| title = | | title = Information Request for an NRC Triennial Permanent Modifications and 10 CFR 50.59 Baseline Inspection 05000263/2016008 (Akd) | ||
| author name = Daley R | | author name = Daley R | ||
| author affiliation = NRC/RGN-III/DRS/EB3 | | author affiliation = NRC/RGN-III/DRS/EB3 | ||
| addressee name = Gardner P | | addressee name = Gardner P | ||
| addressee affiliation = Northern States Power Co | | addressee affiliation = Northern States Power Co | ||
| docket = 05000263 | | docket = 05000263 | ||
Line 14: | Line 14: | ||
| page count = 7 | | page count = 7 | ||
}} | }} | ||
See also: [[ | See also: [[see also::IR 05000263/2016008]] | ||
=Text= | =Text= | ||
{{#Wiki_filter: | {{#Wiki_filter:UNITED STATES | ||
NUCLEAR REGULATORY COMMISSION | |||
REGION III | |||
2443 WARRENVILLE RD. SUITE 210 | |||
LISLE, IL 60532-4352 | |||
October 29, 2015 | |||
Mr. Peter A. Gardner | |||
Site Vice President | |||
Monticello Nuclear Generating Plant | |||
Northern States Power Company, Minnesota | |||
2807 West County Road 75 | |||
Monticello, MN 55362-9637 | |||
SUBJECT: MONTICELLO NUCLEAR GENERATING PLANT - INFORMATION REQUEST | |||
FOR AN NRC TRIENNIAL PERMANENT MODIFICATIONS AND 10 CFR 50.59 | |||
BASELINE INSPECTION 05000263/2016008 | |||
Dear Mr. Gardner: | |||
On February 29, 2016, the U.S. Nuclear Regulatory Commission (NRC) will begin a | |||
MOD/50.59 Baseline Inspection at the Monticello Nuclear Generating Plant. This inspection | |||
will be performed in accordance with the NRC Baseline Inspection Procedure 71111.17T. | |||
The onsite portion of the inspection will take place on February 29 - March 4, 2016, and | |||
March 14 - 18, 2016. | |||
Experience has shown that these baseline inspections are extremely resource intensive, both | |||
for the NRC inspectors and the licensee staff. In order to minimize the inspection impact on | |||
the site, and to ensure a productive inspection for both parties, we have enclosed a request for | |||
documents needed for the inspection. These documents have been divided into three groups. | |||
The first group of information is necessary to ensure that the inspection team is adequately | |||
prepared for the inspection. This information should be made available via compact disc and | |||
delivered to the regional office no later than December 17, 2015. The inspection team will | |||
review this information and, by January 15, 2016, will request specific items that should be | |||
provided for review in the regional office by February 12, 2016. | |||
The second group of requested documents contains additional items that the team will | |||
review, or need access to, during the inspection. Certain documents contained within | |||
Group II (i.e., Item [1]), will be requested for review in the regional office prior to the inspection | |||
by February 12, 2016, as identified above. The remaining documents should be available by | |||
the first day of the onsite inspection, February 29, 2016. | |||
The third group lists information necessary to aid the inspection team in tracking issues | |||
identified as a result of the inspection. It is requested that this information be provided to the | |||
lead inspector as the information is generated during the inspection. It is important that all of | |||
these documents are up-to-date and complete in order to minimize the number of additional | |||
documents requested during the preparation and/or the onsite portions of the inspection. | |||
Mr. | P. Gardner -2- | ||
The lead inspector for this inspection is Mr. Alan Dahbur. We understand that our regulatory | |||
contact for this inspection is Mr. Andy Kouba of your organization. If there are any questions | |||
about the inspection or the material requested, please contact the lead inspector at | |||
(630) 829-9810, or via e-mail at Alan.Dahbur@nrc.gov. | |||
This letter does not contain new or amended information collection requirements subject to | |||
the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information | |||
collection requirements were approved by the Office of Management and Budget, Control | |||
Number 3150-0011. The NRC may not conduct or sponsor, and a person is not required to | |||
respond to, a request for information or an information collection requirement unless the | |||
requesting document displays a currently valid Office of Management and Budget Control | |||
Number. | |||
In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390, Public | |||
Inspections, Exemptions, Requests for Withholding, of the NRC's "Rules of Practice," a copy | |||
of this letter, its enclosure, and your response (if any) will be available electronically for public | |||
inspection in the NRCs Public Document Room or from the Publicly Available Records (PARS) | |||
component of the NRC's Agencywide Documents Access and Management System (ADAMS). | |||
ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html | |||
(the Public Electronic Reading Room). | |||
Sincerely, | |||
/RA/ | |||
Robert C. Daley, Chief | |||
Engineering Branch 3 | |||
Division of Reactor Safety | |||
Docket No. 50-263 | |||
License No. DPR-22 | |||
Enclosure: | |||
Modification and 50.59 Inspection Document Request | |||
cc w/encl: Distribution via LISTSERV | |||
Inspection Report: 05000263/2016008 | |||
Inspection Dates: February 29 - March 4, 2016, and March 14 - 18, 2016 | |||
Inspection Procedure: Inspection Procedure 71111.17T, Evaluations of Changes, Tests, | |||
and Experiments and Permanent Plant Modifications | |||
Lead Inspector: Alan Dahbur | |||
(630) 829-9810 | |||
Alan.Dahbur@nrc.gov | |||
I. Information Requested for In-Office Preparation Week | |||
The following information is requested by December 17, 2015, or sooner, to facilitate | |||
the selection of specific items that will be reviewed during the onsite inspection week. | |||
The inspection team will select specific items from the information requested below, | |||
and submit a list to your staff by January 15, 2016. We will request that certain items | |||
be made available to the regional office prior to the inspection by February 12, 2016. | |||
We request that the remaining items selected from the lists be available and ready for | |||
review on the first day of inspection. All requested information should identify the | |||
associated system and cover the time frame from the receipt of information for the | |||
last MOD/50.59 inspection November 4, 2013, to the present. | |||
The required information identified below should be provided on compact disc (CD). | |||
Please provide three copies of each CD submitted (i.e., one for each inspector). | |||
The preferred file format is a searchable pdf file. The CDs should be indexed and | |||
hyper-linked to facilitate ease of use, if possible. If you have any questions regarding | |||
this information, please call the inspection team leader as soon as possible. | |||
(1) List of permanent plant modifications to systems, structures or components that | |||
are field work complete. (For the purpose of this inspection, permanent plant | |||
modifications include permanent: plant changes, design changes, set point | |||
changes, equivalency evaluations, suitability analyses, and commercial grade | |||
dedications.) | |||
The list should contain the number of each document, the title, the revision | |||
(or date), and the affected system. In addition to the list, please provide a | |||
description of each modification and a list of associated calculations and | |||
affected procedures. | |||
(2) List of all Title 10, Code of Federal Regulations (CFR), Part 50.59 completed | |||
evaluations involving: (a) calculations; (b) procedure revisions; (c) changes | |||
to the facility (modifications); (d) non-routine operating configurations; or | |||
(e) departures in methods of analyses. This list should include 50.59 | |||
evaluations for the following: | |||
a. Changes that have been made under the provisions of 10 CFR 50.59 that | |||
have been updated in accordance with 10 CFR 50.71(e)(4) since the last | |||
MOD/50.59 inspection; | |||
Enclosure | |||
b. Modifications that are field work complete; and | |||
c. Changes to calculations (or initiation of new calculations) that have been | |||
issued. The list should contain the number and title of each document, a | |||
brief description of the change, and the corresponding number and type of | |||
the affected document (i.e., the modification or procedure to which the | |||
evaluation applies). The list should NOT include any evaluations in which | |||
prior U.S. Nuclear Regulatory Commission approval was sought and | |||
obtained. | |||
(3) A list of all 10 CFR 50.59 changes that have been screened out as not requiring | |||
a full evaluation involving: (a) calculations; (b) procedure revisions; (c) changes | |||
to the facility (modifications); (d) non-routine operating configurations; or | |||
(e) departures in methods of analyses. | |||
The list should contain the number and title of each document, a brief description | |||
of the change, and the corresponding number and type of the affected document | |||
(i.e., the modification or procedure to which the evaluation applies). | |||
(4) A list of any modifications, procedure revisions, or Updated Final Safety Analysis | |||
Report (UFSAR) changes where it was determined that 10 CFR 50.59 did not | |||
apply. | |||
(5) A list of calculation changes that have been issued for use. | |||
(6) A list of corrective action documents (open and closed) that address permanent | |||
plant modifications or 10 CFR 50.59 issues, concerns, or processes. These | |||
documents should also include the corrective action documents associated with | |||
