{{#Wiki_filter:Inspection / Activity PlanPage 1 of 209/01/201108:50:56Report 2209/01/2011
{{#Wiki_filter:Page 1 of 2                                                                                    Vogtle 09/01/2011    08:50:56                                                          Inspection / Activity Plan Report 22 09/01/2011 - 12/31/2012 Unit        Planned Dates                                                                                                                                    No. of Staff Number        Start      End    Inspection Activity                                                              Title                                            on Site PSB1-RP       - RAD HAZARD ASSESSMENT AND INSTRUMENTS                                                                                 3 1, 2       09/19/2011  09/23/2011  IP 2515/179            Verification of Licensee Responses to NRC Requirement for Inventories of Materials Tracked in NSTS 1, 2      09/19/2011  09/23/2011  IP 71124.01            Radiological Hazard Assessment and Exposure Controls 1, 2       09/19/2011  09/23/2011  IP 71124.05            Radiation Monitoring Instrumentation EB3 ISI       - UNIT 2 INSERVICE INSPECTION                                                                                           1 2      09/26/2011  09/30/2011  IP 7111108P            Inservice Inspection Activities - PWR EB3SGISI      - UNIT 2 SG INSERVICE INSPECTION                                                                                         1 2      09/26/2011  09/30/2011  IP 7111108P            Inservice Inspection Activities - PWR OL RQ         - REQUAL INSPECTION                                                                                                     6 1, 2       10/24/2011  10/28/2011  IP 7111111B            Licensed Operator Requalification Program OL EXAM       - INITIAL EXAM PREP                                                                                                     4 1          03/05/2012  03/09/2012      V23368              VOGTLE / MARCH 2012 EXAM AT POWER FACILITIES PSB1EP        - EMERGENCY PREPAREDNESS EXERCISE                                                                                       3 1, 2       03/19/2012  03/23/2012  IP 7111401              Exercise Evaluation 1, 2       03/19/2012  03/23/2012  IP 7111404              Emergency Action Level and Emergency Plan Changes 1, 2       03/19/2012  03/23/2012  IP 71151                Performance Indicator Verification OL EXAM       - INITIAL EXAM - WEEK 1                                                                                                 4 1          03/26/2012  03/30/2012      V23368              VOGTLE / MARCH 2012 EXAM AT POWER FACILITIES OL EXAM       - INITIAL EXAM - WEEK 2                                                                                                 4 1          04/09/2012  04/13/2012      V23368              VOGTLE / MARCH 2012 EXAM AT POWER FACILITIES OL EXAM       - INITIAL EXAM - WEEK 3                                                                                                 4 1          04/16/2012  04/20/2012      V23368              VOGTLE / MARCH 2012 EXAM AT POWER FACILITIES TI-177         - TI-177 GAS INTRUSION                                                                                                   3 1, 2       05/21/2012  05/25/2012  IP 2515/177            Managing Gas Accumulation In Emergency Core Cooling, Decay Heat Removal & Containment Spray System PSB1-RP       - OCCUPATIONAL RP BASELINE WK1                                                                                           3 1, 2       09/17/2012  09/21/2012  IP 71124.01            Radiological Hazard Assessment and Exposure Controls 1, 2      09/17/2012  09/21/2012  IP 71124.02            Occupational ALARA Planning and Controls 1, 2      09/17/2012  09/21/2012  IP 71124.03            In-Plant Airborne Radioactivity Control and Mitigation 1, 2       09/17/2012  09/21/2012  IP 71124.04            Occupational Dose Assessment 1, 2       09/17/2012  09/21/2012  IP 71124.05            Radiation Monitoring Instrumentation 1, 2       09/17/2012  09/21/2012  IP 71151                Performance Indicator Verification EB3 ISI       - UNIT 1 INSERVICE INSPECTION                                                                                           1 1          09/24/2012  09/28/2012  IP 7111108P            Inservice Inspection Activities - PWR This report does not include INPO and OUTAGE activities.
-12/31/2012UnitNumberPlanned DatesStart          EndInspection ActivityTitleNo. of Staffon SiteVogtlePSB1-RP- RAD HAZARD ASSESSMENT AND INSTRUMENTS 31, 2 IPVerification of Licensee Responses to NRC Requirement for Inventories of Materials Tracked in NSTS2515/17909/19/201109/23/20111, 2 IPRadiological Hazard Assessment and Exposure Controls71124.0109/19/201109/23/20111, 2 IPRadiation Monitoring Instrumentation71124.0509/19/201109/23/2011EB3 ISI-UNIT 2 INSERVICE INSPECTION 12 IPInservice Inspection Activities - PWR7111108P09/26/201109/30/2011EB3SGISI-UNIT 2 SG INSERVICE INSPECTION 12 IPInservice Inspection Activities - PWR7111108P09/26/201109/30/2011OL RQ-REQUAL INSPECTION 61, 2 IPLicensed Operator Requalification Program7111111B10/24/201110/28/2011OL EXAM-INITIAL EXAM PREP 41 VOGTLE / MARCH 2012 EXAM AT POWER FACILITIESV2336803/05/201203/09/2012PSB1EP-EMERGENCY PREPAREDNESS EXERCISE 31, 2 IPExercise Evaluation711140103/19/201203/23/20121, 2 IPEmergency Action Level and Emergency Plan Changes711140403/19/201203/23/20121, 2 IPPerformance Indicator Verification7115103/19/201203/23/2012OL EXAM-INITIAL EXAM - WEEK 1 41 VOGTLE / MARCH 2012 EXAM AT POWER FACILITIESV2336803/26/201203/30/2012OL EXAM-INITIAL EXAM - WEEK 2 41 VOGTLE / MARCH 2012 EXAM AT POWER FACILITIESV2336804/09/201204/13/2012OL EXAM-INITIAL EXAM - WEEK 3 41 VOGTLE / MARCH 2012 EXAM AT POWER FACILITIESV2336804/16/201204/20/2012TI-177-TI-177 GAS INTRUSION 31, 2 IPManaging Gas Accumulation In Emergency Core Cooling, Decay Heat Removal & Containment Spray System2515/17705/21/201205/25/2012PSB1-RP-OCCUPATIONAL RP BASELINE WK1 31, 2 IPRadiological Hazard Assessment and Exposure Controls71124.0109/17/201209/21/20121, 2 IPOccupational ALARA Planning and Controls71124.0209/17/201209/21/20121, 2 IPIn-Plant Airborne Radioactivity Control and Mitigation71124.0309/17/201209/21/20121, 2 IPOccupational Dose Assessment71124.0409/17/201209/21/20121, 2 IPRadiation Monitoring Instrumentation71124.0509/17/201209/21/20121, 2 IPPerformance Indicator Verification7115109/17/201209/21/2012EB3 ISI-UNIT 1 INSERVICE INSPECTION 11 IPInservice Inspection Activities - PWR7111108P09/24/201209/28/2012This report does not include INPO and OUTAGE activities. This report shows only on-site and announced inspection procedures.
This report shows only on-site and announced inspection procedures.                                             Enclosure
Inspection / Activity PlanPage 2 of 209/01/201108:50:56Report 2209/01/2011
 
