{{#Wiki_filter:In Plant JPM P1 Facility:             Davis-Besse    Task No:  001-043-05-0100                Task Title:      Trip Reactor From #2 Low Voltage Switchgear Room        K/A  
{{#Wiki_filter:In Plant JPM P1 Facility:
Davis-Besse    Task No:  001-043-05-0100                Task Title
:      Trip Reactor From #2 Low Voltage Switchgear Room        K/A  


==Reference:==
==Reference:==
       (001) A2.11 4.4/4.7        Job Performance Measure No:  P1 (JPM 042)    Examinee:           NRC Examiner:        Date:      Method of testing: Simulated Performance __ X _  Actual Performance ___  Classroom ___  Simulator _ _  Plant _ X __
       (001) A2.11 4.4/4.7        Job Performance Measure No
Read to the examinee: I will explain the initial conditions, which steps to simulate or discuss, and provide initiating cues.
:  P1 (JPM 042)    Examinee:
When you complete the task successfully, the objective for this job performance measure will be satisfied. Initial Conditions: The plant conditions are specified in the Initial Conditions and Initiating Cues. Task Standard: Trip Reactor by manually tripping Reactor Trip Breakers in the Low Voltage Switchgear Rooms  Required Materials: DB-OP-02000 Section 3, step 3.3 General  
NRC Examiner:        Date:      Method of testing:
Simulated Performance __ X _  Actual Performance ___  Classroom ___  Simulator _ _  Plant _ X __
Read to the examinee:
I will explain the initial conditions, which steps to simulate or discuss, and provide initiating cues.
When you complete the task successfully, the objective for this job performance measure will be satisfied.
Initial Conditions:
The plant conditions are specified in the Initial Conditions and Initiating Cues.
Task Standard:
Trip Reactor by manually tripping Reactor Trip Breakers in the Low Voltage Switchgear Rooms  Required Materials:
DB-OP-02000 Section 3, step 3.3 General  


==References:==
==References:==
None  Initiating Cue: The plant conditions are specified in the Initial Conditions and Initiating Cues.
 
Time Critical Task: No Alternate Path: No Validation Time: 6 minutes EXAMINER COPY INITIAL CONDITIONS:  The plant has just experienced a severe transient causing a reactor trip signal to be generated. The reactor did not trip. Control power problems have prevented the Control Room from deenergizing E2 and F2. INITIATING CUES: The Unit Supervisor directs you to proceed to the Low Voltage Switchgear Rooms to deenergize the Control Rod Drive system by manually tripping Reactor Trip Breakers in accordance with Step 3.3 of DB-OP-02000, RPS, SFAS, SFRCS Trip or SG Tube Rupture.  
None  Initiating Cue:
(Hand copy of DB-OP-02000 step 3.3 to the examinee)
The plant conditions are specified in the Initial Conditions and Initiating Cues.
CANDIDATE COPY INITIAL CONDITIONS:  The plant has just experienced a severe transient causing a reactor trip signal to be generated. The reactor did not trip. Control power problems have prevented the Control Room from deenergizing E2 and F2. INITIATING CUES: The Unit Supervisor directs you to proceed to the Low Voltage Switchgear Rooms to deenergize the Control Rod Drive by manually tripping Reactor Trip Breakers in accordance with Step 3.3 of DB-OP-02000, RPS, SFAS, SFRCS Trip or SG Tube Rupture.
 
PERFORMANCE INFORMATION NOTE: Critical steps denoted with a "C". Failure to meet any one of these standards for this item constitutes failure. Sequence is NOT critical unless denoted in the "Comments". START TIME:  _______ 1. PERFORMANCE STEP: Recognize the correct procedure step.
Time Critical Task:
STANDARD: Recognize DB-OP-02000, RPS, SFAS, SFRCS Trip or SG Tube Rupture, Step 3.3 RNO as correct procedure step    CUE: None      __________       SAT UNSAT
No Alternate Path:
: 2. PERFORMANCE STEP: Trip Control Rod Drive Breaker A     STANDARD: Push the TRIP pushbutton on Control Rod Drive Breaker A and observe the                               Green Trip flag is visible COMMENT: Performance Note - Performance steps 2, 3, and 4 may be performed in any                                 order, but TRIPPING Control Rod Drive Breaker B and Control Rod Drive Breaker C are required to obtain desired response.
No Validation Time:
CUE: Trip pushbutton has been pushed on Control Rod Drive Breaker A.                   Green TRIP flag is NOT visible.                   The Reactor has NOT TRIPPED.       __________       SAT UNSAT  
6 minutes
 
EXAMINER COPY INITIAL CONDITIONS:  The plant has just experienced a severe transient causing a reactor trip signal to be generated.
The reactor did not trip.
Control power problems have prevented the Control Room from deenergizing E2 and F2.
INITIATING CUES
: The Unit Supervisor directs you to proceed to the Low Voltage Switchgear Rooms to deenergize the Control Rod Drive system by manually tripping Reactor Trip Breakers in accordance with Step 3.3 of DB
-OP-02000, RPS, SFAS, SFRCS Trip or SG Tube Rupture.
 
(Hand copy of DB
-OP-02000 step 3.3 to the examinee)
 
CANDIDATE COPY INITIAL CONDITIONS
:  The plant has just experienced a severe transient causing a reactor trip signal to be generated.
The reactor did not trip.
Control power problems have prevented the Control Room from deenergizing E2 and F2.
INITIATING CUES
: The Unit Supervisor directs you to proceed to the Low Voltage Switchgear Rooms to deenergize the Control Rod Drive by manually tripping Reactor Trip Breakers in accordance with Step 3.3 of DB-OP-02000, RPS, SFAS, SFRCS Trip or SG Tube Rupture.
 
PERFORMANCE INFORMATION NOTE: Critical steps denoted with a "C". Failure to meet any one of these standards for this item constitutes failure. Sequence is NOT critical unless denoted in the "Comments".
START TIME:  _______
: 1. PERFORMANCE STEP:
Recognize the correct procedure step.
STANDARD:
Recognize DB
-OP-02000, RPS, SFAS, SFRCS Trip or SG Tube Rupture, Step 3.3 RNO as correct procedure step    CUE: None      __________
SAT UNSAT
: 2. PERFORMANCE STEP: Trip Control Rod Drive Breaker A STANDARD:
Push the TRIP pushbutton on Control Rod Drive Breaker A and observe the Green Trip flag is vis ible COMMENT: Performance Note - Performance steps 2, 3, and 4 may be performed in any order, but TRIPPING Control Rod Drive Breaker B and Control Rod Drive  
 
Breaker C are required to obtain desired response.
 
CUE: Trip pushbutton has been pushed on Control Rod Drive Breaker A.
Green TRIP flag is NOT visible.
The Reactor has NOT TRIPPED.
__________
SAT UNSAT
: 3. PERFORMANCE STEP: Trip Control Rod Drive Breaker C        ........C........
: 3. PERFORMANCE STEP: Trip Control Rod Drive Breaker C        ........C........
STANDARD: Push the TRIP pushbutton on Control Rod Drive Breaker C and observe the                                Green Trip flag is visible    CUE: TRIP pushbutton has been pushed on Control Rod Drive Breaker C.
Green TRIP flag is visible. 
                (If Control Rod Drive Breaker B HAS been tripped) The Reactor has                              TRIPPED (If Control Rod Drive Breaker B HAS NOT been tripped) The Reactor has                    NOT TRIPPED.                                                                                                                                    __________      SAT UNSAT    4. PERFORMANCE STEP: Trip Control Rod Drive Breaker B  ........C........
STANDARD: Push the TRIP pushbutton on Control Rod Drive Breaker B and observe the                                Green Trip flag is visible          CUE: TRIP pushbutton has been pushed on Control Rod Drive Breaker B.                    Green TRIP flag is visible. 
                  (If Control Rod Drive Breaker C has NOT been tripped, the Reactor has                                  NOT TRIPPED) 
                  (If Control Rod Drive Breaker C HAS been tripped) The Reactor has                      TRIPPED.      __________      SAT UNSAT TERMINATING CUES:  This JPM is complete (Terminated by the examiner)
__________      END TIME 


In Plant JPM P2 Facility:             Davis-Besse    Task No:  001-043-05-0100                          Task Title:      Locally Operate Atmospheric Vent Valve ICS11A       K/A  
STANDARD:
Push the TRIP pushbutton on Control Rod Drive Breaker C and observe the Green Trip flag is vis ible    CUE: TRIP pushbutton has been pushed on Control Rod Drive Breaker C.
 
Green TRIP flag is visible.
 
                (If Control Rod Drive Breaker B HAS been tripped) The Reactor has TRIPPED (If Control Rod Drive Breaker B HAS NOT been tripped) The Reactor has                    NOT TRIPPED.
__________
SAT UNSAT    4. PERFORMANCE STEP: Trip Control Rod Drive Breaker B
  ........C........
 
STANDARD: Push the TRIP pushbutton on Control Rod Drive Breaker B and observe the Green Trip flag is visible          CUE: TRIP pushbutton has been pushed on Control Rod Drive Breaker B.                    Green TRIP flag is visible.
 
                  (If Control Rod Drive Breaker C has NOT been tripped, the Reactor has NOT TRIPPED)
 
                  (If Control Rod Drive Breaker C HAS been tripped) The Reactor has TRIPPED.      __________
SAT UNSAT TERMINATING CUES:  This JPM is complete (Terminated by the examiner)
 
__________
END TIME 
 
In Plant JPM P2 Facility:
Davis-Besse    Task No:  001-043-05-0100                          Task Title
:      Locally Operate Atmospheric Vent Valve ICS11A K/A  


==Reference:==
==Reference:==
       (039) A4.07 2.8/2.9        Job Performance Measure No:    P2 (JPM 024)    Examinee:           NRC Examiner:        Date:      Method of testing: Simulated Performance __ X _  Actual Performance ___  Classroom ___  Simulator _ _  Plant _ X __  Read to the examinee: I will explain the initial conditions, which steps to simulate or discuss, and provide initiating cues. When you complete the task successfully, the objective for this job performance measure will be satisfied. Initial Conditions: The plant conditions are specified in the Initial Conditions and Initiating Cues.
       (039) A4.07 2.8/2.9        Job Performance Measure No:    P2 (JPM 024)    Examinee:
Task Standard: Locally Operate Atmospheric Vent Valve ICS11A Required Materials: DB-OP-02000 Attachment 3  General  
NRC Examiner:        Date:      Method of testing:
Simulated Performance __ X _  Actual Performance ___  Classroom ___  Simulator _ _  Plant _ X __  Read to the examinee:
I will explain the initial conditions, which steps to simulate or discuss, and provide initiating cues. When you complete the task successfully, the objective for this job performance measure will be satisfied.
Initial Conditions:
The plant conditions are specified in the Initial Conditions and Initiating Cues.
 
Task Standard:
Locally Operate Atmospheric Vent Valve ICS11A
 
Required Materials:
DB-OP-02000 Attachment 3  General  


==References:==
==References:==
None  
None  


Initiating Cue: The plant conditions are specified in the Initial Conditions and Initiating Cues. Time Critical Task: No  Alternate Path: No Validation Time: 13 minutes EXAMINER COPY INITIAL CONDITIONS:  The Atmospheric Vent Valves cannot be controlled from the Control Room due to severe loss of instrument air. INITIATING CUES: The Unit Supervisor directs you to locally operate Atmospheric Vent Valve ICS 11A starting at Section D step 3.0 of Attachment 3 of DB-OP-02000 (IA450 has been closed by another operator).  (Hand the trainee a copy of Attachment 3 of DB-OP-02000)
Initiating Cue:
CANDIDATE COPY INITIAL CONDITIONS:  The Atmospheric Vent Valves cannot be controlled from the Control Room due to severe loss of instrument air. INITIATING CUES: The Unit Supervisor directs you to locally operate Atmospheric Vent Valve ICS 11A starting at Section D step 3.0 of Attachment 3 of DB-OP-02000 (IA450 has been closed by another operator).
The plant conditions are specified in the Initial Conditions and Initiating Cues.
PERFORMANCE INFORMATION NOTE: Critical steps denoted with a "C". Failure to meet any one of these standards for this item constitutes failure. Sequence is NOT critical unless denoted in the "Comments". START TIME:  _______ 1. PERFORMANCE STEP: Verify Valve A (ICS11AA) open    STANDARD: Verify Valve A (ICS11AA) is open by turning in the clockwise                               direction and returning to open position   CUE: Valve ICS11AA is rotated a small amount in the clockwise direction and then                      returned to full OPEN       __________       SAT UNSAT
Time Critical Task:
: 2. PERFORMANCE STEP: Open Valve B (ICS11AB)        ........C........ STANDARD: Turn handwheel counterclockwise to open Valve B (ICS11AB)          COMMENT: Step 1-3 shall be performed prior to Step 5   CUE: Valve ICS11AB handwheel is rotated counterclockwise and is open                                                                                                                               __________                                                   SAT UNSAT 3. PERFORMANCE STEP: Notify the Control Room that ICS11A is ready for local manual                                                  operation STANDARD: Communicate with Control Room using radio to determine desired valve                                position          CUE: Communications have been established with the Control Room                   The Reactor Operator directs you to position the Atmospheric Vent Valve to                     10 turns on the handwheel counter                                                                                   __________       SAT UNSAT    4. PERFORMANCE STEP: Check the handwheel counter at 0           STANDARD: Check the handwheel counter is at zero   CUE: Handwheel counter is at zero (0)        __________       SAT UNSAT   5. PERFORMANCE STEP: Establish desired throttle position   ........C........
No  Alternate Path:
STANDARD: Turn the handwheel in the clockwise direction 10 turns until counter reads 10         Note: Valve manual handwheel is reverse acting   CUE: Handwheel is rotated in the clockwise direction                 The handwheel counter is at 10.                   Instrument air has been restored.                 The Reactor Operator directs you to close ICS11A, establish positive shutoff                     and restore instrument air to the Atmospheric Vent Valve.       __________       SAT UNSAT 6. PERFORMANCE STEP: Close the Atmospheric Vent valve (ICS 11A) and establish                ........C........                      positive shutoff STANDARD: Turn the handwheel in the counterclockwise direction until the counter is                                zero (0)          COMMENT: Step 6 shall be performed prior to step 7  CUE: Handwheel is rotated counterclockwise direction                     Handwheel counter is at zero (0)                                                                                                                               __________                                                   SAT UNSAT 7. PERFORMANCE STEP: Close Valve B ICS11AB        ........C........                         STANDARD: Manual handwheel for Valve ICS11AB rotated clockwise until closed CUE: Valve ICS11AB handwheel has been rotated clockwise, valve is closed.                                                                                   __________       SAT UNSAT TERMINATING CUES:  This JPM is complete (Terminated by the examiner)
No Validation Time:
__________      END TIME 
13 minutes
 
EXAMINER COPY INITIAL CONDITIONS:  The Atmospheric Vent Valves cannot be controlled from the Control Room due to severe loss of instrument air.
INITIATING CUES
: The Unit Supervisor directs you to locally operate Atmospheric Vent Valve ICS 11A starting at Section D step 3.0 of Attachment 3 of DB
-OP-02000 (IA450 has been closed by another operator).  (Hand the trainee a copy of Attachment 3 of DB
-OP-02000)
CANDIDATE COPY INITIAL CONDITIONS
:  The Atmospheric Vent Valves cannot be controlled from the Control Room due to severe loss of instrument air.
INITIATING CUES
: The Unit Supervisor directs you to locally operate Atmospheric Vent Valve ICS 11A starting at Section D step 3.0 of Attachment 3 of DB
-OP-02000 (IA450 has been closed by another operator).
PERFORMANCE INFORMATION NOTE: Critical steps denoted with a "C". Failure to meet any one of these standards for this item constitutes failure. Sequence is NOT critical unless denoted in the "Comments".
START TIME:  _______
: 1. PERFORMANCE STEP: Verify Valve A (ICS11AA) open    STANDARD:
Verify Valve A (ICS11AA) is open by turning in the clockwise direction and returning to open position CUE: Valve ICS11AA is rotated a small amount in the clockwise direction and then                      returned to full OPEN
__________
SAT UNSAT
: 2. PERFORMANCE STEP: Open Valve B (ICS11AB)        ........C........
STANDARD:
Turn handwheel counterclockwise to open Valve B (ICS11AB)          COMMENT: Step 1-3 shall be performed prior to Step 5 CUE: Valve ICS11AB handwheel is rotated counterclockwise and is open
 
__________
 
SAT UNSAT
: 3. PERFORMANCE STEP: Notify the Control Room that ICS11A is ready for local manual                                                  operation
 
STANDARD: Communicate with Control Room using radio to determine desired valve                                position          CUE: Communications have been established with the Control Room The Reactor Operator directs you to position the Atmospheric Vent Valve to  
 
10 turns on the handwheel counter
 
__________
SAT UNSAT    4. PERFORMANCE STEP:
Check the handwheel counter at 0 STANDARD:
Check the handwheel counter is at zero CUE: Handwheel counter is at zero (0)        __________
SAT UNSAT
: 5. PERFORMANCE STEP: Establish desired throttle position
  ........C........
 
STANDARD:
Turn the handwheel in the clockwise direction 10 turns until counter reads 10 Note: Valve manual handwheel is reverse acting CUE: Handwheel is rotated in the clockwise direction The handwheel counter is at 10.
Instrument air has been restored.
The Reactor Operator directs you to close ICS11A, establish positive shutoff and restore instrument air to the Atmospheric Vent Valve.
__________
SAT UNSAT
: 6. PERFORMANCE STEP: Close the Atmospheric Vent valve (ICS 11A) and establish                ........C........                      positive shutoff
 
STANDARD:
Turn the handwheel in the counterclockwise direction until the counter is                                zero (0)          COMMENT: Step 6 shall be performed prior to step 7  CUE: Handwheel is rotated counterclockwise direction Handwheel counter is at zero (0)
__________
 
SAT UNSAT
: 7. PERFORMANCE STEP: Close Valve B ICS11AB        ........C........
STANDARD: Manual handwheel for Valve ICS11AB rotated clockwise until closed CUE: Valve ICS11AB handwheel has been rotated clockwise, valve is closed.
 
__________
SAT UNSAT TERMINATING CUES:  This JPM is complete (Terminated by the examiner)


In Plant JPM P3 Facility:             Davis-Besse    Task No:  064-026-05-0401                          Task Title:      Energize Station Blackout Diesel Generator Auxiliaries          K/A  
__________
END TIME 
 
In Plant JPM P3 Facility:
Davis-Besse    Task No:  064-026-05-0401                          Task Title
:      Energize Station Blackout Diesel Generator Auxiliaries          K/A  


==Reference:==
==Reference:==
       (064) A2.12 2.8/3.1        Job Performance Measure No:    P3 (JPM 258)    Examinee:           NRC Examiner:        Date:      Method of testing: Simulated Performance __ X _  Actual Performance ___  Classroom ___  Simulator _ _  Plant _ X __  Read to the examinee: I will explain the initial conditions, which steps to simulate or discuss, and provide initiating cues. When you complete the task successfully, the objective for this job performance measure will be satisfied. Initial Conditions: The plant conditions are specified in the Initial Conditions and Initiating Cues.
       (064) A2.12 2.8/3.1        Job Performance Measure No
Task Standard: Energize Station Blackout Diesel Generator Auxiliaries   Emergency Shutdown Station Blackout Diesel Generator (Loss of Air Cooling Fans)  Required Materials: Section 4.10 of DB-OP-06334, Station Blackout Diesel Generator Operating Procedure Section 5.2 of DB-OP-06334, Emergency Shutdown of Station Blackout Diesel Generator General  
:    P3 (JPM 258)    Examinee:
NRC Examiner:        Date:      Method of testing:
Simulated Performance __ X _  Actual Performance ___  Classroom ___  Simulator _ _  Plant _ X __  Read to the examinee:
I will explain the initial conditions, which steps to simulate or discuss, and provide initiating cues. When you complete the task successfully, the objective for this job performance measure will be satisfied.
Initial Conditions:
The plant conditions are specified in the Initial Conditions and Initiating Cues.
 
Task Standard:
Energize Station Blackout Diesel Generator Auxiliaries Emergency Shutdown Station Blackout Diesel Generator (Loss of Air Cooling Fans)  Required Materials:
Section 4.10 of DB
-OP-06334, Station Blackout Diesel Generator Operating Procedure Section 5.2 of DB
-OP-06334, Emergency Shutdown of Station Blackout Diesel Generator General  


==References:==
==References:==
None Initiating Cue: The plant conditions are specified in the Initial Conditions and Initiating Cues.
Time Critical Task: No Alternate Path: Yes Validation Time: 15 minutes EXAMINER COPY  INITIAL CONDITIONS:  The plant is operating at 100% power  Ambient temperature is 45°F  Breaker AD213, SBDOG to D2, has been opened in preparation for breaker maintenance AD213 was opened 15 minutes ago  INITIATING CUES:  NOTE:  Procedure Step 4.10.2 needs to be initialed indicating that Barring of the Station Blackout Diesel Generator is NOT required. In the procedure step NO should be circled. The Unit Supervisor directs you to perform Section 4.10, Energizing the Station Blackout Diesel Generator Auxiliaries from the Station Blackout Diesel Generator, of DB-OP-06334.
You have an eSOMS handheld computer with the Station Blackout Diesel Generator readings downloaded.  (Provide the examinee a copy of procedure package including section 4.10 of              DB-OP-06334, Station Blackout Diesel Generator Operating Procedure. Procedure Step 4.10.2 needs to be initialed indicating that Barring of the Station Blackout Diesel Generator is NOT required. In the procedure step NO should be circled. Section 5.2 will be provided when it is recognized emergency shutdown of the SBODG is required.)   


CANDIDATE COPY INITIAL CONDITIONS:
None Initiating Cue:
The plant is operating at 100% power Ambient temperature is 45°F Breaker AD213, SBDOG to D2, has been opened in preparation for breaker maintenance AD213 was opened 15 minutes ago INITIATING CUES:
The plant conditions are specified in the Initial Conditions and Initiating Cues.
The Unit Supervisor directs you to perform Section 4.10, Energizing the Station Blackout Diesel Generator Auxiliaries from the Station Blackout Diesel Generator, of DB-OP-06334.
 
Time Critical Task:
No Alternate Path:
Yes Validation Time:
15 minutes
 
EXAMINER COPY INITIAL CONDITIONS:  The plant is operating at 100% power Ambient temperature is 45°F Breaker AD213, SBDOG to D2, has been opened in preparation for breaker maintenance
 
AD213 was opened 15 minutes ago INITIATING CUES:  NOTE:  Procedure Step 4.10.2 needs to be initialed indicating that Barring of the Station Blackout Diesel Generator is NOT required. In the procedure step NO should be circled.
The Unit Supervisor directs you to perform Section 4.10, Energizing the Station Blackout Diesel Generator Auxiliaries from the Station Blackout Diesel Generator, of DB
-OP-06334.
You have an eSOMS handheld computer with the Station Blackout Diesel Generator readings downloaded.  (Provide the examinee a copy of procedure package including section 4.10 of DB-OP-06334, Station Blackout Diesel Generator Operating Procedure.
Procedure Step 4.10.2 needs to be initialed indicating that Barring of the Station Blackout Diesel Generator is NOT required. In the procedure step NO should be circled.
Section 5.2 will be provided when it is recognized emergency shutdown of the SBODG is required.)   
 
CANDIDATE COPY INITIAL CONDITIONS:
The plant is operating at 100% power
 
Ambient temperature is 45°F Breaker AD213, SBDOG to D2, has been opened in preparation for breaker maintenance AD213 was opened 15 minutes ago INITIATING CUES:
The Unit Supervisor directs you to perform Section 4.10, Energizing the Station Blackout Diesel Generator Auxiliaries from the Station Blackout Diesel Generator, of DB
-OP-06334.
You have an eSOMS handheld computer with the Station Blackout Diesel Generator readings Downloaded.     
You have an eSOMS handheld computer with the Station Blackout Diesel Generator readings Downloaded.     


PERFORMANCE INFORMATION NOTE: Critical steps denoted with a "C". Failure to meet any one of these standards for this item constitutes failure. Sequence is NOT critical unless denoted in the "Comments".
PERFORMANCE INFORMATION
START TIME:  _______ 1. PERFORMANCE STEP: Depress and hold the FUEL PRIME pushbutton until fuel oil pressure stabilizes >15 PSIG.          STANDARD: Depresses the FUEL PRIME pushbutton until fuel oil pressure stabilizes greater than 15 PSIG on the black indicator of PI 11160. CUE: FUEL PRIME pushbutton depressed, PI 11160 FUEL FILTER Pressure black                    indicator reads 17 PSIG        __________       SAT UNSAT 2. PERFORMANCE STEP: Place the ELECT PROTECT-MODE SELECT Switch in the TEST ........C........                      position. STANDARD: Rotate the ELECT PROTECT-MODE SELECT Switch to the TEST position                                    on C30202. CUE: The ELECT PROTECT - MODE SELECT Switch has been rotated and points                     towards TEST                                                                                                                      __________       SAT UNSAT 3. PERFORMANCE STEP: Verify SBODG OUTPUT BREAKER AD 301 is open.          STANDARD: On panel C30202, Verifies AD 301 GREEN light is lit.          CUE: AD 301 GREEN LIGHT is lit                                                                                                                               __________                                                   SAT UNSAT   
 
NOTE: Critical steps denoted with a "C". Failure to meet any one of these standards for this item constitutes failure. Sequence is NOT critical unless denoted in the "Comments".
 
START TIME:  _______
: 1. PERFORMANCE STEP:
Depress and hold the FUEL PRIME pushbutton until fuel oil pressure stabilizes >15 PSIG.          STANDARD:
Depresses the FUEL PRIME pushbutton until fuel oil pressure stabilizes greater than 15 PSIG on the black indicator of PI 11160.
CUE: FUEL PRIME pushbutton depressed
, PI 11160 FUEL FILTER Pressure black                    indicator reads 17 PSIG        __________
SAT UNSAT
: 2. PERFORMANCE STEP: Place the ELECT PROTECT
-MODE SELECT Switch in the TEST ........C........                      position. STANDARD:
Rotate the ELECT PROTECT
-MODE SELECT Switch to the TEST position                                    on C30202.
CUE: The ELECT PROTECT - MODE SELECT Switch has been rotated and points towards TEST                                                                                                                      __________
SAT UNSAT
: 3. PERFORMANCE STEP: Verify SBODG OUTPUT BREAKER AD 301 is open.          STANDARD:
On panel C30202, Verifies AD 301 GREEN light is lit.          CUE: AD 301 GREEN LIGHT is lit
 
__________
 
SAT UNSAT   
: 4. PERFORMANCE STEP: Start the SBODG.        ........C........
: 4. PERFORMANCE STEP: Start the SBODG.        ........C........
STANDARD: Depress the SBODG START pushbutton on Panel 30202.          CUE: The START pushbutton has been depressed                                                                                    __________      SAT UNSAT     
: 5. PERFORMANCE STEP: After 30 seconds CHECK the Station Blackout Diesel Generator starts and accelerates to approximately 450 RPM.          STANDARD: After approximately 30 seconds verify the Station Blackout Diesel Generator starts and accelerates to approximately 450 rpm as indicated on ENGINE TACHOMETER on C30203. CUE: After approximately 30 seconds the diesel starts.                  When checking speed on Engine Tachometer, Tachometer on C30203 reads 450 rpm.        __________      SAT UNSAT  6. PERFORMANCE STEP: After approximately 30 seconds, the Station Blackout Diesel Generator accelerates to 900 rpm. STANDARD: Verify the Station Blackout Diesel Generator accelerates to approximately                                900 rpm after 30 seconds as indicated by ENGINE TACHOMETER on                                C30203. CUE: After approximately 30 seconds the diesel accelerates.                  Engine Tachometer on C30203 reads 900 rpm.                                                                                                                      __________      SAT UNSAT  7. PERFORMANCE STEP: Place the SYNCHRONIZE switch in the ON position                ........C........
STANDARD: Install operating handle and rotate the SYNCHONIZE switch to the ON                                position          CUE: The SYNCHRONIZE switch is in the ON position,                  If asked, The synchroscope pointer indicates 1200                                                                                                                              __________                                                  SAT UNSAT  8. PERFORMANCE STEP: Close Breaker AD 301, SBODG OUTPUT BREAKER on Panel          ........C........                      C30202          STANDARD: Rotate handswitch for AD301 to the close position          CUE: AD 301 RED LIGHT is ON                                                                                    __________      SAT UNSAT   
: 9. PERFORMANCE STEP: Place the SYNCHRONIZE switch to OFF          STANDARD: Rotate the SYNCHRONIZE switch to OFF position    CUE: The SYNCHRONIZE switch is in the OFF position        __________      SAT UNSAT  10. PERFORMANCE STEP: Verify both Station Blackout Diesel Generator Jacket Water                                                                                    Radiator fans are operating    STANDARD: Check the status of the fans by observing the breaker lights and/or observing the fans locally, recognize neither fan is operating          NOTE: Alternate Path begins with recognition that fans are not running and                      emergency shutdown the SBODG must be performed  CUE: Both fan breaker lights indicate GREEN (or the fans are not turning if checked                    locally)                                                                                                                                __________      SAT UNSAT  11. PERFORMANCE STEP: Go to Section 5.2, Emergency Shutdown of the Station Blackout                                                  Diesel Generator          STANDARD: Route to section 5.2, Emergency Shutdown of the Station Blackout Diesel                              Generator          CUE: (Provide the examinee a copy of Section 5.2 of DB-OP-06334)                                                                                                                                                                                                                                                                      __________                                                  SAT UNSAT  12. PERFORMANCE STEP: Stop the Station Blackout Diesel Generator                ........C........                                STANDARD: Depress the Emergency Stop pushbutton on panel C30202 or panel C30203.          CUE: The Emergency Stop has been depressed. The Station Blackout Diesel                  Generator is beginning to slow down.                  (If asked) AD 301 GREEN light is ON, RED light is OFF                                                                                                                                                              __________                                                  SAT UNSAT 
: 13. PERFORMANCE STEP: Station Blackout Diesel Generator stops            STANDARD: Verify Engine Tachometer reads zero on C30203          CUE: The Station Blackout Diesel Generator tachometer reads zero                                                                                    __________      SAT UNSAT    TERMINATING CUES:  This JPM is complete (Terminated by the examiner)        __________      END TIME 


Simulator JPM S1 Facility:             Davis-Besse    Task No:    008-005-01-0100              Task Title:      Swap Control Rod Drive Cooling Booster pumps          K/A  
STANDARD: Depress the SBODG START pushbutton on Panel 30202.          CUE: The START pushbutton has been depressed
 
__________
SAT UNSAT     
: 5. PERFORMANCE STEP:
After 30 seconds CHECK the Station Blackout Diesel Generator starts and accelerates to approximately 450 RPM.          STANDARD:
After approximately 30 seconds verify the Station Blackout Diesel Generator starts and accelerates to approximately 450 rpm as indicated on ENGINE TACHOMETER on C30203. CUE: After approximately 30 seconds the diesel starts.                  When checking speed on Engine Tachometer, Tachometer on C30203 reads 450 rpm.        __________
SAT UNSAT
: 6. PERFORMANCE STEP: After approximately 30 seconds, the Station Blackout Diesel Generator accelerates to 900 rpm. STANDARD:
Verify the Station Blackout Diesel Generator accelerates to approximately                                900 rpm after 30 seconds as indicated by ENGINE TACHOMETER on                                C30203. CUE: After approximately 30 seconds the diesel accelerates.
 
