| | issue date = 12/19/2011 | | | issue date = 12/19/2011 |
| | title = Request for Additional Information Regarding Extended Power Uprate | | | title = Request for Additional Information Regarding Extended Power Uprate |
| | author name = Krupa M A | | | author name = Krupa M |
| | author affiliation = Entergy Operations, Inc | | | author affiliation = Entergy Operations, Inc |
| | addressee name = | | | addressee name = |
Line 14: |
Line 14: |
| | page count = 5 | | | page count = 5 |
| | project = TAC:ME4679 | | | project = TAC:ME4679 |
| | stage = RAI | | | stage = Request |
| }} | | }} |
|
| |
|
| =Text= | | =Text= |
| {{#Wiki_filter:G NRO-2011/00 111 December 19, 2011 U.S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555 | | {{#Wiki_filter:Entergy Operations, Inc. |
| | P. O. Box 756 Port Gibson, MS 39150 Michael A. Krupa Director, Extended Power Uprate Grand Gulf Nuclear Station Tel. (601) 437-6694 GNRO-2011/00111 December 19, 2011 U.S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555 |
|
| |
|
| ==SUBJECT:== | | ==SUBJECT:== |
| Request for Additional Information Regarding Extended Power Uprate Grand Gulf Nuclear Station, Unit 1 Docket No. 50 | | Request for Additional Information Regarding Extended Power Uprate Grand Gulf Nuclear Station, Unit 1 Docket No. 50-416 License No. NPF-29 |
| -416 License No. | |
| NPF-29 | |
|
| |
|
| ==REFERENCES:== | | ==REFERENCES:== |
| : 1. Entergy Operations, Inc. letter to the NRC (GNRO | | : 1. Entergy Operations, Inc. letter to the NRC (GNRO-2010/00056), |
| -2010/00056), License Amendment Request | | License Amendment Request - Extended Power Uprate, September 8, 2010 (ADAMS Accession No. ML102660403) |
| - Extended Power Uprate , September 8, 2010 (ADAMS Accession No. ML102660403) | |
| : 2. NRC e-mail to Entergy Operations, Inc., Grand Gulf Extended Power Uprate Reactor Systems Branch Request for Additional Information (ME4679), December 14, 2011 | | : 2. NRC e-mail to Entergy Operations, Inc., Grand Gulf Extended Power Uprate Reactor Systems Branch Request for Additional Information (ME4679), December 14, 2011 |
|
| |
|
| ==Dear Sir or Madam:== | | ==Dear Sir or Madam:== |
|
| |
|
| In Reference 1, Entergy submitted a license amendment request (LAR) to the NRC, which proposes an extended power uprate (EPU) for Grand Gulf Nuclear Station, Unit 1 (GGNS). | | In Reference 1, Entergy submitted a license amendment request (LAR) to the NRC, which proposes an extended power uprate (EPU) for Grand Gulf Nuclear Station, Unit 1 (GGNS). To support its review and approval of this LAR, on October 27, 2011 the NRC staff conducted an on-site audit of the implementation of stability long-term solutions and the impact of EPU on instability and an Anticipated Transient without Scram (ATWS) event. As a result of that audit, the NRC has requested additional information (transmitted via Reference 2) pertaining to simulator scenarios reflecting EPU operating conditions, specifically: |
| To support its review and approval of this LAR | | : 1. Provide data for worst-case ATWS long-term scenario at EPU conditions. Include plots, sequence of events, and initial conditions. |
| , on October 27, 2011 the NRC staff conducted an on-site audit of the implementation of stability long | | : 2. Provide data for worst-case ATWS short-term pressure peak scenario at EPU conditions. |
| -term solutions and the impact of EPU on instability and an Anticipated Transient without Scram (ATWS) event. As a result of that audit, the NRC has requested additional information (transmitted via Reference 2) pertaining to simulator scenarios reflecting EPU operating conditions | |
| , specifically: | |
| : 1. Provide data for worst | |
| -case ATWS long | |
| -term scenario at EPU conditions. | |
| Include plots, sequence of events, and initial conditions. | | Include plots, sequence of events, and initial conditions. |
| : 2. Provide data for wor st-case ATWS short
| | Entergy is currently in the process of incorporating EPU-related system modifications and operating conditions into the GGNS simulator. Based on the current schedule, Entergy commits to provide the requested data to the NRC on or before February 15, 2012. |
| -term pressure peak scenario at EPU conditions.
| | No change is needed to the no significant hazards consideration included in the initial LAR (Reference 1) as a result of the additional information provided. This letter contains one new commitment, which is identified in the attachment. |
| Include plots, sequence of events, and initial conditions.
