MNS-15-005, Fourth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049): Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
(Created page by program invented by StriderTol)
Line 18: Line 18:


=Text=
=Text=
{{#Wiki_filter:Steven D. Capps£r1I1 Vice President' DUKE McGuire Nuclear Station ENERGY. Duke Energy MG01VP 112700 Hagers Ferry Road Huntersville, NC 28078 o: 980.875.4805 f: 980.875.4809 Steven.Capps@duke-energy.com 10 CFR 50.4 February 26, 2015 Serial: MNS-15-005 ATTN: Document Control Desk U.S. Nuclear Regulatory Commission Washington, DC 20555 Duke Energy Carolinas, LLC (Duke Energy)McGuire Nuclear Station (MNS), Units 1 and 2 Docket Nos. 50-369 and 50-370 Renewed License Nos. NPF-9 and NPF-17  
{{#Wiki_filter:Steven D. Capps
  £r1I1     L'*                                                                                    Vice President
'       DUKE                                                                             McGuire Nuclear Station ENERGY.                                                                                     Duke Energy MG01VP   112700 Hagers Ferry Road Huntersville, NC 28078 o: 980.875.4805 f: 980.875.4809 Steven.Capps@duke-energy.com 10 CFR 50.4 February 26, 2015 Serial: MNS-15-005 ATTN: Document Control Desk U.S. Nuclear Regulatory Commission Washington, DC 20555 Duke Energy Carolinas, LLC (Duke Energy)
McGuire Nuclear Station (MNS), Units 1 and 2 Docket Nos. 50-369 and 50-370 Renewed License Nos. NPF-9 and NPF-17


==Subject:==
==Subject:==
Line 28: Line 31:
: 3. NEI 12-06, Diverse and Flexible Coping Strategies (FLEX) Implementation Guide, Revision 0-A, dated August 2012 (ADAMS Accession No. ML12242A378).
: 3. NEI 12-06, Diverse and Flexible Coping Strategies (FLEX) Implementation Guide, Revision 0-A, dated August 2012 (ADAMS Accession No. ML12242A378).
: 4. Duke Energy's Initial Status Report in Response to March 12, 2012, Commission Order Modifying Licenses with Regard To Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order EA-12-049), dated October 29, 2012 (ADAMS Accession No. ML12307A023).
: 4. Duke Energy's Initial Status Report in Response to March 12, 2012, Commission Order Modifying Licenses with Regard To Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order EA-12-049), dated October 29, 2012 (ADAMS Accession No. ML12307A023).
: 5. McGuire Nuclear Station Overall Integrated Plan in Response to March 12, 2012, Commission Order to Modify Licenses With Regard To Requirements for Mitigation Strategies for Beyond Design Basis External Events (Order EA-12-049), dated February 28, 2013 (ADAMS Accession No. ML13063A185).A 2 1 United States Nuclear Regulatory Commission
: 5. McGuire Nuclear Station Overall Integrated Plan in Response to March 12, 2012, Commission Order to Modify Licenses With Regard To Requirements for Mitigation Strategies for Beyond Design Basis External Events (Order EA-12-049),
-.February 26, 2015 Page 2 6. McGuire Nuclear Station First Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-basis External Events (Order Number EA-12-049)
dated February 28, 2013 (ADAMS Accession No. ML13063A185).
A 21
 
United States Nuclear Regulatory Commission
-. February 26, 2015 Page 2
: 6. McGuire Nuclear Station First Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-basis External Events (Order Number EA-12-049)
Dated August 28, 2013 (ADAMS Accession No. ML13254A204).
Dated August 28, 2013 (ADAMS Accession No. ML13254A204).
: 7. McGuire Nuclear Station Second Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-basis External Events (Order Number EA-12-049)
: 7. McGuire Nuclear Station Second Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-basis External Events (Order Number EA-12-049) Dated February 27, 2014 (ADAMS Accession No. ML14073A462).
Dated February 27, 2014 (ADAMS Accession No. ML14073A462).
: 8. McGuire Nuclear Station Third Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-basis External Events (Order Number EA-12-049)
: 8. McGuire Nuclear Station Third Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-basis External Events (Order Number EA-12-049)
Dated August 27, 2014 (ADAMS Accession No. ML14253A188).On March 12, 2012, the Nuclear Regulatory Commission (NRC) issued Order EA-12-049 (Reference
Dated August 27, 2014 (ADAMS Accession No. ML14253A188).
: 1) to Duke Energy. Reference 1 was immediately effective and directs Duke Energy to develop, implement, and maintain guidance and strategies to maintain or restore core cooling, containment, and spent fuel pool cooling capabilities in the event of a beyond-design-basis external event. Specific requirements are outlined in Attachment 2 of Reference 1.Reference 1 required submission of an initial status report 60 days following issuance of the final interim staff guidance (Reference
On March 12, 2012, the Nuclear Regulatory Commission (NRC) issued Order EA-12-049 (Reference 1) to Duke Energy. Reference 1 was immediately effective and directs Duke Energy to develop, implement, and maintain guidance and strategies to maintain or restore core cooling, containment, and spent fuel pool cooling capabilities in the event of a beyond-design-basis external event. Specific requirements are outlined in Attachment 2 of Reference 1.
: 2) and an Overall Integrated Plan (OIP) pursuant to Section IV, Condition C. Reference 2 endorses industry guidance document NEI 12-06, Revision 0 (Reference
Reference 1 required submission of an initial status report 60 days following issuance of the final interim staff guidance (Reference 2) and an Overall Integrated Plan (OIP) pursuant to Section IV, Condition C. Reference 2 endorses industry guidance document NEI 12-06, Revision 0 (Reference 3) with clarifications and exceptions identified in Reference 2. Reference 4 provided the initial status report regarding mitigation strategies at the Oconee, McGuire and Catawba Nuclear Stations. Reference 5 provided the OIP for MNS.
: 3) with clarifications and exceptions identified in Reference
Reference 1 requires submission of a status report at six-month intervals following submittal of the OIP. Reference 3 provides direction regarding the content of the status reports.
: 2. Reference 4 provided the initial status report regarding mitigation strategies at the Oconee, McGuire and Catawba Nuclear Stations.
The purpose of this letter is to provide the fourth six-month status report pursuant to Section IV, Condition C.2, of Reference 1. The attached report provides an update of milestone accomplishments since the last status report, including any changes to the compliance method, schedule, or need for relief and the basis, if any.
Reference 5 provided the OIP for MNS.Reference 1 requires submission of a status report at six-month intervals following submittal of the OIP. Reference 3 provides direction regarding the content of the status reports.The purpose of this letter is to provide the fourth six-month status report pursuant to Section IV, Condition C.2, of Reference
 
: 1. The attached report provides an update of milestone accomplishments since the last status report, including any changes to the compliance method, schedule, or need for relief and the basis, if any.
United States Nuclear Regulatory Commission February 26, 2015 Page 3 This letter contains no new Regulatory Commitments and no revision to existing Regulatory Commitments.
United States Nuclear Regulatory Commission February 26, 2015 Page 3 This letter contains no new Regulatory Commitments and no revision to existing Regulatory Commitments.
Should you have any questions regarding this submittal, please contact George Murphy at (980) 875-5715.I declare under penalty of perjury that the foregoing is true and correct. Executed on February 26, 2015.Sincerely, Steven D. Capps  
Should you have any questions regarding this submittal, please contact George Murphy at (980) 875-5715.
I declare under penalty of perjury that the foregoing is true and correct. Executed on February 26, 2015.
Sincerely, Steven D. Capps


==Enclosure:==
==Enclosure:==


MNS Fourth Six-Month Status Report in Response to Order EA-12-049 United States Nuclear Regulatory Commission February 26, 2015 Page 4 xc: V.M. McCree, Region II Administrator U.S. Nuclear Regulatory Commission Marquis One Tower 245 Peachtree Center Avenue NE, Suite 1200 Atlanta, Georgia 30303-1257 John Boska, Project Manager (OMB)U.S. Nuclear Regulatory Commission One White Flint North, Mailstop O-8G9A 11555 Rockville Pike Rockville, MD 20852-2738 G. E. Miller, Project Manager (CNS & MNS)U.S. Nuclear Regulatory Commission 11555 Rockville Pike Mail Stop 8 G9A Rockville, MD 20852-2738 J. Zeiler NRC Senior Resident Inspector McGuire Nuclear Station Justin Folkwein American Nuclear Insurers 95 Glastonbury Blvd., Suite 300 Glastonbury, CT 06033-4453 ENCLOSURE MNS FOURTH SIX MONTH STATUS REPORT IN RESPONSE TO ORDER EA-12-049 MNS Fourth FLEX Six Month Status Report in Response to Order EA 12-049 1 Introduction McGuire developed an Overall Integrated Plan (OIP) (Reference 1 in Section 8), documenting the diverse and flexible strategies (FLEX), in response to NRC Order EA-12-049.
MNS Fourth Six-Month Status Report in Response to Order EA-12-049
The OIP was submitted to the NRC on February 28, 2013. The first six-month update was provided to the NRC on August 28, 2013 (Reference 3 in Section 8). The second six-month update was provided to the NRC on February 27, 2014 (Reference 5 in Section 8). The third six-month update was provided to the NRC on August 27, 2014 (Reference 6 in Section 8). This enclosure provides an update of milestone accomplishments including any changes to the compliance method, schedule, or need for relief/relaxation and the basis, if any, that occurred during the period from July 29, 2014 to January 31, 2015 (hereafter referred to as "the update period").2 Milestone Accomplishments All remaining Unit 1 milestones were completed during the update period (see Section 3).Unit 1 is considered in compliance with NRC Order EA-12-049 as of November 15, 2014 (Reference 12 in Section 8).The following Unit 2 milestones were completed during the update period: 1) Receive all portable FLEX equipment 2) Transmit results of Phase 2 staffing study 3) Regional Response Center in place Page 1 of 20 3 Milestone Schedule Status The following provides an update to Attachment 2 of the Overall Integrated Plan. It provides the activity status of each item, and whether the expected completion date has changed. The dates are planning dates subject to change as design and implementation details are developed.
 
Target Revised Unit 1 Milestones Completion Activity Target Date Status Completion Date Complete Engineering Change Package and Plan 03/20/2014 Complete NA Work Orders Receive all portable FLEX equipment 05/20/2014 Complete NA Transmit results of Phase 2 staffing study 05/20/2014 Complete NA Complete all FSGs, AOPs, EOPs, OPs 10/31/2014 Complete NA Complete training for all FSGs, AOPs, EOPs, OPs 09/20/2014 Complete NA Complete all Maintenance Procedures 09/20/2014 Complete NA Begin Outage (1EOC23) Fall 2014 Complete NA Storage Plan -Reasonable Protection Facilities Fall 2014 Complete NA Complete Regional Response Center in place 10/19/2014 Complete NA Revised Unit 2 Milestones Completion Activity Target C pet Status Completion Date Date Complete Engineering Change Package and Plan 03/20/2015 Started Date Not Work Orders Revised Receive all portable FLEX equipment 05/20/2015 Complete NA Transmit results of Phase 2 staffing study 05/20/2015 Complete NA Date Not-Complete all FSGs, AOPs, EOPs, OPs 06/20/2015 Started Revise Revised Date Not Complete training for all FSGs, AOPs, EOPs, OPs 09/20/2015 Started Revise Revised Date Not Complete all Maintenance Procedures 09/20/2015 Started Revise Revised Not Date Not Begin Outage (2EOC23) Fall 2015 Sat Revise IStarted Revised Page 2 of 20 Revised Unit 2 Milestones Target Activity Target Completion Status Completion Date Date Storage Plan -Reasonable Protection Facilities Fall 2014 Complete*
United States Nuclear Regulatory Commission February 26, 2015 Page 4 xc:
Summer Complete 2015 Regional Response Center in place 10/11/2015 Complete NA* Facility construction (three buildings) is complete.
V.M. McCree, Region II Administrator U.S. Nuclear Regulatory Commission Marquis One Tower 245 Peachtree Center Avenue NE, Suite 1200 Atlanta, Georgia 30303-1257 John Boska, Project Manager (OMB)
Unit 1 compliance was met with the completion and loading of the first two buildings in Fall 2014. Unit 2 compliance with Order EA-12-049 will be met with the loading of the remaining building.4 Changes to Compliance Method There were no new changes to the compliance method identified during the update period.5 Need for Relief/Relaxation and Basis for the Relief/Relaxation McGuire expects to comply with the Order implementation date and no relief/relaxation is required at this time contingent on the following:
U.S. Nuclear Regulatory Commission One White Flint North, Mailstop O-8G9A 11555 Rockville Pike Rockville, MD 20852-2738 G. E. Miller, Project Manager (CNS & MNS)
* Resolution of issues regarding RCP #1 seal leak-off flow rates and leak-off piping integrity, as identified in NSAL 14-1, Revision 1.6 Open Items The following sections provide tables summarizing the status of the Open Items:* Section 6.a provides the open items identified in the original OIP submitted on February 28, 2013." Section 6.b provides a list of open items that were added after February 28, 2013.* Section 6.c provides a list of open items related to the Interim Staff Evaluation (ISE)received on January 16, 2014.* Section 6.d provides a list of open items related to the NRC Audit Report received on October 9, 2014.Unit 2 designators have been added to the Open Item descriptions where appropriate since Unit 1 is in compliance with the Order.Page 3 of 20 Section 6.a. Open Items Documented in the Overall Integrated Plan.Note: items marked with an asterisk (*) are designed and awaiting implementation.
U.S. Nuclear Regulatory Commission 11555 Rockville Pike Mail Stop 8 G9A Rockville, MD 20852-2738 J. Zeiler NRC Senior Resident Inspector McGuire Nuclear Station Justin Folkwein American Nuclear Insurers 95 Glastonbury Blvd., Suite 300 Glastonbury, CT 06033-4453
Note: items marked with a double asterisk (**) have been completed during this update period.Overall Integrated Plan Open Item Status 1 Implement (Units 1 and 2) plant modification:
 
