| number = ML15098A284
| number = ML15098A284
| issue date = 04/07/2015
| issue date = 04/07/2015
| title = South Texas Project, Units 1 and 2, Notification of Evaluations of Changes, Tests and Experiments and Permanent Plant Modification (05000498/2015007 and 05000499/2015007) and Request for Information
| title = Notification of Evaluations of Changes, Tests and Experiments and Permanent Plant Modification (05000498/2015007 and 05000499/2015007) and Request for Information
| author name = Farmholtz T R
| author name = Farmholtz T
| author affiliation = NRC/RGN-IV/DRS/EB-1
| author affiliation = NRC/RGN-IV/DRS/EB-1
| addressee name = Koehl D L
| addressee name = Koehl D
| addressee affiliation = South Texas Project Nuclear Operating Co
| addressee affiliation = South Texas Project Nuclear Operating Co
| docket = 05000498, 05000499
| docket = 05000498, 05000499
Line 14: Line 14:
| page count = 6
| page count = 6
}}
}}
See also: [[followed by::IR 05000498/2015007]]
See also: [[see also::IR 05000498/2015007]]


=Text=
=Text=
{{#Wiki_filter:UNITED STATES
{{#Wiki_filter:UNITED STATES
NUCLEAR REGULATORY COMMISSION REGION IV 1600 E. LAMAR BLVD. ARLINGTON, TX 76011-4511
                            NUCLEAR REGULATORY COMMISSION
   
                                                REGION IV
April 7, 2015  
                                          1600 E. LAMAR BLVD.
                                        ARLINGTON, TX 76011-4511
                                          April 7, 2015
Mr. Dennis L. Koehl
President and CEO/CNO
STP Nuclear Operating Company
P.O. Box 289
Wadsworth, TX 77483
SUBJECT:        SOUTH TEXAS PROJECT, UNITS 1 AND 2 - NOTIFICATION OF
                EVALUATIONS OF CHANGES, TESTS, AND EXPERIMENTS, AND
                PERMANENT PLANT MODIFICATIONS INSPECTION (05000498/2015007 and
                05000499/2015007) AND REQUEST FOR INFORMATION
Dear Mr. Koehl:
The purpose of this letter is to notify you that U.S. Nuclear Regulatory Commission (NRC) staff
will conduct the baseline inspection of changes, tests, experiments, and permanent plant
modifications at your South Texas Project, Units 1 and 2, from June 1-5, 2015, and June 15-20,
2015. The inspection will consist of three reactor inspectors from the NRCs Region IV office for
two weeks. The inspection will be conducted in accordance with NRC Inspection
Procedure 71111.17T, Evaluations of Changes, Tests, and Experiments and Permanent Plant
Modifications.
Experience has shown that this inspection is resource intensive for both the NRC inspectors
and your staff. In order to minimize the impact to your onsite resources and to ensure a
productive inspection, we have enclosed a request for documents needed for this inspection.
Please note that the documents are requested to be provided by May 26, 2015. Upon review of
these documents, the inspectors will select additional documentation for review upon arrival. It
is important that all of these documents are up-to-date and complete in order to minimize the
number of additional documents requested during the preparation and/or the onsite portions of
the inspection.
We have discussed the schedule for these inspection activities with your staff and understand
that our regulatory contact for this inspection will be Rafael Gonzalez of your licensing
organization. If there are any questions about this inspection or the material requested, please
contact the lead inspector, Gerond George, by telephone at 817-200-1562 or by e-mail at
Gerond.George@nrc.gov.
This letter does not contain new or amended information collection requirements subject to the
Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information collection
requirements were approved by the Office of Management and Budget, Control
Number 3150 0011. The NRC may not conduct or sponsor, and a person is not required to
respond to, a request for information or an information collection requirement unless the


D. Koehl                                          -2-
requesting document displays a currently valid Office of Management and Budget Control
Mr. Dennis L. Koehl President and CEO/CNO
Number.
STP Nuclear Operating Company
In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter and its
enclosure will be available electronically for public inspection in the NRC Public Document
Room or from the Publicly Available Records (PARS) component of NRC's document system
(ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-
rm/adams.html (the Public Electronic Reading Room).
                                              Sincerely,
                                                /RA/
                                              Thomas R. Farnholtz, Chief
                                              Engineering Branch 1
                                              Division of Reactor Safety
Dockets: 50-498; 50-499
Licenses: NPF-76; NPF-80
Enclosure:
      Evaluations of Changes, Tests, and Experiments
      and Permanent Plant Modifications Inspection
      Request for Information
Electronic Distribution to the South Texas Project


