ML13199A255: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
 
(Created page by program invented by StriderTol)
 
(3 intermediate revisions by the same user not shown)
Line 9: Line 9:
| docket = PROJ0753
| docket = PROJ0753
| license number =  
| license number =  
| contact person = Honcharik M C
| contact person = Honcharik M
| package number = ML13199A403
| package number = ML13199A403
| document type = Meeting Briefing Package/Handouts, Status Report
| document type = Meeting Briefing Package/Handouts, Status Report
Line 16: Line 16:


=Text=
=Text=
{{#Wiki_filter:DescriptionCLIIP Candidate?TSTF NumberApplicabilityFee Exempt?Active Travelers Status ReportExtend PCIV Completion Times (NEDC-33046)TSTF-454, Rev. 2BWRs      Actions and ScheduleResponsibility DateNot Exempt (BWROG)NoStatus: GreenTSTF-454, Rev. 2, submitted to NRC on 2/22/2012.CompletedTSTFNRC provided the acceptance and schedule letter on June 13, 2012. The proposed schedule is:Requests for Additional Information (RAIs)     August 20, 2012RAI Response from TSTF                             November 19, 2012Issue Notice for Comment                             April 29, 2013Issue Notice of Availability                           August 26, 2013CompletedNRCThe NRC issued RAIs on October 19, 2012.CompletedNRCThe RAIs reopen the approved Topical Report that is the basis of the Traveler and requests that portions of the Topical Report justification be updated to the current standards. The BWROG is working on a response, but it will take time to complete.9/30/2013TSTFGeneric Letter 2008-01, Managing Gas AccumulationTSTF-523, Rev. 2All      Actions and ScheduleResponsibility DateExemptYesStatus: GreenTSTF-523, Rev. 0 submitted on June 29, 2010.CompletedTSTFNRC provided the acceptance and schedule letter on March 2, 2011.CompletedNRCTSTF-523, Rev. 1, submitted on 3/29/12.CompletedTSTFNRC provided acceptance and schedule letter along with RAIs on June 13, 2012. The proposed schedule is: RAIs issued               June 22, 2012 RAI response             September 21, 2012 Notice for Comment   February 8, 2013 Notice of Availability   May 29, 2013CompletedNRCNRC provided RAIs. TSTF responded on August 30, 2012.CompletedTSTFAt the January 17, 2013 TSTF/NRC meeting, the TSTF agreed to revise the proposed TSTF-523 Bases to clarify the intent of the use of a dedicated individual to close vent valves during performance of the Surveillance. TSTF submitted Revision 2 to the NRC on February 21, 2013.CompletedTSTFNRC to issue the Notice for Comment.7/17/2013NRCPage 1 of  418-Jul-13Green status:   Expected to be successfully completed by the scheduled date.Yellow status: At risk of not to being successfully completed by the scheduled date.
{{#Wiki_filter:Active Travelers Status Report TSTF                                                      CLIIP Number        Applicability          Fee Exempt? Candidate?             Description TSTF-454, Rev. 2      BWRs              Not Exempt           No    Extend PCIV Completion Times (NEDC-33046)
Red status:     Unlikely to be successfully completed by the scheduled date.
(BWROG)
DescriptionCLIIP Candidate?TSTF NumberApplicabilityFee Exempt?Active Travelers Status ReportClarify Use and Application RulesTSTF-529, Rev. 1All       Actions and ScheduleResponsibility DateNot Exempt (Shared)YesStatus: GreenTSTF-529, Rev. 0, submitted on 9/19/11.CompletedTSTFThe TSTF and NRC held a workshop to discuss the changes in TSTF-529 on 10/16/12.CompletedNRCTSTFTSTF submitted TSTF-529, Rev. 1 on 2/28/13.CompletedTSTFNRC provided acceptance and schedule letter on 6/20/2013. Scheduled actions:RAIs     8/1/2013RAI Response 11/1/2013Notice for Comment   4/3/2014Notice of Availability 8/7/2014CompletedNRCNRC to provide RAIs.8/1/2013NRCRevision of Specification 3.8.1, Required Actions B.3.1 and B.3.2TSTF-531, Rev. 0All      Actions and ScheduleResponsibility DateNot Exempt (Shared)YesStatus: GreenTSTF-531, Rev. 0, submitted to NRC on March 29, 2012.CompletedTSTFNRC provided acceptance and schedule letter on 7/13/2012. Proposed schedule:RAIs by August 22, 2012RAI response by November 20, 2012Notice for Comment by April 22, 2013 Notice of Availability by August 23, 2013CompletedNRCNRC provided RAIs on October 19, 2012.CompletedNRCThe TSTF responded to the RAIs on May 22, 2013.CompletedTSTFNRC to issue the Notice for Comment.11/17/2013NRCPage 2 of  418-Jul-13Green status:   Expected to be successfully completed by the scheduled date.Yellow status: At risk of not to being successfully completed by the scheduled date.
Status: Green                              Actions and Schedule                                Responsibility        Date TSTF-454, Rev. 2, submitted to NRC on 2/22/2012.                               TSTF              Completed NRC provided the acceptance and schedule letter on June 13, 2012. The         NRC                Completed proposed schedule is:
Red status:     Unlikely to be successfully completed by the scheduled date.
