ML15257A202: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
(Created page by program invented by StriderTol)
Line 16: Line 16:


=Text=
=Text=
{{#Wiki_filter:MSSVs B 3.7.1 B 3.7  PLANT SYSTEMS B 3.7.1  Main Steam Safety Valves (MSSVs)
{{#Wiki_filter:MSSVs B 3.7.1 B 3.7  PLANT SYSTEMS  
BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.7.1-1 Revision 2 BACKGROUND The primary purpose of the MSSVs is to provide overpressure protection for the secondary system. The MSSVs also provide protection against overpressurizing the reactor coolant pressure boundary by providing a heat sink for the removal of energy from the Reactor Coolant System (RCS) if the preferred heat sink, provided by the condenser and Circulating Water System, is not available.
 
Eight MSSVs are located on each main steam header, outside the Containment Structure, upstream of the main steam isolation valves (MSIVs), as described in Reference 1, Chapter 10. The MSSV rated capacity passes the full steam flow at 102% RATED THERMAL POWER (100% + 2% for instrument error) with the valves full open. This meets the requirements of Reference 2, Section III, Article NC-7000, Class 2 Components. The MSSV design includes staggered setpoints, according to Table 3.7.1-1 in the accompanying Limiting Condition for Operation (LCO), so that only the number of valves needed will actuate. Staggered setpoints reduce the potential for valve chattering, because of insufficient steam pressure to fully open all valves, following a turbine reactor trip. The MSSVs have "R" size orifices. APPLICABLE The design basis for the MSSVs comes from Reference 2, SAFETY ANALYSES Section III, Article NC-7000, Class 2 Components; their purpose is to limit secondary system pressure to  110% of design pressure when passing 100% of design steam flow. This design basis is sufficient to cope with any anticipated operational occurrence or accident considered Reference 1, Chapter 14. The events that challenge the MSSV relieving capacity, and thus RCS pressure, are those characterized as decreased heat removal events, and are presented in Reference 1, Section 14.5. Of these, the full power loss of load event is the limiting anticipated operational occurrence. A loss of load isolates the turbine and condenser, and terminates normal feedwater flow to the steam generators. Before delivery of auxiliary feedwater (AFW) to the steam MSSVs B 3.7.1 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.7.1-2 Revision 23  generators, RCS pressure reaches peak pressure. The peak pressure is < 110% of the design pressure of 2500 psig, but high enough to actuate the pressurizer safety valves.
B 3.7.1  Main Steam Safety Valves (MSSVs)  
Although the Power Level-High Trip is not credited in the loss of load safety analysis, reducing the Power Level-High Trip setpoint ensures the Thermal Power limit supported by the safety analysis is met. The MSSVs satisfy 10 CFR 50.36(c)(2)(ii), Criterion 3. LCO This LCO requires all MSSVs to be OPERABLE in compliance with Reference 2, Section III, Article NC-7000, Class 2 Components, even though this is not a requirement of the Design Basis Accident (DBA) analysis. This is because operation with less than the full number of MSSVs requires limitations on allowable THERMAL POWER (to meet Reference 2, Section III, Article NC-7000, Class 2 Components requirements), and adjustment to the Reactor Protective System trip setpoints to meet the transient analysis limits.
 
These limitations are according to those shown in Table 3.7.1-1, Required Action A.2, and Required Action A.3 in the accompanying LCO.
BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.7.1-1 Revision 2 BACKGROUND The primary purpose of the MSSVs is to provide overpressure protection for the secondary system. The MSSVs also provide  
The OPERABILITY of the MSSVs is defined as the ability to open within the setpoint tolerances, relieve steam generator overpressure, and reseat when pressure has been reduced.
 
The OPERABILITY of the MSSVs is determined by periodic surveillance testing in accordance with the Inservice Testing Program. An MSSV is considered inoperable if it fails to open upon demand.
protection against overpressurizing the reactor coolant  
The lift settings, according to Table 3.7.1-2 in the accompanying LCO, correspond to ambient conditions of the valve at nominal operating temperature and pressure.
 
A Note is added to Table 3.7.1-2, stating that lift settings for a given steam line are also acceptable, if any two valves lift between 935 and 1005 psig, any two other valves lift between 935 and 1035 psig, and the four remaining valves lift between 935 and 1050 psig. Thus, the MSSVs still perform that design basis function properly.
pressure boundary by providing a heat sink for the removal of energy from the Reactor Coolant System (RCS) if the preferred heat sink, provided by the condenser and Circulating Water System, is not available.  
MSSVs B 3.7.1 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.7.1-3 Revision 23  This LCO provides assurance that the MSSVs will perform their designed safety function to mitigate the consequences of accidents that could result in a challenge to the reactor coolant pressure boundary. APPLICABILITY In MODEs 1, 2, and 3, a minimum of five MSSVs per steam generator are required to be OPERABLE, according to Table 3.7.1-1 in the accompanying LCO, which is limiting and bounds all lower MODEs.
 
In MODEs 4 and 5, there are no credible transients requiring the MSSVs.
Eight MSSVs are located on each main steam header, outside the Containment Structure
The steam generators are not normally used for heat removal in MODEs 5 and 6, and thus cannot be overpressurized; there is no requirement for the MSSVs to be OPERABLE in these MODEs. ACTIONS The ACTIONS table is modified by a Note indicating that separate Condition entry is allowed for each MSSV.
, upstream of the main steam isolation valves (MSIVs), as described in Reference 1
A.1 and A.2 An alternative to restoring the inoperable MSSV(s) to OPERABLE status is to reduce power so that the available MSSV relieving capacity meets Code requirements for the power level. The number of inoperable MSSVs will determine the necessary level of reduction in secondary system steam flow and THERMAL POWER required by the reduced reactor trip settings of the power level-high channels. The setpoints in Table 3.7.1-1 have been verified by transient analyses. The operator should limit the maximum steady state power level to some value slightly below this setpoint to avoid an inadvertent overpower trip.
, Chapter 10
The four-hour Completion Time for Required Action A.1 is a reasonable time period to reduce power level and is based on the low probability of an event occurring during this period that would require activation of the MSSVs. An additional 32 hours is allowed in Required Action A.2 to reduce the setpoints. The Completion Time of 36 hours for Required Action A.2 is based on a reasonable time to correct the MSSV MSSVs B 3.7.1 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.7.1-4 Revision 38  inoperability, the time required to perform the power reduction, operating experience in resetting all channels of a protective function, and on the low probability of the occurrence of a transient that could result in steam generator overpressure during this period. B.1 and B.2 If the MSSVs cannot be restored to OPERABLE status in the associated Completion Time, or if one or more steam generators have less than five MSSVs OPERABLE, the unit must be placed in a MODE in which the LCO does not apply. To achieve this status, the unit must be placed in at least MODE 3 within 6 hours, and in MODE 4 within 12 hours. The allowed Completion Times are reasonable, based on operating experience, to reach the required unit conditions from full power conditions in an orderly manner and without challenging unit systems. SURVEILLANCE SR 3.7.1.1 REQUIREMENTS This Surveillance Requirement (SR) verifies the OPERABILITY of the MSSVs by the verification of each MSSV lift setpoints in accordance with the Inservice Testing Program. The safety and relief valve tests are to be performed in accordance with Reference 3. According to Reference 3, the following tests are required for MSSVs:  a. Visual examination;  
. The MSSV rated capacity passes the full steam flow at 102%
RATED THERMAL POWER (100% + 2% for instrument error) with the valves full open. This meets the requirements of Reference 2
, Section III, Article NC-7000, Class 2 Components
. The MSSV design includes staggered setpoints, according to Table 3.7.1-1 in the accompanying Limiting Condition for Operation (
LCO), so that only the number of valves needed will actuate. Staggered setpoints reduce the potential for valve chattering
, because of insufficient steam pressure to fully open all valves
, following a turbine reactor trip. The MSSVs have "R" size orifices.
APPLICABLE The design basis for the MSSVs comes from Reference 2
, SAFETY ANALYSES Section III, Article NC-7000, Class 2 Components
; their purpose is to limit secondary system pressure to  110% of design pressure when passing 100% of design steam flow.
This design basis is sufficient to cope with any anticipated operational occurrence or accident considered Reference 1, Chapter 14
. The events that challenge the MSSV relieving capacity, and thus RCS pressure, are those characterized as decreased heat  
 
removal events, and are presented in Reference 1, Section 14.5
. Of these, the full power loss of load event is the limiting anticipated operational occurrence
. A loss of load isolates the turbine and condenser, and terminates normal feedwater flow to the steam generators. Before  
 
delivery of auxiliary feedwater (AFW) to the steam MSSVs B 3.7.1 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.7.1-2 Revision 23  generators, RCS pressure reaches peak pressure. The peak pressure is < 110% of the design pressure of 2500 psig, but  
 
high enough to actuate the pressurizer safety valves.  
 
Although the Power Level-High Trip is not credited in the loss of load safety analysis, reducing the Power Level-High Trip setpoint ensures the Thermal Power limit supported by the safety analysis is met.
The MSSVs satisfy 10 CFR 50.36(c)(2)(ii), Criterion 3.
LCO This LCO requires all MSSVs to be OPERABLE in compliance with Reference 2, Section III, Article NC-7000, Class 2  
 
Components, even though this is not a requirement of the  
 
Design Basis Accident (DBA) analysis. This is because  
 
operation with less than the full number of MSSVs requires  
 
limitations on allowable THERMAL POWER (to meet Reference 2,  
 
Section III, Article NC-7000, Class 2 Components  
 
requirements), and adjustment to the Reactor Protective  
 
System trip setpoints to meet the transient analysis limits.
 
These limitations are according to those shown in  
 
Table 3.7.1-1, Required Action A.2, and Required Action A.3  
 
in the accompanying LCO.  
 
The OPERABILITY of the MSSVs is defined as the ability to open within the setpoint tolerances, relieve steam generator  
 
overpressure, and reseat when pressure has been reduced.
 
The OPERABILITY of the MSSVs is determined by periodic  
 
surveillance testing in accordance with the Inservice  
 
Testing Program. An MSSV is considered inoperable if it fails to open upon demand.  
 
The lift settings, according to Table 3.7.1-2 in the accompanying LCO, correspond to ambient conditions of the  
 
valve at nominal operating temperature and pressure.  
 
A Note is added to Table 3.7.1-2, stating that lift settings for a given steam line are also acceptable, if any two  
 
valves lift between 935 and 1005 psig, any two other valves lift between 935 and 1035 psig, and the four remaining valves lift between 935 and 1050 psig. Thus, the MSSVs  
 
still perform that design basis function properly.  
 
MSSVs B 3.7.1 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.7.1-3 Revision 23  This LCO provides assurance that the MSSVs will perform their designed safety function to mitigate the consequences  
 
of accidents that could result in a challenge to the reactor  
 
coolant pressure boundary.
APPLICABILITY In MODEs 1, 2, and 3, a minimum of five MSSVs per steam generator are required to be OPERABLE, according to  
 
Table 3.7.1-1 in the accompanying LCO, which is limiting and  
 
bounds all lower MODEs.  
 
In MODEs 4 and 5, there are no credible transients requiring the MSSVs.  
 
The steam generators are not normally used for heat removal in MODEs 5 and 6, and thus cannot be overpressurized; there  
 
is no requirement for the MSSVs to be OPERABLE in these MODEs. ACTIONS The ACTIONS table is modified by a Note indicating that separate Condition entry is allowed for each MSSV.  
 
A.1 and A.2 An alternative to restoring the inoperable MSSV(s) to OPERABLE status is to reduce power so that the available  
 
MSSV relieving capacity meets Code requirements for the power level. The number of inoperable MSSVs will determine the necessary level of reduction in secondary system steam  
 
flow and THERMAL POWER required by the reduced reactor trip  
 
settings of the power level-high channels. The setpoints in  
 
Table 3.7.1-1 have been verified by transient analyses.
The operator should limit the maximum steady state power level to some value slightly below this setpoint to avoid an  
 
inadvertent overpower trip.  
 
The four-hour Completion Time for Required Action A.1 is a reasonable time period to reduce power level and is based on  
 
the low probability of an event occurring during this period  
 
that would require activation of the MSSVs. An additional  
 
32 hours is allowed in Required Action A.2 to reduce the setpoints. The Completion Time of 36 hours for Required Action A.2 is based on a reasonable time to correct the MSSV MSSVs B 3.7.1 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.7.1-4 Revision 38  inoperability, the time required to perform the power reduction, operating experience in resetting all channels of  
 
a protective function, and on the low probability of the  
 
occurrence of a transient that could result in steam  
 
generator overpressure during this period.
B.1 and B.2 If the MSSVs cannot be restored to OPERABLE status in the associated Completion Time, or if one or more steam  
 
generators have less than five MSSVs OPERABLE, the unit must  
 
be placed in a MODE in which the LCO does not apply. To  
 
achieve this status, the unit must be placed in at least  
 
MODE 3 within 6 hours, and in MODE 4 within 12 hours. The  
 
allowed Completion Times are reasonable, based on operating  
 
experience, to reach the required unit conditions from full  
 
power conditions in an orderly manner and without challenging unit systems.
SURVEILLANCE SR 3.7.1.1 REQUIREMENTS This Surveillance Requirement (SR) verifies the OPERABILITY of the MSSVs by the verification of each MSSV lift setpoints  
 
in accordance with the Inservice Testing Program.
The safety and relief valve tests are to be performed in accordance with Reference 3. According to Reference 3, the following tests are required for MSSVs:  a. Visual examination;  
: b. Seat tightness determination;  
: b. Seat tightness determination;  
: c. Setpoint pressure determination (lift setting);  
: c. Setpoint pressure determination (lift setting);  
: d. Compliance with owner's seat tightness criteria; and  e. Verification of the balancing device integrity on balanced valves. The ANSI/American Society of Mechanical Engineers (ASME)
: d. Compliance with owner's seat tightness criteria; and  e. Verification of the balancing device integrity on balanced valves.
Standard requires that all valves be tested every five years, and a minimum of 20% of the valves be tested every 24 months. The ASME Code specifies the activities, as found lift acceptance range, and frequencies necessary to satisfy the requirements. Table 3.7.1-2 defines the lift setting range for each MSSV for OPERABILITY; however, the MSSVs B 3.7.1 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.7.1-5 Revision 38 valves are reset to + 1% during the surveillance test to allow for drift.
The ANSI/American Society of Mechanical Engineers (ASME)  
This SR is modified by a Note that allows entry into and operation in MODE 3 prior to performing the SR. This is to allow testing of the MSSVs at hot conditions. The MSSVs may be either bench tested or tested in situ at hot conditions, using an assist device to simulate lift pressure. If the MSSVs are not tested at hot conditions, the lift setting pressure shall be corrected to ambient conditions of the valve at operating temperature and pressure. REFERENCES 1. Updated Final Safety Analysis Report (UFSAR)  2. ASME, Boiler and Pressure Vessel Code   
 
: 3. ANSI/ASME OM-1-1987, Code for the Operation and Maintenance of Nuclear Power Plants, 1987 MSIVs B 3.7.2 B 3.7  PLANT SYSTEMS B 3.7.2  Main Steam Isolation Valves (MSIVs)
Standard requires that all valves be tested every  
BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.7.2-1 Revision 14 BACKGROUND The MSIVs isolate steam flow from the secondary side of the steam generators following a high energy line break (HELB).
 
Main steam isolation valve closure terminates flow from the unaffected (intact) steam generator. One MSIV is located in each main steam line outside, but close to, the Containment Structure. The MSIVs are downstream from the MSSVs, atmospheric dump valves (ADVs),
five years, and a minimum of 20% of the valves be tested  
and AFW pump turbine steam supplies to prevent their being isolated from the steam generators by MSIV closure. Closing the MSIVs isolates each steam generator from the other, and isolates the turbine, Steam Bypass System, and other auxiliary steam supplies from the steam generators.
 
The MSIVs close on a steam generator isolation signal generated by low steam generator pressure or on a containment spray actuation signal (CSAS) generated by high containment pressure. The MSIVs fail closed on loss of control or actuation power. The steam generator isolation signal also actuates the main feedwater isolation valves (MFIVs) to close. The MSIVs may also be actuated manually.
every 24 months. The ASME Code specifies the activities, as  
A description of the MSIVs is found in Reference 1, Section 10.1. APPLICABLE The design basis of the MSIVs is established by the SAFETY ANALYSES containment analysis for the large steam line break (SLB) inside the Containment Structure, as discussed in Reference 1, Section 14.20. It is also influenced by the accident analysis of the SLB events presented in Reference 1, Section 14.14. The design precludes the blowdown of more than one steam generator, assuming a single active component failure (e.g., the failure of one MSIV to close on demand).
 
found lift acceptance range, and frequencies necessary to  
 
satisfy the requirements. Table 3.7.1-2 defines the lift  
 
setting range for each MSSV for OPERABILITY; however, the MSSVs B 3.7.1 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.7.1-5 Revision 38 valves are reset to +
1% during the surveillance test to allow for drift.  
 
This SR is modified by a Note that allows entry into and operation in MODE 3 prior to performing the SR. This is to  
 
allow testing of the MSSVs at hot conditions. The MSSVs may be either bench tested or tested in situ at hot conditions, using an assist device to simulate lift pressure. If the  
 
MSSVs are not tested at hot conditions, the lift setting  
 
pressure shall be corrected to ambient conditions of the valve at operating temperature and pressure.
REFERENCES 1. Updated Final Safety Analysis Report (UFSAR)  2. ASME, Boiler and Pressure Vessel Code   
: 3. ANSI/ASME OM-1-1987, Code for the Operation and Maintenance of Nuclear Power Plants, 1987  
 
MSIVs B 3.7.2 B 3.7  PLANT SYSTEMS  
 
B 3.7.2  Main Steam Isolation Valves (MSIVs)  
 
BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.7.2-1 Revision 14 BACKGROUND The MSIVs isolate steam flow from the secondary side of the steam generators following a high energy line break (HELB).
 
Main steam isolation valve closure terminates flow from the  
 
unaffected (intact) steam generator.
One MSIV is located in each main steam line outside, but close to, the Containment Structure. The MSIVs are  
 
downstream from the MSSVs, atmospheric dump valves (ADVs),  
 
and AFW pump turbine steam supplies to prevent their being  
 
isolated from the steam generators by MSIV closure. Closing  
 
the MSIVs isolates each steam generator from the other, and  
 
isolates the turbine, Steam Bypass System, and other  
 
auxiliary steam supplies from the steam generators.  
 
The MSIVs close on a steam generator isolation signal generated by low steam generator pressure or on a  
 
containment spray actuation signal (CSAS) generated by high  
 
containment pressure. The MSIVs fail closed on loss of  
 
control or actuation power. The steam generator isolation  
 
signal also actuates the main feedwater isolation valves  
 
(MFIVs) to close. The MSIVs may also be actuated manually.  
 
A description of the MSIVs is found in Reference 1, Section 10.1.
APPLICABLE The design basis of the MSIVs is established by the SAFETY ANALYSES containment analysis for the large steam line break (SLB) inside the Containment Structure, as discussed in Reference 1, Section 14.20. It is also influenced by the accident analysis of the SLB events presented in  
 
Reference 1, Section 14.14. The design precludes the  
 
blowdown of more than one steam generator, assuming a single  
 
active component failure (e.g., the failure of one MSIV to  
 
close on demand).  
 
The limiting case for main SLB Containment Structure response is 75% power, no loss of offsite power, and failure of a steam generator feed pump to trip. This case results in continued feeding of the affected steam generator and maximizes the energy release into the Containment Structure.
The limiting case for main SLB Containment Structure response is 75% power, no loss of offsite power, and failure of a steam generator feed pump to trip. This case results in continued feeding of the affected steam generator and maximizes the energy release into the Containment Structure.
MSIVs B 3.7.2 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.7.2-2 Revision 14 This case does not assume failure of an MSIV; however, an important assumption is both MSIVs are OPERABLE. This prevents blowdown of both steam generators assuming failure of an MSIV to close.
MSIVs B 3.7.2 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.7.2-2 Revision 14 This case does not assume failure of an MSIV; however, an important assumption is both MSIVs are OPERABLE. This  
The accident analysis compares several different SLB events against different acceptance criteria. The large SLB outside the Containment Structure upstream of the MSIV is the limiting SLB for offsite dose, although a break in this short section of main steam header has a very low probability. The large SLB inside the Containment Structure at hot full power is the limiting case for a post-trip return to power. The analysis includes scenarios with offsite power available and with a loss of offsite power following turbine trip.
 
The MSIVs only serve a safety function and remain open during power operation. These valves operate under the following situations:  a. An HELB inside the Containment Structure. In order to maximize the mass and energy release into the Containment Structure, the analysis assumes steam is discharged into the Containment Structure from both steam generators until closure of the MSIV occurs.
prevents blowdown of both steam generators assuming failure  
After MSIV closure, steam is discharged into the Containment Structure only from the affected steam generator. b. A break outside of the Containment Structure and upstream from the MSIVs. This scenario is not a containment pressurization concern. The uncontrolled blowdown of more than one steam generator must be prevented to limit the potential for uncontrolled RCS cooldown and positive reactivity addition. Closure of the MSIVs limits the blowdown to a single steam generator. c. A break downstream of the MSIVs. This type of break will be isolated by the closure of the MSIVs. Events such as increased steam flow through the turbine or the steam bypass valves (e.g., excess load event) will also terminate on closure of the MSIVs. d. A steam generator tube rupture. For this scenario, closure of the MSIV isolates the affected steam MSIVs B 3.7.2 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.7.2-3 Revision 14 generator from the intact steam generator and minimizes radiological releases. The operator is then required to maintain the pressure of the steam generator with the ruptured tube below the MSSV setpoints, a necessary step toward isolating the flow through the rupture. e. The MSIVs are also utilized during other events such as a feedwater line break. These events are less limiting so far as MSIV OPERABILITY is concerned. The MSIVs satisfy 10 CFR 50.36(c)(2)(ii), Criterion 3. LCO This LCO requires that the MSIV in each of the two steam lines be OPERABLE. The MSIVs are considered OPERABLE when the isolation times are within limits, and they close on an isolation actuation signal.
 
This LCO provides assurance that the MSIVs will perform their design safety function to mitigate the consequences of accidents as described in Reference 1, Chapter 14. APPLICABILITY The MSIVs must be OPERABLE in MODE 1 and in MODEs 2 and 3, except when all MSIVs are closed. In these MODEs there is significant mass and energy in the RCS and steam generators.
of an MSIV to close.  
When the MSIVs are closed, they are already performing their safety function. In MODE 4, the steam generator energy is low; therefore, the MSIVs are not required to be OPERABLE.
 
In MODEs 5 and 6, the steam generators do not contain much energy because their temperature is below the boiling point of water; therefore, the MSIVs are not required for isolation of potential high energy secondary system pipe breaks in these MODEs. ACTIONS A.1 With one MSIV inoperable in MODE 1, time is allowed to restore the component to OPERABLE status. Some repairs can be made to the MSIV with the unit hot. The eight hour Completion Time is reasonable, considering the probability of an accident occurring during the time period that would require closure of the MSIVs.
The accident analysis compares several different SLB events against different acceptance criteria. The large SLB outside the Containment Structure upstream of the MSIV is  
MSIVs B 3.7.2 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.7.2-4 Revision 14   B.1  If the MSIV cannot be restored to OPERABLE status within eight hours, the unit must be placed in a MODE in which the LCO does not apply. To achieve this status, the unit must be placed in MODE 2 within six hours and Condition C would be entered. The Completion Time is reasonable, based on operating experience, to reach MODE 2, and close the MSIVs in an orderly manner and without challenging unit systems.
 
C.1 and C.2 Condition C is modified by a Note indicating that separate Condition entry is allowed for each MSIV.
the limiting SLB for offsite dose, although a break in this  
Since the MSIVs are required to be OPERABLE in MODEs 2 and 3, the inoperable MSIVs may either be restored to OPERABLE status or closed. When closed, the MSIVs are already in the position required by the assumptions in the safety analysis.
 
The eight hour Completion Time is consistent with that allowed in Condition A.
short section of main steam header has a very low  
Inoperable MSIVs that cannot be restored to OPERABLE status within the specified Completion Time, but are closed, must be verified on a periodic basis to be closed. This is necessary to ensure that the assumptions in the safety analysis remain valid. The seven day Completion Time is reasonable, based on engineering judgment, MSIV status indications available in the Control Room, and other administrative controls, to ensure these valves are in the closed position.
 
D.1 and D.2 If the MSIVs cannot be restored to OPERABLE status, or closed, within the associated Completion Time, the unit must be placed in a MODE in which the LCO does not apply. To achieve this status, the unit must be placed in at least MODE 3 within 6 hours, and in MODE 4 within 12 hours. The allowed Completion Times are reasonable, based on operating experience, to reach the required unit conditions from MSIVs B 3.7.2 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.7.2-5 Revision 38  MODE 2 conditions in an orderly manner and without challenging unit systems. SURVEILLANCE SR 3.7.2.1 REQUIREMENTS This SR verifies that the closure time of each MSIV is < 5.2 seconds. The MSIV closure time is assumed in the accident and containment analyses.
probability. The large SLB inside the Containment Structure  
The Frequency for this SR is in accordance with the Inservice Testing Program. The MSIVs are tested during each refueling outage in accordance with Reference 2, and sometimes during other cold shutdown periods. The Frequency demonstrates the valve closure time at least once per refueling cycle. Operating experience has shown that these components usually pass the SR when performed. Therefore, the Frequency is acceptable from a reliability standpoint. REFERENCES 1. UFSAR  2. ASME Code for Operation and Maintenance of Nuclear Power Plants AFW System B 3.7.3 B 3.7  PLANT SYSTEMS B 3.7.3  Auxiliary Feedwater (AFW) System BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.7.3-1 Revision 2 BACKGROUND The AFW System automatically supplies feedwater to the steam generators to remove decay heat from the RCS upon the loss of normal feedwater supply. The AFW pumps take suction through a common suction line from the condensate storage tank (CST) (LCO 3.7.4) and pump to the steam generator secondary side via separate and independent connections, to the AFW header outside the Containment Structure. The steam generators function as a heat sink for core decay heat. The heat load is dissipated by releasing steam to the atmosphere from the steam generators via the MSSVs (LCO 3.7.1) or ADVs. If the main condenser is available, steam may be released via the steam bypass valves and the resulting excess water inventory in the hotwell is moved to the backup water supply.
 
The AFW System consists of, one motor-driven AFW pump and two steam turbine-driven pumps configured into two trains. The motor-driven pump provides 100% of AFW flow capacity; each turbine-driven pump can provide 100% of the required capacity to the steam generators as assumed in the accident analysis, but only one turbine-driven pump is lined up to auto start. The other turbine-driven pump is placed in standby and requires a manual start, when it is needed. The pumps are equipped with a common recirculation line to prevent pump operation against a closed system. The motor-driven AFW pump is powered from an independent Class 1E power supply, and feeds both steam generators.
at hot full power is the limiting case for a post-trip  
One pump at full flow is sufficient to remove decay heat and cool the unit to Shutdown Cooling (SDC) System entry conditions. The steam turbine-driven AFW pumps receive steam from either main steam header upstream of the MSIV. Each of the steam feed lines will supply 100% of the requirements of the turbine-driven AFW pump. The turbine-driven AFW pump supplies a common header capable of feeding both steam generators, with air-operated valves (with controllers powered by AC vital buses) actuated to the appropriate steam AFW System B 3.7.3 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.7.3-2 Revision 2 generator by the Auxiliary Feedwater Actuation System (AFAS).
 
The AFW System may also supply feedwater to the steam generators during normal unit startup, shutdown, and hot standby conditions although the normal supply is main feedwater (MFW). The AFW System is designed to supply sufficient water to the steam generator(s) to remove decay heat with steam generator pressure at the setpoint of the MSSVs. Subsequently, the AFW System supplies sufficient water to cool the unit to SDC entry conditions, and steam is released through the ADVs.
return to power. The analysis includes scenarios with  
The AFW System actuates automatically on low steam generator level by the AFAS, as described in LCO 3.3.4. The AFAS logic is designed to feed either or both steam generators with low levels, but will isolate the AFW System from a steam generator having a significantly lower steam pressure than the other steam generator. The AFAS automatically actuates one AFW turbine-driven pump and associated air-operated valves (with controllers powered by AC vital buses) when required, to ensure an adequate feedwater supply to the steam generators. Air-operated valves with controllers powered by AC vital busses are provided for each AFW line to control the AFW flow to each steam generator. The AFW System is discussed in Reference 1. APPLICABLE The AFW System mitigates the consequences of any event with SAFETY ANALYSES a loss of normal feedwater.
 
The design basis of the AFW System is to supply water to the steam generator to remove decay heat and other residual heat, by delivering at least the minimum required flow rate to the steam generators at pressures corresponding to the lowest MSSV set pressure plus 3%.
offsite power available and with a loss of offsite power  
 
following turbine trip.  
 
The MSIVs only serve a safety function and remain open during power operation. These valves operate under the  
 
following situations:  a. An HELB inside the Containment Structure. In order to maximize the mass and energy release into the  
 
Containment Structure, the analysis assumes steam is  
 
discharged into the Containment Structure from both  
 
steam generators until closure of the MSIV occurs.
 
After MSIV closure, steam is discharged into the  
 
Containment Structure only from the affected steam  
 
generator. b. A break outside of the Containment Structure and upstream from the MSIVs. This scenario is not a  
 
containment pressurization concern. The uncontrolled  
 
blowdown of more than one steam generator must be  
 
prevented to limit the potential for uncontrolled RCS  
 
cooldown and positive reactivity addition. Closure of  
 
the MSIVs limits the blowdown to a single steam generator. c. A break downstream of the MSIVs. This type of break will be isolated by the closure of the MSIVs. Events  
 
such as increased steam flow through the turbine or the  
 
steam bypass valves (e.g., excess load event) will also  
 
terminate on closure of the MSIVs. d. A steam generator tube rupture. For this scenario, closure of the MSIV isolates the affected steam MSIVs B 3.7.2 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.7.2-3 Revision 14 generator from the intact steam generator and minimizes radiological releases. The operator is then required  
 
to maintain the pressure of the steam generator with  
 
the ruptured tube below the MSSV setpoints, a necessary  
 
step toward isolating the flow through the rupture. e. The MSIVs are also utilized during other events such as a feedwater line break. These events are less limiting so far as MSIV OPERABILITY is concerned.
The MSIVs satisfy 10 CFR 50.36(c)(2)(ii), Criterion 3.
LCO This LCO requires that the MSIV in each of the two steam lines be OPERABLE. The MSIVs are considered OPERABLE when  
 
the isolation times are within limits, and they close on an  
 
isolation actuation signal.  
 
This LCO provides assurance that the MSIVs will perform their design safety function to mitigate the consequences of accidents as described in Reference 1, Chapter 14.
APPLICABILITY The MSIVs must be OPERABLE in MODE 1 and in MODEs 2 and 3, except when all MSIVs are closed. In these MODEs there is  
 
significant mass and energy in the RCS and steam generators.
 
When the MSIVs are closed, they are already performing their  
 
safety function.
In MODE 4, the steam generator energy is low; therefore, the MSIVs are not required to be OPERABLE.  
 
In MODEs 5 and 6, the steam generators do not contain much energy because their temperature is below the boiling point  
 
of water; therefore, the MSIVs are not required for  
 
isolation of potential high energy secondary system pipe breaks in these MODEs.
ACTIONS A.1 With one MSIV inoperable in MODE 1, time is allowed to restore the component to OPERABLE status. Some repairs can  
 
be made to the MSIV with the unit hot. The eight hour  
 
Completion Time is reasonable, considering the probability  
 
of an accident occurring during the time period that would  
 
require closure of the MSIVs.
MSIVs B 3.7.2 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.7.2-4 Revision 14 B.1  If the MSIV cannot be restored to OPERABLE status within eight hours, the unit must be placed in a MODE in which the  
 
LCO does not apply. To achieve this status, the unit must  
 
be placed in MODE 2 within six hours and Condition C would be entered. The Completion Time is reasonable, based on operating experience, to reach MODE 2, and close the MSIVs  
 
in an orderly manner and without challenging unit systems.  
 
C.1 and C.2 Condition C is modified by a Note indicating that separate Condition entry is allowed for each MSIV.  
 
Since the MSIVs are required to be OPERABLE in MODEs 2 and 3, the inoperable MSIVs may either be restored to  
 
OPERABLE status or closed. When closed, the MSIVs are  
 
already in the position required by the assumptions in the  
 
safety analysis.  
 
The eight hour Completion Time is consistent with that allowed in Condition A.  
 
Inoperable MSIVs that cannot be restored to OPERABLE status within the specified Completion Time, but are closed, must  
 
be verified on a periodic basis to be closed. This is  
 
necessary to ensure that the assumptions in the safety  
 
analysis remain valid. The seven day Completion Time is  
 
reasonable, based on engineering judgment, MSIV status  
 
indications available in the Control Room, and other  
 
administrative controls, to ensure these valves are in the  
 
closed position.  
 
D.1 and D.2 If the MSIVs cannot be restored to OPERABLE status, or closed, within the associated Completion Time, the unit must  
 
be placed in a MODE in which the LCO does not apply. To  
 
achieve this status, the unit must be placed in at least  
 
MODE 3 within 6 hours, and in MODE 4 within 12 hours. The  
 
allowed Completion Times are reasonable, based on operating experience, to reach the required unit conditions from MSIVs B 3.7.2 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.7.2-5 Revision 38  MODE 2 conditions in an orderly manner and without challenging unit systems.
SURVEILLANCE SR 3.7.2.1 REQUIREMENTS This SR verifies that the closure time of each MSIV is  
< 5.2 seconds. The MSIV closure time is assumed in the accident and containment analyses.  
 
The Frequency for this SR is in accordance with the Inservice Testing Program. The MSIVs are tested during each  
 
refueling outage in accordance with Reference 2, and  
 
sometimes during other cold shutdown periods. The Frequency  
 
demonstrates the valve closure time at least once per  
 
refueling cycle. Operating experience has shown that these  
 
components usually pass the SR when performed. Therefore, the Frequency is acceptable from a reliability standpoint.
REFERENCES 1. UFSAR  2. ASME Code for Operation and Maintenance of Nuclear Power Plants
 
AFW System B 3.7.3 B 3.7  PLANT SYSTEMS  
 
B 3.7.3  Auxiliary Feedwater (AFW) System  
 
BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.7.3-1 Revision 2 BACKGROUND The AFW System automatically supplies feedwater to the steam generators to remove decay heat from the RCS upon the loss of normal feedwater supply. The AFW pumps take suction  
 
through a common suction line from the condensate storage tank (CST) (LCO 3.7.4) and pump to the steam generator secondary side via separate and independent connections, to the AFW header outside the Containment Structure. The steam generators function as a heat sink for core decay heat. The heat load is dissipated by releasing steam to the atmosphere  
 
from the steam generators via the MSSVs (LCO 3.7.1) or ADVs.
If the main condenser is available, steam may be released  
 
via the steam bypass valves and the resulting excess water  
 
inventory in the hotwell is moved to the backup water  
 
supply.
The AFW System consists of, one motor-driven AFW pump and two steam turbine-driven pumps configured into two trains.
The motor-driven pump provides 100% of AFW flow capacity; each turbine-driven pump can provide 100% of the required capacity to the steam generators as assumed in the accident  
 
analysis, but only one turbine-driven pump is lined up to auto start. The other turbine-driven pump is placed in standby and requires a manual start, when it is needed. The pumps are equipped with a common recirculation line to  
 
prevent pump operation against a closed system. The motor-driven AFW pump is powered from an independent Class 1E  
 
power supply, and feeds both steam generators.  
 
One pump at full flow is sufficient to remove decay heat and cool the unit to Shutdown Cooling (SDC) System entry  
 
conditions.
The steam turbine-driven AFW pumps receive steam from either main steam header upstream of the MSIV. Each of the steam feed lines will supply 100% of the requirements of the turbine-driven AFW pump. The turbine-driven AFW pump supplies a common header capable of feeding both steam  
 
generators, with air-operated valves (with controllers powered by AC vital buses) actuated to the appropriate steam AFW System B 3.7.3 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.7.3-2 Revision 2 generator by the Auxiliary Feedwater Actuation System (AFAS).
The AFW System may also supply feedwater to the steam generators during normal unit startup, shutdown, and hot  
 
standby conditions although the normal supply is main feedwater (MFW).
The AFW System is designed to supply sufficient water to the steam generator(s) to remove decay heat with steam generator  
 
pressure at the setpoint of the MSSVs. Subsequently, the  
 
AFW System supplies sufficient water to cool the unit to SDC  
 
entry conditions, and steam is released through the ADVs.  
 
The AFW System actuates automatically on low steam generator level by the AFAS, as described in LCO 3.3.4. The AFAS logic is designed to feed either or both steam generators  
 
with low levels, but will isolate the AFW System from a  
 
steam generator having a significantly lower steam pressure  
 
than the other steam generator. The AFAS automatically  
 
actuates one AFW turbine-driven pump and associated air-operated valves (with controllers powered by AC vital buses)  
 
when required, to ensure an adequate feedwater supply to the  
 
steam generators. Air-operated valves with controllers powered by AC vital busses are provided for each AFW line to control the AFW flow to each steam generator.
The AFW System is discussed in Reference 1.
APPLICABLE The AFW System mitigates the consequences of any event with SAFETY ANALYSES a loss of normal feedwater.  
 
The design basis of the AFW System is to supply water to the steam generator to remove decay heat and other residual  
 
heat, by delivering at least the minimum required flow rate  
 
to the steam generators at pressures corresponding to the  
 
lowest MSSV set pressure plus 3%.  
 
The limiting DBAs and transients for the AFW System are as follows:  a. Main SLB; and  b. Loss of normal feedwater.
The limiting DBAs and transients for the AFW System are as follows:  a. Main SLB; and  b. Loss of normal feedwater.
AFW System B 3.7.3 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.7.3-3 Revision 12   The AFW System satisfies 10 CFR 50.36(c)(2)(ii), Criterion 3. LCO This LCO requires that two AFW trains be OPERABLE to ensure that the AFW System will perform its design safety function. A train consists of one pump and the piping, valves, and controls in the direct flow path. Three AFW pumps are installed, consisting of one motor-driven and two non-condensing steam turbine-driven pumps. For a shutdown, only one pump is required to be operating, the others are in standby. Upon automatic initiation of AFW, one motor-driven and one turbine-driven pump automatically start.
AFW System B 3.7.3 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.7.3-3 Revision 12 The AFW System satisfies 10 CFR 50.36(c)(2)(ii),
The AFW System is considered to be OPERABLE when the components and flow paths required to provide AFW flow to the steam generators are OPERABLE. This requires that the motor-driven AFW pump be OPERABLE and capable of supplying AFW flow to both steam generators. The turbine-driven AFW pumps shall be OPERABLE with redundant steam supplies from each of the two main steam lines upstream of the MSIVs and capable of supplying AFW flow to both of the two steam generators. The piping, valves, instrumentation, and controls in the required flow paths shall also be OPERABLE.
Criterion 3.
The LCO is modified by a Note that allows AFW trains required for Operability to be taken out-of-service under administrative control for the performance of periodic testing. This LCO note allows a limited exception to the LCO requirement and allows this condition to exist without requiring any Technical Specification Condition to be entered. The following administrative controls are necessary during periodic testing to ensure the operator(s) can restore the AFW train(s) from the test configuration to its operational configuration when required. A dedicated operator(s) is stationed at the control station(s) with direct communication to the Control Room whenever the train(s) is in the testing configuration. Upon completion of the testing the trains are returned to proper status and verified in proper status by independent operator checks. The administrative controls include certain operator restoration actions that are virtually certain to be successful during accident conditions. These actions AFW System B 3.7.3 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.7.3-4 Revision 26  include but are not limited to the following:  operation of pump discharge valves, operation of trip/throttle valve(s),
LCO This LCO requires that two AFW trains be OPERABLE to ensure that the AFW System will perform its design safety function.
simple handswitch/controller manipulations, and adjusting the local governor speed control knob. The administrative controls do not include actions to restore a tripped AFW pump due to the complicated nature of this task. Periodic tests include those tests that are performed in a controlled manner similar to surveillance tests, but not necessarily on the established surveillance test schedule, such as post-maintenance tests. This Note is necessary because of the AFW pump configuration. APPLICABILITY In MODEs 1, 2, and 3, the AFW System is required to be OPERABLE and to function in the event that the MFW is lost.
A train consists of one pump and the piping, valves, and controls in the direct flow path. Three AFW pumps are installed, consisting of one motor-driven and two non-
In addition, the AFW System is required to supply enough makeup water to replace steam generator secondary inventory and maintain the RCS in MODE 3.
 
In MODE 4, the AFW System is not required, however, it may be used for heat removal via the steam generator although the preferred method is MFW.
condensing steam turbine-driven pumps. For a shutdown, only  
In MODEs 5 and 6, the steam generators are not normally used for decay heat removal, and the AFW System is not required. ACTIONS A Note prohibits the application of LCO 3.0.4.b to an inoperable AFW train. There is an increased risk associated with entering a MODE or other specified condition in the Applicability with an AFW train inoperable and the provisions of LCO 3.0.4.b, which allow entry into a MODE or other specified condition in the Applicability with the LCO not met after performance of a risk assessment addressing inoperable systems and components, should not be applied in this circumstance.
 
A.1 and A.2  With one of the required steam-driven AFW pumps inoperable, action must be taken to align the remaining OPERABLE steam-driven pump to automatic initiating status. This Required Action ensures that a steam-driven AFW pump is available to automatically start, if required. If the OPERABLE AFW pump is properly aligned, the inoperable steam-driven AFW pump must be restored to OPERABLE status (and placed in either AFW System B 3.7.3 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.7.3-5 Revision 48  standby or automatic initiating status, depending upon whether the other steam-driven AFW pump is in standby or automatic initiating status) within seven days. The 72 hour and seven day Completion Times are reasonable, based on the redundant capabilities afforded by the AFW System, the time needed for repairs, and the low probability of a DBA event occurring during this period. Two AFW pumps and flow paths remain to supply feedwater to the steam generators.       B.1 and B.2  With the motor-driven AFW pump inoperable, action must be taken to align the standby steam-driven pump to automatic initiating status. This Required Action ensures that another AFW pump is available to automatically start, if required. If the standby steam-driven pump is properly aligned, the inoperable motor-driven AFW pump must be restored to OPERABLE status within seven days. The 72-hour and seven day, Completion Times are reasonable, based on the redundant capabilities afforded by the AFW System, the time needed for repairs, and the low probability of a DBA event occurring during this period. Two AFW pumps and one flow path remain to supply feedwater to the steam generators.       C.1, C.2, C.3, and C.4  With two AFW pumps inoperable, action must be taken to align the remaining OPERABLE pump to automatic initiating status and to verify the other units motor-driven AFW pump is OPERABLE, along with an OPERABLE cross-tie valve, within one hour. If these Required Actions are completed within the Completion Time, one AFW pump must be restored to OPERABLE status within 72 hours. Verifying the other units motor-driven AFW pump is OPERABLE provides an additional level of assurance that AFW will be available if needed, because the other units AFW can be cross-connected if necessary. The cross-tie valve to the opposite unit is administratively verified OPERABLE by confirming that SR 3.7.3.2 has been performed within the specified Frequency. These one hour Completion Times are reasonable based on the low probability of a DBA occurring during the first hour and the need for AFW during the first hour. The 72 hour completion time to restore one AFW pump to OPERABLE status takes into account the cross-connected capability AFW System B 3.7.3 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.7.3-6 Revision 48 between units and the unlikelihood of an event occurring in the 72 hour period.
one pump is required to be operating, the others are in  
D.1  With one of the required AFW trains inoperable for reasons other than Condition A, B, or C (e.g., flowpath or steam supply valve), action must be taken to restore OPERABLE status within 72 hours. This Condition includes the loss of two steam supply lines to the turbine-driven AFW pumps. The 72 hour Completion Time is reasonable, based on the redundant capabilities afforded by the AFW System, the time needed for repairs, and the low probability of a DBA event occurring during this period. One AFW train remains to supply feedwater to the steam generators.       E.1 and E.2  When the Required Action and associated Completion Time of Condition A, B, C, or D cannot be met the unit must be placed in a MODE in which the LCO does not apply. To achieve this status, the unit must be placed in at least MODE 3 within 6 hours, and in MODE 4 within 12 hours.
 
