Letter Sequence Withholding Request Acceptance |
---|
|
|
MONTHYEARML0729602982007-10-24024 October 2007 Notice of Consideration of Issuance of Amendment Under Exigent Circumstances, Proposed No Significant Hazards Consideration Determination, and Opportunity for a Hearing Project stage: Other ML0731008272007-11-0202 November 2007 Exigent License Amendment Request, Alternative Containment Analysis Methodology Request Information - Gothic Model Input Files Project stage: Request ML0731205062007-11-15015 November 2007 Issuance of Amendments Use of Gothic Code for Recirculation Spray System Exigent Circumstances Project stage: Approval ML0732306102007-11-15015 November 2007 Technical Specifications for Surry, Units 1 and 2, Issuance of Amendments Use of Gothic Code for Recirculation Spray System Exigent Circumstances Project stage: Approval ML0731101042007-11-26026 November 2007 Virginia Electric and Power Company, Units 1 and 2 Request for Withholding Information from Public Disclosure for Surry Power Station, Project stage: Withholding Request Acceptance 2007-11-15
[Table View] |
Similar Documents at Surry |
---|
Category:Letter
MONTHYEARML24283A0702024-10-0707 October 2024 Annual Submittal of Technical Specifications Bases Changes Pursuant to Technical Specification 6.4.J IR 05000280/20244032024-10-0303 October 2024 Cyber Security Inspection Report 05000280-2024403 and 05000281-2024403 Cover Letter (Public) IR 05000280/20240102024-10-0202 October 2024 Biennial Problem Identification and Resolution Inspection Report 05000280/2024010 and 05000281/2024010 ML24270A0022024-09-25025 September 2024 Inservice Inspection Owners Activity Report (OAR) ML24248A1712024-09-0303 September 2024 Proposed License Amendment Request - Temporary Service Water Supply to the Component Cooling Heat Exchangers IR 05000280/20240052024-08-26026 August 2024 Updated Inspection Plan for Surry Power Station, Units 1 and 2 (Report 05000280/2024005 and 05000281-2024005), Rev 1 ML24219A2372024-08-23023 August 2024 Issuance of Amendment Nos. 319 and 319, Adoption of TSTF-577, Rev. 1, Revised Frequencies for Steam Generator Tube Inspection, ML24207A0402024-08-21021 August 2024 Summary of July 17, 2024, Public Meeting - TS 3.7/3.14 AOT for SW Piping Maintenance IR 05000280/20240112024-08-13013 August 2024 Comprehensive Engineering Team Inspection Report 05000280/2024011 and 05000281/2024011 ML24164A0012024-08-12012 August 2024 Proposed Alternative Relief Request V-1 Inservice Testing of Pressure Isolation Valves (EPID l-2023-LLR-0060) IR 05000280/20240022024-08-0101 August 2024 Integrated Inspection Report 05000280/2024002 and 05000281/2024002 05000280/LER-2024-001, Troubleshooting Initiated Unknown Turbine Trip Feature in Control System2024-07-30030 July 2024 Troubleshooting Initiated Unknown Turbine Trip Feature in Control System ML24165A2782024-07-17017 July 2024 Issuance of Amendment Nos. 318 and 318, Reclassification of Regulatory Guide 1.97 Variable for Low Head Safety Injection ML24165A1232024-07-17017 July 2024 Proposed Alternative Relief Request P-1, P-2 Inservice Testing of Residual Heat and Containment Spray Pumps (EPID l-2023-LLR-0058) ML24190A4192024-07-0808 July 2024 Inservice Testing (IST) Program for Pumps and Valves Revised Sixth IST Interval Start Date and Updated Technical Specifications References for Alternative Request V-1 ML24179A2932024-07-0101 July 2024 Notification of Inspection and Request for Information for NRC Problem Identification and Resolution Inspection ML24178A2422024-06-25025 June 2024 2023 Annual Report of Emergency Core Cooling System (ECCS) Model, Changes Pursuant to the Requirements of 10 CFR 50.46 ML24177A2792024-06-20020 June 2024 Preparation and Scheduling of Operator Licensing Examinations ML24166A0622024-06-18018 June 2024 – Proposed Alternative Relief Request P-3, P-4 Inservice Testing of Boric Acid, Component Cooling Water Pumps ML24157A0542024-06-13013 June 2024 Audit Summary in Support of License Amendment Request for Proposed Reclassification of Low Head Safety Injection Flow Instrumentation Related to Regulatory Guide 1.97 ML24143A1622024-06-12012 June 