| | title = 2008/02/28-Order Granting Entergy'S Consent Motion for Expedited Commission Approval of Revised Filing Schedule and Applicant'S Conforming Request for Extension of Time to File Answer to Uwua Locals' Petition to Intervene & Postpone Entergy | | | title = Order Granting Entergy'S Consent Motion for Expedited Commission Approval of Revised Filing Schedule and Applicant'S Conforming Request for Extension of Time to File Answer to Uwua Locals' Petition to Intervene & Postpone Entergy'S Deadline |
| | author name = Vietti-Cook A | | | author name = Vietti-Cook A |
| | author affiliation = NRC/SECY | | | author affiliation = NRC/SECY |
Line 40: |
Line 40: |
| For the Commission | | For the Commission |
| /RA/ | | /RA/ |
| _____________________________
| |
| Annette L. Vietti-Cook Secretary of the Commission Dated at Rockville, Maryland, this 28th day of February, 2008. | | Annette L. Vietti-Cook Secretary of the Commission Dated at Rockville, Maryland, this 28th day of February, 2008. |
|
| |
|
|
---|
Category:Legal-Order
MONTHYEARML20317A1172020-11-12012 November 2020 Commission Memorandum and Order (CLI-20-12) ML20206K8542020-07-22022 July 2020 Order Directing Dismissal of Case (DC Cir.)(Case No. 19-1198) NRC-72-1044, 7-22-20 Order (DC Cir.)(Case No. 19-1198)(Consolidated with 20-1019)2020-07-22022 July 2020 7-22-20 Order (DC Cir.)(Case No. 19-1198)(Consolidated with 20-1019) ML20156A4042020-06-0404 June 2020 Order of the Secretary ML20062G8622020-03-12012 March 2020 2-12-20 Order Consolidating Cases (DC Cir.)(Case No. 19-1198) ML20014E6612020-01-14014 January 2020 Letter from Commission Secretary Annette Vietti-Cook to Janet Azarovitz ML19353C7492019-12-19019 December 2019 Letter from Commission Secretary Annette Vietti-Cook to Mary Lampert of Pilgrim Watch ML19351D6952019-12-17017 December 2019 Commission Memorandum and Order (CLI-19-11) ML19303B3132019-10-28028 October 2019 Statement of Issues (DC Cir.)(Case No. 19-1198) 10-28-19 ML19274B2762019-09-27027 September 2019 Massachusetts Scheduling Order (DC Cir.)(Case No. 19-1198)- 9-27-19 ML19256C4952019-09-13013 September 2019 Order (Granting Motion for Twenty-Two Minute Enlargement of Time) ML19255J0832019-09-12012 September 2019 Letter from Commission Secretary Annette Vietti-Cook to David Madigan, Et Al ML19283C9552019-09-11011 September 2019 Letter from Commission Secretary Annette Vietti-Cook to Congressman William R. Keating ML19253D1862019-09-10010 September 2019 Letter from Commission Secretary Annette Vietti-Cook to Diane Turco and Deb Katz ML19248C8112019-09-0505 September 2019 Order (Clarifying Deadline for Responding to Motions for Stay) ML19246A8082019-09-0303 September 2019 Letter from NRC Acting Secretary, Rochelle C. Bavol, to Judeth Van Hamm ML19241A5872019-08-29029 August 2019 Letter from NRC Acting Secretary, Richard Laufer, to Lawrence Delafield ML19241A5882019-08-29029 August 2019 Letter from NRC Acting Secretary, Richard Laufer, to Janet Azarovitz ML19238A2792019-08-26026 August 2019 Letters from NRC Acting Secretary, Rochelle Bavol, to Senator Markey, Senator Warren and Congressman Keating Re Pilgrim Nuclear Power Station License Transfer Request ML19238A2832019-08-26026 August 2019 Letter from NRC Acting Secretary to Diane Turco of Cape Downwinders and Deb Katz of Citizens Awareness Network ML19238A2982019-08-26026 August 2019 Letter from NRC Acting Secretary to Henrietta Cosentino of the Plymouth Area League of Women Voters ML19170A1012019-08-22022 August 2019 Letter, Order Approving Direct and Indirect Transfer of Renewed Facility Operating License to Holtec Pilgrim, LLC, Owner and Holtec Decommissioning International, LLC, Operator ML19233A2892019-08-21021 August 2019 Order (Granting Motion for Extension of Time) ML19228A1322019-08-16016 August 2019 Order (Clarifying NRC Staff Filing of a Notification of Significant Licensing Action) ML19226A1072019-08-14014 August 2019 Commission Memorandum and Order CLI-19-08 ML19225D2552019-08-13013 August 2019 Letter to the Honorable Edward J. Markey from Annette L. Vietti-Cook, Secretary of the Commission ML19095B1692019-04-0505 April 2019 Memorandum to the Parties (Regarding Commissioner Caputo'S Upcoming Site Visit) ML19079A3012019-03-20020 March 2019 Order (Granting Petitioners Extension of Time to Reply to Applicants' Answer) ML19066A3152019-03-0707 March 2019 Letters from Commission Secretary Annette Vietti-Cook to Senators Edward J. Markey, Elizabeth Warren, and Bill Keating ML19059A4442019-02-28028 February 2019 