| | |
| Entergy is currently in the process of incorporating EPU | | GNRO-2011/00111 Page 2 of 3 If you have any questions or require additional information, please contact Mr. Jerry Burford at 601-368-5755. |
| -related system modifications and operating conditions into the GGNS simulator. Based on the current schedule, Entergy commits to provide the requested data to the NRC on or before February 15, 2012. | | Sincerely, MAK/ghd |
| No change is needed to the no significant hazards consideration includ ed in the initial LAR (Reference 1) as a result of the additional information provided. This letter contains one new commitment, which is identified in the attachment | |
| . Entergy Operations, Inc.
| |
| P. O. Box 756 Port Gibson, MS 39150 Michael A. Krupa Director , Extended Power Uprate Grand Gulf Nuclear Station Tel. (601) 437
| |
| -6694 GNRO-2011/00111 Page 2 of 3 If you have any questions or require additional information, please contact Mr. Jerry Burford at 601-368-5755. Sincerely, MAK/ghd
| |
|
| |
|
| ==Attachment:== | | ==Attachment:== |
|
| |
| List of Regulatory Commitments | | List of Regulatory Commitments |
|
| |
|
| GNRO-2011/00 111 Page 3 of 3 cc: Mr. Elmo E. Collins, Jr. | | GNRO-2011/00111 Page 3 of 3 cc: Mr. Elmo E. Collins, Jr. |
| Regional Administrator, Region IV U. S. Nuclear Regulatory Commission 612 East Lamar Blvd., Suite 400 Arlington, TX 76011 | | Regional Administrator, Region IV U. S. Nuclear Regulatory Commission 612 East Lamar Blvd., Suite 400 Arlington, TX 76011-4125 NRC Senior Resident Inspector Grand Gulf Nuclear Station Port Gibson, MS 39150 U. S. Nuclear Regulatory Commission ATTN: Mr. A. B. Wang, NRR/DORL ATTN: ADDRESSEE ONLY ATTN: Courier Delivery Only Mail Stop OWFN/8 B1 11555 Rockville Pike Rockville, MD 20852-2378 State Health Officer Mississippi Department of Health P. O. Box 1700 Jackson, MS 39215-1700 |
| -4125 NRC Senior Resident Inspector Grand Gulf Nuclear Station Port Gibson, MS 39150 U. S. Nuclear Regulatory Commission ATTN: Mr. A. B. Wang, NRR/DORL ATTN: ADDRESSEE ONLY ATTN: Courier Delivery Only Mail Stop OWFN/8 B1 11555 Rockville Pike Rockville, MD 20852 | |
| -2378 State Health Officer Mississippi Department of Health P. O. Box 1700 Jackson, MS 39215 | |
| -1700 Attachment GNRO-2011/00111 Grand Gulf Nuclear Station Extended Power Uprate LIST OF REGULATORY COMMITMENTS | |
|
| |
|
| Attachment to GNRO-2011/00111 Page 1 of 1 LIST OF REGULATORY COMMITMENTS | | Attachment GNRO-2011/00111 Grand Gulf Nuclear Station Extended Power Uprate LIST OF REGULATORY COMMITMENTS |
|
| |
|
| The following table identifies those actions committed to by Entergy in this document. Any other statements in this submittal are provided for information purposes and are not considered to be regulatory commitments. | | Attachment to GNRO-2011/00111 Page 1 of 1 LIST OF REGULATORY COMMITMENTS The following table identifies those actions committed to by Entergy in this document. Any other statements in this submittal are provided for information purposes and are not considered to be regulatory commitments. |
| COMMITMENT TYPE (Check one) | | TYPE SCHEDULED COMMITMENT (Check one) COMPLETION ONE-TIME CONTINUING DATE ACTION COMPLIANCE (If Required) |
| SCHEDULED COMPLETION DATE (If Required)
| | Entergy will provide data for the following simulator 2/15/2011 scenario runs on or before February 15, 2012: |
| ONE-TIME ACTION CONTINUING COMPLIANCE Entergy will provide data for the following simulator scenario runs on or before February 15, 2012:
| | : 1. Worst-case ATWS long-term scenario at EPU conditions. Include plots, sequence of events, and initial conditions. |
| : 1. Worst-case ATWS long | | : 2. Worst-case ATWS short-term pressure peak scenario at EPU conditions. Include plots, sequence of events, and initial conditions.}} |
| -term scenario at EPU conditions. | |
| Include plots, sequence of events, and initial conditions. | |
| : 2. Worst-case ATWS short | |
| -term pressure peak scenario at EPU conditions. | |
| Include plots, sequence of events, and initial conditions. | |
| 2/15/2011}}
| |
Letter Sequence Request |
---|
TAC:ME4679, Clarify Application of Setpoint Methodology for LSSS Functions (Open) |
Initiation
- Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request
- Acceptance
- Supplement, Supplement
Administration
- Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance
- Meeting
Results
