| issue date = 07/20/1973
| issue date = 07/20/1973
| title = Nine Mile Point Unit 1 - Letter Responding to a Request for Additional Information Concerning the Drywell Vacuum Breakers
| title = Letter Responding to a Request for Additional Information Concerning the Drywell Vacuum Breakers
| author name = Schneider R R
| author name = Schneider R
| author affiliation = Niagara Mohawk Power Corp
| author affiliation = Niagara Mohawk Power Corp
| addressee name = Skovholt D J
| addressee name = Skovholt D
| addressee affiliation = US Atomic Energy Commission (AEC)
| addressee affiliation = US Atomic Energy Commission (AEC)
| docket = 05000220
| docket = 05000220
Line 12: Line 12:
| document type = Letter, Response to Request for Additional Information (RAI), Technical Specifications
| document type = Letter, Response to Request for Additional Information (RAI), Technical Specifications
| page count = 10
| page count = 10
| project =
| stage = Request
}}
}}


=Text=
=Text=
{{#Wiki_filter:.AEC DIS BUTION FOR PART 50 DOCKET MA~AL'TEMPORARY FORM)CONTROL NO: PILE: 'RON: Niagara Mohawk Power Corporation Syracuse, N.Y.13202 R.R.Schneider'-20-73 7-25-73 DATE OF DOC DATE REC'D MEMO RPT OTHER TO vh CLASS UNCLASS XX PROP INFO ORIG 3 si~ned INPUT CC OTHER NO S REC'D 40 SENT AEC PDR X SENT LOCAL PDR X DOCKET NO: 50-220 DESCRIPTION:
{{#Wiki_filter:.AEC DIS   BUTION FOR PART 50 DOCKET MA FORM)                                 CONTROL NO:
Ltr furnishing requested info re drywell vacuum breakers at the Nine Mile Point Nuclear Station Unit 0 l.......PLANT NAME..Nine Mile Point Unit 8 1 ENCLOSURES:
                                                                                  ~AL'TEMPORARY PILE:
NQJil/>ggg Do,go<Remove~t~FOR ACTION/INFORMATION 7-25-73 AB BUTLER(L)W/Copies CLARK(L)W/Copies GOLLER(L)W/'Copies KNIEL(L)W/Copies SCHWENCER(L)
  'RON:                                     DATE OF DOC        DATE REC'D                        MEMO    RPT    OTHER Niagara Mohawk Power Corporation R. R.
W/Copies STOLZ(L)W/Copies VASSALLO(L)
TO Schneider'-20-73 Syracuse, N. Y. 13202 ORIG            CC 7-25-73 OTHER                     SENT AEC PDR      X SENT LOCAL PDR    X vh                         3  si~ned CLASS   UNCLASS         PROP INFO         INPUT         NO   S REC'D                   DOCKET NO:
W/'Copies SCHEMEL(L)
XX                                            40                            50-220 DESCRIPTION:                                                ENCLOSURES:
W/Copies NIEMANN (L)W/6 Copies DICKER(E)W/Copies KNIGHTON (E)W/Copies YOUNGBLOOD(E)
Ltr furnishing   requested info re drywell vacuum breakers at the Nine Mile Point Nuclear Station Unit 0     l.......
W/Copies INTERNAL DISTRIBUTION REGAN(E)W/Copies W/Copies'W/Copies W/Copies G PI R OGC, ROON P-506A~MUNTZING/STAFF CASE GIAMBUSSO BOYD MOORE (L)(BWR)DEYOUNG (L)(PWR)~SKOVHOLT (L)P.COLLINS REG OPR~ILE&REGION(3)MORRIS STEELE TECH REVIEW HENDRIE SCHROEDER MACCARY KNIGHT PAWLICKI SHAO STELLO HOUSTON NOVAK ROSS IPPOLITO~TEDESCO LONG~LAINAS BENAROYA VOLIMER DEN TON GRIMES GRMILL'ASTNER BALLARD SPANGLER ENVIRO MULLER DICKER KNIGHTON YOUNGBLOOD REGAN PROJECT LDR HARLESS LIC ASST BR(MN (E)DIGGS (L)GEARIN (L)GOULBOURNE (L)LEE (L)MAIGRET (L)SERVICE (L)SHEPPARD (E)SMITH (L)TEETS (L), WADE (E)WILLIAMS (E)WILSON (L)A/T IND BRAT IMAN SALTZMAN PLANS MCDONALD DUBE INFO C.MILES~J.RIESLAND W.BUTLER+STOLZ CLARK EXTERNAL DISTRIBUTION