the modification and the 50.59 change implementation. | |||
The list should contain the number, title and revision (or date) of each document, | |||
the affected system and corresponding documentation (if applicable), and should | |||
be sorted in order of significance. | |||
(7) Copies of procedures addressing the following: modifications, design changes, | |||
set point changes, equivalency evaluations or suitability analyses, commercial | |||
grade dedications, post-modification testing, 10 CFR 50.59 evaluations and | |||
screenings, and UFSAR updates. | |||
(8) UFSAR updates submitted in accordance with 10 CFR 50.71(e)(4). Provide | |||
copies of the complete submittal. | |||
(9) Copy of the UFSAR change log or a synopsis of the changes. This should | |||
include all of the changes made to the UFSAR that were incorporated in the last | |||
10 CFR 50.71(e)(4) submittal. | |||
(10) Electronic copy of the UFSAR and Technical Specifications (TSs), if available. | |||
(11) Name(s) and phone number(s) for the regulatory and technical contacts. | |||
(12) Current management and engineering organizational chart. | |||
2 | |||
II. Information Requested to be Available Prior to Inspection. Requests will be Made | |||
for Specific Item (1) Documents by January 15, 2016, for Availability of Requested | |||
Item (1) Documents in Regional Office by February 12, 2016, and Items (2), (3), and | |||
(4) Documents on First Day of Inspection (February 29, 2016) | |||
(1) Copies of all selected items from Section I. This includes copies of | |||
associated documents such as calculations, post-modification test packages, | |||
10 CFR 50.59 evaluations or screenings, and any corrective action documents. | |||
(2) Copies of these documents do not need to be solely available to the inspection | |||
team as long as the inspectors have easy and unrestrained access to them. | |||
a. UFSAR, if not previously provided; | |||
b. Original Final Safety Analysis Report (FSAR) Volumes; | |||
c. Original Safety Evaluation Reports and Supplements; | |||
d. FSAR Question and Answers; | |||
e. Quality Assurance (QA) Plan; | |||
f. TSs, if not previously provided; | |||
g. Latest Individual Plant Examination/Probabilistic Risk Assessment Report; | |||
h. Vendor Manuals; and | |||
i. The latest 10 CFR 50.59 UFSAR Update Submittal. | |||
(3) Please ensure that other supporting documents for the selected items have been | |||
located and are readily retrievable as the inspection team will likely be requesting | |||
these documents during the inspection. Examples of supporting documents are: | |||
a. Drawings supporting the modifications; | |||
b. Procedures affected by the modifications; and | |||
c. UFSAR change papers generated due to a 10 CFR 50.59 evaluation. | |||
(4) Assessment and Corrective Actions: | |||
a. The most recent MOD/50.59 QA audit and/or self-assessment; and | |||
b. Corrective action documents (e.g., condition reports, including status of | |||
corrective actions) generate as a result of the most recent MOD/50.59 QA | |||
audit and/or self-assessment. | |||
3 | |||
III. Information Requested to be provided throughout the inspection | |||
(1) Copies of any corrective action documents generated as a result of the | |||
inspection teams questions or queries during this inspection. | |||
(2) Copies of the list of questions submitted by the inspection team members and | |||
the status/resolution of the information requested (provide daily during the | |||
inspection to each inspection team member). | |||
If you have any questions regarding the information requested, please contact the inspection | |||
team leader. | |||
4 | |||
P. Gardner -2- | |||
The lead inspector for this inspection is Mr. Alan Dahbur. We understand that our regulatory | |||
contact for this inspection is Mr. Andy Kouba of your organization. If there are any questions | |||
about the inspection or the material requested, please contact the lead inspector at | |||
(630) 829-9810, or via e-mail at Alan.Dahbur@nrc.gov. | |||
This letter does not contain new or amended information collection requirements subject to | |||
the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information | |||
collection requirements were approved by the Office of Management and Budget, Control | |||
Number 3150-0011. The NRC may not conduct or sponsor, and a person is not required to | |||
respond to, a request for information or an information collection requirement unless the | |||
requesting document displays a currently valid Office of Management and Budget Control | |||
Number. | |||
In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390, Public | |||
Inspections, Exemptions, Requests for Withholding, of the NRC's "Rules of Practice," a copy | |||
of this letter, its enclosure, and your response (if any) will be available electronically for public | |||