Other: GNRO-2012/00150, Final Report for Replacement Steam Dryer, GNRO-2017/00039, Steam Dryer Visual Inspection Results for the First Two Scheduled Refueling Outages, ML102660403, ML111720830, ML112560396, ML12167A257, ML12167A269, ML12177A287, ML13108A217, NRC-2012-0105, Environmental Assessment and Finding of No Significant Impact Related Amendment Request for Extended Power Uprate to Increase the Maximum Reactor Core Power Operating Limit from 3898 to 4408 Mwt
|
MONTHYEARML1026604002010-08-20020 August 2010 GE-Hitachi Nuclear Energy Americas LLC - Affidavit of Edward Schrull Withholding from Public Disclosure Proprietary Report NEDC-33477P Project stage: Request ML1026603992010-08-31031 August 2010 NEDO-33477, Revision 0, Safety Analysis Report for Grand Gulf Nuclear Station Constant Pressure Power Uprate. Project stage: Request ML1026604032010-09-0808 September 2010 License Amendment Request Extended Power Uprate Project stage: Other GNRO-2010/00056, NEDO-33601, Revison 0, Engineering Report Grand Gulf Replacement Steam Dryer Fatigue Stress Analysis Using Pble Methodology. Appendix E Through Appendix G2010-09-30030 September 2010 NEDO-33601, Revison 0, Engineering Report Grand Gulf Replacement Steam Dryer Fatigue Stress Analysis Using Pble Methodology. Appendix E Through Appendix G Project stage: Request ML1026604062010-09-30030 September 2010 NEDO-33601, Revison 0, Engineering Report Grand Gulf Replacement Steam Dryer Fatigue Stress Analysis Using Pble Methodology. Appendix B Through Appendix D Project stage: Request ML1026604012010-09-30030 September 2010 NEDO-33601, Revison 0, Engineering Report Grand Gulf Replacement Steam Dryer Fatigue Stress Analysis Using Pble Methodology. Cover Through Appendix a Project stage: Request ML1030102002010-11-0909 November 2010 Supplemental Information Needed for Acceptance of License Amendment Request, Extended Power Uprate to Increase the Maximum Reactor Core Power Operating Limit from 3898 to 4408 Megawatts Thermal Project stage: Acceptance Review GNRO-2010/00071, Supplemental Information, License Amendment Request, Extended Power Uprate2010-11-18018 November 2010 Supplemental Information, License Amendment Request, Extended Power Uprate Project stage: Supplement GNRO-2010/00073, Supplemental Information License Amendment Request, Extended Power Uprate2010-11-23023 November 2010 Supplemental Information License Amendment Request, Extended Power Uprate Project stage: Supplement ML1034201082010-12-16016 December 2010 Request for Withholding Information from Public Disclosure, 9/7/10 Affidavit Executed by E. Schrull, GEH Re NEDC-33601P Project stage: Withholding Request Acceptance ML1034705862011-01-0505 January 2011 Request for Withholding Information from Public Disclosure, 11/19/10 Affidavit Executed by E. Schrull, GE-Hitachi, Regarding NEDC-33621P Project stage: Withholding Request Acceptance ML1102602812011-01-26026 January 2011 E-mail, Request for Additional Information Instrument and Controls, Amendment Request for Extended Power Uprate to Increase the Maximum Reactor Core Power Operating Limit from 3898 to 4408 Mwt Project stage: RAI ML1102602872011-01-26026 January 2011 E-mail, Request for Additional Information Fire Protection, Amendment Request for Extended Power Uprate to Increase the Maximum Reactor Core Power Operating Limit from 3898 to 4408 Mwt Project stage: RAI ML1102701872011-01-27027 January 2011 Request for Additional Information, Emcb Non-Steam Dryer Review, Amendment Request for Extended Power Uprate to Increase the Maximum Reactor Core Power Operating Limit from 3898 to 4408 Mwt Project stage: RAI ML1103103902011-01-31031 January 2011 E-mail, Request for Additional Information, Vessels and Internal Integrity Review, Amendment Request for Extended Power Uprate to Increase the Maximum Reactor Core Power Operating Limit from 3898 to 4408 Mwt Project stage: RAI ML1103901732011-02-0808 February 2011 Email, Request for Additional Information, Nrr/Dci/Csgb Review, Amendment Request for Extended Power Uprate to Increase the Maximum Reactor Core Power Operating Limit from 3898 to 4408 Mwt Project stage: RAI GNRO-2011/00012, Request for Additional Information Regarding Extended Power Uprate2011-02-23023 February 2011 Request for Additional Information Regarding Extended Power Uprate Project stage: Request GNRO-2011/00011, Request for Additional Information Regarding Extended Power Uprate2011-02-23023 February 2011 Request for Additional Information Regarding Extended Power Uprate Project stage: Request ML1105407052011-02-23023 February 2011 E-mail, Request for Additional Information, Nrr/Dirs/Ihpb Review, Amendment Request for Extended Power Uprate to Increase the Maximum Reactor Core Power Operating Limit from 3898 to 4408 Mwt Project stage: RAI ML1105407122011-02-23023 