NQJil/>ggg PLANT NAME..     Nine Mile Point Unit 8     1
~l<<LOCAL PDR~1-DTIE(ABERNATHY)(l)(2)(9)-NATIONAL LAB'S~-NSIC(BUCHANAN)
                                                                              ~t~
'1-R.Schoonmaker,OC,GT,D-323 1-ASLB(YORE/SAYRE/
Do,go< Remove FOR ACTION/INFORMATION                                   7-25-73     AB BUTLER(L)         SCHWENCER(L)        NIEMANN(L)                    REGAN(E)
1-R.CATLIN)E-256-GT WOODARD/"H" ST.1-CONSULTANT' 16-CYS ACRS HGMRHG SENT TO LIC ASST.NEWARK/BLAT/AGBABIAN R.DIGGS ON 7-25-.73 3."GERALD ULRIKSON~ORNL 1-PDR-SAN/LA/K(1-GERALD LELLOU0 BROOKHAVEN NAT.LAB 1-AGMED(WALTER KOESTER RM-C-427"GT 1-RD MULLER.F-309 GT C o t~t l, I'
W/ Copies          W/ Copies                W/ 6 Copies              W/ Copies CLARK(L)           STOLZ(L)                DICKER(E)
.AeIYutatory
W/ Copies           W/ Copies               W/ Copies               W/   Copies GOLLER(L)           VASSALLO(L)              KNIGHTON  (E)
'NIAGARA MOHAWK POWER CORPORATION NIAGARA~MOHAWK 300 ERIE BOULEVARD WEST SYRACUSE, N Y.l3202 July 20, 1973~III'r"g Jul g5)gg~
W/ 'Copies         W/ 'Copies               W/   Copies           'W/   Copies KNIEL(L)            SCHEMEL(L)               YOUNGBLOOD(E)
W/ Copies           W/ Copies               W/   Copies             W/   Copies INTERNAL DISTRIBUTION G PI                 TECH REVIEW          DENTON              LIC ASST                          A/T IND R             HENDRIE              GRIMES              BR(MN (E)                        BRAT IMAN OGC, ROON   P-506A   SCHROEDER            GRMILL              DIGGS (L)                        SALTZMAN
~ MUNTZING/STAFF CASE MACCARY KNIGHT
                                              'ASTNER BALLARD GEARIN (L)
GOULBOURNE           (L)         PLANS GIAMBUSSO              PAWLICKI              SPANGLER            LEE (L)                         MCDONALD BOYD                  SHAO                                      MAIGRET   (L)                   DUBE MOORE  (L) (BWR)     STELLO                ENVIRO              SERVICE    (L)
DEYOUNG (L) (PWR)      HOUSTON              MULLER              SHEPPARD    (E)                   INFO
~SKOVHOLT (L)             NOVAK                DICKER              SMITH  (L)                       C. MILES P. COLLINS            ROSS IPPOLITO KNIGHTON YOUNGBLOOD TEETS WADE (L),
(E)
                                                                                                ~ J. RIESLAND W. BUTLER REG OPR              ~ TEDESCO              REGAN              WILLIAMS (E)                +   STOLZ
~ILE & REGION(3)          LONG                  PROJECT LDR        WILSON    (L)                    CLARK MORRIS              ~LAINAS STEELE                BENAROYA              HARLESS VOLIMER EXTERNAL DISTRIBUTION
~l <<LOCAL     PDR
      - DTIE(ABERNATHY)
~1
~ 1 NSIC(BUCHANAN)
ASLB(YORE/SAYRE/
(l)(2)(9)-NATIONALLAB'S
                                                    '1-R.Schoonmaker,OC,GT,D-323 1-R. CATLIN) E-256-GT 1-PDR-SAN/LA/K(
1-GERALD LELLOU0 BROOKHAVEN NAT. LAB WOODARD/ "H" ST.                             1-CONSULTANT'                                 1-AGMED(WALTER KOESTER 16 - CYS ACRS HGMRHG SENT TO LIC ASST.               NEWARK/BLAT/AGBABIAN                           RM-C-427"GT R. DIGGS ON 7-25-.73       3."GERALD ULRIKSON       ~ ORNL               1-RD MULLER. F-309 GT


