W3F1-2021-0074, Commitment Change Notification for Generic Safety Issue - 191 and Generic Letter 2004-02

From kanterella
Jump to navigation Jump to search
Commitment Change Notification for Generic Safety Issue - 191 and Generic Letter 2004-02
ML21350A358
Person / Time
Site: Waterford Entergy icon.png
Issue date: 12/16/2021
From: Lewis J
Entergy Operations
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
W3F1-2021-0074
Download: ML21350A358 (5)


Text

Entergy Operations, Inc.

17265 River Road Killona, LA 70057 Tel 504-739-6028 John Lewis Manager, Regulatory Assurance 10 CFR 50.46 W3F1-2021-0074 December 16, 2021 ATTN: Document Control Desk U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Subject:

Commitment Change Notification for Generic Safety Issue - 191 and Generic Letter 2004-02 Waterford Steam Electric Station, Unit 3 NRC Docket No. 50-382 Renewed Facility Operating License No. NPF-38 In Reference 1, the Nuclear Regulatory Commission (NRC) staff recommended three closure options to the Commission for resolving Generic Safety Issue - 191 (GSl-191), "Closure Options for Generic Safety Issue - 191, Assessment of Debris Accumulation on Pressurized-Water Reactor Sump Performance," and the Commission approved the staff's recommendation to allow Licensees to choose any of the three options to close the issue (Reference 2). On May 16, 2013, Entergy Operations, Inc. (Entergy) submitted a letter to the NRC (Reference 3) identifying the closure option that Waterford 3 Steam Electric Station, Unit 3 (Waterford 3) had selected and the associated implementation schedule. In this letter, Entergy made several commitments to achieve closure of GSl-191 and to address Generic Letter (GL) 2004-02, "Potential Impact of Debris Blockage on Emergency Recirculation During Design Basis Accidents at Pressurized-Water Reactors" (Reference 4).

Subsequently, the Pressurized Water Reactor Owners Group (PWROG) program schedule changed. This resulted in Waterford 3 not being able to meet the original commitment date of June 30, 2015. Based upon the change in the schedule, Entergy revised one of the commitments as documented in Reference 5. Additional revisions were made to the commitments due to the PWROG schedule revisions as documented in Reference 6.

Waterford 3 intends to follow the resolution strategy proposed by the PWROG for establishing in-vessel fiber limits. The PWROG resolution strategy includes testing and analysis as summarized in WCAP-17788-P, "Comprehensive Analysis and Test Program for GSl-191 Closure (PA-SEE-1090) - Cold Leg Break (CLB) Evaluation Method for GSl-191 Long-Term Cooling." Note that the NRC informed the PWROG in 2019 that a Safety Evaluation (SE) would not be issued on WCAP-17788-P. On February 28, 2020, the PWROG approved the Technical

W3F1-2021-0074 Page 2 of 3 Specification Task Force (TSTF)-567 implementation guidance which supports the use of WCAP-17788-P by the PWROG members (Reference 7). Waterford 3 intends to follow the TSTF-567 implementation guidance proposed by the PWROG. As documented in Reference 8,

the commitments were revised to align with the PWROG resolution strategy and the TSTF-56 7

implementation guidance. Entergy is revising the completion date of one of the commitments as documented in Attachment 1 to provide the additional time needed to fully develop and refine the PWROG resolution strategy for application at Waterford 3.

This commitment change does not affect the closure option Waterford 3 selected in Reference 3

and will still support successful closure of GL 2004-02.

This letter contains one revised commitment (Attachment 1).

If you have any questions or require additional information, please contact John Lewis, Regulatory Assurance Manager, at 504-739-6028.

John Lewis JUmmz/c dm

References:

1. Nuclear Regulatory Commission (NRG) Policy Issue, "Closure Options for Generic Safety Issue - 191, Assessment of Debris Accumulation on Pressurized-Water Reactor Sump Performance," SECY-12-0093, (ADAMS Accession No. ML121320270), dated July 9, 2012
2. NRG Staff Memorandum, "Staff Requirements - SECY-12-0093 - Closure Options for Generic Safety Issue - 191, Assessment of Debris Accumulation on Pressurized-Water Reactor Sump Performance," SRM-NRC SECY 0093, (ADAMS Accession No. ML12349A378), dated December 14, 2012
3. Entergy Operations, Inc (Entergy) letter to NRG, "Closure Option for Generic Safety lssue-19 1," W3F1-2013-0027, (ADAMS Accession No. ML13137A133), dated May 16, 2013
4. NRG Generic Letter 2004-02, "Potential Impact of Debris Blockage on Emergency Recirculation During Design Basis Accidents at Pressurized-Water Reactors," (ADAMS Accession No. ML042360586), dated September 13, 2004
5. Entergy letter to NRG, "Commitment Change Notification for Generic Safety Issue - 191," W3F1-2015-0050, (ADAMS Accession No. ML15181A393),

dated June 30, 2015

W3F1-2021-007 4 Page 3 of 3

6. Entergy letter to NRC, "Commitment Change Notification for Generic Safety Issue - 191," W3F1-2016-0089, (ADAMS Accession No. ML16350A459),

dated December 15, 2016

7. Pressurized Water Reactor Owners Group (PWROG), "TSTF-567 Implementation Guidance, Evaluation of In-Vessel Debris Effects, Submittal Template for Final Response to Generic Letter 2004-02 and FSAR Changes," PWROG-16073-P, Revision 0, approved February 28, 2020
8. Entergy letter to NRC, "Commitment Change Notification for Generic Safety Issue - 191 and Generic Letter 2004-02," W3F1-2020-0068, (ADAMS Accession No. ML20329A519), dated November 24, 2020

Attachment:

List of Regulatory Commitments cc: NRC Region IV Regional Administrator NRC Senior Resident Inspector, Waterford Steam Electric Station, Unit 3 NRC Project Manager, Waterford Steam Electric Station, Unit 3

Attachment W3F1-2021-0074 List of Regulatory Commitment s

W3F1-2021-0074 Attachment Page 1 of 1 LIST OF REGULATORY COMMITMENTS The following table identifies those actions committed to by Entergy in this document. Any other statements in this submittal are provided for information purposes and are not considered to be regulatory commitments.

Type (check one)

Commitment One-Time Scheduled Continuing Action Completion Date Compliance After establishing a final determination X To be completed by of the scope of insulation replacement, December 31, 2022.

remediation, or model refinements, Waterford 3 will submit a final updated supplemental response to support closure of GL 2004-02 for Waterford 3.