| | issue date = 03/03/2006 | | | issue date = 03/03/2006 |
| | title = Safety Evaluation Report Related to the License Renewal of Browns Ferry Nuclear Plant, Units 1, 2 and 3 - Request for Additional Information Related to Appendix F Items in the Application and the Topics Discussed in the Public Meeting... | | | title = Safety Evaluation Report Related to the License Renewal of Browns Ferry Nuclear Plant, Units 1, 2 and 3 - Request for Additional Information Related to Appendix F Items in the Application and the Topics Discussed in the Public Meeting... |
| | author name = Lund L L | | | author name = Lund L |
| | author affiliation = NRC/NRR/ADRO/DLR/RLRA | | | author affiliation = NRC/NRR/ADRO/DLR/RLRA |
| | addressee name = Singer K W | | | addressee name = Singer K |
| | addressee affiliation = Tennessee Valley Authority | | | addressee affiliation = Tennessee Valley Authority |
| | docket = 05000259, 05000260, 05000296 | | | docket = 05000259, 05000260, 05000296 |
Line 14: |
Line 14: |
| | page count = 8 | | | page count = 8 |
| | project = TAC:MC1704, TAC:MC1705, TAC:MC1706 | | | project = TAC:MC1704, TAC:MC1705, TAC:MC1706 |
| | stage = RAI | | | stage = Approval |
| }} | | }} |
|
| |
|
Letter Sequence Approval |
---|
|
Results
Other: ML040650206, ML040910016, ML041310029, ML042240255, ML042990519, ML051180464, ML051250308, ML060410288, ML060450582, ML060950060, ML061110094, ML061110102, ML061110126, ML061140322, ML061730464, ML091870509, ML11171A037, ML11171A038, ML11308A018
|
MONTHYEARML0400603592003-12-31031 December 2003 Letter Transmitting Browns Ferry, Units 1, 2 and 3, Application for Renewed Operating Licenses Project stage: Request ML0406502062004-03-0404 March 2004 Determination of Acceptability and Sufficiency for Docketing and Opportunity for a Hearing Regarding the Application from Tennesssee Valley Authority for Renewal of the Operating Licenses for Browns Ferry, Units 1, 2 & 3 Project stage: Other ML0409100162004-03-31031 March 2004 Review Schedule for Application for Renewal of the Operating Licenses for the Browns Ferry Nuclear Plant, Units 1, 2 and 3 Project stage: Other ML0413100292004-05-0606 May 2004 & 03/31/2004 Summary of Telephone Conferences with Tennesssee Valley Authority Concerning Activities on Browns Ferry Nuclear Plant, Units 1, 2 & 3 LRA Project stage: Other ML0419501002004-06-10010 June 2004 Audit and Review Plan for Plant Aging Management Programs and Reviews - Browns Ferry Nuclear Plant, Units 1, 2 and 3 Project stage: Request ML0418101682004-06-28028 June 2004 Summary of Telephone Conference on May 27, 2004, Between the U.S. NRC and the Tennessee Valley Authority Concerning Draft Requests for Additional Information on Browns Ferry Nuclear Plant, Units 1, 2 and 3 LRA Project stage: Draft RAI ML0421104852004-07-28028 July 2004 Summary of Telephone Conference Held on July 1, 2004, Between NRC and TVA Concerning Draft Requests for Additional Information (D-RAI) on Browns Ferry Nuclear Plant Units 1, 2,& 3 Project stage: Draft RAI ML0422402552004-08-10010 August 2004 Audit and Review Plan for Plant Aging Management Reviews and Programs at the Browns Ferry Nuclear Power Plants, Units 1, 2 and 3 Project stage: Other ML0424005502004-08-26026 August 2004 Summary of Telephone Conference Held on July 27, 2004, Between U.S. Nuclear Regulatory Commission & Tennessee Valley Authority Concerning Draft Requests for Additional Information on Browns Ferry Nuclear Plant, Units 1, 2 & 3, License Renew Project stage: Draft RAI ML0424502112004-08-31031 August 2004 Summary of Telephone Conference Held on July 12, 2004, Between the U.S. Nuclear Regulatory Commission (NRC) and the Tennessee Valley Authority (TVA) Concerning Requests for Additional Information (RAI) on Browns Ferry Nuclear Plant, Unts 1, Project stage: RAI ML0426005222004-09-16016 September 2004 Summary of Telephone Conference Held on August 19, 2004, Between the U.S. Nuclear Regulatory