==Dear Mr.Skovholt:==
C o t
Re: Provisional Operating License: Docket No.: 50-220 DPR-17 Mr.Donald J.Skovholt Assistant Director for Reactor Operations Division of Reactor Licensing United States Atomic Energy Commission Washington, D.C.20545 O0,<<~)8 jp jogg 6'OIIQggIIII II~idltlf Regarding your letter requesting additional information concerning the drywell vacuum breakers at Nine Mile Point Nuclear Station Unit 81, the following is submitted:
~ t l, I'
ITEM 1 The present position indicating system utilizes two sets of limit switches, the snap lock limit switch manufactured by the National Acme Company and the Honey-well Model DTE6-2RN heavy duty, micro switches.The snap lock limit switch is used to determine and indicate the open position of any one valve'to the control room.The Honeywell micro switch is used to determine and indicate the closed position of any one valve to the control room.This system was reviewed during the Spring",.I973 refueling outage and the Honeywell micro switches installed at that time.Since the purpose of these limit switches is to provide the control room operator with information regarding the position of the breaker valves, physical separation of the control wiring or indicating lights is not required.However, an additional Honeywell limit, switch will be installed to detect the closed position and provide an alarm to the control room in the event any drywell vacuum breaker valve moves off its seat a predetermined amount.Redundances in the alarm circuit will thus be provided and IEEE 279 criteria satisfied.
 
The pretravel on the Honeywell'switch is.065" maximum and measurements have shown them to be.04" of pretravel.
            .AeIYutatory NIAGARA MOHAWK POWER CORPORATION NIAGARA
The vacuum breaker position is detected by those limit slvitches and are actuated by small arms attached to the valve shaft.The disc must travel approximately
                                                ~        MOHAWK 300 ERIE BOULEVARD WEST SYRACUSE, N Y. l3202 July 20, 1973
.2" before actuation of the limit switch is achieved.Thlerefore, the full potential accuracy cannot be realized due to the existing mounting of the switches.At, the present time, the system is under a staff review to determine what must be done to achieve the desired accuracy of.05"-.06" of disc movement.This review should be completed within a month and actual implimentations will take place, after appropriate reviews, within 30-60 days.The drywell vacuum breakers are completely accessible during the II Mr.Donald J.Skovholt United States Atomic Energy Commission Page 2 7/20/73 power operating condition and thus on line modifications can be made.Until the accuracy of.05"-.06" disc opening can be met and the alarm redundancy completed the following will be done: a.Each reactor transient involving the suppression chamber will be followed with an operability test of the drywell vacuum breaker valves.b.A dial indication will be installed on each valve accurate to indicate.06" move-ment of the disc.This system will provide a daily surveillance of valve closure within the acceptable limits as in ITEM 3 below.These indicators will be installed prior to August 1, 1973.'ITEM 2 During the valve operability test, when air is released from the air test cylinder the valve rapidly closes leaving operating personnel no action to take to manually close the valve.However, to preclude against manual closure.of the valve following testing a management person will be monitoring the testing at the test site (i.e.the valve location)to:assure that no manual intervention takes place.See Item 1 response regarding valve operability test and other additional surveillance to be done until ITEM 1 is complied with in full.ITEM 3 The limit on each individual valve will be set such that with all valves at their limit the maximum value of cumulative leakage will not exceed the maximum allowable.
                                                                              ~  III'r"g Jul  g5)gg~
The value will be approximately
II~idltlf Mr. Donald J. Skovholt Assistant Director for Reactor Operations                                   6'OIIQggIIII Division of Reactor Licensing United States Atomic Energy Commission Washington, D. C.     20545                                         O0,
.06" of disc'ravel off.its seat and will be alarmed in.the, control room.The torus instruments that would be used for surveillance testing and leak rate testing of the drywell vacuum breaker valves read out in the auxilary control room.Their range and accuracy are as follows: Pressure: 0-50 psia+.05 psi.Temperature
                                                              <<~)
: 0-200'F+1'F PSID 0-1.0 psid+.001 psi The instrumentation used by the operator during an LOCA are in the control room and include not only an indicated pressure instrument but a recorder as well.Their range and accuracy is as follows: Pressure: low 0-4 psig+.1 psi high 0-75 psig+1.5 psi Temperature
 
