ML14058A048: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
(Created page by program invented by StriderTol)
Line 17: Line 17:


=Text=
=Text=
{{#Wiki_filter:NRR BriefingTitle: Oconee Flood Protection (NRR/DRA)
{{#Wiki_filter:NRR Briefing Title: Oconee Flood Protection (NRR/DRA)Category:
Category:
Status  
Status


==Background:==
==Background:==


Adequacy of Flood Protection for Standby Shutdown Facility (SSF) Given Failure of theJocassee DamDue to its configuration on Lake Keowee, the Oconee three-unit site relies entirely on accident mitigation from the Standby Shutdown Facility (SSF) to provide RCP seal cooling, inventory  
Adequacy of Flood Protection for Standby Shutdown Facility (SSF) Given Failure of the Jocassee Dam Due to its configuration on Lake Keowee, the Oconee three-unit site relies entirely on accident mitigation from the Standby Shutdown Facility (SSF) to provide RCP seal cooling, inventory control, and secondary side heat removal under several conditions including a site flood from rupture of the upstream Jocassee Pumped Storage Dam. In 2006, the staff using the Significance Determination Process (SDP) evaluated a performance deficiency of an unanalyzed opening made in the SSF rendering it vulnerable to external flood. The licensee appealed the finding twice. During a re-evaluation on the second appeal, the staff discovered that the licensee had erroneously computed a random Jocassee Dam rupture frequency that was significantly lower than what should have been based on actual data.In the 1980s, the licensee had performed a flooding analysis which predicted a resultant flood height of 4.71 feet given Jocassee Dam rupture. This study was used to justify constructing a seismically qualified 5-foot flood protection wall around the entrance to the SSF and was incorporated into the FSAR becoming part of their-licensing basis. ff-the eany 1990,, due to a nationai response plan, the Federal Energy KegdMliory Commission (FERC) with the licensee oerformed a flood analysi o.- cte3 flood height of between 12 and 16 feet. In 1992, the licensee removed the 5-ft wall and Jocassee rupture flood ptcection their iibensing basis using a potentially inappropriate argument.
: control, and secondary side heat removal under several conditions including a site flood from rupture of the upstream JocasseePumped Storage Dam. In 2006, the staff using the Significance Determination Process (SDP) evaluated a performance deficiency of an unanalyzed opening made in the SSF rendering it vulnerable to externalflood. The licensee appealed the finding twice. During a re-evaluation on the second appeal, the staffdiscovered that the licensee had erroneously computed a random Jocassee Dam rupture frequency thatwas significantly lower than what should have been based on actual data.In the 1980s, the licensee had performed a flooding analysis which predicted a resultant flood height of4.71 feet given Jocassee Dam rupture.
The earlier flooding study which predicted a 4.71-foot flood height is not available.
This study was used to justify constructing a seismically qualified 5-foot flood protection wall around the entrance to the SSF and was incorporated into the FSARbecoming part of their-licensing basis. ff-the eany 1990,, due to a nationai response plan, the FederalEnergy KegdMliory Commission (FERC) with the licensee oerformed a flood analysi o.- cte3flood height of between 12 and 16 feet. In 1992, the licensee removed the 5-ft wall and Jocassee ruptureflood ptcection their iibensing basis using a potentially inappropriate argument.
Only the latter FERC flood analysis is available which clearly demonstrates that the current wall does not provide adequate flood protection.
Theearlier flooding study which predicted a 4.71-foot flood height is not available.
Another discrepancy relates to the lower Jocassee Dam rupture frequency which is referenced in several documents including the Oconee Individual Plant Examination of External Events (IPEEE) and license renewal Severe Accident Mitigation Alternatives (SAMA) submittals.
Only the latter FERC floodanalysis is available which clearly demonstrates that the current wall does not provide adequate floodprotection.
Moreover, other licensees with similar dam rupture vulnerabilities might have adopted this rupture frequency and used it to justify screening out consideration of external flood damage at their sites. Since the extent and impact at the individual sites of this underestimate is unknown, the staff will communicate concerns of potential deficiencies with licensees.
Another discrepancy relates to the lower Jocassee Dam rupture frequency which is referenced in severaldocuments including the Oconee Individual Plant Examination of External Events (IPEEE) and licenserenewal Severe Accident Mitigation Alternatives (SAMA) submittals.  
Licensees may be required to re-visit flooding calculations to ensure validity.SuccesseslAccomplishments:
: Moreover, other licensees withsimilar dam rupture vulnerabilities might have adopted this rupture frequency and used it to justifyscreening out consideration of external flood damage at their sites. Since the extent and impact at theindividual sites of this underestimate is unknown, the staff will communicate concerns of potential deficiencies with licensees.
A draft action plan has been prepared, is partially underway, and stakeholders have been identified.
Licensees may be required to re-visit flooding calculations to ensure validity.
A team was assembled initially with personnel from DRA, DE, DORL, and DPR to consider several options on how to proceed. Staff and management meet regularly and provide progress to the ADES. A preliminary averted cost estimate for use in a regulatory analysis has been performed.
SuccesseslAccomplishments:
A draft Information Notice has been written. Potential stakeholders have been briefed through various presentations made to the ET/LT, inter-office Risk Management Team (RMT), DRA staff, and NSIR.Plans and Schedules:
A draft action plan has been prepared, is partially  
One option is to address the removal of SSF flood protection references from the licensing basis and require the licensee to re-instate the wall in the licensing basis. The second option considered compliance using the backfit rule, 10 CFR 109. The staff is investigating whether a backfit regulatory analysis needs to be done. In either case, the licensee only has the current FERC study. In order to comply with the requirements of adequate flood protection, compensatory measures need to be taken by the licensee to protect the SSF beyond the 5-foot level. A third option was to simultaneously use the first two options with a heavier emphasis on the backfit aspect. The team will also assess issuing an order following the guidance of LIC-504, "Integrated Risk-Informed Decision-Making Process for Emergent Issues".Contacts:
: underway, and stakeholders have been identified.
Ateam was assembled initially with personnel from DRA, DE, DORL, and DPR to consider several optionson how to proceed.
Staff and management meet regularly and provide progress to the ADES. Apreliminary averted cost estimate for use in a regulatory analysis has been performed.
A draftInformation Notice has been written.
Potential stakeholders have been briefed through variouspresentations made to the ET/LT, inter-office Risk Management Team (RMT), DRA staff, and NSIR.Plans and Schedules:
One option is to address the removal of SSF flood protection references from the licensing basis andrequire the licensee to re-instate the wall in the licensing basis. The second option considered compliance using the backfit rule, 10 CFR 109. The staff is investigating whether a backfit regulatory analysis needs to be done. In either case, the licensee only has the current FERC study. In order tocomply with the requirements of adequate flood protection, compensatory measures need to be taken bythe licensee to protect the SSF beyond the 5-foot level. A third option was to simultaneously use the firsttwo options with a heavier emphasis on the backfit aspect. The team will also assess issuing an orderfollowing the guidance of LIC-504, "Integrated Risk-Informed Decision-Making Process for EmergentIssues".Contacts:
Mike Franovich 415-1185 or Jeff Circle 415-1152.}}
Mike Franovich 415-1185 or Jeff Circle 415-1152.}}

