Letter Sequence Response to RAI |
---|
EPID:L-2020-LLA-0060, Certificate of Compliance No. 9302, Revision No. 11, for the Model No. NUHOMS MP197HB Package (Approved, Closed) |
|
|
|
---|
Category:Letter type:GNRO
MONTHYEARGNRO-2023/00014, License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b2023-06-0606 June 2023 License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b GNRO-2023/00015, Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors2023-06-0606 June 2023 Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors GNRO-2021/00037, 2021 Annual Report of Changes and Errors to 10 CFR 50.46 Analysis Grand Gulf Nuclear Station, Unit 12021-11-30030 November 2021 2021 Annual Report of Changes and Errors to 10 CFR 50.46 Analysis Grand Gulf Nuclear Station, Unit 1 GNRO-2021/00017, Notification of Readiness for Supplemental Inspection2021-06-22022 June 2021 Notification of Readiness for Supplemental Inspection GNRO-2021/00014, Inservice Testing Program Relief Request VRR-GGNS-2021-1 Pressure Isolation Valve Testing Frequency2021-06-0101 June 2021 Inservice Testing Program Relief Request VRR-GGNS-2021-1 Pressure Isolation Valve Testing Frequency GNRO-2021/00015, Annual Radioactive Effluent Release Report2021-04-28028 April 2021 Annual Radioactive Effluent Release Report GNRO-2021/00011, Revision of Original Report of 10CFR50.59 and Commitments Change Evaluations - July 1, 2018 Through May 21, 20202021-04-19019 April 2021 Revision of Original Report of 10CFR50.59 and Commitments Change Evaluations - July 1, 2018 Through May 21, 2020 GNRO-2021/00012, Annual Report of Individual Monitoring - NRC Form 5 for 2020 Per 10 CFR 20.22062021-04-13013 April 2021 Annual Report of Individual Monitoring - NRC Form 5 for 2020 Per 10 CFR 20.2206 GNRO-2020/00045, 2020 Report of Changes and Errors to 10 CFR 50.46 Analysis2020-12-16016 December 2020 2020 Report of Changes and Errors to 10 CFR 50.46 Analysis GNRO-2020/00034, Notification of Spent Fuel Cask Use2020-10-0808 October 2020 Notification of Spent Fuel Cask Use GNRO-2020/00033, Response to NRC Integrated Inspection Report 05000416/20200022020-09-10010 September 2020 Response to NRC Integrated Inspection Report 05000416/2020002 GNRO-2020/00029, Report of 10 CFR 72.48 Evaluations July 1, 2018 Through June 30, 20202020-08-18018 August 2020 Report of 10 CFR 72.48 Evaluations July 1, 2018 Through June 30, 2020 GNRO-2020/00022, Report of Technical Specification Bases Changes2020-07-21021 July 2020 Report of Technical Specification Bases Changes GNRO-2020/00027, Core Operating Limits Report (COLR) Cycle 23 Revision 1 for Grand Gulf Nuclear Station, Unit 1 (GGNS)2020-07-16016 July 2020 Core Operating Limits Report (COLR) Cycle 23 Revision 1 for Grand Gulf Nuclear Station, Unit 1 (GGNS) GNRO-2020/00023, Response to Request for Additional Information - License Amendment Request for Permanent Extension of Appendix J Type a Integrated Leakage Rate Test Frequencies2020-06-26026 June 2020 Response to Request for Additional Information - License Amendment Request for Permanent Extension of Appendix J Type a Integrated Leakage Rate Test Frequencies GNRO-2020/00020, Core Operating Limits Report (COLR) Cycle 23, and Pressure and Temperature Limits Report (PTLR) Update for Grand Gulf Nuclear Station, Unit 1 (GGNS)2020-05-0505 May 2020 Core Operating Limits Report (COLR) Cycle 23, and Pressure and Temperature Limits Report (PTLR) Update for Grand Gulf Nuclear Station, Unit 1 (GGNS) GNRO-2020/00018, Annual Radiological Effluent Release Report2020-04-30030 April 2020 Annual Radiological Effluent Release Report GNRO-2020/00016, Annual Report of Individual Monitoring -NRC Form 5 for 2019 Per 10 CFR 20.22062020-04-16016 April 2020 Annual Report of Individual Monitoring -NRC Form 5 for 2019 Per 10 CFR 20.2206 GNRO-2020/00015, Response to Request for Additional Information - License Amendment Request for One-Cycle Extension of Appendix J Type a Integrated Leakage Rate Test and Drywell Bypass Leakage Rate Test2020-04-0707 April 2020 Response to Request for Additional Information - License Amendment Request for One-Cycle Extension of Appendix J Type a Integrated Leakage Rate Test and Drywell Bypass Leakage Rate Test GNRO-2020/00007, Spent Fuel Storage Radioactive Effluent Release Report for 20192020-02-20020 February 2020 Spent Fuel Storage Radioactive Effluent Release Report for 2019 GNRO-2020/00006, License Amendment Request for Permanent Extension of Appendix J Type a Integrated Leakage Rate Test Frequencies2020-02-19019 February 2020 License Amendment Request for Permanent Extension of Appendix J Type a Integrated Leakage Rate Test Frequencies GNRO-2019/00052, Report of Changes and Errors to 10 CFR 50.46 Analysis2019-12-13013 December 2019 Report of Changes and Errors to 10 CFR 50.46 Analysis GNRO-2019/00051, Notification of Readiness of 92723 Inspection2019-12-11011 December 2019 Notification of Readiness of 92723 Inspection GNRO-2019/00045, Emergency Plan, Revision 792019-10-29029 October 2019 Emergency Plan, Revision 79 GNRO-2019/00037, Notification of Spent Fuel Cask Use2019-09-20020 September 2019 Notification of Spent Fuel Cask Use GNRO-2019/00036, Correction to Gnro 2019-00017 