: 50-300'F+5'F The computer.also records the drywell and pressure suppression chamber pressure and temperature as follows:
==Dear Mr. Skovholt:==
e~~P P Mr.Donald J.Skovholt United States Atomic Energy Commission Page 3 7/20/73 Pressure: 0-40 psig+.1 psi-alarm at 2.5 psig Temperature
 
: 50-300'F+1'F alarm at 100'F Torus, 120'F Drywell ITEM 4 Td'chnical Specification Considerations Proposed Technical Specifications will be submitted separately, after the necessary reviews are complete.Consideration is, being given to adding the following conditions and surveillance requirements.
8 jp jogg Re:  Provisional Operating License:      DPR-17 Docket No.:    50-220 Regarding your   letter requesting additional information concerning the drywell vacuum breakers     at Nine Mile Point Nuclear Station Unit 81, the following is submitted:
Limiting Conditions for Operation 3.3.6 Drywell Pressure Suppression Chamber Vacuum Breakers a.lien primary containment is required, all drywell-suppression chamber vacuum breakers shall be operable and positioned in the closed position as indicated by the position indication system, except during testing and except as specified in 3.3.6 b and c, below.b.Any drywell-suppression chamber vacuum breaker may.=be non-fully closed as indicated by the position indication system provided that a drywell to torus pressure differential can be maintained greater than 1/2 the initial differential pressure for 1 hour with no N2 makeup.c.Up to one drywell-suppression chamber vacuum breaker may be secured in the closed position.d.If Specifications 3.3.6 a, b or c cannot be met, the situation shall be corrected within 24 hours or.the xeactor.shall be placed in a cold shut=down condition within 24 hours.Surveillance Requirements 4.3.6 Drywell-Pressuxe Suppression Chamber Vacuum Breakers a.Each drywell-suppression chamber vacuum breaker shall be exercised through an opening-closing cycle monthly.b.1&en it is determined that any vacuum breaker valve is not fully closed as indicated by the position indication system at a time when such closure is required, the apparently malfunctioning vacuum breaker valves shall be exercised and pressure tested as specified in 3.3.6 b immediately and" every 15 days thereafter until the apparently malfunctioning valves have been returned to normal service.c.Once each operating cycle, each vacuum breaker valve shall be visually inspected to ensure proper maintenance and operation.
ITEM 1 The present position indicating system utilizes two sets of limit switches, the snap lock limit switch manufactured by the National Acme Company and the Honey-well Model DTE6-2RN heavy duty, micro switches. The snap lock limit switch is used to determine and indicate the open position of any one valve'to the control room.
E, r~~I~~~~~~~~
The Honeywell micro switch is used to determine and indicate the closed position of any one valve to the control room. This system was reviewed during the Spring",.I973 refueling outage and the Honeywell micro switches installed at that time. Since the purpose of these limit switches is to provide the control room operator with information regarding the position of the breaker valves, physical separation of the control wiring or indicating lights is not required. However, an additional Honeywell limit, switch will be installed to detect the closed position and provide an alarm to the control room in the event any drywell vacuum breaker valve moves off its seat a predetermined amount. Redundances in the alarm circuit will thus be provided and IEEE 279 criteria satisfied. The pretravel on the Honeywell 'switch is
her.,Donald J.Skovholt United'tates Atomic Energy Commission Page 4 7/20/73 d.A leak test of the drywell to suppression chamber structure shall be conducted during each refueling outage.Ne believe this report to be responsive to all items enumerated in your letter.Very truly yours, 1 e1 e Vice President-Electric Operations RRS:pw-0 0'I 4}}
.065" maximum and measurements have shown them to be .04" of pretravel. The vacuum breaker position is detected by those limit slvitches and are actuated by small arms attached to the valve shaft. The disc must travel approximately .2" before actuation of the limit switch is achieved. Thlerefore, the full potential accuracy cannot be realized due to the existing mounting of the switches. At, the present time, the system is under a staff review to determine what must be done to achieve the desired accuracy of .05" - .06" of disc movement. This review should be completed within a month and actual implimentations will take place, after appropriate reviews, within 30 - 60 days. The drywell vacuum breakers are completely accessible during the
 
