MONTHYEARW3F1-2021-0024, Emergency Preparedness Documents2021-03-11011 March 2021 Emergency Preparedness Documents ML17114A0372017-04-18018 April 2017 Submittal of Emergency Plan, Revision 048 ML16158A2232016-06-0202 June 2016 Submittal of Revision 302 to Emergency Plan Implementing Procedure EP-002-140, Reentry ML16078A1372016-03-16016 March 2016 Submittal of Revision 032 to EP-001-001, Recognition and Classification of Emergency Conditions and Supporting Documents ML16029A4112016-01-21021 January 2016 Submittal of Revision 025 to Emergency Plan Implementing Procedure, EP-002-052, Nuclear Management Manual. ML16007A0462015-12-16016 December 2015 Revision 313 to Emergency Plan Implementing Procedure, EP-002-010, Notifications and Communications. W3F1-2004-0120, (Waterford 3), Response to Request for Additional Information for Proposed Upgraded Emergency Action Levels (Eals) Using NEI 99-01 Revision 4 Methodology2004-12-15015 December 2004 (Waterford 3), Response to Request for Additional Information for Proposed Upgraded Emergency Action Levels (Eals) Using NEI 99-01 Revision 4 Methodology W3F1-2003-0079, Revision 16 to EP-002-050, Offsite Dose Assessment (Manual).2003-09-29029 September 2003 Revision 16 to EP-002-050, Offsite Dose Assessment (Manual). W3F1-2003-0059, Ses, Emergency Plan Implementing Procedure, EP-002-052, Rev. 182003-08-0404 August 2003 Ses, Emergency Plan Implementing Procedure, EP-002-052, Rev. 18 W3F1-2003-0045, Emergency Plan Implementing Procedures2003-06-12012 June 2003 Emergency Plan Implementing Procedures W3F1-2003-0042, Emergency Plan Implementing Procedures2003-06-0404 June 2003 Emergency Plan Implementing Procedures W3F1-2003-0038, Emergency Plan Implementing Procedures Changes & Revisions, EP-002-170, Revision 10 Through EP-004-010, Revision 52003-05-12012 May 2003 Emergency Plan Implementing Procedures Changes & Revisions, EP-002-170, Revision 10 Through EP-004-010, Revision 5 W3F1-2002-0092, Ses Emergency Plan Implementing Procedure, EP-001-010, Revision 232002-10-24024 October 2002 Ses Emergency Plan Implementing Procedure, EP-001-010, Revision 23 W3F1-2002-0065, Emergency Plan Training Procedure2002-07-31031 July 2002 Emergency Plan Training Procedure ML0224602382002-07-24024 July 2002 Changes to Emergency Plan Implementing Procedures, Including EP-001-001 (Revision 20, Change 1), Recognition & Classification of Emergency Conditions & EP-003-004 (Revision 22, Change 1), Emergency Equipment Inventory 2021-03-11
[Table view] Category:Letter type:W
MONTHYEARW3F1-2023-0056, Owner'S Activity Report Form for Inservice Inspection Performed During Operating Cycle 24 / Refuel 242023-12-19019 December 2023 Owner'S Activity Report Form for Inservice Inspection Performed During Operating Cycle 24 / Refuel 24 W3F1-2023-0055, Reply to a Notice of Violation2023-12-14014 December 2023 Reply to a Notice of Violation W3F1-2023-0052, Core Operating Limits Report (COLR) - Cycle 26, Revision O2023-11-0707 November 2023 Core Operating Limits Report (COLR) - Cycle 26, Revision O W3F1-2023-0049, Revise Technical Specification 3/4.3.2 to Remove Exemption from Testing Certain Relays at Power to Support Elimination of Potential Single Point Vulnerability - Withdrawal2023-09-28028 September 2023 Revise Technical Specification 3/4.3.2 to Remove Exemption from Testing Certain Relays at Power to Support Elimination of Potential Single Point Vulnerability - Withdrawal W3F1-2023-0048, Special Report SR 2023-004-00 for Waterford Steam Electric Station, Unit 3, Radiation Monitor Inoperable Greater than 7 Days2023-09-25025 September 2023 Special Report SR 2023-004-00 for Waterford Steam Electric Station, Unit 3, Radiation Monitor Inoperable Greater than 7 Days W3F1-2023-0035, Application for Technical Specification Change to Revise Surveillance Requirements Included in the Surveillance Frequency Control Program2023-07-26026 July 2023 Application for Technical Specification Change to Revise Surveillance Requirements Included in the Surveillance Frequency Control Program W3F1-2023-0036, Special Report SR-2023-003-01 for