The allowed Completion Times are reasonable, based on operating experience, to reach the required unit conditions from full power conditions in an orderly manner and without challenging unit systems.
standby. Upon automatic initiation of AFW, one motor-driven  
F.1  Required Action F.1 is modified by a Note indicating that all required MODE changes or power reductions are suspended until one AFW train is restored to OPERABLE status.
 
With two AFW trains inoperable in MODEs 1, 2, and 3, the unit may be in a seriously degraded condition with only non-safety-related means for conducting a cooldown. In such a condition, the unit should not be perturbed by any action, including a power change, that might result in a trip.
and one turbine-driven pump automatically start.  
However, a power change is not precluded if it is determined to be the most prudent action. The seriousness of this condition requires that action be started immediately to restore one AFW train to OPERABLE status. While other plant conditions may require entry into LCO 3.0.3, the ACTIONS AFW System B 3.7.3 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.7.3-7 Revision 55  required by LCO 3.0.3 do not have to be completed because they could force the unit into a less safe condition. SURVEILLANCE SR 3.7.3.1 REQUIREMENTS Verifying the correct alignment for manual, power-operated, and automatic valves in the AFW water and steam supply flow paths, provides assurance that the proper flow paths exist for AFW operation. This SR does not apply to valves that are locked, sealed, or otherwise secured in position, since these valves are verified to be in the correct position prior to locking, sealing, or securing. This SR also does not apply to valves that cannot be inadvertently misaligned, such as check valves. This SR does not require any testing or valve manipulations; rather, it involves verification that those valves capable of potentially being mispositioned are in the correct position.
 
The Surveillance Frequency is controlled under the Surveillance Frequency Control Program.
The AFW System is considered to be OPERABLE when the components and flow paths required to provide AFW flow to  
SR 3.7.3.2  Cycling each testable, remote-operated valve that is not in its operating position, provides assurance that the valves will perform as required. Operating position is the position that the valve is in during normal plant operation.
 
This is accomplished by cycling each valve at least one cycle. This SR ensures that valves required to function during certain scenarios, will be capable of being properly positioned. The Frequency is based on engineering judgment that when cycled in accordance with the Inservice Testing Program, these valves can be placed in the desired position when required.
the steam generators are OPERABLE. This requires that the  
SR 3.7.3.3  Verifying that each AFW pump's developed head at the flow test point is greater than or equal to the required developed head ( 2800 ft for the steam-driven pump and  3100 ft for the motor-driven pump), ensures that AFW pump performance has not degraded during the cycle. Flow and differential head are normal tests of pump performance required by Reference 2. Because it is undesirable to AFW System B 3.7.3 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.7.3-8 Revision 55 introduce cold AFW into the steam generators while they are operating, this testing is performed on recirculation flow.
 
This test confirms one point on the pump design curve and is indicative of overall performance. Such inservice tests confirm component OPERABILITY, trend performance, and detect incipient failures by indicating abnormal performance. Performance of inservice testing, discussed in Reference 2, at three month intervals satisfies this requirement.
motor-driven AFW pump be OPERABLE and capable of supplying  
This SR is modified by a Note indicating that the SR should be deferred up to 24 hours until suitable test conditions are established. This deferral is required because there is an insufficient steam pressure to perform the test.
 
SR 3.7.3.4  This SR ensures that AFW can be delivered to the appropriate steam generator, in the event of any accident or transient that generates an AFAS signal, by demonstrating that each automatic valve in the flow path actuates to its correct position on an actual or simulated actuation signal (verification of flow-modulating characteristics is not required). This SR is not required for valves that are locked, sealed, or otherwise secured in the required position under administrative controls. The Surveillance Frequency is controlled under the Surveillance Frequency Control Program.
AFW flow to both steam generators. The turbine-driven AFW  
This SR is modified by a Note indicating that the SR should be deferred up to 24 hours until suitable test conditions have been established.
 
SR 3.7.3.5  This SR ensures that the AFW pumps will start in the event of any accident or transient that generates an AFAS signal by demonstrating that each AFW pump starts automatically on an actual or simulated actuation signal. The Surveillance Frequency is controlled under the Surveillance Frequency Control Program.
pumps shall be OPERABLE with redundant steam supplies from  
This SR is modified by a Note. The Note indicates that the SR should be deferred up to 24 hours until suitable test conditions are established.
 
AFW System B 3.7.3 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.7.3-9 Revision 55   SR 3.7.3.6  This SR ensures that the AFW system is capable of providing a minimum nominal flow to each flow leg. This ensures that the minimum required flow is capable of feeding each flow leg. The test may be performed on one flow leg at a time. The SR is modified by a Note which states, the SR is not required to be performed for the AFW train with the turbine-driven AFW pump until up to 24 hours after reaching 800 psig in the steam generators. The Note ensures that proper test conditions exist prior to performing the test using the turbine-driven AFW pumps. The Surveillance Frequency is controlled under the Surveillance Frequency Control Program.
each of the two main steam lines upstream of the MSIVs and  
SR 3.7.3.7  This SR ensures that the AFW System is properly aligned by verifying the flow path to each steam generator prior to entering MODE 2 operation, after 30 days in MODEs 5 or 6.
 
OPERABILITY of AFW flow paths must be verified before sufficient core heat is generated that would require the operation of the AFW System during a subsequent shutdown.
capable of supplying AFW flow to both of the two steam  
The Frequency is reasonable, based on engineering judgment, and other administrative controls to ensure that flow paths remain OPERABLE. To further ensure AFW System alignment, the OPERABILITY of the flow paths is verified following extended outages to determine that no misalignment of valves has occurred. This SR ensures that the flow path from the CST to the steam generators is properly aligned. Minimum nominal flow to each flow leg is ensured by performance of SR 3.7.3.6. REFERENCES 1. UFSAR, Section 10.3  2. ASME Code for Operation and Maintenance of Nuclear Power Plants CST B 3.7.4 B 3.7  PLANT SYSTEMS B 3.7.4  Condensate Storage Tank (CST)
 
BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.7.4-1 Revision 41 BACKGROUND The CST provides a safety grade source of water to the steam generators for removing decay and sensible heat from the RCS. The CST provides a passive flow of water, by gravity, to the AFW System (LCO 3.7.3). The steam produced is released to the atmosphere by the MSSVs or the atmospheric dump valves. The AFW pumps operate with a continuous recirculation to the CST.
generators. The piping, valves, instrumentation, and  
 
controls in the required flow paths shall also be OPERABLE.  
 
The LCO is modified by a Note that allows AFW trains required for Operability to be taken out-of-service under administrative control for the performance of periodic testing. This LCO note allows a limited exception to the LCO requirement and allows this condition to exist without requiring any Technical Specification Condition to be entered. The following administrative controls are necessary during periodic testing to ensure the operator(s) can restore the AFW train(s) from the test configuration to its operational configuration when required. A dedicated operator(s) is stationed at the control station(s) with direct communication to the Control Room whenever the train(s) is in the testing configuration. Upon completion of the testing the trains are returned to proper status and  
 
verified in proper status by independent operator checks.
The administrative controls include certain operator restoration actions that are virtually certain to be successful during accident conditions. These actions AFW System B 3.7.3 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.7.3-4 Revision 26  include but are not limited to the following:  operation of pump discharge valves, operation of trip/throttle valve(s),  
 
simple handswitch/controller manipulations, and adjusting  
 
the local governor speed control knob. The administrative  
 
controls do not include actions to restore a tripped AFW  
 
pump due to the complicated nature of this task. Periodic tests include those tests that are performed in a controlled manner similar to surveillance tests, but not necessarily on  
 
the established surveillance test schedule, such as post-
 
maintenance tests. This Note is necessary because of the  
 
AFW pump configuration.
APPLICABILITY In MODEs 1, 2, and 3, the AFW System is required to be OPERABLE and to function in the event that the MFW is lost.
 
In addition, the AFW System is required to supply enough  
 
makeup water to replace steam generator secondary inventory  
 
and maintain the RCS in MODE 3.  
 
In MODE 4, the AFW System is not required, however, it may be used for heat removal via the steam generator although  
 
the preferred method is MFW.  
 
In MODEs 5 and 6, the steam generators are not normally used for decay heat removal, and the AFW System is not required.
ACTIONS A Note prohibits the application of LCO 3.0.4.b to an inoperable AFW train. There is an increased risk associated with entering a MODE or other specified condition in the Applicability with an AFW train inoperable and the provisions of LCO 3.0.4.b, which allow entry into a MODE or other specified condition in the Applicability with the LCO not met after performance of a risk assessment addressing inoperable systems and components, should not be applied in this circumstance.  
 
A.1 and A.2  With one of the required steam-driven AFW pumps inoperable, action must be taken to align the remaining OPERABLE steam-
 
driven pump to automatic initiating status. This Required  
 
Action ensures that a steam-driven AFW pump is available to  
 
automatically start, if required. If the OPERABLE AFW pump  
 
is properly aligned, the inoperable steam-driven AFW pump  
 
must be restored to OPERABLE status (and placed in either AFW System B 3.7.3 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.7.3-5 Revision 48  standby or automatic initiating status, depending upon whether the other steam-driven AFW pump is in standby or  
 
automatic initiating status) within seven days. The 72 hour  
 
and seven day Completion Times are reasonable, based on the  
 
redundant capabilities afforded by the AFW System, the time  
 
needed for repairs, and the low probability of a DBA event occurring during this period. Two AFW pumps and flow paths remain to supply feedwater to the steam generators.
B.1 and B.2  With the motor-driven AFW pump inoperable, action must be taken to align the standby steam-driven pump to automatic  
 
initiating status. This Required Action ensures that  
 
another AFW pump is available to automatically start, if  
 
required. If the standby steam-driven pump is properly  
 
aligned, the inoperable motor-driven AFW pump must be  
 
restored to OPERABLE status within seven days. The 72-hour  
 
and seven day, Completion Times are reasonable, based on the  
 
redundant capabilities afforded by the AFW System, the time  
 
needed for repairs, and the low probability of a DBA event  
 
occurring during this period. Two AFW pumps and one flow  
 
path remain to supply feedwater to the steam generators.
C.1, C.2, C.3, and C.4  With two AFW pumps inoperable, action must be taken to align the remaining OPERABLE pump to automatic initiating status  
 
and to verify the other units motor-driven AFW pump is  
 
OPERABLE, along with an OPERABLE cross-tie valve, within  
 
one hour. If these Required Actions are completed within  
 
the Completion Time, one AFW pump must be restored to  
 
OPERABLE status within 72 hours. Verifying the other units  
 
motor-driven AFW pump is OPERABLE provides an additional  
 
level of assurance that AFW will be available if needed,  
 
because the other units AFW can be cross-connected if necessary. The cross-tie valve to the opposite unit is administratively verified OPERABLE by confirming that  
 
SR 3.7.3.2 has been performed within the specified  
 
Frequency. These one hour Completion Times are reasonable  
 
based on the low probability of a DBA occurring during the  
 
first hour and the need for AFW during the first hour. The  
 
72 hour completion time to restore one AFW pump to OPERABLE  
 
status takes into account the cross-connected capability AFW System B 3.7.3 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.7.3-6 Revision 48 between units and the unlikelihood of an event occurring in the 72 hour period.  
 
D.1  With one of the required AFW trains inoperable for reasons other than Condition A, B, or C (e.g., flowpath or steam supply valve), action must be taken to restore OPERABLE status within 72 hours. This Condition includes the loss of  
 
two steam supply lines to the turbine-driven AFW pumps. The  
 
72 hour Completion Time is reasonable, based on the  
 
redundant capabilities afforded by the AFW System, the time  
 
needed for repairs, and the low probability of a DBA event  
 
occurring during this period. One AFW train remains to  
 
supply feedwater to the steam generators.
E.1 and E.2  When the Required Action and associated Completion Time of Condition A, B, C, or D cannot be met the unit must be  
 
placed in a MODE in which the LCO does not apply. To  
 
achieve this status, the unit must be placed in at least  
 
MODE 3 within 6 hours, and in MODE 4 within 12 hours.  
 
The allowed Completion Times are reasonable, based on operating experience, to reach the required unit conditions  
 
from full power conditions in an orderly manner and without  
 
challenging unit systems.  
 
F.1  Required Action F.1 is modified by a Note indicating that all required MODE changes or power reductions are suspended  
 
until one AFW train is restored to OPERABLE status.  
 
With two AFW trains inoperable in MODEs 1, 2, and 3, the unit may be in a seriously degraded condition with only non-safety-related means for conducting a cooldown. In such a condition, the unit should not be perturbed by any action,  
 
including a power change, that might result in a trip.
 
However, a power change is not precluded if it is determined  
 
to be the most prudent action. The seriousness of this  
 
condition requires that action be started immediately to  
 
restore one AFW train to OPERABLE status. While other plant  
 
conditions may require entry into LCO 3.0.3, the ACTIONS AFW System B 3.7.3 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.7.3-7 Revision 55  required by LCO 3.0.3 do not have to be completed because they could force the unit into a less safe condition.
SURVEILLANCE SR 3.7.3.1 REQUIREMENTS Verifying the correct alignment for manual, power-operated, and automatic valves in the AFW water and steam supply flow  
 
paths, provides assurance that the proper flow paths exist  
 
for AFW operation. This SR does not apply to valves that  
 
are locked, sealed, or otherwise secured in position, since  
 
these valves are verified to be in the correct position  
 
prior to locking, sealing, or securing. This SR also does  
 
not apply to valves that cannot be inadvertently misaligned,  
 
such as check valves. This SR does not require any testing  
 
or valve manipulations; rather, it involves verification  
 
that those valves capable of potentially being mispositioned  
 
are in the correct position.  
 
The Surveillance Frequency is controlled under the Surveillance Frequency Control Program.  
 
SR 3.7.3.2  Cycling each testable, remote-operated valve that is not in its operating position, provides assurance that the valves  
 
will perform as required. Operating position is the  
 
position that the valve is in during normal plant operation.
 
This is accomplished by cycling each valve at least one  
 
cycle. This SR ensures that valves required to function  
 
during certain scenarios, will be capable of being properly  
 
positioned. The Frequency is based on engineering judgment that when cycled in accordance with the Inservice Testing Program, these valves can be placed in the desired position  
 
when required.  
 
SR 3.7.3.3  Verifying that each AFW pump's developed head at the flow test point is greater than or equal to the required developed head ( 2800 ft for the steam-driven pump and  3100 ft for the motor-driven pump), ensures that AFW pump performance has not degraded during the cycle. Flow and  
 
differential head are normal tests of pump performance  
 
required by Reference 2. Because it is undesirable to AFW System B 3.7.3 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.7.3-8 Revision 55 introduce cold AFW into the steam generators while they are operating, this testing is performed on recirculation flow.
 
This test confirms one point on the pump design curve and is  
 
indicative of overall performance. Such inservice tests  
 
confirm component OPERABILITY, trend performance, and detect  
 
incipient failures by indicating abnormal performance.
Performance of inservice testing, discussed in Reference 2, at three month intervals satisfies this requirement.  
 
This SR is modified by a Note indicating that the SR should be deferred up to 24 hours until suitable test conditions  
 
are established. This deferral is required because there is  
 
an insufficient steam pressure to perform the test.  
 
SR 3.7.3.4  This SR ensures that AFW can be delivered to the appropriate steam generator, in the event of any accident or transient  
 
that generates an AFAS signal, by demonstrating that each  
 
automatic valve in the flow path actuates to its correct  
 
position on an actual or simulated actuation signal  
 
(verification of flow-modulating characteristics is not  
 
required). This SR is not required for valves that are  
 
locked, sealed, or otherwise secured in the required  
 
position under administrative controls. The Surveillance Frequency is controlled under the Surveillance Frequency Control Program.  
 
This SR is modified by a Note indicating that the SR should be deferred up to 24 hours until suitable test conditions  
 
have been established.  
 
SR 3.7.3.5  This SR ensures that the AFW pumps will start in the event of any accident or transient that generates an AFAS signal by demonstrating that each AFW pump starts automatically on an actual or simulated actuation signal. The Surveillance Frequency is controlled under the Surveillance Frequency Control Program.  
 
This SR is modified by a Note. The Note indicates that the SR should be deferred up to 24 hours until suitable test  
 
conditions are established.
AFW System B 3.7.3 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.7.3-9 Revision 55 SR 3.7.3.6  This SR ensures that the AFW system is capable of providing a minimum nominal flow to each flow leg. This ensures that  
 
the minimum required flow is capable of feeding each flow  
 
leg. The test may be performed on one flow leg at a time.
The SR is modified by a Note which states, the SR is not required to be performed for the AFW train with the turbine-
 
driven AFW pump until up to 24 hours after reaching 800 psig  
 
in the steam generators. The Note ensures that proper test  
 
conditions exist prior to performing the test using the  
 
turbine-driven AFW pumps. The Surveillance Frequency is controlled under the Surveillance Frequency Control Program.  
 
SR 3.7.3.7  This SR ensures that the AFW System is properly aligned by verifying the flow path to each steam generator prior to  
 
entering MODE 2 operation, after 30 days in MODEs 5 or 6.
 
OPERABILITY of AFW flow paths must be verified before  
 
sufficient core heat is generated that would require the  
 
operation of the AFW System during a subsequent shutdown.
 
The Frequency is reasonable, based on engineering judgment,  
 
and other administrative controls to ensure that flow paths  
 
remain OPERABLE. To further ensure AFW System alignment,  
 
the OPERABILITY of the flow paths is verified following  
 
extended outages to determine that no misalignment of valves  
 
has occurred. This SR ensures that the flow path from the  
 
CST to the steam generators is properly aligned. Minimum  
 
nominal flow to each flow leg is ensured by performance of SR 3.7.3.6.
REFERENCES 1. UFSAR, Section 10.3  2. ASME Code for Operation and Maintenance of Nuclear Power Plants  
 
CST B 3.7.4 B 3.7  PLANT SYSTEMS  
 
B 3.7.4  Condensate Storage Tank (CST)  
 
BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.7.4-1 Revision 41 BACKGROUND The CST provides a safety grade source of water to the steam generators for removing decay and sensible heat from the  
 
RCS. The CST provides a passive flow of water, by gravity,  
 
to the AFW System (LCO 3.7.3). The steam produced is released to the atmosphere by the MSSVs or the atmospheric dump valves. The AFW pumps operate with a continuous  
 
recirculation to the CST.  
 
The component required by this Specification is CST No. 12.  
The component required by this Specification is CST No. 12.  


When the MSIVs are open, the preferred means of heat removal is to discharge steam to the condenser by the non-safety grade path of the turbine bypass valves. The condensed steam is returned to the backup water supply (CST No. 11 and CST No. 21) by the condensate pump. This has the advantage of conserving condensate while minimizing releases to the environment.
When the MSIVs are open, the preferred means of heat removal is to discharge steam to the condenser by the non-safety  
Because the CST is a principal component in removing residual heat from the RCS, it is designed to withstand earthquakes and other natural phenomena. The CST is designed to Seismic Category I requirements to ensure availability of the feedwater supply. Feedwater is also available from an alternate source.
 
There is one CST (CST No. 12) shared by Units 1 and 2. A description of the CST is found in Reference 1, Sections 6.3.5.1 and 10.3.2. APPLICABLE The CST provides cooling water to remove decay heat and to SAFETY ANALYSES cool down the unit following all events except for the maximum hypothetical accident and the fuel handling accident in the accident analyses, discussed in Reference 1, Chapter 14. For anticipated operational occurrences and accidents which do not affect the OPERABILITY of the steam generators, the thermal analysis assumption is generally six hours at MODE 3, steaming through the ADVs and MSSVs followed by a cooldown to SDC entry conditions at the design cooldown rate. The dose analysis assumption is an eight hour cooldown to maximize Control Room and offsite doses.
grade path of the turbine bypass valves. The condensed  
CST B 3.7.4 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.7.4-2 Revision 41   The limiting event for the condensate volume is the large feedwater line break with a coincident loss of offsite power. Single failures that also affect this event include the following:  a. The failure of the diesel generator powering the motor-driven AFW pump to the unaffected steam generator (requiring additional steam to drive the remaining AFW pump turbine); and  b. The failure of the steam driven train (requiring a longer time for cooldown using only one motor-driven AFW pump).
 
These are not usually the limiting failures in terms of consequences for these events. The CST satisfies 10 CFR 50.36(c)(2)(ii), Criteria 2 and 3. LCO To satisfy accident analysis assumptions, CST No. 12 must contain sufficient cooling water for both units to ensure that sufficient water is available to maintain the RCS at MODE 3 for six hours following a reactor trip from 102% RATED THERMAL POWER, assuming a coincident loss of offsite power and the most adverse single failure. In doing this, it must retain sufficient water to ensure adequate net positive suction head for the AFW pumps during the cooldown while in MODE 3, as well as to account for any losses from the steam-driven AFW pump turbine, or before isolating AFW to a broken line. The CST usable volume required is  150,000 gallons per unit (300,000 gallons for both units) in the MODE of Applicability. The 300,000 gallons of water is enough to provide for decay heat removal and cooldown of both units.
steam is returned to the backup water supply (CST No. 11 and  
By adjusting the feedwater flow to the permissible cooldown rate, decay heat removal and cooldown of both units can be accomplished in six hours. The 300,000 gallons are also adequate to maintain the RCS in MODE 3 for six hours with steam discharge to atmosphere with concurrent and total loss of offsite power, or to remove decay heat from both units for more than ten hours after initiation of cooldown and still maintain normal no-load water level in the steam generators. The total water volume in the tank includes the CST B 3.7.4 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.7.4-3 Revision 41 usable volume and water not usable because of the tank discharge line location.
 
OPERABILITY of the CST is determined by maintaining the tank volume at or above the minimum required volume.
CST No. 21) by the condensate pump. This has the advantage  
APPLICABILITY In MODEs 1, 2, and 3, the CST is required to be OPERABLE.
 
In MODEs 4, 5 and 6, the CST is not required because the AFW System is not required. ACTIONS A.1 and A.2  If the CST is not OPERABLE, the OPERABILITY of the backup water supply (CST No. 11 for Unit 1 and CST No. 21 for Unit 2) must be verified by administrative means within 4 hours and once every 12 hours thereafter.
of conserving condensate while minimizing releases to the  
OPERABILITY of the backup feedwater supply must include verification that the manual valves in the flow paths from the backup supply to the AFW pumps are open, and availability of the required volume of water (150,000 gallons) in the backup supply. The CST must be returned to OPERABLE status within seven days, as the backup supply may be performing this function in addition to its normal functions. The four hour Completion Time is reasonable, based on operating experience, to verify the OPERABILITY of the backup water supply. Additionally, verifying the backup water supply every 12 hours is adequate to ensure the backup water supply continues to be available.
 
The seven day Completion Time is reasonable, based on an OPERABLE backup water supply being available, and the low probability of an event requiring the use of the water from the CST occurring during this period.
environment.  
If the CST volume is less than 300,000 gallons and greater than 150,000 gallons and both units are in the MODE of Applicability, only one unit must enter this condition provided the unit aligns to the OPERABLE backup water supply (CST No. 11 or CST No. 21).
 
CST B 3.7.4 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.7.4-4 Revision 55  B.1 and B.2  If the CST cannot be restored to OPERABLE status within the associated Completion Time, the affected unit(s) must be placed in a MODE in which the LCO does not apply. To achieve this status, the unit(s) must be placed in at least MODE 3 within 6 hours, and in MODE 4 within 12 hours. The allowed Completion Times are reasonable, based on operating experience, to reach the required unit conditions from full power conditions in an orderly manner and without challenging plant systems. SURVEILLANCE SR 3.7.4.1 REQUIREMENTS This SR verifies that the CST contains the required usable volume of cooling water.  (This volume  150,000 gallons per unit in the MODE of Applicability.)  The Surveillance Frequency is controlled under the Surveillance Frequency Control Program.
Because the CST is a principal component in removing residual heat from the RCS, it is designed to withstand  
Although the volume in the CST for each unit is required to be 150,000 gallons, the total combined volume for both units is 300,000 gallons. REFERENCES 1. UFSAR CC System B 3.7.5 B 3.7  PLANT SYSTEMS B 3.7.5  Component Cooling (CC) System BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.7.5-1 Revision 53 BACKGROUND The CC System provides a heat sink for the removal of process and operating heat from safety-related components during a DBA or transient. During normal operation, the CC System also provides this function for various nonessential components. The CC System serves as a barrier to the release of radioactive byproducts between potentially radioactive systems and the Saltwater (SW) System, and thus to the environment.
 
The CC System consists of two redundant loops that are always cross-connected. A loop consists of one of three redundant pumps, one of two redundant CC heat exchangers along with a common head tank, associated valves, piping, instrumentation, and controls. The third pump, which is an installed spare, can be powered from either electrical train. The redundant cooling capacity of this system, assuming single active failure, is consistent with the assumptions made in the accident analysis.
earthquakes and other natural phenomena. The CST is  
During normal operation one loop typically provides cooling water with a maximum CC heat exchanger outlet temperature of 95&deg;F (a range of 70&deg;F-95&deg;F is acceptable during normal operating conditions) with the redundant loop components in standby. If needed, the redundant loop components can be aligned to supplement the in service loop. While operating on SDC with one loop, the CC heat exchanger outlet temperature may rise to a maximum temperature of 120&deg;F. Additional information on the design and operation of the system, along with a list of the components served, is presented in Reference 1, Section 9.5.2.1. The principal safety-related function of the CC System is the removal of decay heat from the reactor via the SDC System heat exchanger. This may utilize the SDC heat exchanger, during a normal or post accident cooldown and shutdown, or the Containment Spray System during the recirculation phase following a loss of coolant accident (LOCA).
 
CC System B 3.7.5 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.7.5-2 Revision 53 APPLICABLE The design basis of the CC System is for it to support a  SAFETY ANALYSES 100% capacity Containment Cooling System (containment spray, containment coolers, or a combination) removing core decay heat 30 minutes after a design basis LOCA. This prevents the containment sump fluid from increasing in temperature during the recirculation phase following a LOCA, and provides a gradual reduction in the temperature of this fluid as it is supplied to the RCS by the safety injection pumps.
designed to Seismic Category I requirements to ensure  
The CC System is designed to perform its function with a single failure of any active component, assuming a loss of offsite power.
 
The CC System also functions to cool the unit from SDC entry conditions (Tcold < 300&deg;F) to Tcold < 140&deg;F during normal operations. The time required to cool from 300&deg;F to 140&deg;F is a function of the number of CC and SDC loops operating.
availability of the feedwater supply. Feedwater is also  
One CC loop is sufficient to remove decay heat during subsequent operations with Tcold < 140&deg;F. This assumes that a maximum inlet SW temperature occurs simultaneously with the maximum heat loads on the system. The CC System satisfies 10 CFR 50.36(c)(2)(ii), Criterion 3. LCO The CC loops are redundant of each other to the degree that each has separate controls and power supplies and the operation of one does not depend on the other. In the event of a DBA, one CC loop is required to provide the minimum heat removal capability assumed in the safety analysis for the systems to which it supplies cooling water. To ensure this requirement is met, two CC loops must be OPERABLE. At least one CC loop will operate assuming the worst single active failure occurs coincident with the loss of offsite power. Additionally, the containment cooling function will also operate assuming the worst case passive failure post- recirculation actuation signal (RAS).
 
A CC loop is considered OPERABLE when the following:  a. The associated pump and common head tank are OPERABLE; and CC System B 3.7.5 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.7.5-3 Revision 53  b. The associated piping, valves, heat exchanger and instrumentation and controls required to perform the safety-related function are OPERABLE.
available from an alternate source.  
The isolation of CC from other components or systems not required for safety may render those components or systems inoperable, but does not affect the OPERABILITY of the CC System. APPLICABILITY In MODEs 1, 2, 3, and 4, the CC System is a normally operating system that must be prepared to perform its post accident safety functions, primarily RCS heat removal by cooling the SDC heat exchanger.
 
In MODEs 5 and 6, the OPERABILITY requirements of the CC System are determined by the systems it supports. ACTIONS A.1  Required Action A.1 is modified by a Note indicating the requirement of entry into the applicable Conditions and Required Actions of LCO 3.4.6, for SDC made inoperable by CC. This is an exception to LCO 3.0.6 and ensures the proper actions are taken for these components.
There is one CST (CST No. 12) shared by Units 1 and 2. A description of the CST is found in Reference 1, Sections 6.3.5.1 and 10.3.2.
With one CC loop inoperable, action must be taken to restore OPERABLE status within 72 hours. In this Condition, the remaining OPERABLE CC loop is adequate to perform the heat removal function. The 72 hour Completion Time is based on the redundant capabilities afforded by the OPERABLE loop, and the low probability of a DBA occurring during this period.
APPLICABLE The CST provides cooling water to remove decay heat and to SAFETY ANALYSES cool down the unit following all events except for the maximum hypothetical accident and the fuel handling accident in the accident analyses, discussed in Reference 1, Chapter 14. For anticipated operational occurrences and  
B.1 and B.2  If the CC loop cannot be restored to OPERABLE status within the associated Completion Time, the unit must be placed in a MODE in which the LCO does not apply. To achieve this status, the unit must be placed in at least MODE 3 within 6 hours and in MODE 5 within 36 hours.
 
The allowed Completion Times are reasonable, based on operating experience, to reach the required unit conditions CC System B 3.7.5 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.7.5-4 Revision 55  from full power conditions in an orderly manner and without challenging unit systems. SURVEILLANCE SR 3.7.5.1 REQUIREMENTS Verifying the correct alignment for manual, power operated, and automatic valves in the CC flow path provides assurance that the proper flow paths exist for CC operation. This SR does not apply to valves that are locked, sealed, or otherwise secured in position, since these valves are verified to be in the correct position prior to locking, sealing, or securing. This SR also does not apply to valves that cannot be inadvertently misaligned, such as check valves. This SR does not require any testing or valve manipulation; rather, it involves verification that those valves capable of potentially being mispositioned are in their correct position.
accidents which do not affect the OPERABILITY of the steam  
This SR is modified by a Note indicating that the isolation of the CC components or systems may render those components inoperable but does not affect the OPERABILITY of the CC System.
 
The Surveillance Frequency is controlled under the Surveillance Frequency Control Program.
generators, the thermal analysis assumption is generally six hours at MODE 3, steaming through the ADVs and MSSVs followed by a cooldown to SDC entry conditions at the design  
SR 3.7.5.2  This SR verifies proper automatic operation of the CC valves on an actual or simulated safety injection actuation signal (SIAS). The CC System is a normally operating system that cannot be fully actuated as part of routine testing during normal operation. This SR is not required for valves that are locked, sealed, or otherwise secured in the required position under administrative controls. The Surveillance Frequency is controlled under the Surveillance Frequency Control Program.
 
SR 3.7.5.3  This SR verifies proper automatic operation of the CC pumps on an actual or simulated SIAS. The CC System is a normally operating system that cannot be fully actuated as part of routine testing during normal operation. The Surveillance CC System B 3.7.5 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.7.5-5 Revision 55 Frequency is controlled under the Surveillance Frequency Control Program. REFERENCES 1. UFSAR SRW System B 3.7.6 B 3.7  PLANT SYSTEMS B 3.7.6  Service Water (SRW) System BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.7.6-1 Revision 5 BACKGROUND The SRW System provides a heat sink for the removal of process and operating heat from safety-related components during a DBA or transient. During normal operation or a normal shutdown, the SRW System also provides this function for various safety-related and non-safety-related components. The safety-related function is covered by this LCO.
cooldown rate. The dose analysis assumption is an eight hour cooldown to maximize Control Room and offsite doses.
The SRW System consists of two separate, 100% capacity safety-related cooling water subsystems. Each subsystem consists of a 100% capacity pump, head tank, two SRW heat exchangers, piping, valves, and instrumentation. A third pump, which is an installed spare, can be powered from either electrical train. The pumps and valves are remote manually aligned, except in the unlikely event of a LOCA.
CST B 3.7.4 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.7.4-2 Revision 41 The limiting event for the condensate volume is the large feedwater line break with a coincident loss of offsite  
The pumps are automatically started upon receipt of a SIAS and all essential valves are aligned to their post-accident positions.
 
During normal operation, both subsystems are required, and are independent to the degree necessary to assure the safe operation and shutdown of the plant-assuming a single failure. During shutdown, operation of the SRW System is the same as normal operation, except that the heat loads are reduced. Additional information about the design and operation of the SRW System, along with a list of the components served, is presented in Reference 1, Section 9.5.2.2. In the event of a LOCA, the SRW System automatically realigns to isolate Turbine Building (non-safety-related) loads creating two independent and redundant safety-related subsystems. Service water flow to the spent fuel pool (SFP) cooler and the blowdown heat exchanger is automatically isolated as required for the DBA. Each SRW subsystem will supply cooling water to a diesel generator and two containment air coolers. However, the No. 11 SRW subsystem only supplies two containment air coolers since the No. 1A Diesel Generator is air cooled. Each SRW subsystem is sufficiently sized to remove the maximum amount of heat from the containment atmosphere while maintaining SRW System B 3.7.6 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.7.6-2 Revision 41  the SRW supply temperature to the diesel generator below its design limit. APPLICABLE The design basis of the SRW System is for it to support a SAFETY ANALYSES 100% capacity containment cooling system (containment coolers) and to remove core decay heat 30 minutes following a design basis LOCA, as discussed in Reference 1, Section 14.20. This prevents the containment sump fluid from increasing in temperature during the recirculation phase following a LOCA and provides for a gradual reduction in the temperature of this fluid as it is supplied to the RCS by the safety injection pumps. The SRW System is designed to perform its function with a single failure of any active component, assuming the loss of offsite power.
power. Single failures that also affect this event include  
The SRW System satisfies 10 CFR 50.36(c)(2)(ii), Criterion 3. LCO Two SRW subsystems are required to be OPERABLE to provide the required redundancy to ensure that the system functions to remove post-accident heat loads, assuming the worst single active failure occurs coincident with the loss of offsite power. Additionally, this system will also operate assuming that worst case passive failure post-RAS. An SRW subsystem is considered OPERABLE when:  a. The associated pump and head tank are OPERABLE; and  
 
: b. The associated piping, valves, heat exchanger, and instrumentation and controls required to perform the safety-related function are OPERABLE. APPLICABILITY In MODEs 1, 2, 3, and 4, the SRW System is a normally operating system, which is required to support the OPERABILITY of the equipment serviced by the SRW System and required to be OPERABLE in these MODEs.
the following:  a. The failure of the diesel generator powering the motor-driven AFW pump to the unaffected steam generator  
In MODEs 5 and 6, the OPERABILITY requirements of the SRW System are determined by the systems it supports.
 
SRW System B 3.7.6 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.7.6-3 Revision 5 ACTIONS A.1 and A.2  With one SRW heat exchanger inoperable, action must be taken to restore operable status within 7 days. Isolating flow to one associated containment cooling unit will reduce the DBA heat load of the affected SRW subsystem to within the capacity of one SRW heat exchanger, thus ensuring that the SRW temperatures can be maintained within their design limits. This will allow the associated diesel generator (except for 11 SRW which does not cool a diesel generator) to remain operable. In this Condition, the other OPERABLE SRW System is adequate to perform the containment heat removal function. However, the overall reliability is reduced because a single failure in the SRW System could result in loss of SRW containment heat removal function. Required Action A.1 is modified by a Note. The Note indicates that the applicable Conditions of LCO 3.6.6 should be entered for an inoperable containment cooling train. The 7 day Completion Time is based on the redundant capabilities afforded by the OPERABLE subsystem, the Completion Time associated with an inoperable containment cooling unit (3.6.6), and the low probability of a DBA occurring during this time period. B.1  With one SRW subsystem inoperable, action must be taken to restore OPERABLE status within 72 hours. In this Condition, the remaining OPERABLE SRW System is adequate to perform the heat removal function. However, the overall reliability is reduced because a single failure in the SRW System could result in loss of SRW function. Required Action B.1 is modified by a Note. The Note indicates that the applicable Conditions of LCO 3.8.1, should be entered if the inoperable SRW subsystem results in an inoperable diesel generator.
(requiring additional steam to drive the remaining AFW  
The 72 hour Completion Time is based on the redundant capabilities afforded by the OPERABLE subsystem, and the low probability of a DBA occurring during this time period.
 
C.1 and C.2  If the SRW subsystem cannot be restored to OPERABLE status within the associated Completion Time, the unit must be placed in a MODE in which the LCO does not apply. To SRW System B 3.7.6 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.7.6-4 Revision 55  achieve this status, the unit must be placed in at least MODE 3 within 6 hours and in MODE 5 within 36 hours.
pump turbine); and  b. The failure of the steam driven train (requiring a longer time for cooldown using only one motor-driven AFW pump).  
The allowed Completion Times are reasonable, based on operating experience, to reach the required unit conditions from full power conditions in an orderly manner and without challenging unit systems. SURVEILLANCE SR 3.7.6.1 REQUIREMENTS Verifying the correct alignment for manual, power-operated, and automatic valves in the SRW flow path ensures that the proper flow paths exist for SRW operation. This SR does not apply to valves that are locked, sealed, or otherwise secured in position, since they are verified to be in the correct position prior to locking, sealing, or securing.
 
This SR also does not apply to valves that cannot be inadvertently misaligned, such as check valves. This SR does not require any testing or valve manipulation; rather, it involves verification that those valves capable of potentially being mispositioned are in the correct position.
These are not usually the limiting failures in terms of consequences for these events.
This SR is modified by a Note indicating that the isolation of the SRW components or systems may render those components inoperable but does not affect the OPERABILITY of the SRW System.
The CST satisfies 10 CFR 50.36(c)(2)(ii), Criteria 2 and 3.
The Surveillance Frequency is controlled under the Surveillance Frequency Control Program.
LCO To satisfy accident analysis assumptions, CST No. 12 must contain sufficient cooling water for both units to ensure  
SR 3.7.6.2  This SR verifies proper automatic operation of the SRW System valves on an actual or simulated actuation signal (SIAS or CSAS). The SRW System is a normally operating system that cannot be fully actuated as part of normal testing. This surveillance test is not required for valves that are locked, sealed, or otherwise secured in the required position under administrative controls. The Surveillance Frequency is controlled under the Surveillance Frequency Control Program.
 
SRW System B 3.7.6 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.7.6-5 Revision 55  SR 3.7.6.3  The SR verifies proper automatic operation of the SRW System pumps on an actual or simulated actuation signal (SIAS or CSAS). The SRW System is a normally operating system that cannot be fully actuated as part of the normal testing during normal operation. The Surveillance Frequency is controlled under the Surveillance Frequency Control Program.
that sufficient water is available to maintain the RCS at  
REFERENCES 1. UFSAR SW System B 3.7.7 B 3.7  PLANT SYSTEMS B 3.7.7  Saltwater (SW) System BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.7.7-1 Revision 5 BACKGROUND The SW System provides a heat sink for the removal of process and operating heat from safety-related components during a DBA or transient. During normal operation or a normal shutdown, the SW System also provides this function for various safety-related and non-safety-related components. The safety-related function is covered by this LCO.
 
The SW System consists of two subsystems. Each subsystem contains one pump. A third pump, which is an installed spare, can be aligned to either subsystem. The safety-related function of each subsystem is to provide SW to two SRW heat exchangers, a CC heat exchanger, and an Emergency Core Cooling System (ECCS) pump room air cooler in order to transfer heat from these systems to the bay. Seal water for the non-safety-related circulating water pumps is supplied by both or either subsystems. The SW pumps provide the driving head to move SW from the intake structure, through the system and back to the circulating water discharge conduits. The system is designed such that each pump has sufficient head and capacity to provide cooling water such that 100% of the required heat load can be removed by either subsystem.
MODE 3 for six hours following a reactor trip from  
During normal operation, both subsystems in each unit are in operation with one pump running on each header and a third pump in standby. If needed, the standby pumps can be lined-up to either supply header. The SW flow through the SRW and CC heat exchangers is throttled to provide sufficient cooling to the heat exchangers, while maintaining total subsystem flow below a maximum value. Additional information about the design and operation of the SW System, along with a list of the components served, is presented in Reference 1. During an accident, the SW System is required to remove the heat load from the SRW and ECCS pump room, and from the CC following an RAS.
 
SW System B 3.7.7 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.7.7-2 Revision 12 APPLICABLE The most limiting event for the SW System is a LOCA. SAFETY ANALYSES Operation of the SW System following a LOCA is separated into two phases, before the RAS and after the RAS. One subsystem can satisfy cooling requirements of both phases.
102% RATED THERMAL POWER, assuming a coincident loss of  
After a LOCA but before an RAS, each subsystem will cool two SRW heat exchangers and an ECCS pump room air cooler (as required). There is no required flow to the CC heat exchangers. When an RAS occurs, flow is throttled to the CC heat exchanger. Flow to each SRW heat exchanger is reduced while the system remains capable of providing the required flow to the ECCS pump room air coolers. The SW System satisfies 10 CFR 50.36(c)(2)(ii), Criterion 3. LCO Two SW subsystems are required to be OPERABLE to provide the required redundancy to ensure that the system functions to remove post-accident heat loads, assuming the worst single active failure occurs coincident with the loss of offsite power. Additionally, this system will also operate assuming the worst case passive failure post-RAS.
 
offsite power and the most adverse single failure. In doing  
 
this, it must retain sufficient water to ensure adequate net  
 
positive suction head for the AFW pumps during the cooldown  
 
while in MODE 3, as well as to account for any losses from  
 
the steam-driven AFW pump turbine, or before isolating AFW  
 
to a broken line.
The CST usable volume required is  150,000 gallons per unit (300,000 gallons for both units) in the MODE of  
 
Applicability. The 300,000 gallons of water is enough to  
 
provide for decay heat removal and cooldown of both units.
 
By adjusting the feedwater flow to the permissible cooldown rate, decay heat removal and cooldown of both units can be accomplished in six hours. The 300,000 gallons are also  
 
adequate to maintain the RCS in MODE 3 for six hours with  
 
steam discharge to atmosphere with concurrent and total loss  
 
of offsite power, or to remove decay heat from both units  
 
for more than ten hours after initiation of cooldown and  
 
still maintain normal no-load water level in the steam  
 
generators. The total water volume in the tank includes the CST B 3.7.4 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.7.4-3 Revision 41 usable volume and water not usable because of the tank discharge line location.  
 
OPERABILITY of the CST is determined by maintaining the tank volume at or above the minimum required volume.  
 
APPLICABILITY In MODEs 1, 2, and 3, the CST is required to be OPERABLE.  
 
In MODEs 4, 5 and 6, the CST is not required because the AFW System is not required.
ACTIONS A.1 and A.2  If the CST is not OPERABLE, the OPERABILITY of the backup water supply (CST No. 11 for Unit 1 and CST No. 21 for  
 
Unit 2) must be verified by administrative means within  
 
4 hours and once every 12 hours thereafter.  
 