Requests for Additional Information (RAIs) August 20, 2012 RAI Response from TSTF                       November 19, 2012 Issue Notice for Comment                     April 29, 2013 Issue Notice of Availability                   August 26, 2013 The NRC issued RAIs on October 19, 2012.                                       NRC                Completed The RAIs reopen the approved Topical Report that is the basis of the           TSTF                9/30/2013 Traveler and requests that portions of the Topical Report justification be updated to the current standards. The BWROG is working on a response, but it will take time to complete.
DescriptionCLIIP Candidate?TSTF NumberApplicabilityFee Exempt?Active Travelers Status ReportClarify Application of Pressure Boundary Leakage DefinitionTSTF-534, Rev. 0All       Actions and ScheduleResponsibility DateNot Exempt (Shared)YesStatus: GreenTSTF-534, Rev. 0, submitted September 19, 2011.CompletedTSTFNRC sent letter on June 6, 2012 not accepting the Traveler with an opportunity to resubmit.CompletedNRCTSTF responded to nonacceptance letter on September 4, 2012 and withdrew Revision 0 from NRC review.CompletedTSTFNRC to respond to positions in supplement letter.7/31/2013NRCResolve CE Digital TS Inconsistencies Regarding CPCs and CEACsTSTF-536, Rev. 0CE    Actions and ScheduleResponsibility DateNot Exempt (PWROG)YesStatus: GreenTSTF-536, Rev. 0 submitted on 6/18/13.CompletedTSTFNRC to issue acceptance and schedule letter.9/20/2013NRCIncrease CIV Completion Time; Update of TSTF-373TSTF-537, Rev. 0CE    Actions and ScheduleResponsibility DateNot Exempt (PWROG)YesStatus: GreenTSTF-537 was submitted to the NRC on 3/27/12.CompletedTSTFNRC issued acceptance and schedule letter on October 19.RAIs are scheduled to be provided by November 30, 2012. RAI responses are scheduled to be due February 28, 2013.Notice for Comment is scheduled to be issued on June 28, 2013Notice of Availability is scheduled to be issued on September 30, 2013CompletedNRCNRC issued RAI on March 4, 2013. The RAI requests verification that the information in the supporting Topical Report (CE NPSD-1168), which was approved in December, 2000, is still valid.CompletedNRCTSTF to respond to RAIs.9/30/2013TSTFAdd Actions to Preclude Entry into LCO 3.0.3 - RITSTF Initiatives 6b & 6cTSTF-538, Rev. 0B&W    Actions and ScheduleResponsibility DateExemption Requested YesStatus: RedTSTF-538 submitted to NRC on 3/27/12.CompletedTSTF NRC preparing non-acceptance letter that discusses the information needed to review the Traveler.8/30/2013NRCPage 3 of  418-Jul-13Green status:   Expected to be successfully completed by the scheduled date.Yellow status: At risk of not to being successfully completed by the scheduled date.
TSTF-523, Rev. 2      All              Exempt              Yes    Generic Letter 2008-01, Managing Gas Accumulation Status: Green                              Actions and Schedule                                Responsibility        Date TSTF-523, Rev. 0 submitted on June 29, 2010.                                   TSTF              Completed NRC provided the acceptance and schedule letter on March 2, 2011.             NRC                Completed TSTF-523, Rev. 1, submitted on 3/29/12.                                       TSTF              Completed NRC provided acceptance and schedule letter along with RAIs on June 13,       NRC                Completed 2012. The proposed schedule is:
Red status:     Unlikely to be successfully completed by the scheduled date.
RAIs issued             June 22, 2012 RAI response             September 21, 2012 Notice for Comment February 8, 2013 Notice of Availability May 29, 2013 NRC provided RAIs. TSTF responded on August 30, 2012.                         TSTF              Completed At the January 17, 2013 TSTF/NRC meeting, the TSTF agreed to revise the       TSTF              Completed proposed TSTF-523 Bases to clarify the intent of the use of a dedicated individual to close vent valves during performance of the Surveillance.
DescriptionCLIIP Candidate?TSTF NumberApplicabilityFee Exempt?Active Travelers Status ReportProvide Completion Times in Lieu of Immediate Shutdown (RITSTF Initiative 6)TSTF-540, Rev. 0BWRs      Actions and ScheduleResponsibility DateExemption Requested YesStatus: RedTSTF-540 submitted on 5/16/12.CompletedTSTFNRC preparing non-acceptance letter that discusses the information needed to review the Traveler.8/30/2013NRCActive Travelers:9Page 4 of  418-Jul-13Green status:   Expected to be successfully completed by the scheduled date.Yellow status: At risk of not to being successfully completed by the scheduled date.
TSTF submitted Revision 2 to the NRC on February 21, 2013.
Red status:     Unlikely to be successfully completed by the scheduled date.}}
NRC to issue the Notice for Comment.                                           NRC                  7/17/2013 Green status: Expected to be successfully completed by the scheduled date.
Yellow status: At risk of not to being successfully completed by the scheduled date.
Red status:   Unlikely to be successfully completed by the scheduled date.
Page 1 of 4                                                  18-Jul-13
 