P.O. Box 289
                                      Request for Information
  Evaluations of Changes, Tests, and Experiments and Permanent Plant Modifications
                                              Inspection
                                        South Texas Project
Inspection Report:              05000498/2015007 and 05000499/2015007
Onsite Inspection Dates:        June 1-5, 2015
                                June 15-20, 2015
Inspection Procedure:          IP 71111.17T, Evaluations of Changes, Tests, and Experiments
                                and Permanent Plant Modifications
Lead Inspector:                Gerond A. George, Senior Reactor Inspector
Information Requested for the In-Office Preparation Week
The following information should be sent to the Region IV office in hard copy or electronic
format (preferred) by May 26, 2015, to the attention of Gerond A. George. We request that you
categorize the documents in your response with the numbered list below. If only hard copies of
the requested documents are available or if the electronic format is too large, please inform the
lead inspector and provide the documents on the first day of the onsite inspection. Also, the
inspectors will select specific items from the information requested below and request from your
staff additional documents needed during the onsite inspection weeks. We ask that the specific
items requested be available and ready for review on the first day of inspection. If you have any
questions regarding this information request, please contact the lead inspector as soon as
possible.
    1. Procedure(s) for conducting 10 CFR 50.59 screenings and evaluations.
    2. A list with descriptions of all 10 CFR 50.59 screenings (or equivalent) performed since
        the last triennial modification inspection that did not result in an evaluation.
    3. A list with descriptions of all 10 CFR 50.59 evaluations performed the last triennial
        modification inspection that did not result in an application for license amendment.
    4. A list with descriptions of all corrective action documents related to 10 CFR 50.59
        screenings and evaluations since the last triennial modification inspection.
    5. A list of personnel qualified to prepare 10 CFR 50.59 screenings and/or evaluations,
        including qualification dates.
    6. A list of personnel qualified to review and approve 10 CFR 50.59 screenings and/or
        evaluations, including qualification dates.
    7. Procedure(s) for implementing permanent plant modifications.
    8. A list with descriptions of all permanent plant modifications since the last triennial
        modification inspection.
                                                  -1-                                    Enclosure


Wadsworth, TX  77483
    9. A list with descriptions of all corrective action documents related to permanent plant
SUBJECT: SOUTH TEXAS PROJECT, UNITS 1 AND 2 - NOTIFICATION OF EVALUATIONS OF CHANGES, TESTS, AND EXPERIMENTS, AND
        modifications since the last triennial modification inspection.
PERMANENT PLANT MODIFICATI
    10. Current revisions of the Technical Specifications and Bases and the Updated Final
ONS INSPECTION (05000498/2015007 and 05000499/2015007) AND REQUEST FOR INFORMATION
        Safety Analysis Report.
Dear Mr. Koehl:  
Note: Descriptions should be brief but of sufficient detail to ensure that inspectors can
determine the safety and/or risk significance of the screenings, evaluations, and modifications.
Note: For this inspection, permanent plant modifications include permanent plant changes,
design changes, set point changes, procedure changes, equivalency evaluations, suitability
analyses, calculations, and commercial grade dedications.
Inspector Contact Information:
Gerond A. George                  Jonathan Braisted                  Inspector Number 3 to be
Senior Reactor Inspector          Reactor Inspector                  named at later date.
817-200-1562                      817-200-1194
Gerond.George@nrc.gov              Jonathan.Braisted@nrc.gov
Mailing Address:
U.S. NRC, Region IV
Attn: Gerond A. George
1600 East Lamar Blvd.
Arlington, TX 76011-4125
                                                    -2-


D. Koehl                                         -2-
The purpose of this letter is to notify you that U.S. Nuclear Regulatory Commission (NRC) staff will conduct the baseline inspection of changes, tests, experiments, and permanent plant
requesting document displays a currently valid Office of Management and Budget Control
modifications at your South Texas Project, Units 1 and 2, from June 1-5, 2015, and June 15-20, 2015.  The inspection will consist of three reactor inspectors from the NRC's Region IV office for two weeks.  The inspection will be conducted in accordance with NRC Inspection
Number.
Procedure 71111.17T, "Evaluations of Changes, Tests, and Experiments and Permanent Plant
In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter and its
Modifications." 
enclosure will be available electronically for public inspection in the NRC Public Document
 