February 2011 E-mail, Request for Additional Information, Nrr/Dra/Apla Review, Amendment Request for Extended Power Uprate to Increase the Maximum Reactor Core Power Operating Limit from 3898 to 4408 Mwt Project stage: RAI GNRO-2011/00013, Request for Additional Information Regarding Extended Power Uprate2011-02-23023 February 2011 Request for Additional Information Regarding Extended Power Uprate Project stage: Request ML1034200962011-02-25025 February 2011 Request for Withholding Information from Public Disclosure, 8/20/10 Affidavit Executed by E. Schrull, GEH, for NEDC-33477P Project stage: Withholding Request Acceptance ML1106007172011-03-0101 March 2011 Email Request for Additional Information, Round 2, Nrr/Dci/Cvib Review, Amendment Request for Extended Power Uprate to Increase the Maximum Reactor Core Power Operating Limit from 3898 to 4408 Mwt Project stage: RAI GNRO-2011/00016, Request for Additional Information Regarding Extended Power Uprate2011-03-0909 March 2011 Request for Additional Information Regarding Extended Power Uprate Project stage: Request ML1107501322011-03-16016 March 2011 Email, Dose Assessment Branch, Request for Additional Information, Amendment Request for Extended Power Uprate to Increase the Maximum Reactor Core Power Operating Limit from 3898 to 4408 Mwt Project stage: RAI ML1108202242011-03-23023 March 2011 Email, Request for Additional Information, Nrr/Dss/Srxb Review, Amendment Request for Extended Power Uprate to Increase the Maximum Reactor Core Power Operating Limit from 3898 to 4408 Mwt Project stage: RAI ML1108202272011-03-23023 March 2011 Request for Additional Information, Nrr/Dss/Srxb Review, Amendment Request for Extended Power Uprate to Increase the Maximum Reactor Core Power Operating Limit from 3898 to 4408 Mwt Project stage: RAI GNRO-2011/00018, Request for Additional Information Regarding Extended Power Uprate2011-03-30030 March 2011 Request for Additional Information Regarding Extended Power Uprate Project stage: Request GNRO-2011/00021, Response to Request for Additional Information Regarding Extended Power Uprate2011-03-31031 March 2011 Response to Request for Additional Information Regarding Extended Power Uprate Project stage: Response to RAI ML1109401362011-04-0404 April 2011 Email, Request for Additional Information, Nrr/Dci/Csgb Review, Round 2, Amendment Request for Extended Power Uprate to Increase the Maximum Reactor Core Power Operating Limit from 3898 to 4408 Mwt Project stage: RAI ML1109502722011-04-0505 April 2011 Email, Request for Additional Information, Nrr/De/Eeeb Review, Amendment Request for Extended Power Uprate to Increase the Maximum Reactor Core Power Operating Limit from 3898 to 4408 Mwt Project stage: RAI ML1109502812011-04-0505 April 2011 Request for Additional Information, Nrr/De/Eeeb Review, Amendment Request for Extended Power Uprate to Increase the Maximum Reactor Core Power Operating Limit from 3898 to 4408 Mwt Project stage: RAI ML1110301112011-04-12012 April 2011 Email, Request for Additional Information, Nrr/Dss/Snpb Review, Amendment Request for Extended Power Uprate to Increase the Maximum Reactor Core Power Operating Limit from 3898 to 4408 Mwt Project stage: RAI GNRO-2011/00024, Response to Request for Additional Information Regarding Extended Power Uprate2011-04-14014 April 2011 Response to Request for Additional Information Regarding Extended Power Uprate Project stage: Response to RAI ML11112A0982011-04-21021 April 2011 Request for Additional Information Regarding Extended Power Uprate Project stage: Request ML1110401002011-04-27027 April 2011 Request for Withholding Information from Public Disclosure, 3/28/2011 Affidavit Executed by E. Schrull, GEH, for Attachment 1 to GNRO-2011/00018 Project stage: Withholding Request Acceptance ML1110401252011-04-27027 April 2011 Request for Withholding Information from Public Disclosure, 2/20/2011 Affidavit Executed by E. Schrull, GEH, for Attachment 1 to GNRO-2011/00013 Project stage: Withholding Request Acceptance ML1110401132011-04-27027 April 2011 Request for Withholding Information from Public Disclosure, 2/20/2011 Affidavit Executed by E. Schrull, GEH, for Attachment 1 to GNRO-2011/00011 Project stage: Withholding Request Acceptance ML1110401072011-04-27027 April 2011 Request for Withholding Information from Public Disclosure, 2/17/2011 Affidavit Executed by E. Schrull, GEH, for Attachment 1 to GNRO-2011/00012 Project stage: Withholding Request Acceptance ML1110401162011-04-27027 April 2011 Request for Withholding Information from Public Disclosure, 3/30/2011 Affidavit Executed by