Revision as of 22:23, 9 July 2018

NRR Briefing on Oconee Flood Protection (Nrr/Dra)
ML14058A048
Person / Time
Site: Oconee  Duke Energy icon.png
Issue date: 02/04/2014
From:
NRC/NRR/DRA
To:
Shared Package
ML14055A421 List: ... further results
References
FOIA/PA-2012-0325
Download: ML14058A048 (1)


Text

NRR Briefing Title: Oconee Flood Protection (NRR/DRA)Category:

Status

Background:

Adequacy of Flood Protection for Standby Shutdown Facility (SSF) Given Failure of the Jocassee Dam Due to its configuration on Lake Keowee, the Oconee three-unit site relies entirely on accident mitigation from the Standby Shutdown Facility (SSF) to provide RCP seal cooling, inventory control, and secondary side heat removal under several conditions including a site flood from rupture of the upstream Jocassee Pumped Storage Dam. In 2006, the staff using the Significance Determination Process (SDP) evaluated a performance deficiency of an unanalyzed opening made in the SSF rendering it vulnerable to external flood. The licensee appealed the finding twice. During a re-evaluation on the second appeal, the staff discovered that the licensee had erroneously computed a random Jocassee Dam rupture frequency that was significantly lower than what should have been based on actual data.In the 1980s, the licensee had performed a flooding analysis which predicted a resultant flood height of 4.71 feet given Jocassee Dam rupture. This study was used to justify constructing a seismically qualified 5-foot flood protection wall around the entrance to the SSF and was incorporated into the FSAR becoming part of their-licensing basis. ff-the eany 1990,, due to a nationai response plan, the Federal Energy KegdMliory Commission (FERC) with the licensee oerformed a flood analysi o.- cte3 flood height of between 12 and 16 feet. In 1992, the licensee removed the 5-ft wall and Jocassee rupture flood ptcection their iibensing basis using a potentially inappropriate argument.

The earlier flooding study which predicted a 4.71-foot flood height is not available.

Only the latter FERC flood analysis is available which clearly demonstrates that the current wall does not provide adequate flood protection.

Another discrepancy relates to the lower Jocassee Dam rupture frequency which is referenced in several documents including the Oconee Individual Plant Examination of External Events (IPEEE) and license renewal Severe Accident Mitigation Alternatives (SAMA) submittals.

Moreover, other licensees with similar dam rupture vulnerabilities might have adopted this rupture frequency and used it to justify screening out consideration of external flood damage at their sites. Since the extent and impact at the individual sites of this underestimate is unknown, the staff will communicate concerns of potential deficiencies with licensees.

Licensees may be required to re-visit flooding calculations to ensure validity.SuccesseslAccomplishments:

A draft action plan has been prepared, is partially underway, and stakeholders have been identified.

A team was assembled initially with personnel from DRA, DE, DORL, and DPR to consider several options on how to proceed. Staff and management meet regularly and provide progress to the ADES. A preliminary averted cost estimate for use in a regulatory analysis has been performed.

A draft Information Notice has been written. Potential stakeholders have been briefed through various presentations made to the ET/LT, inter-office Risk Management Team (RMT), DRA staff, and NSIR.Plans and Schedules:

One option is to address the removal of SSF flood protection references from the licensing basis and require the licensee to re-instate the wall in the licensing basis. The second option considered compliance using the backfit rule, 10 CFR 109. The staff is investigating whether a backfit regulatory analysis needs to be done. In either case, the licensee only has the current FERC study. In order to comply with the requirements of adequate flood protection, compensatory measures need to be taken by the licensee to protect the SSF beyond the 5-foot level. A third option was to simultaneously use the first two options with a heavier emphasis on the backfit aspect. The team will also assess issuing an order following the guidance of LIC-504, "Integrated Risk-Informed Decision-Making Process for Emergent Issues".Contacts:

Mike Franovich 415-1185 or Jeff Circle 415-1152.