Assured Air to the TDAFWP FCVs and SG PORVs (Current Unit 1 Started*configuration is based on 3rd Six Month Update Change #2)2 Implement (Unit 2) plant modification:
ENCLOSURE MNS FOURTH SIX MONTH STATUS REPORT IN RESPONSE TO ORDER EA-12-049
Assured Water Supply to the TDAFWPs 3 Implement (Unit 2) plant modification:
 
SFP Wide-Range Level Instrumentation 4 Implement plant modification:
MNS Fourth FLEX Six Month Status Report in Response to Order EA 12-049 1     Introduction McGuire developed an Overall Integrated Plan (OIP) (Reference 1 in Section 8), documenting the diverse and flexible strategies (FLEX), in response to NRC Order EA-12-049. The OIP was submitted to the NRC on February 28, 2013. The first six-month update was provided to the NRC on August 28, 2013 (Reference 3 in Section 8). The second six-month update was provided to the NRC on February 27, 2014 (Reference 5 in Section 8). The third six-month update was provided to the NRC on August 27, 2014 (Reference 6 in Section 8). This enclosure provides an update of milestone accomplishments including any changes to the compliance method, schedule, or need for relief/relaxation and the basis, if any, that occurred during the period from July 29, 2014 to January 31, 2015 (hereafter referred to as "the update period").
UHF Completed**
2     Milestone Accomplishments All remaining Unit 1 milestones were completed during the update period (see Section 3).
Communication System Upgrades 5 Implement (Unit 2) plant modification:
Unit 1 is considered in compliance with NRC Order EA-12-049 as of November 15, 2014 (Reference 12 in Section 8).
Started*Process Connections 6 Implement (Unit 2) plant modification:
The following Unit 2 milestones were completed during the update period:
Permanent Connections for Portable Started*Electrical Equipment 7 Implement plant modification:
: 1)   Receive all portable FLEX equipment
FLEX Completed Storage Facilities 8 Implement (Unit 2) plant modification:
: 2)   Transmit results of Phase 2 staffing study
Submersible Ground Water Sump Pump 9 Implement (Unit 2) plant modification:
: 3)   Regional Response Center in place Page 1 of 20
Started*FLEX Strategy Implementation 10 Implement (Unit 2) plant modification: "B" Started*RN to CA Pump Suction Re-route 11 Implement plant modification:
 
Install Emergency Hardhat Light Storage Boxes Completed and Hardhat Hooks 12 A staffing Phase 2 study will be performed in accordance with NEI 12-01 to verify that alt actions can be taken in accordance with the timeline.
3   Milestone Schedule Status The following provides an update to Attachment 2 of the Overall Integrated Plan. It provides the activity status of each item, and whether the expected completion date has changed. The dates are planning dates subject to change as design and implementation details are developed.
Time constraints shown in Attachment 1A will Completed**
Target                     Revised Completion      Activity      Target Unit 1 Milestones Date         Status     Completion Date Complete Engineering Change Package and Plan             03/20/2014     Complete         NA Work Orders Receive all portable FLEX equipment                       05/20/2014     Complete         NA Transmit results of Phase 2 staffing study               05/20/2014     Complete         NA Complete all FSGs, AOPs, EOPs, OPs                       10/31/2014     Complete         NA Complete training for all FSGs, AOPs, EOPs, OPs           09/20/2014     Complete         NA Complete all Maintenance Procedures                       09/20/2014     Complete         NA Begin Outage (1EOC23)                                     Fall 2014     Complete         NA Storage Plan - Reasonable Protection Facilities           Fall 2014     Complete         NA Complete Regional Response Center in place                         10/19/2014     Complete         NA Revised Unit 2 Milestones                   Completion     Activity       Target Cpet        Status     Completion Date                         Date Complete Engineering Change Package and Plan             03/20/2015     Started       Date Not Work Orders                                                                             Revised Receive all portable FLEX equipment                       05/20/2015     Complete         NA Transmit results of Phase 2 staffing study               05/20/2015     Complete         NA Date Not
-Complete all FSGs, AOPs, EOPs, OPs                       06/20/2015     Started       Revise Revised Date Not Complete training for all FSGs, AOPs, EOPs, OPs           09/20/2015     Started       Revise Revised Date Not Complete all Maintenance Procedures                       09/20/2015     Started       Revise Revised Not         Date Not Begin Outage (2EOC23)                                     Fall 2015     Sat           Revise IStarted       Revised Page 2 of 20
 
Revised Unit 2 Milestones                           Target       Activity       Target Completion       Status     Completion Date                         Date Storage Plan - Reasonable Protection Facilities                 Fall 2014     Complete*       Summer Complete                                                                                       2015 Regional Response Center in place                             10/11/2015     Complete         NA
* Facility construction (three buildings) is complete. Unit 1 compliance was met with the completion and loading of the first two buildings in Fall 2014. Unit 2 compliance with Order EA-12-049 will be met with the loading of the remaining building.
4 Changes to Compliance Method There were no new changes to the compliance method identified during the update period.
5   Need for Relief/Relaxation and Basis for the Relief/Relaxation McGuire expects to comply with the Order implementation date and no relief/relaxation is required at this time contingent on the following:
* Resolution of issues regarding RCP #1 seal leak-off flow rates and leak-off piping integrity, as identified in NSAL 14-1, Revision 1.
6   Open Items The following sections provide tables summarizing the status of the Open Items:
* Section 6.a provides   the open items identified in the original OIP submitted on February 28, 2013.
    "   Section 6.b provides   a list of open items that were added after February 28, 2013.
* Section 6.c provides   a list of open items related to the Interim Staff Evaluation (ISE) received on January   16, 2014.
* Section 6.d provides   a list of open items related to the NRC Audit Report received on October 9, 2014.
Unit 2 designators have been added to the Open Item descriptions where appropriate since Unit 1 is in compliance with the Order.
Page 3 of 20
 
Section 6.a.       Open Items Documented in the Overall Integrated Plan.
Note: items marked with an asterisk (*) are designed and awaiting implementation.
Note: items marked with a double asterisk (**) have been completed during this update period.
Overall Integrated Plan Open Item                       Status 1     Implement (Units 1 and 2) plant modification: Assured Air to the TDAFWP FCVs and SG PORVs (Current Unit 1                         Started*
configuration is based on 3rd Six Month Update Change #2) 2     Implement (Unit 2) plant modification:
Assured Water Supply to the TDAFWPs 3     Implement (Unit 2) plant modification:
SFP Wide-Range Level Instrumentation 4     Implement plant modification: UHF                       Completed**
Communication System Upgrades 5     Implement (Unit 2) plant modification:                     Started*
Process Connections 6     Implement (Unit 2) plant modification:
Permanent Connections for Portable                         Started*
Electrical Equipment 7     Implement plant modification: FLEX                       Completed Storage Facilities 8     Implement (Unit 2) plant modification:
Submersible Ground Water Sump Pump 9     Implement (Unit 2) plant modification:                     Started*
FLEX Strategy Implementation 10   Implement (Unit 2) plant modification: "B"                 Started*
RN to CA Pump Suction Re-route 11   Implement plant modification: Install Emergency Hardhat Light Storage Boxes                     Completed and Hardhat Hooks 12   A staffing Phase 2 study will be performed in accordance with NEI 12-01 to verify that alt actions can be taken in accordance with the timeline. Time constraints shown in Attachment 1A will                 Completed**
be validated to be reasonable as the strategy is finalized.
be validated to be reasonable as the strategy is finalized.
Page 4 of 20 13 An analysis was performed in Duke Energy Calculation MCC-1223.31 0012 that indicates that flooding will not occur for at least 48 hours. This analysis will be revised to demonstrate that this Completed time remains unaffected even if potential sources of water from Auxiliary Building or Turbine Building flooding are considered.
Page 4 of 20
14 A calculation will be performed to demonstrate that sufficient negative reactivity can be added through use of a pump and a reactor coolant system vent Completed path to achieve xenon free cool down in accordance with the PWROG FSG guidelines.
 
15 Complete vital battery area room heatup aid (see open item #48) hydrogen Completed.
13 An analysis was performed in Duke Energy Calculation MCC-1223.31   0012 that indicates that flooding will not occur for at least 48 hours. This analysis will be revised to demonstrate that this                     Completed time remains unaffected even if potential sources of water from Auxiliary Building or Turbine Building flooding are considered.
accumulation calculation to determine if Description of this Open Item revised portable fans or HVAC units may be per Open Item 48 required, and timeframe for deployment.
14 A calculation will be performed to demonstrate that sufficient negative reactivity can be added through use of a pump and a reactor coolant system vent                       Completed path to achieve xenon free cool down in accordance with the PWROG FSG guidelines.
16 Complete a calculation to determine when elevated interior doghouse temperatures adversely impact the FLEX Completed strategy and to evaluate methods for mitigation.
15 Complete vital battery area room heatup aid (see open item #48) hydrogen                             Completed.
17 An evaluation will be performed to determine how long raw water can be used to supply SGs without excessively affecting SG capability to remove heat and provide steam to the TDAFW pump.This will help determine when Phase 3 equipment may be needed to assist in providing cleaner water sources.18 MNS will evaluate the need to provide freeze protection for critical Completed instrumentation and exposed FLEX connections.
accumulation calculation to determine if         Description of this Open Item revised portable fans or HVAC units may be                         per Open Item 48 required, and timeframe for deployment.
19 Methods will be initiated to circulate and cool air in lower containment sub compartments to prevent any adverse impact on critical instrumentation.
16 Complete a calculation to determine when elevated interior doghouse temperatures adversely impact the FLEX                       Completed strategy and to evaluate methods for mitigation.
The response time is based on engineering Completed judgment and will be confirmed by analysis.Page 5 of 20 20 Deployment routes will be established and are expected to be utilized to transport FLEX equipment to the deployment areas. The identified paths and deployment areas will be accessible during all modes of operation.
17 An evaluation will be performed to determine how long raw water can be used to supply SGs without excessively affecting SG capability to remove heat and provide steam to the TDAFW pump.
This deployment strategy will be included within an administrative program in order to keep pathways clear or actions to clear the pathways.Completed**
This will help determine when Phase 3 equipment may be needed to assist in providing cleaner water sources.
21 MNS will implement programmatic controls in accordance with NEI 12-06.Procedures and guidelines will be reviewed and revised and/or generated Completed**
18 MNS will evaluate the need to provide freeze protection for critical                                 Completed instrumentation and exposed FLEX connections.
19 Methods will be initiated to circulate and cool air in lower containment sub compartments to prevent any adverse impact on critical instrumentation. The response time is based on engineering                       Completed judgment and will be confirmed by analysis.
Page 5 of 20
 
20 Deployment routes will be established and are expected to be utilized to transport FLEX equipment to the deployment areas. The identified paths and deployment areas will be accessible Completed**
during all modes of operation. This deployment strategy will be included within an administrative program in order to keep pathways clear or actions to clear the pathways.
21 MNS will implement programmatic controls in accordance with NEI 12-06.
Procedures and guidelines will be reviewed and revised and/or generated           Completed**
as required to address additional programmatic controls as a result of FLEX requirements.
as required to address additional programmatic controls as a result of FLEX requirements.
22 Equipment associated with FLEX mitigation strategies will be procured as commercial equipment with design, Completed" storage, maintenance, testing, and configuration control in accordance with NEI 12-06 Section 11.1.23 Installed structures, systems and components pursuant to 10 CFR 50.63(a) will continue to meet augmented Completed guidelines of Regulatory Guide (RG)1.155, Station Blackout.24 The unavailability of equipment and applicable connections that directly perform a FLEX mitigation strategy will Completed" be managed using plant equipment control guidelines developed in accordance with NEI 12-06 Section 11.5.25 Programs and processes will be established (Unit 2) to ensure that personnel proficiency in the mitigation of Started beyond-design-basis events is developed and maintained in accordance with NEI 12-06 Section 11.6.26 The FLEX strategies and basis will be maintained in overall FLEX basis documents.
22 Equipment associated with FLEX mitigation strategies will be procured as commercial equipment with design,               Completed" storage, maintenance, testing, and configuration control in accordance with NEI 12-06 Section 11.1.
Completed**
23 Installed structures, systems and components pursuant to 10 CFR 50.63(a) will continue to meet augmented         Completed guidelines of Regulatory Guide (RG) 1.155, Station Blackout.
Page 6 of 20 4 27 Existing plant configuration control documents will be modified to ensure that changes to the plant design, physical plant layout, roads, buildings, and miscellaneous structures will not Completed**
24 The unavailability of equipment and applicable connections that directly perform a FLEX mitigation strategy will         Completed" be managed using plant equipment control guidelines developed in accordance with NEI 12-06 Section 11.5.
adversely impact the approved FLEX strategies in accordance with NEI 12-06 Section 11.8.28 Training will be initiated through the Systematic Approach to Training (SAT)process. Training will be developed and provided to all involved plant personnel Unit 1 Completed**
25 Programs and processes will be established (Unit 2) to ensure that personnel proficiency in the mitigation of       Started beyond-design-basis events is developed and maintained in accordance with NEI 12-06 Section 11.6.
based on any procedural changes or new procedures developed to address and Unit 2 Started identify FLEX activities.
26 The FLEX strategies and basis will be maintained in overall FLEX basis documents.                                     Completed**
Applicable training will be completed prior to the implementation of FLEX.29 The industry will establish two Regional Response Centers (RRCs) to support Completed" utilities during beyond-design-basis events.30 The N+1 FLEX storage facilities will be designed in accordance with ASCE 7-10, Minimum Design Loads for Buildings and Other Structures.
Page 6 of 20
The FLEX storage facilities will be designed in accordance with ASCE 7-10, to withstand the maximum anticipated hurricane and Completed tornado winds as outlined in NEI 12-06.The FLEX buildings will be located in accordance with NEI 12-06 Section 7.3.1 to prevent damage to more than one of the three facilities due to tornado missiles.31 FLEX storage facilities will be located above any potential site flood level, and/or the effects of localized flooding Completed will be evaluated in the FLEX facility design and equipment deployment.
 