E. Schrull, GEH, for Attachment 1 to GNRO-2011/00021 Project stage: Withholding Request Acceptance GNRO-2011/00035, Response to Request for Additional Information Regarding Extended Power Uprate2011-05-0505 May 2011 Response to Request for Additional Information Regarding Extended Power Uprate Project stage: Response to RAI ML1113001562011-05-10010 May 2011 Email, Request for Additional Information, Nrr/Dss/Scvb Review, Amendment Request for Extended Power Uprate to Increase the Maximum Reactor Core Power Operating Limit from 3898 to 4408 Mwt Project stage: RAI GNRO-2011/00037, Request for Additional Information Regarding Extended Power Uprate2011-05-11011 May 2011 Request for Additional Information Regarding Extended Power Uprate Project stage: Request ML1114002992011-05-20020 May 2011 E-mail, Request for Additional Information, Nrr/Dci/Emcb Review, Round 2, Amendment Request for Extended Power Uprate to Increase the Maximum Reactor Core Power Operating Limit from 3898 to 4408 Mwt Project stage: RAI ML1113905252011-05-31031 May 2011 Request for Withholding Information from Public Disclosure, 4/21/2011 Affidavit Executed by E. Schrull, GEH, for Attachment 1 to GNRO-2011/00025 Project stage: Withholding Request Acceptance ML1115204582011-06-0101 June 2011 Email, Request for Additional Information, Nrr/Dra/Aadb Review, Round 2, Amendment Request for Extended Power Uprate to Increase the Maximum Reactor Core Power Operating Limit from 3898 to 4408 Mwt Project stage: RAI ML1115304392011-06-0606 June 2011 (Redacted) Request for Additional Information from Nrr/De/Emcb Steam Dryer, Round 2, Amendment Request for Extended Power Uprate to Increase the Maximum Reactor Core Power Operating Limit from 3898 to 4408 Mwt Project stage: RAI GNRO-2011/00043, Request for Additional Information Regarding Extended Power Uprate2011-06-0808 June 2011 Request for Additional Information Regarding Extended Power Uprate Project stage: Request GNRO-2011/00046, Response to Request for Additional Information Regarding Extended Power Uprate2011-06-15015 June 2011 Response to Request for Additional Information Regarding Extended Power Uprate Project stage: Response to RAI ML1117200422011-06-20020 June 2011 Licensee Response Regarding Request for Additional Information on Training for Prnms (TAC No. 4679) Project stage: Request 2011-03-30
[Table View] |
|
---|
Category:Letter type:GNRO
MONTHYEARGNRO-2023/00014, License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b2023-06-0606 June 2023 License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b GNRO-2023/00015, Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors2023-06-0606 June 2023 Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors GNRO-2021/00037, 2021 Annual Report of Changes and Errors to 10 CFR 50.46 Analysis Grand Gulf Nuclear Station, Unit 12021-11-30030 November 2021 2021 Annual Report of Changes and Errors to 10 CFR 50.46 Analysis Grand Gulf Nuclear Station, Unit 1 GNRO-2021/00017, Notification of Readiness for Supplemental Inspection2021-06-22022 June 2021 Notification of Readiness for Supplemental Inspection GNRO-2021/00014, Inservice Testing Program Relief Request VRR-GGNS-2021-1 Pressure Isolation Valve Testing Frequency2021-06-0101 June 2021 Inservice Testing Program Relief Request VRR-GGNS-2021-1 Pressure Isolation Valve Testing Frequency GNRO-2021/00015, Annual Radioactive Effluent Release Report2021-04-28028 April 2021 Annual Radioactive Effluent Release Report GNRO-2021/00011, Revision of Original Report of 10CFR50.59 and Commitments Change Evaluations - July 1, 2018 Through May 21, 20202021-04-19019 April 2021 Revision of Original Report of 10CFR50.59 and Commitments Change Evaluations - July 1, 2018 Through May 21, 2020 GNRO-2021/00012, Annual Report of Individual Monitoring - NRC Form 5 for 2020 Per 10 CFR 20.22062021-04-13013 April 2021 Annual Report of Individual Monitoring - NRC Form 5 for 2020 Per 10 CFR 20.2206 GNRO-2020/00045, 2020 Report of Changes and Errors to 10 CFR 50.46 Analysis2020-12-16016 December 2020 2020 Report of Changes and Errors to 10 CFR 50.46 Analysis GNRO-2020/00034, Notification of Spent Fuel Cask Use2020-10-0808 October 2020 Notification of Spent Fuel Cask Use GNRO-2020/00033, Response to NRC Integrated Inspection Report 05000416/20200022020-09-10010 September 2020 Response to NRC Integrated Inspection Report 05000416/2020002 GNRO-2020/00029, Report of 10 CFR 72.48 Evaluations July 1, 2018 Through June 30, 20202020-08-18018 August 2020 Report of 10 CFR 72.48 Evaluations July 1, 2018 Through June 30, 2020 GNRO-2020/00022, Report of Technical