Comanche Peak Nuclear Power Plant Initial License Renewal Application Pre-Application Meeting - Safety September 21, 2021 Lois M. James Senior Project Manager License Renewal Projects Branch Division of New and Renewed Licenses Office of Nuclear Reactor Regulation

Meeting Agenda

  • Introductions - NRC
  • Comanche Peak Nuclear Power Plant (CPNPP)

First License Renewal (60 years) Application -

Luminant

  • Public Comment/Question
  • Adjourn - NRC 2

Overview of License Renewal Process - Agenda

  • Safety Review:

o Process Overview o Tentative Review Schedule

  • NRC Contact Information
  • Conclusion / Questions 3

License Renewal Review Process and Inputs into NRC Licensing Decision Environmental Review (10 CFR 51)

Subsequent License NRC Renewal Renewal Application Hearings* Decision (SLRA) Accepted 10 CFR 2 (10 CFR 54.29)

Safety ACRS Review Recommendation (10 CFR 54) (10 CFR 54.25) 4

Safety Review:

Process Overview Acceptance Review In-Office Technical Review On-Site Audit Breakout Audit Audit Issue Safety Evaluation Report (SER) 5

CPNPP: Tentative Safety Review Schedule Note: The review schedule below is tentative and subject to change.

The schedule is only finalized once the application has been accepted forreview and docketing.

Activity Estimated Date Application Submission Date September 30, 2022 Acceptance Date (Project Start Date) November 21, 2022 In-Office Technical Review Audit December 2022 On-Site Audit January 2023 Breakout Audit January/February 2023 Safety Evaluation Report October 2023 Advisory Committee on Reactor December 2023 Safeguards (ACRS) Full Committee Meeting Licensing Decision May 2024 6

NRC Contact Information Safety Branch Chief