2024 – Correction to Issuance of Amendment Nos. 297 and 280 and Surry Units 1 and 2, Correction to Issuance of Amendment Nos. 317 and 317, to Change Emergency Plan Staff Augmentation Times ML24170B0532024-06-10010 June 2024 DOM-NAF-2-P/NP-A, Revision 0.5, Reactor Core Thermal-Hydraulics Using the VIPRE-D Computer Code ML24141A2862024-05-22022 May 2024 Information Request for the Cyber Security Baseline Inspection, Notification to Perform Inspection 05000280/2024403 and 05000281- 2024403 ML24141A2512024-05-20020 May 2024 Proposed License Amendment Request - Reclassification of Low Head Safety Injection Flow Indication Regulatory Guide 1.97 Variable - Supplemental Information ML24141A0482024-05-17017 May 2024 EN 56958_1 Ametek Solidstate Controls, Inc ML24136A2302024-05-13013 May 2024 Core 1 Cycle 33 Pattern Mdr Revision 0 ML24130A2492024-05-0909 May 2024 Submittal of Information in Support of Surry Power Station Unit 1 Thermal Shield Flexure Replacement Campaign ML24130A2032024-05-0909 May 2024 Proposed License Amendment Request Application to Revise Technical Specifications to Adopt TSTF-577, Revised Frequencies for Steam Generator Tube Inspections Supplemental Information ML24130A1192024-05-0707 May 2024 Inservice Test Program for Pumps and Valves Sixth Interval Update and Associated Relief and Alternative Requests - Response to Request for Additional Information Regarding Alternative Request V-1 ML24142A3852024-04-30030 April 2024 2023 Annual Radioactive Effluent Release Report IR 05000280/20240012024-04-30030 April 2024 Integrated Inspection Report 05000280-2024001 and 05000281-2024001 ML24122C6522024-04-30030 April 2024 Annual Radiological Environmental Operating Report ML24122B3032024-04-29029 April 2024 Associated Independent Spent Fuel Storage Installation, Revision to Emergency Plan Report of Change IR 05000280/20244022024-04-29029 April 2024 Security Baseline Inspection Report 05000280/2024402 and 05000281/2024402 ML24115A1952024-04-24024 April 2024 Notification of Surry Power Station Comprehensive Engineering Team Inspection - U.S. NRC Inspection Report 05000280/2024011 and 05000281/2024011 ML24054A0142024-04-22022 April 2024 Issuance of Amendment Nos. 297 and 280, and Surry Power Station Unit Nos. 1 and 2, Issuance of Amendment Nos. 317 and 317, to Change Emergency Plan Staff Augmentation Times ML24108A1812024-04-15015 April 2024 Proposed License Amendment Request - Reclassification of Low Head Safety Injection Flow Indication Regulatory Guide 1.97 Variable Supplemental Information ML24095A2172024-04-12012 April 2024 – Review of the Spring 2023 Steam Generator Tube Inspection Report ML24088A2482024-03-26026 March 2024 Inservice Testing Program for Pumps and Valves Sixth Interval Update and Associated Relief and Alternative Requests- Response to Request for Additional Information ML24087A2082024-03-22022 March 2024 Proposed License Amendment Request Addition of Containment Limiting Condition for Operation and Surveillance Requirements ML24078A2642024-03-21021 March 2024 – Regulatory Audit in Support of License Amendment Request to Proposed Reclassification of Regulatory Guide 1.97 Variable for Low Head Safety Injection Flow Instrumentation ML24087A1522024-03-18018 March 2024 Annual Changes, Tests, and Experiments Report Regulatory Commitment Evaluation Report ML24023A5762024-03-0808 March 2024 Correction to Issuance of Amendment Nos. 315 and 315, Regarding Revised Emergency Plan for Relocation of the Technical Support Center IR 05000280/20230062024-02-28028 February 2024 Annual Assessment Letter for Surry Power Station, Units 1 and 2 - NRC Inspection Reports 05000280/2023006 and 05000281/2023006 ML24032A4712024-02-20020 February 2024 Exemption from Select Requirements of 10 CFR Part 73 - Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting ML24051A1782024-02-19019 February 2024 Proposed License Amendment Request - Application to Revise Technical Specifications to Adopt TSTF-577, Revised Frequencies for Steam Generator Tube Inspections ML24057A0612024-02-19019 February 2024 and Virgil C. Summer Power Nuclear Stations - Nuclear Property Insurance Coverage IR 05000280/20230042024-02-0909 February 2024 Integrated Inspection Report 05000280/2023004 and 05000281/2023004 IR 05000280/20244012024-02-0606 February 2024 Security Baseline Inspection Report 05000280/2024401, 05000281/2024401 and 07200002/2024401 IR 05000280/20230102024-01-18018 January 2024 – Age Related Degradation Inspection Report 05000280-2023010 and 05000281-2023010 2024-09-03