OPERABILITY of the backup feedwater supply must include verification that the manual valves in the flow paths from  
 
the backup supply to the AFW pumps are open, and  
 
availability of the required volume of water  
 
(150,000 gallons) in the backup supply. The CST must be  
 
returned to OPERABLE status within seven days, as the backup  
 
supply may be performing this function in addition to its  
 
normal functions. The four hour Completion Time is  
 
reasonable, based on operating experience, to verify the  
 
OPERABILITY of the backup water supply. Additionally,  
 
verifying the backup water supply every 12 hours is adequate  
 
to ensure the backup water supply continues to be available.
 
The seven day Completion Time is reasonable, based on an OPERABLE backup water supply being available, and the low probability of an event requiring the use of the water from  
 
the CST occurring during this period.  
 
If the CST volume is less than 300,000 gallons and greater than 150,000 gallons and both units are in the MODE of  
 
Applicability, only one unit must enter this condition  
 
provided the unit aligns to the OPERABLE backup water supply  
 
(CST No. 11 or CST No. 21).  
 
CST B 3.7.4 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.7.4-4 Revision 55  B.1 and B.2  If the CST cannot be restored to OPERABLE status within the associated Completion Time, the affected unit(s) must be  
 
placed in a MODE in which the LCO does not apply. To  
 
achieve this status, the unit(s) must be placed in at least  
 
MODE 3 within 6 hours, and in MODE 4 within 12 hours. The  
 
allowed Completion Times are reasonable, based on operating  
 
experience, to reach the required unit conditions from full  
 
power conditions in an orderly manner and without challenging plant systems.
SURVEILLANCE SR 3.7.4.1 REQUIREMENTS This SR verifies that the CST contains the required usable volume of cooling water.  (This volume  150,000 gallons per unit in the MODE of Applicability.)  The Surveillance Frequency is controlled under the Surveillance Frequency Control Program.  
 
Although the volume in the CST for each unit is required to be 150,000 gallons, the total combined volume for both units is 300,000 gallons.
REFERENCES 1. UFSAR  
 
CC System B 3.7.5 B 3.7  PLANT SYSTEMS  
 
B 3.7.5  Component Cooling (CC) System  
 
BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.7.5-1 Revision 53 BACKGROUND The CC System provides a heat sink for the removal of process and operating heat from safety-related components  
 
during a DBA or transient. During normal operation, the CC  
 
System also provides this function for various nonessential components. The CC System serves as a barrier to the release of radioactive byproducts between potentially  
 
radioactive systems and the Saltwater (SW) System, and thus  
 
to the environment.  
 
The CC System consists of two redundant loops that are always cross-connected. A loop consists of one of three  
 
redundant pumps, one of two redundant CC heat exchangers  
 
along with a common head tank, associated valves, piping,  
 
instrumentation, and controls. The third pump, which is an  
 
installed spare, can be powered from either electrical  
 
train. The redundant cooling capacity of this system,  
 
assuming single active failure, is consistent with the  
 
assumptions made in the accident analysis.  
 
During normal operation one loop typically provides cooling water with a maximum CC heat exchanger outlet temperature of 95&deg;F (a range of 70
&deg;F-95&deg;F is acceptable during normal operating conditions) with the redundant loop components in  
 
standby. If needed, the redundant loop components can be  
 
aligned to supplement the in service loop. While operating  
 
on SDC with one loop, the CC heat exchanger outlet temperature may rise to a maximum temperature of 120
&deg;F. Additional information on the design and operation of the system, along with a list of the components served, is  
 
presented in Reference 1, Section 9.5.2.1. The principal  
 
safety-related function of the CC System is the removal of  
 
decay heat from the reactor via the SDC System heat exchanger. This may utilize the SDC heat exchanger, during a normal or post accident cooldown and shutdown, or the  
 
Containment Spray System during the recirculation phase following a loss of coolant accident (LOCA).  
 
CC System B 3.7.5 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.7.5-2 Revision 53 APPLICABLE The design basis of the CC System is for it to support a  SAFETY ANALYSES 100% capacity Containment Cooling System (containment spray, containment coolers, or a combination) removing core decay  
 
heat 30 minutes after a design basis LOCA. This prevents  
 
the containment sump fluid from increasing in temperature  
 
during the recirculation phase following a LOCA, and provides a gradual reduction in the temperature of this fluid as it is supplied to the RCS by the safety injection  
 
pumps.
The CC System is designed to perform its function with a single failure of any active component, assuming a loss of  
 
offsite power.  
 
The CC System also functions to cool the unit from SDC entry conditions (Tcold < 300&deg;F) to Tcold < 140&deg;F during normal operations. The time required to cool from 300&deg;F to 140&deg;F  
 
is a function of the number of CC and SDC loops operating.
 
One CC loop is sufficient to remove decay heat during  
 
subsequent operations with Tcold < 140&deg;F. This assumes that a maximum inlet SW temperature occurs simultaneously with  
 
the maximum heat loads on the system.
The CC System satisfies 10 CFR 50.36(c)(2)(ii), Criterion 3.
LCO The CC loops are redundant of each other to the degree that each has separate controls and power supplies and the  
 
operation of one does not depend on the other. In the event  
 
of a DBA, one CC loop is required to provide the minimum  
 
heat removal capability assumed in the safety analysis for the systems to which it supplies cooling water. To ensure this requirement is met, two CC loops must be OPERABLE. At  
 
least one CC loop will operate assuming the worst single  
 
active failure occurs coincident with the loss of offsite  
 
power. Additionally, the containment cooling function will  
 
also operate assuming the worst case passive failure post-recirculation actuation signal (RAS).  
 
A CC loop is considered OPERABLE when the following:  a. The associated pump and common head tank are OPERABLE; and CC System B 3.7.5 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.7.5-3 Revision 53  b. The associated piping, valves, heat exchanger and instrumentation and controls required to perform the  
 
safety-related function are OPERABLE.  
 
The isolation of CC from other components or systems not required for safety may render those components or systems inoperable, but does not affect the OPERABILITY of the CC  
 
System. APPLICABILITY In MODEs 1, 2, 3, and 4, the CC System is a normally operating system that must be prepared to perform its post  
 
accident safety functions, primarily RCS heat removal by  
 
cooling the SDC heat exchanger.  
 
In MODEs 5 and 6, the OPERABILITY requirements of the CC System are determined by the systems it supports.
ACTIONS A.1  Required Action A.1 is modified by a Note indicating the requirement of entry into the applicable Conditions and  
 
Required Actions of LCO 3.4.6, for SDC made inoperable by  
 
CC. This is an exception to LCO 3.0.6 and ensures the  
 
proper actions are taken for these components.  
 
With one CC loop inoperable, action must be taken to restore OPERABLE status within 72 hours. In this Condition, the remaining OPERABLE CC loop is adequate to perform the heat  
 
removal function. The 72 hour Completion Time is based on  
 
the redundant capabilities afforded by the OPERABLE loop,  
 
and the low probability of a DBA occurring during this  
 
period.
B.1 and B.2  If the CC loop cannot be restored to OPERABLE status within the associated Completion Time, the unit must be placed in a  
 
MODE in which the LCO does not apply. To achieve this  
 
status, the unit must be placed in at least MODE 3 within  
 
6 hours and in MODE 5 within 36 hours.  
 
The allowed Completion Times are reasonable, based on operating experience, to reach the required unit conditions CC System B 3.7.5 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.7.5-4 Revision 55  from full power conditions in an orderly manner and without challenging unit systems.
SURVEILLANCE SR 3.7.5.1 REQUIREMENTS Verifying the correct alignment for manual, power operated, and automatic valves in the CC flow path provides assurance  
 
that the proper flow paths exist for CC operation. This SR  
 
does not apply to valves that are locked, sealed, or  
 
otherwise secured in position, since these valves are  
 
verified to be in the correct position prior to locking,  
 
sealing, or securing. This SR also does not apply to valves  
 
that cannot be inadvertently misaligned, such as check  
 
valves. This SR does not require any testing or valve  
 
manipulation; rather, it involves verification that those  
 
valves capable of potentially being mispositioned are in  
 
their correct position.  
 
This SR is modified by a Note indicating that the isolation of the CC components or systems may render those components  
 
inoperable but does not affect the OPERABILITY of the CC  
 
System.
The Surveillance Frequency is controlled under the Surveillance Frequency Control Program.  
 
SR 3.7.5.2  This SR verifies proper automatic operation of the CC valves on an actual or simulated safety injection actuation signal  
 
(SIAS). The CC System is a normally operating system that cannot be fully actuated as part of routine testing during normal operation. This SR is not required for valves that  
 
are locked, sealed, or otherwise secured in the required  
 
position under administrative controls. The Surveillance Frequency is controlled under the Surveillance Frequency Control Program.  
 
SR 3.7.5.3  This SR verifies proper automatic operation of the CC pumps on an actual or simulated SIAS. The CC System is a normally  
 
operating system that cannot be fully actuated as part of  
 
routine testing during normal operation. The Surveillance CC System B 3.7.5 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.7.5-5 Revision 55 Frequency is controlled under the Surveillance Frequency Control Program.
REFERENCES 1. UFSAR  
 
SRW System B 3.7.6 B 3.7  PLANT SYSTEMS  
 
B 3.7.6  Service Water (SRW) System  
 
BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.7.6-1 Revision 5 BACKGROUND The SRW System provides a heat sink for the removal of process and operating heat from safety-related components  
 
during a DBA or transient. During normal operation or a  
 
normal shutdown, the SRW System also provides this function for various safety-related and non-safety-related components. The safety-related function is covered by this  
 
LCO.
The SRW System consists of two separate, 100% capacity safety-related cooling water subsystems. Each subsystem  
 
consists of a 100% capacity pump, head tank, two SRW heat exchangers, piping, valves, and instrumentation. A third pump, which is an installed spare, can be powered from  
 
either electrical train. The pumps and valves are remote  
 
manually aligned, except in the unlikely event of a LOCA.
 
The pumps are automatically started upon receipt of a SIAS  
 
and all essential valves are aligned to their post-accident  
 
positions.  
 
During normal operation, both subsystems are required, and are independent to the degree necessary to assure the safe  
 
operation and shutdown of the plant-assuming a single  
 
failure. During shutdown, operation of the SRW System is the same as normal operation, except that the heat loads are  
 
reduced. Additional information about the design and operation of the SRW System, along with a list of the  
 
components served, is presented in Reference 1,  
 
Section 9.5.2.2. In the event of a LOCA, the SRW System  
 
automatically realigns to isolate Turbine Building (non-
 
safety-related) loads creating two independent and redundant  
 
safety-related subsystems. Service water flow to the spent  
 
fuel pool (SFP) cooler and the blowdown heat exchanger is automatically isolated as required for the DBA. Each SRW subsystem will supply cooling water to a diesel generator  
 
and two containment air coolers. However, the No. 11 SRW  
 
subsystem only supplies two containment air coolers since  
 
the No. 1A Diesel Generator is air cooled. Each SRW  
 
subsystem is sufficiently sized to remove the maximum amount  
 
of heat from the containment atmosphere while maintaining SRW System B 3.7.6 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.7.6-2 Revision 41  the SRW supply temperature to the diesel generator below its design limit.
APPLICABLE The design basis of the SRW System is for it to support a SAFETY ANALYSES 100% capacity containment cooling system (containment coolers) and to remove core decay heat 30 minutes following a design basis LOCA, as discussed in Reference 1,  
 
Section 14.20. This prevents the containment sump fluid  
 
from increasing in temperature during the recirculation  
 
phase following a LOCA and provides for a gradual reduction  
 
in the temperature of this fluid as it is supplied to the  
 
RCS by the safety injection pumps. The SRW System is  
 
designed to perform its function with a single failure of  
 
any active component, assuming the loss of offsite power.  
 
The SRW System satisfies 10 CFR 50.36(c)(2)(ii),
Criterion 3.
LCO Two SRW subsystems are required to be OPERABLE to provide the required redundancy to ensure that the system functions  
 
to remove post-accident heat loads, assuming the worst  
 
single active failure occurs coincident with the loss of  
 
offsite power. Additionally, this system will also operate  
 
assuming that worst case passive failure post-RAS.
An SRW subsystem is considered OPERABLE when:  a. The associated pump and head tank are OPERABLE; and  
: b. The associated piping, valves, heat exchanger, and instrumentation and controls required to perform the safety-related function are OPERABLE.
APPLICABILITY In MODEs 1, 2, 3, and 4, the SRW System is a normally operating system, which is required to support the  
 
OPERABILITY of the equipment serviced by the SRW System and  
 
required to be OPERABLE in these MODEs.  
 
In MODEs 5 and 6, the OPERABILITY requirements of the SRW System are determined by the systems it supports.  
 
SRW System B 3.7.6 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.7.6-3 Revision 5 ACTIONS A.1 and A.2  With one SRW heat exchanger inoperable, action must be taken to restore operable status within 7 days. Isolating flow to one associated containment cooling unit will reduce the DBA heat load of the affected SRW subsystem to within the capacity of one SRW heat exchanger, thus ensuring that the SRW temperatures can be maintained within their design limits. This will allow the associated diesel generator (except for 11 SRW which does not cool a diesel generator) to remain operable. In this Condition, the other OPERABLE SRW System is adequate to perform the containment heat removal function. However, the overall reliability is reduced because a single failure in the SRW System could result in loss of SRW containment heat removal function.
Required Action A.1 is modified by a Note. The Note indicates that the applicable Conditions of LCO 3.6.6 should be entered for an inoperable containment cooling train. The 7 day Completion Time is based on the redundant capabilities afforded by the OPERABLE subsystem, the Completion Time associated with an inoperable containment cooling unit (3.6.6), and the low probability of a DBA occurring during this time period. B.1  With one SRW subsystem inoperable, action must be taken to restore OPERABLE status within 72 hours. In this Condition,  
 
the remaining OPERABLE SRW System is adequate to perform the  
 
heat removal function. However, the overall reliability is  
 
reduced because a single failure in the SRW System could  
 
result in loss of SRW function. Required Action B.1 is modified by a Note. The Note indicates that the applicable  
 
Conditions of LCO 3.8.1, should be entered if the inoperable  
 
SRW subsystem results in an inoperable diesel generator.
 
The 72 hour Completion Time is based on the redundant  
 
capabilities afforded by the OPERABLE subsystem, and the low probability of a DBA occurring during this time period.  
 
C.1 and C.2  If the SRW subsystem cannot be restored to OPERABLE status within the associated Completion Time, the unit must be  
 
placed in a MODE in which the LCO does not apply. To SRW System B 3.7.6 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.7.6-4 Revision 55  achieve this status, the unit must be placed in at least MODE 3 within 6 hours and in MODE 5 within 36 hours.  
 
The allowed Completion Times are reasonable, based on operating experience, to reach the required unit conditions  
 
from full power conditions in an orderly manner and without challenging unit systems.
SURVEILLANCE SR 3.7.6.1 REQUIREMENTS Verifying the correct alignment for manual, power-operated, and automatic valves in the SRW flow path ensures that the  
 
proper flow paths exist for SRW operation. This SR does not  
 
apply to valves that are locked, sealed, or otherwise  
 
secured in position, since they are verified to be in the  
 
correct position prior to locking, sealing, or securing.
 
This SR also does not apply to valves that cannot be  
 
inadvertently misaligned, such as check valves. This SR  
 
does not require any testing or valve manipulation; rather,  
 
it involves verification that those valves capable of  
 
potentially being mispositioned are in the correct position.
 
This SR is modified by a Note indicating that the isolation  
 
of the SRW components or systems may render those components  
 
inoperable but does not affect the OPERABILITY of the SRW  
 
System.
The Surveillance Frequency is controlled under the Surveillance Frequency Control Program.  
 
SR 3.7.6.2  This SR verifies proper automatic operation of the SRW System valves on an actual or simulated actuation signal  
 
(SIAS or CSAS). The SRW System is a normally operating  
 
system that cannot be fully actuated as part of normal  
 
testing. This surveillance test is not required for valves  
 
that are locked, sealed, or otherwise secured in the  
 
required position under administrative controls. The Surveillance Frequency is controlled under the Surveillance Frequency Control Program.  
 
SRW System B 3.7.6 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.7.6-5 Revision 55  SR 3.7.6.3  The SR verifies proper automatic operation of the SRW System pumps on an actual or simulated actuation signal (SIAS or  
 
CSAS). The SRW System is a normally operating system that  
 
cannot be fully actuated as part of the normal testing  
 
during normal operation. The Surveillance Frequency is controlled under the Surveillance Frequency Control Program.  
 
REFERENCES 1. UFSAR  
 
SW System B 3.7.7 B 3.7  PLANT SYSTEMS  
 
B 3.7.7  Saltwater (SW) System  
 
BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.7.7-1 Revision 5 BACKGROUND The SW System provides a heat sink for the removal of process and operating heat from safety-related components  
 
during a DBA or transient. During normal operation or a  
 
normal shutdown, the SW System also provides this function for various safety-related and non-safety-related components. The safety-related function is covered by this  
 
LCO.
The SW System consists of two subsystems. Each subsystem contains one pump. A third pump, which is an installed  
 
spare, can be aligned to either subsystem. The safety-
 
related function of each subsystem is to provide SW to two SRW heat exchangers, a CC heat exchanger, and an Emergency Core Cooling System (ECCS) pump room air cooler in order to  
 
transfer heat from these systems to the bay. Seal water for  
 
the non-safety-related circulating water pumps is supplied  
 
by both or either subsystems. The SW pumps provide the  
 
driving head to move SW from the intake structure, through  
 
the system and back to the circulating water discharge  
 
conduits. The system is designed such that each pump has  
 
sufficient head and capacity to provide cooling water such  
 
that 100% of the required heat load can be removed by either  
 
subsystem.  
 
During normal operation, both subsystems in each unit are in operation with one pump running on each header and a third  
 
pump in standby. If needed, the standby pumps can be lined-
 
up to either supply header. The SW flow through the SRW and  
 
CC heat exchangers is throttled to provide sufficient  
 
cooling to the heat exchangers, while maintaining total  
 
subsystem flow below a maximum value.
Additional information about the design and operation of the SW System, along with a list of the components served, is  
 
presented in Reference 1. During an accident, the SW System  
 
is required to remove the heat load from the SRW and ECCS pump room, and from the CC following an RAS.  
 
SW System B 3.7.7 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.7.7-2 Revision 12 APPLICABLE The most limiting event for the SW System is a LOCA. SAFETY ANALYSES Operation of the SW System following a LOCA is separated into two phases, before the RAS and after the RAS. One  
 
subsystem can satisfy cooling requirements of both phases.
 
After a LOCA but before an RAS, each subsystem will cool two  
 
SRW heat exchangers and an ECCS pump room air cooler (as required). There is no required flow to the CC heat exchangers. When an RAS occurs, flow is throttled to the CC heat exchanger. Flow to each SRW heat exchanger is reduced while the system remains capable of providing the required  
 
flow to the ECCS pump room air coolers.
The SW System satisfies 10 CFR 50.36(c)(2)(ii), Criterion 3.
LCO Two SW subsystems are required to be OPERABLE to provide the required redundancy to ensure that the system functions to  
 
remove post-accident heat loads, assuming the worst single  
 
active failure occurs coincident with the loss of offsite  
 
power. Additionally, this system will also operate assuming  
 
the worst case passive failure post-RAS.  
 
An SW subsystem is considered OPERABLE when:  a. The associated pump is OPERABLE; and  
An SW subsystem is considered OPERABLE when:  a. The associated pump is OPERABLE; and  
: b. The associated piping, valves, heat exchangers, and instrumentation and controls required to perform the safety-related function are OPERABLE. APPLICABILITY In MODEs 1, 2, 3, and 4, the SW System is a normally operating system, which is required to support the OPERABILITY of the equipment serviced by the SW System and required to be OPERABLE in these MODEs.
: b. The associated piping, valves, heat exchangers, and instrumentation and controls required to perform the safety-related function are OPERABLE.
In MODEs 5 and 6, the OPERABILITY requirements of the SW System are determined by the systems it supports. ACTIONS A.1  With one SW subsystem inoperable, action must be taken to restore OPERABLE status within 72 hours. In this Condition, the remaining OPERABLE SW subsystem is adequate to perform the heat removal function. However, the overall reliability is reduced because a single failure in the SW subsystem SW System B 3.7.7 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.7.7-3 Revision 2  could result in loss of SW System function. Required Action A.1 is modified by two Notes. The first Note indicates that the applicable Conditions of LCO 3.8.1 should be entered if the inoperable SW subsystem results in an inoperable emergency diesel generator. The second Note indicates that the applicable Conditions and Required Actions of LCO 3.4.6 should be entered if an inoperable SW subsystem results in an inoperable SDC. The 72 hour Completion Time is based on the redundant capabilities afforded by the OPERABLE train, and the low probability of a DBA occurring during this time period.
APPLICABILITY In MODEs 1, 2, 3, and 4, the SW System is a normally operating system, which is required to support the  
B.1 and B.2  If the SW subsystems cannot be restored to OPERABLE status within the associated Completion Time, the unit must be placed in a MODE in which the LCO does not apply. To achieve this status, the unit must be placed in at least MODE 3 within 6 hours, and in MODE 5 within 36 hours.
 
The allowed Completion Times are reasonable, based on operating experience, to reach the required unit conditions from full power conditions in an orderly manner and without challenging unit systems. SURVEILLANCE SR 3.7.7.1 REQUIREMENTS Verifying the correct alignment for manual, power-operated, and automatic valves in the SW System flow path ensures that the proper flow paths exist for SW System operation. This SR does not apply to valves that are locked, sealed, or otherwise secured in position, since they are verified to be in the correct position prior to locking, sealing, or securing. This SR also does not apply to valves that cannot be inadvertently misaligned, such as check valves. This surveillance test does not require any testing or valve manipulation; rather, it involves verification that those valves capable of potentially being mispositioned are in the correct position. This SR is modified by a Note indicating that the isolation of the SW System components or systems may render those components inoperable but does not affect the OPERABILITY of the SW System.
OPERABILITY of the equipment serviced by the SW System and  
SW System B 3.7.7 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.7.7-4 Revision 55  The Surveillance Frequency is controlled under the Surveillance Frequency Control Program. SR 3.7.7.2  This SR verifies proper automatic operation of the SW System valves on an actual or simulated actuation signal (SIAS). The SW System is a normally operating system that cannot be fully actuated as part of the normal testing. This surveillance test is not required for valves that are locked, sealed, or otherwise secured in the required position under administrative controls. The Surveillance Frequency is controlled under the Surveillance Frequency Control Program. Note:  There are currently no SW valves with an Engineered Safety Feature Actuation System signal since automatic system reconfiguration during a LOCA is not required.
 
SR 3.7.7.3  The SR verifies proper automatic operation of the SW System pumps on an actual or simulated actuation signal (SIAS).
required to be OPERABLE in these MODEs.  
The SW System is a normally operating system that cannot be fully actuated as part of the normal testing during normal operation. The Surveillance Frequency is controlled under the Surveillance Frequency Control Program. REFERENCES 1. UFSAR, Section 9.5.2.3, "Saltwater System" CREVS B 3.7.8 B 3.7  PLANT SYSTEMS B 3.7.8  Control Room Emergency Ventilation System (CREVS)
 
BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.7.8-1 Revision 42 BACKGROUND The CREVS provides a protected environment from which occupants can control the unit following an uncontrolled release of radioactivity, hazardous chemicals, or smoke. The CREVS is a shared system providing protection for both Unit 1 and Unit 2.
In MODEs 5 and 6, the OPERABILITY requirements of the SW System are determined by the systems it supports.
The CREVS consists of two trains, including redundant outside air intake ducts and redundant emergency recirculation filter trains that recirculate and filter the Control Room envelope (CRE) air and a CRE boundary that limits the inleakage of unfiltered air. The CREVS also has shared equipment, including an exhaust-to-atmosphere duct containing redundant isolation valves and a normally closed roof-mounted hatch, an exhaust-to-atmosphere duct from the kitchen and toilet area of the Control Room containing a single isolation valve, and common supply and return ducts in both the standby and emergency recirculation portions of the system. The shared equipment is considered to be a part of each CREVS train. Each CREVS emergency recirculation filter train consists of a prefilter, two high efficiency particulate air (HEPA) filters for removal of aerosols, an activated charcoal adsorber section for removal of elemental and organic iodine and a fan. Ductwork, valves or dampers, doors, and barriers also form part of the system. Instrumentation which actuates the system is addressed in LCOs 3.3.4 and 3.3.8.  
ACTIONS A.1  With one SW subsystem inoperable, action must be taken to restore OPERABLE status within 72 hours. In this Condition,  
 
the remaining OPERABLE SW subsystem is adequate to perform  
 
the heat removal function. However, the overall reliability  
 
is reduced because a single failure in the SW subsystem SW System B 3.7.7 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.7.7-3 Revision 2  could result in loss of SW System function. Required Action A.1 is modified by two Notes. The first Note  
 
indicates that the applicable Conditions of LCO 3.8.1 should be entered if the inoperable SW subsystem results in an  
 
inoperable emergency diesel generator. The second Note  
 
indicates that the applicable Conditions and Required Actions of LCO 3.4.6 should be entered if an inoperable SW subsystem results in an inoperable SDC. The 72 hour Completion Time is based on the redundant capabilities  
 
afforded by the OPERABLE train, and the low probability of a  
 
DBA occurring during this time period.  
 
B.1 and B.2  If the SW subsystems cannot be restored to OPERABLE status within the associated Completion Time, the unit must be  
 
placed in a MODE in which the LCO does not apply. To  
 
achieve this status, the unit must be placed in at least  
 
MODE 3 within 6 hours, and in MODE 5 within 36 hours.  
 
The allowed Completion Times are reasonable, based on operating experience, to reach the required unit conditions  
 
from full power conditions in an orderly manner and without challenging unit systems.
SURVEILLANCE SR 3.7.7.1 REQUIREMENTS Verifying the correct alignment for manual, power-operated, and automatic valves in the SW System flow path ensures that  
 
the proper flow paths exist for SW System operation. This  
 
SR does not apply to valves that are locked, sealed, or otherwise secured in position, since they are verified to be in the correct position prior to locking, sealing, or  
 
securing. This SR also does not apply to valves that cannot  
 
be inadvertently misaligned, such as check valves. This  
 
surveillance test does not require any testing or valve manipulation; rather, it involves verification that those  
 
valves capable of potentially being mispositioned are in the  
 
correct position. This SR is modified by a Note indicating  
 
that the isolation of the SW System components or systems  
 
may render those components inoperable but does not affect  
 
the OPERABILITY of the SW System.  
 
SW System B 3.7.7 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.7.7-4 Revision 55  The Surveillance Frequency is controlled under the Surveillance Frequency Control Program.
SR 3.7.7.2  This SR verifies proper automatic operation of the SW System valves on an actual or simulated actuation signal (SIAS).
The SW System is a normally operating system that cannot be fully actuated as part of the normal testing. This  
 
surveillance test is not required for valves that are  
 
locked, sealed, or otherwise secured in the required  
 
position under administrative controls. The Surveillance Frequency is controlled under the Surveillance Frequency Control Program. Note:  There are currently no SW valves with an Engineered Safety Feature Actuation System signal  
 
since automatic system reconfiguration during a LOCA is not  
 
required.  
 
SR 3.7.7.3  The SR verifies proper automatic operation of the SW System pumps on an actual or simulated actuation signal (SIAS).
 
The SW System is a normally operating system that cannot be  
 
fully actuated as part of the normal testing during normal  
 
operation. The Surveillance Frequency is controlled under the Surveillance Frequency Control Program.
REFERENCES 1. UFSAR, Section 9.5.2.3, "Saltwater System"  
 
CREVS B 3.7.8 B 3.7  PLANT SYSTEMS  
 
B 3.7.8  Control Room Emergency Ventilation System (CREVS)  
 
BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.7.8-1 Revision 42 BACKGROUND The CREVS provides a protected environment from which occupants can control the unit following an uncontrolled release of radioactivity, hazardous chemicals, or smoke.
The CREVS is a shared system providing protection for both Unit 1 and Unit 2.  
 
The CREVS consists of two trains, including redundant  
 
outside air intake ducts and redundant emergency  
 
recirculation filter trains that recirculate and filter the  
 
Control Room envelope (CRE) air and a CRE boundary that limits the inleakage of unfiltered air. The CREVS also has shared equipment, including an exhaust-to-atmosphere duct  
 
containing redundant isolation valves and a normally closed  
 
roof-mounted hatch, an exhaust-to-atmosphere duct from the  
 
kitchen and toilet area of the Control Room containing a  
 
single isolation valve, and common supply and return ducts  
 
in both the standby and emergency recirculation portions of  
 
the system. The shared equipment is considered to be a part  
 
of each CREVS train. Each CREVS emergency recirculation  
 
filter train consists of a prefilter, two high efficiency  
 
particulate air (HEPA) filters for removal of aerosols, an  
 
activated charcoal adsorber section for removal of elemental  
 
and organic iodine and a fan. Ductwork, valves or dampers, doors, and barriers also form part of the system.
Instrumentation which actuates the system is addressed in  
 
LCOs 3.3.4 and 3.3.8.  
 
The CRE is the area within the confines of the CRE boundary that contains the spaces that Control Room occupants inhabit to control the Unit during normal and accident conditions.
This area encompasses the Control Room and may encompass non-critical areas to which frequent personnel access or continuous occupancy is not necessary in the event of an accident. The CRE is protected during normal operation, natural events, and accident conditions. The CRE boundary is the combination of walls, floor, roof, ducting, doors, penetrations, and equipment that physically form the CRE.
The OPERABILITY of the CRE boundary must be maintained to ensure that the inleakage of unfiltered air into the CRE will not exceed the inleakage assumed in the licensing basis CREVS B 3.7.8 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.7.8-2 Revision 42 analysis of DBA consequences to CRE occupants. The CRE and its boundary are defined in the Control Room Envelope Habitability Program.
The CREVS is an emergency system, parts of which may also
 
operate during normal unit operations in the standby mode of
 
operation. Actuation of the CREVS ensures the system is in
 
the emergency recirculation mode of operation, ensures the
 
unfiltered outside air intake and unfiltered exhaust-to-
 
atmosphere valves are closed, and aligns the system for
 
emergency recirculation of CRE air through the redundant trains of HEPA and charcoal filters. The prefilters remove
 
any large particles in the air and any entrained water
 
droplets present to prevent excessive loading of the HEPA
 
filters and charcoal adsorbers. A control room
 
recirculation signal (CRRS) initiates this filtered
 
ventilation of the air supply to the CRE.
 
The air recirculating through the CRE is continuously monitored by a radiation detector. Detector output above
 
the setpoint will cause actuation of the CREVS. The CREVS
 
operation in maintaining the Control Room habitable is
 
discussed in Reference 1, Section 9.8.2.3.
 
The redundant emergency recirculation filter train provides the required filtration should an excessive pressure drop
 
develop across the other filter train. A normally closed
 
hatch and double isolation valves are arranged in series to
 
prevent a breach of isolation from the outside atmosphere,
 
except for the exhaust from the Control Room kitchen and
 
toilet areas. The CREVS is designed in accordance with
 
Seismic Category I requirements.
 
The CREVS is designed to maintain a habitable environment in the CRE for 30 days of continuous occupancy after a DBA without exceeding a 5 rem TEDE for the duration of the accident.
APPLICABLE The CREVS components are generally arranged in redundant SAFETY ANALYSES safety-related ventilation trains although some equipment is shared between trains.
 
The CREVS provides automatic airborne radiological protection for the CRE occupants, as demonstrated by the CRE CREVS B 3.7.8 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.7.8-3 Revision 42 occupant dose analyses for the most limiting design basis fission product release presented in Reference 1, Section 14.24.
 
The CREVS provides protection from smoke and hazardous chemicals to the CRE occupants. The analysis of hazardous chemical releases demonstrates that the toxicity limits are not exceeded in the CRE following a hazardous chemical release. The evaluation of a smoke challenge demonstrates that it will not result in the inability of the CRE occupants to control the reactor either from the Control Room or from the remote shutdown panels.
 
The CREVS also provides automatically actuated airborne radiological protection for the Control Room operations, for
 
the design basis fuel handling accident presented in
 
Reference 1, Section 14.18, the control element assembly
 
ejection event (Reference 1, Section 14.13, the main steam
 
line break (Reference 1, Section 14.14), the steam generator
 
tube rupture (Reference 1, Section 14.15), and the seized
 
rotor event (Reference 1, Section 14.16). The fuel handling
 
accident does not assume a single failure to occur.
 
The worst case single active failure of a component of the CREVS, assuming a loss of offsite power, does not impair the
 
ability of the system to perform its design function (except
 
for one valve in the shared duct between the Control Room
 
and the emergency recirculation filter trains).
The CREVS satisfies 10 CFR 50.36(c)(2)(ii), Criterion 3.
LCO The CREVS is required to be OPERABLE to ensure that the Control Room is isolated and at least one emergency
 
recirculation filter train is available, assuming a single active failure. Total system failure could result in exceeding a dose of 5 rem TEDE in the event of a large radioactive release.
 
The CREVS is considered OPERABLE when the individual components necessary to limit CRE occupant exposure are OPERABLE. For MODEs 1, 2, 3, and 4, redundancy is required
 
and CREVS is considered OPERABLE when:  a. Both supply fans are OPERABLE; CREVS B 3.7.8 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.7.8-4 Revision 42  b. Both recirculation fans are OPERABLE;  c. Both fans included in the emergency recirculation filter trains are OPERABLE;  d. Both HEPA filters and charcoal adsorbers are not excessively restricting flow, and are capable of


The CRE is the area within the confines of the CRE boundary that contains the spaces that Control Room occupants inhabit to control the Unit during normal and accident conditions. This area encompasses the Control Room and may encompass non-critical areas to which frequent personnel access or continuous occupancy is not necessary in the event of an accident. The CRE is protected during normal operation, natural events, and accident conditions. The CRE boundary is the combination of walls, floor, roof, ducting, doors, penetrations, and equipment that physically form the CRE. The OPERABILITY of the CRE boundary must be maintained to ensure that the inleakage of unfiltered air into the CRE will not exceed the inleakage assumed in the licensing basis CREVS B 3.7.8 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.7.8-2 Revision 42 analysis of DBA consequences to CRE occupants. The CRE and its boundary are defined in the Control Room Envelope Habitability Program. The CREVS is an emergency system, parts of which may also operate during normal unit operations in the standby mode of operation. Actuation of the CREVS ensures the system is in the emergency recirculation mode of operation, ensures the unfiltered outside air intake and unfiltered exhaust-to-atmosphere valves are closed, and aligns the system for emergency recirculation of CRE air through the redundant trains of HEPA and charcoal filters. The prefilters remove any large particles in the air and any entrained water droplets present to prevent excessive loading of the HEPA filters and charcoal adsorbers. A control room recirculation signal (CRRS) initiates this filtered ventilation of the air supply to the CRE.
performing their filtration functions;  e. Ductwork, valves, and dampers are OPERABLE, such that air circulation can be maintained; and  f. The Control Room outside air intake can be isolated for the emergency recirculation mode of operation, assuming  
The air recirculating through the CRE is continuously monitored by a radiation detector. Detector output above the setpoint will cause actuation of the CREVS. The CREVS operation in maintaining the Control Room habitable is discussed in Reference 1, Section 9.8.2.3.
 
The redundant emergency recirculation filter train provides the required filtration should an excessive pressure drop develop across the other filter train. A normally closed hatch and double isolation valves are arranged in series to prevent a breach of isolation from the outside atmosphere, except for the exhaust from the Control Room kitchen and toilet areas. The CREVS is designed in accordance with Seismic Category I requirements.
a single failure.
The CREVS is designed to maintain a habitable environment in the CRE for 30 days of continuous occupancy after a DBA without exceeding a 5 rem TEDE for the duration of the accident. APPLICABLE The CREVS components are generally arranged in redundant SAFETY ANALYSES safety-related ventilation trains although some equipment is shared between trains.
In order for the CREVS trains to be considered OPERABLE, the CRE boundary must be maintained such that the CRE occupant dose from a large radioactive release does not exceed the calculated dose in the licensing basis consequence analysis for DBAs, and that CRE occupants are protected from hazardous chemicals and smoke.  
The CREVS provides automatic airborne radiological protection for the CRE occupants, as demonstrated by the CRE CREVS B 3.7.8 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.7.8-3 Revision 42 occupant dose analyses for the most limiting design basis fission product release presented in Reference 1, Section 14.24.
 
The CREVS provides protection from smoke and hazardous chemicals to the CRE occupants. The analysis of hazardous chemical releases demonstrates that the toxicity limits are not exceeded in the CRE following a hazardous chemical release. The evaluation of a smoke challenge demonstrates that it will not result in the inability of the CRE occupants to control the reactor either from the Control Room or from the remote shutdown panels.
The LCO is modified by a Note which indicates that only one CREVS redundant component is required to be OPERABLE during  
The CREVS also provides automatically actuated airborne radiological protection for the Control Room operations, for the design basis fuel handling accident presented in Reference 1, Section 14.18, the control element assembly ejection event (Reference 1, Section 14.13, the main steam line break (Reference 1, Section 14.14), the steam generator tube rupture (Reference 1, Section 14.15), and the seized rotor event (Reference 1, Section 14.16). The fuel handling accident does not assume a single failure to occur.
 
The worst case single active failure of a component of the CREVS, assuming a loss of offsite power, does not impair the ability of the system to perform its design function (except for one valve in the shared duct between the Control Room and the emergency recirculation filter trains). The CREVS satisfies 10 CFR 50.36(c)(2)(ii), Criterion 3. LCO The CREVS is required to be OPERABLE to ensure that the Control Room is isolated and at least one emergency recirculation filter train is available, assuming a single active failure. Total system failure could result in exceeding a dose of 5 rem TEDE in the event of a large radioactive release.
movement of irradiated fuel assemblies, when both units are  
The CREVS is considered OPERABLE when the individual components necessary to limit CRE occupant exposure are OPERABLE. For MODEs 1, 2, 3, and 4, redundancy is required and CREVS is considered OPERABLE when:  a. Both supply fans are OPERABLE; CREVS B 3.7.8 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.7.8-4 Revision 42  b. Both recirculation fans are OPERABLE;  c. Both fans included in the emergency recirculation filter trains are OPERABLE;  d. Both HEPA filters and charcoal adsorbers are not excessively restricting flow, and are capable of performing their filtration functions;  e. Ductwork, valves, and dampers are OPERABLE, such that air circulation can be maintained; and  f. The Control Room outside air intake can be isolated for the emergency recirculation mode of operation, assuming a single failure. In order for the CREVS trains to be considered OPERABLE, the CRE boundary must be maintained such that the CRE occupant dose from a large radioactive release does not exceed the calculated dose in the licensing basis consequence analysis for DBAs, and that CRE occupants are protected from hazardous chemicals and smoke.
 
The LCO is modified by a Note which indicates that only one CREVS redundant component is required to be OPERABLE during movement of irradiated fuel assemblies, when both units are in MODEs 5 or 6, or defueled. Therefore, with both units in other than MODEs 1, 2, 3, or 4, redundancy is not required for movement of irradiated fuel assemblies and CREVS is considered OPERABLE when:  a. One supply fan is OPERABLE;  
in MODEs 5 or 6, or defueled. Therefore, with both units in  
 
other than MODEs 1, 2, 3, or 4, redundancy is not required  
 
for movement of irradiated fuel assemblies and CREVS is  
 
considered OPERABLE when:  a. One supply fan is OPERABLE;  
: b. One recirculation fan is OPERABLE;  
: b. One recirculation fan is OPERABLE;  
: c. One fan included in the OPERABLE emergency recirculation filter train is OPERABLE;  d. One train of two HEPA filters and one charcoal adsorber are not excessively restricting flow, and are capable of performing their filtration functions; and  e. Associated ductwork, valves, and dampers are OPERABLE, such that air circulation can be maintained and the Control Room can be isolated for the emergency recirculation mode.
: c. One fan included in the OPERABLE emergency recirculation filter train is OPERABLE;  d. One train of two HEPA filters and one charcoal adsorber are not excessively restricting flow, and are capable  
When implementing the Note (since redundancy is not required), only one of the two isolation valves in each CREVS B 3.7.8 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.7.8-5 Revision 42 outside air intake duct is required, and only one of the two isolation valves in the exhaust to atmosphere duct is required. However, the non-operating flow path must be capable of providing isolation of the Control Room from the outside atmosphere.
 
The LCO is modified by a second Note which indicates that only one CREVS train is required to be OPERABLE for the movement of irradiated fuel assemblies. Therefore, redundancy is not required for movement of irradiated fuel assemblies and only one CREVS train is required to be OPERABLE.
of performing their filtration functions; and  e. Associated ductwork, valves, and dampers are OPERABLE, such that air circulation can be maintained and the  
The LCO is modified by a third Note allowing the CRE boundary to be opened intermittently under administrative controls. This Note only applies to openings in the CRE boundary that can be rapidly restored to the design condition, such as doors, hatches, floor plugs, and access panels. For entry and exit through doors, the administrative control of the opening is performed by the person(s) entering or exiting the area. For other openings, these controls should be proceduralized and consist of stationing a dedicated individual at the opening who is in continuous communication with the operators in the CRE. This individual will have a method to rapidly close the opening and to restore the CRE boundary to a condition equivalent to the design condition when the need for CRE isolation is indicated.
 
APPLICABILITY In MODEs 1, 2, 3, and 4, the CREVS must be OPERABLE to ensure that the CRE will remain habitable during and following a DBA.
Control Room can be isolated for the emergency  
During movement of irradiated fuel assemblies, the CREVS must be OPERABLE to cope with the release from a fuel handling accident. ACTIONS A.1  With one or more ducts with one Control Room outside air intake isolation valve inoperable in MODEs 1, 2, 3, or 4, the OPERABLE Control Room outside air intake valve in each affected duct must be closed immediately. This places the CREVS B 3.7.8 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.7.8-6 Revision 42 OPERABLE Control Room outside air intake isolation valve in each affected duct in its safety function required position.
 
B.1  With the toilet area exhaust isolation valve inoperable, action must be taken to restore OPERABLE status within 24 hours. In this Condition, the toilet area exhaust cannot be isolated, therefore, the valve must be restored to OPERABLE status. The 24 hour period allows enough time to repair the valve while limiting the time the toilet area is open to the atmosphere. The 24 hour Completion Time is based on the low probability of a DBA occurring during this time period.
recirculation mode.  
C.1  With one exhaust to atmosphere isolation valve inoperable in MODEs 1, 2, 3, or 4, action must be taken to restore OPERABLE status within seven days. In this Condition, the remaining OPERABLE exhaust to atmosphere isolation valve is adequate to isolate the Control Room. However, the overall reliability is reduced because a single failure in the OPERABLE exhaust to atmosphere isolation valve could result in loss of exhaust to atmosphere isolation valve function.
 
