Sixth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)
ML16054A836
Person / Time
Site: Callaway Ameren icon.png
Issue date: 02/23/2016
From: Hermann T
Ameren Missouri, Union Electric Co
To:
Document Control Desk, Office of Nuclear Reactor Regulation
Shared Package
ML16054A834 List:
References
EA-12-049, ULNRC-06282
Download: ML16054A836 (5)


Text

Timothy E. Herrmann, P.E.

~rt. Site Vice President Ameren Missouri WAmeren Callaway Energy Center T 573.619.2155 F 573.676.4056 MISSOURI therrmann@ameren.com February 23, 2016 ULNRC-06282 U.S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555-0001 10 CFR2.202 Ladies and Gentlemen:

DOCKET NUMBER 50-483 CALLAWAY PLANT UNIT 1 UNION ELECTRIC CO.

RENEWED FACILITY OPERATING LICENSE NPF-30 SIXTH SIX-MONTH STATUS REPORT IN RESPONSE TO MARCH 12, 2012 COMMISSION ORDER MODIFYING LICENSES WITH REGARD TO REQUIREMENTS FOR MITIGATION STRATEGIES FOR BEYOND-DESIGN-BASIS EXTERNAL EVENTS (ORDER NUMBER EA-12-049)

References:

1. Letter dated March 12,2012 from E. J. Leeds and M. R. Johnson, USNRC, to Adam C.

Heflin, Callaway Plant, Union Electric Company, "Issuance of Order to Modify Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events" (ADAMS Accession Number ML12054A736)

2. NRC Interim Staff Guidance JLD-ISG-2012-01, "Compliance with Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events," Revision 0, August 29, 2012 (ADAMS Accession Number ML12229A174)
3. ULNRC-05924, "Initial Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events," dated October 29, 2012
4. ULNRC-05962, "Overall Integrated Plan in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events," dated February 28, 2013
                                                                                                                                                                                                                    • Junction CC & Hwy 0 Fulton, MO 65251 AmerenMissouri.com
                                                                                                                                                                                                                    • PO Box 620, MC CA-460 ***************
                            • 1

ULNRC-06282 February 23, 2016 Page2

5. ULNRC-06024, "First Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049),"

dated August 29, 2013

6. ULNRC-06087, "Second Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049),"

dated February 26, 2014

7. ULNRC-06135, "Third Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049),"

dated August 28, 2014

8. ULNRC-06184, "Fourth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049),"

dated February 26, 2015

9. ULNRC-06240, "Fifth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049),"

dated August 27, 2015 On March 12, 2012, the U. S. Nuclear Regulatory Commission (NRC) issued the order identified above as Reference 1 to Union Electric Company (dba Ameren Missouri) for Callaway Plant.

Reference 1 was immediately effective and directs Ameren Missouri to develop, implement, and maintain guidance and strategies to maintain or restore core cooling, containment, and spent fuel pool cooling capabilities in the event of a beyond-design-basis external event. Specific requirements are outlined in Attachment 2 of Reference 1.

Reference 1 required submission of an initial status report 60 days following issuance of final interim staff guidance from the NRC (Reference 2) and an Overall Integrated Plan pursuant to Section IV, Condition C. Reference 3 provided Ameren Missouri'S' initial status report regarding mitigation strategies. Reference 4 provided Ameren Missouri's Overall Integrated Plan.

Section IV, Condition C.2 of Reference 1 requires submission of a status report at six-month intervals following submittal of the overall integrated plan. NEI 12-06, "Diverse and Flexible Coping Strategies (FLEX) Implementation Guide," provides direction regarding the content of the status reports. References 5, 6, 7, 8 and 9 provided Ameren Missouri's first, second, third, fourth, and fifth six-month status reports. The enclosure to this letter provides Ameren Missouri's sixth six-month status report pursuant to Section IV, Condition C.2 of Reference 1.

This letter does not contain new commitments.

ULNRC-06282 February 23, 2016 Page 3 If you have any questions concerning the content of this letter, please contact Scott Maglio, Regulatory Affairs Manager, at 573-676-8719.

I declare under penalty of perjury that the foregoing is true and correct.

Sincerely, Executed on: I Z Z 3 / ZOI (..

Timothy E. Herrmann Site Vice President

Enclosures:

1. Ameren Missouri's Sixth Six-Month Status Report for the Implementation of Order EA-12-049, "Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events"
2. Revised Sequence of Events Timeline

ULNRC-06282 February 23, 2016 Page4 cc: Mr. Marc L. Dapas Regional Administrator U.S. Nuclear Regulatory Commission Region IV 1600 East Lamar Boulevard Arlington, TX 76011-4511 Senior Resident Inspector Callaway Resident Office U.S. Nuclear Regulatory Commission 8201 NRC Road Steedman, MO 65077 Mr. L. John Klos Project Manager, Callaway Plant Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission Mail Stop 0-8B 1 Washington, DC 20555-2738

ULNRC-06282 February 23, 2016 Page 5 Index and send hardcopy to QA File A160.0761 Hardcopy:

Certrec Corporation 4150 International Plaza Suite 820 Fort Worth, TX 76109 (Certrec receives ALL attachments as long as they are non-safeguards and may be publicly disclosed.)

