| issue date = 09/19/2013
| issue date = 09/19/2013
| title = Enclosure 3- NRC Presentation Handout
| title = Enclosure 3- NRC Presentation Handout
| author name = Watson B A
| author name = Watson B
| author affiliation = NRC/FSME/DWMEP/DURLD/RDB
| author affiliation = NRC/FSME/DWMEP/DURLD/RDB
| addressee name =  
| addressee name =  
Line 16: Line 16:


=Text=
=Text=
{{#Wiki_filter:Three Mile Island -2 Post Shut Down Activities Report Public Meeting Bruce Watson, CHPChief, Reactor Decommissioning BranchU.S. Nuclear Regulatory Commission, Washington, D.C. 20555 1
{{#Wiki_filter:Three Mile Island - 2 Post Shut Down Activities Report Public Meeting Bruce Watson, CHP Chief, Reactor Decommissioning Branch U.S. Nuclear Regulatory Commission, Washington, D.C. 20555 1
US NRC Decommissioned Facilities 10126802401998199920002001200220032004200520062007200820092010201120122013Power Reactors 2Research ReactorsMaterials Sites Agenda*Discuss the NRC Decommissioning ProcessProcess*Discuss the TMI-2 Post Shutdown Decommissioning Activities Report (PSDAR)*Discuss the NRC Inspection Process*Hear public comments on PSDAR p3 Three Mile Island, Unit 2 PtShtdPost-Shutdown Decommissioning Activities Report John Buckley ReactorDecommissioningBranch Reactor Decommissioning BranchU.S. Nuclear Regulatory Commission, WashingtonDC20555 4Washington
 
, D.C. 20555 NRC Decommissioning Process*Permanently cease operations*Certify permanent cessation of operations*Certify fuel removed from reactor*Submit PSDAR (within 2 years)
US NRC Decommissioned Facilities 12 10 8
*SAFSTORand/orplantdecommissioning
6 4
*SAFSTOR and/or plant decommissioning*Application for license termination (LTP)Liii5*License term ination TMI-2 Decommissioning Process*The March 28, 1979, accident made the shutdownofTMI2differentfromallother shutdown of TMI-2 different from all other reactors.CSS*NRC approved PDM S SAR on September 14, 1993, with License Amendment 45.*GPU submits PSDAR on June 28, 2013, to establish compliance with 50.82.
2 0
6 PSDARRequirements PSDAR Requirements
1998199920002001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 Power Reactors Research Reactors Materials Sites 2
*10 CFR 50.82(a)(4)
 
*PSDAR describes:
Agenda
-planned decommissionin g activities pg-decommissioning schedule
* Discuss the NRC Decommissioning Process
-costestimateforthedecommissioning cost estimate for the decommissioning
* Discuss the TMI-2 Post Shutdown Decommissioning Activities Report (PSDAR)
-environmental impacts of decommissioning7decossog PSDAR Review Process*NRC notices receipt of PSDAR & requestspubliccomments requests public comments*NRC schedules PSDAR public meeting*NRC considers public comments
* Discuss the NRC Inspection Process public comments on PSDAR
*Review PSDAR in accordance with eeSaccodacet Regulatory Guide 1.185
* Hear p 3
*PSDARdoesnotrequireNRCapproval 8*PSDAR does not require NRC approval PSDAR Review Criteria*Decom can be completed as described*Decom can be completed within 60 years*Decom can be completed for the estimated cost
 
*Decom activities do not endanger public ecoacttesdootedagepubc health and safety or the environment 9
Three Mile Island, Unit 2 P t Sh td Post-Shutdown Decommissioning Activities Report John Buckley Reactor Decommissioning Branch U.S. Nuclear Regulatory Commission, Washington D Washington, D.C.
PSDAR Highlights*Decommissioning of TMI-2 will start after TMI-1 operating license expires in April 2034 TMI2illbitiditPDMSdtil
C 20555 4
*TMI-2 will be maintained in current PDMS mode until decommissioning begins
 