32 Debris removal/remediation equipment and procedures will be provided to Completed support FLEX equipment deployment.
27 Existing plant configuration control 4    documents will be modified to ensure that changes to the plant design, physical plant layout, roads, buildings, and miscellaneous structures will not                   Completed**
33 Snow and ice removal/remediation equipment and procedures will be provided to support FLEX equipment Completed deployment.
adversely impact the approved FLEX strategies in accordance with NEI 12-06 Section 11.8.
Page 7 of 20 34 FLEX equipment will be capable of operation under extreme temperatures, and suitably maintained to ensure standby readiness.
28 Training will be initiated through the Systematic Approach to Training (SAT) process. Training will be developed and provided to all involved plant personnel         Unit 1 Completed**
FLEX storage facilities will be designed to Completed accommodate maximum snow and ice loading. FLEX storage facilities will be vented to maintain acceptable temperature.
based on any procedural changes or new procedures developed to address and               Unit 2 Started identify FLEX activities. Applicable training will be completed prior to the implementation of FLEX.
35 An evaluation will be performed to ensure that the 300 gpm pump is capable of adequate flow and pressure to support Completed feed and bleed core cooling in typical Mode 5 and Mode 6 configurations.
29 The industry will establish two Regional Response Centers (RRCs) to support                 Completed" utilities during beyond-design-basis events.
36 Since the overall FLEX strategy is aimed at preventing core damage, the engineering change process will drive out an evaluation to prioritize operator actions associated with containment isolation as time allows. For example, Completed the containment isolations to the Containment Ventilation Unit Condensate Drain Tank (VUCDT) will be closed first since this path connects containment atmosphere directly to the Auxiliary Building.37 An analysis will be performed to validate that containment spray for temperature/pressure control is not required over the long term. If the long term containment analysis determines that containment temperature and/or pressure will reach unacceptable levels Completed over the long term, connections will be installed for containment spray mitigating strategies and will be used with the portable diesel driven pumps to supply water from the UHS to the connections located in the Auxiliary Building.38 Fans in containment that circulate air will be restored as required to cool the cubicle areas and to prevent the increase in temperature from having an adverse impact on essential instrumentation.
30 The N+1 FLEX storage facilities will be designed in accordance with ASCE 7-10, Minimum Design Loads for Buildings and Other Structures. The FLEX storage facilities will be designed in accordance with ASCE 7-10, to withstand the maximum anticipated hurricane and                   Completed tornado winds as outlined in NEI 12-06.
The Completed engineering change process will drive out an evaluation to determine the appropriate timing of these actions.Page 8 of 20 39 Evaluate other long term strategies for cooling containment such as circulating Completed the air volume in the annulus.40 In order to prevent or mitigate this inevitability
The FLEX buildings will be located in accordance with NEI 12-06 Section 7.3.1 to prevent damage to more than one of the three facilities due to tornado missiles.
[i.e., vital battery depletion]:
31 FLEX storage facilities will be located above any potential site flood level, and/or the effects of localized flooding             Completed will be evaluated in the FLEX facility design and equipment deployment.
: 1. Portable power distribution equipment will be used to repower the vital batteries, or 2. An alternate strategy to deploy portable generators and cables will be developed to directly reestablish power to Completed the power supplies in the 7300 cabinets thereby re-powering the instrumentation loops, or 3. An alternate strategy to utilize handheld instruments will be developed to tap into the instrument loops locally to monitor essential parameters.
32 Debris removal/remediation equipment and procedures will be provided to                   Completed support FLEX equipment deployment.
41 An analysis was completed to demonstrate that adequate control room cooling would be available if action was Completed taken to open various doors at around 2 hours after the event occurs. This action will be incorporated into procedures.
33 Snow and ice removal/remediation equipment and procedures will be provided to support FLEX equipment                   Completed deployment.
42 An evaluation will be performed to determine diesel fuel, gasoline and two- Completed cycle oil requirements for Phase 1 and Phase 2 portable equipment.
Page 7 of 20
43 Analysis will be performed to determine Completed commodities requirements.
 
44 Evaluate SFP to ensure predicted makeup water dilution rates in the Spent Completed Fuel Pools for the coping strategies described herein are bounded.45 Analysis will be performed to determine radiation protection equipment Completed requirements.
34 FLEX equipment will be capable of operation under extreme temperatures, and suitably maintained to ensure standby readiness. FLEX storage facilities will be designed to                 Completed accommodate maximum snow and ice loading. FLEX storage facilities will be vented to maintain acceptable temperature.
46 These instruments
35 An evaluation will be performed to ensure that the 300 gpm pump is capable of adequate flow and pressure to support           Completed feed and bleed core cooling in typical Mode 5 and Mode 6 configurations.
[i.e., Essential Instrumentation and Vital I&C] will be used in the FSGs in accordance with the PWROG guidance.
36 Since the overall FLEX strategy is aimed at preventing core damage, the engineering change process will drive out an evaluation to prioritize operator actions associated with containment isolation as time allows. For example,         Completed the containment isolations to the Containment Ventilation Unit Condensate Drain Tank (VUCDT) will be closed first since this path connects containment atmosphere directly to the Auxiliary Building.
Setpoint uncertainty Completed analyses will be developed in accordance with PWROG guidance.Page 9 of 20 47 A portable battery pack with inverter is also being evaluated for use. The battery pack would be rapidly deployed for use to close the CLA motor-operated valves Completed (MOVs) outside of containment penetration without reliance on the valve's limit or torque switches or the valve's relay circuitry.
37 An analysis will be performed to validate that containment spray for temperature/pressure control is not required over the long term. If the long term containment analysis determines that containment temperature and/or pressure will reach unacceptable levels         Completed over the long term, connections will be installed for containment spray mitigating strategies and will be used with the portable diesel driven pumps to supply water from the UHS to the connections located in the Auxiliary Building.
Section 6.b.Open Items added after February 28, 2013 Note: status of items marked with a double asterisk (**) have been completed during this update period.First Six Month Update Status New Open Items 48 Complete vital battery area room heatup calculation to determine if portable fans or HVAC units may be required, and the Completed timeframe for deployment. (Reference open item 15)49 To facilitate the Phase 2 FLEX mitigation response, the high and low pressure make-up pumps for the Reactor Coolant System for each Unit are currently planned to be pre-staged in the Auxiliary Building, near the FLEX connection points. As these areas are within a Category I Completed seismic structure, no spares will be stored in the FLEX buildings for deployment, since "N" pieces of FLEX equipment are already deployed and protected.
38 Fans in containment that circulate air will be restored as required to cool the cubicle areas and to prevent the increase in temperature from having an adverse impact on essential instrumentation. The       Completed engineering change process will drive out an evaluation to determine the appropriate timing of these actions.
Per NEI 12-06 guidance, this equipment will be evaluated for seismic ruggedness.
Page 8 of 20
50 Access to connection points for the Phase 2 FLEX mitigation response will be through the north end of the McGuire Auxiliary Building, an area which is not seismically designed.
 
Section 5.3.2 part 2 of the NEI 12-06 Guidance Document states: "At Completed least one connection point of FLEX equipment will only require access through seismically robust structures.
39 Evaluate other long term strategies for cooling containment such as circulating             Completed the air volume in the annulus.
This includes both the connection point and any areas that plant operators will have to access to deploy or control the capability." Evaluate Page 10 of 20 Auxiliary Building access points for possible qualification of seismic ruggedness.
40 In order to prevent or mitigate this inevitability [i.e., vital battery depletion]:
51 Reference 01 #30. NEI 12-06 Guidance clarification documented in NEI FLEX Guidance Inquiry no. 2013-07 identifies that FLEX buildings designed for hurricane wind speeds and using diverse locations Completed per Section 7.3.1 part (c) are protected from both tornado and hurricane generated missiles.
: 1. Portable power distribution equipment will be used to repower the vital batteries, or
Validate strategy with NEI.Second Six Month Update New Open Items Status 52 McGuire to confirm that the FLEX strategy station battery run-time was calculated in accordance with the IEEE-485 methodology using manufacturer discharge test data applicable to the licensee's FLEX strategy as outlined in the NEI white paper on Extended Battery Duty Cycles. The detailed licensee calculations, supporting vendor discharge test data, FLEX strategy battery load Completed profile, and other inputs/initial conditions required by IEEE-485 will be available on the licensee's web portal for documents and calculations.
: 2. An alternate strategy to deploy portable generators and cables will be developed to directly reestablish power to         Completed the power supplies in the 7300 cabinets thereby re-powering the instrumentation loops, or
The time margin between the calculated station battery run-time for the FLEX strategy and the expected deployment time for FLEX equipment to supply the dc loads is 4 hours.53 See ISE Open Item 3.2.1.8.A.
: 3. An alternate strategy to utilize handheld instruments will be developed to tap into the instrument loops locally to monitor essential parameters.
The PWROG submitted to NRC a position paper, dated August 15, 2013, which provides test data regarding boric acid mixing under single-phase natural circulation conditions and outlined applicability conditions intended to ensure that boric acid addition and mixing would Completed occur under conditions similar to those for which boric acid mixing data is available.
41 An analysis was completed to demonstrate that adequate control room cooling would be available if action was           Completed taken to open various doors at around 2 hours after the event occurs. This action will be incorporated into procedures.
McGuire to confirm its intent to abide by the generic approach discussed above, and address the clarifications in the NRC endorsement letter dated January 8, 2014.Page 11 of 20 54 NEI submitted the EPRI Report 3002000623 entitled "Nuclear Maintenance Applications Center: Preventative Maintenance Basis for FLEX Equipment" on October 23, 2013. Completed McGuire to confirm its intent to abide by the generic approach discussed above in developing FLEX equipment maintenance and testing programs.55 See ISE Confirmatory Item 3.2.1.7.A.
42 An evaluation will be performed to determine diesel fuel, gasoline and two-           Completed cycle oil requirements for Phase 1 and Phase 2 portable equipment.
McGuire to confirm that the guidance in NEI position paper, "Position Paper: Shutdown/Refueling Modes," will be Completed followed in the Mitigation Strategies for BDBEEs occurring during Shutdown/Refueling Modes.56 McGuire to confirm viability of proposed long-term ELAP Phase 3 recovery strategy: Modes 1-4: rely on passive ice condenser response and repowered containment/annulus ventilation fan cooling to prevent Pressurizer/Steam Generator level indication reference legs from flashing during RCS cooldown/depressurization, and realign/restart RHR system (and support Completed**
43 Analysis will be performed to determine             Completed commodities requirements.
systems).
44 Evaluate SFP to ensure predicted makeup water dilution rates in the Spent           Completed Fuel Pools for the coping strategies described herein are bounded.
Manage containment pressure as necessary.
45 Analysis will be performed to determine radiation protection equipment                     Completed requirements.
Modes 5-6: rely on passive ice condenser response and deploy portable FLEX pump within timeframe necessary to manage RCS boration/inventory.
46 These instruments [i.e., Essential Instrumentation and Vital I&C] will be used in the FSGs in accordance with the PWROG guidance. Setpoint uncertainty               Completed analyses will be developed in accordance with PWROG guidance.
Manage containment pressure as necessary and realign/restart RHR system (and support systems).Third Six Month Update Status New Open Items 57 NSAL 14-1: Upon completion of the vendor evaluation of the RCP seal leak-off flow with the installed Number 1 Seal Leak-off orifice, identify the path forward for meeting the FLEX Mitigation Strategy Completed**
Page 9 of 20
Analysis assumptions based on the evaluated leak-off flow.Page 12 of 20 New Open Items Status added this Update None. N/A Section 6.c.Interim Staff Evaluation Open and Confirmatory Items Note: status of items marked with a double asterisk (**) have been completed during this update period.Interim Staff Evaluation Open Item Status 3.2.1.8.A The PWROG submitted to NRC a position paper, dated August 15, 2013, which provides test data regarding boric acid mixing under single-phase natural circulation conditions and outlined applicability conditions intended to ensure that boric acid addition and mixing would occur under conditions similar to those for which boric acid mixing data is available.
 