Commission and the Tennessee Valley Authority Concerning Draft Requests for Additional Information on Browns Ferry Nuclear Plant, Units 1, 2 & 3 LR Project stage: Draft RAI ML0429905192004-10-21021 October 2004 Summary of Telephone Conference Held on September 22, 2004, Between the U.S. Nuclear Regulatory Commission and the Tennessee Valley Authority Concerning Browns Ferry Nuclear Plant, Units 1, 2 and 3, LRA Project stage: Other ML0430905772004-11-0404 November 2004 Request for Additional Information for the Review of the Browns Ferry Nuclear Plant, Units 1, 2 and 3, LRA (TAC Nos. MC1704, MC1705 and MC1706.) Project stage: RAI ML0430905732004-11-0404 November 2004 Request for Additional Information for the Review of the Browns Ferry Nuclear Plant, Units 1, 2 and 3, LRA Project stage: RAI ML0511804642005-04-26026 April 2005 Audit and Review Report for Plant Aging Management Programs (Amps) and Aging Management Reviews (Amrs), Browns Ferry Nuclear Plant, Untis 1, 2 and 3 and Memo Project stage: Other ML0512503082005-05-0404 May 2005 Memo, Audit and Review Report for Plant Aging Management Reviews and Programs at the Browns Ferry Nuclear Power Plant Project stage: Other ML0535603282005-12-20020 December 2005 License Renewal Application - Supplemental Information for the Time Limited Aging Analysis for Stress Relaxation of the Core Plate Hold-Down Bolts and the Unit 1 Periodic Inspection Program (TAC Nos. MC1704. Project stage: Supplement ML0601204532006-01-12012 January 2006 Safety Evaluation Report Related to the License Renewal of Browns Ferry Nuclear Plant, Units 1, 2, and 3 (Tac Nos. MC1704, MC1705, MC1706) Project stage: Approval ML0601103412006-01-12012 January 2006 Transmittal Letter to K. Singer: Safety Evaluation Report Related to the License Renewal of Browns Ferry Nuclear Plant, Units 1, 2, and 3 Project stage: Approval ML0604102882006-01-31031 January 2006 License Renewal Application (LRA) - Annual Update Project stage: Other ML0603302952006-01-31031 January 2006 Safety Evaluation Report Related to the License Renewal of Browns Ferry Nuclear Plant, Units 1,2, and 3 (TAC Nos. MC1704, MC1705, and MC1706) - Request for Additional Information Related to Appendix F Items in the Application Project stage: Approval ML0604505822006-02-14014 February 2006 License Renewal Application (LRA) - Revised Commitment Tables Project stage: Other ML0606203532006-03-0303 March 2006 Safety Evaluation Report Related to the License Renewal of Browns Ferry Nuclear Plant, Units 1, 2 and 3 - Request for Additional Information Related to Appendix F Items in the Application and the Topics Discussed in the Public Meeting... Project stage: Approval ML0606603742006-03-0707 March 2006 (BFN) Units 1, 2, and 3 License Renewal Application (LRA) - Supplemental Information for the Unit 1 Periodic Inspection (TAC MC1704, MC1705 and MC1706) Project stage: Supplement ML0607903762006-03-0707 March 2006 License Renewal Application (LRA) - Supplemental Information for Open Item 2.4-3 Project stage: Supplement ML0609500602006-04-0404 April 2006 (BFN) - Units 1, 2, and 3 License Renewal Application (LRA) - Unit 1 Lower Drywell Liner Inspections, Unit 1 Periodic Inspection Program, and Residual Heat Removal Service Water Piping Inspections Project stage: Other ML0609701682006-04-21021 April 2006 Transmittal of Supplement 1 to the Safety Evaluation Report (NUREG-1843) - Supplemental Safety Evaluation Report Related to the License Renewal of Browns Ferry Nuclear Plant, Units 1, 2, and 3 (TAC Nos. MC1704, MC1705, MC1706) Project stage: Approval ML0611403222006-04-21021 April 2006 Brown Ferry Units 1, 2, and 3 - License Renewal Application - Revised Commitment List Project stage: Other ML0611401822006-05-0404 May 2006 Improved Technical Specifications for Browns Ferry Nuclear Plant, Unit 3 Project stage: Acceptance Review ML0611403522006-05-0404 May 2006 Improved Technical Specifications for Browns Ferry Nuclear