MONTHYEARTSTF-19-09, Technical Specifications Task Force - Transmittal of TSTF-576, Revision 0, Revise Safety/Relief Valve Requirements2019-12-13013 December 2019 Technical Specifications Task Force - Transmittal of TSTF-576, Revision 0, Revise Safety/Relief Valve Requirements Project stage: Request ML20037A1292020-02-13013 February 2020 Acceptance for Review Regarding Traveler TSTF-576, Revision 0, Revise Safety/Relief Valve Requirements Project stage: Acceptance Review ML20132A1832020-05-11011 May 2020 Request for Additional Information TSTF-576, Revision 0, Revised Safety/Relief Valve Requirement Project stage: RAI ML23019A2532022-06-0808 June 2022 Draft of Revision 2 of Traveler TSTF-576, Revise Safety/Relief Valve Requirements Project stage: Draft Other ML22258A1772022-09-15015 September 2022 Comments on Draft of Revision 2 of Traveler TSTF-576, Revise Safety/Relief Valve Requirements Project stage: Draft Other ML23033A5382023-02-0202 February 2023 Forthcoming Public Teleconference Between the U. S. Nuclear Regulatory Commission and the Technical Specifications Task Force Project stage: Request ML23033A3842023-02-0202 February 2023 February 9, 2023, Meeting Handout: NRC Staff Comments on TSTF-576 Revision 2 (Draft), SRV Requirements ML23059A3342023-02-28028 February 2023 TSTF-576 Open Issues Letter Project stage: Other ML23157A2062023-07-0505 July 2023 Acceptance for Review and Revised Schedule Regarding Traveler TSTF-576, Revise Safety/Relief Valve Requirements Project stage: Acceptance Review ML24204A2712024-08-0101 August 2024 TSTF-576 Safety Evaluation Supplement Project stage: Approval ML24249A1452024-09-11011 September 2024 Final Traveler SE of TSTF 576, Revision 3, Revise Safety/Relief Valve Requirements Project stage: Other ML24249A1482024-09-11011 September 2024 Cover Letter for Final Traveler SE of TSTF 576, Revision 3, Revise Safety/Relief Valve Requirements Project stage: Other 2022-09-15
[Table View] |
|
---|
Category:Meeting Briefing Package/Handouts
MONTHYEARML24289A0342024-08-0808 August 2024 Discussion of NRC Staff Comments on Draft TSTF-585, Revision 3, Revise LCO 3.0.3 to Require Managing Risk ML24129A0662024-05-0808 May 2024 5_8_24 Meeting Handouts - History of Traveler Adoption ML24129A0652024-05-0808 May 2024 5_8_24 Meeting Handouts - Active Traveler Summary Report and Priorities ML24129A0672024-05-0808 May 2024 5_8_24 Meeting Handouts - Proposed Change to the PWR ECCS Mode 4 Requirements ML24044A1402024-02-0808 February 2024 TSTF Handout for 02/08/2024 Quarterly Meeting ML24038A3492024-02-0707 February 2024 NRC Comments for Pre-submittal Meeting TSTF-600, Revise the Reactor Coolant System (RCS) Pressure Isolation Valve (PIV) Leakage Testing Frequency ML23257A1582023-09-18018 September 2023 NRC Staff Feedback Draft TSTF-601, Extend Shield Building Completion Time After Refueling for Pre-submittal Meeting on 9/18/23 ML23033A3842023-02-0202 February 2023 February 9, 2023, Meeting Handout: NRC Staff Comments on TSTF-576 Revision 2 (Draft), SRV Requirements ML22298A2162022-10-25025 October 2022 TSTF Meeting Handout TSTF-585 and the Maintenance Rule ML22298A2172022-10-24024 October 2022 TSTF Meeting Handout Strategic Improvements to TS and TS-Related Processes ML22298A2152022-10-20020 October 2022 TSTF Meeting Handout Natural Phenomena and Operability Workshop ML22056A2932022-02-24024 February 2022 2/24/2022 Meeting Handout - Active Traveler Summary Report