inspection in the NRCs Public Document Room or from the Publicly Available Records (PARS) | |||
component of the NRC's Agencywide Documents Access and Management System (ADAMS). | |||
ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html | |||
(the Public Electronic Reading Room). | |||
Sincerely, | |||
/RA/ | |||
Robert C. Daley, Chief | |||
Engineering Branch 3 | |||
Division of Reactor Safety | |||
Docket No. 50-263 | |||
License No. DPR-22 | |||
Enclosure: | |||
Modification and 50.59 Inspection Document Request | |||
cc w/encl: Distribution via LISTSERV | |||
DISTRIBUTION w/encl: | |||
Janelle Jessie Darrell Roberts DRPIII | |||
RidsNrrDorlLpl3-1 Resource Richard Skokowski DRSIII | |||
RidsNrrPMMonticello Allan Barker Jim Clay | |||
RidsNrrDirsIrib Resource Carole Ariano Carmen Olteanu | |||
Cynthia Pederson Linda Linn | |||
ADAMS Accession Number ML15302A013 | |||
Publicly Available Non-Publicly Available Sensitive Non-Sensitive | |||
To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copy | |||
OFFICE RIII RIII | |||
NAME ADahbur:cl RDaley | |||
DATE 10/29/15 10/29/15 | |||
OFFICIAL RECORD COPY | |||
}} | }} |
Latest revision as of 22:45, 16 November 2019
ML15302A013 | |
Person / Time | |
---|---|
Site: | Monticello |
Issue date: | 10/29/2015 |
From: | Robert Daley Engineering Branch 3 |
To: | Gardner P Northern States Power Co |
References | |
IR 2016008 | |
Download: ML15302A013 (7) | |
See also: IR 05000263/2016008
Text
UNITED STATES
NUCLEAR REGULATORY COMMISSION
REGION III
2443 WARRENVILLE RD. SUITE 210
LISLE, IL 60532-4352
October 29, 2015
Mr. Peter A. Gardner
Site Vice President
Monticello Nuclear Generating Plant
Northern States Power Company, Minnesota
2807 West County Road 75
Monticello, MN 55362-9637
SUBJECT: MONTICELLO NUCLEAR GENERATING PLANT - INFORMATION REQUEST
FOR AN NRC TRIENNIAL PERMANENT MODIFICATIONS AND 10 CFR 50.59
BASELINE INSPECTION 05000263/2016008
Dear Mr. Gardner:
On February 29, 2016, the U.S. Nuclear Regulatory Commission (NRC) will begin a
MOD/50.59 Baseline Inspection at the Monticello Nuclear Generating Plant. This inspection
will be performed in accordance with the NRC Baseline Inspection Procedure 71111.17T.
The onsite portion of the inspection will take place on February 29 - March 4, 2016, and
March 14 - 18, 2016.
Experience has shown that these baseline inspections are extremely resource intensive, both
for the NRC inspectors and the licensee staff. In order to minimize the inspection impact on
the site, and to ensure a productive inspection for both parties, we have enclosed a request for
documents needed for the inspection. These documents have been divided into three groups.
The first group of information is necessary to ensure that the inspection team is adequately
prepared for the inspection. This information should be made available via compact disc and
delivered to the regional office no later than December 17, 2015. The inspection team will
review this information and, by January 15, 2016, will request specific items that should be
provided for review in the regional office by February 12, 2016.
The second group of requested documents contains additional items that the team will
review, or need access to, during the inspection. Certain documents contained within
Group II (i.e., Item [1]), will be requested for review in the regional office prior to the inspection
by February 12, 2016, as identified above. The remaining documents should be available by
the first day of the onsite inspection, February 29, 2016.
The third group lists information necessary to aid the inspection team in tracking issues
identified as a result of the inspection. It is requested that this information be provided to the
lead inspector as the information is generated during the inspection. It is important that all of
these documents are up-to-date and complete in order to minimize the number of additional
documents requested during the preparation and/or the onsite portions of the inspection.
P. Gardner -2-
The lead inspector for this inspection is Mr. Alan Dahbur. We understand that our regulatory
contact for this inspection is Mr. Andy Kouba of your organization. If there are any questions
about the inspection or the material requested, please contact the lead inspector at
(630) 829-9810, or via e-mail at Alan.Dahbur@nrc.gov.
This letter does not contain new or amended information collection requirements subject to
the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information
collection requirements were approved by the Office of Management and Budget, Control
Number 3150-0011. The NRC may not conduct or sponsor, and a person is not required to
respond to, a request for information or an information collection requirement unless the
requesting document displays a currently valid Office of Management and Budget Control
Number.