Plant, Unit 1 Project stage: Acceptance Review ML0609703322006-05-0404 May 2006 Ltr to Karl W. Singer - Issuance of Renewed Facility Operating License Nos. DPR-33, DPR-52 and DPR-68 for Browns Ferry Nuclear Plant, Units 1, 2, and 3 Project stage: Approval ML0611101022006-05-0404 May 2006 Renewed Facility Operating License DPR-52 Project stage: Other ML0611101262006-05-0404 May 2006 Renewed Facility Operating License No. DPR-68 Project stage: Other ML0611100942006-05-0404 May 2006 Renewed Facility Operating License DPR-33 Project stage: Other ML0611402092006-05-0404 May 2006 Improved Technical Specifications for Browns Ferry Nuclear Plant, Unit 2 Project stage: Acceptance Review ML0609703552006-05-0404 May 2006 Federal Register Notice - Notice of Issuance of Renewed Facility Operating License Nos. DPR-33, DPR-52 and DPR-68 for an Additional 20-year Period Project stage: Approval ML0613600442006-06-0707 June 2006 Agenda for Public Meeting with Entergy Operations Incorporated Regarding Spent Fuel Pool Rack Configuration Changes at ANO-1 and ANO-2 on Wednesday 06/07/2006, TAC Nos. MC1704, MC1705 Project stage: Meeting ML0617304642006-06-22022 June 2006 Corrections to Technical Specifications and Renewed Facility Operating License No. DPR-33, for Unit 1 Project stage: Other ML0619102062006-07-0606 July 2006 03/01/2006 - Summary of Meeting with TVA on the License Renewal Application for the Browns Ferry Nuclear Plant, Units 1, 2 and 3 Project stage: Meeting ML0618803982006-07-0606 July 2006 03/09/2006 Summary of a Meeting Held Between the U.S. Nuclear Regulatory Commission and the Tennessee Valley Authority on the License Renewal Application for the Browns Ferry Nuclear Plant, Units 1, 2 and 3 Project stage: Meeting ML0918705092009-07-17017 July 2009 G20090346/LTR-09-0303/EDATS: SECY-2009-0304 - Ltr. Mario Bonaca Report on the Safety Aspects of the License Renewal Application for the National Bureau of Standards Test Reactor Project stage: Other ML11171A0382010-12-31031 December 2010 NEDO-33632, Rev. 0, Browns Ferry (Units 1-3), Core Plate Bolt Analysis Stress Analysis Report. Project stage: Other ML11171A0372011-06-15015 June 2011 BWRVIP-25 Core Plate Bolt Stress Analysis Project stage: Other ML11308A0182011-11-0101 November 2011 One-Time Inspection Procedure, 0-TI-565, Rev. 0003 Project stage: Other 2005-05-04
[Table View] |
|
---|
Category:Letter
MONTHYEARIR 05000259/20240032024-11-0404 November 2024 Integrated Inspection Report 05000259/2024003 and 05000260/2024003 and 05000296/2024003 CNL-24-043, Application for Subsequent Renewed Operating Licenses, Second Safety Supplement2024-11-0101 November 2024 Application for Subsequent Renewed Operating Licenses, Second Safety Supplement ML24305A1692024-10-31031 October 2024 Site Emergency Plan Implementing Procedure Revision 05000259/LER-2024-003, Valid Specified System Actuation Caused the Automatic Start of Emergency Diesel Generators2024-10-29029 October 2024 Valid Specified System Actuation Caused the Automatic Start of Emergency Diesel Generators 05000259/LER-2024-001-02, Secondary Containment Isolation Valve Inoperable Due to Mechanical Failure2024-10-28028 October 2024 Secondary Containment Isolation Valve Inoperable Due to Mechanical Failure ML24299A2632024-10-25025 October 2024 Response to Apparent Violation in NRC Inspection Report 05000260/2024090, EA-24-075 ML24289A1232024-10-24024 October 2024 Letter to James Barstow Re Environmental Scoping Summary Report for Browns Ferry CNL-24-074, Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2024-10-23023 October 2024 Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure Revisions ML24308A0042024-10-16016 October 2024 Ahc 24-1578 Environmental Review of the Browns Ferry Nuclear Plant, Units 1, 2 and 3 Subsequent License Renewal Application Limestone County CNL-24-077, Application for Subsequent Renewed Operating Licenses, Response to Request for Additional Information, Set 