Room or from the Publicly Available Records (PARS) component of NRC's document system
Experience has shown that this inspection is resource intensive for both the NRC inspectors and your staff.  In order to minimize the impact to your onsite resources and to ensure a
(ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-
productive inspection, we have enclosed a request for documents needed for this inspection. 
rm/adams.html (the Public Electronic Reading Room).
Please note that the documents are requested to be provided by May 26, 2015.  Upon review of
                                                  Sincerely,
these documents, the inspectors will select additional documentation for review upon arrival.  It
                                                  /RA/
is important that all of these documents are up-to-date and complete in order to minimize the number of additional documents requested during the preparation and/or the onsite portions of the inspection.
                                                  Thomas R. Farnholtz, Chief
 
                                                  Engineering Branch 1
                                                  Division of Reactor Safety
We have discussed the schedule for these inspection activities with your staff and understand
Dockets: 50-498; 50-499
that our regulatory contact for this inspection will be Rafael Gonzalez of your licensing organization.  If there are any questions about this inspection or the material requested, please contact the lead inspector, Gerond George, by telephone at 817-200-1562 or by e-mail at
Licenses: NPF-76; NPF-80
Gerond.George@nrc.gov.
Enclosure:
 
Evaluations of Changes, Tests, and Experiments
   and Permanent Plant Modifications Inspection
This letter does not contain new or amended information collection requirements subject to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.).  Existing information collection requirements were approved by the Office of Management and Budget, Control
   Request for Information
Number 3150 0011.  The NRC may not conduct or sponsor, and a person is not required to respond to, a request for information or an information collection requirement unless the 
Electronic Distribution to South Texas Project
D. Koehl - 2 -
  requesting document displays a currently valid Office of Management and Budget Control Number.
In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its  
 
enclosure will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system  
(ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).  
Sincerely, /RA/ Thomas R. Farnholtz, Chief  
Engineering Branch 1  
Division of Reactor Safety  
 
Dockets:   50-498; 50-499  
Licenses: NPF-76; NPF-80  
 
Enclosure:   Evaluations of Changes, Tests, and Experiments  and Permanent Plant Modifications Inspection 
 
Request for Information
Electronic Distribution to the South Texas Project
 
  - 1 - Enclosure 
Request for Information
Evaluations of Changes, Tests, and Experiments and Permanent Plant Modifications
Inspection
South Texas Project
Inspection Report:   05000498/2015007 and 05000499/2015007
 
Onsite Inspection Dates: June 1-5, 2015  June 15-20, 2015
Inspection Procedure: IP 71111.17T, "Evaluations of Changes, Tests, and Experiments and Permanent Plant Modifications"
Lead Inspector:  Gerond A. George, Senior Reactor Inspector
  Information Requested for the In-Office Preparation Week
  The following information should be sent to the Region IV office in hard copy or electronic format (preferred) by May 26, 2015, to the attention of Gerond A. George.  We request that you categorize the documents in your response with the numbered list below.  If only hard copies of
the requested documents are available or if the electronic format is too large, please inform the
lead inspector and provide the documents on the first day of the onsite inspection.  Also, the
inspectors will select specific items from the information requested below and request from your staff additional documents needed during the onsite inspection weeks.  We ask that the specific items requested be available and ready for review on the first day of inspection.  If you have any questions regarding this information request, please contact the lead inspector as soon as
possible.
 
1. Procedure(s) for conducting 10 CFR 50.59 screenings and evaluations. 
2. A list with descriptions of all 10 CFR 50.59 screenings (or equivalent) performed since the last triennial modification inspection that did not result in an evaluation.   
3. A list with descriptions of all 10 CFR 50.59 evaluations performed the last triennial modification inspection that did not result in an application for license amendment. 
4. A list with descriptions of all corrective action documents related to 10 CFR 50.59 screenings and evaluations since the last triennial modification inspection. 
5. A list of personnel qualified to prepare 10 CFR 50.59 screenings and/or evaluations, including qualification dates.   
6. A list of personnel qualified to review and approve 10 CFR 50.59 screenings and/or evaluations, including qualification dates.   
7. Procedure(s) for implementing permanent plant modifications.   
8. A list with descriptions of all permanent plant modifications since the last triennial modification inspection.   
 