Emergency Plan Revision 782019-08-0808 August 2019 Correction to Gnro 2019-00017 Emergency Plan Revision 78 GNRO-2019/00027, Notification of Readiness of 95001 Supplemental Inspections2019-07-0303 July 2019 Notification of Readiness of 95001 Supplemental Inspections GNRO-2019/00031, Annual Report of Individual Monitoring - NRC Form 5 for 2018 Per 10 CFR 20.2206 - Corrected Report2019-06-25025 June 2019 Annual Report of Individual Monitoring - NRC Form 5 for 2018 Per 10 CFR 20.2206 - Corrected Report GNRO-2019/00028, Supplement to Revise Technical Specification (TS) 3.3.1.1, Reactor Protection System (RPS) Instrumentation, and TS 3.3.4.1, End of Cycle Recirculation Pump Trip (EOC-RPT) Instrumentation.2019-06-13013 June 2019 Supplement to Revise Technical Specification (TS) 3.3.1.1, Reactor Protection System (RPS) Instrumentation, and TS 3.3.4.1, End of Cycle Recirculation Pump Trip (EOC-RPT) Instrumentation. GNRO-2019/00026, Response to Requests for Additional Information Regarding Relief Request Number GG-ISI-023, Inservice Inspection Impracticality - Limited Coverage Examinations During the Third 10-Year Inservice Inspection Interval2019-05-0606 May 2019 Response to Requests for Additional Information Regarding Relief Request Number GG-ISI-023, Inservice Inspection Impracticality - Limited Coverage Examinations During the Third 10-Year Inservice Inspection Interval GNRO-2019/00024, Annual Radioactive Effluent Release Report2019-04-30030 April 2019 Annual Radioactive Effluent Release Report GNRO-2019/00020, Annual Radiological Operating Report (AREOR)2019-04-30030 April 2019 Annual Radiological Operating Report (AREOR) GNRO-2019/00022, Annual Report of Individual Monitoring - NRC Form 5 for 2018 Per 10 CFR 20.22062019-04-22022 April 2019 Annual Report of Individual Monitoring - NRC Form 5 for 2018 Per 10 CFR 20.2206 GNRO-2019/00017, Emergency Plan, Revision 782019-03-14014 March 2019 Emergency Plan, Revision 78 GNRO-2019/00014, Snubber Testing Program for Fourth Inspection Interval2019-03-13013 March 2019 Snubber Testing Program for Fourth Inspection Interval GNRO-2019/00012, Internal Events Probabilistic Risk Assessment (PRA) Sensitivity Study Regarding Risk-Informed Justification for the Relocation of Specific Surveillance Frequency Requirements to a Licensee Controlled Program2019-03-0606 March 2019 Internal Events Probabilistic Risk Assessment (PRA) Sensitivity Study Regarding Risk-Informed Justification for the Relocation of Specific Surveillance Frequency Requirements to a Licensee Controlled Program GNRO-2019/00016, Spent Fuel Storage Radioactive Effluent Release Report for 20182019-02-21021 February 2019 Spent Fuel Storage Radioactive Effluent Release Report for 2018 GNRO-2019/00003, Application to Revise Technical Specification (TS) 3.3.1.1, Reactor Protection System (RPS) Instrumentation, and TS 3.3.4.1, End of Cycle Recirculation Pump Trip (EOC-RPT) Instrumentation2019-01-23023 January 2019 Application to Revise Technical Specification (TS) 3.3.1.1, Reactor Protection System (RPS) Instrumentation, and TS 3.3.4.1, End of Cycle Recirculation Pump Trip (EOC-RPT) Instrumentation GNRO-2018/00057, Submittal of Revision 17 to the Grand Gulf Nuclear Station Physical Security, Safeguards Contingency, and Training and Qualification Plan2018-12-0404 December 2018 Submittal of Revision 17 to the Grand Gulf Nuclear Station Physical Security, Safeguards Contingency, and Training and Qualification Plan GNRO-2018/00055, Response to Request for Additional Information for Technical Specification Change Regarding Risk-Informed Justification for the Relocation of Specific Surveillance Frequency Requirements to a ...2018-11-30030 November 2018 Response to Request for Additional Information for Technical Specification Change Regarding Risk-Informed Justification for the Relocation of Specific Surveillance Frequency Requirements to a ... GNRO-2018/00054, Relief Request No. GG-ISI-023, Inservice Inspection Impracticality: Limited Coverage Examination During the Third 10-Year Inservice Inspection Interval2018-11-30030 November 2018 Relief Request No. GG-ISI-023, Inservice Inspection Impracticality: Limited Coverage Examination During the Third 10-Year Inservice Inspection Interval GNRO-2018/00052, License Amendment Request to Incorporate Tornado Missile Risk Evaluator Into Licensing Basis - Partial Response to Request for Additional Information and Extension of Response to Request for Additional Information2018-10-24024 October 2018 License Amendment Request to Incorporate Tornado Missile Risk Evaluator Into Licensing Basis - Partial Response to Request for Additional Information and Extension of Response to Request for Additional Information GNRO-2018/00051, Supplement to Revise Technical Specifications to Adopt Technical Specification Task Force Traveler TSTF-542, Reactor Pressure Vessel Water Inventory Control2018-10-23023 October 2018 Supplement to Revise Technical Specifications to Adopt Technical Specification Task Force Traveler TSTF-542, Reactor Pressure Vessel Water Inventory Control GNRO-2018/00046, Submittal of 2018 Report of Changes and Errors to 10CFR50.462018-10-16016 October 2018 Submittal of 