Active Travelers Status Report TSTF                                                      CLIIP Number        Applicability          Fee Exempt? Candidate?             Description TSTF-529, Rev. 1       All              Not Exempt          Yes    Clarify Use and Application Rules (Shared)
Status: Green                              Actions and Schedule                                  Responsibility          Date TSTF-529, Rev. 0, submitted on 9/19/11.                                           TSTF                Completed The TSTF and NRC held a workshop to discuss the changes in TSTF-529 on           NRC                Completed 10/16/12.                                                                         TSTF TSTF submitted TSTF-529, Rev. 1 on 2/28/13.                                       TSTF                Completed NRC provided acceptance and schedule letter on 6/20/2013. Scheduled               NRC                Completed actions:
RAIs 8/1/2013 RAI Response 11/1/2013 Notice for Comment 4/3/2014 Notice of Availability 8/7/2014 NRC to provide RAIs.                                                             NRC                    8/1/2013 TSTF-531, Rev. 0      All              Not Exempt          Yes    Revision of Specification 3.8.1, Required Actions B.3.1 and (Shared)                    B.3.2 Status: Green                              Actions and Schedule                                  Responsibility          Date TSTF-531, Rev. 0, submitted to NRC on March 29, 2012.                             TSTF                Completed NRC provided acceptance and schedule letter on 7/13/2012. Proposed               NRC                Completed schedule:
RAIs by August 22, 2012 RAI response by November 20, 2012 Notice for Comment by April 22, 2013 Notice of Availability by August 23, 2013 NRC provided RAIs on October 19, 2012.                                           NRC                  Completed The TSTF responded to the RAIs on May 22, 2013.                                   TSTF                Completed NRC to issue the Notice for Comment.                                             NRC                11/17/2013 Green status: Expected to be successfully completed by the scheduled date.
Yellow status: At risk of not to being successfully completed by the scheduled date.
Red status:   Unlikely to be successfully completed by the scheduled date.
Page 2 of 4                                                    18-Jul-13
 
