{{#Wiki_filter:4 TXU Power Comanche Peak Site NRC Onsite Review Site Geotechnical Investigation Activities 12-13 December 2006 Agenda and Introduction
{{#Wiki_filter:4 TXU Power Comanche Peak Site NRC Onsite Review Site Geotechnical Investigation Activities 12-13 December 2006
 
Agenda and Introduction
* Project Introduction
* Project Introduction
-Introductions
  - Introductions
-Project Background and Status* Project Organization and QA* Site Investigations Overview* Site Orientation
  - Project Background and Status
-Site safety briefing-Logistics-Site tour Comanche Peak Site Background" Multiple reactor technologies considered
* Project Organization and QA
* Site Investigations Overview
* Site Orientation
  - Site safety briefing
  - Logistics
  - Site tour
 
Comanche Peak Site Background
" Multiple reactor technologies considered
* Plant placement designs were developed that enveloped potential reactor technologies
* Plant placement designs were developed that enveloped potential reactor technologies
* Multiple placements on the Comanche Peak site were considered before current placement selected* Geotechnical investigation commenced on borings common to all potential reactor technologies (Phase 1)* Geotechnical investigations will finalize site characterization after the reactor technology is selected (Phase 2)* Hydrogeological investigation  
* Multiple placements on the Comanche Peak site were considered before current placement selected
-including well development performed to investigate groundwater conditions Project Organization Site Geotechnical Investigations TXU Power Enercon Services COLA Development WLA Fugro Seismic, Geologic & Site Geotechnical Geotechnical Characterization Investigations T Support Subcontractors Support Subcontractors Project Organization Responsibilities Site Geotechnical Investigations
* Geotechnical investigation commenced on borings common to all potential reactor technologies (Phase 1)
* TXU Power-Site owner* Enercon Services, Inc.-COLA contractor for TXU Power-Providing QA oversight for geotechnical investigation activities as well as managing interface with site owner* Enercon Subcontractors
* Geotechnical investigations will finalize site characterization after the reactor technology is selected (Phase 2)
-William Lettis & Associates, Inc. (WLA) -Provides Overall Technical Direction for Geological, Geotechnical and Seismological Studies-Fugro -Implementation of Site Characterization Activities; i.e., Drilling, Well Installation, Laboratory Testing, Geotechnical Engineering Services Site Investigation/Data Collection Quality Assurance I TXU Power I I Enercon QA Program I Contracted to perform work under LEnercon QA program]I, I Enercon QA Project Plan Document[ Enercon Project Instruction (P1-02)I-4-Includes drilling, well installation, surface and downhole geophysical testing, geologic mapping, and laboratory testing.*Data Collection Plan*Work Plan (DCP)* lnstructions-Preparation of DCP* lnstructions-Preparation of Work Plan* Instructions-Preparation of Work Instructions
* Hydrogeological investigation - including well development performed to investigate groundwater conditions
*Document Control Register JI Quality Assurance* TXU contracted Enercon Services to perform COLA development under the Enercon Services' QA Program* Geotechnical field investigation, laboratory testing, and engineering analysis performed by William Lettis &Associates and Fugro is performed under the Enercon Services' Quality Assurance Project Plan Geologic and Geotechnical Site Characterization
 
* Characterize subsurface with existing (FSAR) and new data* Sufficient new exploration to confirm and refine site stratigraphy
Project Organization Site Geotechnical Investigations TXU Power Enercon Services COLA Development WLA                         Fugro Seismic, Geologic &                 Site Geotechnical                 Geotechnical Characterization               Investigations T
Support                      Support Subcontractors               Subcontractors
 
Project Organization Responsibilities Site Geotechnical Investigations
* TXU Power
  - Site owner
* Enercon Services, Inc.
  - COLA contractor for TXU Power
  - Providing QA oversight for geotechnical investigation activities as well as managing interface with site owner
* Enercon Subcontractors
  - William Lettis & Associates, Inc. (WLA) - Provides Overall Technical Direction for Geological, Geotechnical and Seismological Studies
  - Fugro - Implementation of Site Characterization Activities; i.e.,
Drilling, Well Installation, Laboratory Testing, Geotechnical Engineering Services
 