  - 2 -  9. A list with descriptions of all corrective action documents related to permanent plant modifications since the last triennial modification inspection.   
10. Current revisions of the Technical Specifications and Bases and the Updated Final Safety Analysis Report.   
Note:  Descriptions should be brief but of sufficient detail to ensure that inspectors can
determine the safety and/or risk significance of the screenings, evaluations, and modifications.   
 
Note:  For this inspection, permanent plant modifications include permanent plant changes, design changes, set point changes, procedure changes, equivalency evaluations, suitability
analyses, calculations, and commercial grade dedications.   
 
  Inspector Contact Information:   
 
Gerond A. George
Senior Reactor Inspector
817-200-1562 Gerond.George@nrc.gov Jonathan Braisted
Reactor Inspector
817-200-1194 Jonathan.Braisted@nrc.gov Inspector Number 3 to be
named at later date. 
 
Mailing Address: 
 
U.S. NRC, Region IV Attn:  Gerond A. George
1600 East Lamar Blvd.
Arlington, TX  76011-4125
 
 
 
 
 
D. Koehl - 2 -
  requesting document displays a currently valid Office of Management and Budget Control Number. 
In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its
 
enclosure will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system
(ADAMS).  ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). 
Sincerely, 
/RA/  Thomas R. Farnholtz, Chief
Engineering Branch 1
Division of Reactor Safety
 
Dockets:  50-498; 50-499
Licenses:  NPF-76; NPF-80
 
Enclosure:  Evaluations of Changes, Tests, and Experiments    and Permanent Plant Modifications Inspection
 
   Request for Information  
 
Electronic Distribution to South Texas Project  
 
Distribution
Distribution
See next page  
See next page
ADAMS Accession Number: ML15098A284
SUNSI Review    ADAMS:              Sensitive              Non-Publicly Available          Keyword
By: GAG            Yes  No          Non-Sensitive          Publicly Available              NRC-002
OFFICE              SRI:DRS/EB1                                                      C:DRS/EB1
NAME                GGeorge                                                          TFarnholtz
SIGNATURE            /RA/                                                              /RA/
DATE                4/6/15                                                            4/7/15
                                      OFFICIAL RECORD COPY


 
Letter to Dennis Koehl from Thomas Farnholtz dated April 7, 2015
SUBJECT:       SOUTH TEXAS PROJECT, UNITS 1 AND 2 - NOTIFICATION OF
                EVALUATIONS OF CHANGES, TESTS, AND EXPERIMENTS, AND
  ADAMS Accession Number:  ML15098A284  SUNSI Review By:  GAG ADAMS:    Yes      No  Sensitive    Non-Sensitive  Non-Publicly Available    Publicly Available Keyword NRC-002 OFFICE SRI:DRS/EB1  C:DRS/EB1 NAME GGeorge  TFarnholtz SIGNATURE /RA/  /RA/ DATE 4/6/15  4/7/15
                PERMANENT PLANT MODIFICATIONS INSPECTION (05000498/2015007 and
OFFICIAL RECORD COPY
                05000499/2015007) AND REQUEST FOR INFORMATION
 
