Meeting Handouts - Meeting with Strategic Teaming and Resources Sharing - Integrated Regulatory Affairs Group
ML023120024
Person / Time
Site: Wolf Creek, Diablo Canyon, Callaway, Comanche Peak  Pacific Gas & Electric icon.png
Issue date: 11/07/2002
From: Donohew J
NRC/NRR/DLPM/LPD4
To:
References
Download: ML023120024 (13)


Text

NRC FORM 658 U.S. NUCLEAR REGULATORY COMMISSION (9-1999)

TRANSMITTAL OF MEETING HANDOUT MATERIALS FOR IMMEDIATE PLACEMENT IN THE PUBLIC DOMAIN This form is to be filled out (typed or hand-printed)by the person who announced the meeting (i.e., the person who issued the meeting notice). The completed form, and the attachedcopy of meeting handout materials,will be sent to the Document ControlDesk on the same day of the meeting; underno circumstances will this be done later than the working day after the meeting.

Do not include proprietarymaterials.

DATE OF MEETING The attached document(s), which was/were handed out in this meeting, is/are to be placed 11/07/2002 in the public domain as soon as possible. The minutes of the meeting will be issued in the near future. Following are administrative details regarding this meeting:

Docket Number(s) 50-483, 50-445, 50-446, 50-275, 50-323, 50-482 Plant/Facility Name Callaway, Comanche Peak, Diablo Canyon, Wolf Creek TAC Number(s) (ifavailable) Not Applicable Reference Meeting Notice ML022740090 dated October 10, 2002 Purpose of Meeting (copy from meeting notice) Meeting with Strategic Teaming and Resources Sharing Integrated Regulatory Affairs Group NAME OF PERSON WHO ISSUED MEETING NOTICE TITLE Jack Donohew Senior Project Manager OFFICE Office of Nuclear Reactor Regulation DIVISION Division of Licensing Project Management BRANCH Project Directorate IV Distribution of this form and attachments:

Docket File/Central File PUBLIC *0c NRC FORM 658 (9-1999) PRINTED ON RECYCLED PAPER This form was designed using InForms

0 0

ct 0 0 0 0 S

Ct 0

cn 0

0 (f

0)

  • 0 0

CO 0 U rz 0

I CO 0)

I C) 0 CO Cl) 40 0

0 0 H c(NI U Ct) CIA S S S S I :kz

.3

Strategic Teaming and Resource Sharing Successes

"* Common Licensing Actions Submitted

- Review Savings

- Burden Reduction

"* Generic Regulatory Issues

- Review of rulemaking, draft regulatory guides, etc.

- Bulletin 2002-01 and 2002-02 Responses

  • Security Order Response 10/31/2002 3

A Strategic Teaming and Resource Sharing

'ff rI, Common Licensing Actions

  • Past Common Submittals

- Bases Control Program (50.59 Rule) - TSTF-364

- Risk Informed Inservice Inspection (ISI)

- Elimination of PASS Requirements - TSTF-366

- Low Power Calorimetric - TSTF-371

- Positive Flux Rate Trip 10/31/2002 4

Strategic Teaming and Resource Sharing Common Licensing Actions

  • Common LARs under review

- Equipment Hatch Open during Fuel Movement (DC)

- Deletion of License Condition for 24 Hour Report (CP)

- Positive Reactivity Additions (DC)

- Reduced NIS Channels (CA, WC) 10/31/2002 5

Strategic Teaming and Resource Shanng STARS Projects NRC Cost Savings Project LICENSEE Est. Proiect Cost Lead WCNOC TXU PG&E STP APS Savings Utility Description AmerenUE Deletion of TS 5 5 3, Post NRC Cost $99360 $734 40 $2,550 00 $1,152.00 $450 00 $2,245 00 $2.550.00 WCNOC Accident Sampling (TSTF 366) Saving Est. $1,556 00 NA $000 $1398.00 $210000 NA $5,054.40 Risk Informed Inservice NRC Cost $9,083 40 $16,985 40 $34,530 00 $9,374.40 $5,423 60 NA $34,530.00 TXU Inspection (Code Case N-578)

Saving Est. $25,446 60 $17,544 60 $000 $25,155.60 $29,106 40 NA $97,253.20 (1)

Allow the containment NRC Cost $2,670 00 $4,703 40 $5,190 00 $10,215 00 $10,740 00 $6,255.00 $4,703 40 WCNOC equipment hatch open during fuel movement Saving Est. $2,520 00 $487 60 $0.00 NA NA NA $3007.60 Revision to TS 5.5.14, Bases NRC Cost $1,512 00 $691.20 $3,744.00 $1,440 00 NA $2,300.00 $3,744 00 TXU Control Program (TSTF-364)

Saving Est. $2,232 00 $3,052.80 $000 $2,304 00 NA $1,444.00 $9,032 80 NRC Cost (2) $11,18400 (3) (2) (3) NA $11,184 00 WCNOC Expanded COLOR (TSTF 339

& 363)

Saving Est. $000 NA $000 Missed Surveillance NRC Cost (4) $1,035 00 $1,200 00 $2,550 00 $2,100.00 $1,200 00 $2,250 00 AUE