The seven day Completion Time is based on the low probability of a DBA occurring during this time period, and the ability of the remaining exhaust to atmosphere isolation valve to provide the required isolation capability.
When implementing the Note (since redundancy is not required), only one of the two isolation valves in each CREVS B 3.7.8 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.7.8-5 Revision 42 outside air intake duct is required, and only one of the two isolation valves in the exhaust to atmosphere duct is  
D.1, D.2, and D.3 If the unfiltered inleakage of potentially contaminated air past the CRE boundary and into the CRE can result in CRE occupant radiological dose greater than the calculated dose of the licensing basis analyses of DBA consequences (allowed to be up to 5 rem TEDE), or inadequate protection of CRE occupants from hazardous chemicals or smoke, the CRE boundary is inoperable. Actions must be taken to restore an OPERABLE CRE boundary within 90 days. During the period that the CRE boundary is considered inoperable, action must be initiated to implement mitigation actions to lessen the effect on CRE occupants from the potential hazards of a radiological or chemical event or a CREVS B 3.7.8 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.7.8-7 Revision 52 challenge from smoke. Required Action D.3 allows time to restore the CRE boundary to OPERABLE status provided mitigating actions can ensure that the CRE remains within the licensing basis habitability limits for the occupants following an accident. Compensatory measures are discussed in Reference 2. These compensatory measures may also be used as mitigating actions as required by Required Action D.2. Temporary analytical methods may also be used as compensatory measures to restore OPERABILITY. Actions must be taken within 24 hours to verify that, in the event of a DBA, the mitigating actions will ensure that CRE occupant radiological exposures will not exceed the calculated dose of the licensing basis analysis of DBA consequences, and that CRE occupants are protected from hazardous chemicals and smoke. These mitigating actions (i.e., actions that are taken to offset the consequences of the inoperable CRE boundary) should be preplanned for implementation upon entry into the condition, regardless of whether entry is intentional or unintentional.  
 
required. However, the non-operating flow path must be  
 
capable of providing isolation of the Control Room from the  
 
outside atmosphere.  
 
The LCO is modified by a second Note which indicates that only one CREVS train is required to be OPERABLE for the  
 
movement of irradiated fuel assemblies. Therefore,  
 
redundancy is not required for movement of irradiated fuel  
 
assemblies and only one CREVS train is required to be OPERABLE.  
 
The LCO is modified by a third Note allowing the CRE boundary to be opened intermittently under administrative controls. This Note only applies to openings in the CRE boundary that can be rapidly restored to the design condition, such as doors, hatches, floor plugs, and access panels. For entry and exit through doors, the administrative control of the opening is performed by the person(s) entering or exiting the area. For other openings, these controls should be proceduralized and consist of stationing a dedicated individual at the opening who is in continuous communication with the operators in the CRE.
This individual will have a method to rapidly close the opening and to restore the CRE boundary to a condition equivalent to the design condition when the need for CRE isolation is indicated.  
 
APPLICABILITY In MODEs 1, 2, 3, and 4, the CREVS must be OPERABLE to ensure that the CRE will remain habitable during and following a DBA.  
 
During movement of irradiated fuel assemblies, the CREVS must be OPERABLE to cope with the release from a fuel  
 
handling accident.
ACTIONS A.1  With one or more ducts with one Control Room outside air intake isolation valve inoperable in MODEs 1, 2, 3, or 4,  
 
the OPERABLE Control Room outside air intake valve in each  
 
affected duct must be closed immediately. This places the CREVS B 3.7.8 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.7.8-6 Revision 42 OPERABLE Control Room outside air intake isolation valve in each affected duct in its safety function required position.  
 
B.1  With the toilet area exhaust isolation valve inoperable, action must be taken to restore OPERABLE status within  
 
24 hours. In this Condition, the toilet area exhaust cannot  
 
be isolated, therefore, the valve must be restored to  
 
OPERABLE status. The 24 hour period allows enough time to  
 
repair the valve while limiting the time the toilet area is  
 
open to the atmosphere. The 24 hour Completion Time is based on the low probability of a DBA occurring during this time period.  
 
C.1  With one exhaust to atmosphere isolation valve inoperable in MODEs 1, 2, 3, or 4, action must be taken to restore  
 
OPERABLE status within seven days. In this Condition, the  
 
remaining OPERABLE exhaust to atmosphere isolation valve is  
 
adequate to isolate the Control Room. However, the overall  
 
reliability is reduced because a single failure in the  
 
OPERABLE exhaust to atmosphere isolation valve could result  
 
in loss of exhaust to atmosphere isolation valve function.
 
The seven day Completion Time is based on the low  
 
probability of a DBA occurring during this time period, and  
 
the ability of the remaining exhaust to atmosphere isolation  
 
valve to provide the required isolation capability.  
 
D.1, D.2, and D.3 If the unfiltered inleakage of potentially contaminated air past the CRE boundary and into the CRE can result in CRE occupant radiological dose greater than the calculated dose of the licensing basis analyses of DBA consequences (allowed to be up to 5 rem TEDE), or inadequate protection of CRE occupants from hazardous chemicals or smoke, the CRE boundary is inoperable. Actions must be taken to restore an OPERABLE CRE boundary within 90 days.
During the period that the CRE boundary is considered inoperable, action must be initiated to implement mitigation actions to lessen the effect on CRE occupants from the potential hazards of a radiological or chemical event or a CREVS B 3.7.8 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.7.8-7 Revision 52 challenge from smoke. Required Action D.3 allows time to restore the CRE boundary to OPERABLE status provided  
 
mitigating actions can ensure that the CRE remains within  
 
the licensing basis habitability limits for the occupants  
 
following an accident. Compensatory measures are discussed  
 
in Reference 2. These compensatory measures may also be used as mitigating actions as required by Required  
 
Action D.2. Temporary analytical methods may also be used  
 
as compensatory measures to restore OPERABILITY. Actions  
 
must be taken within 24 hours to verify that, in the event  
 
of a DBA, the mitigating actions will ensure that CRE occupant radiological exposures will not exceed the calculated dose of the licensing basis analysis of DBA  
 
consequences, and that CRE occupants are protected from  
 
hazardous chemicals and smoke. These mitigating actions  
 
(i.e., actions that are taken to offset the consequences of  
 
the inoperable CRE boundary) should be preplanned for  
 
implementation upon entry into the condition, regardless of  
 
whether entry is intentional or unintentional.
 
The 24 hour Completion Time is reasonable based on the
 
determination that the mitigating actions will ensure
 
protection of the CRE occupants within analyzed limits while
 
limiting the probability that CRE occupants will have to
 
implement protective measures that may adversely affect
 
their ability to control the reactor and maintain it in a
 
safe shutdown condition in the event of a DBA. In addition,
 
the 90 day Completion Time is a reasonable time to diagnose,
 
plan, and possibly repair and test most problems with the
 
CRE boundary.
 
E.1  With one CREVS train inoperable for reasons other than Conditions A, B, C, or D in MODEs 1, 2, 3, or 4, action must
 
be taken to restore OPERABLE status within seven days. In
 
this Condition, the remaining OPERABLE CREVS subsystem is
 
adequate to perform CRE occupant protection function. 
 
However, the overall reliability is reduced because a
 
failure in the OPERABLE CREVS train could result in loss of CREVS function. The seven day Completion Time is based on the low probability of a DBA occurring during this time
 
period, and the ability of the remaining train to provide
 
the required capability.
CREVS B 3.7.8 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.7.8-8 Revision 52 F.1, F.2, and F.3 If both CREVS trains are inoperable in MODE 1, 2, 3, or 4 for reasons other than an inoperable Control Room boundary (i.e., Condition D), at least one CREVS train must be returned to OPERABLE status within 24 hours. The Condition is modified by a Note stating it is not applicable if the second CREVS train is intentionally declared inoperable.
The Condition does not apply to voluntary removal of redundant systems or components from service. The Condition is only applicable if one train is inoperable for any reason and the second train is discovered to be inoperable, or if both trains are discovered to be inoperable at the same time. During the period that the CREVS trains are inoperable, action must be initiated to implement mitigating actions to lessen the effect on CRE occupants from potential hazards while both trains of CREVS are inoperable. In the event of a DBA, the mitigating actions will reduce the consequences of radiological exposures to the CRE occupants.
Specification 3.4.16, RCS Specific Activity, allows limited operation with the RCS activity significantly greater than the LCO limit. This presents a risk to the plant operator during an accident when all the CREVS trains are inoperable.
Therefore, it must be verified within one hour that LCO 3.4.16 is met. This Required Action does not require additional RCS sampling beyond that normally required by LCO 3.4.16.
At least one CREVS train must be returned to OPERABLE status within 24 hours. The Completion Time is based on Reference 3 which demonstrated that the 24 hour Completion Time is acceptable based on the infrequent use of the Required Actions and the small incremental effect on plant risk.
 
G.1  Action G provides the actions to be taken when the Required Action and associated Completion Time of Condition B cannot
 
be met or with one or more CREVS trains inoperable due to an inoperable CRE boundary. It requires the immediate suspension of movement of irradiated fuel assemblies. This
 
places the unit in a condition that minimizes the accident
 
risk. This does not preclude the movement of fuel CREVS B 3.7.8 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.7.8-9 Revision 55  assemblies to a safe position. Since only one CREVS train must be OPERABLE for movement of irradiated fuel assemblies,
 
the Required Action is applicable only to the required CREVS
 
train.
H.1  If both CREVS trains are inoperable for reasons other than Conditions A, B, C, or D, or if one or more ducts have two
 
outside air intake isolation valves inoperable, or if two
 
exhaust to atmosphere isolation valves are inoperable during
 
movement of irradiated fuel assemblies, the CREVS may not be capable of performing the intended function and the unit is in a condition outside the accident analyses. Therefore,
 
movement of irradiated fuel must be suspended immediately. 
 
This does not preclude the movement of fuel assemblies to a
 
safe condition.
I.1 and I.2  If the inoperable CREVs or Control Room boundary cannot be restored to OPERABLE status within the associated Completion
 
Time in MODE 1, 2, 3, or 4, the unit must be placed in a
 
mode that minimizes the accident risk. To achieve this
 
status the unit must be placed in at least MODE 3 within six
 
hours and in MODE 5 within 36 hours. The allowed Completion
 
Times are reasonable, based on operating experience, to
 
reach the required unit conditions from full power
 
conditions in an orderly manner and without challenging unit systems.
SURVEILLANCE SR 3.7.8.1 REQUIREMENTS Standby systems should be checked periodically to ensure that they function properly. Since the environment and
 
normal operating conditions on this system are not severe,
 
testing each required CREVS filter train once every month
 
provides an adequate check on this system.
 
The Surveillance Frequency is controlled under the Surveillance Frequency Control Program.
 
CREVS B 3.7.8 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.7.8-10 Revision 55  SR 3.7.8.2  This SR verifies that the required CREVS testing is performed in accordance with the Ventilation Filter Testing
 
Program (VFTP). The CREVS filter tests are in accordance
 
with portions of Reference 4. The VFTP includes testing
 
HEPA filter performance, charcoal adsorber efficiency,
 
minimum system flow rate, and the physical properties of the
 
activated charcoal (general use and following specific
 
operations). Specific test Frequencies and additional
 
information are discussed in detail in the VFTP.
SR 3.7.8.3  This SR verifies each CREVS train starts and operates on an actual or simulated actuation signal (CRRS). The Surveillance Frequency is controlled under the Surveillance Frequency Control Program.
 
SR 3.7.8.4  This SR verifies the OPERABILITY of the CRE boundary by testing for unfiltered air inleakage past the CRE boundary
 
and into the CRE. The details of the testing are specified
 
in the Control Room Envelope Habitability Program.
 
The CRE is considered habitable when the radiological dose to the CRE occupants calculated in the licensing basis
 
analysis of DBA consequences is no more than 5 rem TEDE and
 
the CRE occupants are protected from hazardous chemicals and
 
smoke. This SR verifies that the unfiltered air inleakage
 
into the CRE is no greater than the flow rate assumed in the
 
licensing basis analysis of DBA consequences. When
 
unfiltered air inleakage is greater than the assumed flow
 
rate, Condition E must be entered. Options for restoring
 
the CRE boundary to OPERABLE status include changing the
 
licensing basis DBA consequences analysis, repairing the CRE
 
boundary, or a combination of these actions. Depending upon
 
the nature of the problem and the corrective action, a full
 
scope inleakage test may not be necessary to establish that the CRE boundary has been restored to OPERABLE status.
 
CREVS B 3.7.8 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.7.8-11 Revision 52 REFERENCES 1. UFSAR  2. Regulatory Guide 1.196, Revision 0, "Control Room Habitability at Light-Water Nuclear Power Reactors,"
May 2003  3. WCAP-16125-NP-A, Justification for Risk-Informed Modifications to Selected Technical Specifications for Conditions Leading to Exigent Plant Shutdown, Revision 2, August 2010  4. Regulatory Guide 1.52, Revision 2, "Design, Testing, and Maintenance Criteria for Post Accident Engineered-Safety-Feature Atmosphere Cleanup System Air Filtration and Adsorption Units of Light-Water-Cooled Nuclear Power Plants," March 1978
 
CRETS B 3.7.9 B 3.7  PLANT SYSTEMS
 
B 3.7.9  Control Room Emergency Temperature System (CRETS)
 
BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.7.9-1 Revision 2 BACKGROUND The CRETS provides temperature control for the Control Room following isolation of the Control Room. The CRETS is a shared system which is supported by the CREVS, since the CREVS must be operating in the emergency recirculation mode for CRETS to perform its safety function.
 
The CRETS consists of two independent, redundant trains that provide cooling of recirculated Control Room air. Each train consists of cooling coils, instrumentation, and
 
controls to provide for Control Room temperature control.
The CRETS is a subsystem providing air temperature control
 
for the Control Room.
 
The CRETS is an emergency system, parts of which may also operate during normal unit operations in the standby mode of
 
operation. A single train will provide the required
 
temperature control to maintain the Control Room below 104&deg;F. The CRETS operation to maintain the Control Room temperature is discussed in Reference 1.
 
APPLICABLE The design basis of the CRETS is to maintain temperature SAFETY ANALYSES of the Control Room environment throughout 30 days of continuous occupancy.
 
The CRETS components are arranged in redundant safety-related trains. During emergency operation, the CRETS
 
maintains the temperature below 104&deg;F. A single active
 
failure of a component of the CRETS, assuming a loss of offsite power, does not impair the ability of the system to perform its design function. Redundant detectors and
 
controls are provided for Control Room temperature control.
The CRETS is designed in accordance with Seismic Category I
 
requirements. The CRETS is capable of removing sensible and
 
latent heat loads from the Control Room, considering equipment heat loads and personnel occupancy requirements,
 
to ensure equipment OPERABILITY.
The CRETS satisfies 10 CFR 50.36(c)(2)(ii), Criterion 3.
 
CRETS B 3.7.9 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.7.9-2 Revision 31 LCO Two independent and redundant trains of the CRETS are required to be OPERABLE to ensure that at least one is
 
available, assuming a single failure disables the other
 
train following isolation of the Control Room. Total system
 
failure could result in the equipment operating temperature
 
exceeding limits in the event of an accident requiring isolation of the Control Room.
 
The CRETS is considered OPERABLE when the individual components that are necessary to maintain the Control Room
 
temperature are OPERABLE. The required components include
 
the cooling coils and associated temperature control
 
instrumentation. In addition, the CRETS must be OPERABLE to
 
the extent that air circulation can be maintained.
 
For MODEs 1, 2, 3, and 4, redundancy is required and both trains must be OPERABLE. The LCO is modified by a Note
 
which indicates that only one CRETS train is required to be
 
OPERABLE for the movement of irradiated fuel assemblies.
Therefore, redundancy is not required for movement of
 
irradiated fuel assemblies and only one CRETS train is required to be OPERABLE.
APPLICABILITY In MODEs 1, 2, 3, and 4, and during movement of irradiated fuel assemblies, the CRETS must be OPERABLE to ensure that
 
the Control Room temperature will not exceed equipment
 
OPERABILITY requirements following isolation of the Control
 
Room. ACTIONS A.1  With one CRETS train inoperable in MODEs 1, 2, 3, or 4, action must be taken to restore OPERABLE status within
 
30 days. In this Condition, the remaining OPERABLE CRETS
 
train is adequate to maintain the Control Room temperature
 
within limits. The 30 day Completion Time is reasonable,
 
based on the low probability of an event occurring requiring
 
Control Room isolation, consideration that the remaining
 
train can provide the required capabilities, and the
 
alternate safety or non-safety-related cooling means that
 
are available.
 
CRETS B 3.7.9 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.7.9-3 Revision 55  B.1 and B.2  If the Required Actions and associated Completion Times of Condition A are not met in MODEs 1, 2, 3, or 4, the unit
 
must be placed in a MODE that minimizes the accident risk. 
 
To achieve this status, the unit must be placed in at least
 
MODE 3 within 6 hours, and in MODE 5 within 36 hours. The allowed Completion Times are reasonable, based on operating experience, to reach the required unit conditions from full
 
power conditions in an orderly manner and without
 
challenging unit systems.
 
C.1  If both CRETS trains are inoperable in MODEs 1, 2, 3, or 4, or during movement of irradiated fuel assemblies, the CRETS
 
may not be capable of performing the intended function and
 
the unit is in a condition outside the accident analysis. 
 
Therefore, LCO 3.0.3 must be entered immediately and
 
movement of irradiated fuel must be suspended immediately. 
 
This does not preclude the movement of fuel assemblies to a safe condition.
SURVEILLANCE SR 3.7.9.1 REQUIREMENTS This SR verifies each required CRETS train has the capability to maintain Control Room temperature  104&deg;F for  12 hours in the recirculation mode. During this test, the backup Control Room air conditioner is to be de-
 
energized. This SR consists of a combination of testing. 
 
The Surveillance Frequency is controlled under the Surveillance Frequency Control Program.
 
REFERENCES 1. UFSAR, Section 9.8.2.3, "Auxiliary Building Ventilating Systems"
 
SFPEVS B 3.7.11 B 3.7  PLANT SYSTEMS
 
B 3.7.11  Spent Fuel Pool Exhaust Ventilation System (SFPEVS)
 
BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.7.11-1 Revision 41 BACKGROUND The SFPEVS exhausts airborne radioactive particulates and gases from the area of the fuel pool into the plant ventilation stack following a fuel handling accident involving recently irradiated fuel.
The SFPEVS consists of two independent, redundant exhaust fans. Ductwork, valves or dampers, and instrumentation also form part of the system. The SFPEVS is supplied power by
 
one non-safety-related power supply.
 
The SFPEVS is operated during normal unit operations. When movement of the air is required (i.e., during movement of recently irradiated fuel assemblies in the Auxiliary
 
Building), normal air discharges from the fuel handling area
 
in the Auxiliary Building. 
 
The SFPEVS is discussed in Reference 1, Sections 9.8.2.3 and 14.18, because it may be used for normal, as well as post-accident ventilation.
APPLICABLE The SFPEVS is designed to mitigate the consequences of a SAFETY ANALYSES fuel handling accident involving handling recently irradiated fuel (i.e., fuel that has occupied part of a
 
critical reactor core within the previous 55 days), in which all rods in the fuel assembly are assumed to be damaged. 
 
The analysis of the fuel handling accident is given in
 
Reference 1, Section 14.18. The DBA analysis of the fuel
 
handling accident assumes that the SFPEVS is functional and exhausts airborne radioactive particulates and gases from the fuel pool area into the plant ventilation stack. The analysis follows the guidance provided in Reference 2.
The SFPEVS satisfies 10 CFR 50.36(c)(2)(ii), Criterion 3.
LCO Two exhaust fans and other equipment listed in the Background Section are required to be OPERABLE and in
 
operation.
 
The SFPEVS is considered OPERABLE when the individual components necessary to direct exhaust into the ventilation SFPEVS B 3.7.11 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.7.11-2 Revision 41 stack are OPERABLE. The SFPEVS is considered OPERABLE when its associated:  a. Fans are OPERABLE; and  b. Ductwork, valves, and dampers are OPERABLE, and air circulation can be maintained.
The SFPEVS is considered in operation when an OPERABLE exhaust fan is in operation.
APPLICABILITY During movement of recently irradiated fuel assemblies in the Auxiliary Building, the SFPEVS is required to be
 
OPERABLE and in operation to mitigate the consequences of a
 
fuel handling accident involving handling recently
 
irradiated fuel by minimizing the atmospheric dispersion to the Control Room. Due to radioactive decay, the SFPEVS is only required to mitigate fuel handling accidents involving
 
handling recently irradiated fuel (i.e., fuel that has
 
occupied part of a critical reactor core within the previous 55 days).
ACTIONS A.1 and A.2  When one SFPEVS exhaust fan is inoperable, action must be taken to verify an OPERABLE SFPEVS train is in operation, or
 
movement of recently irradiated fuel assemblies in the
 
Auxiliary Building must be suspended. One OPERABLE SFPEVS train consists of one OPERABLE exhaust fan. This ensures the proper equipment is operating for the Applicable Safety Analysis.
 
B.1  When there is no OPERABLE SFPEVS train or there is no OPERABLE SFPEVS train in operation during movement of
 
recently irradiated fuel assemblies in the Auxiliary
 
Building, action must be taken to place the unit in a
 
condition in which the LCO does not apply. This Action
 
involves immediately suspending movement of recently
 
irradiated fuel assemblies in the Auxiliary Building. This does not preclude the movement of fuel to a safe position.
 
SFPEVS B 3.7.11 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.7.11-3 Revision 55 SURVEILLANCE SR 3.7.11.1 REQUIREMENTS  The SR requires verification that the SFPEVS is in operation. Verification includes verifying that one exhaust
 
fan is operating and discharging into the ventilation stack. 
 
The Surveillance Frequency is controlled under the Surveillance Frequency Control Program.
 
SR 3.7.11.2 Deleted.
 
SR 3.7.11.3  This SR verifies the integrity of the spent fuel storage pool area. The ability of the spent fuel storage pool area
 
to maintain negative pressure with respect to potentially
 
uncontaminated adjacent areas is periodically tested to
 
verify proper function of the SFPEVS. During operation, the
 
spent fuel storage pool area is designed to maintain a
 
slight negative pressure in the spent fuel storage pool
 
area, with respect to adjacent areas, to ensure that
 
exhausted air is directed to the ventilation stack.
 
The Surveillance Frequency is controlled under the Surveillance Frequency Control Program.
 
REFERENCES 1. UFSAR  2. Regulatory Guide 1.183, Alternative Radiological Source Terms for Evaluating Design Basis Accidents at Nuclear Power Reactors, July 2000
 
PREVS B 3.7.12 B 3.7  PLANT SYSTEMS
 
B 3.7.12  Penetration Room Exhaust Ventilation System (PREVS)
 
BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.7.12-1 Revision 52 BACKGROUND The PREVS filters air from the penetration room.
 
The PREVS consists of two independent and redundant trains.
Each train consists of a prefilter, a HEPA filter, an activated charcoal adsorber section for removal of gaseous activity (principally iodines), and a fan. Ductwork, valves
 
or dampers, and instrumentation also form part of the
 
system. The system initiates filtered ventilation following
 
receipt of a containment isolation actuation signal.
 
The PREVS is a standby system, which may also operate during normal unit operations. During emergency operations, the
 
PREVS dampers are realigned, and fans are started to
 
initiate filtration. Upon receipt of the actuating
 
Engineered Safety Feature Actuation System signal(s), normal
 
air discharges from the penetration room, and the stream of
 
ventilation air discharges through the system filter trains. 
 
The prefilters remove any large particles in the air to
 
prevent excessive loading of the HEPA filters and charcoal
 
adsorbers.
 
The PREVS is discussed in Reference 1, Section 6.6.2, as it may be used for normal, as well as post-accident, atmospheric cleanup functions.
APPLICABLE The design basis of the PREVS is established by the Maximum SAFETY ANALYSES Hypothetical Accident. The system is credited with filtering the radioactive material released through the containment vent when the line is open. Also commensurate with the guidance in Reference 2, a conservative bypass fraction from the Containment to the penetration rooms is
 
assumed. Following a LOCA, the containment isolation signal
 
will start both of the fans associated with the PREVS,
 
filtering the exhaust through the HEPA and charcoal filters,
 
and directing the exhaust into the ventilation stack. The
 
analysis of the effects and consequences of a Maximum
 
Hypothetical Accident are presented in Reference 1,
 
Section 14.24 and follows the guidance presented in
 
Reference 3.
 
PREVS B 3.7.12 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.7.12-2 Revision 41  As a layer of defense, the Penetration Room Exhaust Ventilation System also provides filtered ventilation of radioactive materials leaking from ECCS equipment within the
 
penetration room following an accident, however, credit for
 
this feature was not assumed in the accident analysis
 
(Reference 1, Section 14.24).
 
The PREVS satisfies 10 CFR 50.36(c)(2)(ii), Criterion 3.
LCO Two independent and redundant trains of the PREVS are required to be OPERABLE to ensure that at least one train is
 
available, assuming there is a single failure disabling the
 
other train coincident with a loss of offsite power.
 
The PREVS is considered OPERABLE when the individual components necessary to control radioactive releases are
 
OPERABLE in both trains. A PREVS train is considered
 
OPERABLE when its associated:  a. Fan is OPERABLE;
: b. High efficiency particulate air filter and charcoal adsorber are not excessively restricting flow, and are
 
capable of performing the filtration functions; and  c. Ductwork, valves, and dampers are OPERABLE, and circulation can be maintained.
 
APPLICABILITY In MODEs 1, 2, and 3, the PREVS is required to be OPERABLE to mitigate the potential radioactive material release from
 
a Maximum Hypothetical Accident.
 
In MODEs 4, 5, and 6, the PREVS is not required to be OPERABLE, since the RCS temperature and pressure are low and
 
there is insufficient energy to result in the conditions assumed in the accident analysis.
ACTIONS A.1  With one PREVS train inoperable, action must be taken to restore OPERABLE status within seven days. During this time
 
period, the remaining OPERABLE train is adequate to perform
 
the PREVS function. The seven day Completion Time is
 
reasonable based on the low probability of a DBA occurring PREVS B 3.7.12 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.7.12-3 Revision 52  during this time period, and the consideration that the remaining train can provide the required capability.
B.1 and B.2 With two PREVS trains inoperable, action must be taken to restore at least one PREVS train to OPERABLE status within 24 hours. The Condition is modified by a Note stating it is not applicable if the second PREVS train is intentionally declared inoperable. The Condition does not apply to voluntary removal of redundant systems or components from service. The Condition is only applicable if one train is inoperable for any reason and the second train is discovered to be inoperable, or if both trains are discovered to be inoperable at the same time. In addition, at least one train of containment spray must be verified to be OPERABLE within one hour. In the event of an accident, containment spray reduces the potential radioactive release from the containment, which reduces the consequences of the inoperable PREVS trains. The Completion Time is based on Reference 4 which demonstrated that the 24 hour Completion Time is acceptable based on the infrequent use of the Required Actions and the small incremental effect on plant risk.
C.1 and C.2  If the inoperable train cannot be restored to OPERABLE status within the associated Completion Time, the unit must
 
be placed in a MODE in which the LCO does not apply. To
 
achieve this status, the unit must be placed in at least
 
MODE 3 within 6 hours, and in MODE 4 within 12 hours. The
 
allowed Completion Times are reasonable, based on operating
 
experience, to reach the required unit conditions from full
 
power conditions in an orderly manner and without challenging unit systems.
SURVEILLANCE SR 3.7.12.1 REQUIREMENTS Standby systems should be checked periodically to ensure that they function properly. As the environment and normal
 
operating conditions on this system are not severe, testing
 
each train once every month provides an adequate check on
 
this system.
PREVS B 3.7.12 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.7.12-4 Revision 55 The test is performed by initiating the system from the Control Room, ensuring flow through the HEPA filter and
 
charcoal adsorber train, and verifying this system operates for  15 minutes. The Surveillance Frequency is controlled under the Surveillance Frequency Control Program.
SR 3.7.12.2  This SR verifies the performance of PREVS filter testing in accordance with the VFTP. The PREVS filter tests are in
 
accordance with portions of Reference 5. The VFTP includes
 
testing the performance of the HEPA filter, charcoal
 
adsorber efficiency, minimum system flow rate, and the
 
physical properties of the activated charcoal (general use
 
and following specific operations). Specific test
 
frequencies and additional information are discussed in
 
detail in the VFTP.
 
SR 3.7.12.3  This SR verifies that each PREVS train starts and operates on an actual or simulated actuation signal (Containment
 
Isolation Signal). The Surveillance Frequency is controlled under the Surveillance Frequency Control Program.
 
REFERENCES 1. UFSAR  2. Regulatory Guide 1.194, Atmospheric Relative Concentrations for Control Room Radiological
 
Habitability Assessments at Nuclear Power Plants, June
 
2003  3. Regulatory Guide 1.183, Alternative Radiological Source Terms for Evaluating Design Basis Accidents at Nuclear Power Reactors, July 2000  4. WCAP-16125-NP-A, Justification for Risk-Informed Modifications to Selected Technical Specifications for
 
Conditions Leading to Exigent Plant Shutdown,
 
Revision 2, August 2010 PREVS B 3.7.12 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.7.12-5 Revision 55  5. Regulatory Guide 1.52, Revision 2, "Design, Testing, and Maintenance Criteria for Post Accident Engineered-
 
Safety-Feature Atmosphere Cleanup System Air Filtration
 
and Adsorption Units of Light-Water-Cooled Nuclear Power Plants," March 1978
 
SFP Water Level B 3.7.13 B 3.7  PLANT SYSTEMS
 
B 3.7.13  Spent Fuel Pool (SFP) Water Level
 
BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.7.13-1 Revision 41 BACKGROUND The minimum water level in the SFP meets the assumptions of iodine decontamination factors following a fuel handling
 
accident. The specified water level shields and minimizes
 
the general area dose when the storage racks are filled to their maximum capacity. The water also provides shielding during the movement of spent fuel.
 
A general description of the SFP design is given in Reference 1, Section 9.7.2, and the SFP Cooling and Cleanup
 
System is given in Reference 1, Section 9.4.1. The
 
assumptions of the fuel handling accident are given in Reference 1, Section 14.18.
APPLICABLE Per Reference 2, the Fuel Handling Accident (FHA) analysis  SAFETY ANALYSES may assume a total iodine decontamination factor of 200 based on a minimum water depth of 23 feet. The minimum water level requirement ensures that sufficient water depth
 
is available to remove 99.5% of gap activity, which is comprised of 16% I-131 and 10% of all other iodine isotopes released from the rupture of an irradiated fuel assembly.
The Technical Specifications requirement of 21.5 feet of water above fuel assemblies seated in the SFP storage racks
 
is sufficient to preserve the required 23 feet of water
 
because an FHA was assumed to occur as a fuel assembly
 
strikes the bottom of the SFP.
 
When assemblies are placed on rack spacers with their upper end fittings removed, an FHA caused by a dropped heavy object would result in a lower decontamination factor based
 
on reduced water coverage. A revised decontamination factor
 
of 120 for an FHA during reconstitution or inspection with 20.4 feet of water between the top of the pin and the
 
surface of the water was computed for an assembly placed on a 20.5 inch rack spacer with its upper end fitting removed.
Note that this is very conservative, since normal level
 
control will result in at least 21.5 feet of water above
 
exposed fuel pins. This results in a 99.17% removal rate. 
 
SFP Water Level B 3.7.13 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.7.13-2 Revision 55  The SFP water level satisfies 10 CFR 50.36(c)(2)(ii),
Criteria 2 and 3.
LCO The specified water level preserves the assumptions of the fuel handling accident analysis (Reference 1,
 
Section 14.18). As such, it is the minimum required for fuel storage, reconstitution, and movement within the fuel
 
storage pool.
APPLICABILITY This LCO applies during movement of irradiated fuel assemblies in the SFP since the potential for a release of fission products exists.
ACTIONS A.1  Required Action A.1 is modified by a Note indicating that LCO 3.0.3 does not apply.
 
When the initial conditions for an accident cannot be met, steps should be taken to preclude the accident from
 
occurring. When the SFP water level is lower than the
 
required level, the movement of irradiated fuel assemblies
 
in the SFP is immediately suspended. This effectively
 
precludes a spent fuel handling accident from occurring. 
 
This does not preclude moving a fuel assembly to a safe
 
position.
If moving irradiated fuel assemblies while in MODEs 5 or 6, LCO 3.0.3 would not specify any action. If moving
 
irradiated fuel assemblies while in MODEs 1, 2, 3, and 4,
 
the fuel movement is independent of reactor operations. 
 
Therefore, in either case, inability to suspend movement of
 
irradiated fuel assemblies is not sufficient reason to require a reactor shutdown.
SURVEILLANCE SR 3.7.13.1 REQUIREMENTS This SR verifies sufficient SFP water is available in the event of a fuel handling accident. The water level in the
 
SFP must be checked periodically. The Surveillance Frequency is controlled under the Surveillance Frequency Control Program.
 
SFP Water Level B 3.7.13 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.7.13-3 Revision 41  During refueling operations, the level in the SFP is normally at equilibrium with that of the refueling canal.
REFERENCES 1. UFSAR  2. Regulatory Guide 1.183, Alternative Radiological Source Terms for Evaluating Design Basis Accidents at Nuclear Power Reactors, July 2000
 
Secondary Specific Activity B 3.7.14 B 3.7  PLANT SYSTEMS
 
B 3.7.14  Secondary Specific Activity
 
BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.7.14-1 Revision 41 BACKGROUND Activity in the secondary coolant results from steam generator tube outleakage from the RCS. Under steady state
 
conditions, the activity is primarily iodines with
 
relatively short half lives, and thus is an indication of current conditions. During transients, DOSE EQUIVALENT I-131 spikes have been observed as well as
 
increased releases of some noble gases. Other fission
 
product isotopes, as well as activated corrosion products in
 
lesser amounts, may also be found in the secondary coolant.
 
A limit on secondary coolant specific activity during power operation minimizes releases to the environment because of
 
normal operation, anticipated operational occurrences, and
 
accidents.
 
This limit is lower than the activity value that might be expected from a 100 gallons per day tube leak (LCO 3.4.13) of primary coolant at the limit of 0.5
&#xb5;Ci/gm (LCO 3.4.15).
The main SLB is assumed to result in the release of the noble gas and iodine activity contained in the steam
 
generator inventory, the feedwater, and reactor coolant
 
LEAKAGE via flashing directly to the environment through the main steam gooseneck. 
 
APPLICABLE The accident analysis of the main SLB, as discussed in SAFETY ANALYSES Reference 1, assumes the initial secondary coolant specific activity to have a radioactive isotope concentration of 0.10 &#xb5;Ci/gm DOSE EQUIVALENT I-131. This secondary activity, together with the Technical Specification primary system activity, and failed fuel activity, is used in the analysis for determining the radiological consequences of the postulated accident. The accident analysis shows that the radiological consequences of a main SLB do not exceed
 
the acceptance criteria given in References 1 and 2.
 
With the loss of offsite power post-main SLB, the remaining steam generator is available for core decay heat dissipation
 
by venting steam to the atmosphere through MSSVs and ADVs. 
 
The AFW System supplies the necessary makeup to the steam
 
generator. Venting continues until the reactor coolant Secondary Specific Activity B 3.7.14 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.7.14-2 Revision 41 temperature and pressure have decreased sufficiently for the SDC System to complete the cooldown.
 
Other accidents or transients, such as a steam generator tube rupture, a seized rotor event, and a control element assembly ejection event, involve a partial release of the secondary activity via steam release to the atmosphere via the ADVs and MSSVs. These releases contribute to the offsite and Control Room doses listed in Reference 1, Section 14. These accident analyses show that the radiological consequences of a DBA do not exceed the acceptance criteria given in References 1 and 2.
Secondary specific activity limits satisfy 10 CFR 50.36(c)(2)(ii), Criterion 2.
LCO As indicated in the Applicable Safety Analyses, the specific activity limit in the secondary coolant system of  0.10 &#xb5;Ci/gm DOSE EQUIVALENT I-131 limits the radiological consequences of a DBA to the acceptance criteria given in Reference 1.
 
Monitoring the specific activity of the secondary coolant ensures that when secondary specific activity limits are
 
exceeded, appropriate actions are taken in a timely manner
 
to place the unit in an operational MODE that would minimize the radiological consequences of a DBA.
APPLICABILITY In MODEs 1, 2, 3, and 4, the limits on secondary specific activity apply due to the potential for secondary steam
 
releases to the atmosphere.
 
In MODEs 5 and 6, the steam generators are not being used for heat removal. Both the RCS and steam generators are
 
depressurized, and primary to secondary LEAKAGE is minimal. 
 
Therefore, monitoring of secondary specific activity is not required.
ACTIONS A.1 and A.2  DOSE EQUIVALENT I-131 exceeding the allowable value in the secondary coolant, is an indication of a problem in the RCS,
 
and contributes to increased post-accident doses. If Secondary Specific Activity B 3.7.14 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.7.14-3 Revision 55  secondary specific activity cannot be restored to within limits in the associated Completion Time, the unit must be
 
placed in a MODE in which the LCO does not apply. To
 
achieve this status, the unit must be placed in at least
 
MODE 3 within 6 hours, and in MODE 5 within 36 hours. The
 
allowed Completion Times are reasonable, based on operating experience, to reach the required unit conditions from full power conditions in an orderly manner and without challenging unit systems.
SURVEILLANCE SR 3.7.14.1 REQUIREMENTS This SR ensures that the secondary specific activity is within the limits of the accident analysis. A gamma isotope
 
analysis of the secondary coolant, which determines DOSE
 
EQUIVALENT I-131, confirms the validity of the safety
 
analysis assumptions as to the source terms in post-accident
 
releases. It also serves to identify and trend any unusual
 
isotopic concentrations that might indicate changes in
 
reactor coolant activity or LEAKAGE. The Surveillance Frequency is controlled under the Surveillance Frequency Control Program.
 
REFERENCES 1. UFSAR, Chapter 14, "Safety Analysis"  2. Regulatory Guide 1.183, Alternative Radiological Source Terms for Evaluating Design Basis Accidents at Nuclear Power Reactors, July 2000
 
MFIVs B 3.7.15 B 3.7  PLANT SYSTEMS
 
B 3.7.15  Main Feedwater Isolation Valves (MFIVs)
 
BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.7.15-1 Revision 2 BACKGROUND The MFIVs isolate MFW flow to the secondary side of the steam generators following a HELB. The consequences of HELBs occurring in the main steam lines or in the MFW lines downstream of the MFIVs will be mitigated by their closure.
Closure of the MFIVs effectively terminates the addition of feedwater to an affected steam generator, limiting the mass
 
and energy release for SLBs /or feedwater line breaks (FWLBs) inside the Containment Structure upstream of the reverse flow check valve, and reducing the cooldown effects for SLBs.
 
The MFIVs isolate the non
-safety-related portions from the safety-related portion of the system. In the event of a secondary side pipe rupture inside the Containment Structure upstream of the reverse flow check valve, the valves limit the quantity of high energy fluid that enters the Containment Structure through the break.
One MFIV is located on each MFW line, outside, but close to, the Containment Structure
. The MFIVs are located so that AFW may be supplied to a steam generator following MFIV closure. The piping volume from the valve to the steam
 
generator must be accounted for in calculating mass and
 
energy releases.
 
The MFIVs close on receipt of a steam generator isolation signal generated by low steam generator pressure. The steam generator isolation signal also actuates the MSIVs to close.
The MFIVs may also be actuated manually. In addition
, the MFIVs reverse flow check valve inside the Containment Structure is available to isolate the feedwater line penetrating the Containment Structure
, and to ensure that the consequences of events do not exceed the capacity of the Containment Cooling S ystem. A description of the MFIVs operation on receipt of an steam generator isolation signal is found in Reference 1
.
MFIVs B 3.7.15 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.7.15-2 Revision 13 APPLICABLE The design basis of the MFIVs is established by the analysis SAFETY ANALYSES for the large SLB. It is also influenced by the accident analysis for the large FWLB.
Failure of an MFIV to close following an SLB or FWLB can result in additional mass and energy to the steam generator's contributing to cooldown. This failure also results in additional mass and energy releases following an
 
SLB or FWLB event.
The MFIVs satisfy 10 CFR 50.36(c)(2)(ii), Criterion 3.
LCO This LCO ensures that the MFIVs will isolate MFW flow to the steam generators. Following an FWLB or SLB, these valves
 
will also isolate the non-safety-related portions from the
 
safety-related portions of the system. This LCO requires
 
that one MFIV in each feedwater line be OPERABLE. The MFIVs
 
are considered OPERABLE when the isolation times are within
 
limits, and are closed on an isolation actuation signal.
 
Failure to meet the LCO requirements can result in additional mass and energy being released to the Containment
 
Structure following an SLB or FWLB inside the Containment
 
Structure. Failure to meet the LCO can also add additional
 
mass and energy to the steam generators contributing to cooldown.
APPLICABILITY The MFIVs must be OPERABLE whenever there is significant mass and energy in the RCS and steam generators.
 
In MODEs 1, 2, and 3, the MFIVs are required to be OPERABLE in order to limit the amount of available fluid that could
 
be added to the Containment Structure in the case of a
 
secondary system pipe break inside the Containment
 
Structure.
In MODEs 4, 5, and 6, steam generator energy is low.
 
MFIVs B 3.7.15 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.7.15-3 Revision 14 ACTIONS The ACTIONS table is modified by a Note indicating that separate Condition entry is allowed for each valve.
 
A.1  With one MFIV inoperable, action must be taken to restore the valve to OPERABLE status within 72 hours.
The 72 hour Completion Time takes into account the isolation capability afforded by the MFW regulating valves, and
 
tripping of the MFW pumps, and the low probability of an
 
event occurring during this time period that would require
 
isolation of the MFW flow paths.
 
B.1 and B.2 If the MFIVs cannot be restored to OPERABLE status in the associated Completion Time, the unit must be placed in a
 
MODE in which the LCO does not apply. To achieve this
 
status, the unit must be placed in at least MODE 3 within
 
6 hours, and in MODE 4 within 12 hours. The allowed
 
Completion Times are reasonable, based on operating
 
experience, to reach the required unit conditions from full
 
power conditions in an orderly manner and without challenging unit systems.
SURVEILLANCE SR 3.7.15.1 REQUIREMENTS This SR ensures the closure time for each MFIV is  65 seconds by manual isolation. The MFIV closure time is assumed in the accident and containment analyses.
The Frequency is in accordance with the Inservice Testing Program. The MFIVs are tested during each refueling outage
 
in accordance with Reference 2, and sometimes during other
 
cold shutdown periods. The Frequency demonstrates the valve
 
closure time at least once per refueling cycle. Operating
 
experience has shown that these components usually pass the surveillance test when performed.
 
MFIVs B 3.7.15 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.7.15-4 Revision 38 REFERENCES 1. UFSAR, Section 14.4.2, "Sequence of Events"  2. ASME Code for Operation and Maintenance of Nuclear Power Plants
 
SFP Boron Concentration B 3.7.16 B 3.7  PLANT SYSTEMS
 
B 3.7.16  Spent Fuel Pool (SFP) Boron Concentration
 
BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.7.16-1 Revision 23 BACKGROUND  Fuel assemblies are stored in the spent fuel racks in accordance with criteria based on 10 CFR 50.68. If credit is taken for soluble boron, the k-effective of the spent
 
fuel storage racks loaded with fuel of the maximum fuel assembly reactivity must not exceed 0.95, at a 95%
probability, 95% confidence level, if flooded with borated
 
water, and the k-effective must remain below 1.0
 
(subcritical) at a 95% probability, 95% confidence level, if
 
flooded with unborated water. In addition, the maximum
 
nominal U-235 enrichment of the fresh fuel assemblies is limited to 5.0 weight percent.
APPLICABLE The criticality analyses were done such that the criteria of SAFETY ANALYSES 10 CFR 50.68 are met. Boron dilution events are credible, postulated accidents, when credit for soluble boron is
 
taken. The minimum SFP boron concentration in this
 
Technical Specification supports the initial boron concentration assumption in the dilution calculations.
 