Active Travelers Status Report TSTF                                                      CLIIP Number        Applicability          Fee Exempt? Candidate?             Description TSTF-534, Rev. 0       All              Not Exempt           Yes    Clarify Application of Pressure Boundary Leakage Definition (Shared)
Status: Green                              Actions and Schedule                                  Responsibility      Date TSTF-534, Rev. 0, submitted September 19, 2011.                                 TSTF              Completed NRC sent letter on June 6, 2012 not accepting the Traveler with an               NRC                Completed opportunity to resubmit.
TSTF responded to nonacceptance letter on September 4, 2012 and                 TSTF              Completed withdrew Revision 0 from NRC review.
NRC to respond to positions in supplement letter.                               NRC                7/31/2013 TSTF-536, Rev. 0      CE              Not Exempt          Yes    Resolve CE Digital TS Inconsistencies Regarding CPCs and (PWROG)                     CEACs Status: Green                              Actions and Schedule                                  Responsibility      Date TSTF-536, Rev. 0 submitted on 6/18/13.                                           TSTF              Completed NRC to issue acceptance and schedule letter.                                     NRC                9/20/2013 TSTF-537, Rev. 0      CE              Not Exempt          Yes    Increase CIV Completion Time; Update of TSTF-373 (PWROG)
Status: Green                              Actions and Schedule                                  Responsibility      Date TSTF-537 was submitted to the NRC on 3/27/12.                                   TSTF              Completed NRC issued acceptance and schedule letter on October 19.                         NRC                Completed RAIs are scheduled to be provided by November 30, 2012.
RAI responses are scheduled to be due February 28, 2013.
Notice for Comment is scheduled to be issued on June 28, 2013 Notice of Availability is scheduled to be issued on September 30, 2013 NRC issued RAI on March 4, 2013. The RAI requests verification that the         NRC                Completed information in the supporting Topical Report (CE NPSD-1168), which was approved in December, 2000, is still valid.
TSTF to respond to RAIs.                                                         TSTF                9/30/2013 TSTF-538, Rev. 0      B&W              Exemption            Yes    Add Actions to Preclude Entry into LCO 3.0.3 - RITSTF Requested                  Initiatives 6b & 6c Status: Red                                Actions and Schedule                                  Responsibility      Date TSTF-538 submitted to NRC on 3/27/12.                                           TSTF              Completed NRC preparing non-acceptance letter that discusses the information needed       NRC                8/30/2013 to review the Traveler.
Green status: Expected to be successfully completed by the scheduled date.
Yellow status: At risk of not to being successfully completed by the scheduled date.
Red status:   Unlikely to be successfully completed by the scheduled date.
Page 3 of 4                                                  18-Jul-13
 
Active Travelers Status Report TSTF                                                      CLIIP Number        Applicability          Fee Exempt? Candidate?             Description TSTF-540, Rev. 0      BWRs            Exemption            Yes    Provide Completion Times in Lieu of Immediate Shutdown Requested                  (RITSTF Initiative 6)
Status: Red                                Actions and Schedule                                Responsibility        Date TSTF-540 submitted on 5/16/12.                                                 TSTF                Completed NRC preparing non-acceptance letter that discusses the information needed     NRC                  8/30/2013 to review the Traveler.
Active Travelers: 9 Green status: Expected to be successfully completed by the scheduled date.
Yellow status: At risk of not to being successfully completed by the scheduled date.
Red status:   Unlikely to be successfully completed by the scheduled date.
Page 4 of 4                                                  18-Jul-13}}