Letter from Commission Secretary Annette Vietti-Cook to Senator Vinny Demacedo, Et Al ML17096A7362017-04-0606 April 2017 Commission Memorandum and Order (CLI-17-06) ML16299A1852016-10-20020 October 2016 Letter from the Chairman to Senator Edward J. Markey, Et Al. Re Entergy Nuclear Operations, Inc. Request for Extension of Time to Comply with NRC Order EA-13-109 for Pilgrim Nuclear Power Station ML12341A0782012-12-0606 December 2012 CLI-12-21 Memorandum and Order Denying Jones River Watershed Association and Pilgrim Watch Review of LBP-12-11 ML12264A3882012-09-18018 September 2012 Entergy Nuclear Operations, Inc.; Entergy Nuclear Generation Company Order Granting Extension ML12264A3942012-09-18018 September 2012 Entergy Nuclear Operations, Inc.; Entergy Nuclear Generation Company Corrected Order ML12202B0802012-07-20020 July 2012 Memorandum and Order (Denying Petition for Intervention and Request to Reopen Proceeding and Admit New Contention) ML12202B1742012-07-20020 July 2012 Order of the Secretary Extending Time for Commission Review of LBP-12-11 ML12170A9142012-06-18018 June 2012 Memorandum and Order (Denying Petition for Intervention and Request to Reopen Proceeding and Admit New Contention, LBP-12-11) ML12159A1522012-06-0707 June 2012 Memorandum and Order - CLI-12-15 ML12146A1112012-05-25025 May 2012 Response of the Secretary to the April 30, 2012 Request of Pilgrim Water and Jones River Watershed Association Opposing NRC Staff'S Recommendation in Secy 12-0062 ML12145A6262012-05-24024 May 2012 Memorandum and Order (Denying Petition for Intervention and Request to Reopen the Proceeding and Admit New Contention) ML12138A1112012-05-17017 May 2012 Memorandum and Order, (Requesting Filing on Petitions Under 10 C.F.R. 2.206) ML12138A1502012-05-17017 May 2012 Establishment of Atomic Safety and Licensing Board in the Matter of the Pilgrim Nuclear Power Station ML12138A3022012-05-17017 May 2012 Order (Granting NRC Staff'S Unopposed Motion for Extension; Seeking Input from Parties) ML12137A3132012-05-16016 May 2012 Memorandum of the Secretary Referring the Jones River Watershed Association and Pilgrim Watch'S Request to Reopen the Record, for a Hearing, to File New Contentions, and Jones River Watershed Association Motion to Intervene, in the Pilgrim ML12136A5582012-05-15015 May 2012 Establishment of Atomic Safety and Licensing Board in the Matter of Entergy Nuclear Operations, Inc., License Renewal for Pilgrim Nuclear Power Station ML12131A6392012-05-10010 May 2012 Secretary Referral Memorandum Referring the Jones River Watershed Association Motion to Reopen, Request for Hearing and Request to File a New Contention, in the Pilgrim Nuclear Power Station, Docket No. 50-293-LR Proceeding ML12109A1182012-04-18018 April 2012 Inquiry (Regarding Information on Expected NMFS ESA Determination) ML12093A2702012-04-0202 April 2012 Establishment of Atomic Safety and Licensing Board ML12090A5182012-03-30030 March 2012 Commission Memorandum and Order CLI-12-10 2020-07-22
[Table view] |
Text
UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION DOCKETED 02/28/08
_________________________________________ SERVED 02/28/08
)
ENTERGY NUCLEAR OPERATIONS, INC. ) Docket Nos. 50-255-LT-2 and ENTERGY NUCLEAR PALISADES, LLC ) and 72-7-LT (Palisades Nuclear Plant) )
)
ENTERGY NUCLEAR OPERATIONS, INC. ) Docket Nos. 50-333-LT-2 and ENTERGY NUCLEAR FITZPATRICK, LLC ) and 72-12-LT (James A. Fitzpatrick Nuclear Power Plant) )
)
ENTERGY NUCLEAR OPERATIONS, INC. ) Docket No. 50-293-LT-2 and ENTERGY NUCLEAR GENERATION CO. )
(Pilgrim Nuclear Power Station) )
)
ENTERGY NUCLEAR OPERATIONS, INC. ) Docket No. 50-271-LT-2 and ENTERGY NUCLEAR VERMONT YANKEE, )
LLC (Vermont Yankee Nuclear Power Station) )
)
ENTERGY NUCLEAR OPERATIONS, INC.; ) Docket Nos. 50-003-LT, ENTERGY NUCLEAR INDIAN POINT 2, LLC; ) 50-247-LT, and ENTERGY NUCLEAR INDIAN POINT 3, LLC ) 50-286-LT-2 (Indian Point Nuclear Generating Unit Nos. 1, 2, &3))
)
ENTERGY NUCLEAR OPERATIONS, INC. ) Docket Nos. 50-155-LT-2 and ENTERGY NUCLEAR PALISADES, LLC ) and 72-043-LT-2 (Big Rock Point) )
_________________________________________)
ORDER Pursuant to my authority under 10 C.F.R. 2.346(b) & (j), I grant Entergys Consent Motion . . . for Expedited Commission Approval of Revised Filing Schedule and Applicants Conforming Request for Extension of Time to File Answer to UWUA Locals Petition to Intervene (Feb. 26, 2008). I also postpone Entergy's deadline to answer WestCANs petition to intervene, pending further order of the Commission.