For other non-dilution accident scenarios, the double contingency principle of ANSI N 16.1-1975 requires two
 
unlikely, independent concurrent events to produce a
 
criticality accident and thus allows credit for the nominal
 
soluble boron concentration, as defined in LCO 3.7.16.
The concentration of dissolved boron in the SFPs satisfies Criterion 2 of 10 CFR 50.36(c)(2)(ii).
 
LCO The specified concentration of dissolved boron in the SFP preserves the assumptions used in the analyses of the
 
potential accident scenarios described above. This
 
concentration of dissolved boron is the minimum required concentration for fuel assembly storage and movement within the SFPs.  


The 24 hour Completion Time is reasonable based on the determination that the mitigating actions will ensure protection of the CRE occupants within analyzed limits while limiting the probability that CRE occupants will have to implement protective measures that may adversely affect their ability to control the reactor and maintain it in a safe shutdown condition in the event of a DBA. In addition, the 90 day Completion Time is a reasonable time to diagnose, plan, and possibly repair and test most problems with the CRE boundary.
E.1  With one CREVS train inoperable for reasons other than Conditions A, B, C, or D in MODEs 1, 2, 3, or 4, action must be taken to restore OPERABLE status within seven days. In this Condition, the remaining OPERABLE CREVS subsystem is adequate to perform CRE occupant protection function.
However, the overall reliability is reduced because a failure in the OPERABLE CREVS train could result in loss of CREVS function. The seven day Completion Time is based on the low probability of a DBA occurring during this time period, and the ability of the remaining train to provide the required capability.
CREVS B 3.7.8 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.7.8-8 Revision 52  F.1, F.2, and F.3 If both CREVS trains are inoperable in MODE 1, 2, 3, or 4 for reasons other than an inoperable Control Room boundary (i.e., Condition D), at least one CREVS train must be returned to OPERABLE status within 24 hours. The Condition is modified by a Note stating it is not applicable if the second CREVS train is intentionally declared inoperable. The Condition does not apply to voluntary removal of redundant systems or components from service. The Condition is only applicable if one train is inoperable for any reason and the second train is discovered to be inoperable, or if both trains are discovered to be inoperable at the same time. During the period that the CREVS trains are inoperable, action must be initiated to implement mitigating actions to lessen the effect on CRE occupants from potential hazards while both trains of CREVS are inoperable. In the event of a DBA, the mitigating actions will reduce the consequences of radiological exposures to the CRE occupants. Specification 3.4.16, RCS Specific Activity, allows limited operation with the RCS activity significantly greater than the LCO limit. This presents a risk to the plant operator during an accident when all the CREVS trains are inoperable. Therefore, it must be verified within one hour that LCO 3.4.16 is met. This Required Action does not require additional RCS sampling beyond that normally required by LCO 3.4.16. At least one CREVS train must be returned to OPERABLE status within 24 hours. The Completion Time is based on Reference 3 which demonstrated that the 24 hour Completion Time is acceptable based on the infrequent use of the Required Actions and the small incremental effect on plant risk.
G.1  Action G provides the actions to be taken when the Required Action and associated Completion Time of Condition B cannot be met or with one or more CREVS trains inoperable due to an inoperable CRE boundary. It requires the immediate suspension of movement of irradiated fuel assemblies. This places the unit in a condition that minimizes the accident risk. This does not preclude the movement of fuel CREVS B 3.7.8 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.7.8-9 Revision 55  assemblies to a safe position. Since only one CREVS train must be OPERABLE for movement of irradiated fuel assemblies, the Required Action is applicable only to the required CREVS train.
H.1  If both CREVS trains are inoperable for reasons other than Conditions A, B, C, or D, or if one or more ducts have two outside air intake isolation valves inoperable, or if two exhaust to atmosphere isolation valves are inoperable during movement of irradiated fuel assemblies, the CREVS may not be capable of performing the intended function and the unit is in a condition outside the accident analyses. Therefore, movement of irradiated fuel must be suspended immediately.
This does not preclude the movement of fuel assemblies to a safe condition. I.1 and I.2  If the inoperable CREVs or Control Room boundary cannot be restored to OPERABLE status within the associated Completion Time in MODE 1, 2, 3, or 4, the unit must be placed in a mode that minimizes the accident risk. To achieve this status the unit must be placed in at least MODE 3 within six hours and in MODE 5 within 36 hours. The allowed Completion Times are reasonable, based on operating experience, to reach the required unit conditions from full power conditions in an orderly manner and without challenging unit systems. SURVEILLANCE SR 3.7.8.1 REQUIREMENTS Standby systems should be checked periodically to ensure that they function properly. Since the environment and normal operating conditions on this system are not severe, testing each required CREVS filter train once every month provides an adequate check on this system.
The Surveillance Frequency is controlled under the Surveillance Frequency Control Program.
CREVS B 3.7.8 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.7.8-10 Revision 55  SR 3.7.8.2  This SR verifies that the required CREVS testing is performed in accordance with the Ventilation Filter Testing Program (VFTP). The CREVS filter tests are in accordance with portions of Reference 4. The VFTP includes testing HEPA filter performance, charcoal adsorber efficiency, minimum system flow rate, and the physical properties of the activated charcoal (general use and following specific operations). Specific test Frequencies and additional information are discussed in detail in the VFTP. SR 3.7.8.3  This SR verifies each CREVS train starts and operates on an actual or simulated actuation signal (CRRS). The Surveillance Frequency is controlled under the Surveillance Frequency Control Program.
SR 3.7.8.4  This SR verifies the OPERABILITY of the CRE boundary by testing for unfiltered air inleakage past the CRE boundary and into the CRE. The details of the testing are specified in the Control Room Envelope Habitability Program.
The CRE is considered habitable when the radiological dose to the CRE occupants calculated in the licensing basis analysis of DBA consequences is no more than 5 rem TEDE and the CRE occupants are protected from hazardous chemicals and smoke. This SR verifies that the unfiltered air inleakage into the CRE is no greater than the flow rate assumed in the licensing basis analysis of DBA consequences. When unfiltered air inleakage is greater than the assumed flow rate, Condition E must be entered. Options for restoring the CRE boundary to OPERABLE status include changing the licensing basis DBA consequences analysis, repairing the CRE boundary, or a combination of these actions. Depending upon the nature of the problem and the corrective action, a full scope inleakage test may not be necessary to establish that the CRE boundary has been restored to OPERABLE status.
CREVS B 3.7.8 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.7.8-11 Revision 52 REFERENCES 1. UFSAR  2. Regulatory Guide 1.196, Revision 0, "Control Room Habitability at Light-Water Nuclear Power Reactors," May 2003  3. WCAP-16125-NP-A, Justification for Risk-Informed Modifications to Selected Technical Specifications for Conditions Leading to Exigent Plant Shutdown, Revision 2, August 2010  4. Regulatory Guide 1.52, Revision 2, "Design, Testing, and Maintenance Criteria for Post Accident Engineered-Safety-Feature Atmosphere Cleanup System Air Filtration and Adsorption Units of Light-Water-Cooled Nuclear Power Plants," March 1978 CRETS B 3.7.9 B 3.7  PLANT SYSTEMS B 3.7.9  Control Room Emergency Temperature System (CRETS)
BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.7.9-1 Revision 2 BACKGROUND The CRETS provides temperature control for the Control Room following isolation of the Control Room. The CRETS is a shared system which is supported by the CREVS, since the CREVS must be operating in the emergency recirculation mode for CRETS to perform its safety function.
The CRETS consists of two independent, redundant trains that provide cooling of recirculated Control Room air. Each train consists of cooling coils, instrumentation, and controls to provide for Control Room temperature control. The CRETS is a subsystem providing air temperature control for the Control Room.
The CRETS is an emergency system, parts of which may also operate during normal unit operations in the standby mode of operation. A single train will provide the required temperature control to maintain the Control Room below 104&deg;F. The CRETS operation to maintain the Control Room temperature is discussed in Reference 1.
APPLICABLE The design basis of the CRETS is to maintain temperature SAFETY ANALYSES of the Control Room environment throughout 30 days of continuous occupancy.
The CRETS components are arranged in redundant safety-related trains. During emergency operation, the CRETS maintains the temperature below 104&deg;F. A single active failure of a component of the CRETS, assuming a loss of offsite power, does not impair the ability of the system to perform its design function. Redundant detectors and controls are provided for Control Room temperature control. The CRETS is designed in accordance with Seismic Category I requirements. The CRETS is capable of removing sensible and latent heat loads from the Control Room, considering equipment heat loads and personnel occupancy requirements, to ensure equipment OPERABILITY. The CRETS satisfies 10 CFR 50.36(c)(2)(ii), Criterion 3.
CRETS B 3.7.9 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.7.9-2 Revision 31 LCO Two independent and redundant trains of the CRETS are required to be OPERABLE to ensure that at least one is available, assuming a single failure disables the other train following isolation of the Control Room. Total system failure could result in the equipment operating temperature exceeding limits in the event of an accident requiring isolation of the Control Room.
The CRETS is considered OPERABLE when the individual components that are necessary to maintain the Control Room temperature are OPERABLE. The required components include the cooling coils and associated temperature control instrumentation. In addition, the CRETS must be OPERABLE to the extent that air circulation can be maintained.
For MODEs 1, 2, 3, and 4, redundancy is required and both trains must be OPERABLE. The LCO is modified by a Note which indicates that only one CRETS train is required to be OPERABLE for the movement of irradiated fuel assemblies. Therefore, redundancy is not required for movement of irradiated fuel assemblies and only one CRETS train is required to be OPERABLE. APPLICABILITY In MODEs 1, 2, 3, and 4, and during movement of irradiated fuel assemblies, the CRETS must be OPERABLE to ensure that the Control Room temperature will not exceed equipment OPERABILITY requirements following isolation of the Control Room. ACTIONS A.1  With one CRETS train inoperable in MODEs 1, 2, 3, or 4, action must be taken to restore OPERABLE status within 30 days. In this Condition, the remaining OPERABLE CRETS train is adequate to maintain the Control Room temperature within limits. The 30 day Completion Time is reasonable, based on the low probability of an event occurring requiring Control Room isolation, consideration that the remaining train can provide the required capabilities, and the alternate safety or non-safety-related cooling means that are available.
CRETS B 3.7.9 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.7.9-3 Revision 55  B.1 and B.2  If the Required Actions and associated Completion Times of Condition A are not met in MODEs 1, 2, 3, or 4, the unit must be placed in a MODE that minimizes the accident risk.
To achieve this status, the unit must be placed in at least MODE 3 within 6 hours, and in MODE 5 within 36 hours. The allowed Completion Times are reasonable, based on operating experience, to reach the required unit conditions from full power conditions in an orderly manner and without challenging unit systems.
C.1  If both CRETS trains are inoperable in MODEs 1, 2, 3, or 4, or during movement of irradiated fuel assemblies, the CRETS may not be capable of performing the intended function and the unit is in a condition outside the accident analysis.
Therefore, LCO 3.0.3 must be entered immediately and movement of irradiated fuel must be suspended immediately.
This does not preclude the movement of fuel assemblies to a safe condition. SURVEILLANCE SR 3.7.9.1 REQUIREMENTS This SR verifies each required CRETS train has the capability to maintain Control Room temperature  104&deg;F for  12 hours in the recirculation mode. During this test, the backup Control Room air conditioner is to be de-energized. This SR consists of a combination of testing.
The Surveillance Frequency is controlled under the Surveillance Frequency Control Program.
REFERENCES 1. UFSAR, Section 9.8.2.3, "Auxiliary Building Ventilating Systems" SFPEVS B 3.7.11 B 3.7  PLANT SYSTEMS B 3.7.11  Spent Fuel Pool Exhaust Ventilation System (SFPEVS)
BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.7.11-1 Revision 41 BACKGROUND The SFPEVS exhausts airborne radioactive particulates and gases from the area of the fuel pool into the plant ventilation stack following a fuel handling accident involving recently irradiated fuel. The SFPEVS consists of two independent, redundant exhaust fans. Ductwork, valves or dampers, and instrumentation also form part of the system. The SFPEVS is supplied power by one non-safety-related power supply.
The SFPEVS is operated during normal unit operations. When movement of the air is required (i.e., during movement of recently irradiated fuel assemblies in the Auxiliary Building), normal air discharges from the fuel handling area in the Auxiliary Building.
The SFPEVS is discussed in Reference 1, Sections 9.8.2.3 and 14.18, because it may be used for normal, as well as post-accident ventilation. APPLICABLE The SFPEVS is designed to mitigate the consequences of a SAFETY ANALYSES fuel handling accident involving handling recently irradiated fuel (i.e., fuel that has occupied part of a critical reactor core within the previous 55 days), in which all rods in the fuel assembly are assumed to be damaged.
The analysis of the fuel handling accident is given in Reference 1, Section 14.18. The DBA analysis of the fuel handling accident assumes that the SFPEVS is functional and exhausts airborne radioactive particulates and gases from the fuel pool area into the plant ventilation stack. The analysis follows the guidance provided in Reference 2. The SFPEVS satisfies 10 CFR 50.36(c)(2)(ii), Criterion 3. LCO Two exhaust fans and other equipment listed in the Background Section are required to be OPERABLE and in operation.
The SFPEVS is considered OPERABLE when the individual components necessary to direct exhaust into the ventilation SFPEVS B 3.7.11 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.7.11-2 Revision 41 stack are OPERABLE. The SFPEVS is considered OPERABLE when its associated:  a. Fans are OPERABLE; and  b. Ductwork, valves, and dampers are OPERABLE, and air circulation can be maintained. The SFPEVS is considered in operation when an OPERABLE exhaust fan is in operation. APPLICABILITY During movement of recently irradiated fuel assemblies in the Auxiliary Building, the SFPEVS is required to be OPERABLE and in operation to mitigate the consequences of a fuel handling accident involving handling recently irradiated fuel by minimizing the atmospheric dispersion to the Control Room. Due to radioactive decay, the SFPEVS is only required to mitigate fuel handling accidents involving handling recently irradiated fuel (i.e., fuel that has occupied part of a critical reactor core within the previous 55 days). ACTIONS A.1 and A.2  When one SFPEVS exhaust fan is inoperable, action must be taken to verify an OPERABLE SFPEVS train is in operation, or movement of recently irradiated fuel assemblies in the Auxiliary Building must be suspended. One OPERABLE SFPEVS train consists of one OPERABLE exhaust fan. This ensures the proper equipment is operating for the Applicable Safety Analysis.
B.1  When there is no OPERABLE SFPEVS train or there is no OPERABLE SFPEVS train in operation during movement of recently irradiated fuel assemblies in the Auxiliary Building, action must be taken to place the unit in a condition in which the LCO does not apply. This Action involves immediately suspending movement of recently irradiated fuel assemblies in the Auxiliary Building. This does not preclude the movement of fuel to a safe position.
SFPEVS B 3.7.11 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.7.11-3 Revision 55 SURVEILLANCE SR 3.7.11.1 REQUIREMENTS  The SR requires verification that the SFPEVS is in operation. Verification includes verifying that one exhaust fan is operating and discharging into the ventilation stack.
The Surveillance Frequency is controlled under the Surveillance Frequency Control Program.
SR 3.7.11.2 Deleted.
SR 3.7.11.3  This SR verifies the integrity of the spent fuel storage pool area. The ability of the spent fuel storage pool area to maintain negative pressure with respect to potentially uncontaminated adjacent areas is periodically tested to verify proper function of the SFPEVS. During operation, the spent fuel storage pool area is designed to maintain a slight negative pressure in the spent fuel storage pool area, with respect to adjacent areas, to ensure that exhausted air is directed to the ventilation stack.
The Surveillance Frequency is controlled under the Surveillance Frequency Control Program.
REFERENCES 1. UFSAR  2. Regulatory Guide 1.183, Alternative Radiological Source Terms for Evaluating Design Basis Accidents at Nuclear Power Reactors, July 2000 PREVS B 3.7.12 B 3.7  PLANT SYSTEMS B 3.7.12  Penetration Room Exhaust Ventilation System (PREVS)
BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.7.12-1 Revision 52 BACKGROUND The PREVS filters air from the penetration room.
The PREVS consists of two independent and redundant trains. Each train consists of a prefilter, a HEPA filter, an activated charcoal adsorber section for removal of gaseous activity (principally iodines), and a fan. Ductwork, valves or dampers, and instrumentation also form part of the system. The system initiates filtered ventilation following receipt of a containment isolation actuation signal.
The PREVS is a standby system, which may also operate during normal unit operations. During emergency operations, the PREVS dampers are realigned, and fans are started to initiate filtration. Upon receipt of the actuating Engineered Safety Feature Actuation System signal(s), normal air discharges from the penetration room, and the stream of ventilation air discharges through the system filter trains.
The prefilters remove any large particles in the air to prevent excessive loading of the HEPA filters and charcoal adsorbers.
The PREVS is discussed in Reference 1, Section 6.6.2, as it may be used for normal, as well as post-accident, atmospheric cleanup functions. APPLICABLE The design basis of the PREVS is established by the Maximum SAFETY ANALYSES Hypothetical Accident. The system is credited with filtering the radioactive material released through the containment vent when the line is open. Also commensurate with the guidance in Reference 2, a conservative bypass fraction from the Containment to the penetration rooms is assumed. Following a LOCA, the containment isolation signal will start both of the fans associated with the PREVS, filtering the exhaust through the HEPA and charcoal filters, and directing the exhaust into the ventilation stack. The analysis of the effects and consequences of a Maximum Hypothetical Accident are presented in Reference 1, Section 14.24 and follows the guidance presented in Reference 3.
PREVS B 3.7.12 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.7.12-2 Revision 41  As a layer of defense, the Penetration Room Exhaust Ventilation System also provides filtered ventilation of radioactive materials leaking from ECCS equipment within the penetration room following an accident, however, credit for this feature was not assumed in the accident analysis (Reference 1, Section 14.24).
The PREVS satisfies 10 CFR 50.36(c)(2)(ii), Criterion 3. LCO Two independent and redundant trains of the PREVS are required to be OPERABLE to ensure that at least one train is available, assuming there is a single failure disabling the other train coincident with a loss of offsite power.
The PREVS is considered OPERABLE when the individual components necessary to control radioactive releases are OPERABLE in both trains. A PREVS train is considered OPERABLE when its associated:  a. Fan is OPERABLE;
: b. High efficiency particulate air filter and charcoal adsorber are not excessively restricting flow, and are capable of performing the filtration functions; and  c. Ductwork, valves, and dampers are OPERABLE, and circulation can be maintained.
APPLICABILITY In MODEs 1, 2, and 3, the PREVS is required to be OPERABLE to mitigate the potential radioactive material release from a Maximum Hypothetical Accident.
In MODEs 4, 5, and 6, the PREVS is not required to be OPERABLE, since the RCS temperature and pressure are low and there is insufficient energy to result in the conditions assumed in the accident analysis. ACTIONS A.1  With one PREVS train inoperable, action must be taken to restore OPERABLE status within seven days. During this time period, the remaining OPERABLE train is adequate to perform the PREVS function. The seven day Completion Time is reasonable based on the low probability of a DBA occurring PREVS B 3.7.12 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.7.12-3 Revision 52  during this time period, and the consideration that the remaining train can provide the required capability. B.1 and B.2 With two PREVS trains inoperable, action must be taken to restore at least one PREVS train to OPERABLE status within 24 hours. The Condition is modified by a Note stating it is not applicable if the second PREVS train is intentionally declared inoperable. The Condition does not apply to voluntary removal of redundant systems or components from service. The Condition is only applicable if one train is inoperable for any reason and the second train is discovered to be inoperable, or if both trains are discovered to be inoperable at the same time. In addition, at least one train of containment spray must be verified to be OPERABLE within one hour. In the event of an accident, containment spray reduces the potential radioactive release from the containment, which reduces the consequences of the inoperable PREVS trains. The Completion Time is based on Reference 4 which demonstrated that the 24 hour Completion Time is acceptable based on the infrequent use of the Required Actions and the small incremental effect on plant risk.
C.1 and C.2  If the inoperable train cannot be restored to OPERABLE status within the associated Completion Time, the unit must be placed in a MODE in which the LCO does not apply. To achieve this status, the unit must be placed in at least MODE 3 within 6 hours, and in MODE 4 within 12 hours. The allowed Completion Times are reasonable, based on operating experience, to reach the required unit conditions from full power conditions in an orderly manner and without challenging unit systems. SURVEILLANCE SR 3.7.12.1 REQUIREMENTS Standby systems should be checked periodically to ensure that they function properly. As the environment and normal operating conditions on this system are not severe, testing each train once every month provides an adequate check on this system.
PREVS B 3.7.12 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.7.12-4 Revision 55  The test is performed by initiating the system from the Control Room, ensuring flow through the HEPA filter and charcoal adsorber train, and verifying this system operates for  15 minutes. The Surveillance Frequency is controlled under the Surveillance Frequency Control Program. SR 3.7.12.2  This SR verifies the performance of PREVS filter testing in accordance with the VFTP. The PREVS filter tests are in accordance with portions of Reference 5. The VFTP includes testing the performance of the HEPA filter, charcoal adsorber efficiency, minimum system flow rate, and the physical properties of the activated charcoal (general use and following specific operations). Specific test frequencies and additional information are discussed in detail in the VFTP.
SR 3.7.12.3  This SR verifies that each PREVS train starts and operates on an actual or simulated actuation signal (Containment Isolation Signal). The Surveillance Frequency is controlled under the Surveillance Frequency Control Program.
REFERENCES 1. UFSAR  2. Regulatory Guide 1.194, Atmospheric Relative Concentrations for Control Room Radiological Habitability Assessments at Nuclear Power Plants, June 2003  3. Regulatory Guide 1.183, Alternative Radiological Source Terms for Evaluating Design Basis Accidents at Nuclear Power Reactors, July 2000  4. WCAP-16125-NP-A, Justification for Risk-Informed Modifications to Selected Technical Specifications for Conditions Leading to Exigent Plant Shutdown, Revision 2, August 2010 PREVS B 3.7.12 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.7.12-5 Revision 55  5. Regulatory Guide 1.52, Revision 2, "Design, Testing, and Maintenance Criteria for Post Accident Engineered-Safety-Feature Atmosphere Cleanup System Air Filtration and Adsorption Units of Light-Water-Cooled Nuclear Power Plants," March 1978 SFP Water Level B 3.7.13 B 3.7  PLANT SYSTEMS B 3.7.13  Spent Fuel Pool (SFP) Water Level BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.7.13-1 Revision 41 BACKGROUND The minimum water level in the SFP meets the assumptions of iodine decontamination factors following a fuel handling accident. The specified water level shields and minimizes the general area dose when the storage racks are filled to their maximum capacity. The water also provides shielding during the movement of spent fuel.
A general description of the SFP design is given in Reference 1, Section 9.7.2, and the SFP Cooling and Cleanup System is given in Reference 1, Section 9.4.1. The assumptions of the fuel handling accident are given in Reference 1, Section 14.18. APPLICABLE Per Reference 2, the Fuel Handling Accident (FHA) analysis  SAFETY ANALYSES may assume a total iodine decontamination factor of 200 based on a minimum water depth of 23 feet. The minimum water level requirement ensures that sufficient water depth is available to remove 99.5% of gap activity, which is comprised of 16% I-131 and 10% of all other iodine isotopes released from the rupture of an irradiated fuel assembly. The Technical Specifications requirement of 21.5 feet of water above fuel assemblies seated in the SFP storage racks is sufficient to preserve the required 23 feet of water because an FHA was assumed to occur as a fuel assembly strikes the bottom of the SFP.
When assemblies are placed on rack spacers with their upper end fittings removed, an FHA caused by a dropped heavy object would result in a lower decontamination factor based on reduced water coverage. A revised decontamination factor of 120 for an FHA during reconstitution or inspection with 20.4 feet of water between the top of the pin and the surface of the water was computed for an assembly placed on a 20.5 inch rack spacer with its upper end fitting removed. Note that this is very conservative, since normal level control will result in at least 21.5 feet of water above exposed fuel pins. This results in a 99.17% removal rate.
SFP Water Level B 3.7.13 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.7.13-2 Revision 55  The SFP water level satisfies 10 CFR 50.36(c)(2)(ii), Criteria 2 and 3. LCO The specified water level preserves the assumptions of the fuel handling accident analysis (Reference 1, Section 14.18). As such, it is the minimum required for fuel storage, reconstitution, and movement within the fuel storage pool. APPLICABILITY This LCO applies during movement of irradiated fuel assemblies in the SFP since the potential for a release of fission products exists. ACTIONS A.1  Required Action A.1 is modified by a Note indicating that LCO 3.0.3 does not apply.
When the initial conditions for an accident cannot be met, steps should be taken to preclude the accident from occurring. When the SFP water level is lower than the required level, the movement of irradiated fuel assemblies in the SFP is immediately suspended. This effectively precludes a spent fuel handling accident from occurring.
This does not preclude moving a fuel assembly to a safe position. If moving irradiated fuel assemblies while in MODEs 5 or 6, LCO 3.0.3 would not specify any action. If moving irradiated fuel assemblies while in MODEs 1, 2, 3, and 4, the fuel movement is independent of reactor operations.
Therefore, in either case, inability to suspend movement of irradiated fuel assemblies is not sufficient reason to require a reactor shutdown. SURVEILLANCE SR 3.7.13.1 REQUIREMENTS This SR verifies sufficient SFP water is available in the event of a fuel handling accident. The water level in the SFP must be checked periodically. The Surveillance Frequency is controlled under the Surveillance Frequency Control Program.
SFP Water Level B 3.7.13 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.7.13-3 Revision 41  During refueling operations, the level in the SFP is normally at equilibrium with that of the refueling canal. REFERENCES 1. UFSAR  2. Regulatory Guide 1.183, Alternative Radiological Source Terms for Evaluating Design Basis Accidents at Nuclear Power Reactors, July 2000 Secondary Specific Activity B 3.7.14 B 3.7  PLANT SYSTEMS B 3.7.14  Secondary Specific Activity BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.7.14-1 Revision 41 BACKGROUND Activity in the secondary coolant results from steam generator tube outleakage from the RCS. Under steady state conditions, the activity is primarily iodines with relatively short half lives, and thus is an indication of current conditions. During transients, DOSE EQUIVALENT I-131 spikes have been observed as well as increased releases of some noble gases. Other fission product isotopes, as well as activated corrosion products in lesser amounts, may also be found in the secondary coolant.
A limit on secondary coolant specific activity during power operation minimizes releases to the environment because of normal operation, anticipated operational occurrences, and accidents.
This limit is lower than the activity value that might be expected from a 100 gallons per day tube leak (LCO 3.4.13) of primary coolant at the limit of 0.5 &#xb5;Ci/gm (LCO 3.4.15). The main SLB is assumed to result in the release of the noble gas and iodine activity contained in the steam generator inventory, the feedwater, and reactor coolant LEAKAGE via flashing directly to the environment through the main steam gooseneck.
APPLICABLE The accident analysis of the main SLB, as discussed in SAFETY ANALYSES Reference 1, assumes the initial secondary coolant specific activity to have a radioactive isotope concentration of 0.10 &#xb5;Ci/gm DOSE EQUIVALENT I-131. This secondary activity, together with the Technical Specification primary system activity, and failed fuel activity, is used in the analysis for determining the radiological consequences of the postulated accident. The accident analysis shows that the radiological consequences of a main SLB do not exceed the acceptance criteria given in References 1 and 2.
With the loss of offsite power post-main SLB, the remaining steam generator is available for core decay heat dissipation by venting steam to the atmosphere through MSSVs and ADVs.
The AFW System supplies the necessary makeup to the steam generator. Venting continues until the reactor coolant Secondary Specific Activity B 3.7.14 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.7.14-2 Revision 41 temperature and pressure have decreased sufficiently for the SDC System to complete the cooldown.
Other accidents or transients, such as a steam generator tube rupture, a seized rotor event, and a control element assembly ejection event, involve a partial release of the secondary activity via steam release to the atmosphere via the ADVs and MSSVs. These releases contribute to the offsite and Control Room doses listed in Reference 1, Section 14. These accident analyses show that the radiological consequences of a DBA do not exceed the acceptance criteria given in References 1 and 2. Secondary specific activity limits satisfy 10 CFR 50.36(c)(2)(ii), Criterion 2. LCO As indicated in the Applicable Safety Analyses, the specific activity limit in the secondary coolant system of  0.10 &#xb5;Ci/gm DOSE EQUIVALENT I-131 limits the radiological consequences of a DBA to the acceptance criteria given in Reference 1.
Monitoring the specific activity of the secondary coolant ensures that when secondary specific activity limits are exceeded, appropriate actions are taken in a timely manner to place the unit in an operational MODE that would minimize the radiological consequences of a DBA. APPLICABILITY In MODEs 1, 2, 3, and 4, the limits on secondary specific activity apply due to the potential for secondary steam releases to the atmosphere.
In MODEs 5 and 6, the steam generators are not being used for heat removal. Both the RCS and steam generators are depressurized, and primary to secondary LEAKAGE is minimal.
Therefore, monitoring of secondary specific activity is not required. ACTIONS A.1 and A.2  DOSE EQUIVALENT I-131 exceeding the allowable value in the secondary coolant, is an indication of a problem in the RCS, and contributes to increased post-accident doses. If Secondary Specific Activity B 3.7.14 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.7.14-3 Revision 55  secondary specific activity cannot be restored to within limits in the associated Completion Time, the unit must be placed in a MODE in which the LCO does not apply. To achieve this status, the unit must be placed in at least MODE 3 within 6 hours, and in MODE 5 within 36 hours. The allowed Completion Times are reasonable, based on operating experience, to reach the required unit conditions from full power conditions in an orderly manner and without challenging unit systems. SURVEILLANCE SR 3.7.14.1 REQUIREMENTS This SR ensures that the secondary specific activity is within the limits of the accident analysis. A gamma isotope analysis of the secondary coolant, which determines DOSE EQUIVALENT I-131, confirms the validity of the safety analysis assumptions as to the source terms in post-accident releases. It also serves to identify and trend any unusual isotopic concentrations that might indicate changes in reactor coolant activity or LEAKAGE. The Surveillance Frequency is controlled under the Surveillance Frequency Control Program.
REFERENCES 1. UFSAR, Chapter 14, "Safety Analysis"  2. Regulatory Guide 1.183, Alternative Radiological Source Terms for Evaluating Design Basis Accidents at Nuclear Power Reactors, July 2000 MFIVs B 3.7.15 B 3.7  PLANT SYSTEMS B 3.7.15  Main Feedwater Isolation Valves (MFIVs)
BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.7.15-1 Revision 2 BACKGROUND The MFIVs isolate MFW flow to the secondary side of the steam generators following a HELB. The consequences of HELBs occurring in the main steam lines or in the MFW lines downstream of the MFIVs will be mitigated by their closure. Closure of the MFIVs effectively terminates the addition of feedwater to an affected steam generator, limiting the mass and energy release for SLBs /or feedwater line breaks (FWLBs) inside the Containment Structure upstream of the reverse flow check valve, and reducing the cooldown effects for SLBs.
The MFIVs isolate the non-safety-related portions from the safety-related portion of the system. In the event of a secondary side pipe rupture inside the Containment Structure upstream of the reverse flow check valve, the valves limit the quantity of high energy fluid that enters the Containment Structure through the break. One MFIV is located on each MFW line, outside, but close to, the Containment Structure. The MFIVs are located so that AFW may be supplied to a steam generator following MFIV closure. The piping volume from the valve to the steam generator must be accounted for in calculating mass and energy releases.
The MFIVs close on receipt of a steam generator isolation signal generated by low steam generator pressure. The steam generator isolation signal also actuates the MSIVs to close. The MFIVs may also be actuated manually. In addition, the MFIVs reverse flow check valve inside the Containment Structure is available to isolate the feedwater line penetrating the Containment Structure, and to ensure that the consequences of events do not exceed the capacity of the Containment Cooling System. A description of the MFIVs operation on receipt of an steam generator isolation signal is found in Reference 1.
MFIVs B 3.7.15 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.7.15-2 Revision 13 APPLICABLE The design basis of the MFIVs is established by the analysis SAFETY ANALYSES for the large SLB. It is also influenced by the accident analysis for the large FWLB. Failure of an MFIV to close following an SLB or FWLB can result in additional mass and energy to the steam generator's contributing to cooldown. This failure also results in additional mass and energy releases following an SLB or FWLB event. The MFIVs satisfy 10 CFR 50.36(c)(2)(ii), Criterion 3. LCO This LCO ensures that the MFIVs will isolate MFW flow to the steam generators. Following an FWLB or SLB, these valves will also isolate the non-safety-related portions from the safety-related portions of the system. This LCO requires that one MFIV in each feedwater line be OPERABLE. The MFIVs are considered OPERABLE when the isolation times are within limits, and are closed on an isolation actuation signal.
Failure to meet the LCO requirements can result in additional mass and energy being released to the Containment Structure following an SLB or FWLB inside the Containment Structure. Failure to meet the LCO can also add additional mass and energy to the steam generators contributing to cooldown. APPLICABILITY The MFIVs must be OPERABLE whenever there is significant mass and energy in the RCS and steam generators.
In MODEs 1, 2, and 3, the MFIVs are required to be OPERABLE in order to limit the amount of available fluid that could be added to the Containment Structure in the case of a secondary system pipe break inside the Containment Structure. In MODEs 4, 5, and 6, steam generator energy is low.
MFIVs B 3.7.15 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.7.15-3 Revision 14 ACTIONS The ACTIONS table is modified by a Note indicating that separate Condition entry is allowed for each valve.
A.1  With one MFIV inoperable, action must be taken to restore the valve to OPERABLE status within 72 hours. The 72 hour Completion Time takes into account the isolation capability afforded by the MFW regulating valves, and tripping of the MFW pumps, and the low probability of an event occurring during this time period that would require isolation of the MFW flow paths.
B.1 and B.2  If the MFIVs cannot be restored to OPERABLE status in the associated Completion Time, the unit must be placed in a MODE in which the LCO does not apply. To achieve this status, the unit must be placed in at least MODE 3 within 6 hours, and in MODE 4 within 12 hours. The allowed Completion Times are reasonable, based on operating experience, to reach the required unit conditions from full power conditions in an orderly manner and without challenging unit systems. SURVEILLANCE SR 3.7.15.1 REQUIREMENTS This SR ensures the closure time for each MFIV is  65 seconds by manual isolation. The MFIV closure time is assumed in the accident and containment analyses. The Frequency is in accordance with the Inservice Testing Program. The MFIVs are tested during each refueling outage in accordance with Reference 2, and sometimes during other cold shutdown periods. The Frequency demonstrates the valve closure time at least once per refueling cycle. Operating experience has shown that these components usually pass the surveillance test when performed.
MFIVs B 3.7.15 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.7.15-4 Revision 38 REFERENCES 1. UFSAR, Section 14.4.2, "Sequence of Events"  2. ASME Code for Operation and Maintenance of Nuclear Power Plants SFP Boron Concentration B 3.7.16 B 3.7  PLANT SYSTEMS B 3.7.16  Spent Fuel Pool (SFP) Boron Concentration BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.7.16-1 Revision 23 BACKGROUND  Fuel assemblies are stored in the spent fuel racks in accordance with criteria based on 10 CFR 50.68. If credit is taken for soluble boron, the k-effective of the spent fuel storage racks loaded with fuel of the maximum fuel assembly reactivity must not exceed 0.95, at a 95% probability, 95% confidence level, if flooded with borated water, and the k-effective must remain below 1.0 (subcritical) at a 95% probability, 95% confidence level, if flooded with unborated water. In addition, the maximum nominal U-235 enrichment of the fresh fuel assemblies is limited to 5.0 weight percent. APPLICABLE The criticality analyses were done such that the criteria of SAFETY ANALYSES 10 CFR 50.68 are met. Boron dilution events are credible, postulated accidents, when credit for soluble boron is taken. The minimum SFP boron concentration in this Technical Specification supports the initial boron concentration assumption in the dilution calculations.
For other non-dilution accident scenarios, the double contingency principle of ANSI N 16.1-1975 requires two unlikely, independent concurrent events to produce a criticality accident and thus allows credit for the nominal soluble boron concentration, as defined in LCO 3.7.16. The concentration of dissolved boron in the SFPs satisfies Criterion 2 of 10 CFR 50.36(c)(2)(ii).
LCO The specified concentration of dissolved boron in the SFP preserves the assumptions used in the analyses of the potential accident scenarios described above. This concentration of dissolved boron is the minimum required concentration for fuel assembly storage and movement within the SFPs.
APPLICABILITY This LCO applies whenever fuel assemblies are stored in the SFPs.
APPLICABILITY This LCO applies whenever fuel assemblies are stored in the SFPs.
SFP Boron Concentration B 3.7.16 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.7.16-2 Revision 55 ACTIONS A.1 and A.2 The Required Actions are modified by a Note indicating that LCO 3.0.3 does not apply. If moving irradiated fuel assemblies while in MODE 5 or 6, LCO 3.0.3 would not specify any action. If moving irradiated fuel assemblies while in MODE 1, 2, 3, or 4, the fuel movement is independent of reactor operation. Therefore, inability to suspend movement of fuel assemblies is not a sufficient reason to require a reactor shutdown.  
SFP Boron Concentration B 3.7.16 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.7.16-2 Revision 55 ACTIONS A.1 and A.2 The Required Actions are modified by a Note indicating that LCO 3.0.3 does not apply. If moving irradiated fuel  
 
assemblies while in MODE 5 or 6, LCO 3.0.3 would not specify  
 
any action. If moving irradiated fuel assemblies while in  
 
MODE 1, 2, 3, or 4, the fuel movement is independent of  
 
reactor operation. Therefore, inability to suspend movement  
 
of fuel assemblies is not a sufficient reason to require a  
 
reactor shutdown.  
 