Waterford Steam Electric Station, Unit 3, Radiation Monitor Inoperable Greater than 7 Days2023-05-0404 May 2023 Special Report SR-2023-003-01 for Waterford Steam Electric Station, Unit 3, Radiation Monitor Inoperable Greater than 7 Days W3F1-2023-0032, Annual Radioactive Effluent Release Report (ARERR) 20222023-04-27027 April 2023 Annual Radioactive Effluent Release Report (ARERR) 2022 W3F1-2023-0033, Submittal of Annual Radiological Environmental Operating Report - 20222023-04-27027 April 2023 Submittal of Annual Radiological Environmental Operating Report - 2022 W3F1-2023-0025, Annual Report of Individual Monitoring of Radiation Exposure for 2022 Per 10 CFR 20.22062023-04-11011 April 2023 Annual Report of Individual Monitoring of Radiation Exposure for 2022 Per 10 CFR 20.2206 W3F1-2023-0018, Updated Final Supplemental Response to NRC Generic Letter 2004-022023-03-30030 March 2023 Updated Final Supplemental Response to NRC Generic Letter 2004-02 W3F1-2023-0022, Registration of Dry Fuel Storage Cask Use2023-03-22022 March 2023 Registration of Dry Fuel Storage Cask Use W3F1-2023-0021, Submittal of Special Report SR 2023-003-00 Radiation Monitor Inoperable Greater than 7 Days2023-03-17017 March 2023 Submittal of Special Report SR 2023-003-00 Radiation Monitor Inoperable Greater than 7 Days W3F1-2023-0016, Registration of Dry Fuel Storage Cask Use2023-03-0303 March 2023 Registration of Dry Fuel Storage Cask Use W3F1-2023-0014, Reply to a Notice of Violation; EA-22-1192023-02-20020 February 2023 Reply to a Notice of Violation; EA-22-119 W3F1-2023-0013, Notification of Readiness for Supplemental Inspection2023-02-15015 February 2023 Notification of Readiness for Supplemental Inspection W3F1-2023-0007, Registration of Dry Fuel Storage Cask Use2023-02-0606 February 2023 Registration of Dry Fuel Storage Cask Use W3F1-2023-0010, Special Report SR 2023-002-00, Radiation Monitor Inoperable Greater than 7 Days2023-01-25025 January 2023 Special Report SR 2023-002-00, Radiation Monitor Inoperable Greater than 7 Days W3F1-2023-0002, SR 2023-001-00 for Waterford Steam Electric Station, Unit 3, Radiation Monitor Inoperable Greater than 30 Days2023-01-0505 January 2023 SR 2023-001-00 for Waterford Steam Electric Station, Unit 3, Radiation Monitor Inoperable Greater than 30 Days W3F1-2022-0067, Commitment Change Notification for Generic Safety Issue 191 and Generic Letter 2004-022022-12-20020 December 2022 Commitment Change Notification for Generic Safety Issue 191 and Generic Letter 2004-02 W3F1-2022-0054, Revise Technical Specification 3/4.3.2 to Remove Exemption from Testing Certain Relays at Power to Support Elimination of Potential Single Point Vulnerability2022-11-0101 November 2022 Revise Technical Specification 3/4.3.2 to Remove Exemption from Testing Certain Relays at Power to Support Elimination of Potential Single Point Vulnerability W3F1-2022-0063, Submittal of Emergency Preparedness Documents. Includes EP-001-001, Revision 372022-10-27027 October 2022 Submittal of Emergency Preparedness Documents. Includes EP-001-001, Revision 37 W3F1-2022-0059, Response to Clarification Questions Concerning Supplement to License Amendment Request to Adopt TSTF-5052022-10-13013 October 2022 Response to Clarification Questions Concerning Supplement to License Amendment Request to Adopt TSTF-505 W3F1-2022-0058, Reply to a Notice of Violation; EA-22-0332022-10-12012 October 2022 Reply to a Notice of Violation; EA-22-033 W3F1-2022-0049, Response to Request for Additional Information Regarding License Amendment Requests to Adopt 10 CFR 50.69 and TSTF-5052022-08-19019 August 2022 Response to Request for Additional Information Regarding License Amendment Requests to Adopt 10 CFR 50.69 and TSTF-505 W3F1-2022-0037, Submittal of Owner'S Activity Report Form for Inservice Inspection Performed During Operating Cycle 24 / Refuel 242022-08-0808 August 2022 Submittal of Owner'S Activity Report Form for Inservice Inspection Performed During Operating Cycle 24 / Refuel 24 W3F1-2022-0044, SR-2022-004-00 for Waterford Steam Electric Station, Unit 3, Radiation Monitor