Site Investigation/Data Collection Quality Assurance I       TXU Power       I I
I, Enercon QA Program I         Contracted to perform work under LEnercon     QA program                     ]
I     Plan Document Enercon QA Project
[     Enercon Project Instruction (P1-02) 4-I-
Includes drilling, well installation, surface and downhole geophysical testing, geologic mapping, and laboratory testing.
                                        *Data Collection Plan
                                        *Work Plan (DCP)
* lnstructions-Preparation of DCP
* lnstructions-Preparation of Work Plan
* Instructions-Preparation of Work Instructions
                                        *Document Control Register JI
 
Quality Assurance
* TXU contracted Enercon Services to perform COLA development under the Enercon Services' QA Program
* Geotechnical field investigation, laboratory testing, and engineering analysis performed by William Lettis &
Associates and Fugro is performed under the Enercon Services' Quality Assurance Project Plan
 
Geologic and Geotechnical Site Characterization
* Characterize subsurface with existing (FSAR) and new data
* Sufficient new exploration to confirm and refine site stratigraphy
* Evaluate site subsurface variability
* Evaluate site subsurface variability
* Develop site profile for ground motion response" Identify possible geologic hazards* Verify Vendor plant design parameters" Prepare Conceptual Foundation/Geotechnical Design* Characterize groundwater conditions (water table, confined aquifers, dewatering requirements)
* Develop site profile for ground motion response
* Evaluate rock excavatibility and excavation support Exploration Protocol" Work will follow formal Enercon QA Program" Performed by qualified, experienced geologists/engineers" Senior Review (licensed professionals)" Formal Internal Technical Review (ITR)" Conformance to NRC RG 1.132, RG-1.138" Satisfy vendor and SSI data requirements u-q ffxpkwionb of 0004"k~ Uafts OU* & i- .04*- W-L-w am mAWmr wo.ws.An P 0 -.ON owom Explamallon Somm;. G~oIM *ad foul daft derdwd "om "in & Bekmui (1974).
" Identify possible geologic hazards
* owh PI*S 01o50 SOf UAI ~oCffi Pau" 0 100 200 kfn ED mm  
* Verify Vendor plant design parameters
!xpbusU.n  
" Prepare Conceptual Foundation/Geotechnical Design
-GsoIm~m Ufta jGs~Ie Mm of Tmas~-a r. Wa,~fl, ~~ -Lfl0S l a, --.#4'4 lIt --~ -a,~t a N lIt W~. a that atta, *~~~4t tatI, a,- ,~ it- fl -tatin.c..  
* Characterize groundwater conditions (water table, confined aquifers, dewatering requirements)
-Ir*t-.a tat 345 aaatha Itrtl'atal laW 0 Cfl~flU bIll-c,.~ taaaal Ittw.at '4 *U~ ---~taam Ia; ra flaIl atlC.l'tllat tlttttl Itlalt,, tal11ata ,a taltlal IfI t fllltall .la nl.at' bw, 1 1 th In..,'AOSW't alIt. ,,'4 qnbt 'tatIt twIlIt wIle a tIn., I alt.4 hAtS 'tama wet laIttOl .t*i lwtaa, 1111 ,tt.sbttl wIn ScIwttt't a.U (3w ha. tlSllS,11SS II -latt.*lawlwlI alItI,, qua 1.51 III SI 'tIll atOllS atwIttIt M' -la, gIty flhll'Ih lIlt Ia lOll 51 NVa.tlt.SltaShl 6111 lOll ,,hlt C*4Il. 1*1 ltt,. WIth lattoata a,, MIlaS IllSIaSl,.W.t 8~irce G*.Iogyiht.
* Evaluate rock excavatibility and excavation support
dst*ed tom Mw Oedo~e AMa. of Texas ~ Oval 15 fl*WtS J~II~a. tout Mw Texas COKWI~SI~O.t Oat EffVkOOmWt5~
 