During the audit process, the licensee informed the NRC staff of its intent to abide by the generic approach discussed above. The licensee should address the clarifications in the NRC endorsement letter dated January 8, 2014.Completed NMI, Interim Staff Evaluation Confirmatory Items Status 3.1.1.2.A Deployment of FLEX equipment  
47   A portable battery pack with inverter is also being evaluated for use. The battery pack would be rapidly deployed for use to close the CLA motor-operated valves                       Completed (MOVs) outside of containment penetration without reliance on the valve's limit or torque switches or the valve's relay circuitry.
-On page 57 of its Integrated Plan, in the chart identifying Pressurized Water Reactor (PWR) Portable Equipment Phase 2, the licensee lists (9) 9x12 trailers used to store and deploy power equipment, but does not list tow vehicles.Confirm abilities to move FLEX equipment and the level of protection afforded the means to move.Completed 3.1.1.3.A Procedural interfaces, seismic -Confirm evaluation that shows time is available to deploy ground water sump pumps as Completed needed in critical locations in addition to the vicinity of the TDAFW pump.Page 13 of 20 3.1.1.4.A Off Site Resources, seismic -Confirm development of the MNS playbook as well as identification of the local Completed**
Section 6.b.         Open Items added after February 28, 2013 Note: status of items marked with a double asterisk (**) have been completed during this update period.
Assembly Area and routes to the plant.3.1.3.1.A Protection of FLEX equipment, high winds -Site specific data to justify the assumed tornado width of 1200 feet will be required to confirm the final locations Completed of the FLEX storage facilities conform to NEI 12-06 guidance.3.1.5.2.A Deployment of FLEX equipment, high temperatures  
First Six Month Update                           Status New Open Items 48     Complete vital battery area room heatup calculation to determine if portable fans or HVAC units may be required, and the                       Completed timeframe for deployment. (Reference open item 15) 49     To facilitate the Phase 2 FLEX mitigation response, the high and low pressure make-up pumps for the Reactor Coolant System for each Unit are currently planned to be pre-staged in the Auxiliary Building, near the FLEX connection points. As these areas are within a Category I                       Completed seismic structure, no spares will be stored in the FLEX buildings for deployment, since "N" pieces of FLEX equipment are already deployed and protected. Per NEI 12-06 guidance, this equipment will be evaluated for seismic ruggedness.
-Confirm that the storage facilities will be designed for extreme temperature ranges including concerns Completed for expansion of sheet metal, swollen door seals, etc.3.2.1.A RCS Cooling and Heat Removal, and RCS Inventory Control Strategies  
50     Access to connection points for the Phase 2 FLEX mitigation response will be through the north end of the McGuire Auxiliary Building, an area which is not seismically designed. Section 5.3.2 part 2 of the NEI 12-06 Guidance Document states: "At                       Completed least one connection point of FLEX equipment will only require access through seismically robust structures. This includes both the connection point and any areas that plant operators will have to access to deploy or control the capability." Evaluate Page 10 of 20
-Justify the use of the analysis from Sections 5.2.1 and 5.2.2 of WCAP-17601-P by identifying and evaluating the Completed important parameters and assumptions demonstrating that they are representative of MNS and appropriate for simulating the ELAP transient.
 
3.2.1.1 .A Computer Code Used for ELAP Analysis-Confirm that reliance on the NOTRUMP code for the ELAP analysis of Westinghouse plants is limited to the flow conditions prior to reflux Completed condensation initiation.
Auxiliary Building access points for possible qualification of seismic ruggedness.
This includes specifying an acceptable definition for reflux condensation cooling.3.2.1.2.A RCP seals -Confirm that the RCP seal initial maximum leakage rate used in the analysis is greater than or equal to the upper bound expectation for the ELAP event (21 gpm/seal) discussed in the Completed PWROG white paper addressing the RCP seal leakage for Westinghouse plants.3.2.1.2.B RCP seals -In some plant designs, such as those with 1200 to 1300 psia SG design pressures and no accumulator Completed backing of the main steam system power-operated relief valve (PORV)Page 14 of 20 actuators, the cold legs could experience temperatures as high as 580 degrees F before cooldown commences.
51 Reference 01 #30. NEI 12-06 Guidance clarification documented in NEI FLEX Guidance Inquiry no. 2013-07 identifies that FLEX buildings designed for hurricane wind speeds and using diverse locations           Completed per Section 7.3.1 part (c) are protected from both tornado and hurricane generated missiles. Validate strategy with NEI.
This is beyond the qualification temperature (550 degrees F) of the O-rings used in the RCP seals. For those Westinghouse designs, a discussion of the information (including the applicable analysis and relevant seal leakage testing data)should be provided to justify that (1) the integrity of the associated O-rings will be maintained at the temperature conditions experienced during the ELAP event, and (2) the seal leakage rate of 21 gpm/seal used in the ELAP is adequate and acceptable.
Second Six Month Update New Open Items                     Status 52 McGuire to confirm that the FLEX strategy station battery run-time was calculated in accordance with the IEEE-485 methodology using manufacturer discharge test data applicable to the licensee's FLEX strategy as outlined in the NEI white paper on Extended Battery Duty Cycles. The detailed licensee calculations, supporting vendor discharge test data, FLEX strategy battery load             Completed profile, and other inputs/initial conditions required by IEEE-485 will be available on the licensee's web portal for documents and calculations. The time margin between the calculated station battery run-time for the FLEX strategy and the expected deployment time for FLEX equipment to supply the dc loads is 4 hours.
-4 .4 3.2.1.2.C RCP seals -If the seals are changed to the newly designed Generation 3 SHIELD seals, or non-Westinghouse seals, the acceptability of the use of the newly designed Generation 3 SHIELD seals, or non-Westinghouse seals should be addressed, and the RCP seal leakages rates for use in the ELAP analysis should be provided with acceptable justification.
53 See ISE Open Item 3.2.1.8.A. The PWROG submitted to NRC a position paper, dated August 15, 2013, which provides test data regarding boric acid mixing under single-phase natural circulation conditions and outlined applicability conditions intended to ensure that boric acid addition and mixing would         Completed occur under conditions similar to those for which boric acid mixing data is available.
Completed 3.2.1.3.A Decay Heat -Values of the following key parameters used to determine the decay heat should be specified and the adequacy of the values evaluated:
McGuire to confirm its intent to abide by the generic approach discussed above, and address the clarifications in the NRC endorsement letter dated January 8, 2014.
(1)initial power level, (2) fuel enrichment, (3)fuel burnup, (4) effective full power operating days per fuel cycle, (5) number of fuel cycles, if hybrid fuels are used in the core, and (6) fuel characteristics are based on the beginning of the cycle, middle of the cycle, or end of the cycle.Completed 3.2.1.4.A Initial Values for Key Plant Parameters and Assumptions  
Page 11 of 20
-Confirm results and appropriate actions subsequent to Westinghouse supplying McGuire with Completed additional information regarding the key plant parameters and assumptions.
 
3.2.1.7.A Confirm that MNS will abide by the generic resolution for shutdown and refueling concerns.
54 NEI submitted the EPRI Report 3002000623 entitled "Nuclear Maintenance Applications Center:
Completed**
Preventative Maintenance Basis for FLEX Equipment" on October 23, 2013.                   Completed McGuire to   confirm its intent to abide by the generic   approach discussed above in developing   FLEX equipment maintenance and testing   programs.
Page 15 of 20 I 3.2.3.A Containment Functions Strategies  
55 See ISE Confirmatory Item 3.2.1.7.A.
-Confirm completion of the long term containment analysis and appropriate Completed actions.3.2.4.4.A Lighting and Communications  
McGuire to confirm that the guidance in NEI position paper, "Position Paper:
-Confirmation will be required that upgrades to the site's communications Completed**
Shutdown/Refueling Modes," will be                 Completed followed in the Mitigation Strategies for BDBEEs occurring during Shutdown/Refueling Modes.
56 McGuire to confirm viability of proposed long-term ELAP Phase 3 recovery strategy:
Modes 1-4: rely on passive ice condenser response and repowered containment/annulus ventilation fan cooling to prevent Pressurizer/Steam Generator level indication reference legs from flashing during RCS cooldown/depressurization, and realign/restart RHR system (and support           Completed**
systems). Manage containment pressure as necessary.
Modes 5-6: rely on passive ice condenser response and deploy portable FLEX pump within timeframe necessary to manage RCS boration/inventory. Manage containment pressure as necessary and realign/restart RHR system (and support systems).
Third Six Month Update                     Status New Open Items 57 NSAL 14-1: Upon completion of the vendor evaluation of the RCP seal leak-off flow with the installed Number 1 Seal Leak-off orifice, identify the path forward for meeting the FLEX Mitigation Strategy         Completed**
Analysis assumptions based on the evaluated leak-off flow.
Page 12 of 20
 
New Open Items                               Status added this Update None.                                                         N/A Section 6.c.         Interim Staff Evaluation Open and Confirmatory Items Note: status of items marked with a double asterisk (**) have been completed during this update period.
Interim Staff Evaluation Status Open Item 3.2.1.8.A     The PWROG submitted to NRC a position paper, dated August 15, 2013, which provides test data regarding boric acid mixing under single-phase natural circulation conditions and outlined applicability conditions intended to ensure that boric acid addition and mixing would occur under conditions similar to those for which boric acid                 Completed mixing data is available.
During the audit process, the licensee informed the NRC staff of its intent to abide by the generic approach discussed above. The licensee should address the clarifications in the NRC endorsement letter dated January 8, 2014.
NMI, Interim Staff Evaluation                       Status Confirmatory Items 3.1.1.2.A     Deployment of FLEX equipment - On page 57 of its Integrated Plan, in the chart identifying Pressurized Water Reactor (PWR) Portable Equipment Phase 2, the licensee lists (9) 9x12 trailers used to store and deploy power               Completed equipment, but does not list tow vehicles.
Confirm abilities to move FLEX equipment and the level of protection afforded the means to move.
3.1.1.3.A     Procedural interfaces, seismic - Confirm evaluation that shows time is available to deploy ground water sump pumps as                     Completed needed in critical locations in addition to the vicinity of the TDAFW pump.
Page 13 of 20
 
3.1.1.4.A Off Site Resources, seismic - Confirm development of the MNS playbook as well as identification of the local       Completed**
Assembly Area and routes to the plant.
3.1.3.1.A Protection of FLEX equipment, high winds - Site specific data to justify the assumed tornado width of 1200 feet will be required to confirm the final locations Completed of the FLEX storage facilities conform to NEI 12-06 guidance.
3.1.5.2.A Deployment of FLEX equipment, high temperatures - Confirm that the storage facilities will be designed for extreme temperature ranges including concerns       Completed for expansion of sheet metal, swollen door seals, etc.
3.2.1.A   RCS Cooling and Heat Removal, and RCS Inventory Control Strategies -
Justify the use of the analysis from Sections 5.2.1 and 5.2.2 of WCAP-17601-P by identifying and evaluating the   Completed important parameters and assumptions demonstrating that they are representative of MNS and appropriate for simulating the ELAP transient.
3.2.1.1 .A Computer Code Used for ELAP Analysis
          - Confirm that reliance on the NOTRUMP code for the ELAP analysis of Westinghouse plants is limited to the flow conditions prior to reflux             Completed condensation initiation. This includes specifying an acceptable definition for reflux condensation cooling.
3.2.1.2.A   RCP seals - Confirm that the RCP seal initial maximum leakage rate used in the analysis is greater than or equal to the upper bound expectation for the ELAP event (21 gpm/seal) discussed in the       Completed PWROG white paper addressing the RCP seal leakage for Westinghouse plants.
3.2.1.2.B   RCP seals - In some plant designs, such as those with 1200 to 1300 psia SG design pressures and no accumulator         Completed backing of the main steam system power-operated relief valve (PORV)
Page 14 of 20
 
actuators, the cold legs could experience temperatures as high as 580 degrees F before cooldown commences. This is beyond the qualification temperature (550 degrees F) of the O-rings used in the RCP seals. For those Westinghouse designs, a discussion of the information (including the applicable analysis and relevant seal leakage testing data) should be provided to justify that (1) the integrity of the associated O-rings will be maintained at the temperature conditions experienced during the ELAP event, and (2) the seal leakage rate of 21 gpm/seal used in the ELAP is adequate and acceptable.
          -4                                               .4 3.2.1.2.C     RCP seals - If the seals are changed to the newly designed Generation 3 SHIELD seals, or non-Westinghouse seals, the acceptability of the use of the newly designed Generation 3 SHIELD seals, or non-Westinghouse seals should           Completed be addressed, and the RCP seal leakages rates for use in the ELAP analysis should be provided with acceptable justification.
3.2.1.3.A     Decay Heat - Values of the following key parameters used to determine the decay heat should be specified and the adequacy of the values evaluated: (1) initial power level, (2) fuel enrichment, (3) fuel burnup, (4) effective full power           Completed operating days per fuel cycle, (5) number of fuel cycles, if hybrid fuels are used in the core, and (6) fuel characteristics are based on the beginning of the cycle, middle of the cycle, or end of the cycle.
3.2.1.4.A     Initial Values for Key Plant Parameters and Assumptions - Confirm results and appropriate actions subsequent to Westinghouse supplying McGuire with               Completed additional information regarding the key plant parameters and assumptions.
3.2.1.7.A     Confirm that MNS will abide by the generic resolution for shutdown and refueling concerns.                             Completed**
Page 15 of 20
 