Inoperable Greater than 7 Days2022-07-0606 July 2022 SR-2022-004-00 for Waterford Steam Electric Station, Unit 3, Radiation Monitor Inoperable Greater than 7 Days W3F1-2022-0042, SR-22-003-00 for Waterford Steam Electric Station, Unit 3, Radiation Monitor Inoperable Greater than 7 Days2022-06-27027 June 2022 SR-22-003-00 for Waterford Steam Electric Station, Unit 3, Radiation Monitor Inoperable Greater than 7 Days W3F1-2022-0015, Response to Request for Additional Information to License Amendment Request to Revise Technical Specifications to Adopt TSTF-505, Revision 2, Provide Risk Informed Extended Completion Times - Ritstf.2022-05-16016 May 2022 Response to Request for Additional Information to License Amendment Request to Revise Technical Specifications to Adopt TSTF-505, Revision 2, Provide Risk Informed Extended Completion Times - Ritstf. W3F1-2022-0026, Report of Facility Changes, Tests, and Experiments and Commitment Changes for Two Year Period Ending April 28, 20222022-04-28028 April 2022 Report of Facility Changes, Tests, and Experiments and Commitment Changes for Two Year Period Ending April 28, 2022 W3F1-2022-0028, Annual Radiological Environmental Operating Report - 20212022-04-26026 April 2022 Annual Radiological Environmental Operating Report - 2021 W3F1-2022-0029, Annual Report of Individual Monitoring of Radiation Exposure for 2021 Per 10 CFR 20.22062022-04-26026 April 2022 Annual Report of Individual Monitoring of Radiation Exposure for 2021 Per 10 CFR 20.2206 W3F1-2022-0009, Supplement to Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems, and Components (Sscs) for Nuclear Power Reactors2022-04-25025 April 2022 Supplement to Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems, and Components (Sscs) for Nuclear Power Reactors W3F1-2022-0031, Proposed Revision to Reactor Vessel Surveillance Capsule Withdrawal Schedule to Reflect Location of Standby Capsules 3/W-104 and 6/W-2842022-04-25025 April 2022 Proposed Revision to Reactor Vessel Surveillance Capsule Withdrawal Schedule to Reflect Location of Standby Capsules 3/W-104 and 6/W-284 W3F1-2022-0020, Review of Preliminary Accident Sequence Precursor Report2022-04-11011 April 2022 Review of Preliminary Accident Sequence Precursor Report W3F1-2022-0017, Annual Report on Westinghouse Electric Company LLC Combustion Engineering Emergency Core Cooling System Performance Evaluation Models for Calendar Year 20212022-04-0707 April 2022 Annual Report on Westinghouse Electric Company LLC Combustion Engineering Emergency Core Cooling System Performance Evaluation Models for Calendar Year 2021 W3F1-2022-0019, WAT-2022-02 Post Exam Analysis2022-03-0909 March 2022 WAT-2022-02 Post Exam Analysis W3F1-2022-0011, Special Report SR-22-002-00 for Waterford Steam Electric Station, Unit 3, Radiation Monitor Inoperable Greater than 7 Days2022-02-0808 February 2022 Special Report SR-22-002-00 for Waterford Steam Electric Station, Unit 3, Radiation Monitor Inoperable Greater than 7 Days W3F1-2022-0008, SR-22-001-00, Waterford Steam Electric Station, Unit 3, Radiation Monitors Inoperable Greater than 7 Days2022-02-0101 February 2022 SR-22-001-00, Waterford Steam Electric Station, Unit 3, Radiation Monitors Inoperable Greater than 7 Days W3F1-2021-0074, Commitment Change Notification for Generic Safety Issue - 191 and Generic Letter 2004-022021-12-16016 December 2021 Commitment Change Notification for Generic Safety Issue - 191 and Generic Letter 2004-02 W3F1-2021-0064, Proposed Revision to Reactor Vessel Surveillance Capsule Withdrawal Schedule to Support Relocation of Capsules 104 and 2842021-11-30030 November 2021 Proposed Revision to Reactor Vessel Surveillance Capsule Withdrawal Schedule to Support Relocation of Capsules 104 and 284 W3F1-2021-0061, Supplement to License Amendment Request to Relocate Chemical Detection Systems Technical Specifications to Technical Requirements Manual2021-10-14014 October 2021 Supplement to License Amendment Request to Relocate Chemical Detection Systems Technical Specifications to Technical Requirements Manual W3F1-2021-0063, Request