2018 Report of Changes and Errors to 10CFR50.46 GNRO-2018/00047, Submittal of 2018 Inservice Inspection Summary Report2018-10-16016 October 2018 Submittal of 2018 Inservice Inspection Summary Report GNRO-2018/00048, Response to Request for Additional Information License Amendment Request, Adoption of Emergency Action Level Scheme Pursuant to NEI 99-01, Revision 62018-10-10010 October 2018 Response to Request for Additional Information License Amendment Request, Adoption of Emergency Action Level Scheme Pursuant to NEI 99-01, Revision 6 GNRO-2018/00042, Core Operating Limits Report Cycle 22, Revision 12018-09-18018 September 2018 Core Operating Limits Report Cycle 22, Revision 1 GNRO-2018/00043, Revised Offsite Dose Calculation Manual2018-09-18018 September 2018 Revised Offsite Dose Calculation Manual GNRO-2018/00039, Report of Technical Specification Bases Changes2018-08-20020 August 2018 Report of Technical Specification Bases Changes GNRO-2018/00040, Report of 10CFR50.59 Evaluations and Commitment Change Evaluations - July 1, 2016 Through June 30, 20182018-08-20020 August 2018 Report of 10CFR50.59 Evaluations and Commitment Change Evaluations - July 1, 2016 Through June 30, 2018 2023-06-06
[Table view] Category:Response to Request for Additional Information (RAI)
MONTHYEARML24012A1962024-01-12012 January 2024 Response to 2nd Round Request for Additional Information Concerning Relief Request Number EN-RR-22-001 Proposed Alternative to Use ASME Code Case N-752, Risk-Informed Categorization and ML23159A2302023-06-0808 June 2023 Response to Request for Additional Information Concerning Request to Update ASME Code Relief Request Safety Evaluations with NRC-Approved Revision of BWRVIP Guidelines (GG-ISI-020, and RBS-ISI-019) ML23111A2132023-04-21021 April 2023 Responses to RAI Concerning Relief Request Number EN-RR-22-001 Proposed Alternative to Use ASME Code Case N-752, Risk-Informed Categorization and Treatment for Repair/ Replacement Activities CNRO-2021-00002, Entergy Operations, Inc. - Basis for Concluding the Terms of Confirmatory Order EA-17-132/EA-17-153 Are Complete, Element L2021-01-28028 January 2021 Entergy Operations, Inc. - Basis for Concluding the Terms of Confirmatory Order EA-17-132/EA-17-153 Are Complete, Element L CNRO-2020-00021, Response to Request for Additional Information Regarding Relief Requests GG-ISI-020 and RBS-ISI-0192020-11-0909 November 2020 Response to Request for Additional Information Regarding Relief Requests GG-ISI-020 and RBS-ISI-019 GNRO-2020/00023, Response to Request for Additional Information - License Amendment Request for Permanent Extension of Appendix J Type a Integrated Leakage Rate Test Frequencies2020-06-26026 June 2020 Response to Request for Additional Information - License Amendment Request for Permanent Extension of Appendix J Type a Integrated Leakage Rate Test Frequencies GNRO-2020/00015, Response to Request for Additional Information - License Amendment Request for One-Cycle Extension of Appendix J Type a Integrated Leakage Rate Test and Drywell Bypass Leakage Rate Test2020-04-0707 April 2020 Response to Request for Additional Information - License Amendment Request for One-Cycle Extension of Appendix J Type a Integrated Leakage Rate Test and Drywell Bypass Leakage Rate Test CNRO-2019-00030, Response to Confirmatory Order EA-17-132/EA-17-153, Element K 2019 Summary2019-12-30030 December 2019 Response to Confirmatory Order EA-17-132/EA-17-153, Element K 2019 Summary GNRO-2019/00026, Response to Requests for Additional Information Regarding Relief Request Number GG-ISI-023, Inservice Inspection Impracticality - Limited Coverage Examinations During the Third 10-Year Inservice Inspection Interval2019-05-0606 May 2019 Response to Requests for Additional Information Regarding Relief Request Number GG-ISI-023, Inservice Inspection Impracticality - Limited Coverage Examinations During the Third 10-Year Inservice Inspection Interval ML19023A3282019-01-23023 January 2019 Response to Request for Additional Information Regarding License Amendment Request to Incorporate Tornado Missile Risk Evaluator Into Licensing Basis - Supplement GNRO-2018/00055, Response to Request for Additional Information for Technical Specification Change Regarding Risk-Informed Justification for the Relocation of Specific Surveillance Frequency Requirements to a ...2018-11-30030 November 2018 Response to Request for Additional Information for Technical Specification Change Regarding Risk-Informed Justification for the Relocation of Specific Surveillance Frequency Requirements to a ... GNRO-2018/00052, License Amendment Request to Incorporate Tornado Missile Risk Evaluator Into Licensing Basis - Partial Response to Request for Additional Information and Extension of Response to Request for Additional Information2018-10-24024 October 2018 License Amendment Request to Incorporate Tornado Missile Risk Evaluator Into Licensing Basis - Partial Response to Request for Additional Information and Extension of Response to Request for Additional Information GNRO-2018/00048, Response to Request for Additional Information License Amendment Request, Adoption of Emergency Action Level Scheme Pursuant