[Table view] Category:Proprietary Information Review
MONTHYEARML23101A0422023-05-0303 May 2023 Request for Withholding Information from Public Disclosure for North Anna Power Station Units 1 & 2, Surry Units 1 & 2 and Millstone Units 2 & 3, Request for Withholding, Appendix F of Fleet Report DOM-NAF-2-P ML22355A1832023-03-0101 March 2023 Request for Withholding Information from Public Disclosure for North Anna Station, Units 1 & 2, Surry Station, Units 1 & 2, and Millstone Station, Units 2 & 3 - Request for Withholding Appendix F of Fleet Report DOM-NAF-2 ML22335A4142022-12-21021 December 2022 Request for Withholding Information from Public Disclosure for Dominion Fleet Response to Request for Additional Information Regarding NRC Generic Letter 2004-02 ML22298A0692022-11-16016 November 2022 Request for Withholding Information from Public Disclosure for Surry Power Station Units 1 and 2 ML21148A1502021-06-0808 June 2021 Request for Withholding Information from Public Disclosure for North Anna Power Station, Units 1 & 2, Surry Power Station, Units 1 & 2, and Millstone Power Station, Units 2 & 3, Request for Withholding Response to NRC Request for Additional ML21075A2592021-03-18018 March 2021 Request for Withholding Information from Public Disclosure for North Anna Power Station, Units 1 and 2, Surry Power Station, Units 1 and 2, and Millstone Power Station, Units 2 and 3, Request for Withholding, Appendix E of Fleet Report Dom- ML18351A2572018-12-20020 December 2018 U.S. Nuclear Regulatory Commission Approval of Virginia Electric and Power Company'S Request for Withholding Information from Public Disclosure, Regarding the Application for Subsequent License Renewal of Surry Power Station, Unit Nos. 1 an ML18166A3542018-06-27027 June 2018 Request for Withholding Information from Public Disclosure (EPID L-2017-LR0-0078) ML17277A2962017-11-0202 November 2017 Request for Withholding Information from Public Disclosure (CAC Nos. MF8987 and MF8988; EPID L-2016-LLR-0019) ML17264A2272017-10-20020 October 2017 Request for Withholding Information from Public Disclosure ML17030A0812017-02-24024 February 2017 Request for Withholding Information from Public Disclosure ML17031A1302017-02-23023 February 2017 Request for Withholding Information from Public Disclosure ML13053A3612013-03-0707 March 2013 Request for Withholding Information from Public Disclosure for DNC, DEK, Virginia Kewaunee Unit 1, Millstone Power Station, Units 1, 2 & 3, North Anna Units 1 & 2, Surry Units 1 & 2 Information Pertaining to Foreign Interests ML1025601852010-09-28028 September 2010 ME4600 (Dominion Fleet) Proprietary Determination Ltr 2010-09-13 ML0934504082009-12-23023 December 2009 Millstone Power Station, Units 2 & 3, North Anna Power Station, Units 1 &2, Surry Power Station Units 1 & 2 - Withholding of Information Determined to Be Proprietary ML0732400982007-11-29029 November 2007 Request for Withholding Information from Public for Surry Power Station, Units 1 and 2, North Anna Power Station, Units 1 and 2, and Millstone Power Station and Kewaunee Power Station (TAC Nos. MD6144, MD6145, MD6146, MD6147, MD6148, MD6149 ML0731101042007-11-26026 November 2007 Virginia Electric and Power Company, Units 1 and 2 Request for Withholding Information from Public Disclosure for Surry Power Station, ML0707406522007-03-19019 March 2007 Request for Withholding Information from Public Disclosure, Amendment to Revise the Licensing Basis to Permit Irradiation of the Fuel Assemblies ML0621903542006-08-0707 August 2006 Withholding Information from Public Disclosure. ML0618004712006-07-18018 July 2006 Units 2 & 3, Withholding from Public Disclosure, CD-ROM Containing Electronic Gothic Input & Output Files from Benchmark Cases in Sections 4.3, 4.4, 4.5, & 4.6 of TR DOM-NAF-3, Gothic Methodology for Analyzing. ML0519505702005-07-14014 July 2005 Virginia Electric and Power Company Surry Power Station Unit 2 ASME Section XI Inservice Inspection Program Embedded Flaw Evaluation ML0419005542004-07-0707 July 2004 7/7/04, Surry, Units 1 & 2, Withholding from Public Disclosure, Enclosure 5 of the 5/7/04 Submittal Entitled, Test of Cold Thermal Shock on RCP 93D Shaft Seals in Shutdown Configuration ML0235801542002-12-24024 December 2002 Request for Withholding Information from Public Disclosure, TAC Nos. MB5435, MB5436, MB5433, MB5434 2023-05-03