*TMI-2licenseterminationwilloccurbeforeSeptember TMI2 license termination will occur before September 2053 (60 years after cessation of operations)*Decommissioning costs are estimated to be $844885000(bd2008dll)
NRC Decommissioning Process
$844,885,000 (based on 2008 dollars)*Environmental impacts of planned decommissioning activitiesareboundedbyimpactsassociatedwithpost
* Permanently cease operations
-10activities are bounded by impacts associated with postaccident cleanup activities and GEIS Conclusion*NRC received a PSDAR for TMI-2 on June282013 June 28, 2013*Although NRC is not required to approve SCthe PSDAR by regulation, NR C will review the PSDAR*NRC will consider the public comments in its review of the TMI-2 PSDAR 11 ThreeMileIsland
* Certify permanent cessation of operations
-Unit2Three Mile Island -Unit 2Decommissioning Power Reactor OversightProgram Oversight ProgramPSDAR Public Meeting August 28, 2013Laurie A. Kauffman Health PhysicistDivision of Nuclear Materials Safety Region I Decommissioning Power Reactor OversightProgram Oversight Program*Decommissioning power reactor inspection program is described in Inspection Manual Chapter 2561AlItifdbRiItff
* Certify fuel removed from reactor
*Annual Inspection performed by Region I staff-Verify controls and methods for safe storage of radioactive material and structures at permanently shutdown reactors 13 TMI-2 SAFSTOR PROGRAM*No ongoing decommissioning activities *Material condition of components remain unchanged*Safe storage programs being conducted according to Technical Specifications and site procedures*NRC Inspection Reports are located in ADAMS http://wwwnrcgov/reading
* Submit PSDAR (within 2 years)
-rm/adamshtml http://www
* SAFSTOR and/or plant decommissioning
.nrc.gov/reading rm/adams.html14 NRC Contacts*John Buckley, Project Manager-John.Buckley@nrc.gov-301-415-6607
* Application for license termination (LTP)
*BruceWatson,BranchChief Bruce Watson, Branch Chief-Bruce.Watson@nrc.gov-301-415-6221*Laurie Kauffman, Inspector
* Li License termination i i 5
-Laurie.Kauffman@nrc.gov 610337532315-610-337-5323}}
 
TMI-2 Decommissioning Process
* The March 28, 1979, accident made the shutdown of TMI TMI-2 2 different from all other reactors.
* NRC C approved PDMS  SS SAR on September 14, 1993, with License Amendment 45.
* GPU submits PSDAR on June 28, 2013, to establish compliance with 50.82.
6
 
PSDAR Requirements
* 10 CFR 50.82(a)(4)
* PSDAR describes:
  - p planned decommissioning g activities
  - decommissioning schedule
  - cost estimate for the decommissioning
  - environmental impacts of decommissioning deco    ss o g 7
 
PSDAR Review Process
* NRC notices receipt of PSDAR &
requests public comments
* NRC schedules PSDAR public meeting
* NRC considers public comments
* Review e e PSDAR S      in acco accordance da ce with t
Regulatory Guide 1.185
* PSDAR does not require NRC approval 8
 
PSDAR Review Criteria
* Decom can be completed as described
* Decom can be completed within 60 years
* Decom can be completed for the estimated cost
* Decom eco actactivities t es do not ot e endanger da ge pub public c
health and safety or the environment 9
 
PSDAR Highlights
* Decommissioning of TMI-2 will start after TMI-1 operating license expires in April 2034
* TMI-2 TMI 2 willill b be maintained i t i d iin currentt PDMS mode d until til decommissioning begins
* TMI TMI-22 license termination will occur before September 2053 (60 years after cessation of operations)
* Decommissioning costs are estimated to be
  $844 885 000 (b
  $844,885,000     (basedd on 2008 ddollars) ll )
* Environmental impacts of planned decommissioning activities are bounded by impacts associated with post-post accident cleanup activities and GEIS 10
 
Conclusion
* NRC received a PSDAR for TMI-2 on June 2828, 2013
* Although NRC is not required to approve the PSDAR S      by regulation, NRC C will review the PSDAR
* NRC will consider the public comments in its review of the TMI-2 PSDAR 11
 
Three Mile Island - Unit 2 Decommissioning Power Reactor Oversight Program PSDAR Public Meeting August 28, 2013 Laurie A. Kauffman Health Physicist Division of Nuclear Materials Safety Region I
 
Decommissioning Power Reactor Oversight Program
* Decommissioning power reactor inspection program is described in Inspection Manual Chapter 2561
* Annual A      l IInspection ti performed f      d by b R Region i I staff t ff
  - Verify controls and methods for safe storage of radioactive material and structures at permanently shutdown reactors 13
 
TMI-2 SAFSTOR PROGRAM
* No ongoing decommissioning activities
* Material condition of components remain unchanged
* Safe storage programs being conducted according to Technical Specifications and site procedures
* NRC Inspection Reports are located in ADAMS http://www nrc gov/reading-rm/adams http://www.nrc.gov/reading rm/adams.html html 14
 
