U-602832, Forwards Rev 2 to CPS TS Bases,Consisting of Pages Annotated W/Rev Numbers 2-1 Through 2-14.Text Changes Identified by Rev Bars

From kanterella
(Redirected from U-602832)
Jump to navigation Jump to search
Forwards Rev 2 to CPS TS Bases,Consisting of Pages Annotated W/Rev Numbers 2-1 Through 2-14.Text Changes Identified by Rev Bars
ML20212C688
Person / Time
Site: Clinton Constellation icon.png
Issue date: 10/23/1997
From: Sipek J
ILLINOIS POWER CO.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
Shared Package
ML20212C694 List:
References
U-602832, NUDOCS 9710300101
Download: ML20212C688 (2)


Text

llhnois Power Company Clinton Power Station P O Box 678 Chnton. IL 61727 Tel 217 935-8881 Joseph V. Sipek

% g Director - Licensing u m- cmn U-602832 1A.120 October 23, 1997 1

i i

l Docket No. 50-461 10CFR50.36 Document Control Desk Nuclear Regulatory Commission Washington, D.C. 20555 l

Subject:

Transmittal of Resision 2 to the Clinton Power Station Technical Specification Bases

Dear Madam or Sir:

Pursuant to Clinton Power Station (CPS) Technical Specification 5.5.11,

" Technical Specification (TS) Bases Control Program " please find enclosed resised pages constituting Revision 2 to the CPS TS Bases. The changes associated with this revision were processed in accordance with CPS TS 5.5.1I which became effective with Amendment No. 95 to the CPS Operatica License.

In order to provide plant personnel with the most up-to-date information available in a timely manner, changes to the CPS TS Bases are distributed to controlled copies of the CPS TS in " installments." Installments are collected and then issued together when a revision / update is provided to the NRC. Fourteen installraents were issued during the period of time corresponding to Revision 2 of the CPS TS Bases. As a re ult, Revision 2 to the CPS TS Beses consists of pages annotated with Revision Nos. 2-1, 2-2, 2-3, 2-4, 2-5, 2-6, 2-7, 2-8, 2-9, 2-10, 2-11, 2 12, 2-13, and 2-14.

Changes to the text of the CPS TS Bases are identified with revision bars. No revision bars were included for changes to format, such as moving unrevised text from one page to another.

fhI g W

9710300101 971023 1-PDR ADOCK 0 ll111111111111!!!!I111D1

U-603832 Page 2 of 2 It should be noted that submittal of this revision to the TS Bases at this time is not in compliance with CPS TS 5.5.11 which requires updates to the TS Bases to be submitted to the NRC at a frequency consistent with 10CFR50.71(c). Accordingly, the interval between successive updates should not exceed 24 months. However, this requirement was inadvertently not met for this update in light of the fact that the

. previously provided update to the TS Bases was provided June 23,1995. In response to this identified condition, a plant Condition Report has been initiated, and therefore, appropriate corrective actions will be taken for this non-compliance in accordance with the CPS corrective action program. The NRC Resident Inspector and the NRC Licensing Project Manager for CPS have been informed of this condition.

Sincerely yours, oseph V. Sip 6k Director - Licensing AJP/krk Enclosure cc: NRC Clinton Licensing Project Manager NRC Resident Office, V-690 Regional Administrator, Region III, USNRC Illinois Department of Nuclear Safety 4