-12/31/2012UnitNumberPlanned DatesStart          EndInspection ActivityTitleNo. of Staffon SiteVogtlePSB1-RP-OCCUPATIONAL RP BASELINE WK2 31, 2 IPRadiological Hazard Assessment and Exposure Controls71124.0110/01/201210/05/20121, 2 IPOccupational ALARA Planning and Controls71124.0210/01/201210/05/20121, 2 IPIn-Plant Airborne Radioactivity Control and Mitigation71124.0310/01/201210/05/20121, 2 IPOccupational Dose Assessment71124.0410/01/201210/05/20121, 2 IPRadiation Monitoring Instrumentation71124.0510/01/201210/05/20121, 2 IPPerformance Indicator Verification7115110/01/201210/05/2012EB3SGISI-UNIT 1 SG INSERVICE INSPECTION 11 IPInservice Inspection Activities - PWR7111108P10/03/201210/07/2012VOG TFPI-TRIENNIAL FIRE PROTECTION INSPECTION101, 2 IPFire Protection [Triennial]7111105T11/26/201211/30/20121, 2 IPFire Protection [Triennial]7111105T12/10/201212/10/2012This report does not include INPO and OUTAGE activities. This report shows only on-site and announced inspection procedures.}}
Page 2 of 2                                                                                    Vogtle 09/01/2011    08:50:56                                                        Inspection / Activity Plan Report 22 09/01/2011 - 12/31/2012 Unit        Planned Dates                                                                                              No. of Staff Number        Start      End    Inspection Activity                                                              Title      on Site PSB1-RP       - OCCUPATIONAL RP BASELINE WK2                                                     3 1, 2       10/01/2012  10/05/2012  IP 71124.01            Radiological Hazard Assessment and Exposure Controls 1, 2      10/01/2012  10/05/2012  IP 71124.02            Occupational ALARA Planning and Controls 1, 2      10/01/2012  10/05/2012  IP 71124.03            In-Plant Airborne Radioactivity Control and Mitigation 1, 2      10/01/2012  10/05/2012  IP 71124.04            Occupational Dose Assessment 1, 2       10/01/2012  10/05/2012  IP 71124.05             Radiation Monitoring Instrumentation 1, 2       10/01/2012  10/05/2012  IP 71151                Performance Indicator Verification EB3SGISI      - UNIT 1 SG INSERVICE INSPECTION                                                   1 1          10/03/2012  10/07/2012  IP 7111108P            Inservice Inspection Activities - PWR VOG TFPI       - TRIENNIAL FIRE PROTECTION INSPECTION                                            10 1, 2       11/26/2012  11/30/2012  IP 7111105T            Fire Protection [Triennial]
1, 2      12/10/2012  12/10/2012  IP 7111105T            Fire Protection [Triennial]
This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.       Enclosure}}

Latest revision as of 15:19, 12 November 2019

Report 22 - Vogtle
ML112440292
Person / Time
Site: Vogtle  Southern Nuclear icon.png
Issue date: 09/01/2011
From:
NRC/RGN-II
To:
Shared Package
ML112440284 List:
References
Download: ML112440292 (2)