to NEI 99-01, Revision 62018-10-10010 October 2018 Response to Request for Additional Information License Amendment Request, Adoption of Emergency Action Level Scheme Pursuant to NEI 99-01, Revision 6 GNRO-2017/00068, Response to Official Requests for Additional Information (RAI) for RR GG-ISI-020 to Use BWRVIP Guidelines2017-10-12012 October 2017 Response to Official Requests for Additional Information (RAI) for RR GG-ISI-020 to Use BWRVIP Guidelines ML17269A0782017-09-22022 September 2017 Response to Request for Additional Information (RAI) for Relief Request GG-ISl-021 Associated with Fourth Interval Inservice Inspection Using Code CAS N-702, Dated August 8, 2017 GNRO-2017/00053, Response to Eseb RAI-1, Results of IWE and Iwl Inspections2017-08-25025 August 2017 Response to Eseb RAI-1, Results of IWE and Iwl Inspections GNRO-2016/00059, Response to Generic Letter 2016-01 Regarding Monitoring of Neutron-Absorbing Materials in Spent Fuel Pools2016-11-0101 November 2016 Response to Generic Letter 2016-01 Regarding Monitoring of Neutron-Absorbing Materials in Spent Fuel Pools GNRO-2016/00040, Response to Request for Additional Information (RAI) on Severe Accident Mitigation Alternatives (SAMA) for Grand Gulf Nuclear Station License Renewal Environmental Review2016-09-0707 September 2016 Response to Request for Additional Information (RAI) on Severe Accident Mitigation Alternatives (SAMA) for Grand Gulf Nuclear Station License Renewal Environmental Review GNRO-2016/00036, Response to Requests for Additional Information (Rais) Regarding Final Integrated Plan for Implementation of Order EA-12-051, Reliable Spent Fuel Pool Instrumentation2016-07-29029 July 2016 Response to Requests for Additional Information (Rais) Regarding Final Integrated Plan for Implementation of Order EA-12-051, Reliable Spent Fuel Pool Instrumentation CNRO-2016-00016, Entergy - Response to RAI Questions and Submittal of Relief Request EN-ISI-15-1 (Updated)2016-06-0202 June 2016 Entergy - Response to RAI Questions and Submittal of Relief Request EN-ISI-15-1 (Updated) ML16071A4412016-03-0707 March 2016 Entergy Fleet Relief Request No. RR-EN-15-1-Proposed Alternative to Use ASME Code Case N-789-1 - E-mail from G.Davant to R.Guzman - Response to Second RAI (MF6340 - MF6349) GNRO-2016/00013, Supplemental Correction Response to License Renewal Amendment Request for Additional Information Set 472016-02-26026 February 2016 Supplemental Correction Response to License Renewal Amendment Request for Additional Information Set 47 CNRO-2016-00005, Response to Request for Additional Information Pertaining to a Change to the Entergy Quality Assurance Program Manual (QAPM)2016-02-25025 February 2016 Response to Request for Additional Information Pertaining to a Change to the Entergy Quality Assurance Program Manual (QAPM) CNRO-2016-00002, Entergy - Relief Request Number RR EN-15-1, Rev. 1 - Proposed Alternative to Use ASME Code Case N-789-1, Alternative Requirements for Pad Reinforcement of Class 2 and 3 Moderate Energy Carbon Steel Piping for Raw Water Service, Secti2016-01-29029 January 2016 Entergy - Relief Request Number RR EN-15-1, Rev. 1 - Proposed Alternative to Use ASME Code Case N-789-1, Alternative Requirements for Pad Reinforcement of Class 2 and 3 Moderate Energy Carbon Steel Piping for Raw Water Service, Section Xl, ML15348A4022015-12-14014 December 2015 Amended Response to Request for Additional Information (RAI) 4.2.3-2, Dated October 28, 2015 GNRO-2015/00091, Supplemental Response to Request for Additional Information Regarding License Amendment Request to Revise Technical Specifications for Containment Leak Rate Testing/2015-12-10010 December 2015 Supplemental Response to Request for Additional Information Regarding License Amendment Request to Revise Technical Specifications for Containment Leak Rate Testing/ CNRO-2015-00002, Entergy Operations, Inc. - Response to RAI Questions and Submittal of RR EN-15-2, Rev. 12015-12-0404 December 2015 Entergy Operations, Inc. - Response to RAI Questions and Submittal of RR EN-15-2, Rev. 1 GNRO-2015/00077, Request for Additional Information Regarding Application to Revise Technical Specifications to Adopt Technical Specification Task Force (TSTF) TSTF-522, Revise Ventilation System Surveillance Requirements to Operate for 10 Hours.2015-11-24024 November 2015 Request for Additional Information Regarding Application to Revise Technical Specifications to Adopt Technical Specification Task Force (TSTF) TSTF-522, Revise Ventilation System Surveillance Requirements to Operate for 10 Hours. GNRO-2015/00079, Responses to Request for Additional Information (RAI) Set 53, Dated October 28, 20152015-11-23023 November 2015 Responses to Request for Additional Information (RAI) Set 53, Dated October 28, 2015 GNRO-2015/00063, Response to Request for Additional Information Regarding License Amendment Request to Revise Technical Specifications for Containment Leak Rate Testing2015-10-28028 October 2015 Response to Request for Additional Information Regarding License Amendment Request to Revise Technical Specifications for Containment Leak Rate Testing GNRO-2015/00064, Response to Electronic Request for