| number = ML18025A490 | | number = ML18025A490 | ||
| issue date = 08/29/1975 | | issue date = 08/29/1975 | ||
| title = | | title = Letter Regarding the Definitive Report of Deficiencies in Box Column Supports Which Supplements PLA-74 | ||
| author name = Curtis N | | author name = Curtis N | ||
| author affiliation = Pennsylvania Power & Light Co | | author affiliation = Pennsylvania Power & Light Co | ||
| addressee name = O'Reilly J | | addressee name = O'Reilly J | ||
| addressee affiliation = NRC/RGN-I | | addressee affiliation = NRC/RGN-I | ||
| docket = 05000387, 05000388 | | docket = 05000387, 05000388 | ||
Line 16: | Line 16: | ||
=Text= | =Text= | ||
{{#Wiki_filter:NR-ISTRIBUTION FOR PART 50 DOC T MATERIAL (TEMPORARY FORM)CONTRQL NO: FILE: FROM.Pennsylvania Power 6 Lig | {{#Wiki_filter:NR- ISTRIBUTION FOR PART 50 DOC T MATERIAL (TEMPORARY FORM) | ||
CONTRQL NO: | |||
+ | FILE: | ||
FROM. Pennsylvania Power 6 Lig t DATE OF DOC 'ATE REC'D LTR TW5 RPT OTHER Co. Allentown, Pa N.W Curtis TO:'r ORIG CC OTHER SENT NRC PDR J,P,O'e i 1 ly not ..igned SENT LOCAL PDR PROP INFO INPUT NO CYS REC'D DOCKET NO: " | |||
CLASS //CLASS | |||
( | "'( | ||
(1)(2)(10) | xxx 0-38 aii 6888) | ||
- | DESCR IPTION: ENCLOSURES: | ||
~l f TWO NORTH NINTH STREET, ALLENTOWN, PA.18101 PHONEME t215)821 5 151 August 29, 1975'r Cj.-,&W<).WQ'/(0 | i 'I ~ 'i - ~ | ||
<Yi Mr.Z.P.O'Reilly Director | Ltr notarized 9-3-75 ~,. ~ trans the following | ||
As indicated in the attached report, the decision has'been made to redesign the structures and, to replace all eight units, including those found not to contain defects.The replacement units employ material changes and weld)oint configurations vhich vill facilitate fabrication and should preclude the recurrence of the lamellar tearing phenomenon experienced in original units.Xn addition to those corrective measures identified in PLA-74 and the attached Bechtel detailed.report,, PPkL has concurred in an increase in Bechtel surveillance activities at the vendor's fabrication facility (BeMhlehem Steel Company's Pottstown, PA plant,).Additionally, receiving and preinstallation activities at the SSES site will be aligned to perform a final visual examination before the new units are permanently committed to the plant structure. | ~ | ||
We await your advice should you have any further questions or concerns on this matter.Very truly yours N.W.Curtis Vice President-Engineering 5 Construction CJ QQQ ARS:b PENNSYLVANIA POWER 8 LIGHT COMPANY 0)J/}} | Report On Deficiency In Box Column Supports for The Susquehanna Nuclear Plant Dist Per H; Rushbrook | ||
( 15 cys enc'1 rec'd) | |||
I PLANT NAME: | |||
Susquehana 1 6c 2 Ev .t-tu , ~ i8 l )$ 7~~~ | |||
FOR ACTION/INFORMATION 9-8-75 JGB TLER (L) SCHWENCER (L) ZIEMANN (L) BEGAN (E) REID(L) | |||
W/ Copies W/ Copies W/ Copies W/ Copies W/ COPIES CLARK (L) STOLZ (L) i W/ Copies DICKER (E) LEAR (L) | |||
W/ Copies W/ Copies W/ Copies PARR (L) VASSALLO (L) KNIGHTON (E) SBICS W/ Copies W/ Copies W/ Copies W/ Copies KNI EL,(L) PURPLE (L) YOUNGBLOOD (E) | |||
W/ Copies W/ Copies W/ Copies W/( oples INTERNAL DISTR I BUT ION ECH REVIEYif DENTON A/T IND MGC, ROOM P-SOBA SCHROEOER " | |||
%IACCARY>~ gAMMILL | |||
~R IMES LIC ASST R. DIGGS (L) | |||
H. G EAR IN (L) | |||
B RAITMAN SALTZMAN | |||
~ | |||
GOSSICK/STAFF ~NI'GHT KASTNER GOULBOURNE (L) ME LTZ CASE GIAMBUSSO 'HAO PAWLICKI BALLARD SPANGLER P. KREUTZER (E) | |||
EE (L) PLANS BOYD STELLO .R U3:iBROOQL) + MCDONALD MOORE (L) HOUSTON ENVI RO CHAPMAN | |||