Engine Tachometer on C30203 reads 900 rpm.                                                                                                                      __________
SAT UNSAT  7. PERFORMANCE STEP: Place the SYNCHRONIZE switch in the ON position
                ........C........                     
 
STANDARD:
Install operating handle and rotate the SYNCHONIZE switch to the ON                                position          CUE: The SYNCHRONIZE switch is in the ON position,                  If asked, The synchroscope pointer indicates 1200
 
__________
 
SAT UNSAT
: 8. PERFORMANCE STEP: Close Breaker AD 301, SBODG OUTPUT BREAKER on Panel          ........C........                      C30202          STANDARD: Rotate handswitch for AD301 to the close position CUE: AD 301 RED LIGHT is ON
 
__________
SAT UNSAT   
: 9. PERFORMANCE STEP:
Place the SYNCHRONIZE switch to OFF STANDARD:
Rotate the SYNCHRONIZE switch to OFF position CUE: The SYNCHRONIZE switch is in the OFF position
__________
SAT UNSAT
: 10. PERFORMANCE STEP: Verify both Station Blackout Diesel Generator Jacket Water Radiator fans are operating STANDARD:
Check the status of the fans by observing the breaker lights and/or observing the fans locally, recognize neither fan is operating NOTE: Alternate Path begins with recognition that fans are not running and emergency shutdown the SBODG must be performed CUE: Both fan breaker lights indicate GREEN (or the fans are not turning if checked                    locally)
__________
SAT UNSAT
: 11. PERFORMANCE STEP: Go to Section 5.2, Emergency Shutdown of the Station Blackout Diesel Generator STANDARD:
Route to section 5.2, Emergency Shutdown of the Station Blackout Diesel Generator          CUE: (Provide the examinee a copy of Section 5.2 of DB-OP-06334)                                                                                                                           
 
__________
 
SAT UNSAT
: 12. PERFORMANCE STEP: Stop the Station Blackout Diesel Generator                ........C........
STANDARD:
Depress the Emergency Stop pushbutton on panel C30202 or panel C30203.
CUE: The Emergency Stop has been depressed. The Station Blackout Diesel Generator is beginning to slow down.
                  (If asked) AD 301 GREEN light is ON, RED light is OFF                               
 
__________
 
SAT UNSAT
: 13. PERFORMANCE STEP: Station Blackout Diesel Generator stops            STANDARD: Verify Engine Tachometer reads zero on C30203 CUE: The Station Blackout Diesel Generator tachometer reads zero
 
__________
SAT UNSAT    TERMINATING CUES:  This JPM is complete (Terminated by the examiner)
__________
END TIME 
 
Simulator JPM S1 Facility:
Davis-Besse    Task No:    008-005-01-0100              Task Title
:      Swap Control Rod Drive Cooling Booster pumps          K/A  


==Reference:==
==Reference:==
       (001) A2.11 4.4/4.7        Job Performance Measure No:  S1 (NEW)    Examinee:           NRC Examiner:        Date:      Method of testing: Simulated Performance ___  Actual Performance _X_  Classroom ___  Simulator _X_  Plant ___
       (001) A2.11 4.4/4.7        Job Performance Measure No
Read to the examinee: I will explain the initial conditions, which steps to simulate or discuss, and provide initiating cues. When you complete the task successfully, the objective for this job performance measure will be satisfied. Initial Conditions: The plant conditions are specified in the Initial Conditions and Initiating Cues. Use 100% power IC. Verity #1 CRDC Booster Pump is running. IMF KA H 3D Thermal Overload on #2 CRDC Booster Pump (Insert after EO contacted to open BE2206)
:  S1 (NEW)    Examinee:
Task Standard: Start the STBY CRDC Booster Pump 2 Stop the running CRDC Booster Pump 1 Open pump suction valve CC1328 and restart previously running CRDC Booster Pump 1  Required Materials: DB-OP-06262 Section 3.21 ready for performance of prerequisite 3.21.1 DB-OP-06262 Section 3.19 with prerequisites complete and step 3.19.1 marked N/A General  
NRC Examiner:        Date:      Method of testing:
Simulated Performance ___  Actual Performance _X_  Classroom ___  Simulator _X_  Plant ___
 
Read to the examinee:
I will explain the initial conditions, which steps to simulate or discuss, and provide initiating cues. When you complete the task successfully, the objective for this job performance measure will be satisfied.
Initial Conditions:
The plant conditions are specified in the Initial Conditions and Initiating Cues. Use 100% power IC. Verity #1 CRDC Booster Pump is running.
IMF KA H 3D Thermal Overload on #2 CRDC Booster Pump (Insert after EO contacted to open BE2206)
Task Standard:
Start the STBY CRDC Booster Pump 2 Stop the running CRDC Booster Pump 1 Open pump suction valve CC1328 and restart previously running CRDC Booster Pump 1  Required Materials:
DB-OP-06262 Section 3.21 ready for performance of prerequisite 3.21.1 DB-OP-06262 Section 3.19 with prerequisites complete and step 3.19.1 marked N/A General  


==References:==
==References:==
None Initiating Cue: The plant conditions are specified in the Initial Conditions and Initiating Cues. Time Critical Task: No  Alternate Path: Yes Validation Time:  9 minutes SIMULATOR INSTRUCTIONS  TASK DESCRIPTION: Swap Control Rod Drive Cooling Booster pumps  INITIAL CONDITION: Any at power I/C  ADDITIONAL SETUP/DEVIATION FROM INITIAL CONDITION: Verify #1 CRDC Booster Pump is running  MALFUNCTIONS/FAILURE TO INSERT: #2 CRDC Booster Pump trip after EO is sent to open BE2206 CC1328, CRD Booster Pump 1 Suction Valve, fails closed when pump 1 is stopped 


EXAMINER COPY INITIAL CONDITIONS:  The plant is at 100% All systems are in a normal lineup Engineering has requested to inspect CRD Filter 1 filter element to verify correct size. There are no other issues with CRD Filter 1   Maintenance is ready to disassemble CRD Filter 1 for inspection I & C has removed PDI 2952 from service INITIATING CUES: The Command SRO has directed you to place #2 Control Rod Drive Booster Pump in service in preparation for filter F55-1, FILTER CRDC 1-1 inspection IAW DB-OP-06262 Section 3.21 and 3.19.  (Provide examinee a copy of section 3.19 and 3.21 DB-OP-06262)
None Initiating Cue:
CANDIDATE COPY INITIAL CONDITIONS: The plant is at 100% All systems are in a normal lineup Engineering has requested to inspect CRD Filter 1 filter element to verify correct size. There are no other issues with CRD Filter 1   Maintenance is ready to disassemble CRD Filter 1 for inspection I & C has removed PDI 2952 from service  INITIATING CUES: The Command SRO has directed you to place #2 Control Rod Drive Booster Pump in service in preparation for filter F55-1, FILTER CRDC 1-1 inspection IAW DB-OP-06262 Section 3.21 and 3.19.
The plant conditions are specified in the Initial Conditions and Initiating Cues.
PERFORMANCE INFORMATION NOTE: Critical steps denoted with a "C". Failure to meet any one of these standards for this item constitutes failure. Sequence is NOT critical unless denoted in the "Comments". START TIME:  _______ 1. PERFORMANCE STEP: Verify CRD Booster Pump 2 is in service (Step 3.21.1).
Time Critical Task:
STANDARD: Refer to Subsection 3.19, Startup of CRD Booster Pump 2. CUE: None      __________       SAT UNSAT 2. PERFORMANCE STEP: Start CRD CLNG BOOSTER PUMP 2.  ........C........ STANDARD: Start CRD CLNG BOOSTER PUMP 2 using HIS1924. NOTE: Annunciator 5-6-D will alarm when the second pump is started. The alarm                     may be treated as an expected alarm. If alarm procedure is used guidance                      will be if an evolution is in progress causing the alarm stop the standby                       pump if desired. CUE: None      __________       SAT UNSAT
No  Alternate Path:
: 3. PERFORMANCE STEP: Verify CRD Booster Pump 2 discharge pressure at PI756 is   between 120 and 160 PSIG. STANDARD: Contacts EO to verify CRD Booster Pump 2 discharge pressure at PI756                       is between 120 and 160 PSIG. CUE: Equipment Operator reports CRD Booster Pump 2 discharge pressure at           PI756 is 150 PSIG.                        __________       SAT UNSAT     
Yes Validation Time:  9 minutes
 
SIMULATOR INSTRUCTIONS TASK DESCRIPTION: Swap Control Rod Drive Cooling Booster pumps INITIAL CONDITION: Any at power I/C ADDITIONAL SETUP/DEVIATION FROM INITIAL CONDITION: Verify #1 CRDC Booster Pump is running MALFUNCTIONS/FAILURE TO INSERT: #2 CRDC Booster Pump trip after EO is sent to open BE2206 CC1328, CRD Booster Pump 1 Suction Valve, fails closed when pump 1 is stopped
 
EXAMINER COPY INITIAL CONDITIONS:  The plant is at 100%
All systems are in a normal lineup
 
Engineering has requested to inspect CRD Filter 1 filter element to verify correct size. There are no other issues with CRD Filter 1 Maintenance is ready to disassemble CRD Filter 1 for inspection
 
I & C has removed PDI 2952 from service INITIATING CUES
: The Command SRO has directed you to place #2 Control Rod Drive Booster Pump in service in preparation for filter F55
-1, FILTER CRDC 1
-1 inspection IAW DB
-OP-06262 Section 3.21 and 3.19.  
   (Provide examinee a copy of section 3.19 and 3.21 DB-OP-06262)
CANDIDATE COPY INITIAL CONDITIONS: The plant is at 100%
All systems are in a normal lineup Engineering has requested to inspect CRD Filter 1 filter element to verify correct size. There are no other issues with CRD Filter 1 Maintenance is ready to disassemble CRD Filter 1 for inspection
 
I & C has removed PDI 2952 from service  INITIATING CUES
: The Command SRO has directed you to place #2 Control Rod Drive Booster Pump in service
 
in preparation for filter F55
-1, FILTER CRDC 1
-1 inspection IAW DB
-OP-06262 Section 3.21 and 3.19.
 
PERFORMANCE INFORMATION NOTE: Critical steps denoted with a "C". Failure to meet any one of these standards for this item constitutes failure. Sequence is NOT critical unless denoted in the "Comments".
START TIME:  _______
: 1. PERFORMANCE STEP: Verify CRD Booster Pump 2 is in service (Step 3.21.1).
STANDARD:
Refer to Subsection 3.19, Startup of CRD Booster Pump 2. CUE: None      __________
SAT UNSAT
: 2. PERFORMANCE STEP: Start CRD CLNG BOOSTER PUMP 2.  ........C........
STANDARD:
Start CRD CLNG BOOSTER PUMP 2 using HIS1924. NOTE: Annunciator 5-6-D will alarm when the second pump is started. The alarm may be treated as an expected alarm. If alarm procedure is used guidance                      will be if an evolution is in progress causing the alarm stop the standby pump if desired.
CUE: None      __________
SAT UNSAT
: 3. PERFORMANCE STEP: Verify CRD Booster Pump 2 discharge pressure at PI756 is between 120 and 160 PSIG. STANDARD: Contacts EO to verify CRD Booster Pump 2 discharge pressure at PI756 is between 120 and 160 PSIG. CUE: Equipment Operator reports CRD Booster Pump 2 discharge pressure at PI756 is 150 PSIG.                        __________
SAT UNSAT     
: 4. PERFORMANCE STEP: Stop CRD CLNG BOOSTER PUMP 1 and place in lockout.   
: 4. PERFORMANCE STEP: Stop CRD CLNG BOOSTER PUMP 1 and place in lockout.   
   ........C........ STANDARD: Verify CRD CLNG BOOSTER PUMP 1 off and in LOCKOUT              using HIS1915. NOTE: CC1328, Suction valve for CRD Booster Pump 1, will be triggered to fail                       closed when the pump is shut down (switch bumped by mechanic walking                     down filter inspection).
   ........C........
CUE: None      __________       SAT UNSAT     
STANDARD: Verify CRD CLNG BOOSTER PUMP 1 off and in LOCKOUT              using HIS1915. NOTE: CC1328, Suction valve for CRD Booster Pump 1, will be triggered to fail closed when the pump is shut down (switch bumped by mechanic walking down filter inspection).
: 5. PERFORMANCE STEP: Verify CRD Booster Pump 2 discharge flow on FIS2586 is       greater than 150 GPM. NOTE: Pump 2 will trip triggered by a time delay which may occur during or prior to                       performance steps 5, 6, 7, 8, or 9 and require performance step 10 to be                     implemented. STANDARD: Contacts EO to verify CRD Booster Pump 2 discharge flow on FIS2586           is greater than 150 GPM.       CUE: EO reports flow on FIS2586 is 190 GPM.          __________        SAT UNSAT    6. PERFORMANCE STEP: Complete section 3.19 and route back to section 3.21. STANDARD: Signs section 3.19 complete and routes back to section 3.21. NOTE: Step 3.19.8 pre-identified as N/A since being removed from service. CUE: None      __________       SAT UNSAT    7. PERFORMANCE STEP: Complete prerequisites for section 3.21. STANDARD: Signs step 3.21.1 complete and signs for prerequisites complete. CUE: None      __________       SAT UNSAT       
CUE: None      __________
SAT UNSAT     
: 5. PERFORMANCE STEP: Verify CRD Booster Pump 2 discharge flow on FIS2586 is greater than 150 GPM
. NOTE: Pump 2 will trip triggered by a time delay which may occur during or prior to performance steps 5, 6, 7, 8, or 9 and require performance step 10 to be implemented.
STANDARD: Contacts EO to verify CRD Booster Pump 2 discharge flow on FIS2586 is greater than 150 GPM.
CUE: EO reports flow on FIS2586 is 190 GPM.          __________        SAT UNSAT    6. PERFORMANCE STEP: Complete section 3.19 and route back to section 3.21. STANDARD: Signs section 3.19 complete and routes back to section 3.21. NOTE: Step 3.19.8 pre-identified as N/A since being removed from service
. CUE: None      __________
SAT UNSAT    7. PERFORMANCE STEP: Complete prerequisites for section 3.21. STANDARD: Signs step 3.21.1 complete and signs for prerequisites complete. CUE: None      __________
SAT UNSAT       
: 8. PERFORMANCE STEP: Place HIS1915, CRD CLNG BOOSTER PUMP 1 in LOCKOUT. STANDARD: Verifies switch HIS1915 is in LOCKOUT.
: 8. PERFORMANCE STEP: Place HIS1915, CRD CLNG BOOSTER PUMP 1 in LOCKOUT. STANDARD: Verifies switch HIS1915 is in LOCKOUT.
NOTE: Step 3.21.4 may be marked N/A since the switch was left in LOCKOUT during                     performance of section 3.19. CUE: None      __________       SAT UNSAT    9. PERFORMANCE STEP: Open BE2206, CRD BOOSTER PUMP 1. STANDARD: Contact EO to OPEN BE2206, CRD BOOSTER PUMP 1. CUE: Role play as EO, acknowledge direction to open BE2206.        __________       SAT UNSAT    ALTERNATE PATH - CRD Booster Pump 2 trips and will require placing CRD Booster Pump 1 back into service. CRD Booster Pump 1 suction valve CC1328 will close when the pump is shut down in performance step 4 which will require verifying flow path and opening CC1328 prior to starting CRD Booster Pump 1.           
NOTE: Step 3.21.4 may be marked N/A since the switch was left in LOCKOUT during performance of section 3.19. CUE: None      __________
: 10. PERFORMANCE STEP: Respond to Annunciator 5-6-D, CRD BOOSTER PMP                                          P HI/FLOW LO/GO TO DB-OP-02523, CCW System                                           Malfunctions.        STANDARD: Recognize entry criteria and implement DB-OP-02523, CCW System                                 Malfunctions, or refer to alarm procedure which will direct to the abnormal                               procedure   CUE:  (If asked) Role play as the EO, CRD BOOSTER PUMP 2 is off,   motor is hot to the touch.        __________       SAT UNSAT    11. PERFORMANCE STEP: Verify the standby CRD Booster pump starts.                                                 STANDARD: Attempt to start CRD Booster Pump 1 (will not be successful due to suction                               valve being closed). CUE:  None        __________       SAT UNSAT     
SAT UNSAT    9. PERFORMANCE STEP:
: 12. PERFORMANCE STEP: Monitor CRD Stator temperatures.        STANDARD: Using RNO guidance (since pump 1 was not able to be started) monitor CRD                               Stator temperatures using NSSS Summary Files 12 and 13 and trip the                               reactor if any CRD Stator temperature reaches 180 ºF. CUE:  As a maintenance mechanic report to the control room that while walking down the CRD Filter 1 inspection work in #4 MPR a switch was bumped and it                   sounded like something actuated.       __________       SAT UNSAT    13. PERFORMANCE STEP: Verify the CRD Cooling Booster flow path is available.  ........C........
Open BE2206, CRD BOOSTER PUMP 1. STANDARD: Contact EO to OPEN BE2206, CRD BOOSTER PUMP 1. CUE: Role play as EO, acknowledge direction to open BE2206.        __________
STANDARD: Refer to Attachment 8 for verification of proper flow path to identify CC1328 is                               closed and open CC1328. Start/ensure CRD Cooling Booster Pump 1 is                                       running.
SAT UNSAT    ALTERNATE PATH - CRD Booster Pump 2 trips and will require placing CRD Booster Pump 1 back into service. CRD Booster Pump 1 suction valve CC1328 will close when the pump is shut down in performance step 4 which will require verifying flow path and opening CC1328 prior to starting CRD Booster Pump 1.           
NOTE:  If the CRD Booster Pump 1 switch is left in auto after attempting to start in                     performance step 11 the pump will auto start when CC1328 is open,                      otherwise verify the pump is running by returning the switch to auto. CUE:  None        __________       SAT UNSAT TERMINATING CUES:  This JPM is complete (Terminated by the examiner)
: 10. PERFORMANCE STEP: Respond to Annunciator 5-6-D, CRD BOOSTER PMP                                          P HI/FLOW LO/GO TO DB
__________       END TIME Simulator JPM S2 Facility: Davis-Besse    Task No:  000-093-05-0100    Task Title: Transfer LPI Suctions to the Emergency Sump K/A  
-OP-02523, CCW System Malfunctions.        STANDARD: Recognize entry criteria and implement DB-OP-02523, CCW System Malfunctions, or refer to alarm procedure which will direct to the abnormal procedure CUE:  (If asked) Role play as the EO, CRD BOOSTER PUMP 2 is off, motor is hot to the touch.        __________
SAT UNSAT    11. PERFORMANCE STEP: Verify the standby CRD Booster pump starts.
STANDARD: Attempt to start CRD Booster Pump 1 (will not be successful due to suction valve being closed). CUE:  None        __________
SAT UNSAT     
: 12. PERFORMANCE STEP: Monitor CRD Stator temperatures.        STANDARD: Using RNO guidance (since pump 1 was not able to be started) monitor CRD Stator temperatures using NSSS Summary Files 12 and 13 and trip the reactor if any CRD Stator temperature reaches 180 ºF. CUE:  As a maintenance mechanic report to the control room that while walking  
 
down the CRD Filter 1 inspection work in #4 MPR a switch was bumped and it sounded like something actuated.
__________
SAT UNSAT    13. PERFORMANCE STEP: Verify the CRD Cooling Booster flow path is available.  ........C........
 
STANDARD: Refer to Attachment 8 for verification of proper flow path to identify CC1328 is closed and open CC1328. Start/ensure CRD Cooling Booster Pump 1 is running.
NOTE:  If the CRD Booster Pump 1 switch is left in auto after attempting to start in performance step 11 the pump will auto start when CC1328 is open,                      otherwise verify the pump is running by returning the switch to auto. CUE:  None        __________
SAT UNSAT TERMINATING CUES:  This JPM is complete (Terminated by the examiner)
 
__________
END TIME Simulator JPM S2 Facility:
Davis-Besse    Task No:  000-093-05-0100    Task Title
: Transfer LPI Suctions to the Emergency Sump K/A  


==Reference:==
==Reference:==
  (006) A4.05 (3.9/3.8)________Job Performance Measure No:  S2 (JPM 291)  Examinee:           NRC Examiner:        Date:      Method of testing: Simulated Performance _ __  Actual Performance __X__ Classroom ___  Simulator _X_    Plant ___ Read to the examinee: I will explain the initial conditions, which steps to simulate or discuss, and provide initiating cues. When you complete the task successfully, the objective for this job performance measure will be satisfied. Initial Conditions: The plant conditions are specified in the Initial Conditions and Initiating Cues.
 
Task Standard: Transfer LPI Suctions to the Emergency Sump Required Materials: Attachment 7 Section 2 of DB-OP-02000, RPS, SFAS, SFRCS Trip, or SG Tube Rupture.
(006) A4.05 (3.9/3.8)________Job Performance Measure No
:  S2 (JPM 291)  Examinee:
NRC Examiner:        Date:      Method of testing:
Simulated Performance _
__  Actual Performance __
X__ Classroom ___  Simulator _X_    Plant ___
Read to the examinee:
I will explain the initial conditions, which steps to simulate or discuss, and provide initiating cues. When you complete the task successfully, the objective for this job performance measure will be satisfied.
Initial Conditions:
The plant conditions are specified in the Initial Conditions and Initiating Cues.
 
Task Standard:
Transfer LPI Suctions to the Emergency Sump Required Materials:
Attachment 7 Section 2 of DB-OP-02000, RPS, SFAS, SFRCS Trip, or SG Tube Rupture
.
General  
General  


==References:==
==References:==
None  Initiating Cue: The plant conditions are specified in the Initial Conditions and Initiating Cues.
Time Critical Task: No Alternate Path: Yes  Validation Time: 14 minutes   


SIMULATOR INSTRUCTIONS TASK DESCRIPTION: Transfer LPI Suctions to the Emergency Sump INITIAL CONDITION: Large Break LOCA Spray Pumps are not running   ADDITIONAL SETUP/DEVIATION FROM INITIAL CONDITION: Ensure DH 9A, DH 9B, DH 7A, DH7B and HP 31 are energized   Complete all DB-OP-02000 Section 10 actions up to step 10.13 Turn the "Breaker Open" tags for DH 9A, DH 9B, DH 7A, DH 7B and HP31 upside down Freeze the simulator when BWST level is less than 9 feet Annunciator 5-3-A, BWST LO-LOLVL XFER TO EMER SUMP is in alarm. Output modules L511, L512, L513, and L514 (at least 3 out of 4) have failed to trip.
None  Initiating Cue:
Leave the simulator frozen until the examinee is ready to start the JPM MALFUNCTIONS/FAILURE TO INSERT: Insert both hot leg leaks at the same time, IMF HH41 .8 Fail level 5 output modules to trip, L6AMC, L6BMC, and L6CMC Insight insert TALA531 to 0.1 this is for the BWST LO-LO LVL XFER TO EMER SUMP alarm ACTION/CUES:
The plant conditions are specified in the Initial Conditions and Initiating Cues.
STUDENT COPY INITIAL CONDITIONS: A large break LOCA has occurred and the BWST level is less than nine feet. Both MU pumps and HPI pumps have been stopped in accordance with DB-OP-02000 Section 10 and Specific Rule guidance. DB-OP-02000, Attachment 7, Section 1. Action to close breakers for DH7A, DH7B, DH9A, DH9B, and HP31 has been completed IAW DB-OP-02000 step 10.3.
 
DB-OP-02000, Attachment 7, Section 2, Suction Transfer, Steps 1 through 4 have been completed IAW DB-OP-02000 step 10.11. INITIATING CUES: Annunciator "BWST LO-LO LVL, XFER TO EMER SUMP" (5-3-A) has been received. The Command SRO directs you to transfer LPI suction to the emergency sump in accordance with DB-OP-02000, Attachment 7, Section 2. For the purpose of this JPM the Command SRO is not directing the step by step performance of this attachment.
Time Critical Task:
EXAMINER COPY INITIAL CONDITIONS: A large break LOCA has occurred and the BWST level is less than nine feet. Both MU pumps and HPI pumps have been stopped in accordance with DB-OP-02000 Section 10 and Specific Rule guidance. DB-OP-02000, Attachment 7, Section 1. Action to close breakers for DH7A, DH7B, DH9A, DH9B, and HP31 has been completed IAW DB-OP-02000 step 10.3.
No Alternate Path: Yes  Validation Time:
DB-OP-02000, Attachment 7, Section 2. Suction Transfer, Steps 1 through 4 has been completed IAW DB-OP-02000 step 10.11. INITIATING CUES: Annunciator "BWST LO-LO LVL, XFER TO EMER SUMP" (5-3-A) has been received. The Command SRO directs you to transfer LPI suction to the emergency sump in accordance with DB-OP-02000, Attachment 7, Section 2. For the purpose of this JPM the Command SRO is not directing the step by step performance of this attachment. (Provide the examinee a copy of DB-OP-02000, Attachment 7 Section 2. Freeze simulator until examinee is ready to start-should have time to review)
14 minutes   
PERFORMANCE INFORMATION NOTE: Critical steps denoted with a "C". Failure to meet any one of these standards for this item constitutes failure. Sequence is NOT assumed unless denoted in the "Comments". START TIME:   NOTE: Unfreeze simulator when student has completed procedure review 1. PERFORMANCE STEP: Block SFAS Level 2 on DH 7A, DH 9A, DH 7B and DH 9B. C          STANDARD: Depress BLOCK pushbuttons for DH 7A (HISDH7A1) or DH 9A (HISDH9A)                                      and DH 7B (HISDH7B1) or DH 9B (HISDH9B) and verify all 4 valves are                                      blocked. NOTE: Blocking either DH7A or DH9A will block the other as does DH7B/9B. CUE: None      __________       SAT  UNSAT  2. PERFORMANCE STEP: Check BWST Level is less than or equal to 9 feet. STANDARD: Check BWST level < or equal to 9 feet on level indicators. CUE: None      __________       SAT  UNSAT  3. PERFORMANCE STEP: Open the Containment Emergency Sump Isolation Valves.      STANDARD: Depress the OPEN pushbutton on HIS DH9A. CUE: None        __________       SAT  UNSAT  ALTERNATE PATH - Must recognize DH9A/DH9B did not start opening and the appropriate                                       SFAS Level 5 Output Modules are not tripped as required. This will                                                 require manually tripping the affected Output Modules to allow                                     DH9A/DH9B to be opened.          
 
SIMULATOR INSTRUCTIONS TASK DESCRIPTION: Transfer LPI Suctions to the Emergency Sump INITIAL CONDITION: Large Break LOCA Spray Pumps are not running ADDITIONAL SETUP/DEVIATION FROM INITIAL CONDITION: Ensure DH 9A, DH 9B, DH 7A, DH7B and HP 31 are energized Complete all DB
-OP-02000 Section 10 actions up to step 10.13 Turn the "Breaker Open" tags for DH 9A, DH 9B, DH 7A, DH 7B and HP31 upside down Freeze the simulator when BWST level is less than 9 feet
 
Annunciator 5-3-A, BWST LO
-LOLVL XFER TO EMER SUMP is in alarm. Output modules L511, L512, L513, and L514 (at least 3 out of 4) have failed to trip.
 
Leave the simulator frozen until the examinee is ready to start the JPM MALFUNCTIONS/FAILURE TO INSERT: Insert both hot leg leaks at the same time, IMF HH41 .8 Fail level 5 output modules to trip, L6AMC, L6BMC
, and L6CMC Insight insert TALA531 to 0.1 this is for the BWST LO
-LO LVL XFER TO EMER SUMP alarm ACTION/CUES:
STUDENT COPY INITIAL CONDITIONS: A large break LOCA has occurred and the BWST level is less than nine feet. Both MU pumps and HPI pumps have been stopped in accordance with DB
-OP-02000 Section 10 and Specific Rule guidance.
DB-OP-02000, Attachment 7, Section 1. Action to close breakers for DH7A, DH7B, DH9A, DH9B, and HP31 has been completed IAW DB
-OP-02000 step 10.3.
 
DB-OP-02000, Attachment 7, Section 2, Suction Transfer, Steps 1 through 4 ha ve been completed IAW DB
-OP-02000 step 10.11.
INITIATING CU ES: Annunciator "BWST LO
-LO LVL, XFER TO EMER SUMP" (5-3-A) has been received
. The Command SRO directs you to transfer LPI suction to the emergency sump in accordance with DB-OP-02000, Attachment 7, Section 2.
For the purpose of this JPM the Command SRO is not directing the step by step performance of this attachment.
 
EXAMINER COPY INITIAL CONDITIONS: A large break LOCA has occurred and the BWST level is less than nine feet. Both MU pumps and HPI pumps have been stopped in accordance with DB
-OP-02000 Section 10 and Specific Rule guidance.
DB-OP-02000, Attachment 7, Section 1. Action to close breakers for DH7A, DH7B, DH9A, DH9B, and HP31 has been completed IAW DB
-OP-02000 step 10.3.
 
DB-OP-02000, Attachment 7, Section 2. Suction Transfer, Steps 1 through 4 has been completed IAW DB
-OP-02000 step 10.11.
INITIATING CUES: Annunciator "BWST LO
-LO LVL, XFER TO EMER SUMP" (5-3-A) has been received
. The Command SRO directs you to transfer LPI suction to the emergency sump in accordance with DB-OP-02000, Attachment 7, Section 2.
For the purpose of this JPM the Command SRO is not directing the step by step performance of this attachment.
  (Provide the examinee a copy of DB
-OP-02000, Attachment 7 Section 2. Freeze simulator until examinee is ready to start
-should have time to review)
PERFORMANCE INFORMATION NOTE: Critical steps denoted with a "C". Failure to meet any one of these standards for this item constitutes failure. Sequence is NOT assumed unless denoted in the "Comments".
START TIME:
NOTE: Unfreeze simulator when student has completed procedure review
: 1. PERFORMANCE STEP: Block SFAS Level 2 on DH 7A, DH 9A, DH 7B and DH 9B. C          STANDARD:
Depress BLOCK pushbuttons for DH 7A (HISDH7A1) or DH 9A (HISDH9A)                                      and DH 7B (HISDH7B1) or DH 9B (HISDH9B) and verify all 4 valves are                                      blocked. NOTE: Blocking either DH7A or DH9A will block the other as does DH7B/9B.
CUE: None      __________
SAT  UNSAT  2. PERFORMANCE STEP: Check BWST Level is less than or equal to 9 feet. STANDARD: Check BWST level < or equal to 9 feet on level indicators. CUE: None      __________
SAT  UNSAT  3. PERFORMANCE STEP: Open the Containment Emergency Sump Isolation Valves.      STANDARD:
Depress the OPEN pushbutton on HIS DH9A. CUE: None        __________
SAT  UNSAT  ALTERNATE PATH - Must recognize DH9A/DH9B did not start opening and the appropriate SFAS Level 5 Output Modules are not tripped as required. This will
 
require manually tripping the affected Output Modules to allow DH9A/DH9B to be opened.
: 4. PERFORMANCE STEP: Recognize DH9A does not open.
: 4. PERFORMANCE STEP: Recognize DH9A does not open.
STANDARD: HIS DH9A green light remains lit.
STANDARD: HIS DH9A green light remains lit.
CUE: Role play as Command SRO if required, Acknowledge DH9A did not open.      __________       SAT  UNSAT  5. PERFORMANCE STEP: Open DH 9B.      STANDARD: Depress the OPEN pushbutton on HIS DH9B. CUE: None      __________       SAT  UNSAT  6. PERFORMANCE STEP: Recognize DH9B does not open.
CUE: Role play as Command SRO if required, Acknowledge DH9A did not open.      __________
STANDARD: HIS DH9B green light remains lit.        CUE: Role play as Command SRO if required, Acknowledge DH9B did not open.           __________       SAT UNSAT    7. PERFORMANCE STEP: Manually trip Train 1 SFAS Level 5 Output Modules.                C      STANDARD: Depress and release the trip pushbuttons next to L511 and L513. COMMENT: Step 7 and 8 can be done in either order.
SAT  UNSAT  5. PERFORMANCE STEP: Open DH 9B.      STANDARD:
CUE: Another RO is monitoring conditions for cavitation.       __________       SAT UNSAT    8. PERFORMANCE STEP: Manually trip Train 2 SFAS Level 5 Output Modules.                C            STANDARD: Depress and release the trip pushbuttons next to L512 and L514.         CUE: None        __________ _______________________________________________________________SAT UNSAT__    
Depress the OPEN pushbutton on HIS DH9B. CUE: None      __________
: 9. PERFORMANCE STEP: Open DH 9A.        C                STANDARD: Depress the OPEN pushbutton on HIS DH9A.        CUE: None
SAT  UNSAT  6. PERFORMANCE STEP: Recognize DH9B does not open.
__________       SAT  UNSAT  10. PERFORMANCE STEP: Verify that DH 9A starts to open.        STANDARD: Check GREEN light OFF on HIS DH9A.        CUE: None      __________       SAT  UNSAT    11. PERFORMANCE STEP: Open DH 9B.        C          STANDARD: Depress the OPEN pushbutton on HIS DH9B.        CUE: None      __________       SAT  UNSAT  12. PERFORMANCE STEP: Verify that DH 9B starts to open.        STANDARD: Check GREEN light OFF on HIS DH9B.        CUE: None      __________       SAT  UNSAT  13. PERFORMANCE STEP: Verify that DH 7A starts to close as DH 9A starts to open.        STANDARD: Recognize DH7A starts to close, check RED light OFF on HIS DH7A.        CUE: None      __________       SAT  UNSAT     
STANDARD: HIS DH9B green light remains lit.        CUE: Role play as Command SRO if required, Acknowledge DH9B did not open.
 