Additional Information Regarding Modification of Technical Specification (TS) 3.8.4, DC Sources Operating Surveillance Requirements (Srs) 3.8.4.2 and 3.8.4.5 Amendment Request, 08/28/20152015-10-15015 October 2015 Response to Electronic Request for Additional Information Regarding Modification of Technical Specification (TS) 3.8.4, DC Sources Operating Surveillance Requirements (Srs) 3.8.4.2 and 3.8.4.5 Amendment Request, 08/28/2015 GNRO-2015/00060, Request for Additional Information Regarding Application to Revise Technical Specifications to Adopt Technical Specification Task Force (TSTF) TSTF-522, Revise Ventilation System Surveillance Requirements to Operate for 10 Hours..2015-10-12012 October 2015 Request for Additional Information Regarding Application to Revise Technical Specifications to Adopt Technical Specification Task Force (TSTF) TSTF-522, Revise Ventilation System Surveillance Requirements to Operate for 10 Hours.. GNRO-2015/00058, Response to License Renewal Application (LRA) Request for Additional Information (RAI) Set 47, Question 4.2.1-2c (5) (a) I2015-09-0101 September 2015 Response to License Renewal Application (LRA) Request for Additional Information (RAI) Set 47, Question 4.2.1-2c (5) (a) I GNRO-2015/00042, Response to License Amendment Request for Revision of Five Technical Specification Allowable Value Setpoints Request for Additional Information, Set No. 2, Revision 12015-06-30030 June 2015 Response to License Amendment Request for Revision of Five Technical Specification Allowable Value Setpoints Request for Additional Information, Set No. 2, Revision 1 2024-01-12
[Table view] |
Text
Entergy Operations, Inc.
1340 Echelon Parkway Jackson, MS 39213 Tel 601-368-5138 Ron Gaston Director, Nuclear Licensing 10 CFR 50.90 GNRO-2020/00015 April 7, 2020 ATTN: Document Control Desk U.S. Nuclear Regulatory Commission Washington, DC 20555-0001
Subject:
Response to Request for Additional Information - License Amendment Request for One-Cycle Extension of Appendix J Type A Integrated Leakage Rate Test and Drywell Bypass Leakage Rate Test Grand Gulf Nuclear Station, Unit 1 NRC Docket No. 50-416 Renewed Facility Operating License No. NPF-29
References:
- 1) Entergy Operations, Inc. (Entergy) letter to U. S. Nuclear Regulatory Commission (NRC), "License Amendment Request for One-Cycle Extension of Appendix J Type A Integrated Leakage Rate Test and Drywell Bypass Leakage Rate Test," (ADAMS Accession No. ML20091M363), dated March 31, 2020
- 2) NRC Electronic mail from S. P. Lingam (NRC) to J. Shaw (Entergy),
Subject:
"Grand Gulf - RAI for Exigent LAR Associated with One-Time Extension of Appendix J Type A Integrated Leakage Rate Test Frequencies from 11.5 Years to 13.5 Years (EPID L-2020-LLA-0060),"
dated April 6, 2020 In Reference 1, Entergy Operations, Inc. (Entergy) submitted a request for a proposed amendment to Renewed Facility Operating License (FOL) NPF-29, Appendix A, "Technical Specifications" (TS) for Grand Gulf Nuclear Station, Unit 1 (GGNS). The proposed change would allow for a one-cycle extension of the interval to perform the GGNS Type A integrated leakage rate test (ILRT) and drywell bypass leakage rate test (DWBT) from 11.5 years to 13.5 years.
In Reference 2, the U. S. Nuclear Regulatory Commission (NRC) transmitted a request for additional information (RAI) concerning the proposed license amendment. The Enclosure to this letter provides a response to the NRC RAI.
GNRO-2020/00015 Page 2 of 2 In addition, Attachments 1 and 2 to the Enclosure provide updated versions of the existing TS pages marked up to show the proposed changes and revised (clean) TS pages.
This letter contains no new regulatory commitments.
Should you have any questions or require additional information, please contact Ron Gaston, Director, Nuclear Licensing at 601-368-5138.
In accordance with 10 CFR 50.91, "Notice for public comment; State consultation," paragraph (b), a copy of this application, with attachments, is being provided to the designated State Officials.
I declare under penalty of perjury, the foregoing is true and correct. Executed on April 7, 2020.
Respectfully, Ron Gaston RWG/jls
Enclosure:
Response to Request for Additional Information Attachments to
Enclosure:
- 1. Markup of Technical Specification Pages
- 2. Retyped Technical Specification Pages cc: NRC Region IV Regional Administrator NRC Senior Resident Inspector - Grand Gulf Nuclear Station, Unit 1 State Health Officer, Mississippi Department of Health NRC Project Manager - Grand Gulf Nuclear Station, Unit 1
Enclosure GNRO-2020/00015 Response to Request for Additional Information
Enclosure to GNRO-2020/00015 Page 1 of 5 RESPONSE TO REQUEST FOR ADDITIONAL INFORMATION By letter dated March 31, 2020 (Reference 1), Entergy Operations, Inc. (Entergy), requested NRC approval of a proposed amendment to Renewed Facility Operating License (FOL) NPF-29, Appendix A, "Technical Specifications" (TS) for Grand Gulf Nuclear Station, Unit 1 (GGNS). The proposed change would allow for a one-cycle extension of the interval to perform the GGNS Type A integrated leakage rate test (ILRT) and drywell bypass leakage rate test (DWBT) from 11.5 years to 13.5 years.