Latest revision as of 16:51, 4 November 2019

TSTF Handout from July 18, 2013, Meeting - Active Travelers Status Report
ML13199A255
Person / Time
Site: Technical Specifications Task Force
Issue date: 07/18/2013
From:
Licensing Processes Branch (DPR)
To:
Honcharik M
Shared Package
ML13199A403 List:
References
Download: ML13199A255 (4)


Text

Active Travelers Status Report TSTF CLIIP Number Applicability Fee Exempt? Candidate? Description TSTF-454, Rev. 2 BWRs Not Exempt No Extend PCIV Completion Times (NEDC-33046)

(BWROG)

Status: Green Actions and Schedule Responsibility Date TSTF-454, Rev. 2, submitted to NRC on 2/22/2012. TSTF Completed NRC provided the acceptance and schedule letter on June 13, 2012. The NRC Completed proposed schedule is:

Requests for Additional Information (RAIs) August 20, 2012 RAI Response from TSTF November 19, 2012 Issue Notice for Comment April 29, 2013 Issue Notice of Availability August 26, 2013 The NRC issued RAIs on October 19, 2012. NRC Completed The RAIs reopen the approved Topical Report that is the basis of the TSTF 9/30/2013 Traveler and requests that portions of the Topical Report justification be updated to the current standards. The BWROG is working on a response, but it will take time to complete.

TSTF-523, Rev. 2 All Exempt Yes Generic Letter 2008-01, Managing Gas Accumulation Status: Green Actions and Schedule Responsibility Date TSTF-523, Rev. 0 submitted on June 29, 2010. TSTF Completed NRC provided the acceptance and schedule letter on March 2, 2011. NRC Completed TSTF-523, Rev. 1, submitted on 3/29/12. TSTF Completed NRC provided acceptance and schedule letter along with RAIs on June 13, NRC Completed 2012. The proposed schedule is:

RAIs issued June 22, 2012 RAI response September 21, 2012 Notice for Comment February 8, 2013 Notice of Availability May 29, 2013 NRC provided RAIs. TSTF responded on August 30, 2012. TSTF Completed At the January 17, 2013 TSTF/NRC meeting, the TSTF agreed to revise the TSTF Completed proposed TSTF-523 Bases to clarify the intent of the use of a dedicated individual to close vent valves during performance of the Surveillance.

TSTF submitted Revision 2 to the NRC on February 21, 2013.

NRC to issue the Notice for Comment. NRC 7/17/2013 Green status: Expected to be successfully completed by the scheduled date.

Yellow status: At risk of not to being successfully completed by the scheduled date.

Red status: Unlikely to be successfully completed by the scheduled date.

Page 1 of 4 18-Jul-13

Active Travelers Status Report TSTF CLIIP Number Applicability Fee Exempt? Candidate? Description TSTF-529, Rev. 1 All Not Exempt Yes Clarify Use and Application Rules (Shared)

Status: Green Actions and Schedule Responsibility Date TSTF-529, Rev. 0, submitted on 9/19/11. TSTF Completed The TSTF and NRC held a workshop to discuss the changes in TSTF-529 on NRC Completed 10/16/12. TSTF TSTF submitted TSTF-529, Rev. 1 on 2/28/13. TSTF Completed NRC provided acceptance and schedule letter on 6/20/2013. Scheduled NRC Completed actions:

RAIs 8/1/2013 RAI Response 11/1/2013 Notice for Comment 4/3/2014 Notice of Availability 8/7/2014 NRC to provide RAIs. NRC 8/1/2013 TSTF-531, Rev. 0 All Not Exempt Yes Revision of Specification 3.8.1, Required Actions B.3.1 and (Shared) B.3.2 Status: Green Actions and Schedule Responsibility Date TSTF-531, Rev. 0, submitted to NRC on March 29, 2012. TSTF Completed NRC provided acceptance and schedule letter on 7/13/2012. Proposed NRC Completed schedule:

RAIs by August 22, 2012 RAI response by November 20, 2012 Notice for Comment by April 22, 2013 Notice of Availability by August 23, 2013 NRC provided RAIs on October 19, 2012. NRC Completed The TSTF responded to the RAIs on May 22, 2013. TSTF Completed NRC to issue the Notice for Comment. NRC 11/17/2013 Green status: Expected to be successfully completed by the scheduled date.