__________
SAT UNSAT    7. PERFORMANCE STEP: Manually trip Train 1 SFAS Level 5 Output Modules.                C      STANDARD: Depress and release the trip pushbuttons next to L511 and L513.
COMMENT: Step 7 and 8 can be done in either order
.
CUE: Another RO is monitoring conditions for cavitation.
__________
SAT UNSAT    8. PERFORMANCE STEP: Manually trip Train 2 SFAS Level 5 Output Modules.                C            STANDARD: Depress and release the trip pushbuttons next to L512 and L514.
CUE: None        __________
_______________________________________________________________SAT UNSAT__  
: 9. PERFORMANCE STEP: Open DH 9A.        C                STANDARD:
Depress the OPEN pushbutton on HIS DH9A.        CUE: None
__________
SAT  UNSAT  10. PERFORMANCE STEP: Verify that DH 9A starts to open.        STANDARD:
Check GREEN light OFF on HIS DH9A.        CUE: None      __________
SAT  UNSAT    11. PERFORMANCE STEP: Open DH 9B.        C          STANDARD:
Depress the OPEN pushbutton on HIS DH9B.        CUE: None      __________
SAT  UNSAT  12. PERFORMANCE STEP: Verify that DH 9B starts to open.        STANDARD:
Check GREEN light OFF on HIS DH9B.        CUE: None      __________
SAT  UNSAT  13. PERFORMANCE STEP: Verify that DH 7A starts to close as DH 9A starts to open.        STANDARD:
Recognize DH7A starts to close, check RED light OFF on HIS DH7A.        CUE: None      __________
SAT  UNSAT     
: 14. PERFORMANCE STEP: Verify that DH 7B starts to close as DH 9B starts to open.
: 14. PERFORMANCE STEP: Verify that DH 7B starts to close as DH 9B starts to open.
STANDARD: Recognize DH7B starts to close, check RED light OFF on HIS DH7B.        CUE: None      __________       SAT  UNSAT  15. PERFORMANCE STEP: Verify the transfer is complete.         STANDARD: Check the RED indicating lights on HIS DH9A and HIS DH9B are LIT and                                        the GREEN indicating lights on HIS DH7A and HIS DH7B are LIT.
STANDARD:
Check low pressure injection flow NOT significantly changed.        CUE: None.      __________       SAT  UNSAT  TERMINATING CUES:  This JPM is complete (Terminated by the examiner)       __________       END TIME         
Recognize DH7B starts to close, check RED light OFF on HIS DH7B.        CUE: None      __________
SAT  UNSAT  15. PERFORMANCE STEP: Verify the transfer is complete.
STANDARD:
Check the RED indicating lights on HIS DH9A and HIS DH9B are LIT and                                        the GREEN indicating lights on HIS DH7A and HIS DH7B are LIT.
Check low pressure injection flow NOT significantly changed.        CUE: None.      __________
SAT  UNSAT  TERMINATING CUES:  This JPM is complete (Terminated by the examiner)
__________
END TIME         
 
Simulator JPM S3 Facility:
Davis-Besse    Task No:  004-029-05-0100               


Simulator JPM S3 Facility:            Davis-Besse    Task No:  004-029-05-0100                                Task Title:  Recover From MU/HPI/PORV Cooling        K/A  
Task Title
:  Recover From MU/HPI/PORV Cooling        K/A  


==Reference:==
==Reference:==
       (010) A2.03 4.1/4.2        Job Performance Measure No:  S3 (JPM 063)    Examinee:           NRC Examiner:        Date:      Method of testing: Simulated Performance ___  Actual Performance _X_  Classroom ___  Simulator _X_  Plant ___
       (010) A2.03 4.1/4.2        Job Performance Measure No
Read to the examinee: I will explain the initial conditions, which steps to simulate or discuss, and provide initiating cues.
:  S3 (JPM 063)    Examinee:
NRC Examiner:        Date:      Method of testing:
Simulated Performance ___  Actual Performance _X_  Classroom ___  Simulator _X_  Plant ___
 
Read to the examinee:
I will explain the initial conditions, which steps to simulate or discuss, and provide initiating cues.
When you complete the task successfully, the objective for this job performance measure will be satisfied.
When you complete the task successfully, the objective for this job performance measure will be satisfied.
Initial Conditions: The plant conditions are specified in the Initial Conditions and Initiating Cues. Task Standard: Perform Recovery from MU/HPI PORV Cooling and recognize failure of the PORV to close and take immediate actions. Required Materials: Attachment 25 of DB-OP-02000, RPS, SFAS, SFRCS Trip, or SG Tube Rupture. General  
 
Initial Conditions:
The plant conditions are specified in the Initial Conditions and Initiating Cues.
Task Standard:
Perform Recovery from MU/HPI PORV Cooling and recognize failure of the PORV to close and take immediate actions. Required Materials:
Attachment 25 of DB
-OP-02000, RPS, SFAS, SFRCS Trip, or SG Tube Rupture. General  


==References:==
==References:==
None  Initiating Cue: The plant conditions are specified in the Initial Conditions and Initiating Cues.
Time Critical Task:  No    Alternate Path: Yes Validation Time: 11 minutes SIMULATOR INSTRUCTIONS  TASK DESCRIPTION: Perform Recovery From MU/HPI PORV Cooling and recognize failure of the PORV to close and take immediate actions. INITIAL CONDITION: Loss of all Feedwater MU/HPI cooling initiated MDFP feeding both SGs  ADDITIONAL SETUP/DEVIATION FROM INITIAL CONDITION:  Fail Makeup Pump 2 to start  Fail both AFPTs to start Unfreeze the simulator after the initial cue is given to minimize excessive SCM  MALFUNCTIONS/FAILURE TO INSERT: Fail the PORV open  ACTIONS/CUES None


EXAMINER COPY INITIAL CONDITIONS: The reactor has tripped   All Feedwater was lost   Makeup Pump 2 did NOT start  Makeup/HPI/PORV Cooling was initiated INITIATING CUES: The MDFP has been started and is feeding both Steam Generators.
None  Initiating Cue:
A second operator is controlling Steam Generator levels, pressures, and steaming of Steam Generators. The Unit Supervisor directs you to recover from MU/HPI/PORV Cooling using Attachment 25 of DB-OP-02000. For the purpose of this JPM the Command SRO is not directing the step by step performance of this attachment.
The plant conditions are specified in the Initial Conditions and Initiating Cues.
(Provide Attachment 25 of DB-OP-02000, RPS, SFAS, SFRCS Trip, or SG Tube Rupture)
 
CANDIDATE COPY INITIAL CONDITIONS: The reactor has tripped   All Feedwater was lost   Makeup Pump 2 did NOT start  Makeup/HPI/PORV Cooling was initiated INITIATING CUES: The MDFP has been started and is feeding both Steam Generators A second operator is controlling Steam Generator levels and pressures The Unit Supervisor directs you to recover from MU/HPI/PORV Cooling using Attachment 25 of DB-OP-02000. For the purpose of this JPM the Command SRO is not directing the step by step performance of this attachment.
Time Critical Task:
No    Alternate Path:
Yes Validation Time:
11 minutes
 
SIMULATOR INSTRUCTIONS TASK DESCRIPTION: Perform Recovery From MU/HPI PORV Cooling and recognize failure of the PORV to close and take immediate actions.
INITIAL CONDITION: Loss of all Feedwater MU/HPI cooling initiated MDFP feeding both SGs ADDITIONAL SETUP/DEVIATION FROM INITIAL CONDITION:  Fail Makeup Pump 2 to start Fail both AFPTs to start
 
Unfreeze the simulator after the initial cue is given to minimize excessive SCM MALFUNCTIONS/FAILURE TO INSERT: Fail the PORV open ACTIONS/CUES None
 
EXAMINER COPY INITIAL CONDITIONS: The reactor has tripped All Feedwater was lost Makeup Pump 2 did NOT start  Makeup/HPI/PORV Cooling was initiated INITIATING CUES
: The MDFP has been started and is feeding both Steam Generators.
A second operator is controlling Steam Generator levels, pressures, and steaming of Steam Generators.
The Unit Supervisor directs you to recover from MU/HPI/PORV Cooling using Attachment 25 of  
 
DB-OP-02000. For the purpose of this JPM the Command SRO is not directing the step by step performance of this attachment.
 
(Provide 5 of DB
-OP-02000, RPS, SFAS, SFRCS Trip, or SG Tube Rupture)  
 
CANDIDATE COPY INITIAL CONDITIONS: The reactor has tripped All Feedwater was lost Makeup Pump 2 did NOT start  Makeup/HPI/PORV Cooling was initiated INITIATING CUES
: The MDFP has been started and is feeding both Steam Generators
 
A second operator is controlling Steam Generator levels and pressures
 
The Unit Supervisor directs you to recover from MU/HPI/PORV Cooling using Attachment 25 of DB-OP-02000. For the purpose of this JPM the Command SRO is not directing the step by step performance of this attachment.


PERFORMANCE INFORMATION NOTE: Critical steps denoted with a "C". Failure to meet any one of these standards for this item constitutes failure. Sequence is NOT critical unless denoted in the "Comments". START TIME:  _______   1. PERFORMANCE STEP: Establish the letdown flow.  ........C........ STANDARD: Depress OPEN on HISMU2B. COMMENT: Sequence of opening MU 2B, MU 2A and MU 3 NOT critical     CUE: If asked for desired flow "Establish 70 gpm" (flow rate not critical)   Note: may establish 140 gpm __________       SAT  UNSAT   
PERFORMANCE INFORMATION NOTE: Critical steps denoted with a "C". Failure to meet any one of these standards for this item constitutes failure. Sequence is NOT critical unless denoted in the "Comments".
: 2. PERFORMANCE STEP: Establish the letdown flow.  ........C........ STANDARD: Depress BLOCK for MU 2A. Depress OPEN on HISMU2A.
START TIME:  _______
COMMENT: Sequence of opening MU 2B, MU 2A and MU 3 NOT critical   CUE: If asked for desired flow "Establish 70 gpm" (flow rate not critical)   Note: may establish 140 gpm       __________       SAT  UNSAT  3. PERFORMANCE STEP: Establish the letdown flow  ........C........
: 1. PERFORMANCE STEP: Establish the letdown flow.  ........C........ STANDARD:
STANDARD: Depress BLOCK pushbutton for MU 3. Depress OPEN pushbutton on HISMU3. COMMENT: Sequence of opening MU 2B, MU 2A and MU 3 NOT critical   CUE: If asked for desired flow "Establish 70 gpm" (letdown flow rate not critical). Note: may establish 140 gpm      __________       SAT  UNSAT  4. PERFORMANCE STEP: Open the MU Pumps Minimum Recirc Valves.  ........C........ STANDARD: Depress the OPEN pushbutton on HISMU6407. CUE: None  __________       SAT  UNSAT     
Depress OPEN on HISMU2B. COMMENT: Sequence of opening MU 2B, MU 2A and MU 3 NOT critical CUE: If asked for desired flow "Establish 70 gpm" (flow rate not critical)
: 5. PERFORMANCE STEP: Open the MU Pumps Minimum Recirc Valves. STANDARD: Depress the OPEN pushbutton on HISMU6406. COMMENT: MU 6406 not critical due to MUP 2 not running   CUE: None      __________       SAT  UNSAT  6. PERFORMANCE STEP: IF BOTH MU Pumps are in service perform the following:    STANDARD: Recognize this step does not apply - mark N/A. COMMENT: Only MUP 1 is in service   CUE: None      __________       SAT  UNSAT   
Note: may establish 140 gpm
: 7. PERFORMANCE STEP: Isolate the normal MU Injection header. STANDARD: Depress the CLOSE pushbutton on HISMU6422.
__________
CUE: None      __________       SAT  UNSAT   
SAT  UNSAT   
: 8. PERFORMANCE STEP: Establish desired MU flow rate by throttling MU6419. STANDARD: Depress and hold the CLOSE pushbutton on HIS MU 6419 to throttle the                               valve closed and reduce flow rate to desired value while maintaining adequate Subcooling Margin.
: 2. PERFORMANCE STEP: Establish the letdown flow.  ........C........ STANDARD:
CUE: (If asked) MU 6423B is open to maintain minimum flow       __________       SAT  UNSAT     
Depress BLOCK for MU 2A. Depress OPEN on HISMU2A.
COMMENT: Sequence of opening MU 2B, MU 2A and MU 3 NOT critical CUE: If asked for desired flow "Establish 70 gpm" (flow rate not critical)
Note: may establish 140 gpm
__________
SAT  UNSAT  3. PERFORMANCE STEP: Establish the letdown flow  
   ........C........
STANDARD:
Depress BLOCK pushbutton for MU 3. Depress OPEN pushbutton on HISMU3. COMMENT: Sequence of opening MU 2B, MU 2A and MU 3 NOT critical CUE: If asked for desired flow "Establish 70 gpm" (letdown flow rate not critical). Note: may establish 140 gpm      __________
SAT  UNSAT  4. PERFORMANCE STEP: Open the MU Pumps Minimum Recirc Valves.  ........C........ STANDARD:
Depress the OPEN pushbutton on HISMU6407. CUE: None  __________
SAT  UNSAT     
: 5. PERFORMANCE STEP: Open the MU Pumps Minimum Recirc Valves. STANDARD:
Depress the OPEN pushbutton on HISMU6406. COMMENT: MU 6406 not critical due to MUP 2 not running CUE: None      __________
SAT  UNSAT  6. PERFORMANCE STEP: IF BOTH MU Pumps are in service perform the following:    STANDARD:
Recognize this step does not apply - mark N/A. COMMENT: Only MUP 1 is in service CUE: None      __________
SAT  UNSAT   
: 7. PERFORMANCE STEP: Isolate the normal MU Injection header. STANDARD:
Depress the CLOSE pushbutton on HISMU6422.
CUE: None      __________
SAT  UNSAT   
: 8. PERFORMANCE STEP: Establish desired MU flow rate by throttling MU6419. STANDARD:
Depress and hold the CLOSE pushbutton on HIS MU 6419 to throttle the valve closed and reduce flow rate to desired value while maintaining adequate Subcooling Margin.
CUE: (If asked) MU 6423B is open to maintain minimum flow
__________
SAT  UNSAT     
: 9. PERFORMANCE STEP: Restore MU Pump Suction.  
: 9. PERFORMANCE STEP: Restore MU Pump Suction.  
  ........C........ STANDARD: Depress the OFF pushbutton on HISMU6405. CUE: None        __________       SAT  UNSAT   
  ........C........
STANDARD:
Depress the OFF pushbutton on HISMU6405. CUE: None        __________
SAT  UNSAT   
: 10. PERFORMANCE STEP: Restore MU Pump Suction.
: 10. PERFORMANCE STEP: Restore MU Pump Suction.
STANDARD: Depress the OFF pushbutton on HISMU3971. COMMENT: MU3971 not critical due to MUP 2 not running   CUE: None      __________       SAT  UNSAT   
STANDARD:
: 11. PERFORMANCE STEP: IF only MU Pump 2 is in service perform the following. STANDARD: Recognize this step does not apply - mark N/A. COMMENT: Only MUP 1 is in service   CUE: None      __________       SAT  UNSAT   
Depress the OFF pushbutton on HISMU3971. COMMENT: MU3971 not critical due to MUP 2 not running CUE: None      __________
: 12. PERFORMANCE STEP: Perform the following to recover RCS Inventory control:   STANDARD: Maintain Steam Generator levels per specific rule 4. CUE: Balance Of Plant RO is maintaining SG Levels       __________   SAT  UNSAT 13. PERFORMANCE STEP: Perform the following to recover RCS Inventory control:   STANDARD: Reduce HPI Flow to establish a decreasing SCM trend (maintain minimum Subcooling Margin) by throttling HP2A-D as necessary.
SAT  UNSAT   
Comment: Two handed operations is authorized for positioning HP2A through HP2D   CUE: None      __________   SAT  UNSAT
: 11. PERFORMANCE STEP: IF only MU Pump 2 is in service perform the following. STANDARD:
: 14. PERFORMANCE STEP: Perform the following to recover RCS Inventory control:   STANDARD: Raise letdown flow to maximum available by throttling MU6 and/or placing a second purification demineralizer in service. CUE: If asked for desired flow "Establish 70 gpm" (letdown flow rate not critical).      Note: may establish 140 gpm      __________       SAT  UNSAT       
Recognize this step does not apply - mark N/A. COMMENT: Only MUP 1 is in service CUE: None      __________
SAT  UNSAT   
: 12. PERFORMANCE STEP: Perform the following to recover RCS Inventory control:
STANDARD:
Maintain Steam Generator levels per specific rule 4. CUE: Balance Of Plant RO is maintaining SG Levels
__________
SAT  UNSAT
: 13. PERFORMANCE STEP: Perform the following to recover RCS Inventory control:
STANDARD:
Reduce HPI Flow to establish a decreasing SCM trend (maintain minimum Subcooling Margin) by throttling HP2A
-D as necessary.
Comment: Two handed operations is authorized for positioning HP2A through HP2D CUE: None      __________
SAT  UNSAT
: 14. PERFORMANCE STEP: Perform the following to recover RCS Inventory control:
STANDARD:
Raise letdown flow to maximum available by throttling MU6 and/or placing a second purification demineralizer in service. CUE: If asked for desired flow "Establish 70 gpm" (letdown flow rate not critical).      Note: may establish 140 gpm      __________
SAT  UNSAT       


ALTERNATH PATH: RC2A is expected to close. Must recognize PORV did not close and perform actions of the response not obtained column to close the PORV Block Valve.
ALTERNATH PATH: RC2A is expected to close. Must recognize PORV did not close and perform actions of the response not obtained column to close the PORV Block Valve.
: 15. PERFORMANCE STEP: Close the PORV.
: 15. PERFORMANCE STEP: Close the PORV.
STANDARD: Rotate HIS RC 2A to the AUTO position and Push to Close. Recognize the PORV did NOT close. CUE: None      __________       SAT  UNSAT   
STANDARD:
Rotate HIS RC 2A to the AUTO position and Push to Close. Recognize the PORV did NOT close. CUE: None      __________
SAT  UNSAT   
: 16. PERFORMANCE STEP: Close the PORV Block Valve.  ........C........
: 16. PERFORMANCE STEP: Close the PORV Block Valve.  ........C........
STANDARD: Depress the CLOSE pushbutton on HISRC11 and verify it closes. CUE: None.      __________       SAT  UNSAT  TERMINATING CUES: This JPM is complete (Terminated by the evaluator)         __________       END TIME Simulator JPM S4 Facility: Davis-Besse    Task No:    059-012-04-0100    Task Title: Main Feed Pump Startup/Transfer to ICS Control K/A  
 
STANDARD:
Depress the CLOSE pushbutton on HISRC11 and verify it closes.
CUE: None.      __________
SAT  UNSAT  TERMINATING CUES:
This JPM is complete (Terminated by the evaluator)
__________
END TIME Simulator JPM S4 Facility:
Davis-Besse    Task No:    059-012-04-0100    Task Title
: Main Feed Pump Startup/Transfer to ICS Control K/A  


==Reference:==
==Reference:==
  (059) A4.10 (3.9/3.8)________ Job Performance Measure No:  S4 (JPM New)   Examinee:           NRC Examiner:        Date:      Method of testing: Simulated Performance _ __  Actual Performance __X__ Classroom ___  Simulator _X_    Plant ___ Read to the examinee: I will explain the initial conditions, which steps to simulate or discuss, and provide initiating cues. When you complete the task successfully, the objective for this job performance measure will be satisfied. Initial Conditions: The plant conditions are specified in the Initial Conditions and Initiating Cues.
  (059) A4.10 (3.9/3.8)________
Task Standard: Perform steps to place Main Feed Pump in service and emergency trip due to low oil pressure   Required Materials: DB-OP-06901, Plant Startup, signed off through step 3.24 with step 3.25 in progress DB-OP-06224, Main Feed Pump and Turbine, section 3.16, Startup of MFP2, signed off as                           applicable through step 3.16.43. DB-OP-06224, Main Feed Pump and Turbine, section 3.17, Transferring MFPT 2 Speed Control                           Between MDT20 and ICS DB-OP-02010, pages 10 and 11 for Annunciator 10-1-D General  
Job Performance Measure No
:  S4 (JPM New)
Examinee:
NRC Examiner:        Date:      Method of testing:
Simulated Performance _
__  Actual Performance __
X__ Classroom ___  Simulator _X_    Plant ___
Read to the examinee:
I will explain the initial conditions, which steps to simulate or discuss, and provide initiating cues. When you complete the task successfully, the objective for this job performance measure will be satisfied.
Initial Conditions:
The plant conditions are specified in the Initial Conditions and Initiating Cues.
 
Task Standard:
Perform steps to place Main Feed Pump in service and emergency trip due to low oil pressure Required Materials:
DB-OP-06901, Plant Startup, signed off through step 3.24 with step 3.25 in progress DB-OP-06224, Main Feed Pump and Turbine, section 3.16, Startup of MFP2, signed off as applicable through step 3.16.43.
DB-OP-06224, Main Feed Pump and Turbine, section 3.17, Transferring MFPT 2 Speed Control Between MDT20 and ICS DB-OP-02010, pages 10 and 11 for Annunciator 10-1-D General  


==References:==
==References:==
None Initiating Cue: The plant conditions are specified in the Initial Conditions and Initiating Cues. Time Critical Task: No Alternate Path: Yes  Validation Time: 9 minutes SIMULATOR INSTRUCTIONS TASK DESCRIPTION: Perform steps to place Main Feed Pump in service and emergency trip due to low oil pressure   INITIAL CONDITION: Mode 2 with reactor power at 2%. Main Feed Pump 2 startup in progress and ready to transfer to ICS Hand/Auto station control (step 3.16.44 of DB-OP-06224, Main Feed Pump and Turbine). ADDITIONAL SETUP/DEVIATION FROM INITIAL CONDITION:    MALFUNCTIONS/FAILURE TO INSERT: Insert low oil pressure #2 MFPT when increasing speed to raise discharge pressure to 1000psig to 1050psig (triggered at approximately 950psig)  
 
None Initiating Cue:
The plant conditions are specified in the Initial Conditions and Initiating Cues.
Time Critical Task:
No Alternate Path: Yes  Validation Time: 9 minutes
 
SIMULATOR INSTRUCTIONS
 
TASK DESCRIPTION: Perform steps to place Main Feed Pump in service and emergency trip due to low oil pressure INITIAL CONDITION: Mode 2 with reactor power at 2%. Main Feed Pump 2 startup in progress and ready to transfer to ICS Hand/Auto station control (step 3.16.44 of DB-OP-06224, Main Feed Pump and Turbine). ADDITIONAL SETUP/DEVIATION FROM INITIAL CONDITION:    MALFUNCTIONS/FAILURE TO INSERT: Insert low oil pressure #2 MFPT when increasing speed to raise discharge pressure to 1000psig to 1050psig (triggered at approximately 950psig)  


ACTION/CUES:   
ACTION/CUES:   


STUDENT COPY INITIAL CONDITIONS: Mode 2 with reactor power at 2%. Main Feed Pump 2 startup in progress and ready to transfer to ICS Hand/Auto station control (step 3.16.44 of DB-OP-06224, Main Feed Pump and Turbine) INITIATING CUES: The unit supervisor has directed you to continue with #2 MFP startup starting at step 3.16.44 of DB-OP-06224, Main Feed Pump and Turbine. Transfer #2 MFP to ICS Hand/Auto station control and continue with step 3.26 of DB-OP-06901, Plant Startup, to transfer feedwater from the MDFP to the MFP.
STUDENT COPY INITIAL CONDITIONS: Mode 2 with reactor power at 2%. Main Feed Pump 2 startup in progress and ready to transfer to ICS Hand/Auto station control (step 3.16.44 of DB
EXAMINER COPY INITIAL CONDITIONS: Mode 2 with reactor power at 2%. Main Feed Pump 2 startup in progress and ready to transfer to ICS Hand/Auto station control (step 3.16.44 of DB-OP-06224, Main Feed Pump and Turbine). INITIATING CUES: The unit supervisor has directed you to continue with #2 MFP startup starting at step 3.16.44 of DB-OP-06224, Main Feed Pump and Turbine. Transfer #2 MFP to ICS Hand/Auto station control and continue with step 3.26 of DB-OP-06901, Plant Startup, to transfer feedwater from the MDFP to the MFP. (Provide the examinee a copy of the following documents: DB-OP-06901, Plant Startup, signed off through step 3.24 with step 3.25 in progress DB-OP-06224, Main Feed Pump and Turbine, section 3.16, Startup of MFP2, signed off as                                                     applicable through step 3.16.43. DB-OP-06224, Main Feed Pump and Turbine, section 3.17, Transferring MFPT 2 Speed                           Control Between MDT20 and ICS)     
-OP-06224, Main Feed Pump and Turbine)
INITIATING CUES: The unit supervisor has directed you to continue with #2 MFP startup starting at step 3.16.44 of DB-OP-06224, Main Feed Pump and Turbine. Transfer #2 MFP to ICS Hand/Auto station control and continue with step 3.26 of DB
-OP-06901, Plant Startup, to transfer feedwater from the MDFP to the MFP.
 