QUSKy (TCEQ).C ni I
Exploration Protocol
* Coqane PogOf 03 M 2ft l~ tilecnIss o rus Field Exploration Methods* Standard Penetration Testing (SPT) (Phases 1 and 2)* Rock Coring (NQ, HQ sizes)(Phases 1 and 2)* Borehole Pressuremeter Testing (Phase 2)* Seismic Downhole and P-S Suspension Velocity Measurements (Phases 1 and 2)* Borehole Televiewer Profiles (Phases 1 and 2)* Gamma and Caliper Profiles (Phases 1 and 2)* Seismic Refraction and Gravity (Phase 2)* Spectral Analysis of Surface Waves (SASW) (Phase 2)* Borehole Packer Testing (Phase 2)* Cone Penetration Test (CPT)Soundings (Phase 2 potential)
" Work will follow formal Enercon QA Program
* Groundwater Monitoring Wells (Phase 1)* Geologic Mapping (Phase 2)* Test Pit Excavation and Mapping (Phase 2)  
" Performed by qualified, experienced geologists/engineers
-!I V 22 --.1 1;k r --I. ---I 1_____ ~~~~2 MONTHLY PROGRESS REPORT NO. 10 PERIOD ENDING AUGUST 31, 1975 2" ~"'.NUMBER 87 AUGUST 8, 1975 TEXAS UTILITIES SERVICES, INC.COMANCHE PEAK STEAM ELECTRIC STATION 1980-82 2300 MW INSTALLATION TURBINE GENERATOR AREA. BOTTOM-PUMPING CONCRETE INTO UNIT 1 CIRCULATING WATER DISCHARGE TUNNEL; TOP-SCALING SOUTH EXCAVATION WALL. VIEW TO SOUTHWEST A W 11207 --1020- UNIT I UNIT 2 H-920 8 2 0 --- -- -- -, ---720 4 9j r ~~15'GenRs V z~m t r 1120 1020 920 820-720 1 wi¢I 520 --3 ' 520 420 .--44. ..... 420 320- L 32 P-S 500'0 100 200 300 400 500 feet Notes: 1. Structures are schematic 2. No vertical exaggeration Scale  
" Senior Review (licensed professionals)
'v-( 01/4I 7"Iý7!ýý7-I ~C,
" Formal Internal Technical Review (ITR)
-l II I~ h  
" Conformance to NRC RG 1.132, RG-1.138
---F it.I-3./I r-/ý U A'1'~-l t~- -~-3-ýn AI*~ ~-1 a,.-3 3~2 -"~'-~ #'2.- -~-~-* /-'.1 S N Laboratory Testing Program GEOTECHNICAL INDEX GEOTECHNICAL INDEX Moisture Content and Density Specific Gravity Petrographic Thin Section Carbonate Content Consolidation X-Ray Diffraction/Mineralogy Corrosion Grain Size Proctor Atterberg Limits and Indices (soil)Slaking Durability (core)Organic Content California Bearing Ratio (CBR)Test Laboratory Testing Program GEOTECHNICAL STRENGTH Unconfined Compression (core)Unconfined Compression with Modulus (core)Unit Weight and Density (core)Triaxial CU (3-point)Direct Shear (3-point)DYNAMIC TESTING X-ray of UD Samples Prior to Shipping Resonant Column/Torsional Shear Testing (University of Texas -Austin)Lab Shear Wave Velocity (modulus)
" Satisfy vendor and SSI data requirements
 
ffxpkwionb   of0004"k~Uafts OU* i- &        . 04
                                                                                      *- W-u-q L-w am mAWmr wo.
ws.
An owom Explamallon        P0    -. ON Somm;. G~oIM *ad foul daft derdwd "om "in &Bekmui (1974).
* owh PI*S 01o50                       SOf                         UAI ~oCffi Pau" 0             100             200     kfn                     ED       mm
 