By email dated April 6, 2020 (Reference 2), the NRC informed Entergy that additional information is needed to support the Staffs continued review of the application. The specific question presented in the Reference 2 request for additional information (RAI) is repeated below for ease of review. Entergys response is provided thereafter.
RAI-1
Based on the testing of Type B and Type C component testing performed to date in the current outage (RF22), provide a brief synopsis of the testing results. The information should include the performance testing of the above components that did not show acceptable performance in the previous two outages. In addition, include information on any other components that exceeded the administrative acceptance criteria limits in the current outage and the basis for acceptance of the test results (i.e., actions taken for correcting the leakage or acceptance in as is condition).
Entergy Response As of April 6, 2020, GGNS has completed 92% of the as-found (AF) Type B and Type C Local Leakage Rate Tests (LLRTs) and 29% of the as-left (AL) LLRTs for Refueling Outage (RF) 22.
Type B and C LLRT results indicate <33% of the 0.6La margin for Maximum Pathway Leakage and <15% of the 0.6La margin for Minimum Pathway Leakage. There have been four AF LLRT components which exceeded their administrative leakage limits during RF22, seven during RF21, and seven during RF20. Additional details are provided in Tables 1, 2, and 3, below.
Two of the four RF22 components which exceeded their local administrative limits (i.e., P53F001 and P45F062) were corrected by completing actuator rebuilds. The D23F593 and E12F044A AF leakage values were accepted, and no further work is planned for RF22. The leakage values were acceptable, as neither of the exceeded administrative limits challenged the overall margin to 0.6La, and their respective penetrations were not inoperable.
E12F044A is the only component which exceeded its administrative limit in both RF21 and RF22.
E12F044A exceeded its administrative limit in RF21 with an AF leakage of 1275 sccm. A valve internal inspection was completed during RF21 (Reference Table 2); However, the 1280 sccm AL leakage remained above the administrative limit of 1040 sccm. E12F044A exceeded its administrative limit in RF22 with an AF leakage of 1950 sccm. The resultant increase of 670 sccm from the RF21 AL value to the RF22 AF value represents 0.34% of the overall margin to 0.6La. This did not challenge the overall margin to 0.6La. Additional information is provided in Table 1.
G36F106, B21F016, and E12F028B exceeded their administrative leakage limits in both RF20 and RF21. These valves were repaired or replaced, as indicated in Table 2 below, and did not exceed their administrative leakage limit in RF22.
Enclosure to GNRO-2020/00015 Page 2 of 5 Table 1: RF22 Type B and C Components Exceeding Administrative Limits Valve/Penetration Leakage Administrative Condition Report Resolution (sccm) Leakage Number (sccm)
P53F001 AF: 725 sccm 650 sccm CR-GGN-2020-2771 Work Order (WO)
Instrument Air AL: 60 sccm 52830932 for actuator Outboard rebuild preventative Containment maintenance; Leakage Isolation Valve (CIV) issues resolved after rebuild.
P45F062 AF: 1800 sccm 1580 sccm CR-GGN-2020-3195 Actuator rebuild under the Drywell & AL: 0 sccm same WO (52830471-Containment Floor 01A/B/C). Leakage issues Drain Sump resolved after rebuild.
Pump Discharge Outboard CIV D23F593 AF: 1890 sccm 195 sccm CR-GGN-2020-3313 No other work planned in Drywell Fission RF22; WO 541006 moved Product Monitor to RF23. Leakage Return Inboard CIV accepted. Did not challenge overall margin to 0.6La.
Outboard valve, D23F594, tested satisfactory in RF22 with a leakage of 20 sccm.
continued
Enclosure to GNRO-2020/00015 Page 3 of 5 Table 1: RF22 Type B and C Components Exceeding Administrative Limits (cont.)
Valve/Penetration Leakage Administrative Condition Report Resolution (sccm) Leakage Number (sccm)
E12F044A AF: 1950 sccm 1040 sccm CR-GGN-2020-4379 Exceeded administrative Residual Heat CR-GGN-2020-4631 limit in RF21 and RF22. No Removal (RHR) "A" other work planned in to Low Pressure RF22; Replacement valve Coolant Injection purchased from (LPCI) Inboard CIV manufacturer and expected to be delivered summer 2020 for RF23.
An alternate option is based on discussion with Operations Engineering.
This line is not used at the site; therefore, a request has been submitted for an modification in RF23 to cut and cap the line where E12F044A and its sister valve E12F044B are installed.
For RF22, leakage was accepted as it does not challenge overall margin to 0.6La. E12F044A is an inboard isolation valve in Penetration 20. Other inboard valves in this penetration include E12F042A, E12F028A, E12F025A, and E12F037A as well as E12F027A serving as the outboard valve. All the other components in this penetration tested below their administrative limit.
Enclosure to GNRO-2020/00015 Page 4 of 5 Table 2: RF21 Type B and C Components Exceeding Administrative Limits Valve/Penetration Leakage Administrative Condition Report Resolution (sccm) Leakage Limit Number (sccm)
E12F028B AF: 13800 sccm 4680 sccm CR-GGN-2018-3724 Engineering Change (EC)
RHR "B" to LPCI AL: 40 sccm 78125 was implemented to Inboard CIV accept valve testing in reverse direction, as valve is a containment isolation valve upstream of the containment spray header ring and testing is in direction that would assist in unseating valve.
G36F106 AF: 71000 sccm 1040 sccm CR-GGN-2018-3863 Valve seat replacement.
