{{#Wiki_filter:UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION In the Matter of ENTERGY NUCLEAR OPERATIONS, INC., ENTERGY NUCLEAR GENERATION COMPANY, HOLTEC INTERNATIONAL, AND HOLTEC DECOMMISSIONING INTERNATIONAL, LLC | {{#Wiki_filter:UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION In the Matter of ENTERGY NUCLEAR OPERATIONS, INC., Docket No. 50-293-LT ENTERGY NUCLEAR GENERATION 72-1044-LT COMPANY, HOLTEC INTERNATIONAL, AND HOLTEC DECOMMISSIONING INTERNATIONAL, LLC (Pilgrim Nuclear Power Station) | ||
ORDER The Commonwealth of Massachusetts has requested an extension of time in which it may file, pursuant to 10 C.F.R. § 2.1327(a), an application for a stay of the immediate effectiveness of an NRC Staff order on the license transfer application. 1 Pursuant to my authority under 10 C.F.R. § 2.346(b), I grant the motion. Accordingly, the time for the Commonwealth and Pilgrim Watch to file an application for a stay is extended by five days, as well as any additional days afforded by 10 C.F.R. § 2.306(a). | |||
For the Commission NRC Seal | |||
1 | /RA/ | ||
Annette L. Vietti-Cook | Annette L. Vietti-Cook Secretary of the Commission Dated at Rockville, Maryland, this 21st day of August 2019 1 | ||
Emergency Motion of the Commonwealth of Massachusetts for an Enlargement of Time to File an Application to Stay a Nuclear Regulatory Commission Staff Order Approving the License Transfer Application (Aug. 15, 2019). The Applicants opposed the motion. See Applicants Answer Opposing the Motion of the Commonwealth of Massachusetts for an Enlargement of Time to File an Application for Stay (Aug. 16, 2019). | |||
UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION In the Matter of ) | |||
. | ) | ||
ENTERGY NUCLEAR OPERATIONS, INC. ) | |||
ENTERGY NUCLEAR GENERATION ) Docket Nos. 50-293 and 72-1044 LT COMPANY, HOLTEC INTERNATIONAL, ) | |||
and HOLTEC DECOMMISSIONING ) | |||
INTERNATIONAL, LLC ) | |||
) | |||
(Pilgrim Nuclear Power Station ) | |||
CERTIFICATE OF SERVICE I hereby certify that copies of the foregoing ORDER (Granting Motion for Extension of Time), | |||
have been served upon the following persons by Electronic Information Exchange. | |||
U.S. Nuclear Regulatory Commission U.S. Nuclear Regulatory Commission Office of Commission Appellate Adjudication Office of the General Counsel Mail Stop: O-16B33 Mail Stop - O-14A44 Washington, DC 20555-0001 Washington, DC 20555-0001 E-mail: ocaamail@nrc.gov Tison A. Campbell, Esq. | |||
Anita G. Naber, Esq. | |||
U.S. Nuclear Regulatory Commission David E. Roth, Esq. | |||
Office of the Secretary of the Commission Rebecca A. Susko, Esq. | |||
Mail Stop: O-16B33 Jeremy L. Wachutka, Esq. | |||
Washington, DC 20555-0001 Jennifer E. Scro, Esq. | |||
E-mail: hearingdocket@nrc.gov E-mail: Tison.Campbell@nrc.gov Anita.Naber@nrc.gov Atomic Safety and Licensing Board Panel David.Roth@nrc.gov U.S. Nuclear Regulatory Commission Rebecca.Susko@nrc.gov Washington, DC 20555-0001 Jeremy.Wachutka@nrc.gov E. Roy Hawkens, Chairman Jennifer.Scro@nrc.gov E-mail: Roy.Hawkens@nrc.gov Entergy Services, Inc. | |||
101 Constitution Ave., NW Suite 200 East Washington, DC 20001 Susan H. Raimo E-mail: sraimo@entergy.com | |||
Pilgrim Nuclear Power Station Docket Nos. 50-293 and 72-1044 LT ORDER (Granting Motion for Extension of Time) | |||
Balch & Bingham LLP Pilgrim Watch 1710 Sixth Avenue North F148 Washington Street Birmingham, AL 35203-2015 Duxbury, MA 02332 Peter R. LeJeune, Esq Mary Lampert, Director Alan D. Lovett, Esq, E-mail: Mary.Lampert@comcast.net E-mail: plejeune@balch.com alovett@balch.com Counsel for the Commonwealth of Massachusetts: | |||
Pillsbury Winthrop Shaw Pittman LLP Energy and Environmental Bureau 1200 Seventeenth Street, NW Office of the Attorney General Washington, DC 20036 One Ashburton Place, 18th Floor Meghan Hammond, Esq. Boston, Massachusetts 02108 David R. Lewis, Esq. Joseph Dorfler, Esq. | |||
E-mail: Meghan.Hammond@pillsburylaw.com Seth Schofield, Esq. | |||
David.Lewis@pillsburylaw.com E-mail: Joseph.Dorfler@state.ma.gov Seth.Schofield@mass.gov | |||
[Original signed by Krupskaya T. Castellon] | |||
Office of the Secretary of the Commission Dated at Rockville, Maryland, this 21th day of August 2019 2}} | |||
Pilgrim Nuclear Power Station Docket Nos. 50- | |||
-2015 Peter R. LeJeune, Esq Alan D. Lovett, Esq, E-mail: | |||
Pillsbury Winthrop Shaw Pittman LLP 1200 Seventeenth Street, NW Washington, DC | |||
David R. Lewis, Esq. E-mail: | |||
E-mail: | |||
[Original signed by Krupskaya T. Castellon] |
Revision as of 02:21, 2 February 2020
ML19233A289 | |
Person / Time | |
---|---|
Site: | Pilgrim |
Issue date: | 08/21/2019 |
From: | Annette Vietti-Cook NRC/SECY |
To: | NRC/OCM |
SECY RAS | |
References | |
50-293 LT, 72-1044 LT, License Transfer, RAS 55187 | |
Download: ML19233A289 (3) | |
Text
UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION In the Matter of ENTERGY NUCLEAR OPERATIONS, INC., Docket No. 50-293-LT ENTERGY NUCLEAR GENERATION 72-1044-LT COMPANY, HOLTEC INTERNATIONAL, AND HOLTEC DECOMMISSIONING INTERNATIONAL, LLC (Pilgrim Nuclear Power Station)
ORDER The Commonwealth of Massachusetts has requested an extension of time in which it may file, pursuant to 10 C.F.R. § 2.1327(a), an application for a stay of the immediate effectiveness of an NRC Staff order on the license transfer application. 1 Pursuant to my authority under 10 C.F.R. § 2.346(b), I grant the motion. Accordingly, the time for the Commonwealth and Pilgrim Watch to file an application for a stay is extended by five days, as well as any additional days afforded by 10 C.F.R. § 2.306(a).