                                                                                                            !xpbusU.n - GsoIm~m                           Ufta jGs~Ie Mm of Tmas~
                                                                                                                            -       a
: r.     Wa,
                                                                                                                  ~fl,           ~
                                                                                                              ~         -     Lfl0S           l a,   -
                                                                                                    -       .#4'4             lIt               -     -
                                                                                                                    ~       -             a,~t a N
lIt W~.a                       that atta, *~~~4t             tatI, a,- ,~       it-           fl   -               tatin.c..       -
Ir*t-.a         tat     345 aaatha     Itrtl
                                                                                                  'atal       laW             0 Cfl~flU bIll
                                                                                                      -         c,.~taaaal             Ittw.at '4
* U
                                                                                                  ~                   -         -   -           ~taam Ia;     ra flaIl           atlC.l'tllat tlttttl Itlalt,,         tal11ata ,a             taltlal IfI t fllltall             .la         nl.at'     bw, 11 th In..,
                                                                                                    'AOSW't alIt. ,,'4                 qnbt       'tatIt twIlIt wIle a           tIn.,         I alt.4     hAtS 'tama wet laIttOl           .t*i lwtaa, 1111       ,tt.sbttl wIn ScIwttt't           a.
U (3w ha. tlSllS,11SS 1.51II III -latt.*lawlwlI la,gIty      SIflhll'Ih
                                                                                                                      'tIll atOllSlIlt atwIttIt alItI,,
M' Ia lOll     51-qua NVa.tlt.SltaShl 6111 lOll                     ,,hlt C
                                                                                                            *4Il.         1*1 ltt,. WIth               lattoata a,, MIlaS IllSIaSl,.W.t 8~irce G*.Iogyiht. dst*ed tom MwOedo~e AMa.ofTexas                  ~       Oval 15 fl*WtS J~II~a. tout MwTexas  COKWI~SI~O.tOatEffVkOOmWt5~ QUSKy (TCEQ).
C ni I
* Coqane   PogOf 03   2ft      tilecnIss                                          M     l~ rus o
 
Field Exploration Methods
* Standard Penetration Testing
* Seismic Refraction and Gravity (SPT) (Phases 1 and 2)           (Phase 2)
* Rock Coring (NQ, HQ sizes)
* Spectral Analysis of Surface (Phases 1 and 2)                 Waves (SASW) (Phase 2)
* Borehole Pressuremeter Testing
* Borehole Packer Testing (Phase 2)
(Phase 2)
* Cone Penetration Test (CPT)
* Seismic Downhole and P-S        Soundings (Phase 2 potential)
Suspension Velocity
* Groundwater Monitoring Wells Measurements (Phases 1 and 2)
(Phase 1)
* Borehole Televiewer Profiles
* Geologic Mapping (Phase 2)
(Phases 1 and 2)
* Gamma and Caliper Profiles
* Test Pit Excavation and Mapping (Phases 1 and 2)                (Phase 2)
 
  -!I V
22   --. 1 1; k
I r - -I. - -         - 1
_____ ~~~~2
 
MONTHLY PROGRESS REPORT NO. 10 PERIOD ENDING AUGUST 31, 1975 2" ~"'.
NUMBER 87                                   TEXAS UTILITIES SERVICES, INC.
AUGUST 8, 1975                              COMANCHE PEAK STEAM ELECTRIC STATION 1980-82 2300 MW INSTALLATION TURBINE GENERATOR AREA. BOTTOM-PUMPING CONCRETE INTO UNIT 1 CIRCULATING WATER DISCHARGE TUNNEL; TOP-SCALING SOUTH EXCAVATION WALL. VIEW TO SOUTHWEST
 