Electronic distribution for the following can be made via Responses and Reports ULNRC Distribution:

F. M. Diya T. E. Herrmann B.L.Cox M. L McLachlan S. A. Maglio T. B. Elwood J.T. Patterson D.M. Stepanovic B. E. Huhmann Corporate Communications NSRB Secretary STARS Regulatory Affairs Mr. John O'Neill (Pillsbury Winthrop Shaw Pittman LLP)

Missouri Public Service Commission

Timothy E. Herrmann, P.E.

~rt. Site Vice President Ameren Missouri WAmeren Callaway Energy Center T 573.619.2155 F 573.676.4056 MISSOURI therrmann@ameren.com February 23, 2016 ULNRC-06282 U.S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555-0001 10 CFR2.202 Ladies and Gentlemen:

DOCKET NUMBER 50-483 CALLAWAY PLANT UNIT 1 UNION ELECTRIC CO.

RENEWED FACILITY OPERATING LICENSE NPF-30 SIXTH SIX-MONTH STATUS REPORT IN RESPONSE TO MARCH 12, 2012 COMMISSION ORDER MODIFYING LICENSES WITH REGARD TO REQUIREMENTS FOR MITIGATION STRATEGIES FOR BEYOND-DESIGN-BASIS EXTERNAL EVENTS (ORDER NUMBER EA-12-049)

References:

1. Letter dated March 12,2012 from E. J. Leeds and M. R. Johnson, USNRC, to Adam C.

Heflin, Callaway Plant, Union Electric Company, "Issuance of Order to Modify Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events" (ADAMS Accession Number ML12054A736)

2. NRC Interim Staff Guidance JLD-ISG-2012-01, "Compliance with Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events," Revision 0, August 29, 2012 (ADAMS Accession Number ML12229A174)
3. ULNRC-05924, "Initial Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events," dated October 29, 2012
4. ULNRC-05962, "Overall Integrated Plan in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events," dated February 28, 2013
                                                                                                                                                                                                                    • Junction CC & Hwy 0 Fulton, MO 65251 AmerenMissouri.com
                                                                                                                                                                                                                    • PO Box 620, MC CA-460 ***************
                            • 1

ULNRC-06282 February 23, 2016 Page2

5. ULNRC-06024, "First Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049),"

dated August 29, 2013

6. ULNRC-06087, "Second Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049),"

dated February 26, 2014

7. ULNRC-06135, "Third Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049),"

dated August 28, 2014

8. ULNRC-06184, "Fourth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049),"

dated February 26, 2015

9. ULNRC-06240, "Fifth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049),"

dated August 27, 2015 On March 12, 2012, the U. S. Nuclear Regulatory Commission (NRC) issued the order identified above as Reference 1 to Union Electric Company (dba Ameren Missouri) for Callaway Plant.

Reference 1 was immediately effective and directs Ameren Missouri to develop, implement, and maintain guidance and strategies to maintain or restore core cooling, containment, and spent fuel pool cooling capabilities in the event of a beyond-design-basis external event. Specific requirements are outlined in Attachment 2 of Reference 1.

Reference 1 required submission of an initial status report 60 days following issuance of final interim staff guidance from the NRC (Reference 2) and an Overall Integrated Plan pursuant to Section IV, Condition C. Reference 3 provided Ameren Missouri'S' initial status report regarding mitigation strategies. Reference 4 provided Ameren Missouri's Overall Integrated Plan.

Section IV, Condition C.2 of Reference 1 requires submission of a status report at six-month intervals following submittal of the overall integrated plan. NEI 12-06, "Diverse and Flexible Coping Strategies (FLEX) Implementation Guide," provides direction regarding the content of the status reports. References 5, 6, 7, 8 and 9 provided Ameren Missouri's first, second, third, fourth, and fifth six-month status reports. The enclosure to this letter provides Ameren Missouri's sixth six-month status report pursuant to Section IV, Condition C.2 of Reference 1.

This letter does not contain new commitments.

ULNRC-06282 February 23, 2016 Page 3 If you have any questions concerning the content of this letter, please contact Scott Maglio, Regulatory Affairs Manager, at 573-676-8719.

I declare under penalty of perjury that the foregoing is true and correct.

Sincerely, Executed on: I Z Z 3 / ZOI (..

Timothy E. Herrmann Site Vice President

Enclosures:

1. Ameren Missouri's Sixth Six-Month Status Report for the Implementation of Order EA-12-049, "Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events"
2. Revised Sequence of Events Timeline

ULNRC-06282 February 23, 2016 Page4 cc: Mr. Marc L. Dapas Regional Administrator U.S. Nuclear Regulatory Commission Region IV 1600 East Lamar Boulevard Arlington, TX 76011-4511 Senior Resident Inspector Callaway Resident Office U.S. Nuclear Regulatory Commission 8201 NRC Road Steedman, MO 65077 Mr. L. John Klos Project Manager, Callaway Plant Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission Mail Stop 0-8B 1 Washington, DC 20555-2738

ULNRC-06282 February 23, 2016 Page 5 Index and send hardcopy to QA File A160.0761 Hardcopy:

Certrec Corporation 4150 International Plaza Suite 820 Fort Worth, TX 76109 (Certrec receives ALL attachments as long as they are non-safeguards and may be publicly disclosed.)

Electronic distribution for the following can be made via Responses and Reports ULNRC Distribution:

F. M. Diya T. E. Herrmann B.L.Cox M. L McLachlan S. A. Maglio T. B. Elwood J.T. Patterson D.M. Stepanovic B. E. Huhmann Corporate Communications NSRB Secretary STARS Regulatory Affairs Mr. John O'Neill (Pillsbury Winthrop Shaw Pittman LLP)