[Table view] |
Text
November 26, 2007 Mr. Gerald T. Bischof Vice President, Nuclear Engineering Virginia Electric and Power Company Richmond, Virginia 23261
SUBJECT:
REQUEST FOR WITHHOLDING INFORMATION FROM PUBLIC DISCLOSURE FOR SURRY POWER STATION, UNIT NOS. 1 AND 2 (TAC NOS. MD7033 AND MD7034)
Dear Mr. Bischof:
By letter dated November 2, 2007, Virginia Electric and Power Company (VEPCO) submitted an affidavit also dated November 2, 2007, executed by Gerald T. Bischof, you requested that the information contained in the following document be withheld from public disclosure pursuant to Title 10 of the Code of Federal Regulations (10 CFR), Part 2, Section 2.390:
CD-ROM containing GOTHIC, Containment Analysis Methodology Code and input parameters model files from the demonstration cases in Section 3.3 of Attachment 1 from VEPCOs letter dated November 2, 2007, they are:
- 1. The base case analyzed assuming the actual sump pool surface area of 11,757 sq. ft.
- 2. The proposed alternate methodology assuming a liquid-vapor interface area of 11,757 sq. ft.
plus an additional 40,000 sq. ft. of area. The additional area represents 39.1% of the total surface areas of all steel conductors with a surface temperature that exceeds the boiling temperature of containment pressure about the time of minimum NPSH.
The affidavit stated that the submitted information should be considered exempt from mandatory public disclosure for the following reasons:
(a) This information is of a type that is held in confidence by Dominion, and there is a rational basis for doing so because the information contains sensitive commercial information concerning Dominions containment analysis methodology.
(b) The information was transmitted in confidence.
(c) The information is not available in public sources and could not be gathered readily from other publicly available information.
(d) Public disclosure of this information would create substantial harm to the competitive position of Dominion by disclosing confidential internal containment analysis methodology information to other parties whose commercial interests may be adverse to those of Dominion. Furthermore, Dominion has expended significant engineering resources in the development of the information. Therefore, the use of
G. Bischof this confidential information by competitors, would permit them to use the information developed by Dominion without the expenditure of similar resources; thus giving them a competitive advantage.
We have reviewed your application and the material in accordance with the requirements of 10 CFR 2.390 and, on the basis of your statements, have determined that the submitted information sought to be withheld contains proprietary commercial information and should be withheld from public disclosure.
Therefore, the CD-ROM containing GOTHIC, Containment Analysis Methodology Code and input parameters model files from the demonstration cases in Section 3.3 of Attachment 1 from Dominion letter dated November 2, 2007, marked as proprietary, will be withheld from public disclosure pursuant to 10 CFR 2.390(b)(5) and Section 103(b) of the Atomic Energy Act of 1954, as amended.
Withholding from public inspection shall not affect the right, if any, of persons properly and directly concerned to inspect the documents. If the need arises, we may send copies of this information to our consultants working in this area. We will, of course, ensure that the consultants have signed the appropriate agreements for handling proprietary information.