Reactor Water AL: 0 sccm Cleanup (RWCU)
Backwash Transfer Pump Discharge Inboard CIV E51F064 AF: 3380 sccm 2600 sccm CR-GGN-2018-4166 Actuator rebuild performed.
Steam Supply to AL: 3570 sccm CR-GGN-2018-5845 Torque switch adjustments Reactor Core left leakage at 3570 sccm; Isolation Coolant In-body inspection (RCIC) Turbine performed to blue check Outboard CIV and cleaned seat.
Retested in RF22; as-found LLRT was satisfactory.
P53F002 AF: 800 sccm 650 sccm CR-GGN-2018-4236 Valve replacement under Instrument Air AL: 450 sccm CR-GGN-2018-6352 WO-500229.
Inboard CIV B21F016 AF: 18600 sccm 780 sccm CR-GGN-2018-4448 Valve replacement under Main Steam Line AL: 70 sccm WO 376662.
(MSL) Drain, (Main Steam Isolation Valve (MSIV))
Inboard CIV E30P120 AF: 145 sccm 100 sccm CR-GGN-2018-5190 Appendix J has no Suppression Pool AL: 145 sccm requirements beyond Level Instrument commitment to count the Tubing Outboard leakage against the running total. No operability concerns to address.
Leakage Reduction Program has confirmed leakage within program limits.
E12F044A AF: 1275 sccm 1040 sccm CR-GGN-2018-6191 Issue with troubleshooting Residual Heat AL: 1280 sccm handwheel as threads were Removal (RHR) "A" not engaged; Performed a to Low Pressure valve inbody inspection of Coolant Injection E12F044A, including blue (LPCI) Inboard CIV check of the valve seat.
Enclosure to GNRO-2020/00015 Page 5 of 5 Table 3: RF20 Type B and C Components Exceeding Administrative Limits Valve/Penetration Leakage Administrative Condition Report Resolution (sccm) Leakage Limit Number (sccm)
B21F028A AF: 81000 sccm 47200 sccm CR-GGN-2016-1398 Repaired valve under MSIV for MSL "A" AL: 33400 sccm CR-GGN-2016-1456 WO 52568389.
Outboard CIV B21F016 AF: 9860 sccm 780 sccm CR-GGN-2016-1577 Accepted AF data as AL MSL Drain, MSIV AL: 9860 sccm CR-GGN-2016-1586 and replaced in RF21.
Inboard CIV E12F028B AF: 8600 sccm 4680 sccm CR-GGN-2016-1587 WO 52564082 replaced RHR "B" to LPCI AL: 1400 sccm wearable parts such as seal Inboard CIV ring gasket and replaced the valve internals.
B33F125 AF: >20000 260 sccm CR-GGN-2016-1706 CR notes recommendation Reactor sccm to adjust the torque/limit Recirculation Post AL: 2 sccm setting on B33F125 to Accident Sampling reduce leakage. Repaired Outboard CIV under WO 439571.
G36F106 AF: 37000 sccm 1040 sccm CR-GGN-2016-1860 Recommended in CR to Reactor Water AL: 28600 sccm troubleshoot/rework valve; Cleanup (RWCU) Repaired in RF21.
Backwash Transfer Pump Discharge Inboard CIV E22F004 AF: 40300 sccm 3120 sccm CR-GGN-2016-2380 Exceeded leakage was due High Pressure AL: 2650 sccm to boundary valve leakage.
Core Spray The valve was retested and (HPCS) Pump passed its AL LLRT.
Discharge to Reactor Pressure Vessel (RPV)
REFERENCES
- 1. Entergy Operations, Inc. (Entergy) letter to U. S. Nuclear Regulatory Commission (NRC),
"License Amendment Request for One-Cycle Extension of Appendix J Type A Integrated Leakage Rate Test and Drywell Bypass Leakage Rate Test," (ADAMS Accession No. ML20091M363), dated March 31, 2020
- 2. NRC Electronic mail from S. P. Lingam (NRC) to J. Shaw (Entergy),
Subject:
"Grand Gulf - RAI for Exigent LAR Associated with One-Time Extension of Appendix J Type A Integrated Leakage Rate Test Frequencies from 11.5 Years to 13.5 Years (EPID L-2020-LLA-0060)," dated April 6, 2020Regulatory Guide (RG) 1.163, "Performance-Based Containment Leak-Test Program," September 1995.
Attachment 1 to Enclosure GNRO-2020/00015 Markup of Technical Specification Pages TS Page 3.6-53 5.0-16
Drywell 3.6.5.1 SURVEILLANCE REQUIREMENTS SURVEILLANCE FREQUENCY SR 3.6.5.1.1 Verify bypass leakage is less than or equal to the 24 months following bypass leakage limit. two consecutive tests with bypass leakage However, during the first unit startup following greater than the drywell bypass leak rate testing performed in bypass leakage limit accordance with this SR, the acceptance criterion until two consecutive is leakage < 10% of the bypass leakage limit. tests are less than or equal to the bypass leakage limit AND 48 months following a test with bypass leakage greater than the bypass leakage limit AND
NOTE--------
SR 3.0.2 is not applicable for extensions
> 12 months.
the In accordance with the Surveillance Frequency Control Program except next drywell bypass 23 leak rate test performed after October 19, 2008 test shall be performed no later than plant restart after End of Cycle 22 Refueling Outage (continued)
GRAND GULF 3.6-53 Amendment No. 126*, 164, 209, 214, 219
- With Correction Letter of 9/16/96
Programs and Manuals 5.5 5.5 Programs and Manuals (continued) 5.5.11 Technical Specifications (TS) Bases Control Program This program provides a means for processing changes to the Bases of these Technical Specifications.