EXAMINER COPY INITIAL CONDITIONS: Mode 2 with reactor power at 2%. Main Feed Pump 2 startup in progress and ready to transfer to ICS Hand/Auto station control (step 3.16.44 of DB
-OP-06224, Main Feed Pump and Turbine). INITIATING CUES: The unit supervisor has directed you to continue with #2 MFP startup starting at step 3.16.44 of DB-OP-06224, Main Feed Pump and Turbine. Transfer #2 MFP to ICS Hand/Auto station control and continue with step 3.26 of DB
-OP-06901, Plant Startup, to transfer feedwater from the MDFP to the MFP.
  (Provide the examinee a copy of the following documents:
DB-OP-06901, Plant Startup, signed off through step 3.24 with step 3.25 in progress DB-OP-06224, Main Feed Pump and Turbine, section 3.16, Startup of MFP2, signed off as
 
applicable through step 3.16.43.
DB-OP-06224, Main Feed Pump and Turbine, section 3.17, Transferring MFPT 2 Speed Control Between MDT20 and ICS)     
 
PERFORMANCE INFORMATION
 
NOTE: Critical steps denoted with a "C". Failure to meet any one of these standards for this item constitutes failure. Sequence is NOT assumed unless denoted in the "Comments".
START TIME:
: 1. PERFORMANCE STEP: Perform section 3.17 of DB
-OP-06224, Main Feed Pump Turbine, and transfer MFPT2 Speed Control from MDT20 to ICS.
STANDARD:
Identify step 3.17
.1 of DB-OP-06224, Main Feed Pump Turbine, for transfer of MFPT2 Speed Control from MDT20 to ICS.      CUE: None      __________
SAT  UNSAT  2. PERFORMANCE STEP: Verify MFPT speed is between 3900 RPM and 5150 RPM STANDARD:
Verify MFPT 2 speed between 3900 RPM and 5150 RPM using indicator SI2708B  CUE:    None      __________
SAT  UNSAT  3. PERFORMANCE STEP: Adjust the ICS Bailey Controller output to indicate a zero amp reading on the XFER METER Amp Y1
-806 STANDARD:
Toggle the ICS Bailey Controller speed control, HIC ICS 36A Hand/Auto Station, to indicate a zero amp reading on the XFER METER Amp Y1
-806    CUE: None      __________
SAT  UNSAT    4. PERFORMANCE STEP: Depress ICS on HIS 806C1


PERFORMANCE INFORMATION NOTE: Critical steps denoted with a "C". Failure to meet any one of these standards for this item constitutes failure. Sequence is NOT assumed unless denoted in the "Comments". START TIME:    1. PERFORMANCE STEP: Perform section 3.17 of DB-OP-06224, Main Feed Pump Turbine,                                                and transfer MFPT2 Speed Control from MDT20 to ICS. STANDARD: Identify step 3.17.1 of DB-OP-06224, Main Feed Pump Turbine,                                    for transfer of MFPT2 Speed Control from MDT20 to ICS.      CUE: None      __________        SAT  UNSAT  2. PERFORMANCE STEP: Verify MFPT speed is between 3900 RPM and 5150 RPM  STANDARD: Verify MFPT 2 speed between 3900 RPM and 5150 RPM using indicator                                    SI2708B  CUE:    None      __________      SAT  UNSAT  3. PERFORMANCE STEP: Adjust the ICS Bailey Controller output to indicate a zero amp                                                      reading on the XFER METER Amp Y1-806 STANDARD: Toggle the ICS Bailey Controller speed control, HIC ICS 36A Hand/Auto                                    Station, to indicate a zero amp reading on the XFER METER Amp Y1-806    CUE: None      __________        SAT  UNSAT    4. PERFORMANCE STEP: Depress ICS on HIS 806C1
........C........
........C........
STANDARD: Depress ICS on HIS 806C1   CUE: None                                      __________       SAT  UNSAT         
STANDARD:
: 5. PERFORMANCE STEP: Check that ICS illuminates and the ICS Bailey Controller assumes                                                       control of MFPT speed. STANDARD: Check that ICS illuminates on HIS 806C1 and that the ICS Bailey Controller assumes control of MFPT 2 speed. CUE: None                                    __________       SAT  UNSAT  6. PERFORMANCE STEP: If ICS Control is unstable, THEN return to MDT20 Control. STANDARD: Recognize proper control by the ICS Controller and mark step 3.17.1.e as                                       N/A. CUE: None                                    __________       SAT  UNSAT   
Depress ICS on HIS 806C1 CUE: None                                      __________
: 7. PERFORMANCE STEP: Adjust the MDT20 output to maintain zero amps indicated on the                                                     XFER METER Y1-806.
SAT  UNSAT         
STANDARD: Maintain zero amps indicated on the XFER METER Y1-806 by occasional                                      adjustment as needed of the MDT20 output.             COMMENT: Student may consider step 3.17.1.f in progress while continuing MFP                                 startup and not sign as complete. CUE: None                                    __________       SAT  UNSAT  8. PERFORMANCE STEP: Complete section 3.17 of DB-OP-06224. STANDARD: Sign and date complete by for section 3.17 of DB-OP-06224.              COMMENT: If student considers step 3.17.1.f to be in progress while continuing MFP                                   startup then section 3.17 will not be signed as complete. CUE: None                                    __________       SAT  UNSAT    9. PERFORMANCE STEP: Sign complete step 3.16.44 of DB-OP-06224. STANDARD: Sign complete step 3.16.44 of DB-OP-06224.               COMMENT: If student considers step 3.17.1.f to be in progress while continuing MFP                                 startup and section 3.17 is not signed as complete then step 3.16.44 may                                  remain in progress. Step 3.16.45 would be performed after the MFP is                                 supplying feedwater to the steam generators. CUE: None                                   __________       SAT  UNSAT    10.      PERFORMANCE STEP: Sign compete step 3.25 of DB-OP-06901, Plant Startup. STANDARD: Sign compete step 3.2.5 of DB-OP-06901, Plant Startup.             COMMENT: Student may continue with step 3.2.5 circled (in progress) because                                   section of DB-OP-06224 is not complete until there is flow to the steam generators and the ARTS Channels test/toggle switches are placed in the operate position at step 3.16.45. CUE: None                                      __________       SAT  UNSAT  11. PERFORMANCE STEP: Raise Main Feed Pump Speed until discharge pressure is              ........C........                      between 1000 and 1050 psig (step 3.26.1 of DB-OP-06901). STANDARD: Raise MFPT 2 speed using manual control of HIC ICS 36A Hand/Auto                                     Station, ICS Bailey Controller, to raise discharge pressure to band of                                           1000-1050 psig.                                                                                     NOTE: Alternate Path begins with low oil pressure Annunciator 10-1-D received as discharge pressure is raised (triggered to alarm at approximately 950psig). CUE: None                                               __________       SAT  UNSAT  12.      PERFORMANCE STEP: Identify Annunciator 10-1-D, MFPT 2 LUBE OIL PRESS LO, in                                                     alarm. STANDARD: Recognize annunciator 10-1-D, MFPT 2 LUBE OIL PRESS LO, in alarm and                                     refer to alarm procedure DB-OP-2010. CUE: If student refers to alarm procedure provide copy of DB-OP-02010 pages 10 and 11 for Annunciator 10-1-D                                                   __________       SAT  UNSAT  13.      PERFORMANCE STEP: Determine if bearing pressure is actually Low. STANDARD: Determine bearing pressure is actually Low (<7 psig) using PI1256,                                      Header Control Pressure. CUE: None                                     __________       SAT  UNSAT   
: 5. PERFORMANCE STEP: Check that ICS illuminates and the ICS Bailey Controller assumes control of MFPT speed.
: 14.      PERFORMANCE STEP: Verify automatic start of standby MFPT 2 Main Oil Pump.             ........C........
STANDARD:
COMMENT:  The standby MFPT 2 Main Oil Pump will not auto start. The pump will                                   start manually and almost immediately trip on electrical fault.     STANDARD: Identify standby MFPT 2 Main Oil Pump is not running and start                                      standby MFPT 2 Main Oil Pump.
Check that ICS illuminates on HIS 806C1 and that the ICS Bailey Controller                                  
CUE: None                                     __________       SAT  UNSAT    15.      PERFORMANCE STEP: If Bearing Header Pressure decreases to less than 4 psig THEN              ........C........                     start the Emergency Bearing Oil Pump and trip MFPT 2. STANDARD: Identify Bearing Header Pressure decreases to less than 4 psig using                                    PI1256. Start the Emergency Bearing Oil Pump (HIS1188). CUE: None                                     __________       SAT  UNSAT    16.      PERFORMANCE STEP: If Bearing Header Pressure decreases to less than 4 psig THEN            ........C........                      start the Emergency Bearing Oil Pump and trip MFPT 2. STANDARD: Trip MFPT 2 using HS 798 trip push button. CUE: None                                     __________       SAT  UNSAT      TERMINATING CUES:   This JPM is complete. (Terminated by the examiner)      __________       END TIME   
 
assumes control of MFPT 2 speed.
CUE: None                                    __________
SAT  UNSAT  6. PERFORMANCE STEP: If ICS Control is unstable, THEN return to MDT20 Contro
: l. STANDARD:
Recognize proper control by the ICS Controller and mark step 3.17.1.e as N/A. CUE: None                                    __________
SAT  UNSAT   
: 7. PERFORMANCE STEP: Adjust the MDT20 output to maintain zero amps indicated on the XFER METER Y1
-806.
STANDARD: Maintain zero amps indicated on the XFER METER Y1
-806 by occasional                                      adjustment as needed of the MDT20 output.
COMMENT: Student may consider step 3.17.1.f in progress while continuing MFP startup and not sign as complete.
CUE: None                                    __________
SAT  UNSAT  8. PERFORMANCE STEP: Complete section 3.17 of DB
-OP-06224. STANDARD:
Sign and date complete by for section 3.17 of DB
-OP-06224.              COMMENT: If student considers step 3.17.1.f to be in progress while continuing MFP startup then section 3.17 will not be signed as complete.
CUE: None                                    __________
SAT  UNSAT    9. PERFORMANCE STEP: Sign complete step 3.16.44 of DB-OP-06224. STANDARD:
Sign complete step 3.16.44 of DB-OP-06224.
COMMENT: If student considers step 3.17.1.f to be in progress while continuing MFP startup and section 3.17 is not signed as complete then step 3.16.44 may                                  remain in progress.
Step 3.16.45 would be performed after the MFP is supplying feedwater to the steam generators.
CUE: None
__________
SAT  UNSAT    10.      PERFORMANCE STEP: Sign compete step 3.25 of DB
-OP-06901, Plant Startup.
STANDARD:
Sign compete step 3.2.5 of DB
-OP-06901, Plant Startup.
COMMENT: Student may continue with step 3.2.5 circled (in progress) because  
 
section of DB
-OP-06224 is not complete until there is flow to the steam  
 
generators and the ARTS Channels test/toggle switches are placed in the operate position at step 3.16.45. CUE: None                                      __________
SAT  UNSAT  11. PERFORMANCE STEP:
Raise Main Feed Pump Speed until discharge pressure is  
             ........C........                      between 1000 and 1050 psig (step 3.26.1 of DB
-OP-06901). STANDARD:
Raise MFPT 2 speed using manual control of HIC ICS 36A Hand/Auto Station, ICS Bailey Controller, to raise discharge pressure to band of 1000-1050 psig.
NOTE: Alternate Path begins with low oil pressure Annunciator 10-1-D received as discharge pressure is raised (triggered to alarm at approximately 950psig).
CUE: None
__________
SAT  UNSAT  12.      PERFORMANCE STEP: Identify Annunciator 10-1-D, MFPT 2 LUBE OIL PRESS LO, in alarm. STANDARD:
Recognize annunciator 10-1-D, MFPT 2 LUBE OIL PRESS LO, in alarm and refer to alarm procedure DB
-OP-2010. CUE: If student refers to alarm procedure provide copy of DB-OP-02010 pages 10 and 11 for Annunciator 10-1-D
__________
SAT  UNSAT  13.      PERFORMANCE STEP: Determine if bearing pressure is actually Low
. STANDARD:
Determine bearing pressure is actually Low (<7 psig) using PI12 56,                                      Header Control Pressure.
CUE: None          
 
__________
SAT  UNSAT   
: 14.      PERFORMANCE STEP: Verify automatic start of standby MFPT 2 Main Oil Pump.
            ........C........
 
COMMENT:  The standby MFPT 2 Main Oil Pump will not auto start. The pump will start manually and almost immediately trip on electrical fault.
STANDARD:
Identify standby MFPT 2 Main Oil Pump is not running and start                                      standby MFPT 2 Main Oil Pump.
 
CUE: None          
 
__________
SAT  UNSAT    15.      PERFORMANCE STEP: If Bearing Header Pressure decreases to less than 4 psig THEN  
             ........C........
start the Emergency Bearing Oil Pump and trip MFPT 2.
STANDARD:
Identify Bearing Header Pressure decreases to less than 4 psig using                                    PI1256. Start the Emergency Bearing Oil Pump (HIS1188). CUE: None          
 
__________
SAT  UNSAT    16.      PERFORMANCE STEP: If Bearing Header Pressure decreases to less than 4 psig THEN  
             ........C........                      start the Emergency Bearing Oil Pump and trip MFPT 2.
STANDARD:
Trip MFPT 2 using HS 798 trip push button.
CUE: None          
 
__________
SAT  UNSAT      TERMINATING CUES:
This JPM is complete. (Terminated by the examiner)      __________
END TIME   


Simulator JPM S5 Facility:             Davis-Besse    Task No:  334-018-04-0300    Task Title:      Establish Containment Closure       K/A  
Simulator JPM S5 Facility:
Davis-Besse    Task No:  334-018-04-0300    Task Title
:      Establish Containment Closure K/A  


==Reference:==
==Reference:==
       (103) A3.01 3.9/4.2        Job Performance Measure No:  S5 (JPM 219)    Examinee:           NRC Examiner:        Date:      Method of testing: Simulated Performance ___  Actual Performance _X_  Classroom ___  Simulator _X_  Plant ___ Read to the examinee: I will explain the initial conditions, which steps to simulate or discuss, and provide initiating cues. When you complete the task successfully, the objective for this job performance measure will be satisfied. Initial Conditions: The plant conditions are specified in the Initial Conditions and Initiating Cues.
       (103) A3.01 3.9/4.2        Job Performance Measure No:  S5 (JPM 219)    Examinee:
Task Standard: Establish Containment Closure  Required Materials: DB-OP-06904, Shutdown Operations, Section 11 General  
NRC Examiner:        Date:      Method of testing:
Simulated Performance ___  Actual Performance _X_  Classroom ___  Simulator _X_  Plant ___
Read to the examinee:
I will explain the initial conditions, which steps to simulate or discuss, and provide initiating cues. When you complete the task successfully, the objective for this job performance measure will be satisfied.
Initial Conditions:
The plant conditions are specified in the Initial Conditions and Initiating Cues.
 
Task Standard:
Establish Containment Closure  Required Materials:
DB-OP-06904, Shutdown Operations, Section 11  
 
General  


==References:==
==References:==
Db-OP-02000 Initiating Cue: The plant conditions are specified in the Initial Conditions and Initiating Cues. Time Critical Task: No Alternate Path: No  Validation Time:  8 minutes SIMULATOR INSTRUCTIONS TASK DESCRIPTION: Establish Containment closure INITIAL CONDITION: Initialize to special IC 116 OR MODE 5 IC with DH Loop 2 operating and CTMT Purge in operation on CTMT ADDITIONAL SETUP/DEVIATION FROM INITIAL CONDITION: Manually de-energize A and B buses to simulate a loss of offsite power followed by restoration of offsite power. Emergency Shutdown #1 EDG irf g529g Energize D2 Bus from D1 Bus to restore Instrument Air   MALFUNCTIONS/FAILURE TO INSERT:  DH Pump #2 breaker fail open imf bdp2c CTMT Purge Valves CV5005 and CV5008 fail open imf cav9c imf cavfc ACTION/CUES:   7. ROLE PLAY as Field Supervisor or other OPS WSC to report that all LLRTs are terminated and isolated.    
 
: 8. ROLE PLAY as Field Supervisor or other OPS WSC to report that all personnel       assigned specific Containment Closure responsibilities are carrying out the required                 actions.
Db-OP-02000 Initiating Cue:
EXAMINER COPY INITIAL CONDITIONS: The plant was in MODE 5 with Decay Heat Loop 2 operating when a loss of offsite power occurred.
The plant conditions are specified in the Initial Conditions and Initiating Cues.
EDG #1 tripped and efforts to restart it have been unsuccessful.
Time Critical Task:
EDG #2 is providing power to D1 and D2 Buses. Decay Heat Pump 2 breaker would not re-close after D1 power was restored. Maintenance is investigating. INITIATING CUES: The Shift Manager directs you to establish Containment Closure in accordance with step 11.1.5 of DB-OP-06904 Shutdown Operations (required by DB-OP-02527, Loss of Decay Heat Removal).    (Provide section 11 of DB-OP-06904)
No Alternate Path:
CANDIDATE COPY INITIAL CONDITIONS: The plant was in MODE 5 with Decay Heat Loop 2 operating when a loss of offsite power occurred.
No  Validation Time:  8 minutes
EDG #1 tripped and efforts to restart it have been unsuccessful.
 
SIMULATOR INSTRUCTIONS TASK DESCRIPTION: Establish Containment closure INITIAL CONDITION: Initialize to special IC 116 OR MODE 5 IC with DH Loop 2 operating and CTMT Purge in operation on CTMT ADDITIONAL SETUP/DEVIATION FROM INITIAL CONDITION: Manually de
-energize A and B buses to simulate a loss of offsite power followed by restoration of offsite power.
Emergency Shutdown #1 EDG
 
irf g529g Energize D2 Bus from D1 Bus to restore Instrument Air MALFUNCTIONS/FAILURE TO INSERT:  DH Pump #2 breaker fail open
 
imf bdp2c
 
CTMT Purge Valves CV5005 and CV5008 fail open
 
imf cav9c imf cavfc ACTION/CUES:
: 7. ROLE PLAY as Field Supervisor or other OPS WSC to report that all LLRTs are terminated and isolated.  
: 8. ROLE PLAY as Field Supervisor or other OPS WSC to report that all personnel assigned specific Containment Closure responsibilities are carrying out the required actions.  
 
EXAMINER COPY INITIAL CONDITIONS: The plant was in MODE 5 with Decay Heat Loop 2 operating when a loss of offsite power occurred.
 
EDG #1 tripped and efforts to restart it have been unsuccessful.   
 
EDG #2 is providing power to D1 and D2 Buses.
EDG #2 is providing power to D1 and D2 Buses.
Decay Heat Pump 2 breaker would not re-close after D1 power was restored. Maintenance is investigating. INITIATING CUES: The Shift Manager directs you to establish Containment Closure in accordance with step 11.1.5 of DB-OP-06904 Shutdown Operations (required by DB-OP-02527, Loss of Decay Heat Removal).
Decay Heat Pump 2 breaker would not re
PERFORMANCE INFORMATION NOTE: Critical steps denoted with a "C". Failure to meet any one of these standards for this item constitutes failure. Sequence is NOT critical unless denoted in the "Comments". START TIME:  _______ 1. PERFORMANCE STEP: Locate the correct procedure step.
-close after D1 power was restored. Maintenance is investigating.
STANDARD: Finds step 11.1.5. CUE: None           ___________           SAT  UNSAT  2.        PERFORMANCE STEP:      Announce Containment Closure over the     Gaitronics.
INITIATING CUES: The Shift Manager directs you to establish Containment Closure in accordance with step 11.1.5 of DB-OP-06904 Shutdown Operations (required by DB
STANDARD: Use Gaitronics to announce the following:
-OP-02527, Loss of Decay Heat Removal).
                     "Attention all station personnel, attention all station personnel. All assigned                               personnel establish containment closure immediately. All assigned personnel                       establish containment closure immediately."             CUE: None      ___________           SAT  UNSAT   
    (Provide section 11 of DB
: 3. PERFORMANCE STEP: Verify Containment Purge is shut down.
-OP-06904)
STANDARD: Visual check of Containment Purge supply and Exhaust Fan control switch                                    indications indicate fans are shutdown.
CANDIDATE COPY INITIAL CONDITIONS: The plant was in MODE 5 with Decay Heat Loop 2 operating when a loss of offsite power occurred. 
COMMENT: If system procedure for shutdown is referenced the Containment                                   Purge containment isolation valves will be directed to be closed.                                  Performance steps 5 and 7 would be used to evaluate. CUE: None        ___________           SAT  UNSAT       
 
: 4.      PERFORMANCE STEP: Perform selected isolation of SFAS Containment Penetrations   STANDARD: Refers to DB-OP-02000 Table 2, SFAS Actuated Equipment, and                        isolate containment penetrations able to be positioned from control                       room to establish containment closure. CUE: Shift Manager directs you to refer to DB-OP-02000 Table                         2, SFAS Actuated Equipment, and isolate Level 1 and Level 2                         containment penetrations able to be positioned from control room.                                             (Provide clean copy of table 2)                                                                         ___________           SAT  UNSAT  5. PERFORMANCE STEP: Close Channel 1 SFAS Level 1 Containment Purge ........C........                      Isolation Valves   STANDARD: Press CLOSE on the following switches:   CV 5008 CTMT PURGE OUT   CV 5006 CTMT PURGE IN   COMMENT: CV 5008 will NOT close due to failure. Critical to close CV 5007 CTMT PURGE OUT Channel 2 in Performance Step 7 to isolate this penetration. Critical to close CV 5006 to isolate this penetration due to failure of CV 5005   CUE: None        ___________           SAT  UNSAT  6. PERFORMANCE STEP: Close Channel 2 SFAS Level 1 Containment  ........C........                      Air Sample Isolation Valves STANDARD: Press CLOSE on the following switches:
EDG #1 tripped and efforts to restart it have been unsuccessful. 
CV 5010A CTMT AIR SAMPLE                             CV 5010B CTMT AIR SAMPLE                             CV 5010C CTMT AIR SAMPLE                                CV 5010D CTMT AIR SAMPLE                             CV 5010E CTMT AIR SAMPLE RET   COMMENT: CV5010E is not critical because of check valve CV125. CUE: None        _________       SAT  UNSAT       
 
: 7. PERFORMANCE STEP: Close Channel 2 SFAS Level 1 Containment Purge  ........C........ Isolation Valves   STANDARD: Press CLOSE on the following switches:
EDG #2 is providing power to D1 and D2 Buses. 
CV 5007 CTMT PURGE OUT   CV 5005 CTMT PURGE IN   COMMENT: Critical to close CV 5007 CTMT PURGE OUT to isolate this penetration due to CV 5008 failure. CV 5005 will NOT close due to failure. Critical to close CV 5006 CTMT PURGE OUT Channel 1 in Step 5 to isolate this penetration.
 
CUE: None             ___________           SAT  UNSAT   
Decay Heat Pump 2 breaker would not re
: 8. PERFORMANCE STEP: Close Channel 2 SFAS Level 2 Containment   Vacuum Relief Valve Isolation Valves   STANDARD: Press CLOSE on the following switches:   CV 5075 CTMT VAC RLF VLV ISO   CV 5076 CTMT VAC RLF VLV ISO   CV 5077 CTMT VAC RLF VLV ISO   CV 5078 CTMT VAC RLF VLV ISO   CV 5079 CTMT VAC RLF VLV ISO   COMMENT: Not critical due to check valves isolating penetration. CUE:  None           ___________           SAT  UNSAT   
-close after D1 power was restored. Maintenance is investigating.
: 9. PERFORMANCE STEP: Verify that all LLRTs are terminated and isolated.
INITIATING CUES: The Shift Manager directs you to establish Containment Closure in accordance with step 11.1.5 of DB-OP-06904 Shutdown Operations (required by DB
-OP-02527, Loss of Decay Heat Removal).
PERFORMANCE INFORMATION NOTE: Critical steps denoted with a "C". Failure to meet any one of these standards for this item constitutes failure. Sequence is NOT critical unless denoted in the "Comments".
START TIME:  _______
: 1. PERFORMANCE STEP:
Locate the correct procedure step.
 
STANDARD:
Finds step 11.1.5.
CUE: None
___________
SAT  UNSAT  2.        PERFORMANCE STEP:      Announce Containment Closure over the Gaitronics.
 
STANDARD: Use Gaitronics to announce the following:
 
                     "Attention all station personnel, attention all station personnel. All assigned personnel establish containment closure immediately. All assigned personnel establish containment closure immediately."
CUE: None      ___________
SAT  UNSAT   
: 3. PERFORMANCE STEP:
Verify Containment Purge is shut down.  
 
STANDARD:
Visual check of Containment Purge supply and Exhaust Fan control switch                                    indications indicate fans are shutdown
.
COMMENT: If system procedure for shutdown is referenced the Containment Purge containment isolation valves will be directed to be closed.                                  Performance steps 5 and 7 would be used to evaluate.
CUE: None        ___________
SAT  UNSAT       
: 4.      PERFORMANCE STEP: Perform selected isolation of SFAS Containment  
 
Penetrations STANDARD:
Refers to DB
-OP-02000 Table 2, SFAS Actuated Equipment, and                        isolate containment penetrations able to be positioned from control room to establish containment closure. CUE: Shift Manager directs you to refer to DB
-OP-02000 Table 2, SFAS Actuated Equipment, and isolate Level 1 and Level 2 containment penetrations able to be positioned from control room.                    
                      (Provide clean copy of table 2)
___________
SAT  UNSAT  5. PERFORMANCE STEP:
Close Channel 1 SFAS Level 1 Containment Purge ........C........                      Isolation Valves STANDARD:
Press CLOSE on the following switches:
CV 5008 CTMT PURGE OUT CV 5006 CTMT PURGE IN COMMENT: CV 5008 will NOT close due to failure. Critical to close CV 5007 CTMT PURGE OUT Channel 2 in Performance Step 7 to isolate this penetration.
Critical to close CV 5006 to isolate this penetration due to failure of CV 5005 CUE: None        ___________
SAT  UNSAT  6. PERFORMANCE STEP:
Close Channel 2 SFAS Level 1 Containment  
  ........C........                      Air Sample Isolation Valves  
 
STANDARD: Press CLOSE on the following switches:
 
CV 5010A CTMT AIR SAMPLE CV 5010B CTMT AIR SAMPLE CV 5010C CTMT AIR SAMPLE                                CV 5010D CTMT AIR SAMPLE CV 5010E CTMT AIR SAMPLE RET COMMENT: CV5010E is not critical because of check valve CV125.
CUE: None        _________
SAT  UNSAT       
: 7. PERFORMANCE STEP:
Close Channel 2 SFAS Level 1 Containment Purge  ........C........
Isolation Valves STANDARD:
Press CLOSE on the following switches:
 
CV 5007 CTMT PURGE OUT CV 5005 CTMT PURGE IN COMMENT: Critical to close CV 5007 CTMT PURGE OUT to isolate this penetration due to CV 5008 failure.
CV 5005 will NOT close due to failure. Critical to close CV 5006 CTMT PURGE OUT Channel 1 in Step 5 to isolate this penetration.
 
CUE: None
___________
SAT  UNSAT   
: 8. PERFORMANCE STEP:
Close Channel 2 SFAS Level 2 Containment Vacuum Relief Valve Isolation Valves STANDARD:
Press CLOSE on the following switches:
CV 5075 CTMT VAC RLF VLV ISO CV 5076 CTMT VAC RLF VLV ISO CV 5077 CTMT VAC RLF VLV ISO CV 5078 CTMT VAC RLF VLV ISO CV 5079 CTMT VAC RLF VLV ISO COMMENT: Not critical due to check valves isolating penetration.
CUE:  None
___________
SAT  UNSAT   
: 9. PERFORMANCE STEP:
Verify that all LLRTs are terminated and isolated.
 
STANDARD:
Communication with Field Supervisor. 
 
CUE:  (If asked) The Field Supervisor is verifying that all LLRTs are isolated.
___________
SAT  UNSAT 
: 10. PERFORMANCE STEP:
Verify that the personnel assigned specific Containment                                                      Closure responsibilities are carrying out the required actions.
 
STANDARD: Communication with Field Supervisor.
STANDARD: Communication with Field Supervisor.
CUE:  (If asked) The Field Supervisor is verifying that all LLRTs are isolated.              ___________          SAT  UNSAT 
CUE:  (If asked) The Field Supervisor is verifying that the personnel assigned              . specific Containment Closure responsibilities are carrying out the required  
: 10. PERFORMANCE STEP: Verify that the personnel assigned specific Containment                                                      Closure responsibilities are carrying out the required actions.
 
STANDARD: Communication with Field Supervisor.            CUE:  (If asked) The Field Supervisor is verifying that the personnel assigned              . specific Containment Closure responsibilities are carrying out the required actions.          ___________           SAT  UNSAT    TERMINATING CUES:  This JPM is complete. (Terminated by the examinee).        __________           END TIME Simulator JPM S6 Facility: Davis-Besse    Task No:    063-007-04-0100    Task Title: Battery Load Shed Actions from the Control Room  K/A  
actions.          ___________
SAT  UNSAT    TERMINATING CUES:  This JPM is complete.
(Terminated by the examine e).        __________
END TIME Simulator JPM S6 Facility:
Davis-Besse    Task No:    063-007-04-0100    Task Title
: Battery Load Shed Actions from the Control Room  K/A  


==Reference:==
==Reference:==
  (063) K1.03 (2.9/3.5)_________ Job Performance Measure No:  S6 (JPM New)  Examinee:           NRC Examiner:        Date:      Method of testing: Simulated Performance _ __  Actual Performance __X__  Classroom ___  Simulator _X_    Plant ___ Read to the examinee: I will explain the initial conditions, which steps to simulate or discuss, and provide initiating cues. When you complete the task successfully, the objective for this job performance measure will be satisfied. Initial Conditions:  The plant conditions are specified in the Initial Conditions and Initiating Cues.
 
Task Standard: Perform control room actions for section 1 of attachment 5, Selective Battery Load Shedding, per DB-OP-02521, Loss of AC Bus Power Sources. Required Materials: Copy of attachment 5, Selective Battery Load Shedding, of DB-OP-02521, Loss of AC Bus Power Sources  General  
  (063) K1.03 (2.9/3.5)
_________
Job Performance Measure No
:  S6 (JPM New)  Examinee:
NRC Examiner:        Date:      Method of testing:
Simulated Performance _
__  Actual Performance __X__  Classroom ___  Simulator _X_    Plant ___
Read to the examinee:
I will explain the initial conditions, which steps to simulate or discuss, and provide initiating cues.
When you complete the task successfully, the objective for this job performance measure  
 
will be satisfied.
Initial Conditions:  The plant conditions are specified in the Initial Conditions and Initiating Cues.
 
Task Standard:
Perform control room actions for section 1 of attachment 5, Selective Battery Load Shedding, per DB-OP-02521, Loss of AC Bus Power Sources. Required Materials:
Copy of attachment 5, Selective Battery Load Shedding, of DB-OP-02521, Loss of AC Bus Power Sources  General  


==References:==
==References:==
None Initiating Cue: The plant conditions are specified in the Initial Conditions and Initiating Cues.
 
Time Critical Task: Yes Alternate Path: No Validation Time: 8 minutes       SIMULATOR INSTRUCTIONS TASK DESCRIPTION: Perform section 1 of Selective Battery Load Shedding per DB-OP-02521, Loss of AC Bus Power Sources  INITIAL CONDITION: Mode 3 with Loss of Both Essential 4160 AC Bus Power Sources   ADDITIONAL SETUP/DEVIATION FROM INITIAL CONDITION:
None Initiating Cue:
The plant conditions are specified in the Initial Conditions and Initiating Cues.
 
Time Critical Task:
Yes Alternate Path:
No Validation Time:
8 minutes SIMULATOR INSTRUCTIONS
 
TASK DESCRIPTION: Perform section 1 of Selective Battery Load Shedding per DB-OP-02521, Loss of AC Bus Power Sources  INITIAL CONDITION: Mode 3 with Loss of Both Essential 4160 AC Bus Power Sources ADDITIONAL SETUP/DEVIATION FROM INITIAL CONDITION:
MALFUNCTIONS/FAILURE TO INSERT:   
MALFUNCTIONS/FAILURE TO INSERT:   


ACTION/CUES:   
ACTION/CUES:   


STUDENT COPY INITIAL CONDITIONS: Mode 3 with Loss of Both Essential 4160 AC Bus Power Sources INITIATING CUES: The plant has tripped due to a Loss of Off-Site Power. Maintenance is in progress on EDG 1 and EDG 2 locked out upon startup. Efforts to start the SBODG have been unsuccessful. Both C1 and D1 remain deenergized, and have been for 15 minutes. The Unit Supervisor directs you to perform section 1 of Attachment 5, Selective Battery Load Shedding, from DB-OP-02521, Loss of AC Bus Power Sources. An operator has been just been dispatched to perform attachment 14 per step 2 of attachment 5.
STUDENT COPY INITIAL CONDITIONS: Mode 3 with Loss of Both Essential 4160 AC Bus Power Sources INITIATING CUES: The plant has tripped due to a Loss of Off
-Site Power. Maintenance is in progress on EDG 1 and EDG 2 locked out upon startup. Efforts to start the SBODG have been unsuccessful. Both C1 and D1 remain deenergized, and have been for 15 minutes. The Unit Supervisor directs you to perform section 1 of Attachment 5, Selective Battery Load Shedding, from DB
-OP-02521, Loss of AC Bus Power Sources. An operator has been just been dispatched to perform attachment 14 per step 2 of attachment 5.
 
This is a time critical task. I will inform you when the time critical clock starts.       
This is a time critical task. I will inform you when the time critical clock starts.       


EXAMINER COPY INITIAL CONDITIONS: Mode 3 with Loss of Both Essential 4160 AC Bus Power Sources INITIATING CUES: The plant has tripped due to a Loss of Off-Site Power. Maintenance is in progress on EDG 1 and EDG 2 locked out upon startup. Efforts to start the SBODG have been unsuccessful. Both C1 and D1 remain deenergized, and have been for 15 minutes. The Unit Supervisor directs you to perform section 1 of Attachment 5, Selective Battery Load Shedding, from DB-OP-02521, Loss of AC Bus Power Sources. An operator has been just been dispatched to perform attachment 14 per step 2 of attachment 5.
EXAMINER COPY INITIAL CONDITIONS: Mode 3 with Loss of Both Essential 4160 AC Bus Power Sources INITIATING CUES: The plant has tripped due to a Loss of Off
-Site Power. Maintenance is in progress on EDG 1 and EDG 2 locked out upon startup. Efforts to start the SBODG have been unsuccessful. Both C1 and D1 remain deenergized, and have been for 15 minutes.
The Unit Supervisor directs you to perform section 1 of Attachment 5, Selective Battery Load Shedding, from DB
-OP-02521, Loss of AC Bus Power Sources.
An operator has been just been dispatched to perform attachment 14 per step 2 of attachment 5.
 