12024-10-0909 October 2024 Application for Subsequent Renewed Operating Licenses, Response to Request for Additional Information, Set 1 ML24270A2162024-09-27027 September 2024 Notice of Intentions Regarding Preliminary Finding from NRC Inspection Report 05000260/2024090, EA-24-075 CNL-24-060, Supplement to Request for Approval of the Tennessee Valley Authority Nuclear Quality Assurance Program Description2024-09-24024 September 2024 Supplement to Request for Approval of the Tennessee Valley Authority Nuclear Quality Assurance Program Description ML24262A1502024-09-24024 September 2024 Requalification Program Inspection - Browns Ferry Nuclear Plant ML24262A0602024-09-23023 September 2024 Summary of August 19, 2024, Meeting with Tennessee Valley Authority Regarding a Proposed Supplement to the Tennessee Valley Authority Nuclear Quality Assurance Plan ML24263A2952024-09-19019 September 2024 Site Emergency Plan Implementing Procedure Revision CNL-24-065, Tennessee Valley Authority – Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2024-09-18018 September 2024 Tennessee Valley Authority – Central Emergency Control Center Emergency Plan Implementing Procedure Revisions IR 05000260/20240902024-09-17017 September 2024 NRC Inspection Report 05000260/2024090 and Preliminary White Finding and Apparent Violation - 1 CNL-24-062, Cycle 16 Reload Analysis Report2024-09-16016 September 2024 Cycle 16 Reload Analysis Report ML24255A8862024-09-10010 September 2024 Core Operating Limits Report for Cycle 16 Operation, Revision 0 ML24239A3332024-09-0303 September 2024 Full Audit Plan IR 05000259/20244042024-09-0303 September 2024 Cyber Security Inspection Report 05000259/2024404 and 05000260-2024404 and 05000296/2024404-Cover Letter IR 05000259/20240052024-08-26026 August 2024 Updated Inspection Plan for Browns Ferry Nuclear Plant, Units 1, 2 and 3 - Report 05000259/2024005, 05000260/2024005 and 05000296/2024005 ML24225A1682024-08-16016 August 2024 – Notification of Inspection and Request IR 05000259/20244022024-08-0606 August 2024 Security Baseline Inspection Report 05000259/2024402 and 05000260/2024402 and 05000296/2024402 ML24219A0272024-08-0606 August 2024 Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations IR 05000259/20240022024-08-0202 August 2024 Brown Ferry Nuclear Plant – Integrated Inspection Report05000259/2024002 and 05000260/2024002 and 05000296/2024002 ML24199A0012024-07-22022 July 2024 Clarification and Correction to Exemption from Requirement of 10 CFR 37.11(c)(2) ML24172A1342024-07-15015 July 2024 Exemptions from 10 CFR 37.11(C)(2) (EPID L-2023-LLE-0024) - Letter ML24183A4142024-07-10010 July 2024 – License Renewal Regulatory Limited Scope Audit Regarding the Environmental Review of the License Renewal Application (EPID Number: L-2024-SLE-0000) (Docket Numbers: 50-259, 50-260, and 50-296) 05000296/LER-2024-003, Main Steam Relief Valves Lift Settings Outside of Technical Specifications Required Setpoints2024-07-0808 July 2024 Main Steam Relief Valves Lift Settings Outside of Technical Specifications Required Setpoints 05000259/LER-2024-001-01, Inoperability of Unit 3 Diesel Generator Due to Relay Failure2024-07-0303 July 2024 Inoperability of Unit 3 Diesel Generator Due to Relay Failure ML24184A1142024-07-0202 July 2024 Site Emergency Plan Implementing Procedure Revision ML24183A3842024-07-0101 July 2024 Registration of Use of Cask to Store Spent Fuel (MPC-364, -365) ML24179A0282024-06-26026 June 2024 Evaluation of Effects of Out-of-Limits Condition as Described in IWB-3720(a) 05000259/LER-2024-002, Reactor Scram Due to Generator Step-Up Transformer Failure2024-06-24024 June 2024 Reactor Scram Due to Generator Step-Up Transformer Failure ML24175A0042024-06-23023 June 2024 Interim Report of a Deviation or Failure to Comply Associated with a Valve in the Unit 3 High Pressure Coolant Injection System ML24176A1132024-06-23023 June 2024 American Society of Mechanical