ML22056A2942022-02-24024 February 2022 2/24/2022 Meeting Handout - TSTF 2021 in Review ML22038A6032022-02-10010 February 2022 Summary of January 10, 2022, Meeting with the Technical Specifications Task Force Draft Traveler TSTF-589 Eliminate Automatic Diesel Generator Start During Shutdown ML22013B1422022-02-0101 February 2022 TSTF-576 Workshop February 2022 - NRC Presentation ML21217A0692021-08-0505 August 2021 Meeting Handout - Active Traveler Summary Report ML21158A0902021-06-0707 June 2021 Technical Specifications Branch Feedback/Comments on Draft TSTF-585, Revise LCO 3.0.3 ML21126A0712021-05-0606 May 2021 5/6/2021 Meeting Handout - Interaction of Technical Specification Surveillances and 10 CFR 50.69 ML21126A0732021-05-0606 May 2021 5/6/2021 Meeting Handout - Active Traveler Summary Report ML21126A0722021-05-0606 May 2021 5/6/2021 Meeting Handout - Expected TSTF-577 Submittals ML21029A3082021-01-29029 January 2021 Trio Public Meeting Slides (Thursday, February 4, 2021) ML21007A1112021-01-0707 January 2021 TSTF-577, NRC Staff Slides from Public Meeting on 1_7_2021 ML20329A3412020-11-24024 November 2020 TSTF-576 Example Scenarios for 12/7/2020 Meeting ML20287A2632020-10-13013 October 2020 TSTF Presentation Proposal to Improve the Core Operating Limits Report (COLR) ML20125A0922020-05-0404 May 2020 May 4, 2020, Pre-submittal Meeting Handout Staff Comments Draft TSTF-577, Revised Frequencies for Steam Generator Tube Inspections ML20065J9322020-03-0505 March 2020 March 5 2020 Meeting Handout, Agenda Item VA - Proposal to Revise LCO 3.0.3 ML20069F2882020-03-0505 March 2020 March 5 2020 TSTF Quarterly Meeting Handout, Agenda Item Iia - 2019 in Review ML20065J9902020-03-0505 March 2020 March 5 2020 TSTF Quarterly Meeting Handout, Agenda Item Iiib - Generic RAIs for LARs to Adopt TSTF-505 Rict ML20065J9332020-03-0505 March 2020 March 5 2020 Meeting Handout, Agenda Item IV - Active Traveler Summary Report and Priorities ML20065J9342020-03-0505 March 2020 March 5 2020 Meeting Handout, Agenda Item Iia - 2019 in Review ML20069F2852020-01-0101 January 2020 March 5 2020 TSTF Quarterly Meeting Handout, Agenda Item Via - TSTF Charter Statement 2020 ML19267A1592019-09-24024 September 2019 TSTF Handout for October 16, 2019, Meeting: TSTF-493 Questions ML19259A2082019-09-12012 September 2019 TSTF Presentation from TSTF-576, S/Rv Requirements Pre-submittal Meeting on September 12, 2019 TSTF-19-07, TSTF Handout for October 16, 2019, Meeting: Elimination of Commitment to Adopt TSTF-4932019-06-18018 June 2019 TSTF Handout for October 16, 2019, Meeting: Elimination of Commitment to Adopt TSTF-493 ML19056A4232019-02-21021 February 2019 Meeting Attendees 02/21/2019 ML19056A4242019-02-21021 February 2019 TSTF-568 Proposed Path Forward from 2/21/2019 Meeting ML19056A4262019-02-21021 February 2019 Rewording of TSTF Revision to TSTF-541, Add Exceptions to Surveillance Requirements When the Safety Function Is Being Performed ML18312A3662018-11-0808 November 2018 Handout from 11/8/2018 TSTF Meeting for Agenda Items V.A and V.B Active Traveler Summary Report and Traveler Review Priorities ML18312A3672018-11-0808 November 2018 Handout from 11/08/2018 TSTF Meeting for Agenda Item Ii.B.C November 2018 Traveler Review Schedule Changes ML18221A5712018-08-0909 August 2018 August 9, 2018, Meeting Agenda Item 4.A TSTF Response TSTF-51 -286 -471 ML18221A5722018-08-0909 August 2018 August 9, 2018, Meeting Agenda Item 3.A - DNP LAR Analysis