Text

Page 1 of 2 Vogtle 09/01/2011 08:50:56 Inspection / Activity Plan Report 22 09/01/2011 - 12/31/2012 Unit Planned Dates No. of Staff Number Start End Inspection Activity Title on Site PSB1-RP - RAD HAZARD ASSESSMENT AND INSTRUMENTS 3 1, 2 09/19/2011 09/23/2011 IP 2515/179 Verification of Licensee Responses to NRC Requirement for Inventories of Materials Tracked in NSTS 1, 2 09/19/2011 09/23/2011 IP 71124.01 Radiological Hazard Assessment and Exposure Controls 1, 2 09/19/2011 09/23/2011 IP 71124.05 Radiation Monitoring Instrumentation EB3 ISI - UNIT 2 INSERVICE INSPECTION 1 2 09/26/2011 09/30/2011 IP 7111108P Inservice Inspection Activities - PWR EB3SGISI - UNIT 2 SG INSERVICE INSPECTION 1 2 09/26/2011 09/30/2011 IP 7111108P Inservice Inspection Activities - PWR OL RQ - REQUAL INSPECTION 6 1, 2 10/24/2011 10/28/2011 IP 7111111B Licensed Operator Requalification Program OL EXAM - INITIAL EXAM PREP 4 1 03/05/2012 03/09/2012 V23368 VOGTLE / MARCH 2012 EXAM AT POWER FACILITIES PSB1EP - EMERGENCY PREPAREDNESS EXERCISE 3 1, 2 03/19/2012 03/23/2012 IP 7111401 Exercise Evaluation 1, 2 03/19/2012 03/23/2012 IP 7111404 Emergency Action Level and Emergency Plan Changes 1, 2 03/19/2012 03/23/2012 IP 71151 Performance Indicator Verification OL EXAM - INITIAL EXAM - WEEK 1 4 1 03/26/2012 03/30/2012 V23368 VOGTLE / MARCH 2012 EXAM AT POWER FACILITIES OL EXAM - INITIAL EXAM - WEEK 2 4 1 04/09/2012 04/13/2012 V23368 VOGTLE / MARCH 2012 EXAM AT POWER FACILITIES OL EXAM - INITIAL EXAM - WEEK 3 4 1 04/16/2012 04/20/2012 V23368 VOGTLE / MARCH 2012 EXAM AT POWER FACILITIES TI-177 - TI-177 GAS INTRUSION 3 1, 2 05/21/2012 05/25/2012 IP 2515/177 Managing Gas Accumulation In Emergency Core Cooling, Decay Heat Removal & Containment Spray System PSB1-RP - OCCUPATIONAL RP BASELINE WK1 3 1, 2 09/17/2012 09/21/2012 IP 71124.01 Radiological Hazard Assessment and Exposure Controls 1, 2 09/17/2012 09/21/2012 IP 71124.02 Occupational ALARA Planning and Controls 1, 2 09/17/2012 09/21/2012 IP 71124.03 In-Plant Airborne Radioactivity Control and Mitigation 1, 2 09/17/2012 09/21/2012 IP 71124.04 Occupational Dose Assessment 1, 2 09/17/2012 09/21/2012 IP 71124.05 Radiation Monitoring Instrumentation 1, 2 09/17/2012 09/21/2012 IP 71151 Performance Indicator Verification EB3 ISI - UNIT 1 INSERVICE INSPECTION 1 1 09/24/2012 09/28/2012 IP 7111108P Inservice Inspection Activities - PWR This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures. Enclosure

Page 2 of 2 Vogtle 09/01/2011 08:50:56 Inspection / Activity Plan Report 22 09/01/2011 - 12/31/2012 Unit Planned Dates No. of Staff Number Start End Inspection Activity Title on Site PSB1-RP - OCCUPATIONAL RP BASELINE WK2 3 1, 2 10/01/2012 10/05/2012 IP 71124.01 Radiological Hazard Assessment and Exposure Controls 1, 2 10/01/2012 10/05/2012 IP 71124.02 Occupational ALARA Planning and Controls 1, 2 10/01/2012 10/05/2012 IP 71124.03 In-Plant Airborne Radioactivity Control and Mitigation 1, 2 10/01/2012 10/05/2012 IP 71124.04 Occupational Dose Assessment 1, 2 10/01/2012 10/05/2012 IP 71124.05 Radiation Monitoring Instrumentation 1, 2 10/01/2012 10/05/2012 IP 71151 Performance Indicator Verification EB3SGISI - UNIT 1 SG INSERVICE INSPECTION 1 1 10/03/2012 10/07/2012 IP 7111108P Inservice Inspection Activities - PWR VOG TFPI - TRIENNIAL FIRE PROTECTION INSPECTION 10 1, 2 11/26/2012 11/30/2012 IP 7111105T Fire Protection [Triennial]

1, 2 12/10/2012 12/10/2012 IP 7111105T Fire Protection [Triennial]

This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures. Enclosure