Electronic Distribution:
  Letter to Dennis Koehl from Thomas Farnholtz dated April 7, 2015  
Regional Administrator (Marc.Dapas@nrc.gov)
  SUBJECT: SOUTH TEXAS PROJECT, UNITS 1 AND 2 - NOTIFICATION OF EVALUATIONS OF CHANGES, TESTS, AND EXPERIMENTS, AND  
Deputy Regional Administrator (Kriss.Kennedy@nrc.gov)
PERMANENT PLANT MODIFICATIONS INSPECTION (05000498/2015007 and  
DRP Director (Troy.Pruett@nrc.gov)
05000499/2015007) AND REQUEST FOR INFORMATION  
DRP Deputy Director (Ryan.Lantz@nrc.gov)
  Electronic Distribution:
DRS Director (Anton.Vegel@nrc.gov)
Regional Administrator (Marc.Dapas@nrc.gov)  
DRS Deputy Director (Jeff.Clark@nrc.gov)
Deputy Regional Administrator (Kriss.Kennedy@nrc.gov)  
Senior Resident Inspector (Alfred.Sanchez@nrc.gov)
DRP Director (Troy.Pruett@nrc.gov) DRP Deputy Director (Ryan.Lantz@nrc.gov) DRS Director (Anton.Vegel@nrc.gov)  
Resident Inspector (Nicholas.Hernandez@nrc.gov)
DRS Deputy Director (Jeff.Clark@nrc.gov)
Branch Chief, DRP/B (Neil.OKeefe@nrc.gov)
Senior Resident Inspector (Alfred.Sanchez@nrc.gov)  
Senior Project Engineer, DRP/B (David.Proulx@nrc.gov)
Resident Inspector (Nicholas.Hernandez@nrc.gov) Branch Chief, DRP/B (Neil.OKeefe@nrc.gov) Senior Project Engineer, DRP/B (David.Proulx@nrc.gov)  
Project Engineer, DRP/B (Fabian.Thomas@nrc.gov)
Project Engineer, DRP/B (Fabian.Thomas@nrc.gov)  
Project Engineer, DRP/B (Steven.Janicki@nrc.gov)
Project Engineer, DRP/B (Steven.Janicki@nrc.gov)  
STP Administrative Assistant (Lynn.Wright@nrc.gov)
STP Administrative Assistant (Lynn.Wright@nrc.gov)  
Public Affairs Officer (Victor.Dricks@nrc.gov)
Public Affairs Officer (Victor.Dricks@nrc.gov) Public Affairs Officer (Lara.Uselding@nrc.gov)  
Public Affairs Officer (Lara.Uselding@nrc.gov)
Project Manager (Lisa.Regner@nrc.gov)  
Project Manager (Lisa.Regner@nrc.gov)
Branch Chief, DRS/TSB (Geoffrey.Miller@nrc.gov)  
Branch Chief, DRS/TSB (Geoffrey.Miller@nrc.gov)
RITS Coordinator (Marisa.Herrera@nrc.gov)  
RITS Coordinator (Marisa.Herrera@nrc.gov)
ACES (R4Enforcement.Resource@nrc.gov) Regional Counsel (Karla.Fuller@nrc.gov) Technical Support Assistant (Loretta.Williams@nrc.gov)  
ACES (R4Enforcement.Resource@nrc.gov)
Congressional Affairs Officer (Jenny.Weil@nrc.gov)  
Regional Counsel (Karla.Fuller@nrc.gov)
RIV Congressional Affairs Officer (Angel.Moreno@nrc.gov)  
Technical Support Assistant (Loretta.Williams@nrc.gov)
Congressional Affairs Officer (Jenny.Weil@nrc.gov)
RIV Congressional Affairs Officer (Angel.Moreno@nrc.gov)
RIV/ETA: OEDO (Michael.Waters@nrc.gov)
RIV/ETA: OEDO (Michael.Waters@nrc.gov)
}}
}}

Latest revision as of 13:16, 31 October 2019

Notification of Evaluations of Changes, Tests and Experiments and Permanent Plant Modification (05000498/2015007 and 05000499/2015007) and Request for Information
ML15098A284
Person / Time
Site: South Texas  STP Nuclear Operating Company icon.png
Issue date: 04/07/2015
From: Farmholtz T
Region 4 Engineering Branch 1
To: Koehl D
South Texas
G. George
References
IR 2015007
Download: ML15098A284 (6)


See also: IR 05000498/2015007

Text

UNITED STATES

NUCLEAR REGULATORY COMMISSION

REGION IV

1600 E. LAMAR BLVD.

ARLINGTON, TX 76011-4511

April 7, 2015

Mr. Dennis L. Koehl

President and CEO/CNO

STP Nuclear Operating Company

P.O. Box 289

Wadsworth, TX 77483

SUBJECT: SOUTH TEXAS PROJECT, UNITS 1 AND 2 - NOTIFICATION OF

EVALUATIONS OF CHANGES, TESTS, AND EXPERIMENTS, AND

PERMANENT PLANT MODIFICATIONS INSPECTION (05000498/2015007 and

05000499/2015007) AND REQUEST FOR INFORMATION

Dear Mr. Koehl:

The purpose of this letter is to notify you that U.S. Nuclear Regulatory Commission (NRC) staff

will conduct the baseline inspection of changes, tests, experiments, and permanent plant

modifications at your South Texas Project, Units 1 and 2, from June 1-5, 2015, and June 15-20,

2015. The inspection will consist of three reactor inspectors from the NRCs Region IV office for

two weeks. The inspection will be conducted in accordance with NRC Inspection

Procedure 71111.17T, Evaluations of Changes, Tests, and Experiments and Permanent Plant

Modifications.