ML18221A5742018-08-0909 August 2018 August 9, 2018, Meeting Agenda Item 5.A.6 - TSTF-565R1 ML18221A5752018-08-0909 August 2018 August 9, 2018, Meeting Agenda Item 5.A Active Traveler Summary Report ML18221A5772018-08-0909 August 2018 August 9, 2018, Meeting Agenda Item 4.C - TSTF-542 Adoption Status ML18221A5812018-08-0909 August 2018 August 9, 2018, Meeting Agenda Item 5.A.6 NRC Feedback Re TSTF-568 Evaluation of STS 3.6.3.2 ML18221A5732018-08-0606 August 2018 August 9, 2018, Meeting Agenda Item 7.A - Is the Table of Contents Part of the Technical Specifications? ML18142B0372018-05-17017 May 2018 May 17, 2018, Meeting Agenda Item 2.A - TSTF-563 Coordinated Submittal Pilot ML18142B0352018-05-17017 May 2018 May 17, 2018, Meeting Agenda Item 4.B - TSTF-547 Issue ML18142B0312018-05-17017 May 2018 May 17, 2018, Meeting Agenda Item 8.A - T Traveler Candidates ML18142B0332018-05-17017 May 2018 May 17, 2018, Meeting Agenda Item 8.A - Approved Unincorporated Travelers 2024-08-08
[Table view] |
Text
TSTF-576, Revision 2 (draft), Revise Safety/Relief Valve Requirements (ADAMS Accession No. ML23019A253)
NRC staff feedback to the Technical Specifications Task Force (TSTF) for meeting on February 9, 2023
Background:
Some Boiling Water Reactor plants experience safety/relief valves (SRVs) lifting outside the technical specification (TS) allowable tolerances during post-cycle testing. When this occurs, licensees are required to submit licensee event reports (LERs) (>40 LERs over the past 10 years). These evaluations consistently demonstrate that the specified safety function relating to reactor coolant system overpressure protection was maintained, despite exceeding the tolerances allowed in the relevant surveillance requirement (SR). Industry and the NRC staff have been working to develop a resolution for the issue since late 2019.
Current TSTF Proposal: The TSTF is proposing to change the existing SR in the TS for the SRVs and:
- limit the scope to confirming the as-left setpoints are within acceptable tolerance
- move the SRV as-found lift pressure acceptance criteria from TS to a licensee-controlled document and evaluate performance at a system level Summary of Technical Issue: The existing SR in TS specifies acceptance criteria for the as-found condition of the valves at +/-3% over their setpoints. This supports meeting the limiting condition for operation (LCO) for reactor coolant system (RCS) overpressure and was also determined by staff to ensure that assumptions and inputs for any secondary analyses (containment integrity, etc.) are bounded.
Questions for the TSTF:
In general, demonstrating that the RCS overpressure LCO is met using a system-based approach may be acceptable. However, NRC staff needs to clearly understand the relationship between the new system-based acceptance criteria and other parts of the licensing bases. The following questions will help provide context:
- 1. Are the proposed acceptance criteria for as-found lift pressures also relied on to demonstrate that secondary requirements are met? If so, how was that conclusion reached (similar to the analyses done for the earlier 1% to 3% change)?
- 2. If not, how will licensees determine that other licensing and design basis requirements dependent on as-found valve lift pressure are met? Most of these requirements are at a system level, but SRV discharge line dynamic loading may need to be considered at the SRV-specific level.