- a. Changes to the Bases of the TS shall be made under appropriate administrative controls and reviews.
- b. Licensees may make changes to Bases without prior NRC approval provided the changes do not require either of the following:
- 1. A change in the TS incorporated in the license; or
- 2. A change to the updated FSAR or Bases that requires NRC approval pursuant to 10 CFR 50.59.
- c. The Bases Control Program shall contain provisions to ensure that the Bases are maintained consistent with the UFSAR.
- d. Proposed changes that do not meet the criteria of either Specification 5.5.11.b.1 or Specification 5.5.11.b.2 above shall be reviewed and approved by the NRC prior to implementation. Changes to the Bases implemented without prior NRC approval shall be provided to the NRC on a frequency consistent with 10 CFR 50.71(e).
5.5.12 10 CFR 50, Appendix J, Testing Program 23 This program establishes the leakage rate testing program of the containment as required by 10 CFR 50.54(o) and 10 CFR 50, Appendix J, Option B, as modified by approved exemptions. This program shall be implemented in accordance with the Safety Evaluation issued by the Office of Nuclear Reactor Regulation dated April 26, 1995 (GNRI-95/00087) as modified by the Safety Evaluation issued for Amendment No. 135 to the Operating License, except that the next Type A test performed after the October 19, 2008 Type A test shall be performed no later than the plant restart after the End of Cycle 22 Refueling Outage. For Type B and Type C local leakage rate testing, this program shall be in accordance with the guidelines contained in NEI 94-01, Revision 3-A, "Industry Guideline for Implementing Performance-Based Option of 10 CFR Part 50, Appendix J," dated July 2012. Consistent with standard scheduling practices for Technical Specifications required surveillances, intervals for the recommended surveillance frequency for Type A testing may be extended by up to 25 percent of the test interval, not to exceed 15 months. The calculated peak containment internal pressure for the design basis loss of coolant accident, Pa, is 12.1 psig.
(continued)
GRAND GULF 5.0-16 Amendment No. 157, 164, 191, 205, 209, 214, 219
Attachment 2 to Enclosure GNRO-2020/00015 Retyped Technical Specification Pages TS Page 3.6-53 5.0-16
Drywell 3.6.5.1 SURVEILLANCE REQUIREMENTS SURVEILLANCE FREQUENCY SR 3.6.5.1.1 Verify bypass leakage is less than or equal to the 24 months following bypass leakage limit. two consecutive tests with bypass leakage However, during the first unit startup following greater than the drywell bypass leak rate testing performed in bypass leakage limit accordance with this SR, the acceptance criterion until two consecutive is leakage < 10% of the bypass leakage limit. tests are less than or equal to the bypass leakage limit AND 48 months following a test with bypass leakage greater than the bypass leakage limit AND
NOTE--------
SR 3.0.2 is not applicable for extensions
> 12 months.
In accordance with the Surveillance Frequency Control Program except next drywell bypass leak rate test performed after the October 19, 2008 test shall be performed no later than plant restart after the End of Cycle 23 Refueling Outage (continued)
GRAND GULF 3.6-53 Amendment No. 126*, 164, 209, 214, 219, 224
- With Correction Letter of 9/16/96
Programs and Manuals 5.5 5.5 Programs and Manuals (continued) 5.5.11 Technical Specifications (TS) Bases Control Program This program provides a means for processing changes to the Bases of these Technical Specifications.
- a. Changes to the Bases of the TS shall be made under appropriate administrative controls and reviews.
- b. Licensees may make changes to Bases without prior NRC approval provided the changes do not require either of the following:
- 1. A change in the TS incorporated in the license; or
- 2. A change to the updated FSAR or Bases that requires NRC approval pursuant to 10 CFR 50.59.
- c. The Bases Control Program shall contain provisions to ensure that the Bases are maintained consistent with the UFSAR.
- d. Proposed changes that do not meet the criteria of either Specification 5.5.11.b.1 or Specification 5.5.11.b.2 above shall be reviewed and approved by the NRC prior to implementation. Changes to the Bases implemented without prior NRC approval shall be provided to the NRC on a frequency consistent with 10 CFR 50.71(e).
5.5.12 10 CFR 50, Appendix J, Testing Program This program establishes the leakage rate testing program of the containment as required by 10 CFR 50.54(o) and 10 CFR 50, Appendix J, Option B, as modified by approved exemptions. This program shall be implemented in accordance with the Safety Evaluation issued by the Office of Nuclear Reactor Regulation dated April 26, 1995 (GNRI-95/00087) as modified by the Safety Evaluation issued for Amendment No. 135 to the Operating License, except that the next Type A test performed after the October 19, 2008 Type A test shall be performed no later than the plant restart after the End of Cycle 23 Refueling Outage. For Type B and Type C local leakage rate testing, this program shall be in accordance with the guidelines contained in NEI 94-01, Revision 3-A, "Industry Guideline for Implementing Performance-Based Option of 10 CFR Part 50, Appendix J," dated July 2012. Consistent with standard scheduling practices for Technical Specifications required surveillances, intervals for the recommended surveillance frequency for Type A testing may be extended by up to 25 percent of the test interval, not to exceed 15 months. The calculated peak containment internal pressure for the design basis loss of coolant accident, Pa, is 12.1 psig.
(continued)
GRAND GULF 5.0-16 Amendment No. 157, 164, 191, 205, 209, 214, 219, 224