Specification Bases Changes2020-07-21021 July 2020 Report of Technical Specification Bases Changes GNRO-2020/00027, Core Operating Limits Report (COLR) Cycle 23 Revision 1 for Grand Gulf Nuclear Station, Unit 1 (GGNS)2020-07-16016 July 2020 Core Operating Limits Report (COLR) Cycle 23 Revision 1 for Grand Gulf Nuclear Station, Unit 1 (GGNS) GNRO-2020/00023, Response to Request for Additional Information - License Amendment Request for Permanent Extension of Appendix J Type a Integrated Leakage Rate Test Frequencies2020-06-26026 June 2020 Response to Request for Additional Information - License Amendment Request for Permanent Extension of Appendix J Type a Integrated Leakage Rate Test Frequencies GNRO-2020/00020, Core Operating Limits Report (COLR) Cycle 23, and Pressure and Temperature Limits Report (PTLR) Update for Grand Gulf Nuclear Station, Unit 1 (GGNS)2020-05-0505 May 2020 Core Operating Limits Report (COLR) Cycle 23, and Pressure and Temperature Limits Report (PTLR) Update for Grand Gulf Nuclear Station, Unit 1 (GGNS) GNRO-2020/00018, Annual Radiological Effluent Release Report2020-04-30030 April 2020 Annual Radiological Effluent Release Report GNRO-2020/00016, Annual Report of Individual Monitoring -NRC Form 5 for 2019 Per 10 CFR 20.22062020-04-16016 April 2020 Annual Report of Individual Monitoring -NRC Form 5 for 2019 Per 10 CFR 20.2206 GNRO-2020/00015, Response to Request for Additional Information - License Amendment Request for One-Cycle Extension of Appendix J Type a Integrated Leakage Rate Test and Drywell Bypass Leakage Rate Test2020-04-0707 April 2020 Response to Request for Additional Information - License Amendment Request for One-Cycle Extension of Appendix J Type a Integrated Leakage Rate Test and Drywell Bypass Leakage Rate Test GNRO-2020/00007, Spent Fuel Storage Radioactive Effluent Release Report for 20192020-02-20020 February 2020 Spent Fuel Storage Radioactive Effluent Release Report for 2019 GNRO-2020/00006, License Amendment Request for Permanent Extension of Appendix J Type a Integrated Leakage Rate Test Frequencies2020-02-19019 February 2020 License Amendment Request for Permanent Extension of Appendix J Type a Integrated Leakage Rate Test Frequencies GNRO-2019/00052, Report of Changes and Errors to 10 CFR 50.46 Analysis2019-12-13013 December 2019 Report of Changes and Errors to 10 CFR 50.46 Analysis GNRO-2019/00051, Notification of Readiness of 92723 Inspection2019-12-11011 December 2019 Notification of Readiness of 92723 Inspection GNRO-2019/00045, Emergency Plan, Revision 792019-10-29029 October 2019 Emergency Plan, Revision 79 GNRO-2019/00037, Notification of Spent Fuel Cask Use2019-09-20020 September 2019 Notification of Spent Fuel Cask Use GNRO-2019/00036, Correction to Gnro 2019-00017 Emergency Plan Revision 782019-08-0808 August 2019 Correction to Gnro 2019-00017 Emergency Plan Revision 78 GNRO-2019/00027, Notification of Readiness of 95001 Supplemental Inspections2019-07-0303 July 2019 Notification of Readiness of 95001 Supplemental Inspections GNRO-2019/00031, Annual Report of Individual Monitoring - NRC Form 5 for 2018 Per 10 CFR 20.2206 - Corrected Report2019-06-25025 June 2019 Annual Report of Individual Monitoring - NRC Form 5 for 2018 Per 10 CFR 20.2206 - Corrected Report GNRO-2019/00028, Supplement to Revise Technical Specification (TS) 3.3.1.1, Reactor Protection System (RPS) Instrumentation, and TS 3.3.4.1, End of Cycle Recirculation Pump Trip (EOC-RPT) Instrumentation.2019-06-13013 June 2019 Supplement to Revise Technical Specification (TS) 3.3.1.1, Reactor Protection System (RPS) Instrumentation, and TS 3.3.4.1, End of Cycle Recirculation Pump Trip (EOC-RPT) Instrumentation. GNRO-2019/00026, Response to Requests for Additional Information Regarding Relief Request Number GG-ISI-023, Inservice Inspection Impracticality - Limited Coverage Examinations During the Third 10-Year Inservice Inspection Interval2019-05-0606 May 2019 Response to Requests for Additional Information Regarding Relief Request Number GG-ISI-023, Inservice Inspection Impracticality - Limited Coverage Examinations During the Third 10-Year Inservice Inspection Interval GNRO-2019/00024, Annual Radioactive Effluent Release Report2019-04-30030 April 2019 Annual Radioactive Effluent Release Report GNRO-2019/00020, Annual Radiological Operating Report (AREOR)2019-04-30030 April 2019 Annual Radiological Operating Report (AREOR) GNRO-2019/00022, Annual Report of Individual Monitoring - NRC Form 5 for 2018 Per 10 CFR 20.22062019-04-22022 April 2019 Annual Report of Individual Monitoring - NRC Form 5 for 2018 Per 10 