A                                                                                                   W 11207                                                                                                       -- 1120 1020-                               UNIT I                                     UNIT 2                       H- 1020 920                                                                                                            920 82 0                                               -,          -- -             -------
820-I 720 1 720                                                   4                   9j       r     ~~
wi¢ 15'GenRs                               V     t z~m r I'('*11 520                                                                                               -   -3 '     520 420 .--* .....                       44.                                                                       420 320-                                                                                     L 32 P-S 500' 100 200           300       400 500 feet Notes:
0                                                                    1. Structures are schematic
: 2. No vertical exaggeration Scale
 
                          'v-( 1/4 0
I 7
      "Iý7
            - I C,~
  !ýý7
 
    -l II     I
~ h
 
    --- F it                                         .I m*
                                                    /
- 3.
I                     r
                  -/ý U A'
1'~-l t
                        ~- -~
                              ýn
                                                                *~
a,.              ~-1 AI
                                        -   3                       3~
2   -                 "~'-~     #'2
                                              .- -~-~-*   /
                                      -'.1                     S N
 
Laboratory Testing Program GEOTECHNICAL INDEX                   GEOTECHNICAL INDEX Moisture Content and Petrographic Thin Section Density Carbonate Content Consolidation Specific Gravity X-Ray Diffraction/Mineralogy                           Corrosion Grain Size                             Proctor Atterberg Limits and Indices     California Bearing Ratio (CBR)
(soil)                             Test Slaking Durability (core)
Organic Content
 
Laboratory Testing Program GEOTECHNICAL STRENGTH                               DYNAMIC TESTING Unconfined Compression (core)       X-ray of UD Samples Prior to Shipping Unconfined Compression with    Resonant Column/Torsional Shear Testing Modulus (core)              (University of Texas - Austin)
Unit Weight and Density (core)      Lab Shear Wave Velocity (modulus)
Triaxial CU (3-point)
Direct Shear (3-point)
 
Project Organization Responsibilities Site Geotechnical Investigations
Project Organization Responsibilities Site Geotechnical Investigations
* WLA provides field project management for geotechnical and geologic data collection tasks" WLA Site Coordinator provides supervision of the day-to-day field activities
* WLA provides field project management for geotechnical and geologic data collection tasks
* Rig Geologist is assigned full-time with a drill rig.Responsibilities include:-Verify drilling or testing operations are conducted in conformance with specified procedures
" WLA Site Coordinator provides supervision of the day-to-day field activities
-Document sample or test depths and test results-Maintain field logs of borings, including classification of materials recovered and description of geotechnical soil properties
* Rig Geologist is assigned full-time with a drill rig.
-Chain-of-custody document preparation and logging samples Geotechnical Borehole Procedure" Work Instructions issued to drilling companies and Rig Geologists defining duties* Boring Assignments for each borehole prepared by WLA Site Coordinator.
Responsibilities include:
Boring assignments specify:-Boring location-Boring type-Boring depth-Required tests-Boring Completion
  - Verify drilling or testing operations are conducted in conformance with specified procedures
  - Document sample or test depths and test results
  - Maintain field logs of borings, including classification of materials recovered and description of geotechnical soil properties
  - Chain-of-custody document preparation and logging samples
 
Geotechnical Borehole Procedure
" Work Instructions issued to drilling companies and Rig Geologists defining duties
* Boring Assignments for each borehole prepared by WLA Site Coordinator. Boring assignments specify:
  - Boring location
  - Boring type
  - Boring depth
  - Required tests
  - Boring Completion
* Rig Geologist directs Drill Crew to prepare drill site and perform drilling per Boring Assignment
* Rig Geologist directs Drill Crew to prepare drill site and perform drilling per Boring Assignment
* Rig Geologist monitors drilling, describes samples, maintains field log* Modifications to Boring Assignment instructions, if needed, reviewed and approved by Site Coordinator
* Rig Geologist monitors drilling, describes samples, maintains field log
* Samples transported to site storage facility at end of each day Current Site Activities
* Modifications to Boring Assignment instructions, if needed, reviewed and approved by Site Coordinator
* Borings-22 geotechnical borings completed or in progress* Testing-Caliper-Gamma-Seismic Downhole and P-S Suspension Velocity Measurements
* Samples transported to site storage facility at end of each day
-Borehole Televiewer Profiles* Monitoring Wells-20 monitoring well clusters installed Safety" Personal protective equipment requirements" Incident reporting (including near misses)* Inclement weather precautions
 