This is a time critical task. I will inform you when the time critical clock starts.  (Provide examinee a copy of DB-OP-02521, Loss of AC Bus Power Sources, Attachment 5, Selective Battery Load Shedding)   
This is a time critical task. I will inform you when the time critical clock starts.  (Provide examinee a copy of DB-OP-02521, Loss of AC Bus Power Sources, Attachment 5, Selective Battery Load Shedding)   


PERFORMANCE INFORMATION NOTE: Critical steps denoted with a "C". Failure to meet any one of these standards for this item constitutes failure. Sequence is NOT assumed unless denoted in the "Comments". START TIME:   Time Critical Clock is started when they assume control of the Job Performance Measure. CUE: 15 minutes has elapsed since the loss of power to C1 and D1 Busses. Time Critical Clock starts now. TIME CRITICAL CLOCK START TIME:     1. PERFORMANCE STEP: Perform step 1.a to STOP and LOCKOUT          .......C........                       the following pumps   STANDARD: Stop and lockout Main Feed Pump 1 EBOP (HIS 1209, EMER BEARING                                   OIL PUMP)      CUE: None      __________       SAT  UNSAT  2. PERFORMANCE STEP: Perform applicable step of section 1.a to STOP and LOCKOUT              .......C........                       the following pumps   STANDARD: Stop and lockout Main Feed Pump 2 EBOP (HIS 1188, EMER BEARING                                   OIL PUMP)   CUE:    None      __________       SAT  UNSAT   
PERFORMANCE INFORMATION
: 3. PERFORMANCE STEP: Perform applicable step of section 1.a to STOP and LOCKOUT            .......C........                      the following pumps               STANDARD: Stop and Lockout Makeup Pump 1 DC Oil Pump (HIS-MU24A2). CUE: None      __________       SAT  UNSAT    4. PERFORMANCE STEP: Perform applicable step of section 1.a to STOP and LOCKOUT              .......C........                      the following pumps   STANDARD: Stop and lockout Makeup Pump 2 DC Oil Pump (HIS-MU24B2). CUE: None                                      __________       SAT  UNSAT  5. PERFORMANCE STEP: Perform applicable step of section 1.a to STOP and LOCKOUT              .......C........                      the following pumps               STANDARD: Stop and lockout RCP 1-1 DC Oil Lift Pump (HIS 4115).
 
CUE: None                                    __________       SAT  UNSAT  6. PERFORMANCE STEP: Perform applicable step of section 1.a to STOP and LOCKOUT              ........C........                             the following pumps   STANDARD: Stop and lockout RCP 1-2 DC Oil Lift Pump (HIS 4215). CUE: None                                    __________       SAT  UNSAT  7. PERFORMANCE STEP: Perform applicable step of section 1.a to STOP and LOCKOUT              ........C........                 the following pumps   STANDARD: Stop and lockout RCP 2-1 DC Oil Lift Pump (HIS 4315)   CUE: None                                    __________       SAT  UNSAT  8. PERFORMANCE STEP: Perform applicable step of section 1.a to STOP and LOCKOUT            ........C........                       the following pumps               STANDARD: Stop and lockout RCP 2-2 DC Oil Lift Pump (HIS 4415)   CUE: None                                    __________       SAT  UNSAT  Time Performance Steps 1-8 are complete TIME CRITICAL CLOCK END TIME:   Time requirement is 15 minutes or less from start of TIME CRITICAL CLOCK Start Time                                                                                                                                                                                                                                           __________                                                     SAT  UNSAT   9. PERFORMANCE STEP: Dispatch an Operator to perform Attachment 14, Severe                                                   Battery Load Shed - In Plant Actions. STANDARD: Initial Conditions stated an operator has been dispatched to perform                                     attachment 14. CUE: If needed: The Unit Supervisor has assigned an operator to perform Attachment 14,             Severe Battery Load Shed - In Plant Actions          __________       SAT  UNSAT  10.      PERFORMANCE STEP: Establish Manual Control of Auxiliary Feedwater -  Place ........C........                      AF6452, AFW 1 LEVEL CONTROL VALVE, in MANUAL   STANDARD: Depress manual on level controller LIC6452, AFP 1 Level Controller COMMENT: Manual control of Auxiliary Feedwater can be established for both trains                                  in either order or in parallel as steps are bulleted. Intent of this JPM is to                                 establish manual control for train 1.              CUE: None                                      __________       SAT  UNSAT  11. PERFORMANCE STEP: Establish Manual Control of Auxiliary Feedwater - Slowly            ........C........                       open AFW 1 LEVEL CONTROL VALVE in MANUAL while                                                           reducing AFPT 1 speed using the AFPT 1 GOVERNOR                                                     CONTROL until AF6452 is full open.     STANDARD: Depress open on LIC6452, AFP 1 Level Controller, to slowly open AF6452,                                     AFP Level Control Valve, while maintaining OTSG 1 level (49" setpoint) by                                    reducing speed on AFPT 1 speed using HIS520A, AFPT 1 GOVERNOR                                   CONTROL, until AF6452 is full open. CUE: None                                               __________       SAT  UNSAT  12.      PERFORMANCE STEP: Establish Manual Control of Auxiliary Feedwater -  Maintain SG .......C........                      1 at required level by adjusting AFPT 1 GOVERNOR                                                     CONTROL as necessary. STANDARD: Adjust AFP 1 speed as necessary to maintain desired level (49" setpoint)                                     using HIS520A, AFPT 1 GOVERNOR CONTROL. CUE: None                                     __________      SAT  UNSAT  TERMINATING CUES:  This JPM is complete. (Terminated by the examiner once level control is established)      __________      END TIME   
NOTE: Critical steps denoted with a "C". Failure to meet any one of these standards for this item constitutes failure. Sequence is NOT assumed unless denoted in the "Comments".
START TIME:
Time Critical Clock is started when they assume control of the Job Performance Measure.
CUE: 15 minutes has elapsed since the lo ss of power to C1 and D1 Busses.
Time Critical Clock starts now.
TIME CRITICAL CLOCK START TIME:
: 1. PERFORMANCE STEP: Perform step 1.a to STOP and LOCKOUT          .......C........
the following pumps STANDARD:
Stop and lockout Main Feed Pump 1 EBOP (HIS 1209, EMER BEARING OIL PUMP)      CUE: None      __________
SAT  UNSAT  2. PERFORMANCE STEP: Perform applicable step of section 1.a to STOP and LOCKOUT              .......C........
the following pumps STANDARD:
Stop and lockout Main Feed Pump 2 EBOP (HIS 1188, EMER BEARING OIL PUMP)
CUE:    None      __________
SAT  UNSAT   
: 3. PERFORMANCE STEP:
Perform applicable step of section 1.a to STOP and LOCKOUT  
             .......C........                      the following pumps
 
STANDARD:
Stop and Lockout Makeup Pump 1 DC Oil Pump (HIS
-MU24A2). CUE: None      __________
SAT  UNSAT    4. PERFORMANCE STEP: Perform applicable step of section 1.a to STOP and LOCKOUT  
             .......C........                      the following pumps STANDARD:
Stop and lockout Makeup Pump 2 DC Oil Pump (HIS
-MU24B2). CUE: None                                      __________
SAT  UNSAT  5. PERFORMANCE STEP: Perform applicable step of section 1.a to STOP and LOCKOUT  
             .......C........                      the following pumps STANDARD:
Stop and lockout RCP 1-1 DC Oil Lift Pump (HIS 4115).
 
CUE: None                                    __________
SAT  UNSAT  6. PERFORMANCE STEP: Perform applicable step of section 1.a to STOP and LOCKOUT  
             ........C........
the following pumps STANDARD:
Stop and lockout RCP 1-2 DC Oil Lift Pump (HIS 4215).
CUE: None                                    __________
SAT  UNSAT  7. PERFORMANCE STEP: Perform applicable step of section 1.a to STOP and LOCKOUT  
             ........C........
the following pumps STANDARD:
Stop and lockout RCP 2-1 DC Oil Lift Pump (HIS 4315)
CUE: None                                    __________
SAT  UNSAT  8. PERFORMANCE STEP: Perform applicable step of section 1.a to STOP and LOCKOUT  
             ........C........
the following pumps
 
STANDARD:
Stop and lockout RCP 2-2 DC Oil Lift Pump (HIS 4415)
CUE: None                                    __________
SAT  UNSAT  Time Performance Steps 1
-8 are complete TIME CRITICAL CLOCK END TIME:
Time requirement is 15 minutes or less from start of TIME CRITICAL CLOCK Start Time        
 
__________
SAT  UNSAT
: 9. PERFORMANCE STEP: Dispatch an Operator to perform Attachment 14, Severe Battery Load Shed - In Plant Actions.
STANDARD:
Initial Conditions stated an operator has been dispatched to perform attachment 14.
CUE: If needed
: The Unit Supervisor has assigned an operator to perform Attachment 14, Severe Battery Load Shed - In Plant Actions          __________
SAT  UNSAT  10.      PERFORMANCE STEP: Establish Manual Control of Auxiliary Feedwater  
-  Place ........C........                      AF6452, AFW 1 LEVEL CONTROL VALVE, in MANUAL STANDARD:
Depress manual on level controller LIC6452, AFP 1 Level Controller
 
COMMENT: Manual control of Auxiliary Feedwater can be established for both trains                                  in either order or in parallel as steps are bulleted. Intent of this JPM is to establish manual control for train 1.              CUE: None                                      __________
SAT  UNSAT  11. PERFORMANCE STEP:
Establish Manual Control of Auxiliary Feedwater  
- Slowly            ........C........
open AFW 1 LEVEL CONTROL VALVE in MANUAL while      
 
reducing AFPT 1 speed using the AFPT 1 GOVERNOR CONTROL until AF6452 is full open.
STANDARD:
Depress open on LIC6452, AFP 1 Level Controller, to slowly open AF6452, AFP Level Control Valve, while maintaining OTSG 1 level (49" setpoint) by                                    reducing speed on AFPT 1 speed using HIS520A, AFPT 1 GOVERNOR CONTROL, until AF6452 is full open
. CUE: None
__________
SAT  UNSAT  12.      PERFORMANCE STEP: Establish Manual Control of Auxiliary Feedwater  
-  Maintain SG .......C........                      1 at required level by adjusting AFPT 1 GOVERNOR  
 
CONTROL as necessary.
STANDARD:
Adjust AFP 1 speed as necessary to maintain desired level (49" setpoint) using HIS520A, AFPT 1 GOVERNOR CONTROL.
CUE: None          


Simulator JPM S7 Facility:             Davis-Besse    Task No:      012-003-01-0100    Task Title:      Deenergize/Reenergize Source Range NIs    K/A  
__________
SAT  UNSAT  TERMINATING CUES:
This JPM is complete. (Terminated by the examiner once level control is established)      __________
END TIME   
 
Simulator JPM S7 Facility:
Davis-Besse    Task No:      012-003-01-0100    Task Title
:      Deenergize/Reenergize Source Range NIs    K/A  


==Reference:==
==Reference:==
       (012) A4.02 3.3/3.4        Job Performance Measure No:    S7 (JPM 185)    Examinee:           NRC Examiner:        Date:      Method of testing: Simulated Performance ___  Actual Performance _X_  Classroom ___  Simulator _X_  Plant ___
       (012) A4.02 3.3/3.4        Job Performance Measure No
Read to the examinee: I will explain the initial conditions, which steps to simulate or discuss, and provide initiating cues.
:    S7 (JPM 185)    Examinee:
When you complete the task successfully, the objective for this job performance measure will be satisfied. Initial Conditions: The plant conditions are specified in the Initial Conditions and Initiating Cues. Task Standard: Deenergize Source Range NIs Reenergize Source Range NIs Required Materials: DB-OP-06403, Reactor Protection System (RPS) and Nuclear Instrumentation System (NI) Operating Procedure, section 4.4 General  
NRC Examiner:        Date:      Method of testing:
Simulated Performance ___  Actual Performance _X_  Classroom ___  Simulator _X_  Plant ___
 
Read to the examinee:
I will explain the initial conditions, which steps to simulate or discuss, and provide initiating cues.
When you complete the task successfully, the objective for this job performance measure will be satisfied.
Initial Conditions:
The plant conditions are specified in the Initial Conditions and Initiating Cues.
Task Standard: Deenergize Source Range NIs Reenergize Source Range NIs  
 
Required Materials:
DB-OP-06403, Reactor Protection System (RPS) and Nuclear Instrumentation System (NI) Operating Procedure, section 4.4
 
General  


==References:==
==References:==
None  Initiating Cue: The plant conditions are specified in the Initial Conditions and Initiating Cues.
Time Critical Task:  No    Alternate Path: No Validation Time:  6 minutes SIMULATOR INSTRUCTIONS  TASK DESCRIPTION: Deenergize/Reeneregize Source Range NIs  INITIAL CONDITION: Approximately 5% power  ADDITIONAL SETUP/DEVIATION FROM INITIAL CONDITION: None  MALFUNCTIONS/FAILURE TO INSERT: Fail NI 3: IMF R3V3  ACTION/CUES: Delete the NI 3 failure when both Source Range Instruments are deenergized: DMF R3V3 EXAMINER COPY  INITIAL CONDITIONS: A plant startup is in progress  The plant is at approximately 5% power      A failure has caused the Source Range NIs to energize  INITIATING CUES:  The Unit Supervisor directs you to deenergize the Source Range NIs in accordance with section 4.4 of DB-OP-06403, RPS and NI Operating Procedure.  (Hand a copy of section 4.4 of DB-OP-06403 to examinee)
CANDIDATE COPY  INITIAL CONDITIONS: A plant startup is in progress  The plant is at approximately 5% power      A failure has caused the Source Range NIs to energize  INITIATING CUES:  The Unit Supervisor directs you to deenergize the Source Range NIs in accordance with section 4.4 of DB-OP-06403, RPS and NI Operating Procedure. 


PERFORMANCE INFORMATION NOTE: Critical steps denoted with a "C". Failure to meet any one of these standards for this item constitutes failure. Sequence is NOT critical unless denoted in the "Comments". START TIME:  _______   1. PERFORMANCE STEP: Unlock and open RPS Channel 1 and 2 doors.
None  Initiating Cue:
STANDARD: Keys obtained and RPS Channels I and 2 doors unlocked and opened. CUE: (If necessary) The Control Room acknowledges RPS doors will be open and annunciator alarm received       __________       SAT  UNSAT  2. PERFORMANCE STEP:  Place ON-OFF switch for the Source Range Detector Power                     ........C........                      Supply Module in OFF. STANDARD: Place ON-OFF switch for NI 1 power supply to OFF (RPS Channel 2).
The plant conditions are specified in the Initial Conditions and Initiating Cues.
COMMENT: May deenergize NI 2 before NI 1. CUE: None        __________       SAT  UNSAT  3 PERFORMANCE STEP: Place ON-OFF switch for the Source Range Detector Power                     ........C........                      Supply Module in OFF.
 
STANDARD: Place ON-OFF switch for NI 2 power supply to OFF (RPS Channel 1). CUE: (After both SR NIs are deenergized and the NI 3 failure is deleted) The failure has been repaired. The Unit Supervisor directs you to continue in section 4.4 of DB-OP-06403 and reenergize Source Range NIs 1 and 2       __________         SAT  UNSAT  4. PERFORMANCE STEP:  Place ON-OFF switch for the Source Range Detector Power                     ........C........                      Supply Module in ON. STANDARD: Places ON-OFF switch for NI 1 power supply to ON.
Time Critical Task:
COMMENT: May reenergize NI 2 before NI 1   CUE: None      __________       SAT  UNSAT     
No    Alternate Path:
: 5. PERFORMANCE STEP: Place ON-OFF switch for the Source Range Detector Power              
No Validation Time:  6 minutes
        ........C........                      Supply Module in ON. STANDARD: Places ON-OFF switch for NI 2 power supply to ON. CUE: None    __________        SAT  UNSAT  6. PERFORMANCE STEP: Depress the RESET switch on the Source Range Detector Power ........C........                    Supply Module. COMMENT:  Depressing reset switch will reset the trip to allow the detector to reenergize when required. With Intermediate Range NIs above the cutout value the Source Range Detector will not energize. STANDARD: Depress the RESET switch on NI 1 Power Supply Module. CUE: None  __________        SAT  UNSAT  7. PERFORMANCE STEP: Depress the RESET switch on the Source Range Detector Power ........C........                    Supply Module. COMMENT:  Depressing reset switch will reset the trip to allow the detector to                                  reenergize when required. With Intermediate Range NIs above the                                cutout value the Source Range Detector will not energize. STANDARD: Depress the RESET switch on NI 2 Power Supply Module. CUE: None  __________        SAT  UNSAT  8. PERFORMANCE STEP: Complete procedure section. STANDARD: Determine step 4.4.3.c to be not applicable and sign/date completed by. CUE: None  __________        SAT  UNSAT  9. PERFORMANCE STEP: Lock the doors and return keys.
 
STANDARD: Doors locked and key returned. CUE: None  __________        SAT  UNSAT  TERMINATING CUES:  This JPM is complete (Terminated by the examinee)        __________        END TIME 
SIMULATOR INSTRUCTIONS TASK DESCRIPTION
: Deenergize/Reeneregize Source Range NIs INITIAL CONDITION: Approximately 5% power ADDITIONAL SETUP/DEVIATION FROM INITIAL CONDITION: None  MALFUNCTIONS/FAILURE TO INSERT: Fail NI 3: IMF R3V3  ACTION/CUES: Delete the NI 3 failure when both Source Range Instruments are deenergized: DMF R3V3 EXAMINER COPY INITIAL CONDITIONS: A plant startup is in progress The plant is at approximately 5% power A failure has caused the Source Range NIs to energize INITIATING CUES
:  The Unit Supervisor directs you to deenergize the Source Range NIs in accordance with section 4.4 of DB
-OP-06403, RPS and NI Operating Procedure.  (Hand a copy of section 4.4 of DB
-OP-06403 to examinee)
 
CANDIDATE COPY INITIAL CONDITIONS: A plant startup is in progress The plant is at approximately 5% power A failure has caused the Source Range NIs to energize INITIATING CUES
:  The Unit Supervisor directs you to deenergize the Source Range NIs in accordance with section 4.4 of DB
-OP-06403, RPS and NI Operating Procedure. 
 
PERFORMANCE INFORMATION NOTE: Critical steps denoted with a "C". Failure to meet any one of these standards for this item constitutes failure. Sequence is NOT critical unless denoted in the "Comments".
START TIME:  _______
: 1. PERFORMANCE STEP: Unlock and open RPS Channel 1 and 2 doors.
 
STANDARD:
Keys obtained and RPS Channels I and 2 doors unlocked and opened. CUE: (If necessary) The Control Room acknowledges RPS doors will be open and annunciator alarm received
__________
SAT  UNSAT  2. PERFORMANCE STEP:  Place ON-OFF switch for the Source Range Detector Power            
        ........C........                      Supply Module in OFF. STANDARD: Place ON
-OFF switch for NI 1 power supply to OFF (RPS Channel 2).
COMMENT: May deenergize NI 2 before NI 1
. CUE: None        __________
SAT  UNSAT  3 PERFORMANCE STEP: Place ON-OFF switch for the Source Range Detector Power            
        ........C........                      Supply Module in OFF.
STANDARD:
Place ON-OFF switch for NI 2 power supply to OFF (RPS Channel 1). CUE: (After both SR NIs are deenergized and the NI 3 failure is deleted) The failure has been repaired. The Unit Supervisor directs you to continue in section 4.4 of DB-OP-06403 and reenergize Source Range NIs 1 and 2
__________
SAT  UNSAT  4. PERFORMANCE STEP:  Place ON-OFF switch for the Source Range Detector Power            
        ........C........                      Supply Module in ON. STANDARD:
Places ON
-OFF switch for NI 1 power supply to ON.
COMMENT: May reenergize NI 2 before NI 1 CUE: None      __________
SAT  UNSAT     
: 5. PERFORMANCE STEP: Place ON-OFF switch for the Source Range Detector Power            


Simulator JPM S8 Facility:             Davis-Besse    Task No:             008-004-01-0100    Task Title:      Component Cooling Water Pump Rotation       K/A  
        ........C........                      Supply Module in ON. STANDARD: Places ON
-OFF switch for NI 2 power supply to ON
. CUE: None    __________
SAT  UNSAT  6. PERFORMANCE STEP: Depress the RESET switch on the Source Range Detector Power ........C........                    Supply Module. COMMENT:
Depressing reset switch will reset the trip to allow the detector to reenergize when required. With Intermediate Range NIs above the cutout value the Source Range Detector will not energize
. STANDARD:
Depress the RESET switch on NI 1 Power Supply Module. CUE: None  __________
SAT  UNSAT  7. PERFORMANCE STEP: Depress the RESET switch on the Source Range Detector Power ........C........                    Supply Module. COMMENT:  Depressing reset switch will reset the trip to allow the detector to reenergize when required. With Intermediate Range NIs above the cutout value the Source Range Detector will not energize
. STANDARD:
Depress the RESET switch on NI 2 Power Supply Module. CUE: None  __________
SAT  UNSAT  8. PERFORMANCE STEP: Complete procedure section. STANDARD:
Determine step 4.4.3.c to be not applicable and sign/date completed by. CUE: None  __________
SAT  UNSAT  9. PERFORMANCE STEP: Lock the doors and return keys.
STANDARD:
Doors locked and key returned. CUE: None  __________
SAT  UNSAT  TERMINATING CUES:  This JPM is complete (Terminated by the examinee)
__________
END TIME 
 
Simulator JPM S8 Facility:
Davis-Besse    Task No:
008-004-01-0100    Task Title
:      Component Cooling Water Pump Rotation K/A  


==Reference:==
==Reference:==
       (008) A4.01 3.3/3.1        Job Performance Measure No:    S8 (JPM 018)    Examinee:           NRC Examiner:        Date:      Method of testing: Simulated Performance ___  Actual Performance _X_  Classroom ___  Simulator _X_  Plant ___ Read to the examinee: I will explain the initial conditions, which steps to simulate or discuss, and provide initiating cues. When you complete the task successfully, the objective for this job performance measure will be satisfied. Initial Conditions: The plant conditions are specified in the Initial Conditions and Initiating Cues.
       (008) A4.01 3.3/3.1        Job Performance Measure No
Task Standard: Place Component Cooling Water Pump 2 in service from standby condition and place Component Cooling Water Pump 1 (initially running) in standby. Required Materials: Section 3.2, 3.9, and 3.16 of DB-OP-06262, CCW System Procedure  Limits and Precautions for DB-OP-06262 General  
:    S8 (JPM 018)    Examinee:
NRC Examiner:        Date:      Method of testing:
Simulated Performance ___  Actual Performance _X_  Classroom ___  Simulator _X_  Plant ___
Read to the examinee:
I will explain the initial conditions, which steps to simulate or discuss, and provide initiating cues. When you complete the task successfully, the objective for this job performance measure  
 
will be satisfied.
Initial Conditions:
The plant conditions are specified in the Initial Conditions and Initiating Cues.
 
Task Standard:
Place Component Cooling Water Pump 2 in service from standby condition and place Component Cooling Water Pump 1 (initially running) in standby.
Required Materials:
Section 3.2, 3.9, and 3.16 of DB-OP-06262, CCW System Procedure  Limits and Precautions for DB
-OP-06262 General  


==References:==
==References:==
None  
None  


Initiating Cue: The plant conditions are specified in the Initial Conditions and Initiating Cues. Time Critical Task: No Alternate Path: No  Validation Time:  30 minutes SIMULATOR INSTRUCTIONS TASK DESCRIPTION: Place Component Cooling Water Pump 2 in service from standby condition and place Component Cooling Water Pump 1 (initially running) in standby. INITIAL CONDITION: Mode 1 CCW Pump 1 placed I/S to support testing which has been completed. Makeup Pump 1 left in service and Service Water secondaries left on SW loop 1 (SW1399 open) due to short duration of test. ADDITIONAL SETUP/DEVIATION FROM INITIAL CONDITION: CCW pump 1 running. Hang tags for CCW and SW pumps 3 being aligned to side 2. Makeup pump 1 running. SW 1399 Open and SW 1395 Closed. MALFUNCTIONS/FAILURE TO INSERT: None  ACTION/CUES:   
Initiating Cue:
The plant conditions are specified in the Initial Conditions and Initiating Cues.
Time Critical Task:
No Alternate Path:
No  Validation Time:  30 minutes SIMULATOR INSTRUCTIONS TASK DESCRIPTION
: Place Component Cooling Water Pump 2 in service from standby condition and place Component Cooling Water Pump 1 (initially running) in standby.
INITIAL CONDITION: Mode 1 CCW Pump 1 placed I/S to support testing which has been completed. Makeup Pump 1 left in service and Service Water secondaries left on SW loop 1 (SW1399 open) due to short duration of test. ADDITIONAL SETUP/DEVIATION FROM INITIAL CONDITION: CCW pump 1 running.
Hang tags for CCW and SW pumps 3 being aligned to side 2.
Makeup pump 1 running.
SW 1399 Open and SW 1395 Closed.
MALFUNCTIONS/FAILURE TO INSERT: None  ACTION/CUES:   
 
EXAMINER COPY INITIAL CONDITIONS: Plant is in Mode
: 1. CCW Pump 1 placed I/S to support testing which has been completed. Makeup Pump 1 left in service and Service Water secondaries left on SW loop 1 (SW1399 open) due to short duration of test. NO maintenance work has been done on the CCW System.
INITIATING CUES: Testing is complete and the Unit Supervisor directs you to shift CCW pumps so that CCW Pump 2 is in service and CCW Pump 1 is in standby, in accordance with Section 3.2 and 3.9 of DB-OP-06262, CCW System Procedure.
Valve testing is not required to be performed.
  (Provide student a copy of Section 3.2, 3.9, 3.16, and Limits and Precautions of DB-OP-06262, CCW System Procedure. The procedure is signed off with briefing complete, applicable prerequisites signed off, and some steps pre
-identified that will not be applicable)
CANDIDATE COPY INITIAL CONDITIONS: Plant is in Mode
: 1. CCW Pump 1 placed I/S to support testing which has been completed. Makeup Pump 1 left in service and Service Water secondaries left on SW loop 1 (SW1399 open) due to short duration of test. NO maintenance work has been done on the CCW System.
INITIATING CUES: Testing is complete and the Unit Supervisor directs you to shift CCW pumps so that CCW Pump 2 is in service and CCW Pump 1 is in standby, in accordance with Section 3.2 and 3.9 of DB-OP-06262, CCW System Procedure.
Valve testing is not required to be performed.
 
PERFORMANCE INFORMATION NOTE: Critical steps denoted with a "C". Failure to meet any one of these standards for this item constitutes failure. Sequence is NOT critical unless denoted in the "Comments".
 
START TIME:  _______
: 1. PERFORMANCE STEP:
Locate the correct procedure section.
 
STANDARD:
Identifies Section 3.2 (Component Cooling Water System) as correct procedure section.


EXAMINER COPY  INITIAL CONDITIONS: Plant is in Mode 1. CCW Pump 1 placed I/S to support testing which has been completed. Makeup Pump 1 left in service and Service Water secondaries left on SW loop 1 (SW1399 open) due to short duration of test. NO maintenance work has been done on the CCW System. INITIATING CUES: Testing is complete and the Unit Supervisor directs you to shift CCW pumps so that CCW Pump 2 is in service and CCW Pump 1 is in standby, in accordance with Section 3.2 and 3.9 of DB-OP-06262, CCW System Procedure. Valve testing is not required to be performed.  (Provide student a copy of Section 3.2, 3.9, 3.16, and Limits and Precautions of DB-OP-06262, CCW System Procedure. The procedure is signed off with briefing complete, applicable prerequisites signed off, and some steps pre-identified that will not be applicable)
CANDIDATE COPY  INITIAL CONDITIONS: Plant is in Mode 1. CCW Pump 1 placed I/S to support testing which has been completed. Makeup Pump 1 left in service and Service Water secondaries left on SW loop 1 (SW1399 open) due to short duration of test. NO maintenance work has been done on the CCW System. INITIATING CUES: Testing is complete and the Unit Supervisor directs you to shift CCW pumps so that CCW Pump 2 is in service and CCW Pump 1 is in standby, in accordance with Section 3.2 and 3.9 of DB-OP-06262, CCW System Procedure. Valve testing is not required to be performed.
PERFORMANCE INFORMATION  NOTE: Critical steps denoted with a "C". Failure to meet any one of these standards for this item constitutes failure. Sequence is NOT critical unless denoted in the "Comments".
START TIME:  _______  1. PERFORMANCE STEP: Locate the correct procedure section.
STANDARD: Identifies Section 3.2 (Component Cooling Water System) as correct procedure section.
COMMENT: Hand procedure to examinee. Sequence required for all steps, except steps 7, 8, 12, 13, 17, 18, 19 and 20.
COMMENT: Hand procedure to examinee. Sequence required for all steps, except steps 7, 8, 12, 13, 17, 18, 19 and 20.
CUE: None  __________       SAT  UNSAT   
CUE: None  __________
: 2. PERFORMANCE STEP: Verify Open SW38, CCW Heat Exchanger 1-2 Discharge Iso. STANDARD: Contact an EO to verify position of SW38. CUE: If EO contacted SW38, CCW Heat Exchanger 1-2 Discharge Iso., is OPEN.       __________       SAT  UNSAT   
SAT  UNSAT   
: 3. PERFORMANCE STEP: Start CCW Pump 1-2.  ........C........ STANDARD: Turn HIS1418 clockwise to CLOSE. COMMENT: Annunciator 11-5-B, CCW Pump 2 Flow LO, will alarm. It may be treated                               as an expected alarm as continuing with the procedure will clear the                              low flow condition. CUE: If asked, as EO report flow on FIS 1432 is 2800 gpm      __________       SAT  UNSAT   
: 2. PERFORMANCE STEP:
: 5. PERFORMANCE STEP: Adjust CCW Heat Exchanger Temperature control valve to 80F to                                                     85F OR as directed by the Shift Manager. STANDARD: Prerequisites identify Shift Manager desire of 85&#xba;F set point of TIC1434.                                 Contact an EO to obtain set point of 85&#xba;F on TIC1434. CUE: If needed, Shift Manager desires a set point of 85&#xba;F on TIC1434.                       __________       SAT  UNSAT    6. PERFORMANCE STEP: Route to Section 3.16. STANDARD: Route to Section 3.16 and complete prerequisite steps 3.16.1 and 3.16.2.
Verify Open SW38, CCW Heat Exchanger 1
CUE: None.      __________       SAT  UNSAT  7. PERFORMANCE STEP: Open CC2649 Aux Bldg Return.  ........C........
-2 Discharge Iso.
STANDARD: Depress the OPEN pushbutton on HIS2649.
STANDARD:
COMMENT: Sequence not required for steps 7 and 8    CUE: None.        __________       SAT  UNSAT  8. PERFORMANCE STEP: Open CC5098, CTMT Bldg Return.  ........C........
Contact an EO to verify position of SW38.
STANDARD: Depress the OPEN pushbutton on HIS5098.
CUE: If EO contacted SW38, CCW Heat Exchanger 1
COMMENT: Sequence not required for steps 7 and 8    CUE: None.        __________       SAT  UNSAT  9. PERFORMANCE STEP: OPEN CC5096, CCW Line 2 Discharge Isolation, when return            ........C........                      valves are open.
-2 Discharge Iso., is OPEN.
STANDARD: Depress the OPEN pushbutton on CC5096. CUE: None.        __________       SAT  UNSAT   
__________
: 10. PERFORMANCE STEP: Verify CC1469, CCW from DH Cooler 2 Outlet valve is closed.
SAT  UNSAT   
STANDARD: If open depress the CLOSE pushbutton on HIS1469. COMMENT: CC1469 may have been opened if actions for annunciator 11-5-B, CCW                              Pump 2 Flow LO, were performed at performance step 3. CUE: None. __________       SAT  UNSAT    11. PERFORMANCE STEP: Close CC5095 Non-essen supply.   ........C........ STANDARD: Depress the CLOSE pushbutton on HIS5095. CUE: None. __________       SAT  UNSAT     
: 3. PERFORMANCE STEP:
: 12. PERFORMANCE STEP: Close CC2645 Aux Bldg Return. ........C........ STANDARD: Depress the CLOSE pushbutton on HIS2645 Aux Bldg Return. COMMENT: Sequence not required for steps 12 and 13 CUE: None. __________       SAT  UNSAT   
Start CCW Pump 1-2.  ........C........
: 13. PERFORMANCE STEP: Close CC 5097 CTMT Bldg Return. ........C........ STANDARD: Depress the CLOSE pushbutton on HIS5097 CTMT Bldg Return. COMMENT: Sequence not required for steps 12 and 13    CUE: None. __________       SAT  UNSAT  14. PERFORMANCE STEP: Determine CCW Pump 1 discharge flow less than 3000 gpm as                                                    verified as read on FIS 1422 (local).
STANDARD:
STANDARD: Contact EO to report CCW 1 flow indication.
Turn HIS1418 clockwise to CLOSE.
COMMENT: Annunciator 11-4-B, CCW PMP 1 FLOW LO, will alarm at < 3000 gpm. CUE:  If EO contacted CCW Pump 1 Flow on FIS 1422 is 2800 gpm      .      __________       SAT  UNSAT  15. PERFORMANCE STEP: Open CC1467, CCW from DH Cooler 1 Outlet valve. STANDARD: Depress the OPEN pushbutton on HIS1467. CUE: None.      __________       SAT  UNSAT      16. PERFORMANCE STEP: Verify that CCW Pump 2 has a discharge flow greater than                                                   3000 gpm as read on FIS 1432 (locally).
COMMENT: Annunciator 11-5-B, CCW Pump 2 Flow LO, will alarm. It may be treated  
STANDARD: Contact EO to report CCW flow indication. CUE: If EO contacted CCW Pump 2 Flow on FIS 1432 is 7200 gpm.      __________       SAT  UNSAT  17. PERFORMANCE STEP: Route back to section 3.2.
 
