ML053550391: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
 
(Created page by program invented by StriderTol)
Line 2: Line 2:
| number = ML053550391
| number = ML053550391
| issue date = 12/22/2005
| issue date = 12/22/2005
| title = Turkey Point, Unit 3, Request for Additional Information, Steam Generator Tube Plugging Inservice Inspection Report
| title = Request for Additional Information, Steam Generator Tube Plugging Inservice Inspection Report
| author name = Moroney B T
| author name = Moroney B T
| author affiliation = NRC/NRR/ADRO/DORL/LPLD
| author affiliation = NRC/NRR/ADRO/DORL/LPLD

Revision as of 00:40, 11 February 2019

Request for Additional Information, Steam Generator Tube Plugging Inservice Inspection Report
ML053550391
Person / Time
Site: Turkey Point NextEra Energy icon.png
Issue date: 12/22/2005
From: Moroney B T
NRC/NRR/ADRO/DORL/LPLD
To: Stall J A
Florida Power & Light Co
Moroney B T, NRR/DLPM, 415-3974
References
TAC MC8112
Download: ML053550391 (4)


Text

December 22, 2005Mr. J. A. Stall Senior Vice President, Nuclear andChief Nuclear OfficerFlorida Power and Light Company P.O. Box 14000 Juno Beach, Florida 33408-0420

SUBJECT:

TURKEY POINT PLANT, UNIT 3 - REQUEST FOR ADDITIONALINFORMATION REGARDING STEAM GENERATOR TUBE PLUGGING INSERVICE INSPECTION REPORT (TAC NO. MC8112)

Dear Mr. Stall:

By letter dated June 17, 2005, Florida Power & Light Company submitted the steam generatortube plugging inservice inspection 12-month special report for the fall 2004 refueling outage at Turkey Point Unit 3.The U.S. Nuclear Regulatory Commission staff has reviewed your submittal and finds that aresponse to the enclosed Request for Additional Information is needed before we can complete the review.This request was discussed with Ms. Stavroula Mihalakea of your staff on December 15, 2005,and it was agreed that a response would be provided by March 1, 2006. If you have any questions, please contact me at (301) 415-3974.Sincerely, /RA/Brendan T. Moroney, Project Manager Plant Licensing Branch II-2 Division of Operating Reactor Licensing Office of Nuclear Reactor RegulationDocket Nos. 50-250

Enclosure:

As stated cc w/encl: See next page Mr. J. A. StallDecember 22, 2005Senior Vice President, Nuclear andChief Nuclear OfficerFlorida Power and Light Company P.O. Box 14000 Juno Beach, Florida 33408-0420

SUBJECT:

TURKEY POINT PLANT, UNIT 3 - REQUEST FOR ADDITIONALINFORMATION REGARDING STEAM GENERATOR TUBE PLUGGING INSERVICE INSPECTION REPORT (TAC NO. MC8112)

Dear Mr. Stall:

By letter dated June 17, 2005, Florida Power & Light Company submitted the steam generatortube plugging inservice inspection 12-month special report for the fall 2004 refueling outage at Turkey Point Unit 3.The U.S. Nuclear Regulatory Commission staff has reviewed your submittal and finds that aresponse to the enclosed Request for Additional Information is needed before we can complete the review.This request was discussed with Ms. Stavroula Mihalakea of your staff on December 15, 2005,and it was agreed that a response would be provided by March 1, 2006. If you have any questions, please contact me at (301) 415-3974.Sincerely, /RA/Brendan T. Moroney, Project Manager Plant Licensing Branch II-2 Division of Operating Reactor Licensing Office of Nuclear Reactor RegulationDocket Nos. 50-250

Enclosure:

As stated cc w/encl: See next pageDistribution:PUBLICLPL II-2 R/FRidsNrrPMBMoroneyRidsNrrDorlLpldAHiser BClayton(paper copy)RidsOgcRpYDiaz-CastilloBSingalsRidsRgn2MailCenter(SBinoy) RidsAcrsAcnwMailCenterADAMS ACCESSION No.: ML053550391 NRR-088OFFICELPL II-2/PMLPL II-2/LACSGB/CLPL II-2/SCNAMEBMoroneyRSola forBClaytonEMurphy (acting)by memo datedMMarshallDATE 12/22/05 12/22/059/28/05 12/22/05OFFICIAL RECORD COPY REQUEST FOR ADDITIONAL INFORMATION FOR FLORIDA POWER & LIGHT COMPANY TURKEY POINT UNIT 3STEAM GENERATOR TUBE INSPECTION REPORTDOCKET NO. 50-2501.Attachment 1 of the inservice inspection report indicated that mechanical wear damage wasidentified in locations other than anti-vibration bars (e.g., tube supports, top of tubesheet) insteam generator (SG) A, B, and C. Please explain the cause of these indications. If the indications are attributed to possible loose parts, please discuss whether a foreign object search and retrieval was performed in each SG and whether the loose parts were removed from the SGs. If the parts were not removed or the locations were not visually inspected, please discuss the results of any evaluations performed to ensure these parts (or suspected parts) would not result in a loss of tube integrity for the period of time between inspections.ENCLOSURE Mr. J. A. StallTURKEY POINT PLANT Florida Power and Light Company cc:M. S. Ross, Managing Attorney Florida Power & Light Company P.O. Box 14000 Juno Beach, FL 33408-0420

Marjan Mashhadi, Senior Attorney Florida Power & Light Company 801 Pennsylvania Avenue, NW.

Suite 220 Washington, DC 20004T. O. Jones, Site Vice PresidentTurkey Point Nuclear Plant Florida Power and Light Company 9760 SW. 344th Street Florida City, FL 33035 County Manager Miami-Dade County 111 Northwest 1 Street, 29th Floor Miami, Florida 33128 Senior Resident InspectorTurkey Point Nuclear Plant U.S. Nuclear Regulatory Commission 9762 SW. 344 th StreetFlorida City, Florida 33035Mr. William A. Passetti, ChiefDepartment of Health Bureau of Radiation Control 2020 Capital Circle, SE, Bin #C21 Tallahassee, Florida 32399-1741Mr. Craig Fugate, DirectorDivision of Emergency Preparedness Department of Community Affairs 2740 Centerview Drive Tallahassee, Florida 32399-2100Attorney General Department of Legal Affairs The Capitol Tallahassee, Florida 32304Michael O. PearcePlant General Manager Turkey Point Nuclear Plant Florida Power and Light Company 9760 SW. 344th Street Florida City, FL 33035Walter ParkerLicensing Manager Turkey Point Nuclear Plant 9760 SW 344th Street Florida City, FL 33035Mark Warner, Vice PresidentNuclear Operations Support Florida Power and Light Company P.O. Box 14000 Juno Beach, FL 33408-0420Mr. Rajiv S. KundalkarVice President - Nuclear Engineering Florida Power & Light Company P.O. Box 14000 Juno Beach, FL 33408-0420