When the concentration of boron in the SFPs is less than
 
required, immediate action must be taken to preclude an
 
accident from happening or to mitigate the consequences of
 
an accident in progress. This is most efficiently achieved
 
by immediately suspending the movement of fuel assemblies.
This does not preclude the movement of fuel assemblies to a safe position. In addition, action must be immediately
 
initiated to restore boron concentration to within limits.
SURVEILLANCE SR 3.7.16.1 REQUIREMENTS  This SR verifies that the concentration of boron in the SFPs is within the required limit. As long as this SR is met,
 
the analyzed incidents are fully addressed. The Surveillance Frequency is controlled under the Surveillance Frequency Control Program.
REFERENCES None
 
SFP Storage B 3.7.17 B 3.7  PLANT SYSTEMS B 3.7.17  Spent Fuel Pool (SFP) Storage BASES  CALVERT CLIFFS - UNIT 2 B 3.7.17-1 Revision 23 BACKGROUND This Technical Specification applies to the Unit 2 SFP only.
The spent fuel storage facility was originally designed to store either new (non-irradiated) nuclear fuel assemblies or burned (irradiated) fuel assemblies in a vertical configuration underwater, assuming credit for Boraflex poison sheets but assuming no credit for soluble boron or burnup. The spent fuel storage cells are installed in parallel rows with center-to-center spacing of 10 3/32 inches and with Boraflex sheets between adjacent assemblies. This spacing was sufficient to maintain keff  0.95 for spent fuel of enrichments up to 4.52 wt% for standard fuel design and up to 4.30 wt% for Value Added Pellet (VAP) fuel design.
The burnup and enrichment requirements of LCO 3.7.17(a) ensures that the multiplication factor (keff) for the rack in the SFP is less than the 10 CFR 50.68 regulatory limit with the VAP fuel design, ranging in enrichment from 2.0 to 5.0 wt%, with burnup credit, with partial credit for soluble boron, but without Boraflex credit. The soluble boron credit will be limited to 350 ppm including all biases and uncertainties. For fuel assemblies which do not satisfy the burnup and enrichment requirements of LCO 3.7.17(a), the fuel assemblies may be stored in the Unit 2 SFP if surrounded on all four adjacent faces by empty rack cells or other non-reactive materials per LCO 3.7.17(b).
APPLICABLE The Unit 2 spent fuel storage facility is designed to  SAFETY ANALYSES conform to the requirements of 10 CFR 50.68 by use of adequate spacing, soluble boron credit, and burnup credit.
The SFP storage satisfies Criterion 2 of 10 CFR 50.36(c)(2)(ii).
LCO The restrictions on the placement of fuel assemblies within the Unit 2 SFP are in accordance with Figure 3.7.17-1 and ensure that the Unit 2 SFP meets the requirements of 10 CFR 50.68. The restrictions are consistent with the criticality safety analysis performed for the Unit 2 SFP. Fuel assemblies not meting the criteria of Figure 3.7.17-1 may be SFP Storage B 3.7.17 BASES  CALVERT CLIFFS - UNIT 2 B 3.7.17-2 Revision 23 stored in the Unit 2 SFP in a checkboard pattern in accordance with LCO 3.7.17(b).
APPLICABILITY This LCO applies whenever any fuel assembly is stored in the Unit 2 SFP.
ACTIONS A.1 Required Action A.1 is modified by a Note indicating that LCO 3.0.3 does not apply. If moving fuel assemblies while in MODE 5 or 6, LCO 3.0.3 would not specify any action. If moving fuel assemblies while in MODE 1, 2, 3, or 4, the fuel movement is independent of reactor operation. Therefore, in either case, inability to move fuel assemblies is not a sufficient reason to require a reactor shutdown.
When the configuration of fuel assemblies stored in Unit 2 SFP is not in accordance with Figure 3.7.17-1 or LCO 3.7.17(b), immediate action must be taken to make the necessary fuel assembly movement(s) to bring the fuel assembly configuration into compliance with Figure 3.7.17-1 or LCO 3.7.17(b).
SURVEILLANCE SR 3.7.17.1 REQUIREMENTS  This SR verifies by administrative means that the initial enrichment and burnup of the fuel assembly is in accordance with Figure 3.7.17-1 for LCO 3.7.17(a). This Surveillance Requirement does not address fuel assemblies stored in the Unit 2 SFP in accordance with LCO 3.7.17(b). This will ensure compliance with Specification 4.3.1.1.
REFERENCES None
 
ADVs B 3.7.18 B 3.7  PLANT SYSTEMS B 3.7.18  Atmospheric Dump Valves (ADVs)
BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.7.18-1 Revision 54 BACKGROUND The ADVs provide a safety grade method for cooling the unit to Shutdown Cooling (SDC) System entry conditions, should the preferred heat sink via the Turbine Bypass Valves to the condenser not be available, as discussed in the UFSAR, Section 10.3 (Reference 1). This is done in conjunction with the Auxiliary Feedwater System providing cooling water from the condensate storage tank (CST). The ADVs may also be used during a normal cooldown when steam pressure drops too low for maintenance of a vacuum in the condenser to permit use of the Turbine Bypass Valves.
Two ADV lines are provided, one per steam generator. Each ADV line consists of one ADV and an associated isolation valve. The ADVs are provided with upstream isolation valves to permit their being tested at power, if desired. The ADVs are equipped with manual hand wheels to open and close them.
Pneumatic controllers are used to operate the ADVs as the preferred method, but are not relied upon during an accident. A description of the ADVs is found in Reference 1. The ADVs are considered OPERABLE when the manual control is available for local manual operation.
APPLICABLE The design basis of the ADVs is established by the SAFETY ANALYSES capability to cool the unit to SDC System entry conditions.
The cooldown rate assumed in the accident analyses is obtainable by one or both steam generators. The design is adequate to cool the unit to SDC System entry conditions with only one ADV and one steam generator.
In the steam generator tube rupture accident analysis presented in the UFSAR, the ADVs are assumed to be used by the operator to cool down the unit to SDC System entry conditions because the accident is accompanied by a loss of offsite power. Prior to the operator action, the MSSVs are used to maintain steam generator pressure and temperature at the MSSV setpoint. The ADVs may be used for other accidents that are accompanied by a loss of offsite power. The limiting events are those that render one steam generator unavailable for RCS heat removal, with a coincident loss of offsite power. Typical initiating events falling into this ADVs B 3.7.18 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.7.18-2 Revision 54 category are a feedwater line break, and a SGTR event (limiting case).
The ADVs satisfy Criterion 3 of 10 CFR 50.36(c)(2)(ii).
LCO Two ADV lines are required to be OPERABLE to ensure that at least one ADV is OPERABLE to conduct a unit cooldown following an event in which one steam generator becomes unavailable. A closed isolation valve does not render its ADV line inoperable since operator action time to open the isolation valve is supported in the accident analysis.
Failure to meet the LCO can result in the inability to cool the unit to SDC System entry conditions following an event in which the condenser is unavailable for use with the Turbine Bypass Valves. An ADV is considered OPERABLE when it is capable of providing relief of the main steam flow, and is capable of fully opening and closing when required.
APPLICABILITY In MODES 1, 2, and 3, and in MODE 4, when steam generators are being relied upon for heat removal, the ADVs are required to be OPERABLE. In MODES 5 and 6, a SGTR is not a credible event.
ACTIONS A.1 With one required ADV line inoperable, action must be taken to restore the OPERABLE status within 48 hours. The 48 hour Completion Time takes into account the redundant capability afforded by the remaining OPERABLE ADV line, and a backup in the Turbine Bypass Valves and MSSVs.
B.1 With two required ADV lines inoperable, action must be taken to restore one of the ADV lines to OPERABLE status. As the isolation valve can be closed to isolate an ADV, some repairs may be possible with the unit at power. The 1 hour Completion Time is reasonable to repair inoperable ADV lines, based on the availability of the Turbine Bypass Valves and MSSVs, and the low probability of an event occurring during this period that requires the ADV lines.
ADVs B 3.7.18 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.7.18-3 Revision 55 C.1 and C.2 If the ADV lines cannot be restored to OPERABLE status
 
within the associated Completion Time, the unit must be
 
placed in a MODE in which the LCO does not apply. To
 
achieve this status, the unit must be placed in at least
 
MODE 3 within 6 hours, and in MODE 4, without reliance upon
 
the steam generator for heat removal, within 24 hours. The
 
allowed Completion Times are reasonable, based on operating
 
experience, to reach the required unit conditions from full
 
power conditions in an orderly manner and without
 
challenging unit systems.
SURVEILLANCE SR 3.7.18.1 REQUIREMENTS  To perform a cooldown of the RCS, the ADVs must be able to be opened through their full range. This SR ensures the
 
ADVs are tested through a full cycle at least once per fuel
 
cycle. This test is performed using the manual handwheel
 
assembly. Any use of an ADV using the manual handwheel


When the concentration of boron in the SFPs is less than required, immediate action must be taken to preclude an accident from happening or to mitigate the consequences of an accident in progress. This is most efficiently achieved by immediately suspending the movement of fuel assemblies. This does not preclude the movement of fuel assemblies to a safe position. In addition, action must be immediately initiated to restore boron concentration to within limits. SURVEILLANCE SR 3.7.16.1 REQUIREMENTS  This SR verifies that the concentration of boron in the SFPs is within the required limit. As long as this SR is met, the analyzed incidents are fully addressed. The Surveillance Frequency is controlled under the Surveillance Frequency Control Program. REFERENCES None SFP Storage B 3.7.17 B 3.7  PLANT SYSTEMS B 3.7.17  Spent Fuel Pool (SFP) Storage BASES  CALVERT CLIFFS - UNIT 2 B 3.7.17-1 Revision 23 BACKGROUND This Technical Specification applies to the Unit 2 SFP only. The spent fuel storage facility was originally designed to store either new (non-irradiated) nuclear fuel assemblies or burned (irradiated) fuel assemblies in a vertical configuration underwater, assuming credit for Boraflex poison sheets but assuming no credit for soluble boron or burnup. The spent fuel storage cells are installed in parallel rows with center-to-center spacing of 10 3/32 inches and with Boraflex sheets between adjacent assemblies. This spacing was sufficient to maintain keff  0.95 for spent fuel of enrichments up to 4.52 wt% for standard fuel design and up to 4.30 wt% for Value Added Pellet (VAP) fuel design. The burnup and enrichment requirements of LCO 3.7.17(a) ensures that the multiplication factor (keff) for the rack in the SFP is less than the 10 CFR 50.68 regulatory limit with the VAP fuel design, ranging in enrichment from 2.0 to 5.0 wt%, with burnup credit, with partial credit for soluble boron, but without Boraflex credit. The soluble boron credit will be limited to 350 ppm including all biases and uncertainties. For fuel assemblies which do not satisfy the burnup and enrichment requirements of LCO 3.7.17(a), the fuel assemblies may be stored in the Unit 2 SFP if surrounded on all four adjacent faces by empty rack cells or other non-reactive materials per LCO 3.7.17(b). APPLICABLE The Unit 2 spent fuel storage facility is designed to  SAFETY ANALYSES conform to the requirements of 10 CFR 50.68 by use of adequate spacing, soluble boron credit, and burnup credit. The SFP storage satisfies Criterion 2 of 10 CFR 50.36(c)(2)(ii). LCO The restrictions on the placement of fuel assemblies within the Unit 2 SFP are in accordance with Figure 3.7.17-1 and ensure that the Unit 2 SFP meets the requirements of 10 CFR 50.68. The restrictions are consistent with the criticality safety analysis performed for the Unit 2 SFP. Fuel assemblies not meting the criteria of Figure 3.7.17-1 may be SFP Storage B 3.7.17 BASES  CALVERT CLIFFS - UNIT 2 B 3.7.17-2 Revision 23 stored in the Unit 2 SFP in a checkboard pattern in accordance with LCO 3.7.17(b). APPLICABILITY This LCO applies whenever any fuel assembly is stored in the Unit 2 SFP. ACTIONS A.1 Required Action A.1 is modified by a Note indicating that LCO 3.0.3 does not apply. If moving fuel assemblies while in MODE 5 or 6, LCO 3.0.3 would not specify any action. If moving fuel assemblies while in MODE 1, 2, 3, or 4, the fuel movement is independent of reactor operation. Therefore, in either case, inability to move fuel assemblies is not a sufficient reason to require a reactor shutdown. When the configuration of fuel assemblies stored in Unit 2 SFP is not in accordance with Figure 3.7.17-1 or LCO 3.7.17(b), immediate action must be taken to make the necessary fuel assembly movement(s) to bring the fuel assembly configuration into compliance with Figure 3.7.17-1 or LCO 3.7.17(b). SURVEILLANCE SR 3.7.17.1 REQUIREMENTS  This SR verifies by administrative means that the initial enrichment and burnup of the fuel assembly is in accordance with Figure 3.7.17-1 for LCO 3.7.17(a). This Surveillance Requirement does not address fuel assemblies stored in the Unit 2 SFP in accordance with LCO 3.7.17(b). This will ensure compliance with Specification 4.3.1.1. REFERENCES None ADVs B 3.7.18 B 3.7  PLANT SYSTEMS B 3.7.18  Atmospheric Dump Valves (ADVs) BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.7.18-1 Revision 54 BACKGROUND The ADVs provide a safety grade method for cooling the unit to Shutdown Cooling (SDC) System entry conditions, should the preferred heat sink via the Turbine Bypass Valves to the condenser not be available, as discussed in the UFSAR, Section 10.3 (Reference 1). This is done in conjunction with the Auxiliary Feedwater System providing cooling water from the condensate storage tank (CST). The ADVs may also be used during a normal cooldown when steam pressure drops too low for maintenance of a vacuum in the condenser to permit use of the Turbine Bypass Valves. Two ADV lines are provided, one per steam generator. Each ADV line consists of one ADV and an associated isolation valve. The ADVs are provided with upstream isolation valves to permit their being tested at power, if desired. The ADVs are equipped with manual hand wheels to open and close them. Pneumatic controllers are used to operate the ADVs as the preferred method, but are not relied upon during an accident. A description of the ADVs is found in Reference 1. The ADVs are considered OPERABLE when the manual control is available for local manual operation. APPLICABLE The design basis of the ADVs is established by the SAFETY ANALYSES capability to cool the unit to SDC System entry conditions. The cooldown rate assumed in the accident analyses is obtainable by one or both steam generators. The design is adequate to cool the unit to SDC System entry conditions with only one ADV and one steam generator. In the steam generator tube rupture accident analysis presented in the UFSAR, the ADVs are assumed to be used by the operator to cool down the unit to SDC System entry conditions because the accident is accompanied by a loss of offsite power. Prior to the operator action, the MSSVs are used to maintain steam generator pressure and temperature at the MSSV setpoint. The ADVs may be used for other accidents that are accompanied by a loss of offsite power. The limiting events are those that render one steam generator unavailable for RCS heat removal, with a coincident loss of offsite power. Typical initiating events falling into this ADVs B 3.7.18 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.7.18-2 Revision 54 category are a feedwater line break, and a SGTR event (limiting case). The ADVs satisfy Criterion 3 of 10 CFR 50.36(c)(2)(ii). LCO Two ADV lines are required to be OPERABLE to ensure that at least one ADV is OPERABLE to conduct a unit cooldown following an event in which one steam generator becomes unavailable. A closed isolation valve does not render its ADV line inoperable since operator action time to open the isolation valve is supported in the accident analysis. Failure to meet the LCO can result in the inability to cool the unit to SDC System entry conditions following an event in which the condenser is unavailable for use with the Turbine Bypass Valves. An ADV is considered OPERABLE when it is capable of providing relief of the main steam flow, and is capable of fully opening and closing when required. APPLICABILITY In MODES 1, 2, and 3, and in MODE 4, when steam generators are being relied upon for heat removal, the ADVs are required to be OPERABLE. In MODES 5 and 6, a SGTR is not a credible event. ACTIONS A.1 With one required ADV line inoperable, action must be taken to restore the OPERABLE status within 48 hours. The 48 hour Completion Time takes into account the redundant capability afforded by the remaining OPERABLE ADV line, and a backup in the Turbine Bypass Valves and MSSVs. B.1 With two required ADV lines inoperable, action must be taken to restore one of the ADV lines to OPERABLE status. As the isolation valve can be closed to isolate an ADV, some repairs may be possible with the unit at power. The 1 hour Completion Time is reasonable to repair inoperable ADV lines, based on the availability of the Turbine Bypass Valves and MSSVs, and the low probability of an event occurring during this period that requires the ADV lines.
assembly may satisfy this requirement. The Surveillance Frequency is controlled under the Surveillance Frequency Control Program.
ADVs B 3.7.18 BASES  CALVERT CLIFFS - UNITS 1 & 2 B 3.7.18-3 Revision 55  C.1 and C.2 If the ADV lines cannot be restored to OPERABLE status within the associated Completion Time, the unit must be placed in a MODE in which the LCO does not apply. To achieve this status, the unit must be placed in at least MODE 3 within 6 hours, and in MODE 4, without reliance upon the steam generator for heat removal, within 24 hours. The allowed Completion Times are reasonable, based on operating experience, to reach the required unit conditions from full power conditions in an orderly manner and without challenging unit systems. SURVEILLANCE SR 3.7.18.1 REQUIREMENTS  To perform a cooldown of the RCS, the ADVs must be able to be opened through their full range. This SR ensures the ADVs are tested through a full cycle at least once per fuel cycle. This test is performed using the manual handwheel assembly. Any use of an ADV using the manual handwheel assembly may satisfy this requirement. The Surveillance Frequency is controlled under the Surveillance Frequency Control Program. REFERENCES 1. UFSAR, Section 10.3}}
REFERENCES 1. UFSAR, Section 10.3}}

Revision as of 21:22, 30 June 2018

Calvert Cliffs, Units 1 and 2 - Technical Specification Bases, Revisions 49 Through 55. Part 10 of 12
ML15257A202
Person / Time
Site: Calvert Cliffs  Constellation icon.png
Issue date: 09/04/2015
From:
Exelon Generation Co
To:
Office of Nuclear Reactor Regulation
Shared Package
ML15257A190 List:
References
Download: ML15257A202 (76)


Text

MSSVs B 3.7.1 B 3.7 PLANT SYSTEMS

B 3.7.1 Main Steam Safety Valves (MSSVs)

BASES CALVERT CLIFFS - UNITS 1 & 2 B 3.7.1-1 Revision 2 BACKGROUND The primary purpose of the MSSVs is to provide overpressure protection for the secondary system. The MSSVs also provide

protection against overpressurizing the reactor coolant

pressure boundary by providing a heat sink for the removal of energy from the Reactor Coolant System (RCS) if the preferred heat sink, provided by the condenser and Circulating Water System, is not available.

Eight MSSVs are located on each main steam header, outside the Containment Structure

, upstream of the main steam isolation valves (MSIVs), as described in Reference 1

, Chapter 10

. The MSSV rated capacity passes the full steam flow at 102%

RATED THERMAL POWER (100% + 2% for instrument error) with the valves full open. This meets the requirements of Reference 2

,Section III, Article NC-7000, Class 2 Components

. The MSSV design includes staggered setpoints, according to Table 3.7.1-1 in the accompanying Limiting Condition for Operation (

LCO), so that only the number of valves needed will actuate. Staggered setpoints reduce the potential for valve chattering

, because of insufficient steam pressure to fully open all valves

, following a turbine reactor trip. The MSSVs have "R" size orifices.

APPLICABLE The design basis for the MSSVs comes from Reference 2

, SAFETY ANALYSES Section III, Article NC-7000, Class 2 Components

their purpose is to limit secondary system pressure to 110% of design pressure when passing 100% of design steam flow.

This design basis is sufficient to cope with any anticipated operational occurrence or accident considered Reference 1, Chapter 14

. The events that challenge the MSSV relieving capacity, and thus RCS pressure, are those characterized as decreased heat

removal events, and are presented in Reference 1, Section 14.5

. Of these, the full power loss of load event is the limiting anticipated operational occurrence

. A loss of load isolates the turbine and condenser, and terminates normal feedwater flow to the steam generators. Before

delivery of auxiliary feedwater (AFW) to the steam MSSVs B 3.7.1 BASES CALVERT CLIFFS - UNITS 1 & 2 B 3.7.1-2 Revision 23 generators, RCS pressure reaches peak pressure. The peak pressure is < 110% of the design pressure of 2500 psig, but

high enough to actuate the pressurizer safety valves.

Although the Power Level-High Trip is not credited in the loss of load safety analysis, reducing the Power Level-High Trip setpoint ensures the Thermal Power limit supported by the safety analysis is met.

The MSSVs satisfy 10 CFR 50.36(c)(2)(ii), Criterion 3.

LCO This LCO requires all MSSVs to be OPERABLE in compliance with Reference 2,Section III, Article NC-7000, Class 2

Components, even though this is not a requirement of the

Design Basis Accident (DBA) analysis. This is because

operation with less than the full number of MSSVs requires

limitations on allowable THERMAL POWER (to meet Reference 2,

Section III, Article NC-7000, Class 2 Components

requirements), and adjustment to the Reactor Protective

System trip setpoints to meet the transient analysis limits.

These limitations are according to those shown in

Table 3.7.1-1, Required Action A.2, and Required Action A.3

in the accompanying LCO.

The OPERABILITY of the MSSVs is defined as the ability to open within the setpoint tolerances, relieve steam generator

overpressure, and reseat when pressure has been reduced.

The OPERABILITY of the MSSVs is determined by periodic

surveillance testing in accordance with the Inservice

Testing Program. An MSSV is considered inoperable if it fails to open upon demand.

The lift settings, according to Table 3.7.1-2 in the accompanying LCO, correspond to ambient conditions of the

valve at nominal operating temperature and pressure.

A Note is added to Table 3.7.1-2, stating that lift settings for a given steam line are also acceptable, if any two

valves lift between 935 and 1005 psig, any two other valves lift between 935 and 1035 psig, and the four remaining valves lift between 935 and 1050 psig. Thus, the MSSVs

still perform that design basis function properly.

MSSVs B 3.7.1 BASES CALVERT CLIFFS - UNITS 1 & 2 B 3.7.1-3 Revision 23 This LCO provides assurance that the MSSVs will perform their designed safety function to mitigate the consequences

of accidents that could result in a challenge to the reactor

coolant pressure boundary.

APPLICABILITY In MODEs 1, 2, and 3, a minimum of five MSSVs per steam generator are required to be OPERABLE, according to

Table 3.7.1-1 in the accompanying LCO, which is limiting and

bounds all lower MODEs.

In MODEs 4 and 5, there are no credible transients requiring the MSSVs.

The steam generators are not normally used for heat removal in MODEs 5 and 6, and thus cannot be overpressurized; there

is no requirement for the MSSVs to be OPERABLE in these MODEs. ACTIONS The ACTIONS table is modified by a Note indicating that separate Condition entry is allowed for each MSSV.

A.1 and A.2 An alternative to restoring the inoperable MSSV(s) to OPERABLE status is to reduce power so that the available

MSSV relieving capacity meets Code requirements for the power level. The number of inoperable MSSVs will determine the necessary level of reduction in secondary system steam

flow and THERMAL POWER required by the reduced reactor trip

settings of the power level-high channels. The setpoints in

Table 3.7.1-1 have been verified by transient analyses.

The operator should limit the maximum steady state power level to some value slightly below this setpoint to avoid an

inadvertent overpower trip.

The four-hour Completion Time for Required Action A.1 is a reasonable time period to reduce power level and is based on

the low probability of an event occurring during this period

that would require activation of the MSSVs. An additional

32 hours3.703704e-4 days <br />0.00889 hours <br />5.291005e-5 weeks <br />1.2176e-5 months <br /> is allowed in Required Action A.2 to reduce the setpoints. The Completion Time of 36 hours4.166667e-4 days <br />0.01 hours <br />5.952381e-5 weeks <br />1.3698e-5 months <br /> for Required Action A.2 is based on a reasonable time to correct the MSSV MSSVs B 3.7.1 BASES CALVERT CLIFFS - UNITS 1 & 2 B 3.7.1-4 Revision 38 inoperability, the time required to perform the power reduction, operating experience in resetting all channels of

a protective function, and on the low probability of the

occurrence of a transient that could result in steam

generator overpressure during this period.

B.1 and B.2 If the MSSVs cannot be restored to OPERABLE status in the associated Completion Time, or if one or more steam

generators have less than five MSSVs OPERABLE, the unit must

be placed in a MODE in which the LCO does not apply. To

achieve this status, the unit must be placed in at least

MODE 3 within 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br />, and in MODE 4 within 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br />. The

allowed Completion Times are reasonable, based on operating

experience, to reach the required unit conditions from full

power conditions in an orderly manner and without challenging unit systems.

SURVEILLANCE SR 3.7.1.1 REQUIREMENTS This Surveillance Requirement (SR) verifies the OPERABILITY of the MSSVs by the verification of each MSSV lift setpoints

in accordance with the Inservice Testing Program.

The safety and relief valve tests are to be performed in accordance with Reference 3. According to Reference 3, the following tests are required for MSSVs: a. Visual examination;

b. Seat tightness determination;
c. Setpoint pressure determination (lift setting);
d. Compliance with owner's seat tightness criteria; and e. Verification of the balancing device integrity on balanced valves.

The ANSI/American Society of Mechanical Engineers (ASME)

Standard requires that all valves be tested every

five years, and a minimum of 20% of the valves be tested

every 24 months. The ASME Code specifies the activities, as

found lift acceptance range, and frequencies necessary to

satisfy the requirements. Table 3.7.1-2 defines the lift

setting range for each MSSV for OPERABILITY; however, the MSSVs B 3.7.1 BASES CALVERT CLIFFS - UNITS 1 & 2 B 3.7.1-5 Revision 38 valves are reset to +

1% during the surveillance test to allow for drift.

This SR is modified by a Note that allows entry into and operation in MODE 3 prior to performing the SR. This is to

allow testing of the MSSVs at hot conditions. The MSSVs may be either bench tested or tested in situ at hot conditions, using an assist device to simulate lift pressure. If the

MSSVs are not tested at hot conditions, the lift setting

pressure shall be corrected to ambient conditions of the valve at operating temperature and pressure.

REFERENCES 1. Updated Final Safety Analysis Report (UFSAR) 2. ASME, Boiler and Pressure Vessel Code

3. ANSI/ASME OM-1-1987, Code for the Operation and Maintenance of Nuclear Power Plants, 1987

MSIVs B 3.7.2 B 3.7 PLANT SYSTEMS

B 3.7.2 Main Steam Isolation Valves (MSIVs)

BASES CALVERT CLIFFS - UNITS 1 & 2 B 3.7.2-1 Revision 14 BACKGROUND The MSIVs isolate steam flow from the secondary side of the steam generators following a high energy line break (HELB).

Main steam isolation valve closure terminates flow from the

unaffected (intact) steam generator.

One MSIV is located in each main steam line outside, but close to, the Containment Structure. The MSIVs are

downstream from the MSSVs, atmospheric dump valves (ADVs),

and AFW pump turbine steam supplies to prevent their being

isolated from the steam generators by MSIV closure. Closing

the MSIVs isolates each steam generator from the other, and

isolates the turbine, Steam Bypass System, and other

auxiliary steam supplies from the steam generators.

The MSIVs close on a steam generator isolation signal generated by low steam generator pressure or on a

containment spray actuation signal (CSAS) generated by high

containment pressure. The MSIVs fail closed on loss of

control or actuation power. The steam generator isolation

signal also actuates the main feedwater isolation valves

(MFIVs) to close. The MSIVs may also be actuated manually.

A description of the MSIVs is found in Reference 1, Section 10.1.

APPLICABLE The design basis of the MSIVs is established by the SAFETY ANALYSES containment analysis for the large steam line break (SLB) inside the Containment Structure, as discussed in Reference 1, Section 14.20. It is also influenced by the accident analysis of the SLB events presented in

Reference 1, Section 14.14. The design precludes the

blowdown of more than one steam generator, assuming a single

active component failure (e.g., the failure of one MSIV to

close on demand).

The limiting case for main SLB Containment Structure response is 75% power, no loss of offsite power, and failure of a steam generator feed pump to trip. This case results in continued feeding of the affected steam generator and maximizes the energy release into the Containment Structure.

MSIVs B 3.7.2 BASES CALVERT CLIFFS - UNITS 1 & 2 B 3.7.2-2 Revision 14 This case does not assume failure of an MSIV; however, an important assumption is both MSIVs are OPERABLE. This

prevents blowdown of both steam generators assuming failure

of an MSIV to close.

The accident analysis compares several different SLB events against different acceptance criteria. The large SLB outside the Containment Structure upstream of the MSIV is

the limiting SLB for offsite dose, although a break in this

short section of main steam header has a very low

probability. The large SLB inside the Containment Structure

at hot full power is the limiting case for a post-trip

return to power. The analysis includes scenarios with

offsite power available and with a loss of offsite power

following turbine trip.

The MSIVs only serve a safety function and remain open during power operation. These valves operate under the

following situations: a. An HELB inside the Containment Structure. In order to maximize the mass and energy release into the

Containment Structure, the analysis assumes steam is

discharged into the Containment Structure from both

steam generators until closure of the MSIV occurs.

After MSIV closure, steam is discharged into the

Containment Structure only from the affected steam

generator. b. A break outside of the Containment Structure and upstream from the MSIVs. This scenario is not a

containment pressurization concern. The uncontrolled

blowdown of more than one steam generator must be

prevented to limit the potential for uncontrolled RCS

cooldown and positive reactivity addition. Closure of

the MSIVs limits the blowdown to a single steam generator. c. A break downstream of the MSIVs. This type of break will be isolated by the closure of the MSIVs. Events

such as increased steam flow through the turbine or the

steam bypass valves (e.g., excess load event) will also

terminate on closure of the MSIVs. d. A steam generator tube rupture. For this scenario, closure of the MSIV isolates the affected steam MSIVs B 3.7.2 BASES CALVERT CLIFFS - UNITS 1 & 2 B 3.7.2-3 Revision 14 generator from the intact steam generator and minimizes radiological releases. The operator is then required

to maintain the pressure of the steam generator with

the ruptured tube below the MSSV setpoints, a necessary

step toward isolating the flow through the rupture. e. The MSIVs are also utilized during other events such as a feedwater line break. These events are less limiting so far as MSIV OPERABILITY is concerned.

The MSIVs satisfy 10 CFR 50.36(c)(2)(ii), Criterion 3.

LCO This LCO requires that the MSIV in each of the two steam lines be OPERABLE. The MSIVs are considered OPERABLE when

the isolation times are within limits, and they close on an

isolation actuation signal.

This LCO provides assurance that the MSIVs will perform their design safety function to mitigate the consequences of accidents as described in Reference 1, Chapter 14.

APPLICABILITY The MSIVs must be OPERABLE in MODE 1 and in MODEs 2 and 3, except when all MSIVs are closed. In these MODEs there is

significant mass and energy in the RCS and steam generators.

When the MSIVs are closed, they are already performing their

safety function.

In MODE 4, the steam generator energy is low; therefore, the MSIVs are not required to be OPERABLE.

In MODEs 5 and 6, the steam generators do not contain much energy because their temperature is below the boiling point

of water; therefore, the MSIVs are not required for

isolation of potential high energy secondary system pipe breaks in these MODEs.

ACTIONS A.1 With one MSIV inoperable in MODE 1, time is allowed to restore the component to OPERABLE status. Some repairs can

be made to the MSIV with the unit hot. The eight hour

Completion Time is reasonable, considering the probability

of an accident occurring during the time period that would

require closure of the MSIVs.

MSIVs B 3.7.2 BASES CALVERT CLIFFS - UNITS 1 & 2 B 3.7.2-4 Revision 14 B.1 If the MSIV cannot be restored to OPERABLE status within eight hours, the unit must be placed in a MODE in which the

LCO does not apply. To achieve this status, the unit must

be placed in MODE 2 within six hours and Condition C would be entered. The Completion Time is reasonable, based on operating experience, to reach MODE 2, and close the MSIVs

in an orderly manner and without challenging unit systems.

C.1 and C.2 Condition C is modified by a Note indicating that separate Condition entry is allowed for each MSIV.

Since the MSIVs are required to be OPERABLE in MODEs 2 and 3, the inoperable MSIVs may either be restored to

OPERABLE status or closed. When closed, the MSIVs are

already in the position required by the assumptions in the

safety analysis.

The eight hour Completion Time is consistent with that allowed in Condition A.

Inoperable MSIVs that cannot be restored to OPERABLE status within the specified Completion Time, but are closed, must

be verified on a periodic basis to be closed. This is

necessary to ensure that the assumptions in the safety

analysis remain valid. The seven day Completion Time is

reasonable, based on engineering judgment, MSIV status

indications available in the Control Room, and other

administrative controls, to ensure these valves are in the

closed position.

D.1 and D.2 If the MSIVs cannot be restored to OPERABLE status, or closed, within the associated Completion Time, the unit must

be placed in a MODE in which the LCO does not apply. To

achieve this status, the unit must be placed in at least

MODE 3 within 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br />, and in MODE 4 within 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br />. The

allowed Completion Times are reasonable, based on operating experience, to reach the required unit conditions from MSIVs B 3.7.2 BASES CALVERT CLIFFS - UNITS 1 & 2 B 3.7.2-5 Revision 38 MODE 2 conditions in an orderly manner and without challenging unit systems.

SURVEILLANCE SR 3.7.2.1 REQUIREMENTS This SR verifies that the closure time of each MSIV is

< 5.2 seconds. The MSIV closure time is assumed in the accident and containment analyses.

The Frequency for this SR is in accordance with the Inservice Testing Program. The MSIVs are tested during each

refueling outage in accordance with Reference 2, and

sometimes during other cold shutdown periods. The Frequency

demonstrates the valve closure time at least once per

refueling cycle. Operating experience has shown that these

components usually pass the SR when performed. Therefore, the Frequency is acceptable from a reliability standpoint.

REFERENCES 1. UFSAR 2. ASME Code for Operation and Maintenance of Nuclear Power Plants

AFW System B 3.7.3 B 3.7 PLANT SYSTEMS

B 3.7.3 Auxiliary Feedwater (AFW) System

BASES CALVERT CLIFFS - UNITS 1 & 2 B 3.7.3-1 Revision 2 BACKGROUND The AFW System automatically supplies feedwater to the steam generators to remove decay heat from the RCS upon the loss of normal feedwater supply. The AFW pumps take suction

through a common suction line from the condensate storage tank (CST) (LCO 3.7.4) and pump to the steam generator secondary side via separate and independent connections, to the AFW header outside the Containment Structure. The steam generators function as a heat sink for core decay heat. The heat load is dissipated by releasing steam to the atmosphere

from the steam generators via the MSSVs (LCO 3.7.1) or ADVs.

If the main condenser is available, steam may be released

via the steam bypass valves and the resulting excess water

inventory in the hotwell is moved to the backup water

supply.

The AFW System consists of, one motor-driven AFW pump and two steam turbine-driven pumps configured into two trains.

The motor-driven pump provides 100% of AFW flow capacity; each turbine-driven pump can provide 100% of the required capacity to the steam generators as assumed in the accident

analysis, but only one turbine-driven pump is lined up to auto start. The other turbine-driven pump is placed in standby and requires a manual start, when it is needed. The pumps are equipped with a common recirculation line to

prevent pump operation against a closed system. The motor-driven AFW pump is powered from an independent Class 1E

power supply, and feeds both steam generators.

One pump at full flow is sufficient to remove decay heat and cool the unit to Shutdown Cooling (SDC) System entry

conditions.

The steam turbine-driven AFW pumps receive steam from either main steam header upstream of the MSIV. Each of the steam feed lines will supply 100% of the requirements of the turbine-driven AFW pump. The turbine-driven AFW pump supplies a common header capable of feeding both steam

generators, with air-operated valves (with controllers powered by AC vital buses) actuated to the appropriate steam AFW System B 3.7.3 BASES CALVERT CLIFFS - UNITS 1 & 2 B 3.7.3-2 Revision 2 generator by the Auxiliary Feedwater Actuation System (AFAS).

The AFW System may also supply feedwater to the steam generators during normal unit startup, shutdown, and hot

standby conditions although the normal supply is main feedwater (MFW).

The AFW System is designed to supply sufficient water to the steam generator(s) to remove decay heat with steam generator

pressure at the setpoint of the MSSVs. Subsequently, the

AFW System supplies sufficient water to cool the unit to SDC

entry conditions, and steam is released through the ADVs.

The AFW System actuates automatically on low steam generator level by the AFAS, as described in LCO 3.3.4. The AFAS logic is designed to feed either or both steam generators

with low levels, but will isolate the AFW System from a

steam generator having a significantly lower steam pressure

than the other steam generator. The AFAS automatically

actuates one AFW turbine-driven pump and associated air-operated valves (with controllers powered by AC vital buses)

when required, to ensure an adequate feedwater supply to the

steam generators. Air-operated valves with controllers powered by AC vital busses are provided for each AFW line to control the AFW flow to each steam generator.

The AFW System is discussed in Reference 1.

APPLICABLE The AFW System mitigates the consequences of any event with SAFETY ANALYSES a loss of normal feedwater.

The design basis of the AFW System is to supply water to the steam generator to remove decay heat and other residual

heat, by delivering at least the minimum required flow rate

to the steam generators at pressures corresponding to the

lowest MSSV set pressure plus 3%.

The limiting DBAs and transients for the AFW System are as follows: a. Main SLB; and b. Loss of normal feedwater.

AFW System B 3.7.3 BASES CALVERT CLIFFS - UNITS 1 & 2 B 3.7.3-3 Revision 12 The AFW System satisfies 10 CFR 50.36(c)(2)(ii),

Criterion 3.

LCO This LCO requires that two AFW trains be OPERABLE to ensure that the AFW System will perform its design safety function.

A train consists of one pump and the piping, valves, and controls in the direct flow path. Three AFW pumps are installed, consisting of one motor-driven and two non-

condensing steam turbine-driven pumps. For a shutdown, only

one pump is required to be operating, the others are in

standby. Upon automatic initiation of AFW, one motor-driven

and one turbine-driven pump automatically start.

The AFW System is considered to be OPERABLE when the components and flow paths required to provide AFW flow to

the steam generators are OPERABLE. This requires that the

motor-driven AFW pump be OPERABLE and capable of supplying

AFW flow to both steam generators. The turbine-driven AFW

pumps shall be OPERABLE with redundant steam supplies from

each of the two main steam lines upstream of the MSIVs and

capable of supplying AFW flow to both of the two steam

generators. The piping, valves, instrumentation, and

controls in the required flow paths shall also be OPERABLE.

The LCO is modified by a Note that allows AFW trains required for Operability to be taken out-of-service under administrative control for the performance of periodic testing. This LCO note allows a limited exception to the LCO requirement and allows this condition to exist without requiring any Technical Specification Condition to be entered. The following administrative controls are necessary during periodic testing to ensure the operator(s) can restore the AFW train(s) from the test configuration to its operational configuration when required. A dedicated operator(s) is stationed at the control station(s) with direct communication to the Control Room whenever the train(s) is in the testing configuration. Upon completion of the testing the trains are returned to proper status and

verified in proper status by independent operator checks.

The administrative controls include certain operator restoration actions that are virtually certain to be successful during accident conditions. These actions AFW System B 3.7.3 BASES CALVERT CLIFFS - UNITS 1 & 2 B 3.7.3-4 Revision 26 include but are not limited to the following: operation of pump discharge valves, operation of trip/throttle valve(s),

simple handswitch/controller manipulations, and adjusting

the local governor speed control knob. The administrative

controls do not include actions to restore a tripped AFW

pump due to the complicated nature of this task. Periodic tests include those tests that are performed in a controlled manner similar to surveillance tests, but not necessarily on

the established surveillance test schedule, such as post-

maintenance tests. This Note is necessary because of the

AFW pump configuration.

APPLICABILITY In MODEs 1, 2, and 3, the AFW System is required to be OPERABLE and to function in the event that the MFW is lost.

In addition, the AFW System is required to supply enough

makeup water to replace steam generator secondary inventory

and maintain the RCS in MODE 3.

In MODE 4, the AFW System is not required, however, it may be used for heat removal via the steam generator although

the preferred method is MFW.

In MODEs 5 and 6, the steam generators are not normally used for decay heat removal, and the AFW System is not required.

ACTIONS A Note prohibits the application of LCO 3.0.4.b to an inoperable AFW train. There is an increased risk associated with entering a MODE or other specified condition in the Applicability with an AFW train inoperable and the provisions of LCO 3.0.4.b, which allow entry into a MODE or other specified condition in the Applicability with the LCO not met after performance of a risk assessment addressing inoperable systems and components, should not be applied in this circumstance.

A.1 and A.2 With one of the required steam-driven AFW pumps inoperable, action must be taken to align the remaining OPERABLE steam-

driven pump to automatic initiating status. This Required

Action ensures that a steam-driven AFW pump is available to

automatically start, if required. If the OPERABLE AFW pump

is properly aligned, the inoperable steam-driven AFW pump

must be restored to OPERABLE status (and placed in either AFW System B 3.7.3 BASES CALVERT CLIFFS - UNITS 1 & 2 B 3.7.3-5 Revision 48 standby or automatic initiating status, depending upon whether the other steam-driven AFW pump is in standby or

automatic initiating status) within seven days. The 72 hour8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br />

and seven day Completion Times are reasonable, based on the

redundant capabilities afforded by the AFW System, the time

needed for repairs, and the low probability of a DBA event occurring during this period. Two AFW pumps and flow paths remain to supply feedwater to the steam generators.

B.1 and B.2 With the motor-driven AFW pump inoperable, action must be taken to align the standby steam-driven pump to automatic

initiating status. This Required Action ensures that

another AFW pump is available to automatically start, if

required. If the standby steam-driven pump is properly

aligned, the inoperable motor-driven AFW pump must be

restored to OPERABLE status within seven days. The 72-hour

and seven day, Completion Times are reasonable, based on the

redundant capabilities afforded by the AFW System, the time

needed for repairs, and the low probability of a DBA event

occurring during this period. Two AFW pumps and one flow

path remain to supply feedwater to the steam generators.

C.1, C.2, C.3, and C.4 With two AFW pumps inoperable, action must be taken to align the remaining OPERABLE pump to automatic initiating status

and to verify the other units motor-driven AFW pump is

OPERABLE, along with an OPERABLE cross-tie valve, within

one hour. If these Required Actions are completed within

the Completion Time, one AFW pump must be restored to

OPERABLE status within 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br />. Verifying the other units

motor-driven AFW pump is OPERABLE provides an additional

level of assurance that AFW will be available if needed,

because the other units AFW can be cross-connected if necessary. The cross-tie valve to the opposite unit is administratively verified OPERABLE by confirming that

SR 3.7.3.2 has been performed within the specified

Frequency. These one hour Completion Times are reasonable

based on the low probability of a DBA occurring during the

first hour and the need for AFW during the first hour. The

72 hour8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> completion time to restore one AFW pump to OPERABLE

status takes into account the cross-connected capability AFW System B 3.7.3 BASES CALVERT CLIFFS - UNITS 1 & 2 B 3.7.3-6 Revision 48 between units and the unlikelihood of an event occurring in the 72 hour8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> period.

D.1 With one of the required AFW trains inoperable for reasons other than Condition A, B, or C (e.g., flowpath or steam supply valve), action must be taken to restore OPERABLE status within 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br />. This Condition includes the loss of

two steam supply lines to the turbine-driven AFW pumps. The

72 hour8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> Completion Time is reasonable, based on the

redundant capabilities afforded by the AFW System, the time

needed for repairs, and the low probability of a DBA event

occurring during this period. One AFW train remains to

supply feedwater to the steam generators.

E.1 and E.2 When the Required Action and associated Completion Time of Condition A, B, C, or D cannot be met the unit must be

placed in a MODE in which the LCO does not apply. To

achieve this status, the unit must be placed in at least

MODE 3 within 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br />, and in MODE 4 within 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br />.

The allowed Completion Times are reasonable, based on operating experience, to reach the required unit conditions

from full power conditions in an orderly manner and without

challenging unit systems.

F.1 Required Action F.1 is modified by a Note indicating that all required MODE changes or power reductions are suspended

until one AFW train is restored to OPERABLE status.

With two AFW trains inoperable in MODEs 1, 2, and 3, the unit may be in a seriously degraded condition with only non-safety-related means for conducting a cooldown. In such a condition, the unit should not be perturbed by any action,

including a power change, that might result in a trip.

However, a power change is not precluded if it is determined

to be the most prudent action. The seriousness of this

condition requires that action be started immediately to

restore one AFW train to OPERABLE status. While other plant

conditions may require entry into LCO 3.0.3, the ACTIONS AFW System B 3.7.3 BASES CALVERT CLIFFS - UNITS 1 & 2 B 3.7.3-7 Revision 55 required by LCO 3.0.3 do not have to be completed because they could force the unit into a less safe condition.

SURVEILLANCE SR 3.7.3.1 REQUIREMENTS Verifying the correct alignment for manual, power-operated, and automatic valves in the AFW water and steam supply flow

paths, provides assurance that the proper flow paths exist

for AFW operation. This SR does not apply to valves that

are locked, sealed, or otherwise secured in position, since

these valves are verified to be in the correct position

prior to locking, sealing, or securing. This SR also does

not apply to valves that cannot be inadvertently misaligned,

such as check valves. This SR does not require any testing

or valve manipulations; rather, it involves verification

that those valves capable of potentially being mispositioned

are in the correct position.

The Surveillance Frequency is controlled under the Surveillance Frequency Control Program.

SR 3.7.3.2 Cycling each testable, remote-operated valve that is not in its operating position, provides assurance that the valves

will perform as required. Operating position is the

position that the valve is in during normal plant operation.

This is accomplished by cycling each valve at least one

cycle. This SR ensures that valves required to function

during certain scenarios, will be capable of being properly

positioned. The Frequency is based on engineering judgment that when cycled in accordance with the Inservice Testing Program, these valves can be placed in the desired position

when required.

SR 3.7.3.3 Verifying that each AFW pump's developed head at the flow test point is greater than or equal to the required developed head ( 2800 ft for the steam-driven pump and 3100 ft for the motor-driven pump), ensures that AFW pump performance has not degraded during the cycle. Flow and

differential head are normal tests of pump performance

required by Reference 2. Because it is undesirable to AFW System B 3.7.3 BASES CALVERT CLIFFS - UNITS 1 & 2 B 3.7.3-8 Revision 55 introduce cold AFW into the steam generators while they are operating, this testing is performed on recirculation flow.

This test confirms one point on the pump design curve and is

indicative of overall performance. Such inservice tests

confirm component OPERABILITY, trend performance, and detect

incipient failures by indicating abnormal performance.

Performance of inservice testing, discussed in Reference 2, at three month intervals satisfies this requirement.

This SR is modified by a Note indicating that the SR should be deferred up to 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> until suitable test conditions

are established. This deferral is required because there is

an insufficient steam pressure to perform the test.

SR 3.7.3.4 This SR ensures that AFW can be delivered to the appropriate steam generator, in the event of any accident or transient

that generates an AFAS signal, by demonstrating that each

automatic valve in the flow path actuates to its correct

position on an actual or simulated actuation signal

(verification of flow-modulating characteristics is not

required). This SR is not required for valves that are

locked, sealed, or otherwise secured in the required

position under administrative controls. The Surveillance Frequency is controlled under the Surveillance Frequency Control Program.

This SR is modified by a Note indicating that the SR should be deferred up to 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> until suitable test conditions

have been established.

SR 3.7.3.5 This SR ensures that the AFW pumps will start in the event of any accident or transient that generates an AFAS signal by demonstrating that each AFW pump starts automatically on an actual or simulated actuation signal. The Surveillance Frequency is controlled under the Surveillance Frequency Control Program.

This SR is modified by a Note. The Note indicates that the SR should be deferred up to 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> until suitable test

conditions are established.

AFW System B 3.7.3 BASES CALVERT CLIFFS - UNITS 1 & 2 B 3.7.3-9 Revision 55 SR 3.7.3.6 This SR ensures that the AFW system is capable of providing a minimum nominal flow to each flow leg. This ensures that

the minimum required flow is capable of feeding each flow

leg. The test may be performed on one flow leg at a time.

The SR is modified by a Note which states, the SR is not required to be performed for the AFW train with the turbine-

driven AFW pump until up to 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> after reaching 800 psig

in the steam generators. The Note ensures that proper test

conditions exist prior to performing the test using the

turbine-driven AFW pumps. The Surveillance Frequency is controlled under the Surveillance Frequency Control Program.

SR 3.7.3.7 This SR ensures that the AFW System is properly aligned by verifying the flow path to each steam generator prior to

entering MODE 2 operation, after 30 days in MODEs 5 or 6.

OPERABILITY of AFW flow paths must be verified before

sufficient core heat is generated that would require the

operation of the AFW System during a subsequent shutdown.

The Frequency is reasonable, based on engineering judgment,

and other administrative controls to ensure that flow paths

remain OPERABLE. To further ensure AFW System alignment,

the OPERABILITY of the flow paths is verified following

extended outages to determine that no misalignment of valves

has occurred. This SR ensures that the flow path from the

CST to the steam generators is properly aligned. Minimum

nominal flow to each flow leg is ensured by performance of SR 3.7.3.6.

