOR REGULATION ON DRAFT SAFETY EVALUATION FOR TOPICAL REPORT BAW-10227, REVISION 1, SUPPLEMENT 1P, EVALUATION OF ADVANCED CLADDING AND STRUCTURAL MATERIAL (M5) IN PWR REACTOR FUEL FRAMATOME, INC.
PROJECT NO. 728; DOCKET NO. 99902041 This attachment provides the U.S. Nuclear Regulatory Commission (NRC) staffs review and disposition of the comments made by Framatome Inc. (Framatome) on the draft safety evaluation (SE) for Topical Report BAW-10227, Revision 1, Supplement 1P, Evaluation of Advanced Cladding and Structural Material (M5) in PWR [pressurized water reactor] Reactor Fuel. Framatome provided the comments by letter dated May 16, 2019 (Agencywide Documents Access and Management System Accession No. ML19140A065).
NRC Resolution of Proposed Page Line Proposed Change/Comment Change/Comment 2 47 Change 13 to The NRC staff accepts the proposed editorial change. The change was made accordingly in the final SE.
2 50 Change particles to particle The NRC staff accepts the proposed sizes editorial change. The change was made accordingly in the final SE.
Attachment