Comanche Peak Nuclear Power Plant Initial License Renewal Application Pre-Application Meeting - Safety September 21, 2021 Lois M. James Senior Project Manager License Renewal Projects Branch Division of New and Renewed Licenses Office of Nuclear Reactor Regulation
Meeting Agenda
- Introductions - NRC
- Overview of License Renewal Process - NRC
- Comanche Peak Nuclear Power Plant (CPNPP)
First License Renewal (60 years) Application -
Luminant
- Public Comment/Question
- Adjourn - NRC 2
- License Renewal Review Process and Inputs into NRC Licensing Decision
- Safety Review:
o Process Overview o Tentative Review Schedule
- NRC Contact Information
- Conclusion / Questions 3
Overview of License Renewal Process - Agenda
License Renewal Review Process and Inputs into NRC Licensing Decision Environmental Review (10 CFR 51)
NRC Renewal Decision (10 CFR 54.29)
Subsequent License RenewalApplication (SLRA) Accepted Safety Review (10 CFR 54)
ACRS Recommendation (10 CFR 54.25)
Hearings*
10 CFR 2 4
Safety Review:
Process Overview Issue Safety Evaluation Report (SER)
Acceptance Review In-Office Technical Review Audit On-SiteAudit BreakoutAudit 5
CPNPP: Tentative Safety Review Schedule 6
Activity Estimated Date Application Submission Date September 30, 2022 Acceptance Date (Project Start Date)
November 21, 2022 In-Office Technical Review Audit December 2022 On-Site Audit January 2023 Breakout Audit January/February 2023 Safety Evaluation Report October 2023 Advisory Committee on Reactor Safeguards (ACRS) Full Committee Meeting December 2023 Licensing Decision May 2024 Note: The review schedule below is tentative and subject tochange.
The schedule is only finalized once the application has been accepted forreview and docketing.
NRC Contact Information 7
Safety Branch Chief
- Lauren Gibson (Lauren.Gibson@nrc.gov)
Environmental Branch Chief
- Robert Elliott (Robert.Elliott@nrc.gov)
Questions?