~YOUNG (L) M~ | |||
S. REED(E) | |||
NOVAK MULLER M. S (L) | |||
'RVICE DUBE (Ltr) | |||
SKOVHOLT (L) ROSS DICKER S. S HEPPARD (L) E. COUPE GOLLER (L) (Ltr) IPPOLITO KNIGHTON M. S LATER (E) PETERSON P. COLI INS ~ | |||
~DESCO+~~ YOUNGBLOOD H. S MITH (L) HARTFIELD. (2) | |||
DEN ISE J.COLLINS BEGAN S. TEETS (L) KLECKER | |||
~G FILE OPR Si AAP REGION (2I It LAIHAS BENAROYA PROJECT LDR G. WILLIAMS(E) | |||
~ | |||
EISENHUT WIGG INTON V, WILSON (L) | |||
MIPC VOLLMER . HAR LESS R. INGRAM (L) | |||
~ ~ | |||
1 H. DUE'CAN EXTERNAL DISTRIBUTION LOCAL PDR Wilks Barre, Pa 1TIC (ABERNATHY) (1)(2)(10) NATIONALLABS 1 PD R-SAN/LA/NY 1NSIC (BUCHANAN) 1 W. PENNINGTON, Rm E-20'I GT 1 BROOKI1AVEN NAT LAB 1ASLB 1 CONSU LTANlS 1 G. ULBII<SON ORNL Newton Anderson NEWMARK/0 LUME/AGBADI AN ACRS . ENT fo | |||
~l f | |||
TWO NORTH NINTH STREET, ALLENTOWN, PA. 18101 PHONEME t215) 821 5 151 August 29, 1975' r Cj .-, &W<).WQ'/(0 <Yi Mr. Z. P. O'Reilly Director Region I U.S. Nuclear Regulatory Commission ,+>> | |||
931 Park Avenue King of Prussia, Pennsylvania 19406 ~i <<,,";~ gj SUSQUEHANNA S TEAM ELECTRXC STATION DEFINITIVE REPORT OF DEFICIENCIES IN < | |||
i/'re BOX COLUMN SUPPORTS DOCKET NOS.: 50-387 and 50-388 LICENSE NOS.: CPPR-101 and CPPR-102 ERs 100450/100508 FILE 840-4 PLA-82 Dear Mr. O'ReillyI This letter transmits the subject report which supplements PLA-7 1, 1 dated July 25, 1975 and is intended to complete PPKL's responsibility in reporting the deficiencies in fabricated structural steel members (Box Column Supports) which had 'been located in position for installa-tion in Susquehanna Unit 1 8c 2 structures. | |||
As indicated in the attached report, the decision has 'been made to redesign the structures and, to replace all eight units, including those found not to contain defects. The replacement units employ material changes and weld )oint configurations vhich vill facilitate fabrication and should preclude the recurrence of the lamellar tearing phenomenon experienced in original units. | |||
Xn addition to those corrective measures identified in PLA-74 and the attached Bechtel detailed. report,, PPkL has concurred in an increase in Bechtel surveillance activities at the vendor's fabrication facility (BeMhlehem Steel Company's Pottstown, PA plant,). | |||
Additionally, receiving and preinstallation activities at the SSES site will be aligned to perform a final visual examination before the new units are permanently committed to the plant structure. | |||
We await your advice should you have any further questions or concerns on this matter. | |||
Very truly yours N. W. Curtis Vice President - Engineering 5 Construction CJ QQQ ARS:b PENNSYLVANIA POWER 8 LIGHT COMPANY | |||
0 ) | |||
J/}} |
Latest revision as of 01:42, 22 October 2019
ML18025A490 | |
Person / Time | |
---|---|
Site: | Susquehanna |
Issue date: | 08/29/1975 |
From: | Curtis N Pennsylvania Power & Light Co |
To: | O'Reilly J NRC Region 1 |
References | |
PLA-74, PLA-82 | |
Download: ML18025A490 (4) | |
Text
NR- ISTRIBUTION FOR PART 50 DOC T MATERIAL (TEMPORARY FORM)
CONTRQL NO:
FILE:
FROM. Pennsylvania Power 6 Lig t DATE OF DOC 'ATE REC'D LTR TW5 RPT OTHER Co. Allentown, Pa N.W Curtis TO:'r ORIG CC OTHER SENT NRC PDR J,P,O'e i 1 ly not ..igned SENT LOCAL PDR PROP INFO INPUT NO CYS REC'D DOCKET NO: "
CLASS //CLASS
"'(
xxx 0-38 aii 6888)
DESCR IPTION: ENCLOSURES:
i 'I ~ 'i - ~
Ltr notarized 9-3-75 ~,. ~ trans the following
~