STANDARD: Sign complete for section 3.16. Route to step 3.2.17 and sign complete.
as an expected alarm as continuing with the procedure will clear the                              low flow condition.
CUE: None.      __________       SAT  UNSAT  18. PERFORMANCE STEP: If CC1469 was open to provide minimum flow requirement then                                                   monitor Decay Heat Pump 2 suction pressure.
CUE: If asked, as EO report flow on FIS 1432 is 2800 gpm      __________
STANDARD: If CC1469 was open to provide minimum flow requirement then contact EO to monitor Decay Heat Pump 2 suction pressure using PI1538 per step 3.2.19 of DB-OP-06262. COMMENT: Step 3.2.18 is not applicable. Step 3.2.19 may be applicable if CC1469 was opened per alarm procedure response, requiring monitoring of Decay Heat Pump 2 suction pressure. CUE: (If necessary) Monitor Decay Heat Pump 2 suction pressure using PI1538 per step 3.2.19 of DB-OP-06262. __________       SAT  UNSAT  19. PERFORMANCE STEP: Verify SW1434, CCW Heat Exchanger 2 Control Valve is                                                   operating to maintain proper temperature.
SAT  UNSAT   
STANDARD: Contact EO to report status of TIC 1434. Verify TI 1490 indicates                                approximately 85&#xba;F.          CUE: As EO (If necessary) TIC 1434 is controlling CCW train 2 temperature at 85&#xba;F.      __________       SAT  UNSAT     
: 5. PERFORMANCE STEP:
: 20. PERFORMANCE STEP: Verify surveillance tests are not required.
Adjust CCW Heat Exchanger Temperature control valve to 80F to 85F OR as directed by the Shift Manager. STANDARD:
STANDARD: Contact Unit Supervisor. Per initiating cues valve testing is not required.
Prerequisites identify Shift Manager desire of 85&#xba;F set point of TIC1434.
COMMENT: Steps 3.2.21 through 3.2.25 are not applicable. CUE:  None      __________       SAT  UNSAT  21. PERFORMANCE STEP: Verify Makeup Pump 1 is in service. STANDARD: Verify HIS MU24B indicates Makeup Pump 1 is running. CUE: None.      __________
Contact an EO to obtain set point of 85&#xba;F on TIC1434.
SAT  UNSAT  22. PERFORMANCE STEP: Route to Section 3.9.
CUE: If needed
STANDARD: Route to Section 3.9. CUE: None.      __________       SAT  UNSAT  23. PERFORMANCE STEP: Verify that EDG 1, LPI pump 1 and HPI pump 1 are not operating. STANDARD: Monitor control board for status of EDG 1, LPI 1 and HPI 1. Complete                               Prerequisites. CUE: None.      __________       SAT  UNSAT  24. PERFORMANCE STEP: Verify SW1424, CCW Heat Exchanger Outlet 1 valve, is closed or                                                  15 minutes have elapsed since the heat load has been removed. STANDARD: Check that SW1424 has green light lit or 15 minutes have elapsed.
, Shift Manager desires a set point of 85&#xba;F on TIC1434.
CUE: (If necessary) 15 minutes has elapsed since the heat loads have been removed.      __________       SAT  UNSAT         
__________
: 25. PERFORMANCE STEP: Stop CCW Pump 1. ........C........
SAT  UNSAT    6. PERFORMANCE STEP:
STANDARD: Position HIS1414 to TRIP. CUE: None. __________       SAT  UNSAT   
Route to Section 3.16.
: 26. PERFORMANCE STEP: Set TIC1424 as directed by the Shift Manager in prerequisite                                                     step 3.9.3   STANDARD: Contact EO to slowly adjust TIC1424 to 110F. CUE: TIC1424 is set to 110F. __________       SAT  UNSAT  27. PERFORMANCE STEP: Verify CC 1467, CCW from DH Cooler 1 Outlet valve, is closed. STANDARD: If CC1467 is open, press closed on HIS1467.
STANDARD:
CUE: None. __________       SAT  UNSAT  TERMINATING CUES: This JPM is complete. (Terminated by the examiner)       __________       END TIME}}
Route to Section 3.16 and complete prerequisite steps 3.16.1 and 3.16.2.
CUE: None.      __________
SAT  UNSAT  7. PERFORMANCE STEP:
Open CC2649 Aux Bldg Return.  
   ........C........
STANDARD:
Depress the OPEN pushbutton on HIS2649.
COMMENT: Sequence not required for steps 7 and 8    CUE: None.        __________
SAT  UNSAT  8. PERFORMANCE STEP:
Open CC5098, CTMT Bldg Return.  ........C........
 
STANDARD:
Depress the OPEN pushbutton on HIS5098.
COMMENT: Sequence not required for steps 7 and 8    CUE: None.        __________
SAT  UNSAT  9. PERFORMANCE STEP:
OPEN CC5096, CCW Line 2 Discharge Isolation, when return            ........C........                      valves are open.
 
STANDARD:
Depress the OPEN pushbutton on CC5096.
CUE: None.        __________
SAT  UNSAT   
: 10. PERFORMANCE STEP:
Verify CC1469, CCW from DH Cooler 2 Outlet valve is closed.
 
STANDARD:
If open depress the CLOSE pushbutton on HIS1469.
COMMENT: CC1469 may have been opened if actions for annunciator 11-5-B, CCW                              Pump 2 Flow LO, were performed at performance step 3.
CUE: None. __________
SAT  UNSAT    11. PERFORMANCE STEP:
Close CC5095 Non
-essen supply.
  ........C........
STANDARD:
Depress the CLOSE pushbutton on HIS5095. CUE: None. __________
SAT  UNSAT     
: 12. PERFORMANCE STEP:
Close CC2645 Aux Bldg Return.
  ........C........
STANDARD:
Depress the CLOSE pushbutton on HIS2645 Aux Bldg Return.
COMMENT: Sequence not required for steps 12 and 13 CUE: None. __________
SAT  UNSAT   
: 13. PERFORMANCE STEP:
Close CC 5097 CTMT Bldg Return.
  ........C........
STANDARD:
Depress the CLOSE pushbutton on HIS5097 CTMT Bldg Return.
COMMENT: Sequence not required for steps 12 and 13    CUE: None. __________
SAT  UNSAT  14. PERFORMANCE STEP:
Determine CCW Pump 1 discharge flow less than 3000 gpm as                                                    verified as read on FIS 1422 (local).
STANDARD:
Contact EO to report CCW 1 flow indication.
 
COMMENT: Annunciator 11-4-B, CCW PMP 1 FLOW LO, will alarm at < 3000 gpm.
CUE:  If EO contacted CCW Pump 1 Flow on FIS 1422 is 2800 gpm      .      __________
SAT  UNSAT  15. PERFORMANCE STEP:
Open CC1467, CCW from DH Cooler 1 Outlet valve.
STANDARD:
Depress the OPEN pushbutton on HIS1467.
CUE: None.      __________
SAT  UNSAT      16. PERFORMANCE STEP:
Verify that CCW Pump 2 has a discharge flow greater than 3000 gpm as read on FIS 1432 (locally).
 
STANDARD:
Contact EO to report CCW flow indication.
CUE: If EO contacted CCW Pump 2 Flow on FIS 1432 is 7200 gpm.      __________
SAT  UNSAT  17. PERFORMANCE STEP:
Route back to section 3.2.
 
STANDARD:
Sign complete for section 3.16. Route to step 3.2.17 and sign complete.
CUE: None.      __________
SAT  UNSAT  18. PERFORMANCE STEP:
If CC1469 was open to provide minimum flow requirement then monitor Decay Heat Pump 2 suction pressure.
 
STANDARD:
If CC1469 was open to provide minimum flow requirement then contact EO to monitor Decay Heat Pump 2 suction pressure using PI1538 per step 3.2.19 of DB-OP-06262. COMMENT: Step 3.2.18 is not applicable. Step 3.2.19 may be applicable if CC1469 was opened per alarm procedure response, requiring monitoring of Decay Heat Pump 2 suction pressure.
CUE: (If necessary) Monitor Decay Heat Pump 2 suction pressure using PI1538 per step 3.2.19 of DB
-OP-06262. __________
SAT  UNSAT  19. PERFORMANCE STEP:
Verify SW1434, CCW Heat Exchanger 2 Control Valve is operating to maintain proper temperature.
 
STANDARD:
Contact EO to report status of TIC 1434. Verify TI 1490 indicates                                approximately 85&#xba;F.          CUE: As EO (If necessary) TIC 1434 is controlling CCW train 2 temperature at 85&#xba;F.      __________
SAT  UNSAT     
: 20. PERFORMANCE STEP:
Verify surveillance tests are not required.
 
STANDARD:
Contact Unit Supervisor.
Per initiating cues valve testing is not required.
COMMENT: Steps 3.2.21 through 3.2.25 are not applicable
. CUE:  None      __________
SAT  UNSAT  21. PERFORMANCE STEP:
Verify Makeup Pump 1 is in service.
STANDARD: Verify HIS MU24B indicates Makeup Pump 1 is running.
CUE: None.      __________
 
SAT  UNSAT  22. PERFORMANCE STEP:
Route to Section 3.9.
 
STANDARD:
Route to Section 3.9.
CUE: None.      __________
SAT  UNSAT  23. PERFORMANCE STEP:
Verify that EDG 1, LPI pump 1 and HPI pump 1 are not operating.
STANDARD:
Monitor control board for status of EDG 1, LPI 1 and HPI
: 1. Complete  
 
Prerequisites. CUE: None.      __________
SAT  UNSAT  24. PERFORMANCE STEP:
Verify SW1424, CCW Heat Exchanger Outlet 1 valve, is closed or                                                  15 minutes have elapsed since the heat load has been removed.
STANDARD:
Check that SW1424 has green light lit or 15 minutes have elapsed.
 
CUE: (If necessary) 15 minutes has elapsed since the heat loads have been removed.      __________
SAT  UNSAT         
: 25. PERFORMANCE STEP:
Stop CCW Pump 1.
  ........C........
 
STANDARD:
Position HIS1414 to TRIP.
CUE: None. __________
SAT  UNSAT   
: 26. PERFORMANCE STEP:
Set TIC1424 as directed by the Shift Manager in prerequisite step 3.9.3 STANDARD:
Contact EO to slowly adjust TIC1424 to 110F.
CUE: TIC1424 is set to 110F.
__________
SAT  UNSAT  27. PERFORMANCE STEP:
Verify CC 1467, CCW from DH Cooler 1 Outlet valve, is closed.
STANDARD:
If CC1467 is open, press closed on HIS1467.
 
CUE: None. __________
SAT  UNSAT  TERMINATING CUES:
This JPM is complete. (Terminated by the examiner)
__________
END TIME}}

Revision as of 04:07, 30 June 2018

Operating JPMs
ML16221A553
Person / Time
Site: Davis Besse Cleveland Electric icon.png
Issue date: 08/02/2016
From:
Operations Branch III
To:
FirstEnergy Nuclear Operating Co
Shared Package
ML15274A359 List:
References
Download: ML16221A553 (90)


Text

In Plant JPM P1 Facility:

Davis-Besse Task No: 001-043-05-0100 Task Title

Trip Reactor From #2 Low Voltage Switchgear Room K/A

Reference:

(001) A2.11 4.4/4.7 Job Performance Measure No

P1 (JPM 042) Examinee:

NRC Examiner: Date: Method of testing:

Simulated Performance __ X _ Actual Performance ___ Classroom ___ Simulator _ _ Plant _ X __

Read to the examinee:

I will explain the initial conditions, which steps to simulate or discuss, and provide initiating cues.

When you complete the task successfully, the objective for this job performance measure will be satisfied.

Initial Conditions:

The plant conditions are specified in the Initial Conditions and Initiating Cues.

Task Standard:

Trip Reactor by manually tripping Reactor Trip Breakers in the Low Voltage Switchgear Rooms Required Materials:

DB-OP-02000 Section 3, step 3.3 General

References:

None Initiating Cue:

The plant conditions are specified in the Initial Conditions and Initiating Cues.

Time Critical Task:

No Alternate Path:

No Validation Time:

6 minutes

EXAMINER COPY INITIAL CONDITIONS: The plant has just experienced a severe transient causing a reactor trip signal to be generated.

The reactor did not trip.

Control power problems have prevented the Control Room from deenergizing E2 and F2.

INITIATING CUES

The Unit Supervisor directs you to proceed to the Low Voltage Switchgear Rooms to deenergize the Control Rod Drive system by manually tripping Reactor Trip Breakers in accordance with Step 3.3 of DB

-OP-02000, RPS, SFAS, SFRCS Trip or SG Tube Rupture.

(Hand copy of DB

-OP-02000 step 3.3 to the examinee)

CANDIDATE COPY INITIAL CONDITIONS

The plant has just experienced a severe transient causing a reactor trip signal to be generated.

The reactor did not trip.

Control power problems have prevented the Control Room from deenergizing E2 and F2.

INITIATING CUES

The Unit Supervisor directs you to proceed to the Low Voltage Switchgear Rooms to deenergize the Control Rod Drive by manually tripping Reactor Trip Breakers in accordance with Step 3.3 of DB-OP-02000, RPS, SFAS, SFRCS Trip or SG Tube Rupture.

PERFORMANCE INFORMATION NOTE: Critical steps denoted with a "C". Failure to meet any one of these standards for this item constitutes failure. Sequence is NOT critical unless denoted in the "Comments".

START TIME: _______

1. PERFORMANCE STEP:

Recognize the correct procedure step.

STANDARD:

Recognize DB

-OP-02000, RPS, SFAS, SFRCS Trip or SG Tube Rupture, Step 3.3 RNO as correct procedure step CUE: None __________

SAT UNSAT

2. PERFORMANCE STEP: Trip Control Rod Drive Breaker A STANDARD:

Push the TRIP pushbutton on Control Rod Drive Breaker A and observe the Green Trip flag is vis ible COMMENT: Performance Note - Performance steps 2, 3, and 4 may be performed in any order, but TRIPPING Control Rod Drive Breaker B and Control Rod Drive

Breaker C are required to obtain desired response.

CUE: Trip pushbutton has been pushed on Control Rod Drive Breaker A.

Green TRIP flag is NOT visible.

The Reactor has NOT TRIPPED.

__________

SAT UNSAT

3. PERFORMANCE STEP: Trip Control Rod Drive Breaker C ........C........

STANDARD:

Push the TRIP pushbutton on Control Rod Drive Breaker C and observe the Green Trip flag is vis ible CUE: TRIP pushbutton has been pushed on Control Rod Drive Breaker C.

Green TRIP flag is visible.

(If Control Rod Drive Breaker B HAS been tripped) The Reactor has TRIPPED (If Control Rod Drive Breaker B HAS NOT been tripped) The Reactor has NOT TRIPPED.

__________

SAT UNSAT 4. PERFORMANCE STEP: Trip Control Rod Drive Breaker B

........C........

STANDARD: Push the TRIP pushbutton on Control Rod Drive Breaker B and observe the Green Trip flag is visible CUE: TRIP pushbutton has been pushed on Control Rod Drive Breaker B. Green TRIP flag is visible.

(If Control Rod Drive Breaker C has NOT been tripped, the Reactor has NOT TRIPPED)

(If Control Rod Drive Breaker C HAS been tripped) The Reactor has TRIPPED. __________

SAT UNSAT TERMINATING CUES: This JPM is complete (Terminated by the examiner)

__________

END TIME

In Plant JPM P2 Facility:

Davis-Besse Task No: 001-043-05-0100 Task Title

Locally Operate Atmospheric Vent Valve ICS11A K/A

Reference:

(039) A4.07 2.8/2.9 Job Performance Measure No: P2 (JPM 024) Examinee:

NRC Examiner: Date: Method of testing:

Simulated Performance __ X _ Actual Performance ___ Classroom ___ Simulator _ _ Plant _ X __ Read to the examinee:

I will explain the initial conditions, which steps to simulate or discuss, and provide initiating cues. When you complete the task successfully, the objective for this job performance measure will be satisfied.

Initial Conditions:

The plant conditions are specified in the Initial Conditions and Initiating Cues.

Task Standard:

Locally Operate Atmospheric Vent Valve ICS11A

Required Materials:

DB-OP-02000 Attachment 3 General

References:

None

Initiating Cue:

The plant conditions are specified in the Initial Conditions and Initiating Cues.

Time Critical Task:

No Alternate Path:

No Validation Time:

13 minutes

EXAMINER COPY INITIAL CONDITIONS: The Atmospheric Vent Valves cannot be controlled from the Control Room due to severe loss of instrument air.

INITIATING CUES

The Unit Supervisor directs you to locally operate Atmospheric Vent Valve ICS 11A starting at Section D step 3.0 of Attachment 3 of DB

-OP-02000 (IA450 has been closed by another operator). (Hand the trainee a copy of Attachment 3 of DB

-OP-02000)

CANDIDATE COPY INITIAL CONDITIONS

The Atmospheric Vent Valves cannot be controlled from the Control Room due to severe loss of instrument air.

INITIATING CUES

The Unit Supervisor directs you to locally operate Atmospheric Vent Valve ICS 11A starting at Section D step 3.0 of Attachment 3 of DB

-OP-02000 (IA450 has been closed by another operator).

PERFORMANCE INFORMATION NOTE: Critical steps denoted with a "C". Failure to meet any one of these standards for this item constitutes failure. Sequence is NOT critical unless denoted in the "Comments".

START TIME: _______

1. PERFORMANCE STEP: Verify Valve A (ICS11AA) open STANDARD:

Verify Valve A (ICS11AA) is open by turning in the clockwise direction and returning to open position CUE: Valve ICS11AA is rotated a small amount in the clockwise direction and then returned to full OPEN

__________

SAT UNSAT

2. PERFORMANCE STEP: Open Valve B (ICS11AB) ........C........

STANDARD:

Turn handwheel counterclockwise to open Valve B (ICS11AB) COMMENT: Step 1-3 shall be performed prior to Step 5 CUE: Valve ICS11AB handwheel is rotated counterclockwise and is open

__________

SAT UNSAT

3. PERFORMANCE STEP: Notify the Control Room that ICS11A is ready for local manual operation

STANDARD: Communicate with Control Room using radio to determine desired valve position CUE: Communications have been established with the Control Room The Reactor Operator directs you to position the Atmospheric Vent Valve to

10 turns on the handwheel counter

__________

SAT UNSAT 4. PERFORMANCE STEP:

Check the handwheel counter at 0 STANDARD:

Check the handwheel counter is at zero CUE: Handwheel counter is at zero (0) __________

SAT UNSAT

5. PERFORMANCE STEP: Establish desired throttle position

........C........

STANDARD:

Turn the handwheel in the clockwise direction 10 turns until counter reads 10 Note: Valve manual handwheel is reverse acting CUE: Handwheel is rotated in the clockwise direction The handwheel counter is at 10.

Instrument air has been restored.

The Reactor Operator directs you to close ICS11A, establish positive shutoff and restore instrument air to the Atmospheric Vent Valve.

__________

SAT UNSAT

6. PERFORMANCE STEP: Close the Atmospheric Vent valve (ICS 11A) and establish ........C........ positive shutoff

STANDARD:

Turn the handwheel in the counterclockwise direction until the counter is zero (0) COMMENT: Step 6 shall be performed prior to step 7 CUE: Handwheel is rotated counterclockwise direction Handwheel counter is at zero (0)

__________

SAT UNSAT

7. PERFORMANCE STEP: Close Valve B ICS11AB ........C........

STANDARD: Manual handwheel for Valve ICS11AB rotated clockwise until closed CUE: Valve ICS11AB handwheel has been rotated clockwise, valve is closed.

__________

SAT UNSAT TERMINATING CUES: This JPM is complete (Terminated by the examiner)

__________

END TIME

In Plant JPM P3 Facility:

Davis-Besse Task No: 064-026-05-0401 Task Title

Energize Station Blackout Diesel Generator Auxiliaries K/A

Reference:

(064) A2.12 2.8/3.1 Job Performance Measure No

P3 (JPM 258) Examinee:

NRC Examiner: Date: Method of testing:

Simulated Performance __ X _ Actual Performance ___ Classroom ___ Simulator _ _ Plant _ X __ Read to the examinee:

I will explain the initial conditions, which steps to simulate or discuss, and provide initiating cues. When you complete the task successfully, the objective for this job performance measure will be satisfied.

Initial Conditions:

The plant conditions are specified in the Initial Conditions and Initiating Cues.

Task Standard:

Energize Station Blackout Diesel Generator Auxiliaries Emergency Shutdown Station Blackout Diesel Generator (Loss of Air Cooling Fans) Required Materials:

Section 4.10 of DB

-OP-06334, Station Blackout Diesel Generator Operating Procedure Section 5.2 of DB

-OP-06334, Emergency Shutdown of Station Blackout Diesel Generator General

References:

None Initiating Cue:

The plant conditions are specified in the Initial Conditions and Initiating Cues.

Time Critical Task:

No Alternate Path:

Yes Validation Time:

15 minutes

EXAMINER COPY INITIAL CONDITIONS: The plant is operating at 100% power Ambient temperature is 45°F Breaker AD213, SBDOG to D2, has been opened in preparation for breaker maintenance

AD213 was opened 15 minutes ago INITIATING CUES: NOTE: Procedure Step 4.10.2 needs to be initialed indicating that Barring of the Station Blackout Diesel Generator is NOT required. In the procedure step NO should be circled.

The Unit Supervisor directs you to perform Section 4.10, Energizing the Station Blackout Diesel Generator Auxiliaries from the Station Blackout Diesel Generator, of DB

-OP-06334.

You have an eSOMS handheld computer with the Station Blackout Diesel Generator readings downloaded. (Provide the examinee a copy of procedure package including section 4.10 of DB-OP-06334, Station Blackout Diesel Generator Operating Procedure.

Procedure Step 4.10.2 needs to be initialed indicating that Barring of the Station Blackout Diesel Generator is NOT required. In the procedure step NO should be circled.

Section 5.2 will be provided when it is recognized emergency shutdown of the SBODG is required.)

CANDIDATE COPY INITIAL CONDITIONS:

The plant is operating at 100% power

Ambient temperature is 45°F Breaker AD213, SBDOG to D2, has been opened in preparation for breaker maintenance AD213 was opened 15 minutes ago INITIATING CUES:

The Unit Supervisor directs you to perform Section 4.10, Energizing the Station Blackout Diesel Generator Auxiliaries from the Station Blackout Diesel Generator, of DB

-OP-06334.

You have an eSOMS handheld computer with the Station Blackout Diesel Generator readings Downloaded.

PERFORMANCE INFORMATION

NOTE: Critical steps denoted with a "C". Failure to meet any one of these standards for this item constitutes failure. Sequence is NOT critical unless denoted in the "Comments".

START TIME: _______

1. PERFORMANCE STEP:

Depress and hold the FUEL PRIME pushbutton until fuel oil pressure stabilizes >15 PSIG. STANDARD:

Depresses the FUEL PRIME pushbutton until fuel oil pressure stabilizes greater than 15 PSIG on the black indicator of PI 11160.

CUE: FUEL PRIME pushbutton depressed

, PI 11160 FUEL FILTER Pressure black indicator reads 17 PSIG __________

SAT UNSAT

2. PERFORMANCE STEP: Place the ELECT PROTECT

-MODE SELECT Switch in the TEST ........C........ position. STANDARD:

Rotate the ELECT PROTECT

-MODE SELECT Switch to the TEST position on C30202.

CUE: The ELECT PROTECT - MODE SELECT Switch has been rotated and points towards TEST __________

SAT UNSAT

3. PERFORMANCE STEP: Verify SBODG OUTPUT BREAKER AD 301 is open. STANDARD:

On panel C30202, Verifies AD 301 GREEN light is lit. CUE: AD 301 GREEN LIGHT is lit

__________

SAT UNSAT

4. PERFORMANCE STEP: Start the SBODG. ........C........

STANDARD: Depress the SBODG START pushbutton on Panel 30202. CUE: The START pushbutton has been depressed

__________

SAT UNSAT

5. PERFORMANCE STEP:

After 30 seconds CHECK the Station Blackout Diesel Generator starts and accelerates to approximately 450 RPM. STANDARD:

After approximately 30 seconds verify the Station Blackout Diesel Generator starts and accelerates to approximately 450 rpm as indicated on ENGINE TACHOMETER on C30203. CUE: After approximately 30 seconds the diesel starts. When checking speed on Engine Tachometer, Tachometer on C30203 reads 450 rpm. __________

SAT UNSAT

6. PERFORMANCE STEP: After approximately 30 seconds, the Station Blackout Diesel Generator accelerates to 900 rpm. STANDARD:

Verify the Station Blackout Diesel Generator accelerates to approximately 900 rpm after 30 seconds as indicated by ENGINE TACHOMETER on C30203. CUE: After approximately 30 seconds the diesel accelerates.

Engine Tachometer on C30203 reads 900 rpm. __________

SAT UNSAT 7. PERFORMANCE STEP: Place the SYNCHRONIZE switch in the ON position

........C........

STANDARD:

Install operating handle and rotate the SYNCHONIZE switch to the ON position CUE: The SYNCHRONIZE switch is in the ON position, If asked, The synchroscope pointer indicates 1200

__________

SAT UNSAT

8. PERFORMANCE STEP: Close Breaker AD 301, SBODG OUTPUT BREAKER on Panel ........C........ C30202 STANDARD: Rotate handswitch for AD301 to the close position CUE: AD 301 RED LIGHT is ON

__________

SAT UNSAT

9. PERFORMANCE STEP:

Place the SYNCHRONIZE switch to OFF STANDARD:

Rotate the SYNCHRONIZE switch to OFF position CUE: The SYNCHRONIZE switch is in the OFF position

__________

SAT UNSAT

10. PERFORMANCE STEP: Verify both Station Blackout Diesel Generator Jacket Water Radiator fans are operating STANDARD:

Check the status of the fans by observing the breaker lights and/or observing the fans locally, recognize neither fan is operating NOTE: Alternate Path begins with recognition that fans are not running and emergency shutdown the SBODG must be performed CUE: Both fan breaker lights indicate GREEN (or the fans are not turning if checked locally)

__________

SAT UNSAT

11. PERFORMANCE STEP: Go to Section 5.2, Emergency Shutdown of the Station Blackout Diesel Generator STANDARD:

Route to section 5.2, Emergency Shutdown of the Station Blackout Diesel Generator CUE: (Provide the examinee a copy of Section 5.2 of DB-OP-06334)

__________

SAT UNSAT

12. PERFORMANCE STEP: Stop the Station Blackout Diesel Generator ........C........

STANDARD:

Depress the Emergency Stop pushbutton on panel C30202 or panel C30203.

CUE: The Emergency Stop has been depressed. The Station Blackout Diesel Generator is beginning to slow down.

(If asked) AD 301 GREEN light is ON, RED light is OFF

__________

SAT UNSAT

13. PERFORMANCE STEP: Station Blackout Diesel Generator stops STANDARD: Verify Engine Tachometer reads zero on C30203 CUE: The Station Blackout Diesel Generator tachometer reads zero

__________

SAT UNSAT TERMINATING CUES: This JPM is complete (Terminated by the examiner)

__________

END TIME

Simulator JPM S1 Facility:

Davis-Besse Task No: 008-005-01-0100 Task Title

Swap Control Rod Drive Cooling Booster pumps K/A

Reference:

(001) A2.11 4.4/4.7 Job Performance Measure No

S1 (NEW) Examinee:

NRC Examiner: Date: Method of testing:

Simulated Performance ___ Actual Performance _X_ Classroom ___ Simulator _X_ Plant ___

Read to the examinee:

I will explain the initial conditions, which steps to simulate or discuss, and provide initiating cues. When you complete the task successfully, the objective for this job performance measure will be satisfied.

Initial Conditions:

The plant conditions are specified in the Initial Conditions and Initiating Cues. Use 100% power IC. Verity #1 CRDC Booster Pump is running.

IMF KA H 3D Thermal Overload on #2 CRDC Booster Pump (Insert after EO contacted to open BE2206)

Task Standard:

Start the STBY CRDC Booster Pump 2 Stop the running CRDC Booster Pump 1 Open pump suction valve CC1328 and restart previously running CRDC Booster Pump 1 Required Materials:

DB-OP-06262 Section 3.21 ready for performance of prerequisite 3.21.1 DB-OP-06262 Section 3.19 with prerequisites complete and step 3.19.1 marked N/A General

References:

None Initiating Cue:

The plant conditions are specified in the Initial Conditions and Initiating Cues.

Time Critical Task:

No Alternate Path:

Yes Validation Time: 9 minutes

SIMULATOR INSTRUCTIONS TASK DESCRIPTION: Swap Control Rod Drive Cooling Booster pumps INITIAL CONDITION: Any at power I/C ADDITIONAL SETUP/DEVIATION FROM INITIAL CONDITION: Verify #1 CRDC Booster Pump is running MALFUNCTIONS/FAILURE TO INSERT: #2 CRDC Booster Pump trip after EO is sent to open BE2206 CC1328, CRD Booster Pump 1 Suction Valve, fails closed when pump 1 is stopped

EXAMINER COPY INITIAL CONDITIONS: The plant is at 100%

All systems are in a normal lineup

Engineering has requested to inspect CRD Filter 1 filter element to verify correct size. There are no other issues with CRD Filter 1 Maintenance is ready to disassemble CRD Filter 1 for inspection

I & C has removed PDI 2952 from service INITIATING CUES

The Command SRO has directed you to place #2 Control Rod Drive Booster Pump in service in preparation for filter F55

-1, FILTER CRDC 1

-1 inspection IAW DB

-OP-06262 Section 3.21 and 3.19.

(Provide examinee a copy of section 3.19 and 3.21 DB-OP-06262)

CANDIDATE COPY INITIAL CONDITIONS: The plant is at 100%

All systems are in a normal lineup Engineering has requested to inspect CRD Filter 1 filter element to verify correct size. There are no other issues with CRD Filter 1 Maintenance is ready to disassemble CRD Filter 1 for inspection

I & C has removed PDI 2952 from service INITIATING CUES

The Command SRO has directed you to place #2 Control Rod Drive Booster Pump in service

in preparation for filter F55

-1, FILTER CRDC 1

-1 inspection IAW DB

-OP-06262 Section 3.21 and 3.19.