REFERENCES 1. UFSAR, Section 10.3 2. ASME Code for Operation and Maintenance of Nuclear Power Plants

CST B 3.7.4 B 3.7 PLANT SYSTEMS

B 3.7.4 Condensate Storage Tank (CST)

BASES CALVERT CLIFFS - UNITS 1 & 2 B 3.7.4-1 Revision 41 BACKGROUND The CST provides a safety grade source of water to the steam generators for removing decay and sensible heat from the

RCS. The CST provides a passive flow of water, by gravity,

to the AFW System (LCO 3.7.3). The steam produced is released to the atmosphere by the MSSVs or the atmospheric dump valves. The AFW pumps operate with a continuous

recirculation to the CST.

The component required by this Specification is CST No. 12.

When the MSIVs are open, the preferred means of heat removal is to discharge steam to the condenser by the non-safety

grade path of the turbine bypass valves. The condensed

steam is returned to the backup water supply (CST No. 11 and

CST No. 21) by the condensate pump. This has the advantage

of conserving condensate while minimizing releases to the

environment.

Because the CST is a principal component in removing residual heat from the RCS, it is designed to withstand

earthquakes and other natural phenomena. The CST is

designed to Seismic Category I requirements to ensure

availability of the feedwater supply. Feedwater is also

available from an alternate source.

There is one CST (CST No. 12) shared by Units 1 and 2. A description of the CST is found in Reference 1, Sections 6.3.5.1 and 10.3.2.

APPLICABLE The CST provides cooling water to remove decay heat and to SAFETY ANALYSES cool down the unit following all events except for the maximum hypothetical accident and the fuel handling accident in the accident analyses, discussed in Reference 1, Chapter 14. For anticipated operational occurrences and

accidents which do not affect the OPERABILITY of the steam

generators, the thermal analysis assumption is generally six hours at MODE 3, steaming through the ADVs and MSSVs followed by a cooldown to SDC entry conditions at the design

cooldown rate. The dose analysis assumption is an eight hour cooldown to maximize Control Room and offsite doses.

CST B 3.7.4 BASES CALVERT CLIFFS - UNITS 1 & 2 B 3.7.4-2 Revision 41 The limiting event for the condensate volume is the large feedwater line break with a coincident loss of offsite

power. Single failures that also affect this event include

the following: a. The failure of the diesel generator powering the motor-driven AFW pump to the unaffected steam generator

(requiring additional steam to drive the remaining AFW

pump turbine); and b. The failure of the steam driven train (requiring a longer time for cooldown using only one motor-driven AFW pump).

These are not usually the limiting failures in terms of consequences for these events.

The CST satisfies 10 CFR 50.36(c)(2)(ii), Criteria 2 and 3.

LCO To satisfy accident analysis assumptions, CST No. 12 must contain sufficient cooling water for both units to ensure

that sufficient water is available to maintain the RCS at

MODE 3 for six hours following a reactor trip from

102% RATED THERMAL POWER, assuming a coincident loss of

offsite power and the most adverse single failure. In doing

this, it must retain sufficient water to ensure adequate net

positive suction head for the AFW pumps during the cooldown

while in MODE 3, as well as to account for any losses from

the steam-driven AFW pump turbine, or before isolating AFW

to a broken line.

The CST usable volume required is 150,000 gallons per unit (300,000 gallons for both units) in the MODE of

Applicability. The 300,000 gallons of water is enough to

provide for decay heat removal and cooldown of both units.

By adjusting the feedwater flow to the permissible cooldown rate, decay heat removal and cooldown of both units can be accomplished in six hours. The 300,000 gallons are also

adequate to maintain the RCS in MODE 3 for six hours with

steam discharge to atmosphere with concurrent and total loss

of offsite power, or to remove decay heat from both units

for more than ten hours after initiation of cooldown and

still maintain normal no-load water level in the steam

generators. The total water volume in the tank includes the CST B 3.7.4 BASES CALVERT CLIFFS - UNITS 1 & 2 B 3.7.4-3 Revision 41 usable volume and water not usable because of the tank discharge line location.

OPERABILITY of the CST is determined by maintaining the tank volume at or above the minimum required volume.

APPLICABILITY In MODEs 1, 2, and 3, the CST is required to be OPERABLE.

In MODEs 4, 5 and 6, the CST is not required because the AFW System is not required.

ACTIONS A.1 and A.2 If the CST is not OPERABLE, the OPERABILITY of the backup water supply (CST No. 11 for Unit 1 and CST No. 21 for

Unit 2) must be verified by administrative means within

4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> and once every 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> thereafter.

OPERABILITY of the backup feedwater supply must include verification that the manual valves in the flow paths from

the backup supply to the AFW pumps are open, and

availability of the required volume of water

(150,000 gallons) in the backup supply. The CST must be

returned to OPERABLE status within seven days, as the backup

supply may be performing this function in addition to its

normal functions. The four hour Completion Time is

reasonable, based on operating experience, to verify the

OPERABILITY of the backup water supply. Additionally,

verifying the backup water supply every 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> is adequate

to ensure the backup water supply continues to be available.

The seven day Completion Time is reasonable, based on an OPERABLE backup water supply being available, and the low probability of an event requiring the use of the water from

the CST occurring during this period.

If the CST volume is less than 300,000 gallons and greater than 150,000 gallons and both units are in the MODE of

Applicability, only one unit must enter this condition

provided the unit aligns to the OPERABLE backup water supply

(CST No. 11 or CST No. 21).

CST B 3.7.4 BASES CALVERT CLIFFS - UNITS 1 & 2 B 3.7.4-4 Revision 55 B.1 and B.2 If the CST cannot be restored to OPERABLE status within the associated Completion Time, the affected unit(s) must be

placed in a MODE in which the LCO does not apply. To

achieve this status, the unit(s) must be placed in at least

MODE 3 within 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br />, and in MODE 4 within 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br />. The

allowed Completion Times are reasonable, based on operating

experience, to reach the required unit conditions from full

power conditions in an orderly manner and without challenging plant systems.

SURVEILLANCE SR 3.7.4.1 REQUIREMENTS This SR verifies that the CST contains the required usable volume of cooling water. (This volume 150,000 gallons per unit in the MODE of Applicability.) The Surveillance Frequency is controlled under the Surveillance Frequency Control Program.

Although the volume in the CST for each unit is required to be 150,000 gallons, the total combined volume for both units is 300,000 gallons.

REFERENCES 1. UFSAR

CC System B 3.7.5 B 3.7 PLANT SYSTEMS

B 3.7.5 Component Cooling (CC) System

BASES CALVERT CLIFFS - UNITS 1 & 2 B 3.7.5-1 Revision 53 BACKGROUND The CC System provides a heat sink for the removal of process and operating heat from safety-related components

during a DBA or transient. During normal operation, the CC

System also provides this function for various nonessential components. The CC System serves as a barrier to the release of radioactive byproducts between potentially

radioactive systems and the Saltwater (SW) System, and thus

to the environment.

The CC System consists of two redundant loops that are always cross-connected. A loop consists of one of three

redundant pumps, one of two redundant CC heat exchangers

along with a common head tank, associated valves, piping,

instrumentation, and controls. The third pump, which is an

installed spare, can be powered from either electrical

train. The redundant cooling capacity of this system,

assuming single active failure, is consistent with the

assumptions made in the accident analysis.

During normal operation one loop typically provides cooling water with a maximum CC heat exchanger outlet temperature of 95°F (a range of 70

°F-95°F is acceptable during normal operating conditions) with the redundant loop components in

standby. If needed, the redundant loop components can be

aligned to supplement the in service loop. While operating

on SDC with one loop, the CC heat exchanger outlet temperature may rise to a maximum temperature of 120

°F. Additional information on the design and operation of the system, along with a list of the components served, is

presented in Reference 1, Section 9.5.2.1. The principal

safety-related function of the CC System is the removal of

decay heat from the reactor via the SDC System heat exchanger. This may utilize the SDC heat exchanger, during a normal or post accident cooldown and shutdown, or the

Containment Spray System during the recirculation phase following a loss of coolant accident (LOCA).

CC System B 3.7.5 BASES CALVERT CLIFFS - UNITS 1 & 2 B 3.7.5-2 Revision 53 APPLICABLE The design basis of the CC System is for it to support a SAFETY ANALYSES 100% capacity Containment Cooling System (containment spray, containment coolers, or a combination) removing core decay

heat 30 minutes after a design basis LOCA. This prevents

the containment sump fluid from increasing in temperature

during the recirculation phase following a LOCA, and provides a gradual reduction in the temperature of this fluid as it is supplied to the RCS by the safety injection

pumps.

The CC System is designed to perform its function with a single failure of any active component, assuming a loss of

offsite power.

The CC System also functions to cool the unit from SDC entry conditions (Tcold < 300°F) to Tcold < 140°F during normal operations. The time required to cool from 300°F to 140°F

is a function of the number of CC and SDC loops operating.

One CC loop is sufficient to remove decay heat during

subsequent operations with Tcold < 140°F. This assumes that a maximum inlet SW temperature occurs simultaneously with

the maximum heat loads on the system.

The CC System satisfies 10 CFR 50.36(c)(2)(ii), Criterion 3.

LCO The CC loops are redundant of each other to the degree that each has separate controls and power supplies and the

operation of one does not depend on the other. In the event

of a DBA, one CC loop is required to provide the minimum

heat removal capability assumed in the safety analysis for the systems to which it supplies cooling water. To ensure this requirement is met, two CC loops must be OPERABLE. At

least one CC loop will operate assuming the worst single

active failure occurs coincident with the loss of offsite

power. Additionally, the containment cooling function will

also operate assuming the worst case passive failure post-recirculation actuation signal (RAS).

A CC loop is considered OPERABLE when the following: a. The associated pump and common head tank are OPERABLE; and CC System B 3.7.5 BASES CALVERT CLIFFS - UNITS 1 & 2 B 3.7.5-3 Revision 53 b. The associated piping, valves, heat exchanger and instrumentation and controls required to perform the

safety-related function are OPERABLE.

The isolation of CC from other components or systems not required for safety may render those components or systems inoperable, but does not affect the OPERABILITY of the CC

System. APPLICABILITY In MODEs 1, 2, 3, and 4, the CC System is a normally operating system that must be prepared to perform its post

accident safety functions, primarily RCS heat removal by

cooling the SDC heat exchanger.

In MODEs 5 and 6, the OPERABILITY requirements of the CC System are determined by the systems it supports.

ACTIONS A.1 Required Action A.1 is modified by a Note indicating the requirement of entry into the applicable Conditions and

Required Actions of LCO 3.4.6, for SDC made inoperable by

CC. This is an exception to LCO 3.0.6 and ensures the

proper actions are taken for these components.

With one CC loop inoperable, action must be taken to restore OPERABLE status within 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br />. In this Condition, the remaining OPERABLE CC loop is adequate to perform the heat

removal function. The 72 hour8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> Completion Time is based on

the redundant capabilities afforded by the OPERABLE loop,

and the low probability of a DBA occurring during this

period.

B.1 and B.2 If the CC loop cannot be restored to OPERABLE status within the associated Completion Time, the unit must be placed in a

MODE in which the LCO does not apply. To achieve this

status, the unit must be placed in at least MODE 3 within

6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> and in MODE 5 within 36 hours4.166667e-4 days <br />0.01 hours <br />5.952381e-5 weeks <br />1.3698e-5 months <br />.

The allowed Completion Times are reasonable, based on operating experience, to reach the required unit conditions CC System B 3.7.5 BASES CALVERT CLIFFS - UNITS 1 & 2 B 3.7.5-4 Revision 55 from full power conditions in an orderly manner and without challenging unit systems.

SURVEILLANCE SR 3.7.5.1 REQUIREMENTS Verifying the correct alignment for manual, power operated, and automatic valves in the CC flow path provides assurance

that the proper flow paths exist for CC operation. This SR

does not apply to valves that are locked, sealed, or

otherwise secured in position, since these valves are

verified to be in the correct position prior to locking,

sealing, or securing. This SR also does not apply to valves

that cannot be inadvertently misaligned, such as check

valves. This SR does not require any testing or valve

manipulation; rather, it involves verification that those

valves capable of potentially being mispositioned are in

their correct position.

This SR is modified by a Note indicating that the isolation of the CC components or systems may render those components

inoperable but does not affect the OPERABILITY of the CC

System.

The Surveillance Frequency is controlled under the Surveillance Frequency Control Program.

SR 3.7.5.2 This SR verifies proper automatic operation of the CC valves on an actual or simulated safety injection actuation signal

(SIAS). The CC System is a normally operating system that cannot be fully actuated as part of routine testing during normal operation. This SR is not required for valves that

are locked, sealed, or otherwise secured in the required

position under administrative controls. The Surveillance Frequency is controlled under the Surveillance Frequency Control Program.

SR 3.7.5.3 This SR verifies proper automatic operation of the CC pumps on an actual or simulated SIAS. The CC System is a normally

operating system that cannot be fully actuated as part of

routine testing during normal operation. The Surveillance CC System B 3.7.5 BASES CALVERT CLIFFS - UNITS 1 & 2 B 3.7.5-5 Revision 55 Frequency is controlled under the Surveillance Frequency Control Program.

REFERENCES 1. UFSAR

SRW System B 3.7.6 B 3.7 PLANT SYSTEMS

B 3.7.6 Service Water (SRW) System

BASES CALVERT CLIFFS - UNITS 1 & 2 B 3.7.6-1 Revision 5 BACKGROUND The SRW System provides a heat sink for the removal of process and operating heat from safety-related components

during a DBA or transient. During normal operation or a

normal shutdown, the SRW System also provides this function for various safety-related and non-safety-related components. The safety-related function is covered by this

LCO.

The SRW System consists of two separate, 100% capacity safety-related cooling water subsystems. Each subsystem

consists of a 100% capacity pump, head tank, two SRW heat exchangers, piping, valves, and instrumentation. A third pump, which is an installed spare, can be powered from

either electrical train. The pumps and valves are remote

manually aligned, except in the unlikely event of a LOCA.

The pumps are automatically started upon receipt of a SIAS

and all essential valves are aligned to their post-accident

positions.

During normal operation, both subsystems are required, and are independent to the degree necessary to assure the safe

operation and shutdown of the plant-assuming a single

failure. During shutdown, operation of the SRW System is the same as normal operation, except that the heat loads are

reduced. Additional information about the design and operation of the SRW System, along with a list of the

components served, is presented in Reference 1,

Section 9.5.2.2. In the event of a LOCA, the SRW System

automatically realigns to isolate Turbine Building (non-

safety-related) loads creating two independent and redundant

safety-related subsystems. Service water flow to the spent

fuel pool (SFP) cooler and the blowdown heat exchanger is automatically isolated as required for the DBA. Each SRW subsystem will supply cooling water to a diesel generator

and two containment air coolers. However, the No. 11 SRW

subsystem only supplies two containment air coolers since

the No. 1A Diesel Generator is air cooled. Each SRW

subsystem is sufficiently sized to remove the maximum amount

of heat from the containment atmosphere while maintaining SRW System B 3.7.6 BASES CALVERT CLIFFS - UNITS 1 & 2 B 3.7.6-2 Revision 41 the SRW supply temperature to the diesel generator below its design limit.

APPLICABLE The design basis of the SRW System is for it to support a SAFETY ANALYSES 100% capacity containment cooling system (containment coolers) and to remove core decay heat 30 minutes following a design basis LOCA, as discussed in Reference 1,

Section 14.20. This prevents the containment sump fluid

from increasing in temperature during the recirculation

phase following a LOCA and provides for a gradual reduction

in the temperature of this fluid as it is supplied to the

RCS by the safety injection pumps. The SRW System is

designed to perform its function with a single failure of

any active component, assuming the loss of offsite power.

The SRW System satisfies 10 CFR 50.36(c)(2)(ii),

Criterion 3.

LCO Two SRW subsystems are required to be OPERABLE to provide the required redundancy to ensure that the system functions

to remove post-accident heat loads, assuming the worst

single active failure occurs coincident with the loss of

offsite power. Additionally, this system will also operate

assuming that worst case passive failure post-RAS.

An SRW subsystem is considered OPERABLE when: a. The associated pump and head tank are OPERABLE; and

b. The associated piping, valves, heat exchanger, and instrumentation and controls required to perform the safety-related function are OPERABLE.

APPLICABILITY In MODEs 1, 2, 3, and 4, the SRW System is a normally operating system, which is required to support the

OPERABILITY of the equipment serviced by the SRW System and

required to be OPERABLE in these MODEs.

In MODEs 5 and 6, the OPERABILITY requirements of the SRW System are determined by the systems it supports.

SRW System B 3.7.6 BASES CALVERT CLIFFS - UNITS 1 & 2 B 3.7.6-3 Revision 5 ACTIONS A.1 and A.2 With one SRW heat exchanger inoperable, action must be taken to restore operable status within 7 days. Isolating flow to one associated containment cooling unit will reduce the DBA heat load of the affected SRW subsystem to within the capacity of one SRW heat exchanger, thus ensuring that the SRW temperatures can be maintained within their design limits. This will allow the associated diesel generator (except for 11 SRW which does not cool a diesel generator) to remain operable. In this Condition, the other OPERABLE SRW System is adequate to perform the containment heat removal function. However, the overall reliability is reduced because a single failure in the SRW System could result in loss of SRW containment heat removal function.

Required Action A.1 is modified by a Note. The Note indicates that the applicable Conditions of LCO 3.6.6 should be entered for an inoperable containment cooling train. The 7 day Completion Time is based on the redundant capabilities afforded by the OPERABLE subsystem, the Completion Time associated with an inoperable containment cooling unit (3.6.6), and the low probability of a DBA occurring during this time period. B.1 With one SRW subsystem inoperable, action must be taken to restore OPERABLE status within 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br />. In this Condition,

the remaining OPERABLE SRW System is adequate to perform the

heat removal function. However, the overall reliability is

reduced because a single failure in the SRW System could

result in loss of SRW function. Required Action B.1 is modified by a Note. The Note indicates that the applicable

Conditions of LCO 3.8.1, should be entered if the inoperable

SRW subsystem results in an inoperable diesel generator.

The 72 hour8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> Completion Time is based on the redundant

capabilities afforded by the OPERABLE subsystem, and the low probability of a DBA occurring during this time period.

C.1 and C.2 If the SRW subsystem cannot be restored to OPERABLE status within the associated Completion Time, the unit must be

placed in a MODE in which the LCO does not apply. To SRW System B 3.7.6 BASES CALVERT CLIFFS - UNITS 1 & 2 B 3.7.6-4 Revision 55 achieve this status, the unit must be placed in at least MODE 3 within 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> and in MODE 5 within 36 hours4.166667e-4 days <br />0.01 hours <br />5.952381e-5 weeks <br />1.3698e-5 months <br />.

The allowed Completion Times are reasonable, based on operating experience, to reach the required unit conditions

from full power conditions in an orderly manner and without challenging unit systems.

SURVEILLANCE SR 3.7.6.1 REQUIREMENTS Verifying the correct alignment for manual, power-operated, and automatic valves in the SRW flow path ensures that the

proper flow paths exist for SRW operation. This SR does not

apply to valves that are locked, sealed, or otherwise

secured in position, since they are verified to be in the

correct position prior to locking, sealing, or securing.

This SR also does not apply to valves that cannot be

inadvertently misaligned, such as check valves. This SR

does not require any testing or valve manipulation; rather,

it involves verification that those valves capable of

potentially being mispositioned are in the correct position.

This SR is modified by a Note indicating that the isolation

of the SRW components or systems may render those components

inoperable but does not affect the OPERABILITY of the SRW

System.

The Surveillance Frequency is controlled under the Surveillance Frequency Control Program.

SR 3.7.6.2 This SR verifies proper automatic operation of the SRW System valves on an actual or simulated actuation signal

(SIAS or CSAS). The SRW System is a normally operating

system that cannot be fully actuated as part of normal

testing. This surveillance test is not required for valves

that are locked, sealed, or otherwise secured in the

required position under administrative controls. The Surveillance Frequency is controlled under the Surveillance Frequency Control Program.

SRW System B 3.7.6 BASES CALVERT CLIFFS - UNITS 1 & 2 B 3.7.6-5 Revision 55 SR 3.7.6.3 The SR verifies proper automatic operation of the SRW System pumps on an actual or simulated actuation signal (SIAS or

CSAS). The SRW System is a normally operating system that

cannot be fully actuated as part of the normal testing

during normal operation. The Surveillance Frequency is controlled under the Surveillance Frequency Control Program.

REFERENCES 1. UFSAR

SW System B 3.7.7 B 3.7 PLANT SYSTEMS

B 3.7.7 Saltwater (SW) System

BASES CALVERT CLIFFS - UNITS 1 & 2 B 3.7.7-1 Revision 5 BACKGROUND The SW System provides a heat sink for the removal of process and operating heat from safety-related components

during a DBA or transient. During normal operation or a

normal shutdown, the SW System also provides this function for various safety-related and non-safety-related components. The safety-related function is covered by this

LCO.

The SW System consists of two subsystems. Each subsystem contains one pump. A third pump, which is an installed

spare, can be aligned to either subsystem. The safety-

related function of each subsystem is to provide SW to two SRW heat exchangers, a CC heat exchanger, and an Emergency Core Cooling System (ECCS) pump room air cooler in order to

transfer heat from these systems to the bay. Seal water for

the non-safety-related circulating water pumps is supplied

by both or either subsystems. The SW pumps provide the

driving head to move SW from the intake structure, through

the system and back to the circulating water discharge

conduits. The system is designed such that each pump has

sufficient head and capacity to provide cooling water such

that 100% of the required heat load can be removed by either

subsystem.

During normal operation, both subsystems in each unit are in operation with one pump running on each header and a third

pump in standby. If needed, the standby pumps can be lined-

up to either supply header. The SW flow through the SRW and

CC heat exchangers is throttled to provide sufficient

cooling to the heat exchangers, while maintaining total

subsystem flow below a maximum value.

Additional information about the design and operation of the SW System, along with a list of the components served, is

presented in Reference 1. During an accident, the SW System

is required to remove the heat load from the SRW and ECCS pump room, and from the CC following an RAS.

SW System B 3.7.7 BASES CALVERT CLIFFS - UNITS 1 & 2 B 3.7.7-2 Revision 12 APPLICABLE The most limiting event for the SW System is a LOCA. SAFETY ANALYSES Operation of the SW System following a LOCA is separated into two phases, before the RAS and after the RAS. One

subsystem can satisfy cooling requirements of both phases.

After a LOCA but before an RAS, each subsystem will cool two

SRW heat exchangers and an ECCS pump room air cooler (as required). There is no required flow to the CC heat exchangers. When an RAS occurs, flow is throttled to the CC heat exchanger. Flow to each SRW heat exchanger is reduced while the system remains capable of providing the required

flow to the ECCS pump room air coolers.

The SW System satisfies 10 CFR 50.36(c)(2)(ii), Criterion 3.

LCO Two SW subsystems are required to be OPERABLE to provide the required redundancy to ensure that the system functions to

remove post-accident heat loads, assuming the worst single

active failure occurs coincident with the loss of offsite

power. Additionally, this system will also operate assuming

the worst case passive failure post-RAS.

An SW subsystem is considered OPERABLE when: a. The associated pump is OPERABLE; and

b. The associated piping, valves, heat exchangers, and instrumentation and controls required to perform the safety-related function are OPERABLE.

APPLICABILITY In MODEs 1, 2, 3, and 4, the SW System is a normally operating system, which is required to support the

OPERABILITY of the equipment serviced by the SW System and

required to be OPERABLE in these MODEs.

In MODEs 5 and 6, the OPERABILITY requirements of the SW System are determined by the systems it supports.

ACTIONS A.1 With one SW subsystem inoperable, action must be taken to restore OPERABLE status within 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br />. In this Condition,

the remaining OPERABLE SW subsystem is adequate to perform

the heat removal function. However, the overall reliability

is reduced because a single failure in the SW subsystem SW System B 3.7.7 BASES CALVERT CLIFFS - UNITS 1 & 2 B 3.7.7-3 Revision 2 could result in loss of SW System function. Required Action A.1 is modified by two Notes. The first Note

indicates that the applicable Conditions of LCO 3.8.1 should be entered if the inoperable SW subsystem results in an

inoperable emergency diesel generator. The second Note

indicates that the applicable Conditions and Required Actions of LCO 3.4.6 should be entered if an inoperable SW subsystem results in an inoperable SDC. The 72 hour8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> Completion Time is based on the redundant capabilities

afforded by the OPERABLE train, and the low probability of a

DBA occurring during this time period.

B.1 and B.2 If the SW subsystems cannot be restored to OPERABLE status within the associated Completion Time, the unit must be

placed in a MODE in which the LCO does not apply. To

achieve this status, the unit must be placed in at least

MODE 3 within 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br />, and in MODE 5 within 36 hours4.166667e-4 days <br />0.01 hours <br />5.952381e-5 weeks <br />1.3698e-5 months <br />.

The allowed Completion Times are reasonable, based on operating experience, to reach the required unit conditions

from full power conditions in an orderly manner and without challenging unit systems.

SURVEILLANCE SR 3.7.7.1 REQUIREMENTS Verifying the correct alignment for manual, power-operated, and automatic valves in the SW System flow path ensures that

the proper flow paths exist for SW System operation. This

SR does not apply to valves that are locked, sealed, or otherwise secured in position, since they are verified to be in the correct position prior to locking, sealing, or

securing. This SR also does not apply to valves that cannot

be inadvertently misaligned, such as check valves. This

surveillance test does not require any testing or valve manipulation; rather, it involves verification that those

valves capable of potentially being mispositioned are in the

correct position. This SR is modified by a Note indicating

that the isolation of the SW System components or systems

may render those components inoperable but does not affect

the OPERABILITY of the SW System.

SW System B 3.7.7 BASES CALVERT CLIFFS - UNITS 1 & 2 B 3.7.7-4 Revision 55 The Surveillance Frequency is controlled under the Surveillance Frequency Control Program.

SR 3.7.7.2 This SR verifies proper automatic operation of the SW System valves on an actual or simulated actuation signal (SIAS).

The SW System is a normally operating system that cannot be fully actuated as part of the normal testing. This

surveillance test is not required for valves that are

locked, sealed, or otherwise secured in the required

position under administrative controls. The Surveillance Frequency is controlled under the Surveillance Frequency Control Program. Note: There are currently no SW valves with an Engineered Safety Feature Actuation System signal

since automatic system reconfiguration during a LOCA is not

required.

SR 3.7.7.3 The SR verifies proper automatic operation of the SW System pumps on an actual or simulated actuation signal (SIAS).

The SW System is a normally operating system that cannot be

fully actuated as part of the normal testing during normal

operation. The Surveillance Frequency is controlled under the Surveillance Frequency Control Program.

REFERENCES 1. UFSAR, Section 9.5.2.3, "Saltwater System"

CREVS B 3.7.8 B 3.7 PLANT SYSTEMS

B 3.7.8 Control Room Emergency Ventilation System (CREVS)

BASES CALVERT CLIFFS - UNITS 1 & 2 B 3.7.8-1 Revision 42 BACKGROUND The CREVS provides a protected environment from which occupants can control the unit following an uncontrolled release of radioactivity, hazardous chemicals, or smoke.

The CREVS is a shared system providing protection for both Unit 1 and Unit 2.

The CREVS consists of two trains, including redundant

outside air intake ducts and redundant emergency

recirculation filter trains that recirculate and filter the

Control Room envelope (CRE) air and a CRE boundary that limits the inleakage of unfiltered air. The CREVS also has shared equipment, including an exhaust-to-atmosphere duct

containing redundant isolation valves and a normally closed

roof-mounted hatch, an exhaust-to-atmosphere duct from the

kitchen and toilet area of the Control Room containing a

single isolation valve, and common supply and return ducts

in both the standby and emergency recirculation portions of

the system. The shared equipment is considered to be a part

of each CREVS train. Each CREVS emergency recirculation

filter train consists of a prefilter, two high efficiency

particulate air (HEPA) filters for removal of aerosols, an

activated charcoal adsorber section for removal of elemental

and organic iodine and a fan. Ductwork, valves or dampers, doors, and barriers also form part of the system.

Instrumentation which actuates the system is addressed in

LCOs 3.3.4 and 3.3.8.

The CRE is the area within the confines of the CRE boundary that contains the spaces that Control Room occupants inhabit to control the Unit during normal and accident conditions.

This area encompasses the Control Room and may encompass non-critical areas to which frequent personnel access or continuous occupancy is not necessary in the event of an accident. The CRE is protected during normal operation, natural events, and accident conditions. The CRE boundary is the combination of walls, floor, roof, ducting, doors, penetrations, and equipment that physically form the CRE.

The OPERABILITY of the CRE boundary must be maintained to ensure that the inleakage of unfiltered air into the CRE will not exceed the inleakage assumed in the licensing basis CREVS B 3.7.8 BASES CALVERT CLIFFS - UNITS 1 & 2 B 3.7.8-2 Revision 42 analysis of DBA consequences to CRE occupants. The CRE and its boundary are defined in the Control Room Envelope Habitability Program.

The CREVS is an emergency system, parts of which may also

operate during normal unit operations in the standby mode of

operation. Actuation of the CREVS ensures the system is in

the emergency recirculation mode of operation, ensures the

unfiltered outside air intake and unfiltered exhaust-to-

atmosphere valves are closed, and aligns the system for

emergency recirculation of CRE air through the redundant trains of HEPA and charcoal filters. The prefilters remove

any large particles in the air and any entrained water

droplets present to prevent excessive loading of the HEPA

filters and charcoal adsorbers. A control room

recirculation signal (CRRS) initiates this filtered

ventilation of the air supply to the CRE.

The air recirculating through the CRE is continuously monitored by a radiation detector. Detector output above

the setpoint will cause actuation of the CREVS. The CREVS

operation in maintaining the Control Room habitable is

discussed in Reference 1, Section 9.8.2.3.

The redundant emergency recirculation filter train provides the required filtration should an excessive pressure drop

develop across the other filter train. A normally closed

hatch and double isolation valves are arranged in series to

prevent a breach of isolation from the outside atmosphere,

except for the exhaust from the Control Room kitchen and

toilet areas. The CREVS is designed in accordance with

Seismic Category I requirements.

The CREVS is designed to maintain a habitable environment in the CRE for 30 days of continuous occupancy after a DBA without exceeding a 5 rem TEDE for the duration of the accident.

APPLICABLE The CREVS components are generally arranged in redundant SAFETY ANALYSES safety-related ventilation trains although some equipment is shared between trains.

The CREVS provides automatic airborne radiological protection for the CRE occupants, as demonstrated by the CRE CREVS B 3.7.8 BASES CALVERT CLIFFS - UNITS 1 & 2 B 3.7.8-3 Revision 42 occupant dose analyses for the most limiting design basis fission product release presented in Reference 1, Section 14.24.

The CREVS provides protection from smoke and hazardous chemicals to the CRE occupants. The analysis of hazardous chemical releases demonstrates that the toxicity limits are not exceeded in the CRE following a hazardous chemical release. The evaluation of a smoke challenge demonstrates that it will not result in the inability of the CRE occupants to control the reactor either from the Control Room or from the remote shutdown panels.

The CREVS also provides automatically actuated airborne radiological protection for the Control Room operations, for

the design basis fuel handling accident presented in

Reference 1, Section 14.18, the control element assembly

ejection event (Reference 1, Section 14.13, the main steam

line break (Reference 1, Section 14.14), the steam generator

tube rupture (Reference 1, Section 14.15), and the seized

rotor event (Reference 1, Section 14.16). The fuel handling

accident does not assume a single failure to occur.

The worst case single active failure of a component of the CREVS, assuming a loss of offsite power, does not impair the

ability of the system to perform its design function (except

for one valve in the shared duct between the Control Room

and the emergency recirculation filter trains).

The CREVS satisfies 10 CFR 50.36(c)(2)(ii), Criterion 3.

LCO The CREVS is required to be OPERABLE to ensure that the Control Room is isolated and at least one emergency

recirculation filter train is available, assuming a single active failure. Total system failure could result in exceeding a dose of 5 rem TEDE in the event of a large radioactive release.

The CREVS is considered OPERABLE when the individual components necessary to limit CRE occupant exposure are OPERABLE. For MODEs 1, 2, 3, and 4, redundancy is required

and CREVS is considered OPERABLE when: a. Both supply fans are OPERABLE; CREVS B 3.7.8 BASES CALVERT CLIFFS - UNITS 1 & 2 B 3.7.8-4 Revision 42 b. Both recirculation fans are OPERABLE; c. Both fans included in the emergency recirculation filter trains are OPERABLE; d. Both HEPA filters and charcoal adsorbers are not excessively restricting flow, and are capable of

performing their filtration functions; e. Ductwork, valves, and dampers are OPERABLE, such that air circulation can be maintained; and f. The Control Room outside air intake can be isolated for the emergency recirculation mode of operation, assuming

a single failure.

In order for the CREVS trains to be considered OPERABLE, the CRE boundary must be maintained such that the CRE occupant dose from a large radioactive release does not exceed the calculated dose in the licensing basis consequence analysis for DBAs, and that CRE occupants are protected from hazardous chemicals and smoke.

The LCO is modified by a Note which indicates that only one CREVS redundant component is required to be OPERABLE during

movement of irradiated fuel assemblies, when both units are

in MODEs 5 or 6, or defueled. Therefore, with both units in

other than MODEs 1, 2, 3, or 4, redundancy is not required

for movement of irradiated fuel assemblies and CREVS is

considered OPERABLE when: a. One supply fan is OPERABLE;

b. One recirculation fan is OPERABLE;
c. One fan included in the OPERABLE emergency recirculation filter train is OPERABLE; d. One train of two HEPA filters and one charcoal adsorber are not excessively restricting flow, and are capable

of performing their filtration functions; and e. Associated ductwork, valves, and dampers are OPERABLE, such that air circulation can be maintained and the

Control Room can be isolated for the emergency

recirculation mode.

When implementing the Note (since redundancy is not required), only one of the two isolation valves in each CREVS B 3.7.8 BASES CALVERT CLIFFS - UNITS 1 & 2 B 3.7.8-5 Revision 42 outside air intake duct is required, and only one of the two isolation valves in the exhaust to atmosphere duct is

required. However, the non-operating flow path must be

capable of providing isolation of the Control Room from the

outside atmosphere.

The LCO is modified by a second Note which indicates that only one CREVS train is required to be OPERABLE for the

movement of irradiated fuel assemblies. Therefore,

redundancy is not required for movement of irradiated fuel

assemblies and only one CREVS train is required to be OPERABLE.

The LCO is modified by a third Note allowing the CRE boundary to be opened intermittently under administrative controls. This Note only applies to openings in the CRE boundary that can be rapidly restored to the design condition, such as doors, hatches, floor plugs, and access panels. For entry and exit through doors, the administrative control of the opening is performed by the person(s) entering or exiting the area. For other openings, these controls should be proceduralized and consist of stationing a dedicated individual at the opening who is in continuous communication with the operators in the CRE.

This individual will have a method to rapidly close the opening and to restore the CRE boundary to a condition equivalent to the design condition when the need for CRE isolation is indicated.

APPLICABILITY In MODEs 1, 2, 3, and 4, the CREVS must be OPERABLE to ensure that the CRE will remain habitable during and following a DBA.

During movement of irradiated fuel assemblies, the CREVS must be OPERABLE to cope with the release from a fuel

handling accident.

ACTIONS A.1 With one or more ducts with one Control Room outside air intake isolation valve inoperable in MODEs 1, 2, 3, or 4,

the OPERABLE Control Room outside air intake valve in each

affected duct must be closed immediately. This places the CREVS B 3.7.8 BASES CALVERT CLIFFS - UNITS 1 & 2 B 3.7.8-6 Revision 42 OPERABLE Control Room outside air intake isolation valve in each affected duct in its safety function required position.

B.1 With the toilet area exhaust isolation valve inoperable, action must be taken to restore OPERABLE status within

24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />. In this Condition, the toilet area exhaust cannot

be isolated, therefore, the valve must be restored to

OPERABLE status. The 24 hour2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> period allows enough time to

repair the valve while limiting the time the toilet area is

open to the atmosphere. The 24 hour2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> Completion Time is based on the low probability of a DBA occurring during this time period.

C.1 With one exhaust to atmosphere isolation valve inoperable in MODEs 1, 2, 3, or 4, action must be taken to restore

OPERABLE status within seven days. In this Condition, the

remaining OPERABLE exhaust to atmosphere isolation valve is

adequate to isolate the Control Room. However, the overall

reliability is reduced because a single failure in the

OPERABLE exhaust to atmosphere isolation valve could result

in loss of exhaust to atmosphere isolation valve function.

The seven day Completion Time is based on the low

probability of a DBA occurring during this time period, and

the ability of the remaining exhaust to atmosphere isolation

valve to provide the required isolation capability.

D.1, D.2, and D.3 If the unfiltered inleakage of potentially contaminated air past the CRE boundary and into the CRE can result in CRE occupant radiological dose greater than the calculated dose of the licensing basis analyses of DBA consequences (allowed to be up to 5 rem TEDE), or inadequate protection of CRE occupants from hazardous chemicals or smoke, the CRE boundary is inoperable. Actions must be taken to restore an OPERABLE CRE boundary within 90 days.

During the period that the CRE boundary is considered inoperable, action must be initiated to implement mitigation actions to lessen the effect on CRE occupants from the potential hazards of a radiological or chemical event or a CREVS B 3.7.8 BASES CALVERT CLIFFS - UNITS 1 & 2 B 3.7.8-7 Revision 52 challenge from smoke. Required Action D.3 allows time to restore the CRE boundary to OPERABLE status provided

mitigating actions can ensure that the CRE remains within

the licensing basis habitability limits for the occupants

following an accident. Compensatory measures are discussed

in Reference 2. These compensatory measures may also be used as mitigating actions as required by Required

Action D.2. Temporary analytical methods may also be used

as compensatory measures to restore OPERABILITY. Actions

must be taken within 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> to verify that, in the event

of a DBA, the mitigating actions will ensure that CRE occupant radiological exposures will not exceed the calculated dose of the licensing basis analysis of DBA

consequences, and that CRE occupants are protected from

hazardous chemicals and smoke. These mitigating actions

(i.e., actions that are taken to offset the consequences of

the inoperable CRE boundary) should be preplanned for

implementation upon entry into the condition, regardless of

whether entry is intentional or unintentional.

The 24 hour2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> Completion Time is reasonable based on the

determination that the mitigating actions will ensure

protection of the CRE occupants within analyzed limits while

limiting the probability that CRE occupants will have to

implement protective measures that may adversely affect

their ability to control the reactor and maintain it in a

safe shutdown condition in the event of a DBA. In addition,

the 90 day Completion Time is a reasonable time to diagnose,

plan, and possibly repair and test most problems with the

CRE boundary.

E.1 With one CREVS train inoperable for reasons other than Conditions A, B, C, or D in MODEs 1, 2, 3, or 4, action must

be taken to restore OPERABLE status within seven days. In

this Condition, the remaining OPERABLE CREVS subsystem is

adequate to perform CRE occupant protection function.

However, the overall reliability is reduced because a

failure in the OPERABLE CREVS train could result in loss of CREVS function. The seven day Completion Time is based on the low probability of a DBA occurring during this time

period, and the ability of the remaining train to provide

the required capability.

CREVS B 3.7.8 BASES CALVERT CLIFFS - UNITS 1 & 2 B 3.7.8-8 Revision 52 F.1, F.2, and F.3 If both CREVS trains are inoperable in MODE 1, 2, 3, or 4 for reasons other than an inoperable Control Room boundary (i.e., Condition D), at least one CREVS train must be returned to OPERABLE status within 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />. The Condition is modified by a Note stating it is not applicable if the second CREVS train is intentionally declared inoperable.

The Condition does not apply to voluntary removal of redundant systems or components from service. The Condition is only applicable if one train is inoperable for any reason and the second train is discovered to be inoperable, or if both trains are discovered to be inoperable at the same time. During the period that the CREVS trains are inoperable, action must be initiated to implement mitigating actions to lessen the effect on CRE occupants from potential hazards while both trains of CREVS are inoperable. In the event of a DBA, the mitigating actions will reduce the consequences of radiological exposures to the CRE occupants.

Specification 3.4.16, RCS Specific Activity, allows limited operation with the RCS activity significantly greater than the LCO limit. This presents a risk to the plant operator during an accident when all the CREVS trains are inoperable.

Therefore, it must be verified within one hour that LCO 3.4.16 is met. This Required Action does not require additional RCS sampling beyond that normally required by LCO 3.4.16.

At least one CREVS train must be returned to OPERABLE status within 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />. The Completion Time is based on Reference 3 which demonstrated that the 24 hour2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> Completion Time is acceptable based on the infrequent use of the Required Actions and the small incremental effect on plant risk.

G.1 Action G provides the actions to be taken when the Required Action and associated Completion Time of Condition B cannot

be met or with one or more CREVS trains inoperable due to an inoperable CRE boundary. It requires the immediate suspension of movement of irradiated fuel assemblies. This

places the unit in a condition that minimizes the accident

risk. This does not preclude the movement of fuel CREVS B 3.7.8 BASES CALVERT CLIFFS - UNITS 1 & 2 B 3.7.8-9 Revision 55 assemblies to a safe position. Since only one CREVS train must be OPERABLE for movement of irradiated fuel assemblies,

the Required Action is applicable only to the required CREVS

train.

H.1 If both CREVS trains are inoperable for reasons other than Conditions A, B, C, or D, or if one or more ducts have two

outside air intake isolation valves inoperable, or if two

exhaust to atmosphere isolation valves are inoperable during

movement of irradiated fuel assemblies, the CREVS may not be capable of performing the intended function and the unit is in a condition outside the accident analyses. Therefore,

movement of irradiated fuel must be suspended immediately.

This does not preclude the movement of fuel assemblies to a

safe condition.

I.1 and I.2 If the inoperable CREVs or Control Room boundary cannot be restored to OPERABLE status within the associated Completion

Time in MODE 1, 2, 3, or 4, the unit must be placed in a

mode that minimizes the accident risk. To achieve this

status the unit must be placed in at least MODE 3 within six

hours and in MODE 5 within 36 hours4.166667e-4 days <br />0.01 hours <br />5.952381e-5 weeks <br />1.3698e-5 months <br />. The allowed Completion

Times are reasonable, based on operating experience, to

reach the required unit conditions from full power

conditions in an orderly manner and without challenging unit systems.

SURVEILLANCE SR 3.7.8.1 REQUIREMENTS Standby systems should be checked periodically to ensure that they function properly. Since the environment and

normal operating conditions on this system are not severe,

testing each required CREVS filter train once every month

provides an adequate check on this system.

The Surveillance Frequency is controlled under the Surveillance Frequency Control Program.

CREVS B 3.7.8 BASES CALVERT CLIFFS - UNITS 1 & 2 B 3.7.8-10 Revision 55 SR 3.7.8.2 This SR verifies that the required CREVS testing is performed in accordance with the Ventilation Filter Testing

Program (VFTP). The CREVS filter tests are in accordance

with portions of Reference 4. The VFTP includes testing

HEPA filter performance, charcoal adsorber efficiency,

minimum system flow rate, and the physical properties of the

activated charcoal (general use and following specific

operations). Specific test Frequencies and additional

information are discussed in detail in the VFTP.

