Initial License Renewal Application - NRC Presubmittal Meeting Slides - Environmental
ML21259A033
Person / Time
Site: Comanche Peak  Luminant icon.png
Issue date: 09/16/2021
From: Lois James
NRC/NRR/DNRL/NLRP
To:
James L, NRR/DNRL/NRLP, 301-415-3306
References
EPID L-2020-RNW-0029
Download: ML21259A033 (10)


Text

Comanche Peak Nuclear Power Plant Initial License Renewal Application Pre-Application Meeting -

Environmental September 21, 2021 Tam Tran, Environmental Project Manager License Renewal Branch Division of Rulemaking, Environmental, and Financial Support Office of Nuclear Material Safety and Safeguards

Meeting Agenda

  • Introductions - NRC
  • Comanche Peak Nuclear Power Plant (CPNPP)

First License Renewal (60 years) Application -

Luminant

  • Public Comment/Question
  • Adjourn - NRC 2

Overview of License Renewal Process - Agenda

  • Environmental Review:

Process Overview Environmental Review - Resources Tentative Review Schedule Logistical Considerations

  • NRC Contact Information
  • Conclusion / Questions 3

License Renewal Review Process and Inputs into NRC Licensing Decision Environmental Review (10 CFR 51)

NRC Renewal Decision (10 CFR 54.29)

Subsequent License RenewalApplication (SLRA) Accepted Safety Review (10 CFR 54)

ACRS Recommendation (10 CFR 54.25)

Hearings*

10 CFR 2 4

Public Scoping Meeting Environmental Site Audit Issue Final Supplemental Environmental Impact Statement Consider Public Comments Issue Draft Supplemental Environmental Impact Statement for Public Comment Environmental Review:

Process Overview

Environmental Review -

Resources

CPNPP: Tentative Environmental Review Schedule 7

Activity Estimated Date Application Submission Date September 30, 2022 Acceptance Date (Project Start Date)

November 21, 2022 Scoping Period (with public meeting approximately midway through)

December 2022/January 2023 Environmental Audit January 2023 Draft Supplemental Environmental Impact Statement (SEIS) Published August 2023 DSEIS Public Comment Period August/September 2023 Final SEIS Published April 2024 Licensing Decision May 2024 Note: The review schedule below is tentative and subject tochange.

The schedule is only finalized once the application has been accepted forreview and docketing.

Logistical Considerations

  • NRC requests recommendations and contact info for the following:

Public Meeting Venue Public Libraries Local Publications and News Papers Hotel and Lodging

NRC Contact Information 9

Safety Branch Chief

Environmental Branch Chief

Questions?

1 0