In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390, Public
Inspections, Exemptions, Requests for Withholding, of the NRC's "Rules of Practice," a copy
of this letter, its enclosure, and your response (if any) will be available electronically for public
inspection in the NRCs Public Document Room or from the Publicly Available Records (PARS)
component of the NRC's Agencywide Documents Access and Management System (ADAMS).
ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html
(the Public Electronic Reading Room).
Sincerely,
/RA/
Robert C. Daley, Chief
Engineering Branch 3
Division of Reactor Safety
Docket No. 50-263
License No. DPR-22
Enclosure:
Modification and 50.59 Inspection Document Request
cc w/encl: Distribution via LISTSERV
Inspection Report: 05000263/2016008
Inspection Dates: February 29 - March 4, 2016, and March 14 - 18, 2016
Inspection Procedure: Inspection Procedure 71111.17T, Evaluations of Changes, Tests,
and Experiments and Permanent Plant Modifications
Lead Inspector: Alan Dahbur
(630) 829-9810
Alan.Dahbur@nrc.gov
I. Information Requested for In-Office Preparation Week
The following information is requested by December 17, 2015, or sooner, to facilitate
the selection of specific items that will be reviewed during the onsite inspection week.
The inspection team will select specific items from the information requested below,
and submit a list to your staff by January 15, 2016. We will request that certain items
be made available to the regional office prior to the inspection by February 12, 2016.
We request that the remaining items selected from the lists be available and ready for
review on the first day of inspection. All requested information should identify the
associated system and cover the time frame from the receipt of information for the
last MOD/50.59 inspection November 4, 2013, to the present.
The required information identified below should be provided on compact disc (CD).
Please provide three copies of each CD submitted (i.e., one for each inspector).
The preferred file format is a searchable pdf file. The CDs should be indexed and
hyper-linked to facilitate ease of use, if possible. If you have any questions regarding
this information, please call the inspection team leader as soon as possible.
(1) List of permanent plant modifications to systems, structures or components that
are field work complete. (For the purpose of this inspection, permanent plant
modifications include permanent: plant changes, design changes, set point
changes, equivalency evaluations, suitability analyses, and commercial grade
dedications.)
The list should contain the number of each document, the title, the revision
(or date), and the affected system. In addition to the list, please provide a
description of each modification and a list of associated calculations and
affected procedures.
(2) List of all Title 10, Code of Federal Regulations (CFR), Part 50.59 completed
evaluations involving: (a) calculations; (b) procedure revisions; (c) changes
to the facility (modifications); (d) non-routine operating configurations; or
(e) departures in methods of analyses. This list should include 50.59
evaluations for the following:
a. Changes that have been made under the provisions of 10 CFR 50.59 that
have been updated in accordance with 10 CFR 50.71(e)(4) since the last
MOD/50.59 inspection;
Enclosure
b. Modifications that are field work complete; and
c. Changes to calculations (or initiation of new calculations) that have been
issued. The list should contain the number and title of each document, a
brief description of the change, and the corresponding number and type of
the affected document (i.e., the modification or procedure to which the
evaluation applies). The list should NOT include any evaluations in which
prior U.S. Nuclear Regulatory Commission approval was sought and
obtained.
(3) A list of all 10 CFR 50.59 changes that have been screened out as not requiring
a full evaluation involving: (a) calculations; (b) procedure revisions; (c) changes
to the facility (modifications); (d) non-routine operating configurations; or
(e) departures in methods of analyses.
The list should contain the number and title of each document, a brief description
of the change, and the corresponding number and type of the affected document
(i.e., the modification or procedure to which the evaluation applies).
(4) A list of any modifications, procedure revisions, or Updated Final Safety Analysis
Report (UFSAR) changes where it was determined that 10 CFR 50.59 did not
apply.
(5) A list of calculation changes that have been issued for use.
(6) A list of corrective action documents (open and closed) that address permanent
plant modifications or 10 CFR 50.59 issues, concerns, or processes. These
documents should also include the corrective action documents associated with
the modification and the 50.59 change implementation.
The list should contain the number, title and revision (or date) of each document,
the affected system and corresponding documentation (if applicable), and should
be sorted in order of significance.
(7) Copies of procedures addressing the following: modifications, design changes,
set point changes, equivalency evaluations or suitability analyses, commercial
grade dedications, post-modification testing, 10 CFR 50.59 evaluations and
screenings, and UFSAR updates.