3.2.3.A   Containment Functions Strategies -
I            Confirm completion of the long term containment analysis and appropriate       Completed actions.
3.2.4.4.A Lighting and Communications -
Confirmation will be required that upgrades to the site's communications     Completed**
systems have been completed.
systems have been completed.
3.2.4.6.A Ventilation for Equipment Cooling and Personnel Habitability  
3.2.4.6.A Ventilation for Equipment Cooling and Personnel Habitability - Room heat up response for specific MNS areas are completed but need to be evaluated by       Completed NRC personnel. Confirm completion of evaluation and appropriate actions.
-Room heat up response for specific MNS areas are completed but need to be evaluated by Completed NRC personnel.
3.2.4.7.A Water Sources - Confirm that plant procedures specify that a flow path is promptly established for makeup flow to the steam generators and identify backup water sources in order of intended use;     Completed and that plant procedures/guidance should specify clear criteria for transferring to the next preferred source of water.
Confirm completion of evaluation and appropriate actions.3.2.4.7.A Water Sources -Confirm that plant procedures specify that a flow path is promptly established for makeup flow to the steam generators and identify backup water sources in order of intended use; Completed and that plant procedures/guidance should specify clear criteria for transferring to the next preferred source of water.3.2.4.8.A Electrical Power Sources -Confirm completion of Flex DG sizing calculation Completed and appropriate actions.3.2.4.9.A Portable Equipment Fuel -Confirm completion of evaluation and appropriate Completed actions to assess long-term FLEX equipment fuel oil requirements.
3.2.4.8.A Electrical Power Sources - Confirm completion of Flex DG sizing calculation   Completed and appropriate actions.
3.2.4.10.A The battery sizing calculation needs to be verified when revised to show that dc power for 2 of 4 channels can be Completed maintained for 24 hours without a charger. in place.3.2.4.10.B Load Reduction to Conserve DC Power -Confirm that ELAP procedures/guidance will direct operators to conserve dc power Completed during the event by stripping nonessential loads as soon as practical.
3.2.4.9.A   Portable Equipment Fuel - Confirm completion of evaluation and appropriate   Completed actions to assess long-term FLEX equipment fuel oil requirements.
3.4.A Offsite Resources  
3.2.4.10.A The battery sizing calculation needs to be verified when revised to show that dc power for 2 of 4 channels can be           Completed maintained for 24 hours without a charger. in place.
-Confirm NEI 12-06, Section 12.2, Guidelines 2 through 10 Completed**
3.2.4.10.B Load Reduction to Conserve DC Power -
are addressed with the RRC.Page 16 of 20 Section 6.d.NRC Onsite Mitigation Strategy Audit Report Note: status of items marked with a double asterisk (**) have been completed during this update period.Note: status of items marked "Pending" are industry issues in the process of being addressed by NRC or via the PWROG. Site-specific evaluation of these items has been completed.
Confirm that ELAP procedures/guidance will direct operators to conserve dc power Completed during the event by stripping nonessential loads as soon as practical.
Open Item # Audit Report Open Item Description Status Attachment 3, Off-Site Resources:
3.4.A       Offsite Resources - Confirm NEI 12-06, Section 12.2, Guidelines 2 through 10     Completed**
The NRC staff Item ISE CI requests that the licensee provide a copy Completed**
are addressed with the RRC.
3.1.1.4.A of the playbook once it's finalized.
Page 16 of 20
Attachment 3, Lighting and Communications:
 
The NRC Item ISE CI requested that the licensee provide 3.2.4.4.A confirmation of the modifications to the Completed**
Section 6.d.         NRC Onsite Mitigation Strategy Audit Report Note: status of items marked with a double asterisk (**) have been completed during this update period.
communications systems once completed.
Note: status of items marked "Pending" are industry issues in the process of being addressed by NRC or via the PWROG. Site-specific evaluation of these items has been completed.
Attachment 3, Process Connections:
Open Item #       Audit Report Open Item Description                     Status ,       Off-Site Resources: The NRC staff Item ISE CI         requests that the licensee provide a copy           Completed**
The NRC staff Licensee requested that the licensee provide a Identified OIP summary of the plant modifications to Completed" Open Item 5 implement the FLEX strategy for staff review.Attachment 3, Containment Functions Strategies:
3.1.1.4.A           of the playbook once it's finalized. ,       Lighting and Communications: The NRC Item ISE CI         requested that the licensee provide 3.2.4.4.A           confirmation of the modifications to the             Completed**
The Item ISE CI licensee has provided a response to the 3.2.3.A question on the ePortal; however, the Completed**
communications systems once completed. ,       Process Connections: The NRC staff Licensee           requested that the licensee provide a Identified OIP     summary of the plant modifications to               Completed" Open Item 5         implement the FLEX strategy for staff review. ,       Containment Functions Strategies: The Item ISE CI         licensee has provided a response to the 3.2.3.A             question on the ePortal; however, the                 Completed**
staff requests that the calculations be posted on the ePortal.Attachment 3, Portable Equipment Fuel: Provide Item ISE CI information on the fuel quality from the 3.2.4.9.A trucks that will be onsite to initially refuel Completed**
staff requests that the calculations be posted on the ePortal. ,       Portable Equipment Fuel: Provide Item ISE CI         information on the fuel quality from the 3.2.4.9.A           trucks that will be onsite to initially refuel       Completed**
FLEX equipment.
FLEX equipment. ,       NOTRUMP Code: The staff performed a SE Review           confirmatory ELAP analysis using Item 5             TRACE and is currently reviewing the results between TRACE and                               Pending NOTRUMP. In addition, the staff has requested a copy of the PWROG application of NOTRUMP white paper.
Attachment 3, NOTRUMP Code: The staff performed a SE Review confirmatory ELAP analysis using Item 5 TRACE and is currently reviewing the results between TRACE and Pending NOTRUMP. In addition, the staff has requested a copy of the PWROG application of NOTRUMP white paper.Attachment 3, RCP Leakage Rate: The NRC staff SE Review understands that Westinghouse has Item 7 recently recalculated seal leak-off line pressures under loss of seal cooling events based on a revised seal leakage Pending model and additional design-specific information for certain plants. Please clarify whether the piping in your seal leak-off line is capable of withstanding the pressure predicted during an ELAP Page 17 of 20 event according to the revised seal leakage model. If not, please discuss any planned modifications to the seal leak-off piping design and the associated completion timeline.
Attachment 3,       RCP Leakage Rate: The NRC staff SE Review           understands that Westinghouse has Item 7             recently recalculated seal leak-off line pressures under loss of seal cooling events based on a revised seal leakage                 Pending model and additional design-specific information for certain plants. Please clarify whether the piping in your seal leak-off line is capable of withstanding the pressure predicted during an ELAP Page 17 of 20
Alternately, please clarify that the seal leakage rate would remain in an acceptable range if the affected seal leak-off piping were to rupture.Attachment 3, RCP Leakage Rate: Please provide SE Review adequate justification for the seal Item 8 leakage rates calculated according to the Westinghouse seal leakage model that was revised following the issuance of NSAL-14-1.
 
The justification should include a discussion of the following factors: 1. Benchmarking of the seal leakage model against relevant data from tests or operating events, 2. Discussion of the impact on the seal leakage rate due to fluid temperatures greater than 550°F resulting in increased Pending deflection at the seal interface, 3. Clarification whether the second-stage reactor coolant pump seal would remain closed under ELAP conditions predicted by the revised seal leakage model and a technical basis to support the determination, and, 4. Justification that the interpolation scheme used to compute the integrated leakage from the reactor coolant pump seals from a limited number of computer simulations (e.g., three) is realistic or conservative.
event according to the revised seal leakage model. If not, please discuss any planned modifications to the seal leak-off piping design and the associated completion timeline. Alternately, please clarify that the seal leakage rate would remain in an acceptable range if the affected seal leak-off piping were to rupture. , RCP Leakage Rate:         Please provide SE Review     adequate justification for the seal Item 8       leakage rates calculated according to the Westinghouse seal leakage model that was revised following the issuance of NSAL-14-1. The justification should include a discussion of the following factors:
Attachment 4, Battery Sizing Calculations:
: 1. Benchmarking of the seal leakage model against relevant data from tests or operating events,
The staff Item ISE Cl will complete a vendor audit of the Pending 3.2.4.10.A batteries.
: 2. Discussion of the impact on the seal leakage rate due to fluid temperatures greater than 550°F resulting in increased   Pending deflection at the seal interface,
Attachment 4, Off-Site Resources:
: 3. Clarification whether the second-stage reactor coolant pump seal would remain closed under ELAP conditions predicted by the revised seal leakage model and a technical basis to support the determination, and,
The NRC staff Item ISE Cl discussed with the licensee its plan to 3.4.A address minimum capabilities of off-site resources, outlined in the 10 guidelines in NEI 12-06. The licensee indicated that the National SAFER Response Completed" Center generated a generic response to address the guidelines, and coordination of McGuire strategies with the National SAFER Response Centers is ongoing.During the onsite audit, the licensee provided a copy of the generic response Page 18 of 20 and the NRC staff is still in the process of reviewing the document.Attachment 4, Loss of Heat Tracing Effects, NEI 12-06, AQ 35 Section 3.2.2, Guideline 12: The staff is currently reviewing the licensee's Completed**
: 4. Justification that the interpolation scheme used to compute the integrated leakage from the reactor coolant pump seals from a limited number of computer simulations (e.g., three) is realistic or conservative. , Battery Sizing Calculations: The staff Item ISE Cl   will complete a vendor audit of the         Pending 3.2.4.10.A     batteries. , Off-Site Resources: The NRC staff Item ISE Cl   discussed with the licensee its plan to 3.4.A         address minimum capabilities of off-site resources, outlined in the 10 guidelines in NEI 12-06. The licensee indicated that the National SAFER Response         Completed" Center generated a generic response to address the guidelines, and coordination of McGuire strategies with the National SAFER Response Centers is ongoing.
response on the e-Portal.Attachment 4, Shutdown and Refueling Modes: During Item ISE Cl the onsite audit, the licensee provided a 3.2.1.7.A copy of the PWROG interim generic guidance that identified minimal coping strategies for PWRs when an ELAP Pending event occurs in a shutdown mode, and the NRC staff is still in the process of reviewing the document.7 Potential Interim Staff Evaluation Impacts There are no potential impacts to the Interim Staff Evaluation identified at this time.8 References The following references support the updates to the Overall Integrated Plan described in this enclosure.
During the onsite audit, the licensee provided a copy of the generic response Page 18 of 20
: 1. McGuire Nuclear Station Overall Integrated Plan in Response to March 12, 2012 Commission Order to Modify Licenses With Regard to Requirements for Mitigation Strategies for Beyond Design Basis External Events (Order EA-12-049), dated February 28, 2013 (ADAMS Accession No. ML13063A185).2. NRC Order Number EA-12-049, "Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events," dated March 12, 2012 (ADAMS Accession No. ML12054A735).
 