II Mr. Donald J. Skovholt                                                           Page  2 United States Atomic Energy Commission                                           7/20/73 power operating condition and thus on line modifications can be made. Until the accuracy of .05" - .06" disc opening can be met and the alarm redundancy completed the following will be done:
: a. Each reactor transient involving the suppression chamber     will be followed with an operability test of the drywell vacuum breaker valves.
: b. A dial indication will be installed on each valve accurate to indicate .06" move-ment of the disc. This system will provide a daily surveillance of valve closure within the acceptable limits as in ITEM 3 below. These indicators will be installed prior to August 1, 1973.
'ITEM 2 During the valve operability test, when air is released from the air test cylinder the valve rapidly closes leaving operating personnel no action to take to manually close the valve. However, to preclude against manual closure. of the valve following testing a management person will be monitoring the testing at the test site (i.e. the valve location) to:assure that no manual intervention takes place.
See Item 1 response regarding valve operability test and other additional surveillance to be done until ITEM 1 is complied with in full.
ITEM 3 The limit on each individual valve will be set such that with all valves at their limit the maximum value of cumulative leakage will not exceed the maximum allowable. The value will be approximately .06" of disc'ravel off .its seat and will be alarmed in .the, control room. The torus instruments that would be used for surveillance testing and leak rate testing of the drywell vacuum breaker valves read out in the auxilary control room. Their range and accuracy are as follows:
Pressure     : 0 -   50 psia +.05 psi.
Temperature   : 0 - 200'F +1'F PSID             0 -     1.0 psid +.001 psi The instrumentation used by the operator during an LOCA are in the control room and include not only an indicated pressure instrument but a recorder as well. Their range and accuracy   is   as follows:
Pressure     : low 0   - 4 psig +.1 psi high 0 -75 psig +1.5 psi Temperature   : 50 - 300'F +5'F The computer. also records   the drywell and pressure suppression chamber pressure and temperature as follows:
 