(8) UFSAR updates submitted in accordance with 10 CFR 50.71(e)(4). Provide
copies of the complete submittal.
(9) Copy of the UFSAR change log or a synopsis of the changes. This should
include all of the changes made to the UFSAR that were incorporated in the last
10 CFR 50.71(e)(4) submittal.
(10) Electronic copy of the UFSAR and Technical Specifications (TSs), if available.
(11) Name(s) and phone number(s) for the regulatory and technical contacts.
(12) Current management and engineering organizational chart.
2
II. Information Requested to be Available Prior to Inspection. Requests will be Made
for Specific Item (1) Documents by January 15, 2016, for Availability of Requested
Item (1) Documents in Regional Office by February 12, 2016, and Items (2), (3), and
(4) Documents on First Day of Inspection (February 29, 2016)
(1) Copies of all selected items from Section I. This includes copies of
associated documents such as calculations, post-modification test packages,
10 CFR 50.59 evaluations or screenings, and any corrective action documents.
(2) Copies of these documents do not need to be solely available to the inspection
team as long as the inspectors have easy and unrestrained access to them.
a. UFSAR, if not previously provided;
b. Original Final Safety Analysis Report (FSAR) Volumes;
c. Original Safety Evaluation Reports and Supplements;
d. FSAR Question and Answers;
e. Quality Assurance (QA) Plan;
f. TSs, if not previously provided;
g. Latest Individual Plant Examination/Probabilistic Risk Assessment Report;
h. Vendor Manuals; and
i. The latest 10 CFR 50.59 UFSAR Update Submittal.
(3) Please ensure that other supporting documents for the selected items have been
located and are readily retrievable as the inspection team will likely be requesting
these documents during the inspection. Examples of supporting documents are:
a. Drawings supporting the modifications;
b. Procedures affected by the modifications; and
c. UFSAR change papers generated due to a 10 CFR 50.59 evaluation.
(4) Assessment and Corrective Actions:
a. The most recent MOD/50.59 QA audit and/or self-assessment; and
b. Corrective action documents (e.g., condition reports, including status of
corrective actions) generate as a result of the most recent MOD/50.59 QA
audit and/or self-assessment.
3
III. Information Requested to be provided throughout the inspection
(1) Copies of any corrective action documents generated as a result of the
inspection teams questions or queries during this inspection.
(2) Copies of the list of questions submitted by the inspection team members and
the status/resolution of the information requested (provide daily during the
inspection to each inspection team member).
If you have any questions regarding the information requested, please contact the inspection
team leader.
4
P. Gardner -2-
The lead inspector for this inspection is Mr. Alan Dahbur. We understand that our regulatory
contact for this inspection is Mr. Andy Kouba of your organization. If there are any questions
about the inspection or the material requested, please contact the lead inspector at
(630) 829-9810, or via e-mail at Alan.Dahbur@nrc.gov.
This letter does not contain new or amended information collection requirements subject to
the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information
collection requirements were approved by the Office of Management and Budget, Control
Number 3150-0011. The NRC may not conduct or sponsor, and a person is not required to
respond to, a request for information or an information collection requirement unless the
requesting document displays a currently valid Office of Management and Budget Control
Number.
In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390, Public
Inspections, Exemptions, Requests for Withholding, of the NRC's "Rules of Practice," a copy
of this letter, its enclosure, and your response (if any) will be available electronically for public
inspection in the NRCs Public Document Room or from the Publicly Available Records (PARS)
component of the NRC's Agencywide Documents Access and Management System (ADAMS).
ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html
(the Public Electronic Reading Room).
Sincerely,
/RA/
Robert C. Daley, Chief
Engineering Branch 3
Division of Reactor Safety
Docket No. 50-263
License No. DPR-22
Enclosure:
Modification and 50.59 Inspection Document Request
cc w/encl: Distribution via LISTSERV
DISTRIBUTION w/encl:
Janelle Jessie Darrell Roberts DRPIII
RidsNrrDorlLpl3-1 Resource Richard Skokowski DRSIII
RidsNrrPMMonticello Allan Barker Jim Clay
RidsNrrDirsIrib Resource Carole Ariano Carmen Olteanu
Cynthia Pederson Linda Linn
ADAMS Accession Number ML15302A013
Publicly Available Non-Publicly Available Sensitive Non-Sensitive
To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copy
OFFICE RIII RIII
NAME ADahbur:cl RDaley
DATE 10/29/15 10/29/15
OFFICIAL RECORD COPY