and the NRC staff is still in the process of reviewing the document.
Attachment 4,       Loss of Heat Tracing Effects, NEI 12-06, AQ 35               Section 3.2.2, Guideline 12: The staff is currently reviewing the licensee's                     Completed**
response on the e-Portal.
Attachment 4,       Shutdown and Refueling Modes: During Item ISE Cl         the onsite audit, the licensee provided a 3.2.1.7.A           copy of the PWROG interim generic guidance that identified minimal coping strategies for PWRs when an ELAP                         Pending event occurs in a shutdown mode, and the NRC staff is still in the process of reviewing the document.
7     Potential Interim Staff Evaluation Impacts There are no potential impacts to the Interim Staff Evaluation identified at this time.
8     References The following references support the updates to the Overall Integrated Plan described in this enclosure.
: 1. McGuire Nuclear Station Overall Integrated Plan in Response to March 12, 2012 Commission Order to Modify Licenses With Regard to Requirements for Mitigation Strategies for Beyond Design Basis External Events (Order EA-12-049), dated February 28, 2013 (ADAMS Accession No. ML13063A185).
: 2. NRC Order Number EA-12-049, "Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events," dated March 12, 2012 (ADAMS Accession No. ML12054A735).
: 3. McGuire Nuclear Station, First Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses With Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049), dated August 28, 2013 (ADAMS Accession No. ML13254A204).
: 3. McGuire Nuclear Station, First Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses With Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049), dated August 28, 2013 (ADAMS Accession No. ML13254A204).
: 4. William B. McGuire Nuclear Station, Units 1 and 2-Interim Staff Evaluation Relating to Overall Integrated Plan in Response to Order EA-12-049 (Mitigation Strategies) dated January 16, 2014 (ADAMS Accession No. ML13338A421).
: 4. William B. McGuire Nuclear Station, Units 1 and 2-Interim Staff Evaluation Relating to Overall Integrated Plan in Response to Order EA-12-049 (Mitigation Strategies) dated January 16, 2014 (ADAMS Accession No. ML13338A421).
: 5. McGuire Nuclear Station, Second Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses With Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049), dated February 27, 2014 (ADAMS Accession No.ML14073A462).
: 5. McGuire Nuclear Station, Second Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses With Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049), dated February 27, 2014 (ADAMS Accession No.
: 6. McGuire Nuclear Station, Third Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses With Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049), dated August 27, 2014 (ADAMS Accession No. ML14253A188).Page 19 of 20
ML14073A462).
: 7. NSAL-14-1, Revision 1 "Impact of Reactor Coolant Pump No. 1 Seal Leakoff Piping on Reactor Coolant Pump Seal Leakage During a Loss of All Seal Cooling," dated September 9, 2014.8. WCAP-17601-P, Revision 1 "Reactor Coolant System Response to ELAP for Westinghouse, Combustion Engineering and B&W NSSS Designs", January 2013 (ADAMS Accession No. ML13042A010).
: 6. McGuire Nuclear Station, Third Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses With Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049), dated August 27, 2014 (ADAMS Accession No. ML14253A188).
: 9. NEI letter "EA-12-049 Mitigating Strategies Resolution of Extended Battery Duty Cycles Generic Concern" dated August 27, 2013 (ML13241A186), and NRC endorsement letter dated September 16, 2013 (ADAMS Accession No. ML13241A188).10. EP/ll/A5000/ECA-0.0, Revision 35.11. McGuire Nuclear Station, Units 1 and 2 -Report for the Audit Regarding Implementation of Mitigating Strategies and Reliable Spent Fuel Pool Instrumentation Related to Orders EA-12-049 and EA-12-051, dated October 9, 2014 (ADAMS Accession No.ML14241A454).
Page 19 of 20
: 12. Notification of Full Compliance with Order EA-12-049, "Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond Design Basis External Events" and with Order EA-1 2-051, "Order to Modify Licenses with Regard to Reliable Spent Fuel Pool Instrumentation" -McGuire Nuclear Station Unit 1, dated November 18, 2014 (ADAMS Accession No. ML14335A322).
: 7. NSAL-14-1, Revision 1 "Impact of Reactor Coolant Pump No. 1 Seal Leakoff Piping on Reactor Coolant Pump Seal Leakage During a Loss of All Seal Cooling,"
dated September 9, 2014.
: 8. WCAP-17601-P, Revision 1 "Reactor Coolant System Response to ELAP for Westinghouse, Combustion Engineering and B&W NSSS Designs", January 2013 (ADAMS Accession No. ML13042A010).
: 9. NEI letter "EA-12-049 Mitigating Strategies Resolution of Extended Battery Duty Cycles Generic Concern" dated August 27, 2013 (ML13241A186), and NRC endorsement letter dated September 16, 2013 (ADAMS Accession No. ML13241A188).
: 10. EP/ll/A5000/ECA-0.0, Revision 35.
: 11. McGuire Nuclear Station, Units 1 and 2 - Report for the Audit Regarding Implementation of Mitigating Strategies and Reliable Spent Fuel Pool Instrumentation Related to Orders EA-12-049 and EA-12-051, dated October 9, 2014 (ADAMS Accession No.
ML14241A454).
: 12. Notification of Full Compliance with Order EA-12-049, "Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond Design Basis External Events" and with Order EA-1 2-051, "Order to Modify Licenses with Regard to Reliable Spent Fuel Pool Instrumentation" - McGuire Nuclear Station Unit 1, dated November 18, 2014 (ADAMS Accession No. ML14335A322).
Page 20 of 20}}
Page 20 of 20}}

Revision as of 15:16, 31 October 2019

Fourth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)
ML15075A016
Person / Time
Site: Mcguire, McGuire  Duke Energy icon.png
Issue date: 02/26/2015
From: Capps S
Duke Energy Carolinas, Duke Energy Corp
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
EA-12-049, MNS-15-005
Download: ML15075A016 (25)


Text

Steven D. Capps

£r1I1 L'* Vice President

' DUKE McGuire Nuclear Station ENERGY. Duke Energy MG01VP 112700 Hagers Ferry Road Huntersville, NC 28078 o: 980.875.4805 f: 980.875.4809 Steven.Capps@duke-energy.com 10 CFR 50.4 February 26, 2015 Serial: MNS-15-005 ATTN: Document Control Desk U.S. Nuclear Regulatory Commission Washington, DC 20555 Duke Energy Carolinas, LLC (Duke Energy)

McGuire Nuclear Station (MNS), Units 1 and 2 Docket Nos. 50-369 and 50-370 Renewed License Nos. NPF-9 and NPF-17

Subject:

Fourth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses With Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)

References:

1. Nuclear Regulatory Commission (NRC) Order Number EA-1 2-049, Order Modifying Licensees With Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events, Revision 0, dated March 12, 2012 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML12054A735).
2. NRC Interim Staff Guidance JLD-ISG-2012-01, Compliance with Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation strategies for Beyond-Design-Basis External Events, Revision 0, dated August 29, 2012 (ADAMS Accession No. ML12229A174).
3. NEI 12-06, Diverse and Flexible Coping Strategies (FLEX) Implementation Guide, Revision 0-A, dated August 2012 (ADAMS Accession No. ML12242A378).
4. Duke Energy's Initial Status Report in Response to March 12, 2012, Commission Order Modifying Licenses with Regard To Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order EA-12-049), dated October 29, 2012 (ADAMS Accession No. ML12307A023).
5. McGuire Nuclear Station Overall Integrated Plan in Response to March 12, 2012, Commission Order to Modify Licenses With Regard To Requirements for Mitigation Strategies for Beyond Design Basis External Events (Order EA-12-049),

dated February 28, 2013 (ADAMS Accession No. ML13063A185).

A 21

United States Nuclear Regulatory Commission

-. February 26, 2015 Page 2

6. McGuire Nuclear Station First Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-basis External Events (Order Number EA-12-049)

Dated August 28, 2013 (ADAMS Accession No. ML13254A204).

7. McGuire Nuclear Station Second Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-basis External Events (Order Number EA-12-049) Dated February 27, 2014 (ADAMS Accession No. ML14073A462).
8. McGuire Nuclear Station Third Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-basis External Events (Order Number EA-12-049)

Dated August 27, 2014 (ADAMS Accession No. ML14253A188).

On March 12, 2012, the Nuclear Regulatory Commission (NRC) issued Order EA-12-049 (Reference 1) to Duke Energy. Reference 1 was immediately effective and directs Duke Energy to develop, implement, and maintain guidance and strategies to maintain or restore core cooling, containment, and spent fuel pool cooling capabilities in the event of a beyond-design-basis external event. Specific requirements are outlined in Attachment 2 of Reference 1.

Reference 1 required submission of an initial status report 60 days following issuance of the final interim staff guidance (Reference 2) and an Overall Integrated Plan (OIP) pursuant to Section IV, Condition C. Reference 2 endorses industry guidance document NEI 12-06, Revision 0 (Reference 3) with clarifications and exceptions identified in Reference 2. Reference 4 provided the initial status report regarding mitigation strategies at the Oconee, McGuire and Catawba Nuclear Stations. Reference 5 provided the OIP for MNS.

Reference 1 requires submission of a status report at six-month intervals following submittal of the OIP. Reference 3 provides direction regarding the content of the status reports.

The purpose of this letter is to provide the fourth six-month status report pursuant to Section IV, Condition C.2, of Reference 1. The attached report provides an update of milestone accomplishments since the last status report, including any changes to the compliance method, schedule, or need for relief and the basis, if any.

United States Nuclear Regulatory Commission February 26, 2015 Page 3 This letter contains no new Regulatory Commitments and no revision to existing Regulatory Commitments.

Should you have any questions regarding this submittal, please contact George Murphy at (980) 875-5715.

I declare under penalty of perjury that the foregoing is true and correct. Executed on February 26, 2015.

Sincerely, Steven D. Capps

Enclosure:

MNS Fourth Six-Month Status Report in Response to Order EA-12-049

United States Nuclear Regulatory Commission February 26, 2015 Page 4 xc:

V.M. McCree, Region II Administrator U.S. Nuclear Regulatory Commission Marquis One Tower 245 Peachtree Center Avenue NE, Suite 1200 Atlanta, Georgia 30303-1257 John Boska, Project Manager (OMB)

U.S. Nuclear Regulatory Commission One White Flint North, Mailstop O-8G9A 11555 Rockville Pike Rockville, MD 20852-2738 G. E. Miller, Project Manager (CNS & MNS)

U.S. Nuclear Regulatory Commission 11555 Rockville Pike Mail Stop 8 G9A Rockville, MD 20852-2738 J. Zeiler NRC Senior Resident Inspector McGuire Nuclear Station Justin Folkwein American Nuclear Insurers 95 Glastonbury Blvd., Suite 300 Glastonbury, CT 06033-4453

ENCLOSURE MNS FOURTH SIX MONTH STATUS REPORT IN RESPONSE TO ORDER EA-12-049

MNS Fourth FLEX Six Month Status Report in Response to Order EA 12-049 1 Introduction McGuire developed an Overall Integrated Plan (OIP) (Reference 1 in Section 8), documenting the diverse and flexible strategies (FLEX), in response to NRC Order EA-12-049. The OIP was submitted to the NRC on February 28, 2013. The first six-month update was provided to the NRC on August 28, 2013 (Reference 3 in Section 8). The second six-month update was provided to the NRC on February 27, 2014 (Reference 5 in Section 8). The third six-month update was provided to the NRC on August 27, 2014 (Reference 6 in Section 8). This enclosure provides an update of milestone accomplishments including any changes to the compliance method, schedule, or need for relief/relaxation and the basis, if any, that occurred during the period from July 29, 2014 to January 31, 2015 (hereafter referred to as "the update period").

2 Milestone Accomplishments All remaining Unit 1 milestones were completed during the update period (see Section 3).

Unit 1 is considered in compliance with NRC Order EA-12-049 as of November 15, 2014 (Reference 12 in Section 8).

The following Unit 2 milestones were completed during the update period:

1) Receive all portable FLEX equipment
2) Transmit results of Phase 2 staffing study
3) Regional Response Center in place Page 1 of 20

3 Milestone Schedule Status The following provides an update to Attachment 2 of the Overall Integrated Plan. It provides the activity status of each item, and whether the expected completion date has changed. The dates are planning dates subject to change as design and implementation details are developed.

Target Revised Completion Activity Target Unit 1 Milestones Date Status Completion Date Complete Engineering Change Package and Plan 03/20/2014 Complete NA Work Orders Receive all portable FLEX equipment 05/20/2014 Complete NA Transmit results of Phase 2 staffing study 05/20/2014 Complete NA Complete all FSGs, AOPs, EOPs, OPs 10/31/2014 Complete NA Complete training for all FSGs, AOPs, EOPs, OPs 09/20/2014 Complete NA Complete all Maintenance Procedures 09/20/2014 Complete NA Begin Outage (1EOC23) Fall 2014 Complete NA Storage Plan - Reasonable Protection Facilities Fall 2014 Complete NA Complete Regional Response Center in place 10/19/2014 Complete NA Revised Unit 2 Milestones Completion Activity Target Cpet Status Completion Date Date Complete Engineering Change Package and Plan 03/20/2015 Started Date Not Work Orders Revised Receive all portable FLEX equipment 05/20/2015 Complete NA Transmit results of Phase 2 staffing study 05/20/2015 Complete NA Date Not

-Complete all FSGs, AOPs, EOPs, OPs 06/20/2015 Started Revise Revised Date Not Complete training for all FSGs, AOPs, EOPs, OPs 09/20/2015 Started Revise Revised Date Not Complete all Maintenance Procedures 09/20/2015 Started Revise Revised Not Date Not Begin Outage (2EOC23) Fall 2015 Sat Revise IStarted Revised Page 2 of 20

Revised Unit 2 Milestones Target Activity Target Completion Status Completion Date Date Storage Plan - Reasonable Protection Facilities Fall 2014 Complete* Summer Complete 2015 Regional Response Center in place 10/11/2015 Complete NA

  • Facility construction (three buildings) is complete. Unit 1 compliance was met with the completion and loading of the first two buildings in Fall 2014. Unit 2 compliance with Order EA-12-049 will be met with the loading of the remaining building.