e
    ~   ~
P P
 
Mr. Donald J. Skovholt                                                               Page  3 United States Atomic Energy Commission                                               7/20/73 Pressure     : 0 - 40 psig +.1 psi-alarm at 2.5 psig Temperature   : 50   - 300'F +1'F alarm at 100'F Torus, 120'F Drywell ITEM 4 Td'chnical Specification Considerations Proposed Technical Specifications will be submitted separately, after the necessary reviews are complete. Consideration is, being given to adding the following conditions and surveillance requirements.
Limiting Conditions for Operation 3.3.6   Drywell Pressure Suppression Chamber     Vacuum Breakers
: a. lien primary containment is required,       all drywell-suppression chamber vacuum breakers shall be operable and positioned in the closed       position as indicated by the position indication system, except during       testing and except as specified in 3.3.6 b and c, below.
: b. Any   drywell-suppression chamber vacuum breaker may.=be non-fully closed as indicated by the position indication system provided that a drywell to torus pressure differential can be maintained greater than 1/2 the initial differential pressure for 1 hour with no N2 makeup.
: c. Up to   one drywell-suppression chamber vacuum breaker   may be secured   in the closed position.
: d. If Specifications 3.3.6 a, b or c cannot be met, the situation shall be corrected within 24 hours or .the xeactor .shall be placed in a cold shut=
down condition within 24 hours.
Surveillance Requirements 4.3.6   Drywell-Pressuxe Suppression Chamber Vacuum Breakers
: a. Each drywell-suppression chamber vacuum breaker shall be exercised through an opening-closing cycle monthly.
: b. 1&en   it is determined that any vacuum breaker valve is not   fully closed as indicated by the position indication system at a time when such closure is required, the apparently malfunctioning vacuum breaker valves shall be exercised and pressure tested as specified in 3.3.6 b immediately and" every 15 days thereafter     until the apparently malfunctioning valves have been   returned to normal service.
: c. Once each   operating cycle, each vacuum breaker valve shall be visually inspected to ensure proper maintenance and operation.
 
E, r
                ~ ~
I
      ~ ~
          ~ ~
                ~ ~
~ ~
 
her.,Donald J. Skovholt                                                         Page  4 United'tates Atomic Energy Commission                                           7/20/73
: d. A leak test of the drywell to suppression chamber structure shall be conducted during each refueling outage.
Ne believe this report to be responsive to all items enumerated in your letter.
Very truly yours, 1 e1 e Vice President - Electric Operations RRS:pw-
 
0   0 '
I 4}}

Latest revision as of 19:59, 4 February 2020

Letter Responding to a Request for Additional Information Concerning the Drywell Vacuum Breakers
ML17037C261
Person / Time
Site: Nine Mile Point Constellation icon.png
Issue date: 07/20/1973
From: Schneider R
Niagara Mohawk Power Corp
To: Skovholt D
US Atomic Energy Commission (AEC)
References
Download: ML17037C261 (10)


Text

.AEC DIS BUTION FOR PART 50 DOCKET MA FORM) CONTROL NO:

~AL'TEMPORARY PILE:

'RON: DATE OF DOC DATE REC'D MEMO RPT OTHER Niagara Mohawk Power Corporation R. R.

TO Schneider'-20-73 Syracuse, N. Y. 13202 ORIG CC 7-25-73 OTHER SENT AEC PDR X SENT LOCAL PDR X vh 3 si~ned CLASS UNCLASS PROP INFO INPUT NO S REC'D DOCKET NO:

XX 40 50-220 DESCRIPTION: ENCLOSURES:

Ltr furnishing requested info re drywell vacuum breakers at the Nine Mile Point Nuclear Station Unit 0 l.......

NQJil/>ggg PLANT NAME.. Nine Mile Point Unit 8 1

~t~

Do,go< Remove FOR ACTION/INFORMATION 7-25-73 AB BUTLER(L) SCHWENCER(L) NIEMANN(L) REGAN(E)

W/ Copies W/ Copies W/ 6 Copies W/ Copies CLARK(L) STOLZ(L) DICKER(E)

W/ Copies W/ Copies W/ Copies W/ Copies GOLLER(L) VASSALLO(L) KNIGHTON (E)

W/ 'Copies W/ 'Copies W/ Copies 'W/ Copies KNIEL(L) SCHEMEL(L) YOUNGBLOOD(E)

W/ Copies W/ Copies W/ Copies W/ Copies INTERNAL DISTRIBUTION G PI TECH REVIEW DENTON LIC ASST A/T IND R HENDRIE GRIMES BR(MN (E) BRAT IMAN OGC, ROON P-506A SCHROEDER GRMILL DIGGS (L) SALTZMAN

~ MUNTZING/STAFF CASE MACCARY KNIGHT

'ASTNER BALLARD GEARIN (L)

GOULBOURNE (L) PLANS GIAMBUSSO PAWLICKI SPANGLER LEE (L) MCDONALD BOYD SHAO MAIGRET (L) DUBE MOORE (L) (BWR) STELLO ENVIRO SERVICE (L)