for One-Time Exemption from 10 CFR 50, Appendix E Biennial Emergency Preparedness Evaluated Exercise Requirements Due to Severe Storm Recovery2021-10-12012 October 2021 Request for One-Time Exemption from 10 CFR 50, Appendix E Biennial Emergency Preparedness Evaluated Exercise Requirements Due to Severe Storm Recovery W3F1-2021-0050, Response to U. S. Nuclear Regulatory Commission Request for Additional Information Regarding License Amendment Request to Adopt2021-10-0101 October 2021 Response to U. S. Nuclear Regulatory Commission Request for Additional Information Regarding License Amendment Request to Adopt W3F1-2021-0060, Response to Request for Additional Information Regarding License Amendment Request to Relocate Chemical Detection Systems Technical Specifications to Technical Requirements Manual2021-09-30030 September 2021 Response to Request for Additional Information Regarding License Amendment Request to Relocate Chemical Detection Systems Technical Specifications to Technical Requirements Manual W3F1-2021-0039, Application for Technical Specification Change to Revise Pressure/Temperature and Low Temperature Overpressure Protection for 55 Effective Full Power Years2021-08-25025 August 2021 Application for Technical Specification Change to Revise Pressure/Temperature and Low Temperature Overpressure Protection for 55 Effective Full Power Years W3F1-2021-0055, Supplement to License Amendment Request to Relocate Boration Systems Technical Specifications to the Technical Requirements Manual2021-08-20020 August 2021 Supplement to License Amendment Request to Relocate Boration Systems Technical Specifications to the Technical Requirements Manual W3F1-2021-0057, (Waterford 3) - Emergency Plan Revision 0522021-08-18018 August 2021 (Waterford 3) - Emergency Plan Revision 052 W3F1-2021-0054, License Amendment Request to Implement a Digital Upgrade to the Core Protection Calculator (CPC) System and Control Element Assembly Calculator (Ceac) System, Dated July 23, 20202021-07-29029 July 2021 License Amendment Request to Implement a Digital Upgrade to the Core Protection Calculator (CPC) System and Control Element Assembly Calculator (Ceac) System, Dated July 23, 2020 W3F1-2021-0051, Revised Licensing Technical Report for the Common Q Core Protection Calculator System - License Amendment Request to Implement a Digital Upgrade to the Core Protection Calculator System and Control Element Assembly Calculator2021-07-19019 July 2021 Revised Licensing Technical Report for the Common Q Core Protection Calculator System - License Amendment Request to Implement a Digital Upgrade to the Core Protection Calculator System and Control Element Assembly Calculator 2023-09-28
[Table view] |
Text
Entergy Nuclear South Entergy Operations, Inc.
17265 River Road
~~~~ ,~~~~~~~~~~, Ki~~~~~~~~~lllona, LA 70066 En/IL Ltab'V nt Tel 504 739 6440 Fax 504 739 6698 kpeters~entergy.com Ken Peters Director Nudear Safety Assurance Waterford 3 W3F11-2003-0059 A4.05 PR August 4, 2003 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D.C. 20555
Subject:
Waterford 3 SES Docket No. 50-382 License No. NPF-38 Emergency Plan Implementing Procedure Gentlemen:
In accordance with Appendix E of 10CFR50 and 10CFR50.4(b)(5), Entergy is submitting a changed Waterford 3 Emergency Plan Implementing Procedure. This changed procedure was reviewed in accordance with 10CFR50.54(q) requirements and was determined not to decrease the effectiveness of the Emergency Plan.
The following procedure is included in this submittal:
- 1. EP-002-052 (Revision 18, Change 1), Protective Action Guidelines. This change added a NOTE to give the Emergency Coordinator or EOF Director examples for adding additional protective response areas for protective actions.
This letter does not contain any commitments. Should you have any questions concerning this procedure, please contact J.J. Lewis, Emergency Planning Manager, at (504) 739-6624.
Ver truly yours, K.J. Peters Director, Nuclear Safety Assurance KJP/GCS/ssf Attarhment:
Lea__....._.... -.EP-fl02-n52
--- ___, Revisinn
.- - .I 1. Chana 1_,,_..