NRC Contacts
* John Buckley, Project Manager
  - John.Buckley@nrc.gov
  - 301-415-6607
* Bruce Watson, Branch Chief
  - Bruce.Watson@nrc.gov
  - 301-415-6221
* Laurie Kauffman, Inspector
  - Laurie.Kauffman@nrc.gov
  - 610-337-5323 610 337 5323 15}}

Latest revision as of 13:22, 4 November 2019

Enclosure 3- NRC Presentation Handout
ML13262A149
Person / Time
Site: Three Mile Island Constellation icon.png
Issue date: 09/19/2013
From: Bruce Watson
NRC/FSME/DWMEP/DURLD/RDB
To:
Shared Package
ML13262A166 List:
References
Download: ML13262A149 (15)


Text

Three Mile Island - 2 Post Shut Down Activities Report Public Meeting Bruce Watson, CHP Chief, Reactor Decommissioning Branch U.S. Nuclear Regulatory Commission, Washington, D.C. 20555 1

US NRC Decommissioned Facilities 12 10 8

6 4

2 0

1998199920002001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 Power Reactors Research Reactors Materials Sites 2

Agenda

  • Discuss the NRC Decommissioning Process
  • Discuss the TMI-2 Post Shutdown Decommissioning Activities Report (PSDAR)
  • Discuss the NRC Inspection Process public comments on PSDAR
  • Hear p 3

Three Mile Island, Unit 2 P t Sh td Post-Shutdown Decommissioning Activities Report John Buckley Reactor Decommissioning Branch U.S. Nuclear Regulatory Commission, Washington D Washington, D.C.

C 20555 4

NRC Decommissioning Process

  • Permanently cease operations
  • Certify permanent cessation of operations
  • Certify fuel removed from reactor
  • Submit PSDAR (within 2 years)
  • SAFSTOR and/or plant decommissioning
  • Application for license termination (LTP)
  • Li License termination i i 5

TMI-2 Decommissioning Process

  • The March 28, 1979, accident made the shutdown of TMI TMI-2 2 different from all other reactors.
  • NRC C approved PDMS SS SAR on September 14, 1993, with License Amendment 45.
  • GPU submits PSDAR on June 28, 2013, to establish compliance with 50.82.

6

PSDAR Requirements

- p planned decommissioning g activities

- decommissioning schedule

- cost estimate for the decommissioning

- environmental impacts of decommissioning deco ss o g 7

PSDAR Review Process

  • NRC notices receipt of PSDAR &

requests public comments

  • NRC schedules PSDAR public meeting
  • NRC considers public comments
  • Review e e PSDAR S in acco accordance da ce with t

Regulatory Guide 1.185

  • PSDAR does not require NRC approval 8

PSDAR Review Criteria

  • Decom can be completed as described
  • Decom can be completed within 60 years
  • Decom can be completed for the estimated cost
  • Decom eco actactivities t es do not ot e endanger da ge pub public c

health and safety or the environment 9

PSDAR Highlights

  • Decommissioning of TMI-2 will start after TMI-1 operating license expires in April 2034
  • TMI-2 TMI 2 willill b be maintained i t i d iin currentt PDMS mode d until til decommissioning begins
  • TMI TMI-22 license termination will occur before September 2053 (60 years after cessation of operations)
  • Decommissioning costs are estimated to be

$844 885 000 (b

$844,885,000 (basedd on 2008 ddollars) ll )

  • Environmental impacts of planned decommissioning activities are bounded by impacts associated with post-post accident cleanup activities and GEIS 10

Conclusion

  • NRC received a PSDAR for TMI-2 on June 2828, 2013
  • Although NRC is not required to approve the PSDAR S by regulation, NRC C will review the PSDAR
  • NRC will consider the public comments in its review of the TMI-2 PSDAR 11

Three Mile Island - Unit 2 Decommissioning Power Reactor Oversight Program PSDAR Public Meeting August 28, 2013 Laurie A. Kauffman Health Physicist Division of Nuclear Materials Safety Region I

Decommissioning Power Reactor Oversight Program

  • Annual A l IInspection ti performed f d by b R Region i I staff t ff

- Verify controls and methods for safe storage of radioactive material and structures at permanently shutdown reactors 13

TMI-2 SAFSTOR PROGRAM

  • No ongoing decommissioning activities
  • Material condition of components remain unchanged
  • Safe storage programs being conducted according to Technical Specifications and site procedures

NRC Contacts

  • John Buckley, Project Manager

- John.Buckley@nrc.gov

- 301-415-6607

- Bruce.Watson@nrc.gov

- 301-415-6221

- Laurie.Kauffman@nrc.gov

- 610-337-5323 610 337 5323 15