In addition, Entergys additional request to file pleadings via the NRCs E-filing system solely on the Pilgrim docket for the duration of this matter is granted. This ruling also applies to future filings by the participants with respect to the Indian Point dockets. In essence, I am consolidating all dockets for E-filing purposes under the Pilgrim docket umbrella. All other dockets pertaining to this adjudication that are presently available on the E-filing Adjudicatory
2 Submission Form will be removed.
IT IS SO ORDERED.
For the Commission
/RA/
Annette L. Vietti-Cook Secretary of the Commission Dated at Rockville, Maryland, this 28th day of February, 2008.
UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION In the Matter of )
)
ENTERGY NUCLEAR OPERATIONS, INC. )
Palisades Nuclear Plant ) Docket Nos. 50-255-LT-2 & 72-7-LT James A. FitzPatrick Nuclear Power Plant ) Docket Nos. 50-333-LT-2 & 72-12-LT Pilgrim Nuclear Power Station ) Docket No. 50-293-LT-2 Vermont Yankee Nuclear Power Station ) Docket No. 50-271-LT-2 Indian Point Nuclear Generating Unit No. 1 ) Docket No. 50-003-LT Indian Point Nuclear Generating Unit No. 2 ) Docket No. 50-247-LT Indian Point Nuclear Generating Unit No. 3 ) Docket No. 50-286-LT-2 Big Rock Point ) Docket Nos. 50-155-LT-2 & 72-043-LT-2 CERTIFICATE OF SERVICE I hereby certify that copies of the foregoing COMMISSION ORDER have been served upon the following persons by the e-filing system with electronic mail notification to the proceeding participants.
Office of Commission Appellate Office of the General Counsel Adjudication Mail Stop - O-15 D21 U.S. Nuclear Regulatory Commission U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 Washington, DC 20555-0001 E-mail: ocaamail@nrc.gov E-mail: ogclt@nrc.gov Scott H. Strauss, Esq. Sarah Wagner, Esq.
Rebecca J. Baldwin, Esq. L.O.B. Room 422 Spiegel & McDiarmid Albany, NY 12248 1333 New Hampshire Ave., NW E-mail: sarahwagneresq@gmail.com Washington, DC 20036 E-mail: scott.strauss@spiegelmcd.com; rebecca.baldwin@spiegelmcd.com
2 Docket Nos. 50-255-LT-2 & 72-7-LT Docket Nos. 50-333-LT-2 & 72-12-LT Docket No. 50-293-LT-2 Docket No. 50-271-LT-2 Docket No. 50-003-LT Docket No. 50-247-LT Docket No. 50-286-LT-2 Docket Nos. 50-155-LT-2 & 72-043-LT-2 Richard J. Koda, Principal Paul M. Bessette, Esq.,
Koda Consulting, Inc. Stephen J. Burdick, Esq.
409 Main Street John E. Matthews, Esq.
Ridgefield, CT 06877-4511 Martin ONeill, Esq.
E-mail: rjkoda@earthlink.net Kathryn M. Sutton, Esq.
Annette M. White, Esq.
Vincent C. Zabielski, Esq.
Mauri T. Lemoncelli, Esq.
Morgan, Lewis, & Bockius, LLP 1111 Pennsylvania, Ave., NW Washington, DC 20004 E-mail: pbessette@morganlewis.com sburdick@morganlewis.com; jmatthews@morganlewis.com; martin.oneill@morganlewis.com; ksutton@morganlewis.com; annette.white@morganlewis.com; vzabielski@morganlewis.com; mlemoncelli@morganlewis.com
[Original signed by R. L. Giitter]
Office of the Secretary of the Commission Dated at Rockville, Maryland this 28th day of February 2008