CFR 20.2206 GNRO-2019/00017, Emergency Plan, Revision 782019-03-14014 March 2019 Emergency Plan, Revision 78 GNRO-2019/00014, Snubber Testing Program for Fourth Inspection Interval2019-03-13013 March 2019 Snubber Testing Program for Fourth Inspection Interval GNRO-2019/00012, Internal Events Probabilistic Risk Assessment (PRA) Sensitivity Study Regarding Risk-Informed Justification for the Relocation of Specific Surveillance Frequency Requirements to a Licensee Controlled Program2019-03-0606 March 2019 Internal Events Probabilistic Risk Assessment (PRA) Sensitivity Study Regarding Risk-Informed Justification for the Relocation of Specific Surveillance Frequency Requirements to a Licensee Controlled Program GNRO-2019/00016, Spent Fuel Storage Radioactive Effluent Release Report for 20182019-02-21021 February 2019 Spent Fuel Storage Radioactive Effluent Release Report for 2018 GNRO-2019/00003, Application to Revise Technical Specification (TS) 3.3.1.1, Reactor Protection System (RPS) Instrumentation, and TS 3.3.4.1, End of Cycle Recirculation Pump Trip (EOC-RPT) Instrumentation2019-01-23023 January 2019 Application to Revise Technical Specification (TS) 3.3.1.1, Reactor Protection System (RPS) Instrumentation, and TS 3.3.4.1, End of Cycle Recirculation Pump Trip (EOC-RPT) Instrumentation GNRO-2018/00057, Submittal of Revision 17 to the Grand Gulf Nuclear Station Physical Security, Safeguards Contingency, and Training and Qualification Plan2018-12-0404 December 2018 Submittal of Revision 17 to the Grand Gulf Nuclear Station Physical Security, Safeguards Contingency, and Training and Qualification Plan GNRO-2018/00055, Response to Request for Additional Information for Technical Specification Change Regarding Risk-Informed Justification for the Relocation of Specific Surveillance Frequency Requirements to a ...2018-11-30030 November 2018 Response to Request for Additional Information for Technical Specification Change Regarding Risk-Informed Justification for the Relocation of Specific Surveillance Frequency Requirements to a ... GNRO-2018/00054, Relief Request No. GG-ISI-023, Inservice Inspection Impracticality: Limited Coverage Examination During the Third 10-Year Inservice Inspection Interval2018-11-30030 November 2018 Relief Request No. GG-ISI-023, Inservice Inspection Impracticality: Limited Coverage Examination During the Third 10-Year Inservice Inspection Interval GNRO-2018/00052, License Amendment Request to Incorporate Tornado Missile Risk Evaluator Into Licensing Basis - Partial Response to Request for Additional Information and Extension of Response to Request for Additional Information2018-10-24024 October 2018 License Amendment Request to Incorporate Tornado Missile Risk Evaluator Into Licensing Basis - Partial Response to Request for Additional Information and Extension of Response to Request for Additional Information GNRO-2018/00051, Supplement to Revise Technical Specifications to Adopt Technical Specification Task Force Traveler TSTF-542, Reactor Pressure Vessel Water Inventory Control2018-10-23023 October 2018 Supplement to Revise Technical Specifications to Adopt Technical Specification Task Force Traveler TSTF-542, Reactor Pressure Vessel Water Inventory Control GNRO-2018/00046, Submittal of 2018 Report of Changes and Errors to 10CFR50.462018-10-16016 October 2018 Submittal of 2018 Report of Changes and Errors to 10CFR50.46 GNRO-2018/00047, Submittal of 2018 Inservice Inspection Summary Report2018-10-16016 October 2018 Submittal of 2018 Inservice Inspection Summary Report GNRO-2018/00048, Response to Request for Additional Information License Amendment Request, Adoption of Emergency Action Level Scheme Pursuant to NEI 99-01, Revision 62018-10-10010 October 2018 Response to Request for Additional Information License Amendment Request, Adoption of Emergency Action Level Scheme Pursuant to NEI 99-01, Revision 6 GNRO-2018/00042, Core Operating Limits Report Cycle 22, Revision 12018-09-18018 September 2018 Core Operating Limits Report Cycle 22, Revision 1 GNRO-2018/00043, Revised Offsite Dose Calculation Manual2018-09-18018 September 2018 Revised Offsite Dose Calculation Manual GNRO-2018/00039, Report of Technical Specification Bases Changes2018-08-20020 August 2018 Report of Technical Specification Bases Changes GNRO-2018/00040, Report of 10CFR50.59 Evaluations and Commitment Change Evaluations - July 1, 2016 Through June 30, 20182018-08-20020 August 2018 Report of 10CFR50.59 Evaluations and Commitment Change Evaluations - July 1, 2016 Through June 30, 2018 2023-06-06
[Table view] |
Text
Entergy Operations, Inc.