$2,250.00 Requirements SR 3 0 3 (TSTF 358) Saving Est. $0.00 $1,215 00 $1,050 00 ($300 00) $150.00 $1,050 00 $3,165 00 Revised Low Power NRC Cost $1,500 00 (4) NA (2) NA NA $1,500 00 AUE Calorimetric Surveillance (SR 3.3.1.2) Saving Est $0.00 $000 Revision to TS Regarding NRC Cost $9,105 00 $5,295 00 (2) (4) (4) (2) $9,105 00 AUE Suspension of Positive Reactivity Additions Saving Est. $000 $3,810 00 $3,810.00 (1) Estimate additional $50,000 saved (generic review costs spread out among applicants other than TXU)

(2) Not yet submitted (3) Approved pre-STARS (4) More charges expected 10/31/2002 6

Strategic Teaming and Resource Shanng Future LARs - Scheduled 2002/03 Licensing Action Participants/ Schedule Lead Plant Priority TSTF-283 Rev. 3, Mode restrictions for CA WC ST CP DC PV Last quarter of CP SRs in Electrical Specifications Y Y N Y Y Y 2002 or early Doug 2003 Spalding TSTF-360, Revision of DC Electrical CA WC ST CP DC PV Last quarter of CP Specifications D N Y D 2002 or early Mike 2003 Riggcs TSTF-359 Rev. 7, "Allow mode CA WC ST CP DC PV Last quarter of DC changes when not meeting certain 2002

  • Ken LCOs" Y Y Y Y Y Y Schrader TSTF-370, "Increase in Accumulator CA WC ST CP DC PV Last quarter CP- Bob Completion Time from 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> to 24 A A A Y Y A 2002. Dacko hours (WCAP-1 5049)," CLIIP Item.

SER in the FR 07/02 with comments due 08/02.

TSTF-411 WCAP-15376,"Risk- CA WC ST CP DC PV Submit end of WC/CA Informed Assessment of the RTS & Y Y Y Y Y N 2nd quarter - Bert ESFAS Surveillance Test Intervals 2003

Worked together, or back to back.

TSTF-418 WCAP-14333 Rev. 1, CA WC ST CP DC PV Submit end of WC/CA "Relaxation of RPS/ESF Completion Y Y A Y Y N 2nd quarter - Bert Times" and associated TSTF-418 2003

  • Yates submitted 9/01.
  • - Schedules are dependent on NRC approval of topical reports and/or TSTF.

"& S = submitted, N = No (Not Applicable), Y = Yes (Applies), A = Approved, ? =

Applicability undetermined, D = Deferred 10/31/2002 7

A Strategic Teaming and Resource Sharing Other Future LARs Licensing Action Participants/ P Schedule Lead Plant Priority TSTF-417 WCAP-15622, Extend the CA WC ST CP DC PV H To be CA - Mike AOTs for AC Electrical Power Systems Y Y N Y Y N submitted by Riggs and supporting TSTF-417 end of 2003

  • TSTF-412 Rev. 1, Provide Actions for One CA WC ST CP DC PV M Last half of DC-Ken Steam Supply to Turbine Driven AFW Y Y N Y Y Y 2003 *. Do Schrader Pump Inoperable _ I with TSTF-245 TSTF-245 Rev. 1, Operability of AFW CA WC ST CP DC PV M Last half of DC - Ken System Y Y A Y Y A 2003. Do with Schrader TSTF-412 TSTF- 421 WCAP-1 5666, "RCP Flywheel CA WC ST CP DC PV M TBD (2003?)
  • First plant Inspection Elimination Risk Assessment" affected and supporting TSTF-421. Y Y Y Y N Y

"* * - Schedules are dependent on NRC approval of topical reports and/or TSTF.

"* S = submitted, N = No (Not Applicable), Y = Yes (Applies), A = Approved, ? =

10/31/2002 Applicability undetermined, D = Deferred 8

A J

Strategic Teaming and Resource Sharing i.t RASIG o Regulatory Affairs Strategic Issues Group

"* First STARS Center of Business (COB)

"* Staff:

- Manager (IRAG Chairman) - Don Woodlan

- STARS Washington Representative - Rich Luckett

- Projects Manager - Diane Hooper 10/31/2002 9

Strategic Teaming and Resource Sharing RASIG Products

"* Strategic Issue Summaries

"* Briefing papers for STARS management

"* Recommended strategies, priorities, actions or comments on regulatory issues in the form of white papers (position papers), draft letters, etc.

10/31/2002 10

Strategic Teaming and Resource Sharing Jff (i

STARS/NRC Licensing Workshop

"* Proposal STARS to host a joint NRC/STARS Region IV Licensing Workshop during 2003

"* Discussion

- Purpose & Goal of Workshop

- NRC Support

- Possible Dates and Locations 10/31/2002 I1I

T: Strategic Teaming and Resource Sharing Challenges / Areas for Improvement / Lessons Learned

"* Challenges (Security Orders, Steam Generator Inspections, Reactor Vessel Head Inspections)

"* Areas for Improvement / Lessons Learned

- Formats, commonality, parallel versus staggered submittals, lead NRR PMs

"* Open Discussion 10/31/2002 12