PERFORMANCE INFORMATION NOTE: Critical steps denoted with a "C". Failure to meet any one of these standards for this item constitutes failure. Sequence is NOT critical unless denoted in the "Comments".

START TIME: _______

1. PERFORMANCE STEP: Verify CRD Booster Pump 2 is in service (Step 3.21.1).

STANDARD:

Refer to Subsection 3.19, Startup of CRD Booster Pump 2. CUE: None __________

SAT UNSAT

2. PERFORMANCE STEP: Start CRD CLNG BOOSTER PUMP 2. ........C........

STANDARD:

Start CRD CLNG BOOSTER PUMP 2 using HIS1924. NOTE: Annunciator 5-6-D will alarm when the second pump is started. The alarm may be treated as an expected alarm. If alarm procedure is used guidance will be if an evolution is in progress causing the alarm stop the standby pump if desired.

CUE: None __________

SAT UNSAT

3. PERFORMANCE STEP: Verify CRD Booster Pump 2 discharge pressure at PI756 is between 120 and 160 PSIG. STANDARD: Contacts EO to verify CRD Booster Pump 2 discharge pressure at PI756 is between 120 and 160 PSIG. CUE: Equipment Operator reports CRD Booster Pump 2 discharge pressure at PI756 is 150 PSIG. __________

SAT UNSAT

4. PERFORMANCE STEP: Stop CRD CLNG BOOSTER PUMP 1 and place in lockout.

........C........

STANDARD: Verify CRD CLNG BOOSTER PUMP 1 off and in LOCKOUT using HIS1915. NOTE: CC1328, Suction valve for CRD Booster Pump 1, will be triggered to fail closed when the pump is shut down (switch bumped by mechanic walking down filter inspection).

CUE: None __________

SAT UNSAT

5. PERFORMANCE STEP: Verify CRD Booster Pump 2 discharge flow on FIS2586 is greater than 150 GPM

. NOTE: Pump 2 will trip triggered by a time delay which may occur during or prior to performance steps 5, 6, 7, 8, or 9 and require performance step 10 to be implemented.

STANDARD: Contacts EO to verify CRD Booster Pump 2 discharge flow on FIS2586 is greater than 150 GPM.

CUE: EO reports flow on FIS2586 is 190 GPM. __________ SAT UNSAT 6. PERFORMANCE STEP: Complete section 3.19 and route back to section 3.21. STANDARD: Signs section 3.19 complete and routes back to section 3.21. NOTE: Step 3.19.8 pre-identified as N/A since being removed from service

. CUE: None __________

SAT UNSAT 7. PERFORMANCE STEP: Complete prerequisites for section 3.21. STANDARD: Signs step 3.21.1 complete and signs for prerequisites complete. CUE: None __________

SAT UNSAT

8. PERFORMANCE STEP: Place HIS1915, CRD CLNG BOOSTER PUMP 1 in LOCKOUT. STANDARD: Verifies switch HIS1915 is in LOCKOUT.

NOTE: Step 3.21.4 may be marked N/A since the switch was left in LOCKOUT during performance of section 3.19. CUE: None __________

SAT UNSAT 9. PERFORMANCE STEP:

Open BE2206, CRD BOOSTER PUMP 1. STANDARD: Contact EO to OPEN BE2206, CRD BOOSTER PUMP 1. CUE: Role play as EO, acknowledge direction to open BE2206. __________

SAT UNSAT ALTERNATE PATH - CRD Booster Pump 2 trips and will require placing CRD Booster Pump 1 back into service. CRD Booster Pump 1 suction valve CC1328 will close when the pump is shut down in performance step 4 which will require verifying flow path and opening CC1328 prior to starting CRD Booster Pump 1.

10. PERFORMANCE STEP: Respond to Annunciator 5-6-D, CRD BOOSTER PMP P HI/FLOW LO/GO TO DB

-OP-02523, CCW System Malfunctions. STANDARD: Recognize entry criteria and implement DB-OP-02523, CCW System Malfunctions, or refer to alarm procedure which will direct to the abnormal procedure CUE: (If asked) Role play as the EO, CRD BOOSTER PUMP 2 is off, motor is hot to the touch. __________

SAT UNSAT 11. PERFORMANCE STEP: Verify the standby CRD Booster pump starts.

STANDARD: Attempt to start CRD Booster Pump 1 (will not be successful due to suction valve being closed). CUE: None __________

SAT UNSAT

12. PERFORMANCE STEP: Monitor CRD Stator temperatures. STANDARD: Using RNO guidance (since pump 1 was not able to be started) monitor CRD Stator temperatures using NSSS Summary Files 12 and 13 and trip the reactor if any CRD Stator temperature reaches 180 ºF. CUE: As a maintenance mechanic report to the control room that while walking

down the CRD Filter 1 inspection work in #4 MPR a switch was bumped and it sounded like something actuated.

__________

SAT UNSAT 13. PERFORMANCE STEP: Verify the CRD Cooling Booster flow path is available. ........C........

STANDARD: Refer to Attachment 8 for verification of proper flow path to identify CC1328 is closed and open CC1328. Start/ensure CRD Cooling Booster Pump 1 is running.

NOTE: If the CRD Booster Pump 1 switch is left in auto after attempting to start in performance step 11 the pump will auto start when CC1328 is open, otherwise verify the pump is running by returning the switch to auto. CUE: None __________

SAT UNSAT TERMINATING CUES: This JPM is complete (Terminated by the examiner)

__________

END TIME Simulator JPM S2 Facility:

Davis-Besse Task No: 000-093-05-0100 Task Title

Transfer LPI Suctions to the Emergency Sump K/A

Reference:

(006) A4.05 (3.9/3.8)________Job Performance Measure No

S2 (JPM 291) Examinee:

NRC Examiner: Date: Method of testing:

Simulated Performance _

__ Actual Performance __

X__ Classroom ___ Simulator _X_ Plant ___

Read to the examinee:

I will explain the initial conditions, which steps to simulate or discuss, and provide initiating cues. When you complete the task successfully, the objective for this job performance measure will be satisfied.

Initial Conditions:

The plant conditions are specified in the Initial Conditions and Initiating Cues.

Task Standard:

Transfer LPI Suctions to the Emergency Sump Required Materials:

Attachment 7 Section 2 of DB-OP-02000, RPS, SFAS, SFRCS Trip, or SG Tube Rupture

.

General

References:

None Initiating Cue:

The plant conditions are specified in the Initial Conditions and Initiating Cues.

Time Critical Task:

No Alternate Path: Yes Validation Time:

14 minutes

SIMULATOR INSTRUCTIONS TASK DESCRIPTION: Transfer LPI Suctions to the Emergency Sump INITIAL CONDITION: Large Break LOCA Spray Pumps are not running ADDITIONAL SETUP/DEVIATION FROM INITIAL CONDITION: Ensure DH 9A, DH 9B, DH 7A, DH7B and HP 31 are energized Complete all DB

-OP-02000 Section 10 actions up to step 10.13 Turn the "Breaker Open" tags for DH 9A, DH 9B, DH 7A, DH 7B and HP31 upside down Freeze the simulator when BWST level is less than 9 feet

Annunciator 5-3-A, BWST LO

-LOLVL XFER TO EMER SUMP is in alarm. Output modules L511, L512, L513, and L514 (at least 3 out of 4) have failed to trip.

Leave the simulator frozen until the examinee is ready to start the JPM MALFUNCTIONS/FAILURE TO INSERT: Insert both hot leg leaks at the same time, IMF HH41 .8 Fail level 5 output modules to trip, L6AMC, L6BMC

, and L6CMC Insight insert TALA531 to 0.1 this is for the BWST LO

-LO LVL XFER TO EMER SUMP alarm ACTION/CUES:

STUDENT COPY INITIAL CONDITIONS: A large break LOCA has occurred and the BWST level is less than nine feet. Both MU pumps and HPI pumps have been stopped in accordance with DB

-OP-02000 Section 10 and Specific Rule guidance.

DB-OP-02000, Attachment 7, Section 1. Action to close breakers for DH7A, DH7B, DH9A, DH9B, and HP31 has been completed IAW DB

-OP-02000 step 10.3.

DB-OP-02000, Attachment 7, Section 2, Suction Transfer, Steps 1 through 4 ha ve been completed IAW DB

-OP-02000 step 10.11.

INITIATING CU ES: Annunciator "BWST LO

-LO LVL, XFER TO EMER SUMP" (5-3-A) has been received

. The Command SRO directs you to transfer LPI suction to the emergency sump in accordance with DB-OP-02000, Attachment 7, Section 2.

For the purpose of this JPM the Command SRO is not directing the step by step performance of this attachment.

EXAMINER COPY INITIAL CONDITIONS: A large break LOCA has occurred and the BWST level is less than nine feet. Both MU pumps and HPI pumps have been stopped in accordance with DB

-OP-02000 Section 10 and Specific Rule guidance.

DB-OP-02000, Attachment 7, Section 1. Action to close breakers for DH7A, DH7B, DH9A, DH9B, and HP31 has been completed IAW DB

-OP-02000 step 10.3.

DB-OP-02000, Attachment 7, Section 2. Suction Transfer, Steps 1 through 4 has been completed IAW DB

-OP-02000 step 10.11.

INITIATING CUES: Annunciator "BWST LO

-LO LVL, XFER TO EMER SUMP" (5-3-A) has been received

. The Command SRO directs you to transfer LPI suction to the emergency sump in accordance with DB-OP-02000, Attachment 7, Section 2.

For the purpose of this JPM the Command SRO is not directing the step by step performance of this attachment.

(Provide the examinee a copy of DB

-OP-02000, Attachment 7 Section 2. Freeze simulator until examinee is ready to start

-should have time to review)

PERFORMANCE INFORMATION NOTE: Critical steps denoted with a "C". Failure to meet any one of these standards for this item constitutes failure. Sequence is NOT assumed unless denoted in the "Comments".

START TIME:

NOTE: Unfreeze simulator when student has completed procedure review

1. PERFORMANCE STEP: Block SFAS Level 2 on DH 7A, DH 9A, DH 7B and DH 9B. C STANDARD:

Depress BLOCK pushbuttons for DH 7A (HISDH7A1) or DH 9A (HISDH9A) and DH 7B (HISDH7B1) or DH 9B (HISDH9B) and verify all 4 valves are blocked. NOTE: Blocking either DH7A or DH9A will block the other as does DH7B/9B.

CUE: None __________

SAT UNSAT 2. PERFORMANCE STEP: Check BWST Level is less than or equal to 9 feet. STANDARD: Check BWST level < or equal to 9 feet on level indicators. CUE: None __________

SAT UNSAT 3. PERFORMANCE STEP: Open the Containment Emergency Sump Isolation Valves. STANDARD:

Depress the OPEN pushbutton on HIS DH9A. CUE: None __________

SAT UNSAT ALTERNATE PATH - Must recognize DH9A/DH9B did not start opening and the appropriate SFAS Level 5 Output Modules are not tripped as required. This will

require manually tripping the affected Output Modules to allow DH9A/DH9B to be opened.

4. PERFORMANCE STEP: Recognize DH9A does not open.

STANDARD: HIS DH9A green light remains lit.

CUE: Role play as Command SRO if required, Acknowledge DH9A did not open. __________

SAT UNSAT 5. PERFORMANCE STEP: Open DH 9B. STANDARD:

Depress the OPEN pushbutton on HIS DH9B. CUE: None __________

SAT UNSAT 6. PERFORMANCE STEP: Recognize DH9B does not open.

STANDARD: HIS DH9B green light remains lit. CUE: Role play as Command SRO if required, Acknowledge DH9B did not open.

__________

SAT UNSAT 7. PERFORMANCE STEP: Manually trip Train 1 SFAS Level 5 Output Modules. C STANDARD: Depress and release the trip pushbuttons next to L511 and L513.

COMMENT: Step 7 and 8 can be done in either order

.

CUE: Another RO is monitoring conditions for cavitation.

__________

SAT UNSAT 8. PERFORMANCE STEP: Manually trip Train 2 SFAS Level 5 Output Modules. C STANDARD: Depress and release the trip pushbuttons next to L512 and L514.

CUE: None __________

_______________________________________________________________SAT UNSAT__

9. PERFORMANCE STEP: Open DH 9A. C STANDARD:

Depress the OPEN pushbutton on HIS DH9A. CUE: None

__________

SAT UNSAT 10. PERFORMANCE STEP: Verify that DH 9A starts to open. STANDARD:

Check GREEN light OFF on HIS DH9A. CUE: None __________

SAT UNSAT 11. PERFORMANCE STEP: Open DH 9B. C STANDARD:

Depress the OPEN pushbutton on HIS DH9B. CUE: None __________

SAT UNSAT 12. PERFORMANCE STEP: Verify that DH 9B starts to open. STANDARD:

Check GREEN light OFF on HIS DH9B. CUE: None __________

SAT UNSAT 13. PERFORMANCE STEP: Verify that DH 7A starts to close as DH 9A starts to open. STANDARD:

Recognize DH7A starts to close, check RED light OFF on HIS DH7A. CUE: None __________

SAT UNSAT

14. PERFORMANCE STEP: Verify that DH 7B starts to close as DH 9B starts to open.

STANDARD:

Recognize DH7B starts to close, check RED light OFF on HIS DH7B. CUE: None __________

SAT UNSAT 15. PERFORMANCE STEP: Verify the transfer is complete.

STANDARD:

Check the RED indicating lights on HIS DH9A and HIS DH9B are LIT and the GREEN indicating lights on HIS DH7A and HIS DH7B are LIT.

Check low pressure injection flow NOT significantly changed. CUE: None. __________

SAT UNSAT TERMINATING CUES: This JPM is complete (Terminated by the examiner)

__________

END TIME

Simulator JPM S3 Facility:

Davis-Besse Task No: 004-029-05-0100

Task Title

Recover From MU/HPI/PORV Cooling K/A

Reference:

(010) A2.03 4.1/4.2 Job Performance Measure No

S3 (JPM 063) Examinee:

NRC Examiner: Date: Method of testing:

Simulated Performance ___ Actual Performance _X_ Classroom ___ Simulator _X_ Plant ___

Read to the examinee:

I will explain the initial conditions, which steps to simulate or discuss, and provide initiating cues.

When you complete the task successfully, the objective for this job performance measure will be satisfied.

Initial Conditions:

The plant conditions are specified in the Initial Conditions and Initiating Cues.

Task Standard:

Perform Recovery from MU/HPI PORV Cooling and recognize failure of the PORV to close and take immediate actions. Required Materials:

Attachment 25 of DB

-OP-02000, RPS, SFAS, SFRCS Trip, or SG Tube Rupture. General

References:

None Initiating Cue:

The plant conditions are specified in the Initial Conditions and Initiating Cues.

Time Critical Task:

No Alternate Path:

Yes Validation Time:

11 minutes

SIMULATOR INSTRUCTIONS TASK DESCRIPTION: Perform Recovery From MU/HPI PORV Cooling and recognize failure of the PORV to close and take immediate actions.

INITIAL CONDITION: Loss of all Feedwater MU/HPI cooling initiated MDFP feeding both SGs ADDITIONAL SETUP/DEVIATION FROM INITIAL CONDITION: Fail Makeup Pump 2 to start Fail both AFPTs to start

Unfreeze the simulator after the initial cue is given to minimize excessive SCM MALFUNCTIONS/FAILURE TO INSERT: Fail the PORV open ACTIONS/CUES None

EXAMINER COPY INITIAL CONDITIONS: The reactor has tripped All Feedwater was lost Makeup Pump 2 did NOT start Makeup/HPI/PORV Cooling was initiated INITIATING CUES

The MDFP has been started and is feeding both Steam Generators.

A second operator is controlling Steam Generator levels, pressures, and steaming of Steam Generators.

The Unit Supervisor directs you to recover from MU/HPI/PORV Cooling using Attachment 25 of

DB-OP-02000. For the purpose of this JPM the Command SRO is not directing the step by step performance of this attachment.

(Provide 5 of DB

-OP-02000, RPS, SFAS, SFRCS Trip, or SG Tube Rupture)

CANDIDATE COPY INITIAL CONDITIONS: The reactor has tripped All Feedwater was lost Makeup Pump 2 did NOT start Makeup/HPI/PORV Cooling was initiated INITIATING CUES

The MDFP has been started and is feeding both Steam Generators

A second operator is controlling Steam Generator levels and pressures

The Unit Supervisor directs you to recover from MU/HPI/PORV Cooling using Attachment 25 of DB-OP-02000. For the purpose of this JPM the Command SRO is not directing the step by step performance of this attachment.

PERFORMANCE INFORMATION NOTE: Critical steps denoted with a "C". Failure to meet any one of these standards for this item constitutes failure. Sequence is NOT critical unless denoted in the "Comments".

START TIME: _______

1. PERFORMANCE STEP: Establish the letdown flow. ........C........ STANDARD:

Depress OPEN on HISMU2B. COMMENT: Sequence of opening MU 2B, MU 2A and MU 3 NOT critical CUE: If asked for desired flow "Establish 70 gpm" (flow rate not critical)

Note: may establish 140 gpm

__________

SAT UNSAT

2. PERFORMANCE STEP: Establish the letdown flow. ........C........ STANDARD:

Depress BLOCK for MU 2A. Depress OPEN on HISMU2A.

COMMENT: Sequence of opening MU 2B, MU 2A and MU 3 NOT critical CUE: If asked for desired flow "Establish 70 gpm" (flow rate not critical)

Note: may establish 140 gpm

__________

SAT UNSAT 3. PERFORMANCE STEP: Establish the letdown flow

........C........

STANDARD:

Depress BLOCK pushbutton for MU 3. Depress OPEN pushbutton on HISMU3. COMMENT: Sequence of opening MU 2B, MU 2A and MU 3 NOT critical CUE: If asked for desired flow "Establish 70 gpm" (letdown flow rate not critical). Note: may establish 140 gpm __________

SAT UNSAT 4. PERFORMANCE STEP: Open the MU Pumps Minimum Recirc Valves. ........C........ STANDARD:

Depress the OPEN pushbutton on HISMU6407. CUE: None __________

SAT UNSAT

5. PERFORMANCE STEP: Open the MU Pumps Minimum Recirc Valves. STANDARD:

Depress the OPEN pushbutton on HISMU6406. COMMENT: MU 6406 not critical due to MUP 2 not running CUE: None __________

SAT UNSAT 6. PERFORMANCE STEP: IF BOTH MU Pumps are in service perform the following: STANDARD:

Recognize this step does not apply - mark N/A. COMMENT: Only MUP 1 is in service CUE: None __________

SAT UNSAT

7. PERFORMANCE STEP: Isolate the normal MU Injection header. STANDARD:

Depress the CLOSE pushbutton on HISMU6422.

CUE: None __________

SAT UNSAT

8. PERFORMANCE STEP: Establish desired MU flow rate by throttling MU6419. STANDARD:

Depress and hold the CLOSE pushbutton on HIS MU 6419 to throttle the valve closed and reduce flow rate to desired value while maintaining adequate Subcooling Margin.

CUE: (If asked) MU 6423B is open to maintain minimum flow

__________

SAT UNSAT

9. PERFORMANCE STEP: Restore MU Pump Suction.

........C........

STANDARD:

Depress the OFF pushbutton on HISMU6405. CUE: None __________

SAT UNSAT

10. PERFORMANCE STEP: Restore MU Pump Suction.

STANDARD:

Depress the OFF pushbutton on HISMU3971. COMMENT: MU3971 not critical due to MUP 2 not running CUE: None __________

SAT UNSAT

11. PERFORMANCE STEP: IF only MU Pump 2 is in service perform the following. STANDARD:

Recognize this step does not apply - mark N/A. COMMENT: Only MUP 1 is in service CUE: None __________

SAT UNSAT

12. PERFORMANCE STEP: Perform the following to recover RCS Inventory control:

STANDARD:

Maintain Steam Generator levels per specific rule 4. CUE: Balance Of Plant RO is maintaining SG Levels

__________

SAT UNSAT

13. PERFORMANCE STEP: Perform the following to recover RCS Inventory control:

STANDARD:

Reduce HPI Flow to establish a decreasing SCM trend (maintain minimum Subcooling Margin) by throttling HP2A

-D as necessary.

Comment: Two handed operations is authorized for positioning HP2A through HP2D CUE: None __________

SAT UNSAT

14. PERFORMANCE STEP: Perform the following to recover RCS Inventory control:

STANDARD:

Raise letdown flow to maximum available by throttling MU6 and/or placing a second purification demineralizer in service. CUE: If asked for desired flow "Establish 70 gpm" (letdown flow rate not critical). Note: may establish 140 gpm __________

SAT UNSAT

ALTERNATH PATH: RC2A is expected to close. Must recognize PORV did not close and perform actions of the response not obtained column to close the PORV Block Valve.

15. PERFORMANCE STEP: Close the PORV.

STANDARD:

Rotate HIS RC 2A to the AUTO position and Push to Close. Recognize the PORV did NOT close. CUE: None __________

SAT UNSAT

16. PERFORMANCE STEP: Close the PORV Block Valve. ........C........

STANDARD:

Depress the CLOSE pushbutton on HISRC11 and verify it closes.

CUE: None. __________

SAT UNSAT TERMINATING CUES:

This JPM is complete (Terminated by the evaluator)

__________

END TIME Simulator JPM S4 Facility:

Davis-Besse Task No: 059-012-04-0100 Task Title

Main Feed Pump Startup/Transfer to ICS Control K/A

Reference:

(059) A4.10 (3.9/3.8)________

Job Performance Measure No

S4 (JPM New)

Examinee:

NRC Examiner: Date: Method of testing:

Simulated Performance _

__ Actual Performance __

X__ Classroom ___ Simulator _X_ Plant ___

Read to the examinee:

I will explain the initial conditions, which steps to simulate or discuss, and provide initiating cues. When you complete the task successfully, the objective for this job performance measure will be satisfied.

Initial Conditions:

The plant conditions are specified in the Initial Conditions and Initiating Cues.

Task Standard:

Perform steps to place Main Feed Pump in service and emergency trip due to low oil pressure Required Materials:

DB-OP-06901, Plant Startup, signed off through step 3.24 with step 3.25 in progress DB-OP-06224, Main Feed Pump and Turbine, section 3.16, Startup of MFP2, signed off as applicable through step 3.16.43.

DB-OP-06224, Main Feed Pump and Turbine, section 3.17, Transferring MFPT 2 Speed Control Between MDT20 and ICS DB-OP-02010, pages 10 and 11 for Annunciator 10-1-D General

References:

None Initiating Cue:

The plant conditions are specified in the Initial Conditions and Initiating Cues.

Time Critical Task:

No Alternate Path: Yes Validation Time: 9 minutes

SIMULATOR INSTRUCTIONS

TASK DESCRIPTION: Perform steps to place Main Feed Pump in service and emergency trip due to low oil pressure INITIAL CONDITION: Mode 2 with reactor power at 2%. Main Feed Pump 2 startup in progress and ready to transfer to ICS Hand/Auto station control (step 3.16.44 of DB-OP-06224, Main Feed Pump and Turbine). ADDITIONAL SETUP/DEVIATION FROM INITIAL CONDITION: MALFUNCTIONS/FAILURE TO INSERT: Insert low oil pressure #2 MFPT when increasing speed to raise discharge pressure to 1000psig to 1050psig (triggered at approximately 950psig)

ACTION/CUES:

STUDENT COPY INITIAL CONDITIONS: Mode 2 with reactor power at 2%. Main Feed Pump 2 startup in progress and ready to transfer to ICS Hand/Auto station control (step 3.16.44 of DB

-OP-06224, Main Feed Pump and Turbine)

INITIATING CUES: The unit supervisor has directed you to continue with #2 MFP startup starting at step 3.16.44 of DB-OP-06224, Main Feed Pump and Turbine. Transfer #2 MFP to ICS Hand/Auto station control and continue with step 3.26 of DB

-OP-06901, Plant Startup, to transfer feedwater from the MDFP to the MFP.

EXAMINER COPY INITIAL CONDITIONS: Mode 2 with reactor power at 2%. Main Feed Pump 2 startup in progress and ready to transfer to ICS Hand/Auto station control (step 3.16.44 of DB

-OP-06224, Main Feed Pump and Turbine). INITIATING CUES: The unit supervisor has directed you to continue with #2 MFP startup starting at step 3.16.44 of DB-OP-06224, Main Feed Pump and Turbine. Transfer #2 MFP to ICS Hand/Auto station control and continue with step 3.26 of DB

-OP-06901, Plant Startup, to transfer feedwater from the MDFP to the MFP.

(Provide the examinee a copy of the following documents:

DB-OP-06901, Plant Startup, signed off through step 3.24 with step 3.25 in progress DB-OP-06224, Main Feed Pump and Turbine, section 3.16, Startup of MFP2, signed off as

applicable through step 3.16.43.

DB-OP-06224, Main Feed Pump and Turbine, section 3.17, Transferring MFPT 2 Speed Control Between MDT20 and ICS)

PERFORMANCE INFORMATION

NOTE: Critical steps denoted with a "C". Failure to meet any one of these standards for this item constitutes failure. Sequence is NOT assumed unless denoted in the "Comments".

START TIME:

1. PERFORMANCE STEP: Perform section 3.17 of DB

-OP-06224, Main Feed Pump Turbine, and transfer MFPT2 Speed Control from MDT20 to ICS.

STANDARD:

Identify step 3.17

.1 of DB-OP-06224, Main Feed Pump Turbine, for transfer of MFPT2 Speed Control from MDT20 to ICS. CUE: None __________

SAT UNSAT 2. PERFORMANCE STEP: Verify MFPT speed is between 3900 RPM and 5150 RPM STANDARD:

Verify MFPT 2 speed between 3900 RPM and 5150 RPM using indicator SI2708B CUE: None __________

SAT UNSAT 3. PERFORMANCE STEP: Adjust the ICS Bailey Controller output to indicate a zero amp reading on the XFER METER Amp Y1

-806 STANDARD:

Toggle the ICS Bailey Controller speed control, HIC ICS 36A Hand/Auto Station, to indicate a zero amp reading on the XFER METER Amp Y1

-806 CUE: None __________

SAT UNSAT 4. PERFORMANCE STEP: Depress ICS on HIS 806C1

........C........

STANDARD:

Depress ICS on HIS 806C1 CUE: None __________

SAT UNSAT

5. PERFORMANCE STEP: Check that ICS illuminates and the ICS Bailey Controller assumes control of MFPT speed.

STANDARD:

Check that ICS illuminates on HIS 806C1 and that the ICS Bailey Controller

assumes control of MFPT 2 speed.

CUE: None __________

SAT UNSAT 6. PERFORMANCE STEP: If ICS Control is unstable, THEN return to MDT20 Contro

l. STANDARD:

Recognize proper control by the ICS Controller and mark step 3.17.1.e as N/A. CUE: None __________

SAT UNSAT

7. PERFORMANCE STEP: Adjust the MDT20 output to maintain zero amps indicated on the XFER METER Y1

-806.

STANDARD: Maintain zero amps indicated on the XFER METER Y1

-806 by occasional adjustment as needed of the MDT20 output.

COMMENT: Student may consider step 3.17.1.f in progress while continuing MFP startup and not sign as complete.

CUE: None __________

SAT UNSAT 8. PERFORMANCE STEP: Complete section 3.17 of DB

-OP-06224. STANDARD:

Sign and date complete by for section 3.17 of DB

-OP-06224. COMMENT: If student considers step 3.17.1.f to be in progress while continuing MFP startup then section 3.17 will not be signed as complete.

CUE: None __________

SAT UNSAT 9. PERFORMANCE STEP: Sign complete step 3.16.44 of DB-OP-06224. STANDARD:

Sign complete step 3.16.44 of DB-OP-06224.

COMMENT: If student considers step 3.17.1.f to be in progress while continuing MFP startup and section 3.17 is not signed as complete then step 3.16.44 may remain in progress.

Step 3.16.45 would be performed after the MFP is supplying feedwater to the steam generators.

CUE: None

__________

SAT UNSAT 10. PERFORMANCE STEP: Sign compete step 3.25 of DB

-OP-06901, Plant Startup.

STANDARD:

Sign compete step 3.2.5 of DB

-OP-06901, Plant Startup.

COMMENT: Student may continue with step 3.2.5 circled (in progress) because

section of DB

-OP-06224 is not complete until there is flow to the steam

generators and the ARTS Channels test/toggle switches are placed in the operate position at step 3.16.45. CUE: None __________

SAT UNSAT 11. PERFORMANCE STEP:

Raise Main Feed Pump Speed until discharge pressure is

........C........ between 1000 and 1050 psig (step 3.26.1 of DB

-OP-06901). STANDARD:

Raise MFPT 2 speed using manual control of HIC ICS 36A Hand/Auto Station, ICS Bailey Controller, to raise discharge pressure to band of 1000-1050 psig.

NOTE: Alternate Path begins with low oil pressure Annunciator 10-1-D received as discharge pressure is raised (triggered to alarm at approximately 950psig).

CUE: None

__________

SAT UNSAT 12. PERFORMANCE STEP: Identify Annunciator 10-1-D, MFPT 2 LUBE OIL PRESS LO, in alarm. STANDARD:

Recognize annunciator 10-1-D, MFPT 2 LUBE OIL PRESS LO, in alarm and refer to alarm procedure DB

-OP-2010. CUE: If student refers to alarm procedure provide copy of DB-OP-02010 pages 10 and 11 for Annunciator 10-1-D

__________

SAT UNSAT 13. PERFORMANCE STEP: Determine if bearing pressure is actually Low

. STANDARD:

Determine bearing pressure is actually Low (<7 psig) using PI12 56, Header Control Pressure.

CUE: None

__________

SAT UNSAT

14. PERFORMANCE STEP: Verify automatic start of standby MFPT 2 Main Oil Pump.

........C........

COMMENT: The standby MFPT 2 Main Oil Pump will not auto start. The pump will start manually and almost immediately trip on electrical fault.

STANDARD:

Identify standby MFPT 2 Main Oil Pump is not running and start standby MFPT 2 Main Oil Pump.

CUE: None

__________

SAT UNSAT 15. PERFORMANCE STEP: If Bearing Header Pressure decreases to less than 4 psig THEN

........C........

start the Emergency Bearing Oil Pump and trip MFPT 2.

STANDARD:

Identify Bearing Header Pressure decreases to less than 4 psig using PI1256. Start the Emergency Bearing Oil Pump (HIS1188). CUE: None

__________

SAT UNSAT 16. PERFORMANCE STEP: If Bearing Header Pressure decreases to less than 4 psig THEN

........C........ start the Emergency Bearing Oil Pump and trip MFPT 2.

STANDARD:

Trip MFPT 2 using HS 798 trip push button.

CUE: None

__________

SAT UNSAT TERMINATING CUES:

This JPM is complete. (Terminated by the examiner) __________

END TIME

Simulator JPM S5 Facility:

Davis-Besse Task No: 334-018-04-0300 Task Title

Establish Containment Closure K/A

Reference:

(103) A3.01 3.9/4.2 Job Performance Measure No: S5 (JPM 219) Examinee:

NRC Examiner: Date: Method of testing:

Simulated Performance ___ Actual Performance _X_ Classroom ___ Simulator _X_ Plant ___

Read to the examinee:

I will explain the initial conditions, which steps to simulate or discuss, and provide initiating cues. When you complete the task successfully, the objective for this job performance measure will be satisfied.