P. O. Box 756 Port Gibson, MS 39150 Michael A. Krupa Director, Extended Power Uprate Grand Gulf Nuclear Station Tel. (601) 437-6694 GNRO-2011/00111 December 19, 2011 U.S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555
SUBJECT:
Request for Additional Information Regarding Extended Power Uprate Grand Gulf Nuclear Station, Unit 1 Docket No. 50-416 License No. NPF-29
REFERENCES:
- 1. Entergy Operations, Inc. letter to the NRC (GNRO-2010/00056),
License Amendment Request - Extended Power Uprate, September 8, 2010 (ADAMS Accession No. ML102660403)
- 2. NRC e-mail to Entergy Operations, Inc., Grand Gulf Extended Power Uprate Reactor Systems Branch Request for Additional Information (ME4679), December 14, 2011
Dear Sir or Madam:
In Reference 1, Entergy submitted a license amendment request (LAR) to the NRC, which proposes an extended power uprate (EPU) for Grand Gulf Nuclear Station, Unit 1 (GGNS). To support its review and approval of this LAR, on October 27, 2011 the NRC staff conducted an on-site audit of the implementation of stability long-term solutions and the impact of EPU on instability and an Anticipated Transient without Scram (ATWS) event. As a result of that audit, the NRC has requested additional information (transmitted via Reference 2) pertaining to simulator scenarios reflecting EPU operating conditions, specifically:
- 1. Provide data for worst-case ATWS long-term scenario at EPU conditions. Include plots, sequence of events, and initial conditions.
- 2. Provide data for worst-case ATWS short-term pressure peak scenario at EPU conditions.
Include plots, sequence of events, and initial conditions.
Entergy is currently in the process of incorporating EPU-related system modifications and operating conditions into the GGNS simulator. Based on the current schedule, Entergy commits to provide the requested data to the NRC on or before February 15, 2012.
No change is needed to the no significant hazards consideration included in the initial LAR (Reference 1) as a result of the additional information provided. This letter contains one new commitment, which is identified in the attachment.
GNRO-2011/00111 Page 2 of 3 If you have any questions or require additional information, please contact Mr. Jerry Burford at 601-368-5755.
Sincerely, MAK/ghd
Attachment:
List of Regulatory Commitments
GNRO-2011/00111 Page 3 of 3 cc: Mr. Elmo E. Collins, Jr.
Regional Administrator, Region IV U. S. Nuclear Regulatory Commission 612 East Lamar Blvd., Suite 400 Arlington, TX 76011-4125 NRC Senior Resident Inspector Grand Gulf Nuclear Station Port Gibson, MS 39150 U. S. Nuclear Regulatory Commission ATTN: Mr. A. B. Wang, NRR/DORL ATTN: ADDRESSEE ONLY ATTN: Courier Delivery Only Mail Stop OWFN/8 B1 11555 Rockville Pike Rockville, MD 20852-2378 State Health Officer Mississippi Department of Health P. O. Box 1700 Jackson, MS 39215-1700
Attachment GNRO-2011/00111 Grand Gulf Nuclear Station Extended Power Uprate LIST OF REGULATORY COMMITMENTS
Attachment to GNRO-2011/00111 Page 1 of 1 LIST OF REGULATORY COMMITMENTS The following table identifies those actions committed to by Entergy in this document. Any other statements in this submittal are provided for information purposes and are not considered to be regulatory commitments.
TYPE SCHEDULED COMMITMENT (Check one) COMPLETION ONE-TIME CONTINUING DATE ACTION COMPLIANCE (If Required)
Entergy will provide data for the following simulator 2/15/2011 scenario runs on or before February 15, 2012:
- 1. Worst-case ATWS long-term scenario at EPU conditions. Include plots, sequence of events, and initial conditions.
- 2. Worst-case ATWS short-term pressure peak scenario at EPU conditions. Include plots, sequence of events, and initial conditions.