-_._, I
Emergency Plan Implementing Procedure W3FI-2003-0059 Page 2 August 4, 2003 cc: (w/Attachment)
Emergency Response Coordinator, NRC Region IV Senior EP Inspector - DRS, NRC Region IV (w/o Attachment)
N. Kalyanam (NRC-NRR)
P.J. Elkmann (NRC Region IV)
J. Smith N.S. Reynolds NRC Resident Inspectors Office
ATTACHMENT TO W3Fl-2003-0059 EP-002-052, Revision 18, Change I (Protective Action Guidelines)
REQUESTIAPPROVAL PAGE TY RE LAT ED ~~~~~~~~~~~~~1 PORC QUALIFIED REVIEWER PROCEDURE NUMBER: EP-002-052 REVISION: 18 CHANGE: 1 DEVIATION: NIA TITLE: Protective Action Guidelines EFFECTIVE DATE/MILESTONE: N/A (NA If Same as Approval Date)
PROCEDURE OWNER: Emergency Planning Manager (Position Title)
PREPARER (Print Name I Initial): Marc Van Der Horst I _L4 DATE: 6/6/03 ACTION:
[] New Procedure Lii Deletion l Revision s Change EC? WA N
(Applicable W2.109 Step Numbers)
[II] Deviation Expiration Date/Milestone: N/A a] Temporary Procedure Applicable Conditions: N/A DESCRIPTION AND JUSTIFICATION OF CHANGE:
Added NOTE to page 5 to give the Emergency Coordinator or EOF Director examples for adding additional protective response areas for protective actions.
O RequesttApproval Page Continuation Sheet(s) attached.
EC SUPERVISOR APPROVAL: N/A DATE:
50.59 REVIEWER Required? 0 REVIEW: N/A DATE:
o PROGRAMMATICALLY EXCLUDED PORC Mtg. No.: 03- DATE:
50.54 REVIEWER Required? 0 REVIEW: ' c . DATE: E TECHNICAL REVIEWER REVIEW: - DATE:
Change Notice (CN)? C CHANGE NOTICE (CN) SUPERVISOR APPROVAL: N/A DATE:
CHANGE NOTICE (CN) ON-SHIFT SMICRS APPROVAL: N/A DATE:
2 Week Final Approval DATE:
QUALIFIED REVIEWER Required? 0 REVIEW: DATE: & -.- C3 GROUP/DEPT. HEAD REVIEW 0 or APPROVALS 0 DATE:
GM, PLANT OPERATIONS REVIEW a or APPROVAL 0 / DATE:
VICE PRESIDENT, OPERATIONS APPROVAL: N/A DATE:
CONTRULLED W2 1099PMN r Attachment 7.1 (Page 1 of 3) 17
Emergency Plan Implementing Procedure EP-002-052 Protective Action Guidelines Revision 18 TABLE OF CONTENTS 1.0 PURPOSE 2
2.0 REFERENCES
2 3.0 RESPONSIBILITIES 4.0 INATING CONDMONS 3 6.0 PROCEDURE 5.1 General Guidelines 4 5.2 Worksheet Selection 6 5.3 Evaluation of Dose Projection Information 7 5.4 PARs Beyond the Plume Emergency Planning Zone (EPZ) 8 6.0 FINAL CONDITIONS 9 7.0 ATTACHMENTS g 7.1 Protective Actions Based on General Emergency Classification 10 7.2 Protective Action Guidelines Worksheet, Release Occurring 11 7.3 Affected Compass Sectors/Protective Response Areas Chart 12 7.4 Protective Response Areas 13 8.0 RECORDS 9 LIST OF EFFECTIVE PAGES 2-9 Revision 18 11 Revision 13 10 Revision 12 12 Revision 10 13 Revision 6 1,5 Change I
- INFORMATIONAL USE I
Emergency Plan Implementing Procedure EP-002-052 Protective Action Guidelines Revision 18 5.1.5.1 The initial default PARs for General Emergency are: I A. Evacuate Al, BI, Cl, DI (2-mile radius);
and B. Evacuate 5-miles downwind; and, I C. Shelter all other Protective Response Areas in the Plume Emergency Planning Zone (10-mile radius).
5.1.5.2 These initial default PARs have been agreed upon with the State agencies In advance. I NOTE The Emergency Coordinator or EOF Director may exercise judgment to add additional protective response areas for protective actions as long as the decisions have a sound basis. In no case are minimum protective actions described in this procedure to be removed. The following are provided as examples for adding additional areas:
- 1. Winds are expected to shift and are within 5 degrees or less of the point where the new area is to be added.
- 2. Dose Projection for a protective response area is increasing and within 100 mrem _ less of exceeding a Protective Action Recommendation value.
5.1.5.3 Continue to evaluate the conditions and update the PARs as necessary. I 5