Text

NUREG-1021, Revision 11 Rev 1 ES-301 Control Room/In-Plant Systems Outline Form ES-301-2 Facility: Davis Besse Nuclear Power Station Date of Examination: 2/1/2021 to 2/5/2021 Exam Level: RO SRO(I) SRO(U)

Operating Test No.: DB1LOT21 Control Room Systems@ (8 for RO); (7 for SRO-I); (2 or 3 for SRO-U)

System / JPM Title Type Code*

Safety Function S1 006 / Establish long term boron dilution (006 A4.07)

A, D, E, EN, L

2 S2 061 / Initiate and Isolate SFRCS and perform actions for an AFW Pump Trip (061 A2.04)

A, N, E, L 4S S3 012 / Place all four RPS Channels in Shutdown Bypass (012 A4.03)

D, L 7

In-Plant Systems@ (3 for RO); (3 for SRO-I); (3 or 2 for SRO-U)

System / JPM Title Type Code*

Safety Function P1 064 / Energizing SBODG Auxiliaries (064 A2.12)

A, E, D 6

P2 068 / Complete Primary RO Actions outside CTRM for Serious CTRM Fire (068 AA1.21)

D, R 8

All RO and SRO control room (and in-plant) systems must be different and serve different safety functions; all 5 SRO-U systems must serve different safety functions; in-plant systems and functions may overlap those tested in the control room.

  • Type Codes Criteria for RO / SRO-I / SRO-U (A)lternate Path (C)ontrol room (D)irect from bank (E)mergency or abnormal in-plant (EN)gineered safety feature (L)ow-power / Shutdown (N)ew or (M)odified from bank including 1(A)

(P)revious 2 exams (R)CA (S)imulator 4-6 / 4-6 / 2-3 9 / 8 / 4 1 / 1 / 1 1 / 1 / > 1 (control room system) 1 / 1 / 1 2 / 2 / 1 3/ 3 / 2 (randomly selected) 1 / 1 / 1