ML14058A032

From kanterella
Jump to navigation Jump to search
Presentation to the Lessons Learned Oversight Board on Oconee Nuclear Station External Flood Protection Issue
ML14058A032
Person / Time
Site: Oconee  Duke Energy icon.png
Issue date: 05/05/2009
From: Jeff Circle
NRC/NRR/DRA
To:
Shared Package
ML14055A421 List: ... further results
References
FOIA/PA-2012-0325
Download: ML14058A032 (8)


Text

Oconee Nuclear Station External Flood Protection Issue Presentation to the Lessons Learned Oversight Board May 5, 2009 Jeff Circle Division of Risk Assessment Office of Nuclear Reactor Regulation Off icia S nly - Securi 1U.S.NRC elated I ormatio Prwi.u*

b~pk d

atEfrnm e~x nt

Background of Issue Oconee Nuclear Station Three-unit site with potentially unique flooding vulnerability:

- On Lake Keowee near Seneca, SC.

- Reliance of 2-unit Keowee Dam as the sole source emergency ac power.

- Site is 11 miles downstream of Jocassee Dam

. A 385-ft high pumped storage hydro-station holding back Lake Jocassee.

Licensee constructed the Standby Shutdown Facility (SSF) on site to address several issues including internal flooding:

  • Houses equipment to safely shut down all 3 units (to Mode 3) in the event of catastrophic flood.
  1. Licensee constructed 5-ft walls around entrances to address external flooding vulnerability from a Jocassee Dam rupture.

o Licensee extended these walls to 7.5-ft in February 2009.

icial Use ly - Sec rity -

2 US, RC elate In mat' n Prowithpk and Lde bwmm. c

Site Inundation Study

, Licensee performed a Jocassee Dam rupture inundation study in 1992.

- Required by Federal Energy Regulatory Commission (FERC) Emergency Action Plan (EAP) on Jocassee license to Duke Hydro.

Calculated inundation levels at ONS ranged from 12.5 to 16.8 feet above SSF grade and clearly above flood protection walls.

NRC Service Water System Operational Performance Inspection (SWSOPI) in 1994 identified potential deficiency in that the 5-ft entrance wall height was significantly less than that predicted by the inundation study.

s l**USNRy

-,Sec ity -

)US.NC d Inma'n L

II N MM1 d1GAORT CC

Licensee Disposition

  1. Licensee stated that Jocassee Dam rupture floods are outside of licensing basis for ONS.

s Licensee committed to addressing this apparent lack of flood protection in its IPEEE submittal in 1995.

s An assessment of the Jocassee Dam flood hazard was included in the IPEEE without disposition of the inspection issue.

fcial Use nly Security4 US C Inforne tionu

NRC Disposition s Review of IPEEE submittals to NRR was managed byRES.

@ Region II service water inspection staff met with NRR staff on September 1, 1994 to discuss several issues arising from the inspection:

- NRR staff considered the SSF flood protection issue of minimal importance and did not provide any bases for these views.

- RES staff was not informed of the lack of resolution of the Jocassee Dam rupture SSF flood inundation issue.

@ NRC staff issued standard close-out letter to the licensee which resolved most IPEEE issues identified in NUREG-1407.

UTSNRC 5*

ted Inforn

_P,,j11ie x~rop~eadlh&F~wnmmnt

Rememergence of Issue

  • The Reactor Oversight Process (ROP) evaluated a licensee performance deficiency arising from an opening made in the side of the SSF below the 5-ft flood protection level for 2 years without an adequate evaluation.

Concerns over adequacy of the SSF wall and the 1992 flood height calculation results resuraced during evaluation of the performance deficiency using the Significance Determination Process (SDP) in 2006.

, NRC staff reviewed the dam failure probability frequency and discovered a flaw in the licensee's calculation in 2007.

Final determination of finding was found to be of WHITE significance.

UR Official Use

- S'c rity -

6 PmeciqPopIkn a~ht Fk um'd

'? "

Actions Taken by NRC Staff NRR concluded that the protection of the Oconee site from external flooding was an adequate protection issue with the following actions taken:

- Issued a 10 CFR 50.54(f) letter requesting information on consequences and how the licensee addresses adequate protection of the site against external floods.

- Determined basis for allowing short-term continued operation of the facility.

- Now interacting with the licensee.

Evaluation of potential generic flooding issues at other sites.

icial Use nly Sec ty-7 (TUSNRC

)la d In rmform MM S

WA ! !t 1 OML IItRC10"(A t.

Mu;x &opkae fwlu En. imnul

Conclusions Several opportunities were missed:

In 1994, NRC reported that the licensee removed external flood protection of the SSF from the Oconee UFSAR and downgraded it to a "PRA issue".

- NRC accepted this and did not question the licensee's rationale used for removal of Jocassee Dam rupture and SSF flood protection.

- NRC did not address the licensing basis impact beyond that of PRA.

e The SWSOPI team members met with NRR in September 1994:

- No written basis was given for the decision by NRR not to consider the importance of high dam rupture frequency and consequence when passing the IPEEE submittal to RES for review.

- No tracking of this issue was made when the review was returned to NRR for issue of the closeout letter.

Ofiia s nl, y-Se

-ri)-

jU.S.NRC Phnct aPooand (At Eurnn

..