Yellow status: At risk of not to being successfully completed by the scheduled date.

Red status: Unlikely to be successfully completed by the scheduled date.

Page 2 of 4 18-Jul-13

Active Travelers Status Report TSTF CLIIP Number Applicability Fee Exempt? Candidate? Description TSTF-534, Rev. 0 All Not Exempt Yes Clarify Application of Pressure Boundary Leakage Definition (Shared)

Status: Green Actions and Schedule Responsibility Date TSTF-534, Rev. 0, submitted September 19, 2011. TSTF Completed NRC sent letter on June 6, 2012 not accepting the Traveler with an NRC Completed opportunity to resubmit.

TSTF responded to nonacceptance letter on September 4, 2012 and TSTF Completed withdrew Revision 0 from NRC review.

NRC to respond to positions in supplement letter. NRC 7/31/2013 TSTF-536, Rev. 0 CE Not Exempt Yes Resolve CE Digital TS Inconsistencies Regarding CPCs and (PWROG) CEACs Status: Green Actions and Schedule Responsibility Date TSTF-536, Rev. 0 submitted on 6/18/13. TSTF Completed NRC to issue acceptance and schedule letter. NRC 9/20/2013 TSTF-537, Rev. 0 CE Not Exempt Yes Increase CIV Completion Time; Update of TSTF-373 (PWROG)

Status: Green Actions and Schedule Responsibility Date TSTF-537 was submitted to the NRC on 3/27/12. TSTF Completed NRC issued acceptance and schedule letter on October 19. NRC Completed RAIs are scheduled to be provided by November 30, 2012.

RAI responses are scheduled to be due February 28, 2013.

Notice for Comment is scheduled to be issued on June 28, 2013 Notice of Availability is scheduled to be issued on September 30, 2013 NRC issued RAI on March 4, 2013. The RAI requests verification that the NRC Completed information in the supporting Topical Report (CE NPSD-1168), which was approved in December, 2000, is still valid.

TSTF to respond to RAIs. TSTF 9/30/2013 TSTF-538, Rev. 0 B&W Exemption Yes Add Actions to Preclude Entry into LCO 3.0.3 - RITSTF Requested Initiatives 6b & 6c Status: Red Actions and Schedule Responsibility Date TSTF-538 submitted to NRC on 3/27/12. TSTF Completed NRC preparing non-acceptance letter that discusses the information needed NRC 8/30/2013 to review the Traveler.

Green status: Expected to be successfully completed by the scheduled date.

Yellow status: At risk of not to being successfully completed by the scheduled date.

Red status: Unlikely to be successfully completed by the scheduled date.

Page 3 of 4 18-Jul-13

Active Travelers Status Report TSTF CLIIP Number Applicability Fee Exempt? Candidate? Description TSTF-540, Rev. 0 BWRs Exemption Yes Provide Completion Times in Lieu of Immediate Shutdown Requested (RITSTF Initiative 6)

Status: Red Actions and Schedule Responsibility Date TSTF-540 submitted on 5/16/12. TSTF Completed NRC preparing non-acceptance letter that discusses the information needed NRC 8/30/2013 to review the Traveler.

Active Travelers: 9 Green status: Expected to be successfully completed by the scheduled date.

Yellow status: At risk of not to being successfully completed by the scheduled date.

Red status: Unlikely to be successfully completed by the scheduled date.

Page 4 of 4 18-Jul-13