Form 2.1-1 Examination Prep Checklist
ML24045A071
Person / Time
Site: Davis Besse Cleveland Electric icon.png
Issue date: 01/29/2024
From:
NRC/RGN-III
To:
Energy Harbor Nuclear Corp
Greg Roach
Shared Package
ML22251A151 List:
References
L-24-029
Download: ML24045A071 (1)


Text

Form 2.1-1 Examination Preparation Checklist Facility: Davis Besse Date of Examination: January 2024 Developed by: Written:

Facility NRC

//

Operating:

Facility NRC Days from Exam Date Task Description CEs Initials

-240 07/01/22

1. Examination administration date confirmed (A.1-5). For NRC-prepared examinations, arrangements are made for the facility licensee to submit reference materials (B.4, C.4.g and F).

GMR

-210 7/01/22

2. NRC examiners and facility licensee contact assigned (B.1 and C.1-3).

GMR

-210 6/12/23

3. Facility licensee contact briefed on examination security and other requirements (D.4).

As applicable, the facility licensee contact submits to the NRC any prescreened K/As for elimination from the written examination outline, with a description of the facility licensees prescreening process (ES-4.1 A.1.a and ES-4.1 B.2).

GMR

-210 07/01/22

4. Reference material due for NRC-prepared examinations (F).

GMR

-210 6/12/23 6/14/23

5. Examination kick-off call held (C.4). The NRC sends the corporate notification letter (A.5). GMR

-195 07/01/22

6. Written examination outline developed by the NRC and sent to the facility licensee contact (must be on the examination security agreement) (B.2, ES-4.1 A.1.b and ES-4.1 A.2.a).

GMR

-150 07/27/23

7. Operating test outlines and checklists due: Forms 1.3-1, 2.3-1, 3.2-1, 3.2-2, 3.3-1, and 3.4-1, as applicable (B.6). Facility licensee provides a draft operating test administration schedule to the NRC (B.18).

GMR

-136 N/A

8. Operating test outlines reviewed by the NRC and feedback provided to the facility licensee (ES-2.3).

N/A

-100 8/2/23

9. NRC-prepared examinations approved by the NRC supervisor and forwarded for facility licensee review (ES-2.3).

GMR

-75 10/12/23

10. Proposed examinations (written, JPMs, and scenarios, as applicable) and outline forms; quality checklists and supporting documentation (including Forms 2.3-2 and 2.3-4 and any Form 2.3-1, 1.3-1, and 3.4-1 updates); and reference materials due.

GMR

-60 11/08/23

11. Preliminary waiver/excusal requests due (ES-2.2 E.1).

N/A

-50 10/26/23

12. Written examination and operating test reviews completed (ES-2.3). The NRC supervisors authorization to proceed with the facility review granted (ES-2.3 D).

GMR

-50 11/16/23

13. Examination review results discussed between the NRC and the facility licensee (B.14).

GMR

-35 12/4/23

14. Examination preparatory week conducted by the NRC and the facility licensee (I).

GMR

-30 12/8/23

15. Preliminary license applications, including any waiver/excusal requests, due (ES-2-2 C.1).

GMR

-14 12/18/23

16. Final license applications, including any waiver/excusal requests, due and Form 2.2-1 prepared (ES-2.2 C and E).

GMR

-7 12/14/23

17. Written examinations and operating tests approved by the NRC supervisor (C.9)

GMR

-7 1/5/24

18. Facility licensee management feedback on the examination requested by the NRC supervisor (C.10).

GMR

-7 12/18/23

19. Final applications reviewed; 10% of applications audited to confirm qualifications/eligibility (ES-2.2 G); and examination approval letter (Letter 2.3-1) and waiver/excusal letters sent.

GMR

-7 12/6/23

20. Written examination administration guidelines reviewed with the facility licensee (D.14).

GMR

-7 12/14/23

21. Approved scenarios and job performance measures distributed to NRC examiners (D.12).

GMR