Initial Conditions:

The plant conditions are specified in the Initial Conditions and Initiating Cues.

Task Standard:

Establish Containment Closure Required Materials:

DB-OP-06904, Shutdown Operations, Section 11

General

References:

Db-OP-02000 Initiating Cue:

The plant conditions are specified in the Initial Conditions and Initiating Cues.

Time Critical Task:

No Alternate Path:

No Validation Time: 8 minutes

SIMULATOR INSTRUCTIONS TASK DESCRIPTION: Establish Containment closure INITIAL CONDITION: Initialize to special IC 116 OR MODE 5 IC with DH Loop 2 operating and CTMT Purge in operation on CTMT ADDITIONAL SETUP/DEVIATION FROM INITIAL CONDITION: Manually de

-energize A and B buses to simulate a loss of offsite power followed by restoration of offsite power.

Emergency Shutdown #1 EDG

irf g529g Energize D2 Bus from D1 Bus to restore Instrument Air MALFUNCTIONS/FAILURE TO INSERT: DH Pump #2 breaker fail open

imf bdp2c

CTMT Purge Valves CV5005 and CV5008 fail open

imf cav9c imf cavfc ACTION/CUES:

7. ROLE PLAY as Field Supervisor or other OPS WSC to report that all LLRTs are terminated and isolated.
8. ROLE PLAY as Field Supervisor or other OPS WSC to report that all personnel assigned specific Containment Closure responsibilities are carrying out the required actions.

EXAMINER COPY INITIAL CONDITIONS: The plant was in MODE 5 with Decay Heat Loop 2 operating when a loss of offsite power occurred.

EDG #1 tripped and efforts to restart it have been unsuccessful.

EDG #2 is providing power to D1 and D2 Buses.

Decay Heat Pump 2 breaker would not re

-close after D1 power was restored. Maintenance is investigating.

INITIATING CUES: The Shift Manager directs you to establish Containment Closure in accordance with step 11.1.5 of DB-OP-06904 Shutdown Operations (required by DB

-OP-02527, Loss of Decay Heat Removal).

(Provide section 11 of DB

-OP-06904)

CANDIDATE COPY INITIAL CONDITIONS: The plant was in MODE 5 with Decay Heat Loop 2 operating when a loss of offsite power occurred.

EDG #1 tripped and efforts to restart it have been unsuccessful.

EDG #2 is providing power to D1 and D2 Buses.

Decay Heat Pump 2 breaker would not re

-close after D1 power was restored. Maintenance is investigating.

INITIATING CUES: The Shift Manager directs you to establish Containment Closure in accordance with step 11.1.5 of DB-OP-06904 Shutdown Operations (required by DB

-OP-02527, Loss of Decay Heat Removal).

PERFORMANCE INFORMATION NOTE: Critical steps denoted with a "C". Failure to meet any one of these standards for this item constitutes failure. Sequence is NOT critical unless denoted in the "Comments".

START TIME: _______

1. PERFORMANCE STEP:

Locate the correct procedure step.

STANDARD:

Finds step 11.1.5.

CUE: None

___________

SAT UNSAT 2. PERFORMANCE STEP: Announce Containment Closure over the Gaitronics.

STANDARD: Use Gaitronics to announce the following:

"Attention all station personnel, attention all station personnel. All assigned personnel establish containment closure immediately. All assigned personnel establish containment closure immediately."

CUE: None ___________

SAT UNSAT

3. PERFORMANCE STEP:

Verify Containment Purge is shut down.

STANDARD:

Visual check of Containment Purge supply and Exhaust Fan control switch indications indicate fans are shutdown

.

COMMENT: If system procedure for shutdown is referenced the Containment Purge containment isolation valves will be directed to be closed. Performance steps 5 and 7 would be used to evaluate.

CUE: None ___________

SAT UNSAT

4. PERFORMANCE STEP: Perform selected isolation of SFAS Containment

Penetrations STANDARD:

Refers to DB

-OP-02000 Table 2, SFAS Actuated Equipment, and isolate containment penetrations able to be positioned from control room to establish containment closure. CUE: Shift Manager directs you to refer to DB

-OP-02000 Table 2, SFAS Actuated Equipment, and isolate Level 1 and Level 2 containment penetrations able to be positioned from control room.

(Provide clean copy of table 2)

___________

SAT UNSAT 5. PERFORMANCE STEP:

Close Channel 1 SFAS Level 1 Containment Purge ........C........ Isolation Valves STANDARD:

Press CLOSE on the following switches:

CV 5008 CTMT PURGE OUT CV 5006 CTMT PURGE IN COMMENT: CV 5008 will NOT close due to failure. Critical to close CV 5007 CTMT PURGE OUT Channel 2 in Performance Step 7 to isolate this penetration.

Critical to close CV 5006 to isolate this penetration due to failure of CV 5005 CUE: None ___________

SAT UNSAT 6. PERFORMANCE STEP:

Close Channel 2 SFAS Level 1 Containment

........C........ Air Sample Isolation Valves

STANDARD: Press CLOSE on the following switches:

CV 5010A CTMT AIR SAMPLE CV 5010B CTMT AIR SAMPLE CV 5010C CTMT AIR SAMPLE CV 5010D CTMT AIR SAMPLE CV 5010E CTMT AIR SAMPLE RET COMMENT: CV5010E is not critical because of check valve CV125.

CUE: None _________

SAT UNSAT

7. PERFORMANCE STEP:

Close Channel 2 SFAS Level 1 Containment Purge ........C........

Isolation Valves STANDARD:

Press CLOSE on the following switches:

CV 5007 CTMT PURGE OUT CV 5005 CTMT PURGE IN COMMENT: Critical to close CV 5007 CTMT PURGE OUT to isolate this penetration due to CV 5008 failure.

CV 5005 will NOT close due to failure. Critical to close CV 5006 CTMT PURGE OUT Channel 1 in Step 5 to isolate this penetration.

CUE: None

___________

SAT UNSAT

8. PERFORMANCE STEP:

Close Channel 2 SFAS Level 2 Containment Vacuum Relief Valve Isolation Valves STANDARD:

Press CLOSE on the following switches:

CV 5075 CTMT VAC RLF VLV ISO CV 5076 CTMT VAC RLF VLV ISO CV 5077 CTMT VAC RLF VLV ISO CV 5078 CTMT VAC RLF VLV ISO CV 5079 CTMT VAC RLF VLV ISO COMMENT: Not critical due to check valves isolating penetration.

CUE: None

___________

SAT UNSAT

9. PERFORMANCE STEP:

Verify that all LLRTs are terminated and isolated.

STANDARD:

Communication with Field Supervisor.

CUE: (If asked) The Field Supervisor is verifying that all LLRTs are isolated.

___________

SAT UNSAT

10. PERFORMANCE STEP:

Verify that the personnel assigned specific Containment Closure responsibilities are carrying out the required actions.

STANDARD: Communication with Field Supervisor.

CUE: (If asked) The Field Supervisor is verifying that the personnel assigned . specific Containment Closure responsibilities are carrying out the required

actions. ___________

SAT UNSAT TERMINATING CUES: This JPM is complete.

(Terminated by the examine e). __________

END TIME Simulator JPM S6 Facility:

Davis-Besse Task No: 063-007-04-0100 Task Title

Battery Load Shed Actions from the Control Room K/A

Reference:

(063) K1.03 (2.9/3.5)

_________

Job Performance Measure No

S6 (JPM New) Examinee:

NRC Examiner: Date: Method of testing:

Simulated Performance _

__ Actual Performance __X__ Classroom ___ Simulator _X_ Plant ___

Read to the examinee:

I will explain the initial conditions, which steps to simulate or discuss, and provide initiating cues.

When you complete the task successfully, the objective for this job performance measure

will be satisfied.

Initial Conditions: The plant conditions are specified in the Initial Conditions and Initiating Cues.

Task Standard:

Perform control room actions for section 1 of attachment 5, Selective Battery Load Shedding, per DB-OP-02521, Loss of AC Bus Power Sources. Required Materials:

Copy of attachment 5, Selective Battery Load Shedding, of DB-OP-02521, Loss of AC Bus Power Sources General

References:

None Initiating Cue:

The plant conditions are specified in the Initial Conditions and Initiating Cues.

Time Critical Task:

Yes Alternate Path:

No Validation Time:

8 minutes SIMULATOR INSTRUCTIONS

TASK DESCRIPTION: Perform section 1 of Selective Battery Load Shedding per DB-OP-02521, Loss of AC Bus Power Sources INITIAL CONDITION: Mode 3 with Loss of Both Essential 4160 AC Bus Power Sources ADDITIONAL SETUP/DEVIATION FROM INITIAL CONDITION:

MALFUNCTIONS/FAILURE TO INSERT:

ACTION/CUES:

STUDENT COPY INITIAL CONDITIONS: Mode 3 with Loss of Both Essential 4160 AC Bus Power Sources INITIATING CUES: The plant has tripped due to a Loss of Off

-Site Power. Maintenance is in progress on EDG 1 and EDG 2 locked out upon startup. Efforts to start the SBODG have been unsuccessful. Both C1 and D1 remain deenergized, and have been for 15 minutes. The Unit Supervisor directs you to perform section 1 of Attachment 5, Selective Battery Load Shedding, from DB

-OP-02521, Loss of AC Bus Power Sources. An operator has been just been dispatched to perform attachment 14 per step 2 of attachment 5.

This is a time critical task. I will inform you when the time critical clock starts.

EXAMINER COPY INITIAL CONDITIONS: Mode 3 with Loss of Both Essential 4160 AC Bus Power Sources INITIATING CUES: The plant has tripped due to a Loss of Off

-Site Power. Maintenance is in progress on EDG 1 and EDG 2 locked out upon startup. Efforts to start the SBODG have been unsuccessful. Both C1 and D1 remain deenergized, and have been for 15 minutes.

The Unit Supervisor directs you to perform section 1 of Attachment 5, Selective Battery Load Shedding, from DB

-OP-02521, Loss of AC Bus Power Sources.

An operator has been just been dispatched to perform attachment 14 per step 2 of attachment 5.

This is a time critical task. I will inform you when the time critical clock starts. (Provide examinee a copy of DB-OP-02521, Loss of AC Bus Power Sources, Attachment 5, Selective Battery Load Shedding)

PERFORMANCE INFORMATION

NOTE: Critical steps denoted with a "C". Failure to meet any one of these standards for this item constitutes failure. Sequence is NOT assumed unless denoted in the "Comments".

START TIME:

Time Critical Clock is started when they assume control of the Job Performance Measure.

CUE: 15 minutes has elapsed since the lo ss of power to C1 and D1 Busses.

Time Critical Clock starts now.

TIME CRITICAL CLOCK START TIME:

1. PERFORMANCE STEP: Perform step 1.a to STOP and LOCKOUT .......C........

the following pumps STANDARD:

Stop and lockout Main Feed Pump 1 EBOP (HIS 1209, EMER BEARING OIL PUMP) CUE: None __________

SAT UNSAT 2. PERFORMANCE STEP: Perform applicable step of section 1.a to STOP and LOCKOUT .......C........

the following pumps STANDARD:

Stop and lockout Main Feed Pump 2 EBOP (HIS 1188, EMER BEARING OIL PUMP)

CUE: None __________

SAT UNSAT

3. PERFORMANCE STEP:

Perform applicable step of section 1.a to STOP and LOCKOUT

.......C........ the following pumps

STANDARD:

Stop and Lockout Makeup Pump 1 DC Oil Pump (HIS

-MU24A2). CUE: None __________

SAT UNSAT 4. PERFORMANCE STEP: Perform applicable step of section 1.a to STOP and LOCKOUT

.......C........ the following pumps STANDARD:

Stop and lockout Makeup Pump 2 DC Oil Pump (HIS

-MU24B2). CUE: None __________

SAT UNSAT 5. PERFORMANCE STEP: Perform applicable step of section 1.a to STOP and LOCKOUT

.......C........ the following pumps STANDARD:

Stop and lockout RCP 1-1 DC Oil Lift Pump (HIS 4115).

CUE: None __________

SAT UNSAT 6. PERFORMANCE STEP: Perform applicable step of section 1.a to STOP and LOCKOUT

........C........

the following pumps STANDARD:

Stop and lockout RCP 1-2 DC Oil Lift Pump (HIS 4215).

CUE: None __________

SAT UNSAT 7. PERFORMANCE STEP: Perform applicable step of section 1.a to STOP and LOCKOUT

........C........

the following pumps STANDARD:

Stop and lockout RCP 2-1 DC Oil Lift Pump (HIS 4315)

CUE: None __________

SAT UNSAT 8. PERFORMANCE STEP: Perform applicable step of section 1.a to STOP and LOCKOUT

........C........

the following pumps

STANDARD:

Stop and lockout RCP 2-2 DC Oil Lift Pump (HIS 4415)

CUE: None __________

SAT UNSAT Time Performance Steps 1

-8 are complete TIME CRITICAL CLOCK END TIME:

Time requirement is 15 minutes or less from start of TIME CRITICAL CLOCK Start Time

__________

SAT UNSAT

9. PERFORMANCE STEP: Dispatch an Operator to perform Attachment 14, Severe Battery Load Shed - In Plant Actions.

STANDARD:

Initial Conditions stated an operator has been dispatched to perform attachment 14.

CUE: If needed

The Unit Supervisor has assigned an operator to perform Attachment 14, Severe Battery Load Shed - In Plant Actions __________

SAT UNSAT 10. PERFORMANCE STEP: Establish Manual Control of Auxiliary Feedwater

- Place ........C........ AF6452, AFW 1 LEVEL CONTROL VALVE, in MANUAL STANDARD:

Depress manual on level controller LIC6452, AFP 1 Level Controller

COMMENT: Manual control of Auxiliary Feedwater can be established for both trains in either order or in parallel as steps are bulleted. Intent of this JPM is to establish manual control for train 1. CUE: None __________

SAT UNSAT 11. PERFORMANCE STEP:

Establish Manual Control of Auxiliary Feedwater

- Slowly ........C........

open AFW 1 LEVEL CONTROL VALVE in MANUAL while

reducing AFPT 1 speed using the AFPT 1 GOVERNOR CONTROL until AF6452 is full open.

STANDARD:

Depress open on LIC6452, AFP 1 Level Controller, to slowly open AF6452, AFP Level Control Valve, while maintaining OTSG 1 level (49" setpoint) by reducing speed on AFPT 1 speed using HIS520A, AFPT 1 GOVERNOR CONTROL, until AF6452 is full open

. CUE: None

__________

SAT UNSAT 12. PERFORMANCE STEP: Establish Manual Control of Auxiliary Feedwater

- Maintain SG .......C........ 1 at required level by adjusting AFPT 1 GOVERNOR

CONTROL as necessary.

STANDARD:

Adjust AFP 1 speed as necessary to maintain desired level (49" setpoint) using HIS520A, AFPT 1 GOVERNOR CONTROL.

CUE: None

__________

SAT UNSAT TERMINATING CUES:

This JPM is complete. (Terminated by the examiner once level control is established) __________

END TIME

Simulator JPM S7 Facility:

Davis-Besse Task No: 012-003-01-0100 Task Title

Deenergize/Reenergize Source Range NIs K/A

Reference:

(012) A4.02 3.3/3.4 Job Performance Measure No

S7 (JPM 185) Examinee:

NRC Examiner: Date: Method of testing:

Simulated Performance ___ Actual Performance _X_ Classroom ___ Simulator _X_ Plant ___

Read to the examinee:

I will explain the initial conditions, which steps to simulate or discuss, and provide initiating cues.

When you complete the task successfully, the objective for this job performance measure will be satisfied.

Initial Conditions:

The plant conditions are specified in the Initial Conditions and Initiating Cues.

Task Standard: Deenergize Source Range NIs Reenergize Source Range NIs

Required Materials:

DB-OP-06403, Reactor Protection System (RPS) and Nuclear Instrumentation System (NI) Operating Procedure, section 4.4

General

References:

None Initiating Cue:

The plant conditions are specified in the Initial Conditions and Initiating Cues.

Time Critical Task:

No Alternate Path:

No Validation Time: 6 minutes

SIMULATOR INSTRUCTIONS TASK DESCRIPTION

Deenergize/Reeneregize Source Range NIs INITIAL CONDITION: Approximately 5% power ADDITIONAL SETUP/DEVIATION FROM INITIAL CONDITION: None MALFUNCTIONS/FAILURE TO INSERT: Fail NI 3: IMF R3V3 ACTION/CUES: Delete the NI 3 failure when both Source Range Instruments are deenergized: DMF R3V3 EXAMINER COPY INITIAL CONDITIONS: A plant startup is in progress The plant is at approximately 5% power A failure has caused the Source Range NIs to energize INITIATING CUES
The Unit Supervisor directs you to deenergize the Source Range NIs in accordance with section 4.4 of DB

-OP-06403, RPS and NI Operating Procedure. (Hand a copy of section 4.4 of DB

-OP-06403 to examinee)

CANDIDATE COPY INITIAL CONDITIONS: A plant startup is in progress The plant is at approximately 5% power A failure has caused the Source Range NIs to energize INITIATING CUES

The Unit Supervisor directs you to deenergize the Source Range NIs in accordance with section 4.4 of DB

-OP-06403, RPS and NI Operating Procedure.

PERFORMANCE INFORMATION NOTE: Critical steps denoted with a "C". Failure to meet any one of these standards for this item constitutes failure. Sequence is NOT critical unless denoted in the "Comments".

START TIME: _______

1. PERFORMANCE STEP: Unlock and open RPS Channel 1 and 2 doors.

STANDARD:

Keys obtained and RPS Channels I and 2 doors unlocked and opened. CUE: (If necessary) The Control Room acknowledges RPS doors will be open and annunciator alarm received

__________

SAT UNSAT 2. PERFORMANCE STEP: Place ON-OFF switch for the Source Range Detector Power

........C........ Supply Module in OFF. STANDARD: Place ON

-OFF switch for NI 1 power supply to OFF (RPS Channel 2).

COMMENT: May deenergize NI 2 before NI 1

. CUE: None __________

SAT UNSAT 3 PERFORMANCE STEP: Place ON-OFF switch for the Source Range Detector Power

........C........ Supply Module in OFF.

STANDARD:

Place ON-OFF switch for NI 2 power supply to OFF (RPS Channel 1). CUE: (After both SR NIs are deenergized and the NI 3 failure is deleted) The failure has been repaired. The Unit Supervisor directs you to continue in section 4.4 of DB-OP-06403 and reenergize Source Range NIs 1 and 2

__________

SAT UNSAT 4. PERFORMANCE STEP: Place ON-OFF switch for the Source Range Detector Power

........C........ Supply Module in ON. STANDARD:

Places ON

-OFF switch for NI 1 power supply to ON.

COMMENT: May reenergize NI 2 before NI 1 CUE: None __________

SAT UNSAT

5. PERFORMANCE STEP: Place ON-OFF switch for the Source Range Detector Power

........C........ Supply Module in ON. STANDARD: Places ON

-OFF switch for NI 2 power supply to ON

. CUE: None __________

SAT UNSAT 6. PERFORMANCE STEP: Depress the RESET switch on the Source Range Detector Power ........C........ Supply Module. COMMENT:

Depressing reset switch will reset the trip to allow the detector to reenergize when required. With Intermediate Range NIs above the cutout value the Source Range Detector will not energize

. STANDARD:

Depress the RESET switch on NI 1 Power Supply Module. CUE: None __________

SAT UNSAT 7. PERFORMANCE STEP: Depress the RESET switch on the Source Range Detector Power ........C........ Supply Module. COMMENT: Depressing reset switch will reset the trip to allow the detector to reenergize when required. With Intermediate Range NIs above the cutout value the Source Range Detector will not energize

. STANDARD:

Depress the RESET switch on NI 2 Power Supply Module. CUE: None __________

SAT UNSAT 8. PERFORMANCE STEP: Complete procedure section. STANDARD:

Determine step 4.4.3.c to be not applicable and sign/date completed by. CUE: None __________

SAT UNSAT 9. PERFORMANCE STEP: Lock the doors and return keys.

STANDARD:

Doors locked and key returned. CUE: None __________

SAT UNSAT TERMINATING CUES: This JPM is complete (Terminated by the examinee)

__________

END TIME

Simulator JPM S8 Facility:

Davis-Besse Task No:

008-004-01-0100 Task Title

Component Cooling Water Pump Rotation K/A

Reference:

(008) A4.01 3.3/3.1 Job Performance Measure No

S8 (JPM 018) Examinee:

NRC Examiner: Date: Method of testing:

Simulated Performance ___ Actual Performance _X_ Classroom ___ Simulator _X_ Plant ___

Read to the examinee:

I will explain the initial conditions, which steps to simulate or discuss, and provide initiating cues. When you complete the task successfully, the objective for this job performance measure

will be satisfied.

Initial Conditions:

The plant conditions are specified in the Initial Conditions and Initiating Cues.

Task Standard:

Place Component Cooling Water Pump 2 in service from standby condition and place Component Cooling Water Pump 1 (initially running) in standby.

Required Materials:

Section 3.2, 3.9, and 3.16 of DB-OP-06262, CCW System Procedure Limits and Precautions for DB

-OP-06262 General

References:

None

Initiating Cue:

The plant conditions are specified in the Initial Conditions and Initiating Cues.

Time Critical Task:

No Alternate Path:

No Validation Time: 30 minutes SIMULATOR INSTRUCTIONS TASK DESCRIPTION

Place Component Cooling Water Pump 2 in service from standby condition and place Component Cooling Water Pump 1 (initially running) in standby.

INITIAL CONDITION: Mode 1 CCW Pump 1 placed I/S to support testing which has been completed. Makeup Pump 1 left in service and Service Water secondaries left on SW loop 1 (SW1399 open) due to short duration of test. ADDITIONAL SETUP/DEVIATION FROM INITIAL CONDITION: CCW pump 1 running.

Hang tags for CCW and SW pumps 3 being aligned to side 2.

Makeup pump 1 running.

SW 1399 Open and SW 1395 Closed.

MALFUNCTIONS/FAILURE TO INSERT: None ACTION/CUES:

EXAMINER COPY INITIAL CONDITIONS: Plant is in Mode

1. CCW Pump 1 placed I/S to support testing which has been completed. Makeup Pump 1 left in service and Service Water secondaries left on SW loop 1 (SW1399 open) due to short duration of test. NO maintenance work has been done on the CCW System.

INITIATING CUES: Testing is complete and the Unit Supervisor directs you to shift CCW pumps so that CCW Pump 2 is in service and CCW Pump 1 is in standby, in accordance with Section 3.2 and 3.9 of DB-OP-06262, CCW System Procedure.

Valve testing is not required to be performed.

(Provide student a copy of Section 3.2, 3.9, 3.16, and Limits and Precautions of DB-OP-06262, CCW System Procedure. The procedure is signed off with briefing complete, applicable prerequisites signed off, and some steps pre

-identified that will not be applicable)

CANDIDATE COPY INITIAL CONDITIONS: Plant is in Mode

1. CCW Pump 1 placed I/S to support testing which has been completed. Makeup Pump 1 left in service and Service Water secondaries left on SW loop 1 (SW1399 open) due to short duration of test. NO maintenance work has been done on the CCW System.

INITIATING CUES: Testing is complete and the Unit Supervisor directs you to shift CCW pumps so that CCW Pump 2 is in service and CCW Pump 1 is in standby, in accordance with Section 3.2 and 3.9 of DB-OP-06262, CCW System Procedure.

Valve testing is not required to be performed.

PERFORMANCE INFORMATION NOTE: Critical steps denoted with a "C". Failure to meet any one of these standards for this item constitutes failure. Sequence is NOT critical unless denoted in the "Comments".

START TIME: _______

1. PERFORMANCE STEP:

Locate the correct procedure section.

STANDARD:

Identifies Section 3.2 (Component Cooling Water System) as correct procedure section.

COMMENT: Hand procedure to examinee. Sequence required for all steps, except steps 7, 8, 12, 13, 17, 18, 19 and 20.

CUE: None __________

SAT UNSAT

2. PERFORMANCE STEP:

Verify Open SW38, CCW Heat Exchanger 1

-2 Discharge Iso.

STANDARD:

Contact an EO to verify position of SW38.

CUE: If EO contacted SW38, CCW Heat Exchanger 1

-2 Discharge Iso., is OPEN.

__________

SAT UNSAT

3. PERFORMANCE STEP:

Start CCW Pump 1-2. ........C........

STANDARD:

Turn HIS1418 clockwise to CLOSE.

COMMENT: Annunciator 11-5-B, CCW Pump 2 Flow LO, will alarm. It may be treated

as an expected alarm as continuing with the procedure will clear the low flow condition.

CUE: If asked, as EO report flow on FIS 1432 is 2800 gpm __________

SAT UNSAT

5. PERFORMANCE STEP:

Adjust CCW Heat Exchanger Temperature control valve to 80F to 85F OR as directed by the Shift Manager. STANDARD:

Prerequisites identify Shift Manager desire of 85ºF set point of TIC1434.

Contact an EO to obtain set point of 85ºF on TIC1434.

CUE: If needed

, Shift Manager desires a set point of 85ºF on TIC1434.

__________

SAT UNSAT 6. PERFORMANCE STEP:

Route to Section 3.16.

STANDARD:

Route to Section 3.16 and complete prerequisite steps 3.16.1 and 3.16.2.

CUE: None. __________

SAT UNSAT 7. PERFORMANCE STEP:

Open CC2649 Aux Bldg Return.

........C........

STANDARD:

Depress the OPEN pushbutton on HIS2649.

COMMENT: Sequence not required for steps 7 and 8 CUE: None. __________

SAT UNSAT 8. PERFORMANCE STEP:

Open CC5098, CTMT Bldg Return. ........C........

STANDARD:

Depress the OPEN pushbutton on HIS5098.

COMMENT: Sequence not required for steps 7 and 8 CUE: None. __________

SAT UNSAT 9. PERFORMANCE STEP:

OPEN CC5096, CCW Line 2 Discharge Isolation, when return ........C........ valves are open.

STANDARD:

Depress the OPEN pushbutton on CC5096.

CUE: None. __________

SAT UNSAT

10. PERFORMANCE STEP:

Verify CC1469, CCW from DH Cooler 2 Outlet valve is closed.

STANDARD:

If open depress the CLOSE pushbutton on HIS1469.

COMMENT: CC1469 may have been opened if actions for annunciator 11-5-B, CCW Pump 2 Flow LO, were performed at performance step 3.

CUE: None. __________

SAT UNSAT 11. PERFORMANCE STEP:

Close CC5095 Non

-essen supply.

........C........

STANDARD:

Depress the CLOSE pushbutton on HIS5095. CUE: None. __________

SAT UNSAT

12. PERFORMANCE STEP:

Close CC2645 Aux Bldg Return.

........C........

STANDARD:

Depress the CLOSE pushbutton on HIS2645 Aux Bldg Return.

COMMENT: Sequence not required for steps 12 and 13 CUE: None. __________

SAT UNSAT

13. PERFORMANCE STEP:

Close CC 5097 CTMT Bldg Return.

........C........

STANDARD:

Depress the CLOSE pushbutton on HIS5097 CTMT Bldg Return.

COMMENT: Sequence not required for steps 12 and 13 CUE: None. __________

SAT UNSAT 14. PERFORMANCE STEP:

Determine CCW Pump 1 discharge flow less than 3000 gpm as verified as read on FIS 1422 (local).

STANDARD:

Contact EO to report CCW 1 flow indication.

COMMENT: Annunciator 11-4-B, CCW PMP 1 FLOW LO, will alarm at < 3000 gpm.

CUE: If EO contacted CCW Pump 1 Flow on FIS 1422 is 2800 gpm . __________

SAT UNSAT 15. PERFORMANCE STEP:

Open CC1467, CCW from DH Cooler 1 Outlet valve.

STANDARD:

Depress the OPEN pushbutton on HIS1467.

CUE: None. __________

SAT UNSAT 16. PERFORMANCE STEP:

Verify that CCW Pump 2 has a discharge flow greater than 3000 gpm as read on FIS 1432 (locally).

STANDARD:

Contact EO to report CCW flow indication.

CUE: If EO contacted CCW Pump 2 Flow on FIS 1432 is 7200 gpm. __________

SAT UNSAT 17. PERFORMANCE STEP:

Route back to section 3.2.

STANDARD:

Sign complete for section 3.16. Route to step 3.2.17 and sign complete.

CUE: None. __________

SAT UNSAT 18. PERFORMANCE STEP:

If CC1469 was open to provide minimum flow requirement then monitor Decay Heat Pump 2 suction pressure.

STANDARD:

If CC1469 was open to provide minimum flow requirement then contact EO to monitor Decay Heat Pump 2 suction pressure using PI1538 per step 3.2.19 of DB-OP-06262. COMMENT: Step 3.2.18 is not applicable. Step 3.2.19 may be applicable if CC1469 was opened per alarm procedure response, requiring monitoring of Decay Heat Pump 2 suction pressure.

CUE: (If necessary) Monitor Decay Heat Pump 2 suction pressure using PI1538 per step 3.2.19 of DB

-OP-06262. __________

SAT UNSAT 19. PERFORMANCE STEP:

Verify SW1434, CCW Heat Exchanger 2 Control Valve is operating to maintain proper temperature.

STANDARD:

Contact EO to report status of TIC 1434. Verify TI 1490 indicates approximately 85ºF. CUE: As EO (If necessary) TIC 1434 is controlling CCW train 2 temperature at 85ºF. __________

SAT UNSAT

20. PERFORMANCE STEP:

Verify surveillance tests are not required.

STANDARD:

Contact Unit Supervisor.

Per initiating cues valve testing is not required.

COMMENT: Steps 3.2.21 through 3.2.25 are not applicable

. CUE: None __________

SAT UNSAT 21. PERFORMANCE STEP:

Verify Makeup Pump 1 is in service.

STANDARD: Verify HIS MU24B indicates Makeup Pump 1 is running.

CUE: None. __________

SAT UNSAT 22. PERFORMANCE STEP:

Route to Section 3.9.

STANDARD:

Route to Section 3.9.

CUE: None. __________

SAT UNSAT 23. PERFORMANCE STEP:

Verify that EDG 1, LPI pump 1 and HPI pump 1 are not operating.

STANDARD:

Monitor control board for status of EDG 1, LPI 1 and HPI

1. Complete

Prerequisites. CUE: None. __________

SAT UNSAT 24. PERFORMANCE STEP:

Verify SW1424, CCW Heat Exchanger Outlet 1 valve, is closed or 15 minutes have elapsed since the heat load has been removed.

STANDARD:

Check that SW1424 has green light lit or 15 minutes have elapsed.

CUE: (If necessary) 15 minutes has elapsed since the heat loads have been removed. __________

SAT UNSAT

25. PERFORMANCE STEP:

Stop CCW Pump 1.

........C........

STANDARD:

Position HIS1414 to TRIP.

CUE: None. __________

SAT UNSAT

26. PERFORMANCE STEP:

Set TIC1424 as directed by the Shift Manager in prerequisite step 3.9.3 STANDARD:

Contact EO to slowly adjust TIC1424 to 110F.

CUE: TIC1424 is set to 110F.

__________

SAT UNSAT 27. PERFORMANCE STEP:

Verify CC 1467, CCW from DH Cooler 1 Outlet valve, is closed.

STANDARD:

If CC1467 is open, press closed on HIS1467.

CUE: None. __________

SAT UNSAT TERMINATING CUES:

This JPM is complete. (Terminated by the examiner)

__________

END TIME