Engineers, Section XI, Fourth 10 Year Inspection Interval, Inservice Inspection, System Pressure Test, Containment Inspection, and Repair and Replacement Programs, Owner’S Activity Report Cycle 21 Oper ML24089A1152024-06-21021 June 2024 Transmittal Letter, Environmental Assessments and Findings of No Significant Impact Related to Exemption Requests from 10 CFR 37.11(c)(2) ML24155A0042024-06-18018 June 2024 Proposed Alternative to the Requirements of the ASME Code (Revised Alternative Request 0-ISI-47) ML24158A5312024-06-0606 June 2024 Registration of Use of Cask to Store Spent Fuel (MPC-361, -362, -363) ML24071A0292024-06-0505 June 2024 Subsequent License Renewal Application Enclosure 3 - Proprietary Determination Letter ML24068A2612024-06-0505 June 2024 SLRA Fluence Methodology Report - Proprietary Determination Letter IR 05000259/20244032024-05-22022 May 2024 – Security Baseline Report 05000259/2024403 and 05000260/2024403 and 05000296/2024403 05000260/LER-2024-002, High Pressure Coolant Injection Inoperable Due to Rupture Disc Failure and Resulting System Isolation2024-05-20020 May 2024 High Pressure Coolant Injection Inoperable Due to Rupture Disc Failure and Resulting System Isolation ML24141A0482024-05-17017 May 2024 EN 56958_1 Ametek Solidstate Controls, Inc ML24136A0702024-05-15015 May 2024 2023 Annual Radiological Environmental Operating Report IR 05000259/20240012024-05-14014 May 2024 Integrated Inspection Report 05000259/2024001, 05000260/2024001, and 05000296/2024001 CNL-24-040, Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2024-05-0808 May 2024 Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure Revisions ML24123A2012024-05-0202 May 2024 NRC Cybersecurity Baseline Inspection (NRC Inspection Report 05000259/2024404, 05000260-2024404, 05000296/2024404) and Request for Information ML24122A6852024-05-0101 May 2024 2023 Annual Radioactive Effluent Release Report and Offsite Dose Calculation Manual 2024-09-03
[Table view] |
Text
March 3, 2006Mr. Karl W. SingerChief Nuclear Officer and Executive Vice President Tennessee Valley Authority 6A Lookout Place 1101 Market Street Chattanooga, TN 37402-2801
SUBJECT:
SAFETY EVALUATION REPORT RELATED TO THE LICENSE RENEWAL OFBROWNS FERRY NUCLEAR PLANT, UNITS 1, 2, AND 3 - REQUEST FOR ADDITIONAL INFORMATION RELATED TO APPENDIX F ITEMS IN THE APPLICATION AND THE TOPICS DISCUSSED IN THE PUBLIC MEETING ON MARCH 1, 2006 AT THE NUCLEAR REGULATORY COMMISSION(TAC NOS. MC1704, MC1705, AND MC1706)
Dear Mr. Singer:
By letter dated December 31, 2003, Tennessee Valley Authority (TVA or the applicant)submitted an application to the U.S. Nuclear Regulatory Commission (NRC or the staff) for therenewal of the Browns Ferry Nuclear Plant (BFN), Units 1, 2 and 3 operating licenses for up to an additional 20 years. The license renewal application (LRA) was submitted pursuant to Title 10 of the Code of Federal Regulations Part 54 (or the Rule), "Requirements for Renewal ofOperating Licenses for Nuclear Power Plants." The NRC staff met with TVA staff, including Mr. Masoud Bajestani, Vice President for the BFNUnit 1 Restart Program, in a public meeting on March 1, 2006, and discussed the status of the items discussed in our request for additional information sent to you in a letter dated January 31, 2006. We provided to you a list of information that is st ill needed to complete oursafety review of the LRA, and discussed the content of a letter you would need to send to us confirming your completion of 10 CFR 50.59 evaluations for items in Appendix F of the license renewal application. You are aware that the staff has scheduled a Full Committee meeting onMarch 9, 2006, with the Advisory Committee on Reactor Safeguards (ACRS or the Committee),