SR 3.7.8.3 This SR verifies each CREVS train starts and operates on an actual or simulated actuation signal (CRRS). The Surveillance Frequency is controlled under the Surveillance Frequency Control Program.

SR 3.7.8.4 This SR verifies the OPERABILITY of the CRE boundary by testing for unfiltered air inleakage past the CRE boundary

and into the CRE. The details of the testing are specified

in the Control Room Envelope Habitability Program.

The CRE is considered habitable when the radiological dose to the CRE occupants calculated in the licensing basis

analysis of DBA consequences is no more than 5 rem TEDE and

the CRE occupants are protected from hazardous chemicals and

smoke. This SR verifies that the unfiltered air inleakage

into the CRE is no greater than the flow rate assumed in the

licensing basis analysis of DBA consequences. When

unfiltered air inleakage is greater than the assumed flow

rate, Condition E must be entered. Options for restoring

the CRE boundary to OPERABLE status include changing the

licensing basis DBA consequences analysis, repairing the CRE

boundary, or a combination of these actions. Depending upon

the nature of the problem and the corrective action, a full

scope inleakage test may not be necessary to establish that the CRE boundary has been restored to OPERABLE status.

CREVS B 3.7.8 BASES CALVERT CLIFFS - UNITS 1 & 2 B 3.7.8-11 Revision 52 REFERENCES 1. UFSAR 2. Regulatory Guide 1.196, Revision 0, "Control Room Habitability at Light-Water Nuclear Power Reactors,"

May 2003 3. WCAP-16125-NP-A, Justification for Risk-Informed Modifications to Selected Technical Specifications for Conditions Leading to Exigent Plant Shutdown, Revision 2, August 2010 4. Regulatory Guide 1.52, Revision 2, "Design, Testing, and Maintenance Criteria for Post Accident Engineered-Safety-Feature Atmosphere Cleanup System Air Filtration and Adsorption Units of Light-Water-Cooled Nuclear Power Plants," March 1978

CRETS B 3.7.9 B 3.7 PLANT SYSTEMS

B 3.7.9 Control Room Emergency Temperature System (CRETS)

BASES CALVERT CLIFFS - UNITS 1 & 2 B 3.7.9-1 Revision 2 BACKGROUND The CRETS provides temperature control for the Control Room following isolation of the Control Room. The CRETS is a shared system which is supported by the CREVS, since the CREVS must be operating in the emergency recirculation mode for CRETS to perform its safety function.

The CRETS consists of two independent, redundant trains that provide cooling of recirculated Control Room air. Each train consists of cooling coils, instrumentation, and

controls to provide for Control Room temperature control.

The CRETS is a subsystem providing air temperature control

for the Control Room.

The CRETS is an emergency system, parts of which may also operate during normal unit operations in the standby mode of

operation. A single train will provide the required

temperature control to maintain the Control Room below 104°F. The CRETS operation to maintain the Control Room temperature is discussed in Reference 1.

APPLICABLE The design basis of the CRETS is to maintain temperature SAFETY ANALYSES of the Control Room environment throughout 30 days of continuous occupancy.

The CRETS components are arranged in redundant safety-related trains. During emergency operation, the CRETS

maintains the temperature below 104°F. A single active

failure of a component of the CRETS, assuming a loss of offsite power, does not impair the ability of the system to perform its design function. Redundant detectors and

controls are provided for Control Room temperature control.

The CRETS is designed in accordance with Seismic Category I

requirements. The CRETS is capable of removing sensible and

latent heat loads from the Control Room, considering equipment heat loads and personnel occupancy requirements,

to ensure equipment OPERABILITY.

The CRETS satisfies 10 CFR 50.36(c)(2)(ii), Criterion 3.

CRETS B 3.7.9 BASES CALVERT CLIFFS - UNITS 1 & 2 B 3.7.9-2 Revision 31 LCO Two independent and redundant trains of the CRETS are required to be OPERABLE to ensure that at least one is

available, assuming a single failure disables the other

train following isolation of the Control Room. Total system

failure could result in the equipment operating temperature

exceeding limits in the event of an accident requiring isolation of the Control Room.

The CRETS is considered OPERABLE when the individual components that are necessary to maintain the Control Room

temperature are OPERABLE. The required components include

the cooling coils and associated temperature control

instrumentation. In addition, the CRETS must be OPERABLE to

the extent that air circulation can be maintained.

For MODEs 1, 2, 3, and 4, redundancy is required and both trains must be OPERABLE. The LCO is modified by a Note

which indicates that only one CRETS train is required to be

OPERABLE for the movement of irradiated fuel assemblies.

Therefore, redundancy is not required for movement of

irradiated fuel assemblies and only one CRETS train is required to be OPERABLE.

APPLICABILITY In MODEs 1, 2, 3, and 4, and during movement of irradiated fuel assemblies, the CRETS must be OPERABLE to ensure that

the Control Room temperature will not exceed equipment

OPERABILITY requirements following isolation of the Control

Room. ACTIONS A.1 With one CRETS train inoperable in MODEs 1, 2, 3, or 4, action must be taken to restore OPERABLE status within

30 days. In this Condition, the remaining OPERABLE CRETS

train is adequate to maintain the Control Room temperature

within limits. The 30 day Completion Time is reasonable,

based on the low probability of an event occurring requiring

Control Room isolation, consideration that the remaining

train can provide the required capabilities, and the

alternate safety or non-safety-related cooling means that

are available.

CRETS B 3.7.9 BASES CALVERT CLIFFS - UNITS 1 & 2 B 3.7.9-3 Revision 55 B.1 and B.2 If the Required Actions and associated Completion Times of Condition A are not met in MODEs 1, 2, 3, or 4, the unit

must be placed in a MODE that minimizes the accident risk.

To achieve this status, the unit must be placed in at least

MODE 3 within 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br />, and in MODE 5 within 36 hours4.166667e-4 days <br />0.01 hours <br />5.952381e-5 weeks <br />1.3698e-5 months <br />. The allowed Completion Times are reasonable, based on operating experience, to reach the required unit conditions from full

power conditions in an orderly manner and without

challenging unit systems.

C.1 If both CRETS trains are inoperable in MODEs 1, 2, 3, or 4, or during movement of irradiated fuel assemblies, the CRETS

may not be capable of performing the intended function and

the unit is in a condition outside the accident analysis.

Therefore, LCO 3.0.3 must be entered immediately and

movement of irradiated fuel must be suspended immediately.

This does not preclude the movement of fuel assemblies to a safe condition.

SURVEILLANCE SR 3.7.9.1 REQUIREMENTS This SR verifies each required CRETS train has the capability to maintain Control Room temperature 104°F for 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> in the recirculation mode. During this test, the backup Control Room air conditioner is to be de-

energized. This SR consists of a combination of testing.

The Surveillance Frequency is controlled under the Surveillance Frequency Control Program.

REFERENCES 1. UFSAR, Section 9.8.2.3, "Auxiliary Building Ventilating Systems"

SFPEVS B 3.7.11 B 3.7 PLANT SYSTEMS

B 3.7.11 Spent Fuel Pool Exhaust Ventilation System (SFPEVS)

BASES CALVERT CLIFFS - UNITS 1 & 2 B 3.7.11-1 Revision 41 BACKGROUND The SFPEVS exhausts airborne radioactive particulates and gases from the area of the fuel pool into the plant ventilation stack following a fuel handling accident involving recently irradiated fuel.

The SFPEVS consists of two independent, redundant exhaust fans. Ductwork, valves or dampers, and instrumentation also form part of the system. The SFPEVS is supplied power by

one non-safety-related power supply.

The SFPEVS is operated during normal unit operations. When movement of the air is required (i.e., during movement of recently irradiated fuel assemblies in the Auxiliary

Building), normal air discharges from the fuel handling area

in the Auxiliary Building.

The SFPEVS is discussed in Reference 1, Sections 9.8.2.3 and 14.18, because it may be used for normal, as well as post-accident ventilation.

APPLICABLE The SFPEVS is designed to mitigate the consequences of a SAFETY ANALYSES fuel handling accident involving handling recently irradiated fuel (i.e., fuel that has occupied part of a

critical reactor core within the previous 55 days), in which all rods in the fuel assembly are assumed to be damaged.

The analysis of the fuel handling accident is given in

Reference 1, Section 14.18. The DBA analysis of the fuel

handling accident assumes that the SFPEVS is functional and exhausts airborne radioactive particulates and gases from the fuel pool area into the plant ventilation stack. The analysis follows the guidance provided in Reference 2.

The SFPEVS satisfies 10 CFR 50.36(c)(2)(ii), Criterion 3.

LCO Two exhaust fans and other equipment listed in the Background Section are required to be OPERABLE and in

operation.

The SFPEVS is considered OPERABLE when the individual components necessary to direct exhaust into the ventilation SFPEVS B 3.7.11 BASES CALVERT CLIFFS - UNITS 1 & 2 B 3.7.11-2 Revision 41 stack are OPERABLE. The SFPEVS is considered OPERABLE when its associated: a. Fans are OPERABLE; and b. Ductwork, valves, and dampers are OPERABLE, and air circulation can be maintained.

The SFPEVS is considered in operation when an OPERABLE exhaust fan is in operation.

APPLICABILITY During movement of recently irradiated fuel assemblies in the Auxiliary Building, the SFPEVS is required to be

OPERABLE and in operation to mitigate the consequences of a

fuel handling accident involving handling recently

irradiated fuel by minimizing the atmospheric dispersion to the Control Room. Due to radioactive decay, the SFPEVS is only required to mitigate fuel handling accidents involving

handling recently irradiated fuel (i.e., fuel that has

occupied part of a critical reactor core within the previous 55 days).

ACTIONS A.1 and A.2 When one SFPEVS exhaust fan is inoperable, action must be taken to verify an OPERABLE SFPEVS train is in operation, or

movement of recently irradiated fuel assemblies in the

Auxiliary Building must be suspended. One OPERABLE SFPEVS train consists of one OPERABLE exhaust fan. This ensures the proper equipment is operating for the Applicable Safety Analysis.

B.1 When there is no OPERABLE SFPEVS train or there is no OPERABLE SFPEVS train in operation during movement of

recently irradiated fuel assemblies in the Auxiliary

Building, action must be taken to place the unit in a

condition in which the LCO does not apply. This Action

involves immediately suspending movement of recently

irradiated fuel assemblies in the Auxiliary Building. This does not preclude the movement of fuel to a safe position.

SFPEVS B 3.7.11 BASES CALVERT CLIFFS - UNITS 1 & 2 B 3.7.11-3 Revision 55 SURVEILLANCE SR 3.7.11.1 REQUIREMENTS The SR requires verification that the SFPEVS is in operation. Verification includes verifying that one exhaust

fan is operating and discharging into the ventilation stack.

The Surveillance Frequency is controlled under the Surveillance Frequency Control Program.

SR 3.7.11.2 Deleted.

SR 3.7.11.3 This SR verifies the integrity of the spent fuel storage pool area. The ability of the spent fuel storage pool area

to maintain negative pressure with respect to potentially

uncontaminated adjacent areas is periodically tested to

verify proper function of the SFPEVS. During operation, the

spent fuel storage pool area is designed to maintain a

slight negative pressure in the spent fuel storage pool

area, with respect to adjacent areas, to ensure that

exhausted air is directed to the ventilation stack.

The Surveillance Frequency is controlled under the Surveillance Frequency Control Program.

REFERENCES 1. UFSAR 2. Regulatory Guide 1.183, Alternative Radiological Source Terms for Evaluating Design Basis Accidents at Nuclear Power Reactors, July 2000

PREVS B 3.7.12 B 3.7 PLANT SYSTEMS

B 3.7.12 Penetration Room Exhaust Ventilation System (PREVS)

BASES CALVERT CLIFFS - UNITS 1 & 2 B 3.7.12-1 Revision 52 BACKGROUND The PREVS filters air from the penetration room.

The PREVS consists of two independent and redundant trains.

Each train consists of a prefilter, a HEPA filter, an activated charcoal adsorber section for removal of gaseous activity (principally iodines), and a fan. Ductwork, valves

or dampers, and instrumentation also form part of the

system. The system initiates filtered ventilation following

receipt of a containment isolation actuation signal.

The PREVS is a standby system, which may also operate during normal unit operations. During emergency operations, the

PREVS dampers are realigned, and fans are started to

initiate filtration. Upon receipt of the actuating

Engineered Safety Feature Actuation System signal(s), normal

air discharges from the penetration room, and the stream of

ventilation air discharges through the system filter trains.

The prefilters remove any large particles in the air to

prevent excessive loading of the HEPA filters and charcoal

adsorbers.

The PREVS is discussed in Reference 1, Section 6.6.2, as it may be used for normal, as well as post-accident, atmospheric cleanup functions.

APPLICABLE The design basis of the PREVS is established by the Maximum SAFETY ANALYSES Hypothetical Accident. The system is credited with filtering the radioactive material released through the containment vent when the line is open. Also commensurate with the guidance in Reference 2, a conservative bypass fraction from the Containment to the penetration rooms is

assumed. Following a LOCA, the containment isolation signal

will start both of the fans associated with the PREVS,

filtering the exhaust through the HEPA and charcoal filters,

and directing the exhaust into the ventilation stack. The

analysis of the effects and consequences of a Maximum

Hypothetical Accident are presented in Reference 1,

Section 14.24 and follows the guidance presented in

Reference 3.

PREVS B 3.7.12 BASES CALVERT CLIFFS - UNITS 1 & 2 B 3.7.12-2 Revision 41 As a layer of defense, the Penetration Room Exhaust Ventilation System also provides filtered ventilation of radioactive materials leaking from ECCS equipment within the

penetration room following an accident, however, credit for

this feature was not assumed in the accident analysis

(Reference 1, Section 14.24).

The PREVS satisfies 10 CFR 50.36(c)(2)(ii), Criterion 3.

LCO Two independent and redundant trains of the PREVS are required to be OPERABLE to ensure that at least one train is

available, assuming there is a single failure disabling the

other train coincident with a loss of offsite power.

The PREVS is considered OPERABLE when the individual components necessary to control radioactive releases are

OPERABLE in both trains. A PREVS train is considered

OPERABLE when its associated: a. Fan is OPERABLE;

b. High efficiency particulate air filter and charcoal adsorber are not excessively restricting flow, and are

capable of performing the filtration functions; and c. Ductwork, valves, and dampers are OPERABLE, and circulation can be maintained.

APPLICABILITY In MODEs 1, 2, and 3, the PREVS is required to be OPERABLE to mitigate the potential radioactive material release from

a Maximum Hypothetical Accident.

In MODEs 4, 5, and 6, the PREVS is not required to be OPERABLE, since the RCS temperature and pressure are low and

there is insufficient energy to result in the conditions assumed in the accident analysis.

ACTIONS A.1 With one PREVS train inoperable, action must be taken to restore OPERABLE status within seven days. During this time

period, the remaining OPERABLE train is adequate to perform

the PREVS function. The seven day Completion Time is

reasonable based on the low probability of a DBA occurring PREVS B 3.7.12 BASES CALVERT CLIFFS - UNITS 1 & 2 B 3.7.12-3 Revision 52 during this time period, and the consideration that the remaining train can provide the required capability.

B.1 and B.2 With two PREVS trains inoperable, action must be taken to restore at least one PREVS train to OPERABLE status within 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />. The Condition is modified by a Note stating it is not applicable if the second PREVS train is intentionally declared inoperable. The Condition does not apply to voluntary removal of redundant systems or components from service. The Condition is only applicable if one train is inoperable for any reason and the second train is discovered to be inoperable, or if both trains are discovered to be inoperable at the same time. In addition, at least one train of containment spray must be verified to be OPERABLE within one hour. In the event of an accident, containment spray reduces the potential radioactive release from the containment, which reduces the consequences of the inoperable PREVS trains. The Completion Time is based on Reference 4 which demonstrated that the 24 hour2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> Completion Time is acceptable based on the infrequent use of the Required Actions and the small incremental effect on plant risk.

C.1 and C.2 If the inoperable train cannot be restored to OPERABLE status within the associated Completion Time, the unit must

be placed in a MODE in which the LCO does not apply. To

achieve this status, the unit must be placed in at least

MODE 3 within 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br />, and in MODE 4 within 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br />. The

allowed Completion Times are reasonable, based on operating

experience, to reach the required unit conditions from full

power conditions in an orderly manner and without challenging unit systems.

SURVEILLANCE SR 3.7.12.1 REQUIREMENTS Standby systems should be checked periodically to ensure that they function properly. As the environment and normal

operating conditions on this system are not severe, testing

each train once every month provides an adequate check on

this system.

PREVS B 3.7.12 BASES CALVERT CLIFFS - UNITS 1 & 2 B 3.7.12-4 Revision 55 The test is performed by initiating the system from the Control Room, ensuring flow through the HEPA filter and

charcoal adsorber train, and verifying this system operates for 15 minutes. The Surveillance Frequency is controlled under the Surveillance Frequency Control Program.

SR 3.7.12.2 This SR verifies the performance of PREVS filter testing in accordance with the VFTP. The PREVS filter tests are in

accordance with portions of Reference 5. The VFTP includes

testing the performance of the HEPA filter, charcoal

adsorber efficiency, minimum system flow rate, and the

physical properties of the activated charcoal (general use

and following specific operations). Specific test

frequencies and additional information are discussed in

detail in the VFTP.

SR 3.7.12.3 This SR verifies that each PREVS train starts and operates on an actual or simulated actuation signal (Containment

Isolation Signal). The Surveillance Frequency is controlled under the Surveillance Frequency Control Program.

REFERENCES 1. UFSAR 2. Regulatory Guide 1.194, Atmospheric Relative Concentrations for Control Room Radiological

Habitability Assessments at Nuclear Power Plants, June

2003 3. Regulatory Guide 1.183, Alternative Radiological Source Terms for Evaluating Design Basis Accidents at Nuclear Power Reactors, July 2000 4. WCAP-16125-NP-A, Justification for Risk-Informed Modifications to Selected Technical Specifications for

Conditions Leading to Exigent Plant Shutdown,

Revision 2, August 2010 PREVS B 3.7.12 BASES CALVERT CLIFFS - UNITS 1 & 2 B 3.7.12-5 Revision 55 5. Regulatory Guide 1.52, Revision 2, "Design, Testing, and Maintenance Criteria for Post Accident Engineered-

Safety-Feature Atmosphere Cleanup System Air Filtration

and Adsorption Units of Light-Water-Cooled Nuclear Power Plants," March 1978

SFP Water Level B 3.7.13 B 3.7 PLANT SYSTEMS

B 3.7.13 Spent Fuel Pool (SFP) Water Level

BASES CALVERT CLIFFS - UNITS 1 & 2 B 3.7.13-1 Revision 41 BACKGROUND The minimum water level in the SFP meets the assumptions of iodine decontamination factors following a fuel handling

accident. The specified water level shields and minimizes

the general area dose when the storage racks are filled to their maximum capacity. The water also provides shielding during the movement of spent fuel.

A general description of the SFP design is given in Reference 1, Section 9.7.2, and the SFP Cooling and Cleanup

System is given in Reference 1, Section 9.4.1. The

assumptions of the fuel handling accident are given in Reference 1, Section 14.18.

APPLICABLE Per Reference 2, the Fuel Handling Accident (FHA) analysis SAFETY ANALYSES may assume a total iodine decontamination factor of 200 based on a minimum water depth of 23 feet. The minimum water level requirement ensures that sufficient water depth

is available to remove 99.5% of gap activity, which is comprised of 16% I-131 and 10% of all other iodine isotopes released from the rupture of an irradiated fuel assembly.

The Technical Specifications requirement of 21.5 feet of water above fuel assemblies seated in the SFP storage racks

is sufficient to preserve the required 23 feet of water

because an FHA was assumed to occur as a fuel assembly

strikes the bottom of the SFP.

When assemblies are placed on rack spacers with their upper end fittings removed, an FHA caused by a dropped heavy object would result in a lower decontamination factor based

on reduced water coverage. A revised decontamination factor

of 120 for an FHA during reconstitution or inspection with 20.4 feet of water between the top of the pin and the

surface of the water was computed for an assembly placed on a 20.5 inch rack spacer with its upper end fitting removed.

Note that this is very conservative, since normal level

control will result in at least 21.5 feet of water above

exposed fuel pins. This results in a 99.17% removal rate.

SFP Water Level B 3.7.13 BASES CALVERT CLIFFS - UNITS 1 & 2 B 3.7.13-2 Revision 55 The SFP water level satisfies 10 CFR 50.36(c)(2)(ii),

Criteria 2 and 3.

LCO The specified water level preserves the assumptions of the fuel handling accident analysis (Reference 1,

Section 14.18). As such, it is the minimum required for fuel storage, reconstitution, and movement within the fuel

storage pool.

APPLICABILITY This LCO applies during movement of irradiated fuel assemblies in the SFP since the potential for a release of fission products exists.

ACTIONS A.1 Required Action A.1 is modified by a Note indicating that LCO 3.0.3 does not apply.

When the initial conditions for an accident cannot be met, steps should be taken to preclude the accident from

occurring. When the SFP water level is lower than the

required level, the movement of irradiated fuel assemblies

in the SFP is immediately suspended. This effectively

precludes a spent fuel handling accident from occurring.

This does not preclude moving a fuel assembly to a safe

position.

If moving irradiated fuel assemblies while in MODEs 5 or 6, LCO 3.0.3 would not specify any action. If moving

irradiated fuel assemblies while in MODEs 1, 2, 3, and 4,

the fuel movement is independent of reactor operations.

Therefore, in either case, inability to suspend movement of

irradiated fuel assemblies is not sufficient reason to require a reactor shutdown.

SURVEILLANCE SR 3.7.13.1 REQUIREMENTS This SR verifies sufficient SFP water is available in the event of a fuel handling accident. The water level in the

SFP must be checked periodically. The Surveillance Frequency is controlled under the Surveillance Frequency Control Program.

SFP Water Level B 3.7.13 BASES CALVERT CLIFFS - UNITS 1 & 2 B 3.7.13-3 Revision 41 During refueling operations, the level in the SFP is normally at equilibrium with that of the refueling canal.

REFERENCES 1. UFSAR 2. Regulatory Guide 1.183, Alternative Radiological Source Terms for Evaluating Design Basis Accidents at Nuclear Power Reactors, July 2000

Secondary Specific Activity B 3.7.14 B 3.7 PLANT SYSTEMS

B 3.7.14 Secondary Specific Activity

BASES CALVERT CLIFFS - UNITS 1 & 2 B 3.7.14-1 Revision 41 BACKGROUND Activity in the secondary coolant results from steam generator tube outleakage from the RCS. Under steady state

conditions, the activity is primarily iodines with

relatively short half lives, and thus is an indication of current conditions. During transients, DOSE EQUIVALENT I-131 spikes have been observed as well as

increased releases of some noble gases. Other fission

product isotopes, as well as activated corrosion products in

lesser amounts, may also be found in the secondary coolant.

A limit on secondary coolant specific activity during power operation minimizes releases to the environment because of

normal operation, anticipated operational occurrences, and

accidents.

This limit is lower than the activity value that might be expected from a 100 gallons per day tube leak (LCO 3.4.13) of primary coolant at the limit of 0.5

µCi/gm (LCO 3.4.15).

The main SLB is assumed to result in the release of the noble gas and iodine activity contained in the steam

generator inventory, the feedwater, and reactor coolant

LEAKAGE via flashing directly to the environment through the main steam gooseneck.

APPLICABLE The accident analysis of the main SLB, as discussed in SAFETY ANALYSES Reference 1, assumes the initial secondary coolant specific activity to have a radioactive isotope concentration of 0.10 µCi/gm DOSE EQUIVALENT I-131. This secondary activity, together with the Technical Specification primary system activity, and failed fuel activity, is used in the analysis for determining the radiological consequences of the postulated accident. The accident analysis shows that the radiological consequences of a main SLB do not exceed

the acceptance criteria given in References 1 and 2.

With the loss of offsite power post-main SLB, the remaining steam generator is available for core decay heat dissipation

by venting steam to the atmosphere through MSSVs and ADVs.

The AFW System supplies the necessary makeup to the steam

generator. Venting continues until the reactor coolant Secondary Specific Activity B 3.7.14 BASES CALVERT CLIFFS - UNITS 1 & 2 B 3.7.14-2 Revision 41 temperature and pressure have decreased sufficiently for the SDC System to complete the cooldown.

Other accidents or transients, such as a steam generator tube rupture, a seized rotor event, and a control element assembly ejection event, involve a partial release of the secondary activity via steam release to the atmosphere via the ADVs and MSSVs. These releases contribute to the offsite and Control Room doses listed in Reference 1, Section 14. These accident analyses show that the radiological consequences of a DBA do not exceed the acceptance criteria given in References 1 and 2.

Secondary specific activity limits satisfy 10 CFR 50.36(c)(2)(ii), Criterion 2.

LCO As indicated in the Applicable Safety Analyses, the specific activity limit in the secondary coolant system of 0.10 µCi/gm DOSE EQUIVALENT I-131 limits the radiological consequences of a DBA to the acceptance criteria given in Reference 1.

Monitoring the specific activity of the secondary coolant ensures that when secondary specific activity limits are

exceeded, appropriate actions are taken in a timely manner

to place the unit in an operational MODE that would minimize the radiological consequences of a DBA.

APPLICABILITY In MODEs 1, 2, 3, and 4, the limits on secondary specific activity apply due to the potential for secondary steam

releases to the atmosphere.

In MODEs 5 and 6, the steam generators are not being used for heat removal. Both the RCS and steam generators are

depressurized, and primary to secondary LEAKAGE is minimal.

Therefore, monitoring of secondary specific activity is not required.

ACTIONS A.1 and A.2 DOSE EQUIVALENT I-131 exceeding the allowable value in the secondary coolant, is an indication of a problem in the RCS,

and contributes to increased post-accident doses. If Secondary Specific Activity B 3.7.14 BASES CALVERT CLIFFS - UNITS 1 & 2 B 3.7.14-3 Revision 55 secondary specific activity cannot be restored to within limits in the associated Completion Time, the unit must be

placed in a MODE in which the LCO does not apply. To

achieve this status, the unit must be placed in at least

MODE 3 within 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br />, and in MODE 5 within 36 hours4.166667e-4 days <br />0.01 hours <br />5.952381e-5 weeks <br />1.3698e-5 months <br />. The

allowed Completion Times are reasonable, based on operating experience, to reach the required unit conditions from full power conditions in an orderly manner and without challenging unit systems.

SURVEILLANCE SR 3.7.14.1 REQUIREMENTS This SR ensures that the secondary specific activity is within the limits of the accident analysis. A gamma isotope

analysis of the secondary coolant, which determines DOSE

EQUIVALENT I-131, confirms the validity of the safety

analysis assumptions as to the source terms in post-accident

releases. It also serves to identify and trend any unusual

isotopic concentrations that might indicate changes in

reactor coolant activity or LEAKAGE. The Surveillance Frequency is controlled under the Surveillance Frequency Control Program.

REFERENCES 1. UFSAR, Chapter 14, "Safety Analysis" 2. Regulatory Guide 1.183, Alternative Radiological Source Terms for Evaluating Design Basis Accidents at Nuclear Power Reactors, July 2000

MFIVs B 3.7.15 B 3.7 PLANT SYSTEMS

B 3.7.15 Main Feedwater Isolation Valves (MFIVs)

BASES CALVERT CLIFFS - UNITS 1 & 2 B 3.7.15-1 Revision 2 BACKGROUND The MFIVs isolate MFW flow to the secondary side of the steam generators following a HELB. The consequences of HELBs occurring in the main steam lines or in the MFW lines downstream of the MFIVs will be mitigated by their closure.

Closure of the MFIVs effectively terminates the addition of feedwater to an affected steam generator, limiting the mass

and energy release for SLBs /or feedwater line breaks (FWLBs) inside the Containment Structure upstream of the reverse flow check valve, and reducing the cooldown effects for SLBs.

The MFIVs isolate the non

-safety-related portions from the safety-related portion of the system. In the event of a secondary side pipe rupture inside the Containment Structure upstream of the reverse flow check valve, the valves limit the quantity of high energy fluid that enters the Containment Structure through the break.

One MFIV is located on each MFW line, outside, but close to, the Containment Structure

. The MFIVs are located so that AFW may be supplied to a steam generator following MFIV closure. The piping volume from the valve to the steam

generator must be accounted for in calculating mass and

energy releases.

The MFIVs close on receipt of a steam generator isolation signal generated by low steam generator pressure. The steam generator isolation signal also actuates the MSIVs to close.

The MFIVs may also be actuated manually. In addition

, the MFIVs reverse flow check valve inside the Containment Structure is available to isolate the feedwater line penetrating the Containment Structure

, and to ensure that the consequences of events do not exceed the capacity of the Containment Cooling S ystem. A description of the MFIVs operation on receipt of an steam generator isolation signal is found in Reference 1

.

MFIVs B 3.7.15 BASES CALVERT CLIFFS - UNITS 1 & 2 B 3.7.15-2 Revision 13 APPLICABLE The design basis of the MFIVs is established by the analysis SAFETY ANALYSES for the large SLB. It is also influenced by the accident analysis for the large FWLB.

Failure of an MFIV to close following an SLB or FWLB can result in additional mass and energy to the steam generator's contributing to cooldown. This failure also results in additional mass and energy releases following an

SLB or FWLB event.

The MFIVs satisfy 10 CFR 50.36(c)(2)(ii), Criterion 3.

LCO This LCO ensures that the MFIVs will isolate MFW flow to the steam generators. Following an FWLB or SLB, these valves

will also isolate the non-safety-related portions from the

safety-related portions of the system. This LCO requires

that one MFIV in each feedwater line be OPERABLE. The MFIVs

are considered OPERABLE when the isolation times are within

limits, and are closed on an isolation actuation signal.

Failure to meet the LCO requirements can result in additional mass and energy being released to the Containment

Structure following an SLB or FWLB inside the Containment

Structure. Failure to meet the LCO can also add additional

mass and energy to the steam generators contributing to cooldown.

APPLICABILITY The MFIVs must be OPERABLE whenever there is significant mass and energy in the RCS and steam generators.

In MODEs 1, 2, and 3, the MFIVs are required to be OPERABLE in order to limit the amount of available fluid that could

be added to the Containment Structure in the case of a

secondary system pipe break inside the Containment

Structure.

In MODEs 4, 5, and 6, steam generator energy is low.

MFIVs B 3.7.15 BASES CALVERT CLIFFS - UNITS 1 & 2 B 3.7.15-3 Revision 14 ACTIONS The ACTIONS table is modified by a Note indicating that separate Condition entry is allowed for each valve.

A.1 With one MFIV inoperable, action must be taken to restore the valve to OPERABLE status within 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br />.

The 72 hour8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> Completion Time takes into account the isolation capability afforded by the MFW regulating valves, and

tripping of the MFW pumps, and the low probability of an

event occurring during this time period that would require

isolation of the MFW flow paths.

B.1 and B.2 If the MFIVs cannot be restored to OPERABLE status in the associated Completion Time, the unit must be placed in a

MODE in which the LCO does not apply. To achieve this

status, the unit must be placed in at least MODE 3 within

6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br />, and in MODE 4 within 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br />. The allowed

Completion Times are reasonable, based on operating

experience, to reach the required unit conditions from full

power conditions in an orderly manner and without challenging unit systems.

SURVEILLANCE SR 3.7.15.1 REQUIREMENTS This SR ensures the closure time for each MFIV is 65 seconds by manual isolation. The MFIV closure time is assumed in the accident and containment analyses.

The Frequency is in accordance with the Inservice Testing Program. The MFIVs are tested during each refueling outage

in accordance with Reference 2, and sometimes during other

cold shutdown periods. The Frequency demonstrates the valve

closure time at least once per refueling cycle. Operating

experience has shown that these components usually pass the surveillance test when performed.

MFIVs B 3.7.15 BASES CALVERT CLIFFS - UNITS 1 & 2 B 3.7.15-4 Revision 38 REFERENCES 1. UFSAR, Section 14.4.2, "Sequence of Events" 2. ASME Code for Operation and Maintenance of Nuclear Power Plants

SFP Boron Concentration B 3.7.16 B 3.7 PLANT SYSTEMS

B 3.7.16 Spent Fuel Pool (SFP) Boron Concentration

BASES CALVERT CLIFFS - UNITS 1 & 2 B 3.7.16-1 Revision 23 BACKGROUND Fuel assemblies are stored in the spent fuel racks in accordance with criteria based on 10 CFR 50.68. If credit is taken for soluble boron, the k-effective of the spent

fuel storage racks loaded with fuel of the maximum fuel assembly reactivity must not exceed 0.95, at a 95%

probability, 95% confidence level, if flooded with borated

water, and the k-effective must remain below 1.0

(subcritical) at a 95% probability, 95% confidence level, if

flooded with unborated water. In addition, the maximum

nominal U-235 enrichment of the fresh fuel assemblies is limited to 5.0 weight percent.

APPLICABLE The criticality analyses were done such that the criteria of SAFETY ANALYSES 10 CFR 50.68 are met. Boron dilution events are credible, postulated accidents, when credit for soluble boron is

taken. The minimum SFP boron concentration in this

Technical Specification supports the initial boron concentration assumption in the dilution calculations.

For other non-dilution accident scenarios, the double contingency principle of ANSI N 16.1-1975 requires two

unlikely, independent concurrent events to produce a

criticality accident and thus allows credit for the nominal

soluble boron concentration, as defined in LCO 3.7.16.

The concentration of dissolved boron in the SFPs satisfies Criterion 2 of 10 CFR 50.36(c)(2)(ii).

LCO The specified concentration of dissolved boron in the SFP preserves the assumptions used in the analyses of the

potential accident scenarios described above. This

concentration of dissolved boron is the minimum required concentration for fuel assembly storage and movement within the SFPs.

APPLICABILITY This LCO applies whenever fuel assemblies are stored in the SFPs.

SFP Boron Concentration B 3.7.16 BASES CALVERT CLIFFS - UNITS 1 & 2 B 3.7.16-2 Revision 55 ACTIONS A.1 and A.2 The Required Actions are modified by a Note indicating that LCO 3.0.3 does not apply. If moving irradiated fuel

assemblies while in MODE 5 or 6, LCO 3.0.3 would not specify

any action. If moving irradiated fuel assemblies while in

MODE 1, 2, 3, or 4, the fuel movement is independent of

reactor operation. Therefore, inability to suspend movement

of fuel assemblies is not a sufficient reason to require a

reactor shutdown.

When the concentration of boron in the SFPs is less than

required, immediate action must be taken to preclude an

accident from happening or to mitigate the consequences of

an accident in progress. This is most efficiently achieved

by immediately suspending the movement of fuel assemblies.

This does not preclude the movement of fuel assemblies to a safe position. In addition, action must be immediately

initiated to restore boron concentration to within limits.

SURVEILLANCE SR 3.7.16.1 REQUIREMENTS This SR verifies that the concentration of boron in the SFPs is within the required limit. As long as this SR is met,

the analyzed incidents are fully addressed. The Surveillance Frequency is controlled under the Surveillance Frequency Control Program.

REFERENCES None

SFP Storage B 3.7.17 B 3.7 PLANT SYSTEMS B 3.7.17 Spent Fuel Pool (SFP) Storage BASES CALVERT CLIFFS - UNIT 2 B 3.7.17-1 Revision 23 BACKGROUND This Technical Specification applies to the Unit 2 SFP only.

The spent fuel storage facility was originally designed to store either new (non-irradiated) nuclear fuel assemblies or burned (irradiated) fuel assemblies in a vertical configuration underwater, assuming credit for Boraflex poison sheets but assuming no credit for soluble boron or burnup. The spent fuel storage cells are installed in parallel rows with center-to-center spacing of 10 3/32 inches and with Boraflex sheets between adjacent assemblies. This spacing was sufficient to maintain keff 0.95 for spent fuel of enrichments up to 4.52 wt% for standard fuel design and up to 4.30 wt% for Value Added Pellet (VAP) fuel design.

The burnup and enrichment requirements of LCO 3.7.17(a) ensures that the multiplication factor (keff) for the rack in the SFP is less than the 10 CFR 50.68 regulatory limit with the VAP fuel design, ranging in enrichment from 2.0 to 5.0 wt%, with burnup credit, with partial credit for soluble boron, but without Boraflex credit. The soluble boron credit will be limited to 350 ppm including all biases and uncertainties. For fuel assemblies which do not satisfy the burnup and enrichment requirements of LCO 3.7.17(a), the fuel assemblies may be stored in the Unit 2 SFP if surrounded on all four adjacent faces by empty rack cells or other non-reactive materials per LCO 3.7.17(b).

APPLICABLE The Unit 2 spent fuel storage facility is designed to SAFETY ANALYSES conform to the requirements of 10 CFR 50.68 by use of adequate spacing, soluble boron credit, and burnup credit.

The SFP storage satisfies Criterion 2 of 10 CFR 50.36(c)(2)(ii).

LCO The restrictions on the placement of fuel assemblies within the Unit 2 SFP are in accordance with Figure 3.7.17-1 and ensure that the Unit 2 SFP meets the requirements of 10 CFR 50.68. The restrictions are consistent with the criticality safety analysis performed for the Unit 2 SFP. Fuel assemblies not meting the criteria of Figure 3.7.17-1 may be SFP Storage B 3.7.17 BASES CALVERT CLIFFS - UNIT 2 B 3.7.17-2 Revision 23 stored in the Unit 2 SFP in a checkboard pattern in accordance with LCO 3.7.17(b).

APPLICABILITY This LCO applies whenever any fuel assembly is stored in the Unit 2 SFP.

ACTIONS A.1 Required Action A.1 is modified by a Note indicating that LCO 3.0.3 does not apply. If moving fuel assemblies while in MODE 5 or 6, LCO 3.0.3 would not specify any action. If moving fuel assemblies while in MODE 1, 2, 3, or 4, the fuel movement is independent of reactor operation. Therefore, in either case, inability to move fuel assemblies is not a sufficient reason to require a reactor shutdown.

When the configuration of fuel assemblies stored in Unit 2 SFP is not in accordance with Figure 3.7.17-1 or LCO 3.7.17(b), immediate action must be taken to make the necessary fuel assembly movement(s) to bring the fuel assembly configuration into compliance with Figure 3.7.17-1 or LCO 3.7.17(b).

SURVEILLANCE SR 3.7.17.1 REQUIREMENTS This SR verifies by administrative means that the initial enrichment and burnup of the fuel assembly is in accordance with Figure 3.7.17-1 for LCO 3.7.17(a). This Surveillance Requirement does not address fuel assemblies stored in the Unit 2 SFP in accordance with LCO 3.7.17(b). This will ensure compliance with Specification 4.3.1.1.

REFERENCES None

ADVs B 3.7.18 B 3.7 PLANT SYSTEMS B 3.7.18 Atmospheric Dump Valves (ADVs)

BASES CALVERT CLIFFS - UNITS 1 & 2 B 3.7.18-1 Revision 54 BACKGROUND The ADVs provide a safety grade method for cooling the unit to Shutdown Cooling (SDC) System entry conditions, should the preferred heat sink via the Turbine Bypass Valves to the condenser not be available, as discussed in the UFSAR, Section 10.3 (Reference 1). This is done in conjunction with the Auxiliary Feedwater System providing cooling water from the condensate storage tank (CST). The ADVs may also be used during a normal cooldown when steam pressure drops too low for maintenance of a vacuum in the condenser to permit use of the Turbine Bypass Valves.

Two ADV lines are provided, one per steam generator. Each ADV line consists of one ADV and an associated isolation valve. The ADVs are provided with upstream isolation valves to permit their being tested at power, if desired. The ADVs are equipped with manual hand wheels to open and close them.

Pneumatic controllers are used to operate the ADVs as the preferred method, but are not relied upon during an accident. A description of the ADVs is found in Reference 1. The ADVs are considered OPERABLE when the manual control is available for local manual operation.

APPLICABLE The design basis of the ADVs is established by the SAFETY ANALYSES capability to cool the unit to SDC System entry conditions.

The cooldown rate assumed in the accident analyses is obtainable by one or both steam generators. The design is adequate to cool the unit to SDC System entry conditions with only one ADV and one steam generator.

In the steam generator tube rupture accident analysis presented in the UFSAR, the ADVs are assumed to be used by the operator to cool down the unit to SDC System entry conditions because the accident is accompanied by a loss of offsite power. Prior to the operator action, the MSSVs are used to maintain steam generator pressure and temperature at the MSSV setpoint. The ADVs may be used for other accidents that are accompanied by a loss of offsite power. The limiting events are those that render one steam generator unavailable for RCS heat removal, with a coincident loss of offsite power. Typical initiating events falling into this ADVs B 3.7.18 BASES CALVERT CLIFFS - UNITS 1 & 2 B 3.7.18-2 Revision 54 category are a feedwater line break, and a SGTR event (limiting case).

The ADVs satisfy Criterion 3 of 10 CFR 50.36(c)(2)(ii).

LCO Two ADV lines are required to be OPERABLE to ensure that at least one ADV is OPERABLE to conduct a unit cooldown following an event in which one steam generator becomes unavailable. A closed isolation valve does not render its ADV line inoperable since operator action time to open the isolation valve is supported in the accident analysis.

Failure to meet the LCO can result in the inability to cool the unit to SDC System entry conditions following an event in which the condenser is unavailable for use with the Turbine Bypass Valves. An ADV is considered OPERABLE when it is capable of providing relief of the main steam flow, and is capable of fully opening and closing when required.

APPLICABILITY In MODES 1, 2, and 3, and in MODE 4, when steam generators are being relied upon for heat removal, the ADVs are required to be OPERABLE. In MODES 5 and 6, a SGTR is not a credible event.

ACTIONS A.1 With one required ADV line inoperable, action must be taken to restore the OPERABLE status within 48 hours5.555556e-4 days <br />0.0133 hours <br />7.936508e-5 weeks <br />1.8264e-5 months <br />. The 48 hour5.555556e-4 days <br />0.0133 hours <br />7.936508e-5 weeks <br />1.8264e-5 months <br /> Completion Time takes into account the redundant capability afforded by the remaining OPERABLE ADV line, and a backup in the Turbine Bypass Valves and MSSVs.

B.1 With two required ADV lines inoperable, action must be taken to restore one of the ADV lines to OPERABLE status. As the isolation valve can be closed to isolate an ADV, some repairs may be possible with the unit at power. The 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> Completion Time is reasonable to repair inoperable ADV lines, based on the availability of the Turbine Bypass Valves and MSSVs, and the low probability of an event occurring during this period that requires the ADV lines.

ADVs B 3.7.18 BASES CALVERT CLIFFS - UNITS 1 & 2 B 3.7.18-3 Revision 55 C.1 and C.2 If the ADV lines cannot be restored to OPERABLE status

within the associated Completion Time, the unit must be

placed in a MODE in which the LCO does not apply. To

achieve this status, the unit must be placed in at least

MODE 3 within 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br />, and in MODE 4, without reliance upon

the steam generator for heat removal, within 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />. The

allowed Completion Times are reasonable, based on operating

experience, to reach the required unit conditions from full

power conditions in an orderly manner and without

challenging unit systems.

SURVEILLANCE SR 3.7.18.1 REQUIREMENTS To perform a cooldown of the RCS, the ADVs must be able to be opened through their full range. This SR ensures the

ADVs are tested through a full cycle at least once per fuel

cycle. This test is performed using the manual handwheel

assembly. Any use of an ADV using the manual handwheel

assembly may satisfy this requirement. The Surveillance Frequency is controlled under the Surveillance Frequency Control Program.

REFERENCES 1. UFSAR, Section 10.3