Experience has shown that this inspection is resource intensive for both the NRC inspectors

and your staff. In order to minimize the impact to your onsite resources and to ensure a

productive inspection, we have enclosed a request for documents needed for this inspection.

Please note that the documents are requested to be provided by May 26, 2015. Upon review of

these documents, the inspectors will select additional documentation for review upon arrival. It

is important that all of these documents are up-to-date and complete in order to minimize the

number of additional documents requested during the preparation and/or the onsite portions of

the inspection.

We have discussed the schedule for these inspection activities with your staff and understand

that our regulatory contact for this inspection will be Rafael Gonzalez of your licensing

organization. If there are any questions about this inspection or the material requested, please

contact the lead inspector, Gerond George, by telephone at 817-200-1562 or by e-mail at

Gerond.George@nrc.gov.

This letter does not contain new or amended information collection requirements subject to the

Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information collection

requirements were approved by the Office of Management and Budget, Control

Number 3150 0011. The NRC may not conduct or sponsor, and a person is not required to

respond to, a request for information or an information collection requirement unless the

D. Koehl -2-

requesting document displays a currently valid Office of Management and Budget Control

Number.

In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter and its

enclosure will be available electronically for public inspection in the NRC Public Document

Room or from the Publicly Available Records (PARS) component of NRC's document system

(ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-

rm/adams.html (the Public Electronic Reading Room).

Sincerely,

/RA/

Thomas R. Farnholtz, Chief

Engineering Branch 1

Division of Reactor Safety

Dockets: 50-498; 50-499

Licenses: NPF-76; NPF-80

Enclosure:

Evaluations of Changes, Tests, and Experiments

and Permanent Plant Modifications Inspection

Request for Information

Electronic Distribution to the South Texas Project

Request for Information

Evaluations of Changes, Tests, and Experiments and Permanent Plant Modifications

Inspection

South Texas Project

Inspection Report: 05000498/2015007 and 05000499/2015007

Onsite Inspection Dates: June 1-5, 2015

June 15-20, 2015

Inspection Procedure: IP 71111.17T, Evaluations of Changes, Tests, and Experiments

and Permanent Plant Modifications

Lead Inspector: Gerond A. George, Senior Reactor Inspector

Information Requested for the In-Office Preparation Week

The following information should be sent to the Region IV office in hard copy or electronic

format (preferred) by May 26, 2015, to the attention of Gerond A. George. We request that you

categorize the documents in your response with the numbered list below. If only hard copies of

the requested documents are available or if the electronic format is too large, please inform the

lead inspector and provide the documents on the first day of the onsite inspection. Also, the

inspectors will select specific items from the information requested below and request from your

staff additional documents needed during the onsite inspection weeks. We ask that the specific

items requested be available and ready for review on the first day of inspection. If you have any

questions regarding this information request, please contact the lead inspector as soon as

possible.

1. Procedure(s) for conducting 10 CFR 50.59 screenings and evaluations.

2. A list with descriptions of all 10 CFR 50.59 screenings (or equivalent) performed since

the last triennial modification inspection that did not result in an evaluation.

3. A list with descriptions of all 10 CFR 50.59 evaluations performed the last triennial

modification inspection that did not result in an application for license amendment.

4. A list with descriptions of all corrective action documents related to 10 CFR 50.59

screenings and evaluations since the last triennial modification inspection.

5. A list of personnel qualified to prepare 10 CFR 50.59 screenings and/or evaluations,

including qualification dates.

6. A list of personnel qualified to review and approve 10 CFR 50.59 screenings and/or

evaluations, including qualification dates.

7. Procedure(s) for implementing permanent plant modifications.

8. A list with descriptions of all permanent plant modifications since the last triennial

modification inspection.