DEYOUNG (L) (PWR) HOUSTON MULLER SHEPPARD (E) INFO

~SKOVHOLT (L) NOVAK DICKER SMITH (L) C. MILES P. COLLINS ROSS IPPOLITO KNIGHTON YOUNGBLOOD TEETS WADE (L),

(E)

~ J. RIESLAND W. BUTLER REG OPR ~ TEDESCO REGAN WILLIAMS (E) + STOLZ

~ILE & REGION(3) LONG PROJECT LDR WILSON (L) CLARK MORRIS ~LAINAS STEELE BENAROYA HARLESS VOLIMER EXTERNAL DISTRIBUTION

~l <<LOCAL PDR

- DTIE(ABERNATHY)

~1

~ 1 NSIC(BUCHANAN)

ASLB(YORE/SAYRE/

(l)(2)(9)-NATIONALLAB'S

'1-R.Schoonmaker,OC,GT,D-323 1-R. CATLIN) E-256-GT 1-PDR-SAN/LA/K(

1-GERALD LELLOU0 BROOKHAVEN NAT. LAB WOODARD/ "H" ST. 1-CONSULTANT' 1-AGMED(WALTER KOESTER 16 - CYS ACRS HGMRHG SENT TO LIC ASST. NEWARK/BLAT/AGBABIAN RM-C-427"GT R. DIGGS ON 7-25-.73 3."GERALD ULRIKSON ~ ORNL 1-RD MULLER. F-309 GT

C o t

~ t l, I'

.AeIYutatory NIAGARA MOHAWK POWER CORPORATION NIAGARA

~ MOHAWK 300 ERIE BOULEVARD WEST SYRACUSE, N Y. l3202 July 20, 1973

~ III'r"g Jul g5)gg~

II~idltlf Mr. Donald J. Skovholt Assistant Director for Reactor Operations 6'OIIQggIIII Division of Reactor Licensing United States Atomic Energy Commission Washington, D. C. 20545 O0,

<<~)

Dear Mr. Skovholt:

8 jp jogg Re: Provisional Operating License: DPR-17 Docket No.: 50-220 Regarding your letter requesting additional information concerning the drywell vacuum breakers at Nine Mile Point Nuclear Station Unit 81, the following is submitted:

ITEM 1 The present position indicating system utilizes two sets of limit switches, the snap lock limit switch manufactured by the National Acme Company and the Honey-well Model DTE6-2RN heavy duty, micro switches. The snap lock limit switch is used to determine and indicate the open position of any one valve'to the control room.

The Honeywell micro switch is used to determine and indicate the closed position of any one valve to the control room. This system was reviewed during the Spring",.I973 refueling outage and the Honeywell micro switches installed at that time. Since the purpose of these limit switches is to provide the control room operator with information regarding the position of the breaker valves, physical separation of the control wiring or indicating lights is not required. However, an additional Honeywell limit, switch will be installed to detect the closed position and provide an alarm to the control room in the event any drywell vacuum breaker valve moves off its seat a predetermined amount. Redundances in the alarm circuit will thus be provided and IEEE 279 criteria satisfied. The pretravel on the Honeywell 'switch is

.065" maximum and measurements have shown them to be .04" of pretravel. The vacuum breaker position is detected by those limit slvitches and are actuated by small arms attached to the valve shaft. The disc must travel approximately .2" before actuation of the limit switch is achieved. Thlerefore, the full potential accuracy cannot be realized due to the existing mounting of the switches. At, the present time, the system is under a staff review to determine what must be done to achieve the desired accuracy of .05" - .06" of disc movement. This review should be completed within a month and actual implimentations will take place, after appropriate reviews, within 30 - 60 days. The drywell vacuum breakers are completely accessible during the

II Mr. Donald J. Skovholt Page 2 United States Atomic Energy Commission 7/20/73 power operating condition and thus on line modifications can be made. Until the accuracy of .05" - .06" disc opening can be met and the alarm redundancy completed the following will be done:

a. Each reactor transient involving the suppression chamber will be followed with an operability test of the drywell vacuum breaker valves.
b. A dial indication will be installed on each valve accurate to indicate .06" move-ment of the disc. This system will provide a daily surveillance of valve closure within the acceptable limits as in ITEM 3 below. These indicators will be installed prior to August 1, 1973.

