Appendix D Scenario Outline Form ES-D-1 NUREG-1021, Revision 11 Page 1 of 22 Facility:

Davis-Besse Scenario No.

1 Op Test No.:

DB1LOT22 Examiners:

Operators:

SRO ATC BOP Initial Conditions: 100% Power Turnover: Maintain 100% Power Planned: Shift Routines Critical tasks:

1. Close the Pressurizer Spray Valve and PORV Block Valve
2. Restore RCP Seal Return Event No.

Malf.

No.

Event Type*

Event Description 1

(N) ATC Place Purification Demin 3 I/S per Chemistry request 2

(I) ATC Leaking Power Operated Relief Valve (PORV) (TS) 3 (C) BOP Trip TPCW Pump 1 Hi Bearing Temp / Start STBY pump 4

Inverter YV1 DC input failure (TS) 5 (R) ATC/(C) BOP TPCW Pump 2 trips / Lower power to capacity of 1 pump 6

Major Steam Leak in CTMT / Trip Reactor 7

(C) BOP AFP 1 Trips - Start the MDFP (N)ormal, (R)eactivity, (I)nstrument, (C)omponent, (M)ajor

Appendix D Scenario Outline Form ES-D-1 NUREG-1021, Revision 11 Page 1 of 20 Facility:

Davis-Besse Scenario No.:

2 Op Test No.:

DB NRC 2022 Examiners:

Operators:

SRO ATC BOP Initial Conditions: 100% Power Turnover: Maintain 100% Power Planned: Shift routines Critical tasks:

1. Shutdown Reactor - ATWS
2. Isolate Overcooling Steam Generators Event No.

Malf.

No.

Event Type*

Event Description 1

(C) ATC Weekly Run of the Standby Makeup Pump 2 Oil Pumps (TRM) 2 (C) BOP Main Feedwater Pump Turbine 1 High Drain Tank Level 3

(C) BOP Swap SFP Pumps due to high bearing temp/vibration 4

(R) ATC / BOP Dropped Control Rod - Reduce Reactor Power (TS) 5 Major Main Generator Lockout - ATWS 6

(C) BOP Stuck Open Main Steam Safety Valve - Overcooling 7

(C) BOP Steam Feed Rupture Control System fails to automatically align for a low pressure trip on Steam Generator 1 (N)ormal, (R)eactivity, (I)nstrument, (C)omponent, (M)ajor

Appendix D Scenario Outline Form ES-D-1 NUREG-1021, Revision 11 Page 1 of 18 Facility:

Davis-Besse Scenario No.:

3 Op Test No.:

DB NRC 2022 Examiners:

Operators:

SRO ATC BOP Initial Conditions: 60% Power Turnover: Shutdown Main Feedwater Pump1 to 1000 RPM Auxiliary Feedwater Pump 1 Out of Service Planned: Complete the Shutdown of Main Feedwater Pump 1 Critical tasks:

1. Trip all 4 RCPs
2. Initiate High Pressure Injection Cooling Event No.

Malf.

No.

Event Type*

Event Description 1

(N) BOP Remove Main Feedwater Pump 1 from service 2

(C) ATC / BOP Component Cooling Water Pump 2 Trips (TS) 3 Bus F7 Failure / Motor Driven Feedwater Pump Inop (TS) 4 (C) BOP Station Air Compressor 2 setpoint failure - Low air header pressure 5

(R) ATC (C) BOP Rising Main Condenser Pressure - Reduce Reactor Power Trip the Main Generator 6

Major Trip the Reactor - Initiate / Isolate Steam Feedwater Rupture Control system 7

(C) ATC/BOP Auxiliary Feedwater Pump 2 Trips - Emergency Feedwater Pump does not start - Loss of All Feedwater Standby Makeup Pumps fails to start - Makeup / High Pressure Injection / PORV Cooling (N)ormal, (R)eactivity, (I)nstrument, (C)omponent, (M)ajor