For the Commission NRC Seal
/RA/
Annette L. Vietti-Cook Secretary of the Commission Dated at Rockville, Maryland, this 21st day of August 2019 1
Emergency Motion of the Commonwealth of Massachusetts for an Enlargement of Time to File an Application to Stay a Nuclear Regulatory Commission Staff Order Approving the License Transfer Application (Aug. 15, 2019). The Applicants opposed the motion. See Applicants Answer Opposing the Motion of the Commonwealth of Massachusetts for an Enlargement of Time to File an Application for Stay (Aug. 16, 2019).
UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION In the Matter of )
)
ENTERGY NUCLEAR OPERATIONS, INC. )
ENTERGY NUCLEAR GENERATION ) Docket Nos. 50-293 and 72-1044 LT COMPANY, HOLTEC INTERNATIONAL, )
and HOLTEC DECOMMISSIONING )
INTERNATIONAL, LLC )
)
(Pilgrim Nuclear Power Station )
CERTIFICATE OF SERVICE I hereby certify that copies of the foregoing ORDER (Granting Motion for Extension of Time),
have been served upon the following persons by Electronic Information Exchange.
U.S. Nuclear Regulatory Commission U.S. Nuclear Regulatory Commission Office of Commission Appellate Adjudication Office of the General Counsel Mail Stop: O-16B33 Mail Stop - O-14A44 Washington, DC 20555-0001 Washington, DC 20555-0001 E-mail: ocaamail@nrc.gov Tison A. Campbell, Esq.
Anita G. Naber, Esq.
U.S. Nuclear Regulatory Commission David E. Roth, Esq.
Office of the Secretary of the Commission Rebecca A. Susko, Esq.
Mail Stop: O-16B33 Jeremy L. Wachutka, Esq.
Washington, DC 20555-0001 Jennifer E. Scro, Esq.
E-mail: hearingdocket@nrc.gov E-mail: Tison.Campbell@nrc.gov Anita.Naber@nrc.gov Atomic Safety and Licensing Board Panel David.Roth@nrc.gov U.S. Nuclear Regulatory Commission Rebecca.Susko@nrc.gov Washington, DC 20555-0001 Jeremy.Wachutka@nrc.gov E. Roy Hawkens, Chairman Jennifer.Scro@nrc.gov E-mail: Roy.Hawkens@nrc.gov Entergy Services, Inc.
101 Constitution Ave., NW Suite 200 East Washington, DC 20001 Susan H. Raimo E-mail: sraimo@entergy.com
Pilgrim Nuclear Power Station Docket Nos. 50-293 and 72-1044 LT ORDER (Granting Motion for Extension of Time)
Balch & Bingham LLP Pilgrim Watch 1710 Sixth Avenue North F148 Washington Street Birmingham, AL 35203-2015 Duxbury, MA 02332 Peter R. LeJeune, Esq Mary Lampert, Director Alan D. Lovett, Esq, E-mail: Mary.Lampert@comcast.net E-mail: plejeune@balch.com alovett@balch.com Counsel for the Commonwealth of Massachusetts:
Pillsbury Winthrop Shaw Pittman LLP Energy and Environmental Bureau 1200 Seventeenth Street, NW Office of the Attorney General Washington, DC 20036 One Ashburton Place, 18th Floor Meghan Hammond, Esq. Boston, Massachusetts 02108 David R. Lewis, Esq. Joseph Dorfler, Esq.
E-mail: Meghan.Hammond@pillsburylaw.com Seth Schofield, Esq.
David.Lewis@pillsburylaw.com E-mail: Joseph.Dorfler@state.ma.gov Seth.Schofield@mass.gov
[Original signed by Krupskaya T. Castellon]
Office of the Secretary of the Commission Dated at Rockville, Maryland, this 21th day of August 2019 2