Comanche Peak Nuclear Power Plant Initial License Renewal Application Pre-Application Meeting -

Environmental September 21, 2021 Tam Tran, Environmental Project Manager License Renewal Branch Division of Rulemaking, Environmental, and Financial Support Office of Nuclear Material Safety and Safeguards

Meeting Agenda

  • Introductions - NRC
  • Comanche Peak Nuclear Power Plant (CPNPP)

First License Renewal (60 years) Application -

Luminant

  • Public Comment/Question
  • Adjourn - NRC 2

Overview of License Renewal Process - Agenda

  • Environmental Review:

- Process Overview

- Environmental Review - Resources

- Tentative Review Schedule

- Logistical Considerations

  • NRC Contact Information
  • Conclusion / Questions 3

License Renewal Review Process and Inputs into NRC Licensing Decision Environmental Review (10 CFR 51)

Subsequent License NRC Renewal Renewal Application Hearings* Decision (SLRA) Accepted 10 CFR 2 (10 CFR 54.29)

Safety ACRS Review Recommendation (10 CFR 54) (10 CFR 54.25) 4

Environmental Review:

Process Overview Issue Environmental Draft Issue Site Audit Supplemental Consider Final Environmental Public Supplemental Public Scoping Impact Comments Environmental Meeting Statement Impact for Public Statement Comment

Environmental Review -

Resources

CPNPP: Tentative Environmental Review Schedule Note: The review schedule below is tentative and subject to change.

The schedule is only finalized once the application has been accepted forreview and docketing.

Activity Estimated Date Application Submission Date September 30, 2022 Acceptance Date (Project Start Date) November 21, 2022 Scoping Period (with public meeting December 2022/January 2023 approximately midway through)

Environmental Audit January 2023 Draft Supplemental Environmental Impact August 2023 Statement (SEIS) Published DSEIS Public Comment Period August/September 2023 Final SEIS Published April 2024 Licensing Decision May 2024 7

Logistical Considerations

  • NRC requests recommendations and contact info for the following:

- Public Meeting Venue

- Public Libraries

- Local Publications and News Papers

- Hotel and Lodging

NRC Contact Information Safety Branch Chief

Environmental Branch Chief

Questions?