-1- Enclosure

9. A list with descriptions of all corrective action documents related to permanent plant

modifications since the last triennial modification inspection.

10. Current revisions of the Technical Specifications and Bases and the Updated Final

Safety Analysis Report.

Note: Descriptions should be brief but of sufficient detail to ensure that inspectors can

determine the safety and/or risk significance of the screenings, evaluations, and modifications.

Note: For this inspection, permanent plant modifications include permanent plant changes,

design changes, set point changes, procedure changes, equivalency evaluations, suitability

analyses, calculations, and commercial grade dedications.

Inspector Contact Information:

Gerond A. George Jonathan Braisted Inspector Number 3 to be

Senior Reactor Inspector Reactor Inspector named at later date.

817-200-1562 817-200-1194

Gerond.George@nrc.gov Jonathan.Braisted@nrc.gov

Mailing Address:

U.S. NRC, Region IV

Attn: Gerond A. George

1600 East Lamar Blvd.

Arlington, TX 76011-4125

-2-

D. Koehl -2-

requesting document displays a currently valid Office of Management and Budget Control

Number.

In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter and its

enclosure will be available electronically for public inspection in the NRC Public Document

Room or from the Publicly Available Records (PARS) component of NRC's document system

(ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-

rm/adams.html (the Public Electronic Reading Room).

Sincerely,

/RA/

Thomas R. Farnholtz, Chief

Engineering Branch 1

Division of Reactor Safety

Dockets: 50-498; 50-499

Licenses: NPF-76; NPF-80

Enclosure:

Evaluations of Changes, Tests, and Experiments

and Permanent Plant Modifications Inspection

Request for Information

Electronic Distribution to South Texas Project

Distribution

See next page

ADAMS Accession Number: ML15098A284

SUNSI Review ADAMS: Sensitive Non-Publicly Available Keyword

By: GAG Yes No Non-Sensitive Publicly Available NRC-002

OFFICE SRI:DRS/EB1 C:DRS/EB1

NAME GGeorge TFarnholtz

SIGNATURE /RA/ /RA/

DATE 4/6/15 4/7/15

OFFICIAL RECORD COPY

Letter to Dennis Koehl from Thomas Farnholtz dated April 7, 2015

SUBJECT: SOUTH TEXAS PROJECT, UNITS 1 AND 2 - NOTIFICATION OF

EVALUATIONS OF CHANGES, TESTS, AND EXPERIMENTS, AND

PERMANENT PLANT MODIFICATIONS INSPECTION (05000498/2015007 and

05000499/2015007) AND REQUEST FOR INFORMATION

Electronic Distribution:

Regional Administrator (Marc.Dapas@nrc.gov)

Deputy Regional Administrator (Kriss.Kennedy@nrc.gov)

DRP Director (Troy.Pruett@nrc.gov)

DRP Deputy Director (Ryan.Lantz@nrc.gov)

DRS Director (Anton.Vegel@nrc.gov)

DRS Deputy Director (Jeff.Clark@nrc.gov)

Senior Resident Inspector (Alfred.Sanchez@nrc.gov)

Resident Inspector (Nicholas.Hernandez@nrc.gov)

Branch Chief, DRP/B (Neil.OKeefe@nrc.gov)

Senior Project Engineer, DRP/B (David.Proulx@nrc.gov)

Project Engineer, DRP/B (Fabian.Thomas@nrc.gov)

Project Engineer, DRP/B (Steven.Janicki@nrc.gov)

STP Administrative Assistant (Lynn.Wright@nrc.gov)

Public Affairs Officer (Victor.Dricks@nrc.gov)

Public Affairs Officer (Lara.Uselding@nrc.gov)

Project Manager (Lisa.Regner@nrc.gov)

Branch Chief, DRS/TSB (Geoffrey.Miller@nrc.gov)

RITS Coordinator (Marisa.Herrera@nrc.gov)

ACES (R4Enforcement.Resource@nrc.gov)

Regional Counsel (Karla.Fuller@nrc.gov)

Technical Support Assistant (Loretta.Williams@nrc.gov)

Congressional Affairs Officer (Jenny.Weil@nrc.gov)

RIV Congressional Affairs Officer (Angel.Moreno@nrc.gov)

RIV/ETA: OEDO (Michael.Waters@nrc.gov)