Report On Deficiency In Box Column Supports for The Susquehanna Nuclear Plant Dist Per H; Rushbrook
( 15 cys enc'1 rec'd)
I PLANT NAME:
Susquehana 1 6c 2 Ev .t-tu , ~ i8 l )$ 7~~~
FOR ACTION/INFORMATION 9-8-75 JGB TLER (L) SCHWENCER (L) ZIEMANN (L) BEGAN (E) REID(L)
W/ Copies W/ Copies W/ Copies W/ Copies W/ COPIES CLARK (L) STOLZ (L) i W/ Copies DICKER (E) LEAR (L)
W/ Copies W/ Copies W/ Copies PARR (L) VASSALLO (L) KNIGHTON (E) SBICS W/ Copies W/ Copies W/ Copies W/ Copies KNI EL,(L) PURPLE (L) YOUNGBLOOD (E)
W/ Copies W/ Copies W/ Copies W/( oples INTERNAL DISTR I BUT ION ECH REVIEYif DENTON A/T IND MGC, ROOM P-SOBA SCHROEOER "
%IACCARY>~ gAMMILL
~R IMES LIC ASST R. DIGGS (L)
H. G EAR IN (L)
B RAITMAN SALTZMAN
~
GOSSICK/STAFF ~NI'GHT KASTNER GOULBOURNE (L) ME LTZ CASE GIAMBUSSO 'HAO PAWLICKI BALLARD SPANGLER P. KREUTZER (E)
EE (L) PLANS BOYD STELLO .R U3:iBROOQL) + MCDONALD MOORE (L) HOUSTON ENVI RO CHAPMAN
~YOUNG (L) M~
S. REED(E)
NOVAK MULLER M. S (L)
'RVICE DUBE (Ltr)
SKOVHOLT (L) ROSS DICKER S. S HEPPARD (L) E. COUPE GOLLER (L) (Ltr) IPPOLITO KNIGHTON M. S LATER (E) PETERSON P. COLI INS ~
~DESCO+~~ YOUNGBLOOD H. S MITH (L) HARTFIELD. (2)
DEN ISE J.COLLINS BEGAN S. TEETS (L) KLECKER
~G FILE OPR Si AAP REGION (2I It LAIHAS BENAROYA PROJECT LDR G. WILLIAMS(E)
~
EISENHUT WIGG INTON V, WILSON (L)
MIPC VOLLMER . HAR LESS R. INGRAM (L)
~ ~
1 H. DUE'CAN EXTERNAL DISTRIBUTION LOCAL PDR Wilks Barre, Pa 1TIC (ABERNATHY) (1)(2)(10) NATIONALLABS 1 PD R-SAN/LA/NY 1NSIC (BUCHANAN) 1 W. PENNINGTON, Rm E-20'I GT 1 BROOKI1AVEN NAT LAB 1ASLB 1 CONSU LTANlS 1 G. ULBII<SON ORNL Newton Anderson NEWMARK/0 LUME/AGBADI AN ACRS . ENT fo
~l f
TWO NORTH NINTH STREET, ALLENTOWN, PA. 18101 PHONEME t215) 821 5 151 August 29, 1975' r Cj .-, &W<).WQ'/(0 <Yi Mr. Z. P. O'Reilly Director Region I U.S. Nuclear Regulatory Commission ,+>>
931 Park Avenue King of Prussia, Pennsylvania 19406 ~i <<,,";~ gj SUSQUEHANNA S TEAM ELECTRXC STATION DEFINITIVE REPORT OF DEFICIENCIES IN <
i/'re BOX COLUMN SUPPORTS DOCKET NOS.: 50-387 and 50-388 LICENSE NOS.: CPPR-101 and CPPR-102 ERs 100450/100508 FILE 840-4 PLA-82 Dear Mr. O'ReillyI This letter transmits the subject report which supplements PLA-7 1, 1 dated July 25, 1975 and is intended to complete PPKL's responsibility in reporting the deficiencies in fabricated structural steel members (Box Column Supports) which had 'been located in position for installa-tion in Susquehanna Unit 1 8c 2 structures.
As indicated in the attached report, the decision has 'been made to redesign the structures and, to replace all eight units, including those found not to contain defects. The replacement units employ material changes and weld )oint configurations vhich vill facilitate fabrication and should preclude the recurrence of the lamellar tearing phenomenon experienced in original units.
Xn addition to those corrective measures identified in PLA-74 and the attached Bechtel detailed. report,, PPkL has concurred in an increase in Bechtel surveillance activities at the vendor's fabrication facility (BeMhlehem Steel Company's Pottstown, PA plant,).
Additionally, receiving and preinstallation activities at the SSES site will be aligned to perform a final visual examination before the new units are permanently committed to the plant structure.
We await your advice should you have any further questions or concerns on this matter.
Very truly yours N. W. Curtis Vice President - Engineering 5 Construction CJ QQQ ARS:b PENNSYLVANIA POWER 8 LIGHT COMPANY