Current Site Activities
* Borings
  - 22 geotechnical borings completed or in progress
* Testing
  - Caliper
  - Gamma
  - Seismic Downhole and P-S Suspension Velocity Measurements
  - Borehole Televiewer Profiles
* Monitoring Wells
  - 20 monitoring well clusters installed
 
Safety
" Personal protective equipment requirements
" Incident reporting (including near misses)
* Inclement weather precautions
* Potential hazardous insects/reptiles
* Potential hazardous insects/reptiles
* Plant access requirements Q&A}}
* Plant access requirements
 
Q&A}}

Latest revision as of 09:34, 23 November 2019

12/12-13/2006 Slides, Txu Power Comanche Peak Site, NRC Onsite Review, Site Geotechnical Investigation Activities.
ML070720250
Person / Time
Site: Comanche Peak  Luminant icon.png
Issue date: 12/12/2006
From:
TXU Power
To:
Office of Nuclear Reactor Regulation
References
Download: ML070720250 (25)


Text

4 TXU Power Comanche Peak Site NRC Onsite Review Site Geotechnical Investigation Activities 12-13 December 2006

Agenda and Introduction

  • Project Introduction

- Introductions

- Project Background and Status

  • Project Organization and QA
  • Site Investigations Overview
  • Site Orientation

- Site safety briefing

- Logistics

- Site tour

Comanche Peak Site Background

" Multiple reactor technologies considered

  • Plant placement designs were developed that enveloped potential reactor technologies
  • Multiple placements on the Comanche Peak site were considered before current placement selected
  • Geotechnical investigation commenced on borings common to all potential reactor technologies (Phase 1)
  • Geotechnical investigations will finalize site characterization after the reactor technology is selected (Phase 2)
  • Hydrogeological investigation - including well development performed to investigate groundwater conditions

Project Organization Site Geotechnical Investigations TXU Power Enercon Services COLA Development WLA Fugro Seismic, Geologic & Site Geotechnical Geotechnical Characterization Investigations T

Support Support Subcontractors Subcontractors

Project Organization Responsibilities Site Geotechnical Investigations

  • TXU Power

- Site owner

  • Enercon Services, Inc.

- COLA contractor for TXU Power

- Providing QA oversight for geotechnical investigation activities as well as managing interface with site owner

  • Enercon Subcontractors

- William Lettis & Associates, Inc. (WLA) - Provides Overall Technical Direction for Geological, Geotechnical and Seismological Studies

- Fugro - Implementation of Site Characterization Activities; i.e.,

Drilling, Well Installation, Laboratory Testing, Geotechnical Engineering Services

Site Investigation/Data Collection Quality Assurance I TXU Power I I

I, Enercon QA Program I Contracted to perform work under LEnercon QA program ]

I Plan Document Enercon QA Project

[ Enercon Project Instruction (P1-02) 4-I-

Includes drilling, well installation, surface and downhole geophysical testing, geologic mapping, and laboratory testing.