If the basis for withholding this information from public inspection should change in the future such that the information could then be made available for public inspection, you should promptly notify the NRC. You also should understand that the NRC may have cause to review this determination in the future, for example, if the scope of a Freedom of Information Act request includes your information. In all review situations, if the NRC makes a determination adverse to the above, you will be notified in advance of any public disclosure.
If you have any questions regarding this matter, I may be reached at 301-415-2728.
Sincerely,
/RA/
R. A. Jervey, Project Manager Plant Licensing Branch II-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-280 and 50-281 cc: See next page
G. Bischof this confidential information by competitors, would permit them to use the information developed by Dominion without the expenditure of similar resources; thus giving them a competitive advantage.
We have reviewed your application and the material in accordance with the requirements of 10 CFR 2.390 and, on the basis of your statements, have determined that the submitted information sought to be withheld contains proprietary commercial information and should be withheld from public disclosure.
Therefore, the CD-ROM containing GOTHIC, Containment Analysis Methodology Code and input parameters model files from the demonstration cases in Section 3.3 of Attachment 1 from Dominion letter dated October 22, 2007, marked as proprietary, will be withheld from public disclosure pursuant to 10 CFR 2.390(b)(5) and Section 103(b) of the Atomic Energy Act of 1954, as amended.
Withholding from public inspection shall not affect the right, if any, of persons properly and directly concerned to inspect the documents. If the need arises, we may send copies of this information to our consultants working in this area. We will, of course, ensure that the consultants have signed the appropriate agreements for handling proprietary information.
If the basis for withholding this information from public inspection should change in the future such that the information could then be made available for public inspection, you should promptly notify the NRC. You also should understand that the NRC may have cause to review this determination in the future, for example, if the scope of a Freedom of Information Act request includes your information. In all review situations, if the NRC makes a determination adverse to the above, you will be notified in advance of any public disclosure.
If you have any questions regarding this matter, I may be reached at 301-415-2728.
Sincerely,
/RA/
R. A. Jervey, Project Manager Plant Licensing Branch II-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-280 and 50-281 cc: See next page DISTRIBUTION:
PUBLIC RidsRgn2MailCenter(EGuthrie)
LPL2-1 Rdg RidsNrrPMRJervey (hard copy)
RidsNrrDorlLpl2-1(EMarinos) RidsNrrLAMO=Brien (hard copy)
RidsOgcMailCenter RidsAcrsAcnwMailCenter RidsNrrSrxb(GCranston)
ADAMS Accession No: ML073110104 NRR084 OFFICE LPL2-1/PM LPL2-1/LA NRR/SRXB/BC LPL2-1/BC NAME RJervey MO=Brien GCranston EMarinos DATE 11/20/07 11/20/07 11/20/07 11 /26 /07 OFFICIAL AGENCY RECORD
Surry Power Station, Units 1 & 2 cc:
Mr. David A. Christian Office of the Attorney General President and Chief Nuclear Officer Commonwealth of Virginia Virginia Electrical and Power Company 900 East Main Street Innsbrook Technical Center Richmond, Virginia 23219 5000 Dominion Boulevard Glen Allen, VA 23060-6711 Mr. Chris L. Funderburk, Director Nuclear Licensing & Operations Support Ms. Lillian M. Cuoco, Esq. Dominion Resources Services, Inc.
Senior Counsel Innsbrook Technical Center Dominion Resources Services, Inc. 5000 Dominion Blvd.
120 Tredegar Street, RS-2 Glen Allen, Virginia 23060-6711 Richmond, VA 23219 Mr. Matt Adams, Director Mr. Donald E. Jernigan Nuclear Safety & Licensing Site Vice President Virginia Electric and Power Company Surry Power Station Surry Power Station Virginia Electric and Power Company 5570 Hog Island Road 5570 Hog Island Road Surry, VA 23883-0315 Surry, Virginia 23883-0315 Senior Resident Inspector Surry Power Station U. S. Nuclear Regulatory Commission 5850 Hog Island Road Surry, Virginia 23883 Chairman Board of Supervisors of Surry County Surry County Courthouse Surry, Virginia 23683 Dr. W. T. Lough Virginia State Corporation Commission Division of Energy Regulation Post Office Box 1197 Richmond, Virginia 23218 Dr. Robert B. Stroube, MD, MPH State Health Commissioner Office of the Commissioner Virginia Department of Health Post Office Box 2448 Richmond, Virginia 23218