'ITEM 2 During the valve operability test, when air is released from the air test cylinder the valve rapidly closes leaving operating personnel no action to take to manually close the valve. However, to preclude against manual closure. of the valve following testing a management person will be monitoring the testing at the test site (i.e. the valve location) to:assure that no manual intervention takes place.

See Item 1 response regarding valve operability test and other additional surveillance to be done until ITEM 1 is complied with in full.

ITEM 3 The limit on each individual valve will be set such that with all valves at their limit the maximum value of cumulative leakage will not exceed the maximum allowable. The value will be approximately .06" of disc'ravel off .its seat and will be alarmed in .the, control room. The torus instruments that would be used for surveillance testing and leak rate testing of the drywell vacuum breaker valves read out in the auxilary control room. Their range and accuracy are as follows:

Pressure  : 0 - 50 psia +.05 psi.

Temperature  : 0 - 200'F +1'F PSID 0 - 1.0 psid +.001 psi The instrumentation used by the operator during an LOCA are in the control room and include not only an indicated pressure instrument but a recorder as well. Their range and accuracy is as follows:

Pressure  : low 0 - 4 psig +.1 psi high 0 -75 psig +1.5 psi Temperature  : 50 - 300'F +5'F The computer. also records the drywell and pressure suppression chamber pressure and temperature as follows:

e

~ ~

P P

Mr. Donald J. Skovholt Page 3 United States Atomic Energy Commission 7/20/73 Pressure  : 0 - 40 psig +.1 psi-alarm at 2.5 psig Temperature  : 50 - 300'F +1'F alarm at 100'F Torus, 120'F Drywell ITEM 4 Td'chnical Specification Considerations Proposed Technical Specifications will be submitted separately, after the necessary reviews are complete. Consideration is, being given to adding the following conditions and surveillance requirements.

Limiting Conditions for Operation 3.3.6 Drywell Pressure Suppression Chamber Vacuum Breakers

a. lien primary containment is required, all drywell-suppression chamber vacuum breakers shall be operable and positioned in the closed position as indicated by the position indication system, except during testing and except as specified in 3.3.6 b and c, below.
b. Any drywell-suppression chamber vacuum breaker may.=be non-fully closed as indicated by the position indication system provided that a drywell to torus pressure differential can be maintained greater than 1/2 the initial differential pressure for 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> with no N2 makeup.
c. Up to one drywell-suppression chamber vacuum breaker may be secured in the closed position.
d. If Specifications 3.3.6 a, b or c cannot be met, the situation shall be corrected within 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> or .the xeactor .shall be placed in a cold shut=

down condition within 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />.

Surveillance Requirements 4.3.6 Drywell-Pressuxe Suppression Chamber Vacuum Breakers

a. Each drywell-suppression chamber vacuum breaker shall be exercised through an opening-closing cycle monthly.
b. 1&en it is determined that any vacuum breaker valve is not fully closed as indicated by the position indication system at a time when such closure is required, the apparently malfunctioning vacuum breaker valves shall be exercised and pressure tested as specified in 3.3.6 b immediately and" every 15 days thereafter until the apparently malfunctioning valves have been returned to normal service.
c. Once each operating cycle, each vacuum breaker valve shall be visually inspected to ensure proper maintenance and operation.

E, r

~ ~

I

~ ~

~ ~

~ ~

~ ~

her.,Donald J. Skovholt Page 4 United'tates Atomic Energy Commission 7/20/73

d. A leak test of the drywell to suppression chamber structure shall be conducted during each refueling outage.

Ne believe this report to be responsive to all items enumerated in your letter.

Very truly yours, 1 e1 e Vice President - Electric Operations RRS:pw-