to present the staff's final safety evaluation (SER). The information and letter discussed in the March 1, 2006, meeting need to be submitted before the March 9, 2006, ACRS meeting andcontain the following: 1.By letter dated January 31, 2006, staff requested additional information of all the 10 CFR 50.59 evaluations that are already in place or expect to be completed before March 2006 regarding these 13 Appendix F items. You submitted a March 2, 2006, letter that discusses the Appendix F items that require 10 CFR 50.59 evaluation. Theitems are still incomplete in that your March 2, 2006, letter doesn't clearly certify that the10 CFR 50.59 evaluations have been completed by the date of the letter, and that as aresult of these evaluations, no license amendments (in accordance with 10 CFR 50.90) have been required to implement the items. The letter should also state that all the K. Singer remaining items that do not require a 10 CFR 50.59 evaluation have been or will beimplemented prior to restart.In addition, the March 2, 2006, letter does not provide details of the 10 CFR 50.59evaluations indicating that the evaluations are ready for audit by staff as to completion of these 13 items that form a current licensing basis (CLB) as required by the Rule. We discussed the importance of this item at the public meeting. The staff can not make asafety finding without a current licensing basis for Unit 1.2.During the 526th meeting of the ACRS, held on October 5-6, 2005, the Committeemembers reviewed the license renewal application for the BFN Units 1, 2, and 3 and the associated SER with open items prepared by the NRC staff. In their letter datedOctober 19, 2005, the Committee summarized the results of the interim review of this license renewal application and indicated the need for a robust and efficient aging management program (AMP) to periodically inspect systems and components that hadnot been replaced. It was not clear to the Committee whic h systems and componentswill be included in the scope of the periodic inspection program. The Committeecommented that the final SER should include a description of the attributes of the newperiodic inspection program for BFN Unit 1 components that will not be replaced beforerestart. We have not received sufficient information as of today to fulfill that stipulation. The staff still needs additional detail on TVA's sampling plan as well as a discussion ofhow the operating experience from Units 2 and 3 are applicable to the lay up condition at Unit 1. Furthermore, TVA should clearly indicate where the credit is taken for restart inspections to fulfill the requirement of the baseline for the periodic inspections.3.On March 1, 2006, during a meeting regarding an extended power uprate request forBFN, the TVA verbally informed the NRC staff that it is considering construction of a 16-cell cooling tower (and other alternatives) to replace the tower lost in the 1975 fire event.
This would alter a previous commitment to the staff to construct a 20-cell cooling tower that was evaluated for the license renewal application. The staff needs to evaluate theimpact of this change to the environmental review already completed (Supplemental Environmental Impact Statement for Browns Ferry License Renewal) and the impact on the LRA review schedule.
K. Singer-3-The staff is under time constraints and without a satisfactory safety finding can not proceed withthe review or be prepared to make their presentation to the ACRS Full Committee meeting asplanned for March 9, 2006. The staff requests that you provide all information described in this letter by March 6, 2006. Otherwise, the review schedule of Unit 1 will be adversely impacted. If you have any questions regarding this matter, please contact me at 301-415-3248 or via e-mail at LXL@nrc.gov