  • Data Collection Plan
  • Work Plan (DCP)
  • lnstructions-Preparation of DCP
  • lnstructions-Preparation of Work Plan
  • Instructions-Preparation of Work Instructions
  • Document Control Register JI

Quality Assurance

  • TXU contracted Enercon Services to perform COLA development under the Enercon Services' QA Program
  • Geotechnical field investigation, laboratory testing, and engineering analysis performed by William Lettis &

Associates and Fugro is performed under the Enercon Services' Quality Assurance Project Plan

Geologic and Geotechnical Site Characterization

  • Characterize subsurface with existing (FSAR) and new data
  • Sufficient new exploration to confirm and refine site stratigraphy
  • Evaluate site subsurface variability
  • Develop site profile for ground motion response

" Identify possible geologic hazards

  • Verify Vendor plant design parameters

" Prepare Conceptual Foundation/Geotechnical Design

  • Characterize groundwater conditions (water table, confined aquifers, dewatering requirements)
  • Evaluate rock excavatibility and excavation support

Exploration Protocol

" Work will follow formal Enercon QA Program

" Performed by qualified, experienced geologists/engineers

" Senior Review (licensed professionals)

" Formal Internal Technical Review (ITR)

" Conformance to NRC RG 1.132, RG-1.138

" Satisfy vendor and SSI data requirements

ffxpkwionb of0004"k~Uafts OU* i- & . 04

  • - W-u-q L-w am mAWmr wo.

ws.

An owom Explamallon P0 -. ON Somm;. G~oIM *ad foul daft derdwd "om "in &Bekmui (1974).

  • owh PI*S 01o50 SOf UAI ~oCffi Pau" 0 100 200 kfn ED mm

!xpbusU.n - GsoIm~m Ufta jGs~Ie Mm of Tmas~

- a

r. Wa,

~fl, ~

~ - Lfl0S l a, -

- .#4'4 lIt - -

~ - a,~t a N

lIt W~.a that atta, *~~~4t tatI, a,- ,~ it- fl - tatin.c.. -

Ir*t-.a tat 345 aaatha Itrtl

'atal laW 0 Cfl~flU bIll

- c,.~taaaal Ittw.at '4

  • U

~ - - - ~taam Ia; ra flaIl atlC.l'tllat tlttttl Itlalt,, tal11ata ,a taltlal IfI t fllltall .la nl.at' bw, 11 th In..,

'AOSW't alIt. ,,'4 qnbt 'tatIt twIlIt wIle a tIn., I alt.4 hAtS 'tama wet laIttOl .t*i lwtaa, 1111 ,tt.sbttl wIn ScIwttt't a.

U (3w ha. tlSllS,11SS 1.51II III -latt.*lawlwlI la,gIty SIflhll'Ih

'tIll atOllSlIlt atwIttIt alItI,,

M' Ia lOll 51-qua NVa.tlt.SltaShl 6111 lOll ,,hlt C

  • 4Il. 1*1 ltt,. WIth lattoata a,, MIlaS IllSIaSl,.W.t 8~irce G*.Iogyiht. dst*ed tom MwOedo~e AMa.ofTexas ~ Oval 15 fl*WtS J~II~a. tout MwTexas COKWI~SI~O.tOatEffVkOOmWt5~ QUSKy (TCEQ).

C ni I

  • Coqane PogOf 03 2ft tilecnIss M l~ rus o

Field Exploration Methods

  • Standard Penetration Testing
  • Seismic Refraction and Gravity (SPT) (Phases 1 and 2) (Phase 2)
  • Rock Coring (NQ, HQ sizes)
  • Spectral Analysis of Surface (Phases 1 and 2) Waves (SASW) (Phase 2)
  • Borehole Pressuremeter Testing
  • Borehole Packer Testing (Phase 2)

(Phase 2)

  • Cone Penetration Test (CPT)
  • Seismic Downhole and P-S Soundings (Phase 2 potential)

Suspension Velocity

  • Groundwater Monitoring Wells Measurements (Phases 1 and 2)

(Phase 1)

  • Borehole Televiewer Profiles
  • Geologic Mapping (Phase 2)

(Phases 1 and 2)

  • Gamma and Caliper Profiles
  • Test Pit Excavation and Mapping (Phases 1 and 2) (Phase 2)

-!I V

22 --. 1 1; k

I r - -I. - - - 1

_____ ~~~~2

MONTHLY PROGRESS REPORT NO. 10 PERIOD ENDING AUGUST 31, 1975 2" ~"'.