4 Changes to Compliance Method There were no new changes to the compliance method identified during the update period.

5 Need for Relief/Relaxation and Basis for the Relief/Relaxation McGuire expects to comply with the Order implementation date and no relief/relaxation is required at this time contingent on the following:

  • Resolution of issues regarding RCP #1 seal leak-off flow rates and leak-off piping integrity, as identified in NSAL 14-1, Revision 1.

6 Open Items The following sections provide tables summarizing the status of the Open Items:

  • Section 6.a provides the open items identified in the original OIP submitted on February 28, 2013.

" Section 6.b provides a list of open items that were added after February 28, 2013.

  • Section 6.c provides a list of open items related to the Interim Staff Evaluation (ISE) received on January 16, 2014.
  • Section 6.d provides a list of open items related to the NRC Audit Report received on October 9, 2014.

Unit 2 designators have been added to the Open Item descriptions where appropriate since Unit 1 is in compliance with the Order.

Page 3 of 20

Section 6.a. Open Items Documented in the Overall Integrated Plan.

Note: items marked with an asterisk (*) are designed and awaiting implementation.

Note: items marked with a double asterisk (**) have been completed during this update period.

Overall Integrated Plan Open Item Status 1 Implement (Units 1 and 2) plant modification: Assured Air to the TDAFWP FCVs and SG PORVs (Current Unit 1 Started*

configuration is based on 3rd Six Month Update Change #2) 2 Implement (Unit 2) plant modification:

Assured Water Supply to the TDAFWPs 3 Implement (Unit 2) plant modification:

SFP Wide-Range Level Instrumentation 4 Implement plant modification: UHF Completed**

Communication System Upgrades 5 Implement (Unit 2) plant modification: Started*

Process Connections 6 Implement (Unit 2) plant modification:

Permanent Connections for Portable Started*

Electrical Equipment 7 Implement plant modification: FLEX Completed Storage Facilities 8 Implement (Unit 2) plant modification:

Submersible Ground Water Sump Pump 9 Implement (Unit 2) plant modification: Started*

FLEX Strategy Implementation 10 Implement (Unit 2) plant modification: "B" Started*

RN to CA Pump Suction Re-route 11 Implement plant modification: Install Emergency Hardhat Light Storage Boxes Completed and Hardhat Hooks 12 A staffing Phase 2 study will be performed in accordance with NEI 12-01 to verify that alt actions can be taken in accordance with the timeline. Time constraints shown in Attachment 1A will Completed**

be validated to be reasonable as the strategy is finalized.

Page 4 of 20

13 An analysis was performed in Duke Energy Calculation MCC-1223.31 0012 that indicates that flooding will not occur for at least 48 hours5.555556e-4 days <br />0.0133 hours <br />7.936508e-5 weeks <br />1.8264e-5 months <br />. This analysis will be revised to demonstrate that this Completed time remains unaffected even if potential sources of water from Auxiliary Building or Turbine Building flooding are considered.

14 A calculation will be performed to demonstrate that sufficient negative reactivity can be added through use of a pump and a reactor coolant system vent Completed path to achieve xenon free cool down in accordance with the PWROG FSG guidelines.

15 Complete vital battery area room heatup aid (see open item #48) hydrogen Completed.

accumulation calculation to determine if Description of this Open Item revised portable fans or HVAC units may be per Open Item 48 required, and timeframe for deployment.

16 Complete a calculation to determine when elevated interior doghouse temperatures adversely impact the FLEX Completed strategy and to evaluate methods for mitigation.

17 An evaluation will be performed to determine how long raw water can be used to supply SGs without excessively affecting SG capability to remove heat and provide steam to the TDAFW pump.

This will help determine when Phase 3 equipment may be needed to assist in providing cleaner water sources.

18 MNS will evaluate the need to provide freeze protection for critical Completed instrumentation and exposed FLEX connections.

19 Methods will be initiated to circulate and cool air in lower containment sub compartments to prevent any adverse impact on critical instrumentation. The response time is based on engineering Completed judgment and will be confirmed by analysis.

Page 5 of 20

20 Deployment routes will be established and are expected to be utilized to transport FLEX equipment to the deployment areas. The identified paths and deployment areas will be accessible Completed**

during all modes of operation. This deployment strategy will be included within an administrative program in order to keep pathways clear or actions to clear the pathways.

21 MNS will implement programmatic controls in accordance with NEI 12-06.

Procedures and guidelines will be reviewed and revised and/or generated Completed**

as required to address additional programmatic controls as a result of FLEX requirements.

22 Equipment associated with FLEX mitigation strategies will be procured as commercial equipment with design, Completed" storage, maintenance, testing, and configuration control in accordance with NEI 12-06 Section 11.1.

23 Installed structures, systems and components pursuant to 10 CFR 50.63(a) will continue to meet augmented Completed guidelines of Regulatory Guide (RG) 1.155, Station Blackout.

24 The unavailability of equipment and applicable connections that directly perform a FLEX mitigation strategy will Completed" be managed using plant equipment control guidelines developed in accordance with NEI 12-06 Section 11.5.

25 Programs and processes will be established (Unit 2) to ensure that personnel proficiency in the mitigation of Started beyond-design-basis events is developed and maintained in accordance with NEI 12-06 Section 11.6.

26 The FLEX strategies and basis will be maintained in overall FLEX basis documents. Completed**

Page 6 of 20

27 Existing plant configuration control 4 documents will be modified to ensure that changes to the plant design, physical plant layout, roads, buildings, and miscellaneous structures will not Completed**

adversely impact the approved FLEX strategies in accordance with NEI 12-06 Section 11.8.

28 Training will be initiated through the Systematic Approach to Training (SAT) process. Training will be developed and provided to all involved plant personnel Unit 1 Completed**

based on any procedural changes or new procedures developed to address and Unit 2 Started identify FLEX activities. Applicable training will be completed prior to the implementation of FLEX.

29 The industry will establish two Regional Response Centers (RRCs) to support Completed" utilities during beyond-design-basis events.

30 The N+1 FLEX storage facilities will be designed in accordance with ASCE 7-10, Minimum Design Loads for Buildings and Other Structures. The FLEX storage facilities will be designed in accordance with ASCE 7-10, to withstand the maximum anticipated hurricane and Completed tornado winds as outlined in NEI 12-06.

The FLEX buildings will be located in accordance with NEI 12-06 Section 7.3.1 to prevent damage to more than one of the three facilities due to tornado missiles.

31 FLEX storage facilities will be located above any potential site flood level, and/or the effects of localized flooding Completed will be evaluated in the FLEX facility design and equipment deployment.

32 Debris removal/remediation equipment and procedures will be provided to Completed support FLEX equipment deployment.

33 Snow and ice removal/remediation equipment and procedures will be provided to support FLEX equipment Completed deployment.

Page 7 of 20

34 FLEX equipment will be capable of operation under extreme temperatures, and suitably maintained to ensure standby readiness. FLEX storage facilities will be designed to Completed accommodate maximum snow and ice loading. FLEX storage facilities will be vented to maintain acceptable temperature.

35 An evaluation will be performed to ensure that the 300 gpm pump is capable of adequate flow and pressure to support Completed feed and bleed core cooling in typical Mode 5 and Mode 6 configurations.

36 Since the overall FLEX strategy is aimed at preventing core damage, the engineering change process will drive out an evaluation to prioritize operator actions associated with containment isolation as time allows. For example, Completed the containment isolations to the Containment Ventilation Unit Condensate Drain Tank (VUCDT) will be closed first since this path connects containment atmosphere directly to the Auxiliary Building.

37 An analysis will be performed to validate that containment spray for temperature/pressure control is not required over the long term. If the long term containment analysis determines that containment temperature and/or pressure will reach unacceptable levels Completed over the long term, connections will be installed for containment spray mitigating strategies and will be used with the portable diesel driven pumps to supply water from the UHS to the connections located in the Auxiliary Building.

38 Fans in containment that circulate air will be restored as required to cool the cubicle areas and to prevent the increase in temperature from having an adverse impact on essential instrumentation. The Completed engineering change process will drive out an evaluation to determine the appropriate timing of these actions.

Page 8 of 20

39 Evaluate other long term strategies for cooling containment such as circulating Completed the air volume in the annulus.

40 In order to prevent or mitigate this inevitability [i.e., vital battery depletion]:

1. Portable power distribution equipment will be used to repower the vital batteries, or
2. An alternate strategy to deploy portable generators and cables will be developed to directly reestablish power to Completed the power supplies in the 7300 cabinets thereby re-powering the instrumentation loops, or
3. An alternate strategy to utilize handheld instruments will be developed to tap into the instrument loops locally to monitor essential parameters.

41 An analysis was completed to demonstrate that adequate control room cooling would be available if action was Completed taken to open various doors at around 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> after the event occurs. This action will be incorporated into procedures.

42 An evaluation will be performed to determine diesel fuel, gasoline and two- Completed cycle oil requirements for Phase 1 and Phase 2 portable equipment.

43 Analysis will be performed to determine Completed commodities requirements.

44 Evaluate SFP to ensure predicted makeup water dilution rates in the Spent Completed Fuel Pools for the coping strategies described herein are bounded.

45 Analysis will be performed to determine radiation protection equipment Completed requirements.

46 These instruments [i.e., Essential Instrumentation and Vital I&C] will be used in the FSGs in accordance with the PWROG guidance. Setpoint uncertainty Completed analyses will be developed in accordance with PWROG guidance.

Page 9 of 20

47 A portable battery pack with inverter is also being evaluated for use. The battery pack would be rapidly deployed for use to close the CLA motor-operated valves Completed (MOVs) outside of containment penetration without reliance on the valve's limit or torque switches or the valve's relay circuitry.

Section 6.b. Open Items added after February 28, 2013 Note: status of items marked with a double asterisk (**) have been completed during this update period.

First Six Month Update Status New Open Items 48 Complete vital battery area room heatup calculation to determine if portable fans or HVAC units may be required, and the Completed timeframe for deployment. (Reference open item 15) 49 To facilitate the Phase 2 FLEX mitigation response, the high and low pressure make-up pumps for the Reactor Coolant System for each Unit are currently planned to be pre-staged in the Auxiliary Building, near the FLEX connection points. As these areas are within a Category I Completed seismic structure, no spares will be stored in the FLEX buildings for deployment, since "N" pieces of FLEX equipment are already deployed and protected. Per NEI 12-06 guidance, this equipment will be evaluated for seismic ruggedness.

50 Access to connection points for the Phase 2 FLEX mitigation response will be through the north end of the McGuire Auxiliary Building, an area which is not seismically designed. Section 5.3.2 part 2 of the NEI 12-06 Guidance Document states: "At Completed least one connection point of FLEX equipment will only require access through seismically robust structures. This includes both the connection point and any areas that plant operators will have to access to deploy or control the capability." Evaluate Page 10 of 20

Auxiliary Building access points for possible qualification of seismic ruggedness.

51 Reference 01 #30. NEI 12-06 Guidance clarification documented in NEI FLEX Guidance Inquiry no. 2013-07 identifies that FLEX buildings designed for hurricane wind speeds and using diverse locations Completed per Section 7.3.1 part (c) are protected from both tornado and hurricane generated missiles. Validate strategy with NEI.

Second Six Month Update New Open Items Status 52 McGuire to confirm that the FLEX strategy station battery run-time was calculated in accordance with the IEEE-485 methodology using manufacturer discharge test data applicable to the licensee's FLEX strategy as outlined in the NEI white paper on Extended Battery Duty Cycles. The detailed licensee calculations, supporting vendor discharge test data, FLEX strategy battery load Completed profile, and other inputs/initial conditions required by IEEE-485 will be available on the licensee's web portal for documents and calculations. The time margin between the calculated station battery run-time for the FLEX strategy and the expected deployment time for FLEX equipment to supply the dc loads is 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br />.

53 See ISE Open Item 3.2.1.8.A. The PWROG submitted to NRC a position paper, dated August 15, 2013, which provides test data regarding boric acid mixing under single-phase natural circulation conditions and outlined applicability conditions intended to ensure that boric acid addition and mixing would Completed occur under conditions similar to those for which boric acid mixing data is available.

McGuire to confirm its intent to abide by the generic approach discussed above, and address the clarifications in the NRC endorsement letter dated January 8, 2014.

Page 11 of 20

54 NEI submitted the EPRI Report 3002000623 entitled "Nuclear Maintenance Applications Center:

Preventative Maintenance Basis for FLEX Equipment" on October 23, 2013. Completed McGuire to confirm its intent to abide by the generic approach discussed above in developing FLEX equipment maintenance and testing programs.

55 See ISE Confirmatory Item 3.2.1.7.A.

McGuire to confirm that the guidance in NEI position paper, "Position Paper:

Shutdown/Refueling Modes," will be Completed followed in the Mitigation Strategies for BDBEEs occurring during Shutdown/Refueling Modes.

56 McGuire to confirm viability of proposed long-term ELAP Phase 3 recovery strategy:

Modes 1-4: rely on passive ice condenser response and repowered containment/annulus ventilation fan cooling to prevent Pressurizer/Steam Generator level indication reference legs from flashing during RCS cooldown/depressurization, and realign/restart RHR system (and support Completed**

systems). Manage containment pressure as necessary.