.Sincerely,/RA/Louise Lund, Branch ChiefLicense Renewal Branch A Division of License Renewal Office of Nuclear Reactor RegulationDocket Nos. 50-259, 50-260, and 50-296 cc: See next page K. Singer-3-The staff is under time constraints and without a satisfactory safety finding can not proceed withthe review or be prepared to make their presentation to the ACRS Full Committee meeting asplanned for March 9, 2006. The staff requests that you provide all information described in this letter by March 6, 2006. Otherwise, the review schedule of Unit 1 will be adversely impacted. If you have any questions regarding this matter, please contact me at 301-415-3248 or via e-mail at LXL@nrc.gov
.Sincerely,/RA/Louise Lund, Branch ChiefLicense Renewal Branch A Division of License Renewal Office of Nuclear Reactor RegulationDocket Nos. 50-259, 50-260, and 50-296cc: See next pageADAMS ACCESSION NUMBER: ML060620353 E:\Filenet\ML060620353.wpdOFFICEPM:RLRA:DLRLA:RLRA:DLRPM:RLRA:DLRBC:RLRA:DLRNAMERSubbaratnam(YDiaz-Sanabria for)YEdmondsYDiaz-SanabriaLLundDATE3/3/063/3/063/3/063/3/06 BROWNS FERRY NUCLEAR PLANTTennessee Valley Authority cc:Mr. Karl W. Singer Chief Nuclear Officer and Executive Vice President Tennessee Valley Authority 6A Lookout Place 1101 Market Street Chattanooga, TN 37402-2801Mr. Ashok S. Bhatnagar, Senior Vice President Nuclear Operations Tennessee Valley Authority 6A Lookout Place 1101 Market Street Chattanooga, TN 37402-2801Mr. Larry S. Bryant, Vice PresidentNuclear Engineering & Technical Services Tennessee Valley Authority 6A Lookout Place 1101 Market Street Chattanooga, TN 37402-2801Brian O'Grady, Site Vice PresidentBrowns Ferry Nuclear Plant Tennessee Valley Authority P.O. Box 2000 Decatur, AL 35609General CounselTennessee Valley Authority ET 11A 400 West Summit Hill DriveKnoxville, TN 37902Mr. John C. Fornicola, ManagerNuclear Assurance and Licensing Tennessee Valley Authority 6A Lookout Place 1101 Market Street Chattanooga, TN 37402-2801Mr. Bruce M. Aukland, Plant ManagerBrowns Ferry Nuclear Plant Tennessee Valley Authority P.O. Box 2000 Decatur, AL 35609Mr. Masoud Bajestani, Vice PresidentBrowns Ferry Unit 1 Restart Browns Ferry Nuclear Plant Tennessee Valley Authority P.O. Box 2000 Decatur, AL 35609Mr. Robert G. Jones, General ManagerBrowns Ferry Site Operations Browns Ferry Nuclear Plant Tennessee Valley Authority P.O. Box 2000 Decatur, AL 35609Mr. Scott M. ShaefferBrowns Ferry Unit 1 Project Engineer Division of Reactor Projects, Branch 6 U.S. Nuclear Regulatory Commission 61 Forsyth Street, SW Suite 23T85 Atlanta, GA 30303-8931Mr. Glenn W. Morris, ManagerCorporate Nuclear Licensing and Industry Affairs Tennessee Valley Authority 4X Blue Ridge 1101 Market Street Chattanooga, TN 37402-2801Mr. William D. Crouch, M anagerLicensing and Industry Affairs Browns Ferry Nuclear Plant Tennessee Valley Authority P.O. Box 2000 Decatur, AL 35609 BROWNS FERRY NUCLEAR PLANT Tennessee Valley Authority cc:
Senior Resident InspectorU.S. Nuclear Regulatory Commission Browns Ferry Nuclear Plant 10833 Shaw Road Athens, AL 35611-6970State Health OfficerAlabama Dept. of Public Health RSA Tower - Administration Suite 1552 P.O. Box 303017 Montgomery, AL 36130-3017ChairmanLimestone County Commission 310 West Washington Street Athens, AL 35611Mr. James RossNuclear Energy Institute 1776 I St., NW, Suite 400 Washington, DC 20006-2708Mr. Robert J. Beecken, Vice PresidentNuclear Support Tennessee Valley Authority 6A Lookout Place 1101 Market Street Chattanooga, TN 37402-2801 Letter to Karl W. Singer From L. Lund dated March 3, 2006
SUBJECT:
SAFETY EVALUATION REPORT RELATED TO THE LICENSE RENEWAL OFBROWNS FERRY NUCLEAR PLANT, UNITS 1, 2, AND 3 - REQUEST FOR ADDITIONAL INFORMATION RELATED TO APPENDIX F ITEMS IN THE APPLICATION AND THE TOPICS DISCUSSED IN THE PUBLIC MEETING ON MARCH 1, 2006 AT THE NUCLEAR REGULATORY COMMISSION(TAC NOS. MC1704, MC1705, AND MC1706)
DISTRIBUTION
- JFair RWeisman AMurphy RPettis GGalletti CLi GBagchi SSmith (srs3)
SDuraiswamy YL (Renee) Li RidsNrrDlr RidsNrrDlrRlra RidsNrrDlrRlrb RidsNrrDe RidsNrrDci RidsNrreEemb RidsNrrDeEeeb RidsNrrDeEqva RidsNrrDss RidsNrrDnrl RidsOgcMailCenter RidsNrrDipm DLR Staff
EBrown MMarshall MChernoff CJulian, RII SCahill, RII AHodgdon CCarpenter DCoe EKleeh