NUMBER 87 TEXAS UTILITIES SERVICES, INC.

AUGUST 8, 1975 COMANCHE PEAK STEAM ELECTRIC STATION 1980-82 2300 MW INSTALLATION TURBINE GENERATOR AREA. BOTTOM-PUMPING CONCRETE INTO UNIT 1 CIRCULATING WATER DISCHARGE TUNNEL; TOP-SCALING SOUTH EXCAVATION WALL. VIEW TO SOUTHWEST

A W 11207 -- 1120 1020- UNIT I UNIT 2 H- 1020 920 920 82 0 -, -- - -------

820-I 720 1 720 4 9j r ~~

wi¢ 15'GenRs V t z~m r I'('*11 520 - -3 ' 520 420 .--* ..... 44. 420 320- L 32 P-S 500' 100 200 300 400 500 feet Notes:

0 1. Structures are schematic

2. No vertical exaggeration Scale

'v-( 1/4 0

I 7

"Iý7

- I C,~

!ýý7

-l II I

~ h

--- F it .I m*

/

- 3.

I r

-/ý U A'

1'~-l t

~- -~

ýn

  • ~

a,. ~-1 AI

- 3 3~

2 - "~'-~ #'2

.- -~-~-* /

-'.1 S N

Laboratory Testing Program GEOTECHNICAL INDEX GEOTECHNICAL INDEX Moisture Content and Petrographic Thin Section Density Carbonate Content Consolidation Specific Gravity X-Ray Diffraction/Mineralogy Corrosion Grain Size Proctor Atterberg Limits and Indices California Bearing Ratio (CBR)

(soil) Test Slaking Durability (core)

Organic Content

Laboratory Testing Program GEOTECHNICAL STRENGTH DYNAMIC TESTING Unconfined Compression (core) X-ray of UD Samples Prior to Shipping Unconfined Compression with Resonant Column/Torsional Shear Testing Modulus (core) (University of Texas - Austin)

Unit Weight and Density (core) Lab Shear Wave Velocity (modulus)

Triaxial CU (3-point)

Direct Shear (3-point)

Project Organization Responsibilities Site Geotechnical Investigations

  • WLA provides field project management for geotechnical and geologic data collection tasks

" WLA Site Coordinator provides supervision of the day-to-day field activities

  • Rig Geologist is assigned full-time with a drill rig.

Responsibilities include:

- Verify drilling or testing operations are conducted in conformance with specified procedures

- Document sample or test depths and test results

- Maintain field logs of borings, including classification of materials recovered and description of geotechnical soil properties

- Chain-of-custody document preparation and logging samples

Geotechnical Borehole Procedure

" Work Instructions issued to drilling companies and Rig Geologists defining duties

  • Boring Assignments for each borehole prepared by WLA Site Coordinator. Boring assignments specify:

- Boring location

- Boring type

- Boring depth

- Required tests

- Boring Completion

  • Rig Geologist directs Drill Crew to prepare drill site and perform drilling per Boring Assignment
  • Rig Geologist monitors drilling, describes samples, maintains field log
  • Modifications to Boring Assignment instructions, if needed, reviewed and approved by Site Coordinator
  • Samples transported to site storage facility at end of each day

Current Site Activities

  • Borings

- 22 geotechnical borings completed or in progress

  • Testing

- Caliper

- Gamma

- Seismic Downhole and P-S Suspension Velocity Measurements

- Borehole Televiewer Profiles

  • Monitoring Wells

- 20 monitoring well clusters installed

Safety

" Personal protective equipment requirements

" Incident reporting (including near misses)

  • Inclement weather precautions
  • Potential hazardous insects/reptiles
  • Plant access requirements

Q&A