Modes 5-6: rely on passive ice condenser response and deploy portable FLEX pump within timeframe necessary to manage RCS boration/inventory. Manage containment pressure as necessary and realign/restart RHR system (and support systems).

Third Six Month Update Status New Open Items 57 NSAL 14-1: Upon completion of the vendor evaluation of the RCP seal leak-off flow with the installed Number 1 Seal Leak-off orifice, identify the path forward for meeting the FLEX Mitigation Strategy Completed**

Analysis assumptions based on the evaluated leak-off flow.

Page 12 of 20

New Open Items Status added this Update None. N/A Section 6.c. Interim Staff Evaluation Open and Confirmatory Items Note: status of items marked with a double asterisk (**) have been completed during this update period.

Interim Staff Evaluation Status Open Item 3.2.1.8.A The PWROG submitted to NRC a position paper, dated August 15, 2013, which provides test data regarding boric acid mixing under single-phase natural circulation conditions and outlined applicability conditions intended to ensure that boric acid addition and mixing would occur under conditions similar to those for which boric acid Completed mixing data is available.

During the audit process, the licensee informed the NRC staff of its intent to abide by the generic approach discussed above. The licensee should address the clarifications in the NRC endorsement letter dated January 8, 2014.

NMI, Interim Staff Evaluation Status Confirmatory Items 3.1.1.2.A Deployment of FLEX equipment - On page 57 of its Integrated Plan, in the chart identifying Pressurized Water Reactor (PWR) Portable Equipment Phase 2, the licensee lists (9) 9x12 trailers used to store and deploy power Completed equipment, but does not list tow vehicles.

Confirm abilities to move FLEX equipment and the level of protection afforded the means to move.

3.1.1.3.A Procedural interfaces, seismic - Confirm evaluation that shows time is available to deploy ground water sump pumps as Completed needed in critical locations in addition to the vicinity of the TDAFW pump.

Page 13 of 20

3.1.1.4.A Off Site Resources, seismic - Confirm development of the MNS playbook as well as identification of the local Completed**

Assembly Area and routes to the plant.

3.1.3.1.A Protection of FLEX equipment, high winds - Site specific data to justify the assumed tornado width of 1200 feet will be required to confirm the final locations Completed of the FLEX storage facilities conform to NEI 12-06 guidance.

3.1.5.2.A Deployment of FLEX equipment, high temperatures - Confirm that the storage facilities will be designed for extreme temperature ranges including concerns Completed for expansion of sheet metal, swollen door seals, etc.

3.2.1.A RCS Cooling and Heat Removal, and RCS Inventory Control Strategies -

Justify the use of the analysis from Sections 5.2.1 and 5.2.2 of WCAP-17601-P by identifying and evaluating the Completed important parameters and assumptions demonstrating that they are representative of MNS and appropriate for simulating the ELAP transient.

3.2.1.1 .A Computer Code Used for ELAP Analysis

- Confirm that reliance on the NOTRUMP code for the ELAP analysis of Westinghouse plants is limited to the flow conditions prior to reflux Completed condensation initiation. This includes specifying an acceptable definition for reflux condensation cooling.

3.2.1.2.A RCP seals - Confirm that the RCP seal initial maximum leakage rate used in the analysis is greater than or equal to the upper bound expectation for the ELAP event (21 gpm/seal) discussed in the Completed PWROG white paper addressing the RCP seal leakage for Westinghouse plants.

3.2.1.2.B RCP seals - In some plant designs, such as those with 1200 to 1300 psia SG design pressures and no accumulator Completed backing of the main steam system power-operated relief valve (PORV)

Page 14 of 20

actuators, the cold legs could experience temperatures as high as 580 degrees F before cooldown commences. This is beyond the qualification temperature (550 degrees F) of the O-rings used in the RCP seals. For those Westinghouse designs, a discussion of the information (including the applicable analysis and relevant seal leakage testing data) should be provided to justify that (1) the integrity of the associated O-rings will be maintained at the temperature conditions experienced during the ELAP event, and (2) the seal leakage rate of 21 gpm/seal used in the ELAP is adequate and acceptable.

-4 .4 3.2.1.2.C RCP seals - If the seals are changed to the newly designed Generation 3 SHIELD seals, or non-Westinghouse seals, the acceptability of the use of the newly designed Generation 3 SHIELD seals, or non-Westinghouse seals should Completed be addressed, and the RCP seal leakages rates for use in the ELAP analysis should be provided with acceptable justification.

3.2.1.3.A Decay Heat - Values of the following key parameters used to determine the decay heat should be specified and the adequacy of the values evaluated: (1) initial power level, (2) fuel enrichment, (3) fuel burnup, (4) effective full power Completed operating days per fuel cycle, (5) number of fuel cycles, if hybrid fuels are used in the core, and (6) fuel characteristics are based on the beginning of the cycle, middle of the cycle, or end of the cycle.

3.2.1.4.A Initial Values for Key Plant Parameters and Assumptions - Confirm results and appropriate actions subsequent to Westinghouse supplying McGuire with Completed additional information regarding the key plant parameters and assumptions.

3.2.1.7.A Confirm that MNS will abide by the generic resolution for shutdown and refueling concerns. Completed**

Page 15 of 20

3.2.3.A Containment Functions Strategies -

I Confirm completion of the long term containment analysis and appropriate Completed actions.

3.2.4.4.A Lighting and Communications -

Confirmation will be required that upgrades to the site's communications Completed**

systems have been completed.

3.2.4.6.A Ventilation for Equipment Cooling and Personnel Habitability - Room heat up response for specific MNS areas are completed but need to be evaluated by Completed NRC personnel. Confirm completion of evaluation and appropriate actions.

3.2.4.7.A Water Sources - Confirm that plant procedures specify that a flow path is promptly established for makeup flow to the steam generators and identify backup water sources in order of intended use; Completed and that plant procedures/guidance should specify clear criteria for transferring to the next preferred source of water.

3.2.4.8.A Electrical Power Sources - Confirm completion of Flex DG sizing calculation Completed and appropriate actions.

3.2.4.9.A Portable Equipment Fuel - Confirm completion of evaluation and appropriate Completed actions to assess long-term FLEX equipment fuel oil requirements.

3.2.4.10.A The battery sizing calculation needs to be verified when revised to show that dc power for 2 of 4 channels can be Completed maintained for 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> without a charger. in place.

3.2.4.10.B Load Reduction to Conserve DC Power -

Confirm that ELAP procedures/guidance will direct operators to conserve dc power Completed during the event by stripping nonessential loads as soon as practical.

3.4.A Offsite Resources - Confirm NEI 12-06, Section 12.2, Guidelines 2 through 10 Completed**

are addressed with the RRC.

Page 16 of 20

Section 6.d. NRC Onsite Mitigation Strategy Audit Report Note: status of items marked with a double asterisk (**) have been completed during this update period.

Note: status of items marked "Pending" are industry issues in the process of being addressed by NRC or via the PWROG. Site-specific evaluation of these items has been completed.

Open Item # Audit Report Open Item Description Status , Off-Site Resources: The NRC staff Item ISE CI requests that the licensee provide a copy Completed**

3.1.1.4.A of the playbook once it's finalized. , Lighting and Communications: The NRC Item ISE CI requested that the licensee provide 3.2.4.4.A confirmation of the modifications to the Completed**

communications systems once completed. , Process Connections: The NRC staff Licensee requested that the licensee provide a Identified OIP summary of the plant modifications to Completed" Open Item 5 implement the FLEX strategy for staff review. , Containment Functions Strategies: The Item ISE CI licensee has provided a response to the 3.2.3.A question on the ePortal; however, the Completed**

staff requests that the calculations be posted on the ePortal. , Portable Equipment Fuel: Provide Item ISE CI information on the fuel quality from the 3.2.4.9.A trucks that will be onsite to initially refuel Completed**

FLEX equipment. , NOTRUMP Code: The staff performed a SE Review confirmatory ELAP analysis using Item 5 TRACE and is currently reviewing the results between TRACE and Pending NOTRUMP. In addition, the staff has requested a copy of the PWROG application of NOTRUMP white paper.

Attachment 3, RCP Leakage Rate: The NRC staff SE Review understands that Westinghouse has Item 7 recently recalculated seal leak-off line pressures under loss of seal cooling events based on a revised seal leakage Pending model and additional design-specific information for certain plants. Please clarify whether the piping in your seal leak-off line is capable of withstanding the pressure predicted during an ELAP Page 17 of 20

event according to the revised seal leakage model. If not, please discuss any planned modifications to the seal leak-off piping design and the associated completion timeline. Alternately, please clarify that the seal leakage rate would remain in an acceptable range if the affected seal leak-off piping were to rupture. , RCP Leakage Rate: Please provide SE Review adequate justification for the seal Item 8 leakage rates calculated according to the Westinghouse seal leakage model that was revised following the issuance of NSAL-14-1. The justification should include a discussion of the following factors:

1. Benchmarking of the seal leakage model against relevant data from tests or operating events,
2. Discussion of the impact on the seal leakage rate due to fluid temperatures greater than 550°F resulting in increased Pending deflection at the seal interface,
3. Clarification whether the second-stage reactor coolant pump seal would remain closed under ELAP conditions predicted by the revised seal leakage model and a technical basis to support the determination, and,
4. Justification that the interpolation scheme used to compute the integrated leakage from the reactor coolant pump seals from a limited number of computer simulations (e.g., three) is realistic or conservative. , Battery Sizing Calculations: The staff Item ISE Cl will complete a vendor audit of the Pending 3.2.4.10.A batteries. , Off-Site Resources: The NRC staff Item ISE Cl discussed with the licensee its plan to 3.4.A address minimum capabilities of off-site resources, outlined in the 10 guidelines in NEI 12-06. The licensee indicated that the National SAFER Response Completed" Center generated a generic response to address the guidelines, and coordination of McGuire strategies with the National SAFER Response Centers is ongoing.

During the onsite audit, the licensee provided a copy of the generic response Page 18 of 20

and the NRC staff is still in the process of reviewing the document.

Attachment 4, Loss of Heat Tracing Effects, NEI 12-06, AQ 35 Section 3.2.2, Guideline 12: The staff is currently reviewing the licensee's Completed**

response on the e-Portal.

Attachment 4, Shutdown and Refueling Modes: During Item ISE Cl the onsite audit, the licensee provided a 3.2.1.7.A copy of the PWROG interim generic guidance that identified minimal coping strategies for PWRs when an ELAP Pending event occurs in a shutdown mode, and the NRC staff is still in the process of reviewing the document.

7 Potential Interim Staff Evaluation Impacts There are no potential impacts to the Interim Staff Evaluation identified at this time.

8 References The following references support the updates to the Overall Integrated Plan described in this enclosure.

1. McGuire Nuclear Station Overall Integrated Plan in Response to March 12, 2012 Commission Order to Modify Licenses With Regard to Requirements for Mitigation Strategies for Beyond Design Basis External Events (Order EA-12-049), dated February 28, 2013 (ADAMS Accession No. ML13063A185).
2. NRC Order Number EA-12-049, "Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events," dated March 12, 2012 (ADAMS Accession No. ML12054A735).
3. McGuire Nuclear Station, First Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses With Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049), dated August 28, 2013 (ADAMS Accession No. ML13254A204).
4. William B. McGuire Nuclear Station, Units 1 and 2-Interim Staff Evaluation Relating to Overall Integrated Plan in Response to Order EA-12-049 (Mitigation Strategies) dated January 16, 2014 (ADAMS Accession No. ML13338A421).
5. McGuire Nuclear Station, Second Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses With Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049), dated February 27, 2014 (ADAMS Accession No.

ML14073A462).

6. McGuire Nuclear Station, Third Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses With Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049), dated August 27, 2014 (ADAMS Accession No. ML14253A188).

Page 19 of 20

7. NSAL-14-1, Revision 1 "Impact of Reactor Coolant Pump No. 1 Seal Leakoff Piping on Reactor Coolant Pump Seal Leakage During a Loss of All Seal Cooling,"

dated September 9, 2014.

8. WCAP-17601-P, Revision 1 "Reactor Coolant System Response to ELAP for Westinghouse, Combustion Engineering and B&W NSSS Designs", January 2013 (ADAMS Accession No. ML13042A010).
9. NEI letter "EA-12-049 Mitigating Strategies Resolution of Extended Battery Duty Cycles Generic Concern" dated August 27, 2013 (ML13241A186), and NRC endorsement letter dated September 16, 2013 (ADAMS Accession No. ML13241A188).
10. EP/ll/A5000/ECA-0.0, Revision 35.
11. McGuire Nuclear Station, Units 1 and 2 - Report for the Audit Regarding Implementation of Mitigating Strategies and Reliable Spent Fuel Pool Instrumentation Related to Orders EA-12-049 and EA-12-051, dated October 9, 2014 (ADAMS Accession No.

ML14241A454).

12. Notification of Full Compliance with Order EA-12-049, "Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond Design Basis External Events" and with Order EA-1 2-051, "Order to Modify Licenses with Regard to Reliable Spent Fuel Pool Instrumentation" - McGuire Nuclear Station Unit 1, dated November 18, 2014 (ADAMS Accession No. ML14335A322).

Page 20 of 20